JP4009148B2 - Construction by-product reduction plan system, construction by-product reduction plan method, and construction by-product reduction plan program - Google Patents
Construction by-product reduction plan system, construction by-product reduction plan method, and construction by-product reduction plan program Download PDFInfo
- Publication number
- JP4009148B2 JP4009148B2 JP2002186268A JP2002186268A JP4009148B2 JP 4009148 B2 JP4009148 B2 JP 4009148B2 JP 2002186268 A JP2002186268 A JP 2002186268A JP 2002186268 A JP2002186268 A JP 2002186268A JP 4009148 B2 JP4009148 B2 JP 4009148B2
- Authority
- JP
- Japan
- Prior art keywords
- construction
- building
- input
- generation amount
- product
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 297
- 239000006227 byproduct Substances 0.000 title claims description 210
- 230000009467 reduction Effects 0.000 title claims description 74
- 238000000034 method Methods 0.000 title claims description 29
- 238000004364 calculation method Methods 0.000 claims description 62
- 238000013461 design Methods 0.000 claims description 41
- 239000000463 material Substances 0.000 claims description 38
- 238000012545 processing Methods 0.000 claims description 26
- 230000000694 effects Effects 0.000 claims description 9
- 230000008569 process Effects 0.000 claims description 8
- 239000002699 waste material Substances 0.000 claims description 7
- 230000006870 function Effects 0.000 description 60
- 238000010586 diagram Methods 0.000 description 13
- 230000015654 memory Effects 0.000 description 11
- 239000010426 asphalt Substances 0.000 description 10
- 238000011156 evaluation Methods 0.000 description 8
- 238000007726 management method Methods 0.000 description 8
- 238000004078 waterproofing Methods 0.000 description 5
- 230000008859 change Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 3
- 230000007613 environmental effect Effects 0.000 description 3
- 238000012937 correction Methods 0.000 description 2
- 238000004891 communication Methods 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000003203 everyday effect Effects 0.000 description 1
- 239000000284 extract Substances 0.000 description 1
- 239000010440 gypsum Substances 0.000 description 1
- 229910052602 gypsum Inorganic materials 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- XEBWQGVWTUSTLN-UHFFFAOYSA-M phenylmercury acetate Chemical compound CC(=O)O[Hg]C1=CC=CC=C1 XEBWQGVWTUSTLN-UHFFFAOYSA-M 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、建設副産物発生量低減計画システム、建設副産物発生量低減計画方法、及び建設副産物発生量低減計画プログラムにかかり、特に、建設工事に伴って副次的に発生する建設副産物の発生量を低減するための計画をする建設副産物発生量低減計画システム、建設副産物発生量低減計画方法、及び建設副産物発生量低減計画プログラムに関する。
【0002】
【従来の技術】
建設現場では、建設工事に伴って副次的に得られる建設副産物が排出される。該建設副産物には、再生資源及び廃棄物からなる様々な物質が含まれ、近年では、建設副産物の削減が重要課題とされている。
【0003】
建設副産物を削減するにあたり、発生する建設副産物を予測する建設副産物予測管理システムが提案されている(特開平11−303395号公報)。
【0004】
特開平11−303395号公報に記載の技術では、建設工事の工事内容毎に各搬入資機材から発生する建設副産物及び各搬入資機材の単位数量当たりに発生する各建設副産物の発生歩掛かりを設定した歩掛かりデータ、建設施設の用途や、構造、規模に応じて発生歩掛かりを調整する調整値を設定した調整データを記憶する記憶手段と、工事内容毎に各搬入資機材の数量その他建設副産物の発生量を予測するための情報を入力する入力手段と、入力手段より工事内容毎に入力される各搬入資機材の数量に基づき記憶手段に記憶された歩掛かりデータとの演算を行って建設副産物の発生量を求める演算手段とを備え、発生歩掛かりを各搬入資機材の数量に掛けて建設副産物の発生量を求めることが提案されている。これによって、建設副産物の発生量を分類して予測し建設工事毎に一元管理することが可能となる。
【0005】
【発明が解決しようとする課題】
しかしながら、特開平11−303395号公報に記載の技術では、インプット情報は設計仕様で、アウトプット情報は建設副産物発生量であるため、目標値を設定した場合に、その目標値を達成するための効果的な方策がなく、目標値を達成したとしてもその目標値を達成するために多大な時間を要する、という問題がある。
【0006】
また、建設副産物低減のための技術開発、改善活動は日々実施されており、これらの技術の適用効果を従来のシステムにて扱うには、システムを管理している担当者がデータベースをその都度、修正する必要があり、修正作業が煩雑となる、という問題がある。
【0007】
本発明は、上記問題を解決すべく成されたもので、建設副産物発生量算定において、効率的かつ質の高い検討ができると共に、建設副産物低減に伴って地球環境美化促進に貢献することができる建設副産物発生量的現計画システム、建設副産物発生量低減計画方法、及び建設副産物発生量低減計画プログラムを提供することを目的とする。
【0008】
【課題を解決するための手段】
上記目的を達成するために請求項1に記載の発明は、建設する建物の仕様及び構造に関する建物概要を入力する入力手段と、前記建物概要と、該建物概要に対応する建設副産物の標準発生量との対応関係を複数種類記憶すると共に、建設する建物に用いる投入資機材と、該投入資機材に対応する建設副産物の発生係数との対応関係を複数記憶し、かつ前記建物概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む建築処理内容と、該建築処理内容に対応する建設副産物の削減効果を表す特定係数との対応関係を複数種類記憶する記憶手段と、前記入力手段によって入力された前記建物概要と前記記憶手段に記憶された前記標準発生量との対応関係に基づいて、建設する建物における建設副産物の標準発生量を算出し、該算出された標準発生量から建設副産物発生量が抑制されるように、建設する建物における建設副産物発生量の目標値を設定するための設定手段と、前記入力手段によって入力された前記建物概要に基づいて、建設する建物に用いる投入資機材を算定する算定手段と、前記算定手段によって算定された投入資機材と、前記記憶手段に記憶された前記投入資機材に対応する前記発生係数とから発生する建設副産物発生量を算出する算出手段と、前記算出手段によって算出された建設副産物発生量と、前記設定手段によって設定された目標値と、に基づいて、前記記憶手段に記憶された複数種類の前記建築処理内容の中から前記目標値が達成されるように前記建築処理内容を選択して、選択した建築処理内容と、該建築処理内容に対応する前記特定係数との対応関係から求めた建設副産物発生量とを、建設副産物発生量を低減するための低減案として生成する生成手段と、を備えることを特徴としている。
【0009】
請求項1に記載の発明によれば、入力手段では、建設する建物に関する建物概要を入力する。入力する建物概要としては、例えば、用途、延床面積、建築面積、構造形式、基準階高、地下階高、地上階数、地下階数等を入力する。
【0010】
記憶手段には、建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係が複数種類記憶されると共に、建設する建物に用いる投入資機材と該投入資機材に対応する建設副産物の発生係数との対応関係が複数記憶され、かつ建物概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む建築処理内容と該建築処理内容に対応する建設副産物の削減効果を表す特定係数との対応関係が複数種類記憶されている。例えば、記憶手段には、過去の実績から定められる各種情報が記憶される。
【0011】
設定手段では、入力手段によって入力された建物概要と、記憶手段に記憶された建設副産物の標準発生量との対応関係と、に基づいて、建設する建物における建設副産物の標準発生量が算出され、算出された標準発生量から建設副産物発生量が低減されるように、建設する建物における建設副産物発生量の目標値を設定する。当該目標値の設定は、記憶手段に記憶された建設副産物の標準発生量を超えない値で、任意に設定する。
【0012】
ここで、算定手段では、入力手段によって入力された建物概要に基づいて、投入資機材が算定される。算定手段は、例えば、予め設定された建物の用途毎の部位・箇所−仕様・構工法データベースを用いて、用途毎の仕様・構工法を設定し、設定された仕様と建物概要に基づいて、設計数量を算出し、算出された設計数量と設定された構工法に基づいて投入資機材とその数量を算定することができる。
【0013】
また、算出手段では、算定手段によって算定された投入資機材と、記憶手段に記憶された投入資機材に対応する発生係数とから発生する建設副産物発生量が算出される。算出手段による算出は、例えば、予め定められた投入資機材毎に発生する建設副産物発生量の発生係数からなるデータベースを用いることによって算出可能である。
【0014】
そして、生成手段では、算出手段によって算出された建設副産物発生量と、設定手段によって設定された目標値と、に基づいて、記憶手段に記憶された複数種類の建築処理内容の中から目標値が達成されるように建築処理内容が選択され、選択された建築処理内容と、該建築処理内容に対応する特定係数との対応関係から求めた建設副産物発生量とが、建設副産物発生量を低減するための低減案として生成される。例えば、各部位・箇所毎の設計仕様、構工法、構工法における個別対策等の案を複数予め定めたデータベースを用いて建設副産物発生量の低減案を個別対策、構工法、設計仕様等を順次に変更することによって生成することが可能である。
【0015】
すなわち、目標値を達成することができる設計仕様・構工法を計画するために、インプット情報を建設副産物の発生量目標値とし、アウトプット情報を設計仕様・構工法等の低減案とすることにより、目標値を達成するための計画を容易に作成できる。
【0016】
従って、建設副産物発生量算定において、効率的かつ質の高い検討ができると共に、建設副産物低減に伴って地球環境負荷低減に貢献することができる
請求項2に記載の発明は、請求項1に記載の発明において、前記建物概要に対応する建設副産物発生量の実績値を入力する実績入力手段と、前記実績入力手段によって入力された建設副産物発生量に基づいて、前記記憶手段に記憶された前記建物概要に対応する建設副産物の標準発生量との対応関係を更新する更新手段と、をさらに備えることを特徴としている。
【0017】
請求項2に記載の発明によれば、請求項1に記載の発明において、実績入力手段と、更新手段を更に備えており、実績入力手段によって、例えば、建設の任意の段階における建物概要に対応する建設副産物発生量の実績値を入力することによって、更新手段によって、建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係を更新することができる。これによって、最新の情報を元に、建設副産物発生量の低減案を生成することができ、質の高い計画を立てることができる。
【0018】
請求項3に記載の発明は、建設する建物に関する建物概要を入力する入力ステップと、前記入力ステップで入力された前記建物概要と、予め定められた前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係に基づいて、建設する建物における建設副産物の標準発生量を算出し、該算出された標準発生量から建設副産物が抑制されるように、建設する建物における建設副産物発生量の目標値を設定する設定ステップと、前記入力ステップで入力された前記建物概要に基づいて、建設する建物に用いる投入資機材を算定する算定ステップと、前記算定ステップで算定された投入資機材と、予め定められた建設する建物に用いる投入資機材と該投入資機材に対応する建設副産物の発生係数との対応関係から発生する建設副産物発生量を算出する算出ステップと、前記算定ステップで算定された建設副産物発生量と、前記設定ステップで設定された目標値と、に基づいて、前記建築概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む複数種類の建築処理内容の中から前記目標値が達成されるように前記建築処理内容を選択して、選択した建築処理内容と、該建築処理内容に対応して予め定めた建設副産物の削減効果を現す特定係数との対応関係から求めた建設副産物発生量とを、建設副産物発生量を低減するための低減案として生成する生成ステップと、を有することを特徴としている。
【0019】
請求項3に記載の発明によれば、入力ステップでは、建設する建物に関する建物概要を入力する。入力する建物概要としては、例えば、用途、延床面積、建築面積、構造形式、基準階高、地下階高、地上階数、地下階数等を入力する。
【0020】
設定ステップでは、入力ステップで入力された建物概要と、予め定められた建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係に基づいて、建設する建物における建設副産物の標準発生量を算出し、算出された標準発生量から建設副産物発生量が低減されるように、建設する建物における建設副産物発生量の目標値を設定する。例えば、過去の実績から前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係を複数記憶する記憶手段を設けて、これを用いて入力ステップで入力された建物概要から建設する建物における建設副産物発生量の目標値を設定することができる。なお、目標値は、予め定められた建設副産物発生量を超えない値で、任意に設定する。
【0021】
ここで、算定ステップでは、入力ステップで入力された建物概要に基づいて、投入資機材が算定される。例えば、予め設定された建物の用途毎の部位・箇所−仕様・構工法データベースを用いて、用途毎の仕様・構工法を設定し、設定された仕様と建物概要に基づいて、設計数量を算出し、算出された設計数量と設定された構工法に基づいて投入資機材とその数量を算定することができる。
【0022】
また、算出ステップでは、算定ステップで算定された投入資機材と、予め定められた建設する建物に用いる投入資機材とその投入資機材に対応する建設副産物発生係数との対応関係から発生する建設副産物発生量が算出される。例えば、予め定められた投入資機材毎に発生する建設副産物発生量の発生係数からなるデータベースを用いることによって算出可能である。
【0023】
そして、生成ステップでは、算出ステップで算出された建設副産物発生量と、設定ステップで設定された目標値と、に基づいて、建築概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む複数種類の建築処理内容の中から目標値が達成されるように建築処理を選択して、選択した建築処理内容と、該建築処理内容に対応する予め定めた建設副産物の削減効果を表す特定係数との対応関係から求めた建設副産物発生量とを、建設副産物発生量を低減するための低減案として生成する。例えば、各部位・箇所毎の設計仕様、構工法、構工法における個別対策等の案を複数予め定めたデータベースを用いて建設副産物発生量の低減案を個別対策、構工法、設計仕様等を順次に変更することによって生成することが可能である。
【0024】
すなわち、目標値を達成することができる設計仕様・構工法を計画するために、インプット情報を建設副産物の発生量目標値とし、アウトプット情報を設計仕様・構工法等の低減案とすることにより、目標値を達成することができる計画作成を容易にすることができる。
【0025】
従って、建設副産物発生量評価において、効率的かつ質の高い検討ができると共に、建設副産物低減に伴って地球環境負荷低減に貢献することができる
請求項4に記載の発明は、請求項3に記載の発明において、前記建物概要に対応する建設副産物発生量の実績値を入力する実績入力ステップと、前記実績入力ステップで入力された建設副産物発生量に基づいて、予め定められた前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係を更新する更新ステップと、をさらに有することを特徴としている。
【0026】
請求項4に記載の発明によれば、請求項3に記載の発明において、実績入力ステップと、更新ステップを更に有しており、実績入力ステップで、例えば、建設の任意の段階における建物概要に対応する建設副産物発生量の実績値を入力することによって、更新ステップで、予め定められた建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係を更新することができる。これによって、最新の情報を元に、建設副産物発生量の低減案を生成することができ、質の高い計画を立てることができる。
なお、請求項3及び請求項4に記載の建設副産物発生量低減計画方法は、請求項5及び請求項6に記載の発明のように、コンピュータに実行させる建設副産物発生量低減計画プログラムとしてもよい。
【0027】
【発明の実施の形態】
以下、図面を参照して本発明の実施の形態の一例を詳細に説明する。
【0028】
図1には、本発明の実施の形態に係わる建設副産物発生量低減計画システム10の概略構成を示す。
【0029】
図1に示すように、建設副産物発生量低減計画システム10は、CPU12、ROM14、RAM16、及びI/O18がコマンドやデータの授受をすることが可能なように接続されたマイクロコンピュータを含んで構成されている。I/O18には、フレキシブルディスク装置などのリードライト装置20、キーボードなどの入力装置22、ディスプレイモニタなどの表示装置24、及び処理プログラムなどが記憶された各種メモリが26、28接続されている。なお、入力装置22は本発明の入力手段に相当する。
【0030】
リードライト装置20は、記憶媒体20Aが挿抜可能に構成されている。記憶媒体20Aにはフレキシブルディスクなどがある。なお、後述する各機能における処理等は、リードライト装置20を用いて記憶媒体20Aから実行可能である。従って、後述する各機能における処理は、本体内のメモリなどに記憶することなく、予め記憶媒体20Aに記憶しておき、リードライト装置20を介して記憶媒体20Aに記録された処理プログラムを実行してもよい。なお、ハードディスク装置等の大容量記憶装置を備えて、記憶媒体に記憶された処理プログラムを格納(インストール)して該当する処理をしてもよい。なお、記憶媒体としては、CD−ROM、MD、MO、DVD装置、DAT装置等を用いればよい。
【0031】
また、I/O18には、画像データやテキストデータを用紙や感光材料等に印刷して出力するプリンタ30が接続されている。
【0032】
さらに、I/O18には、各種メモリ26、28が接続されているが、メモリ26には、後述する各機能を実行するための処理プログラムなどが記憶され、メモリ28には後述する各機能毎に用いる種々のデータベース等が記憶されている。なお、メモリ26は、処理プログラムがROM14やRAM16に記憶される場合は不要である。
【0033】
メモリ28に記憶されたデータベースとしては、建設副産物発生量の実績データベース、仕様・構工法データベース、建設副産物発生量の実績から予め求めた各投入資機材毎の建設副産物発生量の発生係数データベース、及び建設副産物低減案からなるデフォルト・代替案データベース等が記憶されている。なお、メモリ28は、本発明の記憶手段に相当する。
【0034】
実績データベースは、用途、延床面積、構造形式、基準階高、地下階高、地上階数、地下階数等の各要素毎に、単位面積当たりの建設副産物の標準発生量が記憶されている。
【0035】
仕様・構工法データベースは、用途毎の部位・箇所における仕様・構工法情報が記憶されている。
【0036】
発生係数データベースは、投入資機材名とその単位、建設副産物名、及び建設副産物分類とその単位毎の建設副産物の発生量を算出するための係数が記憶されている。
【0037】
デフォルト・代替案データベースは、部位・箇所毎の設計仕様、構工法、及び建設副産物軽減のための対応策が記憶されており、各部位・箇所毎にそのデフォルトが予め定められている。
【0038】
建設副産物発生量低減計画システム10には、上記構成以外にも各種電気機器や各種ソフトウエアを含んで構成してもよいが、汎用的かつ一般的なハードウエア構成であるため、詳細な説明を省略する。
【0039】
上述のように構成された建設副産物発生量低減計画システム10は、大きく分けて、図2に示すように、目標値設定機能32、算出モデル生成機能34、発生量算定機能36、削減案算定機能38、評価・管理機能40、及び学習機能42の6つの機能に分けられ、各機能が順に機能する。なお、目標設定機能32は本発明の設定手段及び設定ステップに相当し、算出モデル生成機能34は本発明の算定手段及び算定ステップに相当し、発生量算定機能36は本発明の算出手段及び算出ステップに相当し、削減案算定機能38は本発明の生成手段及び生成ステップに相当し、評価・管理機能40は本発明の実績入力手段及び実績入力ステップに相当し、学習機能42は本発明の更新手段及び更新ステップに相当する。
【0040】
続いて、これらの各機能について順に説明していく。まず、目標設定機能32について図3を参照して説明する。
【0041】
目標設定機能32では、入力装置22を用いて建物概要を設定する(S50)。例えば、当該プロジェクトの用途(事務所、工場、店舗等)、延床面積、構造形式等を、入力装置22を用いて設定する。なお、建物概要の設定(S50)は本発明の入力ステップに相当する。
【0042】
建物概要が設定されると、メモリ28に記憶された実績データベース28Aを用いて建設副産物の標準発生量が算出される(S52)。建設副産物の標準発生量は、実績データベース28Aに含まれる、用途別、延床面積別、構造形式別の単位面積当たりの建設副産物の標準発生量から、当該プロジェクトで発生する総標準発生量が抽出されることによって算出される。例えば、実績データベース28Aから、図4に示すように、用途別、延床面積別、構造形式別の単位面積当たりの建設副産物の標準発生量を抽出し、当該プロジェクトで発生する標準発生量を算出すると、延床面積2000m2、事務所、S造のプロジェクトの場合では、13×0.8=10.4m3/100m2の標準発生量となる。
【0043】
続いて、建設副産物の標準発生量に対して、どの程度削減努力をするかを入力装置22を用いて設定する(S54)。目標値としては悪くとも建設副産物の標準発生量を超えない値を設定する。例えば、建設副産物の標準発生量の0.9等を設定する。なお、目標値の設定は任意に行うものとする。これによって、建設副産物発生量の目標値が設定される。
【0044】
次に、算出モデル生成機能34では、図5に示すように、目標値設定機能32と同様に、入力装置22を用いて建物概要を設定する(S60)。ここでは、例えば、当該プロジェクトの用途、延床面積、建築面積、構造形式、基準階高、地下階高、地上階数、地下階数等を設定する。なお、当該入力は、目標値設定機能32の建物概要設定時に入力するようにしてもよい。
【0045】
建物概要が設定されると、用途と、用途毎の部位・箇所−仕様・構工法データベース28Bを用いて、当該プロジェクトの部位・箇所毎の仕様・構工法がデフォルト設定される(S62)。例えば、図6に示すように、用途と、用途毎の部位・箇所−仕様・構工法データベース28Bを用いて、部位・箇所が屋根防水で、仕様・構工法がアスファルト防水・密着工法等のように設定されていく。
【0046】
続いて、設定された建物概要及び仕様・構工法から投入資機材・数量が算定される(S64)。例えば、図7に示すように、設計仕様と建物概要から予め定めた所定の計算式を用いて、設計数量が算出され、当該設計数量と構工法から予め定めた所定の計算式を用いて、アスファルトプライマー○kg、アスファルトルーフィング△m2、アスファルトコンパウンド□kg等のように投入資機材とその数量が算定される。
【0047】
続いて、発生量算定機能36では、図8に示すように、算出モデル生成機能34で算出された投入資機材とその数量が設定されて(S70)、発生係数データベース28Cを用いて、当該投入資機材とその数量から建設副産物の発生量が算出される(S72)。
【0048】
発生係数データベース28Cは、図9に示すように、投入資機材名に対応して、単位、該投入資機材から発生する建設副産物名、該建設副産物の分類、及び単位からなり、建設副産物の単位毎に発生係数が予め記憶されている。例えば、図9の例で建設副産物の発生量を算出すると、屋根防水において、アスファルトプライマーが100kg投入する場合には、建設副産物としてアスファルトプライマー容器(金属くず)が100×a(kg)、または、100×b(m3)発生することになる。
【0049】
一方、上述のように、各投入資機材毎に算定された建設副産物を削減するために削減案算定機能38では、図10に示すような、予め定められたデフォルト・代替案データベース28Dを用いて目標値を達成できる対策が施される。本実施の形態では、デフォルト・代替案データベース28Dのデータベース構造が、図10に示すように、各部位・箇所毎に設計仕様、構工法、個別対策が予めデフォルトとして設定されていて、これの代替案を変更することによって対策が行われる。当該対策は、個別対策、構工法、設計仕様の順に変更していくことによって、建設副産物の発生量が目標値以内となるように削減案が算定される。すなわち、削減案算定機能38は、図12に示すように、まず、建設副産物発生割合の最も高い設計仕様が抽出される(S80)。そして、個別対策を変更して(S82)、目標値を達成するまで個別対策の変更が行われる(S82〜S86)。ここで、個別対策だけでは目標値を達成できない場合には(S84)、構工法を変更して(S88)、変更した構工法における個別対策を変更し、順次上述の個別対策の変更を行うことによって、目標値以下に建設副産物発生量がなるまで繰り返される(S82〜S88)。さらに、ここで構工法変更しても目標値を達成できない場合には(S90)、設計仕様を変更して(S92)、変更した設計仕様について個別対策を変更して、順次上述の個別対策の変更を行うことによって、目標値以下に建設副産物発生量がなるまで繰り返される(S82〜S92)。
【0050】
ここで、個別対策とは、投入資機材の調達段階での工夫を意味し、例えば、石膏ボードのプレカット等を予め行っておくことにより、建設副産物を削減することが可能である。また、構工法とは、工事段階での工夫を意味し、例えば、PCa工法、乾式工法等があり、各工法に応じて建設副産物の発生量が異なるので、構工法を変更することによって、建設副産物を削減することが可能である。さらに、設計仕様とは設計段階での工夫を意味し、設計仕様そのものを変更することによって、建設副産物を削減することが可能である。
【0051】
削減案算定機能38では、上述のように基本的には、個別対策→構工法→設計仕様の順に変更の優先順位が設定されており、個別対策を行っても建設副産物の発生量が目標値を達成しない場合に、構工法を変更する。そして、変更した構工法の個別対策を行っても建設副産物の発生量が目標値を達成しない場合に、さらに、設計仕様まで変更して建設副産物の発生量の削減案算定を行う。これによって、確実に建設副産物発生量の目標値を達成する削減案を算定することができる。
【0052】
例えば、削減ステップの例を図11に示す。図11では、建設副産物の発生量の目標値が1000kg、このときのデフォルトにより算出した建設副産物発生量が1050kgとする。ここで、図11の下段には、各設計仕様、構工法、個別対策の建設副産物発生量の例が示され、各個別対策における削減効果が示されている。
【0053】
この例では、アスファルト防水、A工法、A1対策のデフォルト状態では、1050kgであるので、目標値に対して50kgオーバーとなる。
【0054】
続いて、アスファルト防水、A工法、A2対策では、1030kgで、目標値に対して30kgオーバーとなるので、目標値を達成できない。
【0055】
次のアスファルト防水、B工法、B1対策では、1040kgで、目標値に対して40kgオーバーとなるので、目標値を達成できない。
【0056】
次のアスファルト防水、B工法、B2対策では、970kgで、目標値に対して−30kgとなり、目標値達成となる。従って、図11の例では、B工法のB2対策が削減案として採用される。
【0057】
なお、本実施の形態の削減案算定機能38では、上述のように個別対策→構工法→設計仕様の順に優先順位を設けて削減案を算定するようにしたが、これに限るものではなく、例えば、優先順位を設けずに、設計仕様及び構工法に拘わらず目標値を達成するまで最も削減率の高い対策順に採用するようにしてもよい。
【0058】
また、評価・管理機能40では、図13に示すように、まず、入力装置22を用いて実績データを入力する(S100)。例えば、必須入力情報として、(1)建物概要、(2)建設副産物発生量の実績を入力する。この他の入力情報としては、建設副産物低減の取り組みをした方法に対する実績値や発生量予測システムのデータベースになかった情報の入力等を行う。
【0059】
ところで、建設物副産物発生量の実績値の入力は、全てを入力するのは、困難であるため作業所が注目している箇所の入力を行うようにしてもよい。例えば、図14に示すように、設計仕様、構工法、個別対策毎の発生量の実績を、入力装置22を用いて入力する。
【0060】
また、建設副産物発生量低減計画システム10のデータベース28になかった情報の入力は、例えば、建設副産物削減のための新工法を開発し、最初に適用した現場にて、システムに図15に示すような情報(例えば、設計仕様、構工法、投入資機材・数量、個別対策、発生量等)を登録する。
【0061】
上述のような一連の入力を行うことによって、実績データベース28Aが更新される(S102)。これによって、随時データベースが更新されて最新の情報に基づいて、建設副産物発生量を算出することができるので、質の高い建設副産物発生量低減の計画を立てることができる。
【0062】
そして、学習機能42では、図16に示すように、発生係数データベース28Cの洗い替えが行われる(S110)。すなわち、図14に示す実績データ入力における(1)建物概要、(2)建設副産物発生量の実績、の情報より、用途別、延床面積別、構造形式別に分類し、平均をとることにより、例えば用途別、延床面積別、構造形式別、単位面積当たり発生量標準の数値が随時更新される。これによって、用途別、延床面積別、構造形式別の単位面積当たり発生量標準へ反映される。
【0063】
また、削減案算定機能による建設副産物削減の取り組みをした方法に対する実績値が蓄積された場合、その件数の平均値をとり、建設副産物発生量算出のための各種係数が随時更新される。例えば、図17に示すように、実績1及び実績2が評価管理機能40で入力された場合には、当該発生量の平均値から発生係数を算出して更新する。図17に示す場合には、更新前の発生係数が0.5で発生量が100、実績1の発生量が80、実績2の発生量が60であるので、実績の発生量の平均値は70となる。従って、発生係数は、0.5×70/100=0.35として、データベースの更新が行われる。このように発生係数データベースの更新を行うことによって実績が入力されるたびに、建設副産物発生量の予測値の精度が向上すると共に、計画毎に建設副産物発生量を低減することができる。
【0064】
続いて、次期計画への反映が行われる(S112)。ここでは、建設副産物発生量低減計画システム10のデータベース28に無かった情報から、例えば用途別、延床面積別、構造形式別に分類し、平均をとることにより、用途別、延床面積別、構造形式別の単位面積当たり発生量標準の数値が随時更新される。
【0065】
例えば、図18に示すように、建設副産物削減のための新工法に関する情報から、設計仕様、構工法、投入資機材・数量、個別対策、副産物発生量等を抽出して、データベース28に新たに追加する。これによって、次期計画への反映を行うことができる。
【0066】
なお、本発明の実施の形態に係わる建設副産物発生量低減計画システム10は、図19に示すようなコンピュータやPDA(Personal Digital Assistants)等の情報端末を無線又は有線でネットワーク接続可能なコンピュータ・ネットワーク・システムに適用するようにしてもよい。
【0067】
続いて、コンピュータ・ネットワーク・システムに適用した場合について説明する。
【0068】
図19に示すように、各々同一または異なる複数のコンピュータ150、152、154、156を、それぞれモデム、ルータ、TA(ターミナルアダプタ:Terminal Adapter)等の接続装置160を介して、インターネットやその他の小規模ネットワークとしてのLAN(Local Area Network)で代表されるネットワーク158に接続し、複数のコンピュータ(図19では、4台として示すが4台に限定されるものではない)150、152、154、156を、ネットワーク158を介して相互通信により情報授受が可能に構成する。
【0069】
この時、コンピュータ150のはサーバ・コンピュータとして機能させ、複数のコンピュータ152、154、156は、複数の建設現場に設ける。そして、各コンピュータ152、154、156の基本構成を、データベースが記憶されたメモリ28を除いて、図1に示す上記の実施の形態に係わる建設副産物発生量低減計画システム10の構成とし、サーバコンピュータ150については、図1と同一構成として、データベースの管理を行うように構成する。すなわち、サーバコンピュータ150にデータベースを格納して複数のコンピュータ152、154、156からアクセス可能なように構成する。
【0070】
そして、各コンピュータ152、154、156にて、目標値設定機能32、算出モデル生成機能34、発生量算定機能36、削減案算定機能38の各々の機能を上記と同様に実行するようにし、評価・管理機能40及び学習機能42については、サーバコンピュータ150と各コンピュータ152、154、156によって行うようにすることによって、各コンピュータ152、154、156から建設副産物発生量の実績を更新することができ、最新の情報に基づいて建設副産物発生量の削減計画を行うことができる。
【0071】
【発明の効果】
以上説明したように本発明によれば、予め設定された建物概要に対応する建設副産物発生量と、建設する建物概要に基づいて、建設する建物における建設副産物発生量の目標値を設定すると共に、建物概要から投入資機材及び該投入資機材から発生する建設副産物発生量を算出し、算出された建設副産物発生量と目標値に基づいて、建設副産物発生量を低減するための低減案を作成するので、建設副産物発生量評価において、効率的かつ質の高い検討ができると共に、建設副産物低減に伴って地球環境負荷低減に貢献することができる、という効果がある。
【図面の簡単な説明】
【図1】本発明の実施の形態に係わる建設副産物低減計画システムの構成を示すブロック図である。
【図2】本発明の実施の形態に係わる建設副産物低減計画システムの各機能を示す機能ブロック図である。
【図3】目標値設定機能の流れを示すフローチャートである。
【図4】実績データベースより抽出したデータの一例を示す図である。
【図5】算出モデル生成機能の流れを示すフローチャートである。
【図6】算出モデル生成機能における仕様・構工法設定を説明するための機能ブロック図である。
【図7】算出モデル生成機能における数量算定を説明するための機能ブロック図である。
【図8】発生量算定機能の流れを示すフローチャートである。
【図9】発生係数データベースのデータベース構造の一例を示す図である。
【図10】デフォルト・代替案データベースのデータベース構造の一例を示す図である。
【図11】削減案算定機能における削減ステップの例を示す図である。
【図12】削減案算定機能の流れを示すフローチャートである。
【図13】評価・管理機能の流れを示すフローチャートである。
【図14】設計仕様、構工法、個別対策毎の発生量の実績入力の一例を示す図である。
【図15】データベースにない新規事項の一例を示す図である。
【図16】学習機能の流れを示すフローチャートである。
【図17】学習機能の一例を示す図である。
【図18】学習機能のその他の例を示す図である。
【図19】コンピュータ・ネットワーク・システムに建設副産物発生量低減計画システムを適用した場合の概略構成を示す図である。
【符号の説明】
10 建設副産物発生量低減計画システム
22 入力装置
28 メモリ
32 目標値設定機能
34 算出モデル生成機能
36 発生量算定機能
38 削減案算定機能
40 評価・管理機能
42 学習機能[0001]
BACKGROUND OF THE INVENTION
The present invention is a construction by-product reduction plan system.,Construction by-product reduction plan method, And construction by-product reduction plan programIn particular, a construction by-product generation reduction plan system that plans to reduce the amount of construction by-products generated by construction work.,Construction by-product reduction plan method, And construction by-product reduction plan programAbout.
[0002]
[Prior art]
At the construction site, construction by-products obtained as a by-product of the construction work are discharged. The construction by-products include various substances composed of recycled resources and waste, and in recent years, the reduction of construction by-products has become an important issue.
[0003]
In reducing construction by-products, a construction by-product prediction management system for predicting construction by-products generated has been proposed (Japanese Patent Laid-Open No. 11-303395).
[0004]
In the technology described in Japanese Patent Application Laid-Open No. 11-303395, the construction by-product generated from each incoming equipment and the construction yield of each construction by-product generated per unit quantity of each incoming equipment is set for each construction work. Storage means that stores adjustment data that sets adjustment values for adjusting the amount of generated work according to construction data, construction facility use, structure, and scale, and the amount of each imported equipment for each construction content and other construction by-products Construction is performed by calculating input means for inputting information for predicting the amount of occurrence of the accident and the step data stored in the storage means based on the quantity of each equipment that is input for each construction content from the input means. Computation means for obtaining the amount of by-product generated is proposed, and the amount of construction by-product is determined by multiplying the amount of generated yield by the quantity of each equipment carried in. This makes it possible to classify and predict the amount of construction by-products generated and to centrally manage each construction work.
[0005]
[Problems to be solved by the invention]
However, in the technique described in Japanese Patent Application Laid-Open No. 11-303395, the input information is a design specification and the output information is a construction by-product generation amount. Therefore, when a target value is set, the target value is achieved. There is a problem that there is no effective measure, and even if the target value is achieved, it takes a long time to achieve the target value.
[0006]
In addition, technology development and improvement activities for reducing construction byproducts are carried out every day, and in order to handle the application effects of these technologies in the conventional system, the person in charge managing the system needs to update the database each time. There is a problem that correction is necessary and the correction work becomes complicated.
[0007]
The present invention has been made to solve the above-mentioned problems, and in the calculation of the amount of construction by-products generated, it is possible to make an efficient and high-quality study and to contribute to the promotion of beautification of the global environment along with the reduction of construction by-products. Construction by-product generation amount present plan system,Construction by-product reduction plan method, And construction by-product reduction plan programThe purpose is to provide.
[0008]
[Means for Solving the Problems]
In order to achieve the above object, the invention described in
[0009]
According to the first aspect of the present invention, the input means inputs the building outline related to the building to be constructed. As the building outline to be input, for example, the usage, total floor area, building area, structure type, reference floor height, basement floor height, number of ground floors, number of basement floors, etc. are input.
[0010]
The storage means includes a plurality of correspondence relationships between the building outline and the standard amount of construction by-products corresponding to the building outline.typeA plurality of correspondence relations between the input materials and equipment used for the building to be constructed and the generation coefficient of the construction by-product corresponding to the input materials and equipment are stored, and the structure of the building part in the outline of the building is stored.Including design stage, construction stage, and input equipment procurement stageConstruction processingContentAnd the building processContentCorresponding to construction by-productsReducing effectWith specific coefficientCorrespondenceIstypeIt is remembered. For example, the storage unit stores various information determined from past results.
[0011]
In the setting means, the standard generation amount of the construction by-product in the building to be constructed is calculated based on the correspondence between the building outline inputted by the input means and the standard generation amount of the construction by-product stored in the storage means. A target value of the construction by-product generation amount in the building to be constructed is set so that the construction by-product generation amount is reduced from the calculated standard generation amount. The target value is arbitrarily set to a value that does not exceed the standard amount of construction by-products stored in the storage means.
[0012]
Here, the calculation means calculates the input materials and equipment based on the building outline input by the input means. The calculation means uses, for example, a preset site / location / specification / construction method database for each use of the building, sets the specification / construction method for each use, and based on the set specifications and the building outline, The design quantity can be calculated, and the input equipment and the quantity can be calculated based on the calculated design quantity and the set construction method.
[0013]
Further, in the calculation means, the input materials and equipment calculated by the calculation means and the storage means are stored.Corresponds to the input materials and equipmentThe amount of construction by-products generated from the generation coefficient is calculated. The calculation by the calculation means can be performed by using, for example, a database including a generation coefficient of a construction by-product generation amount generated for each predetermined input material and equipment.
[0014]
And in the generation means, based on the construction by-product generation amount calculated by the calculation means and the target value set by the setting means,From the multiple types of construction processing contents stored in the storage meansTo achieve the target valueBuilt inConstruction processContentChoiceIs,ChoiceIsBuilding processingObtained from the correspondence between the content and the specific coefficient corresponding to the construction processing contentAmount of construction by-products generatedAnd the amount of construction by-products generatedTo reduceReductionGenerated as a draft. For example, using a database that predetermines multiple design specifications, construction methods, individual measures in the construction method, etc. for each part / location, a specific plan for reducing the amount of construction by-products generated, construction methods, design specifications, etc. It can be generated by changing to
[0015]
In other words, in order to plan a design specification / construction method that can achieve the target value, by setting the input information as the target value for the amount of construction by-products and the output information as a reduction plan for the design specification / construction method, etc. , You can easily create a plan to achieve the target value.
[0016]
Therefore, in the calculation of the amount of construction by-products generated, it is possible to make an efficient and high-quality study and contribute to the reduction of the global environmental load along with the reduction of construction by-products.
The invention according to
[0017]
According to the second aspect of the present invention, in the first aspect of the present invention, the apparatus further comprises a record input means and an update means, and the record input means supports, for example, a building outline at an arbitrary stage of construction. By inputting the actual value of the generated amount of construction by-products, the correspondence between the building outline and the standard amount of construction by-products corresponding to the building outline can be updated by the updating means. This makes it possible to generate a plan for reducing the amount of construction by-products generated based on the latest information, and to make a high-quality plan.
[0018]
According to a third aspect of the present invention, there is provided an input step for inputting a building outline relating to a building to be constructed, the building outline inputted in the input step, the predetermined building outline and a construction byproduct corresponding to the building outline. The standard generation amount of construction by-products in the building to be constructed is calculated based on the corresponding relationship with the standard generation amount of the building, and the generation of construction by-products in the building to be constructed is suppressed from the calculated standard generation amount. A setting step for setting a target value of quantity, a calculation step for calculating input materials and equipment to be used in a building to be constructed based on the building outline input in the input step, and input materials and equipment calculated in the calculation step And a by-product of the construction by-product generated from the correspondence between the input equipment and materials used in the predetermined building to be constructed and the generation coefficient of the construction by-product corresponding to the input equipment and materials A calculation step of calculating a raw amount, and the calculated construction waste generation amount that is calculated in step, the target value set by the setting step, based on,Among the architectural outlines, from among multiple types of construction processing contents, including design stage ingenuity, construction stage ingenuity, and input stage equipment procurement stage ingenuity regarding the structure of the building partSo that the target value is achievedSaidConstruction processingContentSelect the selected building processIt was determined from the correspondence between the content and the specific coefficient that shows the reduction effect of construction by-products determined in advance corresponding to the construction processing content.Amount of construction by-products generatedWhenIs generated as a reduction plan for reducing the generation amount of construction by-products.
[0019]
According to the invention described in
[0020]
In the setting step, the standard generation of construction by-products in the building to be constructed is based on the correspondence between the building outline input in the input step and the predetermined building outline and the standard amount of construction by-products corresponding to the building outline. The amount is calculated, and a target value of the construction by-product generation amount in the building to be constructed is set so that the construction by-product generation amount is reduced from the calculated standard generation amount. For example, a storage means for storing a plurality of correspondence relationships between the building outline and the standard generation amount of construction by-products corresponding to the building outline from past results is provided, and construction is performed from the building outline input in the input step using this. It is possible to set a target value for the amount of construction by-products generated in a building. The target value is arbitrarily set to a value that does not exceed a predetermined construction by-product generation amount.
[0021]
Here, in the calculation step, the input equipment is calculated based on the building outline input in the input step. For example, using a preset part / location-specification / construction method database for each use of a building, set the specification / construction method for each application and calculate the design quantity based on the set specifications and the building outline. The input materials and equipment and the quantity can be calculated based on the calculated design quantity and the set construction method.
[0022]
In addition, in the calculation step, construction by-products generated from the corresponding relationship between the input equipment and materials calculated in the calculation step, the predetermined input materials and equipment used for the building to be constructed, and the construction by-product generation coefficient corresponding to the input equipment and materials. The amount generated is calculated. For example, the calculation can be performed by using a database composed of generation coefficients of construction by-product generation amounts generated for each predetermined input equipment.
[0023]
Then, in the generation step, based on the construction by-product generation amount calculated in the calculation step and the target value set in the setting step,Among the architectural outlines, from multiple types of construction processing contents, including design stage ingenuity, construction stage ingenuity, and input stage equipment procurement stage ingenuityTo achieve the target valueBuilt inSelect the building process and the selected building processIt was obtained from the correspondence between the content and a specific coefficient representing the reduction effect of a predetermined construction by-product corresponding to the construction processing content.Amount of construction by-products generatedWhenIs generated as a reduction plan for reducing the amount of construction by-products generated. For example,eachUsing a database that predetermines multiple design specifications, construction methods, and individual measures in the construction method for each part / location, change the individual measures, construction methods, design specifications, etc. in order to reduce the amount of construction by-products generated Can be generated.
[0024]
In other words, in order to plan a design specification / construction method that can achieve the target value, by setting the input information as the target value for the amount of construction by-products and the output information as a reduction plan for the design specification / construction method, etc. Planning can be achieved, the target value can be facilitated.
[0025]
Therefore, in the evaluation of the amount of construction by-products generated, it is possible to make an efficient and high-quality study and contribute to the reduction of the global environmental load along with the reduction of construction by-products.
According to a fourth aspect of the present invention, in the third aspect of the present invention, the actual input step of inputting an actual value of the construction by-product generation amount corresponding to the building outline, and the generation of the construction by-product input in the actual input step The method further comprises an updating step of updating a correspondence relationship between the predetermined building outline and a standard amount of construction by-products corresponding to the building outline based on the quantity.
[0026]
According to the invention described in
The construction by-product generation amount reduction planning method according to
[0027]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an example of an embodiment of the present invention will be described in detail with reference to the drawings.
[0028]
FIG. 1 shows a schematic configuration of a construction byproduct generation amount
[0029]
As shown in FIG. 1, the construction by-product generation amount
[0030]
The read /
[0031]
The I / O 18 is connected to a
[0032]
Further,
[0033]
The database stored in the
[0034]
The performance database stores the standard generation amount of construction by-products per unit area for each element such as use, total floor area, structure type, reference floor height, basement floor height, number of ground floors, number of basement floors.
[0035]
The specification / construction method database stores the specification / construction method information at the site / location for each application.
[0036]
The occurrence coefficient database stores input equipment names and units, construction by-product names, construction by-product classifications, and coefficients for calculating the amount of construction by-products generated for each unit.
[0037]
The default / alternative database stores design specifications for each part / location, construction method, and countermeasures for reducing construction by-products, and the default is predetermined for each part / location.
[0038]
The construction by-product generation amount
[0039]
The construction by-product generation amount
[0040]
Subsequently, each of these functions will be described in order. First, the
[0041]
In the
[0042]
When the building outline is set, the standard amount of construction by-products is calculated using the results database 28A stored in the memory 28 (S52). The standard generation amount of construction by-products is extracted from the standard generation amount of construction by-products per unit area by usage, total floor area, and structure type included in the results database 28A. To be calculated. For example, from the results database 28A, as shown in FIG. 4, the standard generation amount of construction by-products per unit area by application, total floor area, and structure type is extracted, and the standard generation amount generated in the project is calculated. Then, total floor area 2000m2In the case of a project of office, S construction, 13 × 0.8 = 10.4mThree/ 100m2The standard generation amount of
[0043]
Subsequently, how much reduction efforts are made with respect to the standard amount of construction by-products is set using the input device 22 (S54). As a target value, a value that does not exceed the standard amount of construction by-products at the worst is set. For example, 0.9 is set as the standard generation amount of construction by-products. The target value is set arbitrarily. Thereby, the target value of the amount of construction by-products generated is set.
[0044]
Next, as shown in FIG. 5, the calculation
[0045]
When the building outline is set, the specification and construction method for each part / location of the project are set by default using the use and the part / location-specification / construction method database 28B for each use (S62). For example, as shown in FIG. 6, using the application and the site / location-specification / construction method database 28B for each application, the site / location is waterproof, and the specification / construction method is asphalt waterproof / adhesion method, etc. It will be set to.
[0046]
Subsequently, the input equipment / quantity is calculated from the set outline of the building and the specification / construction method (S64). For example, as shown in FIG. 7, the design quantity is calculated using a predetermined calculation formula determined in advance from the design specifications and the building outline, and the predetermined calculation formula determined in advance from the design quantity and the construction method is used. Asphalt primer ○ kg, asphalt roofing △ m2Input materials and equipment such as asphalt compound □ kg are calculated.
[0047]
Subsequently, in the generation
[0048]
As shown in FIG. 9, the
[0049]
On the other hand, as described above, the reduction plan calculation function 38 in order to reduce the construction by-products calculated for each input material and equipment uses a predetermined default / alternative plan database 28D as shown in FIG. Measures are taken to achieve the target value. In the present embodiment, as shown in FIG. 10, the database structure of the default / alternative plan database 28D has design specifications, construction methods, and individual measures set in advance as defaults for each part / location. Measures are taken by changing the draft. By changing the measures in the order of individual measures, construction methods, and design specifications, a reduction plan is calculated so that the amount of construction by-products is within the target value. That is, as shown in FIG. 12, the reduction plan calculation function 38 first extracts a design specification having the highest construction by-product generation rate (S80). Then, the individual countermeasure is changed (S82), and the individual countermeasure is changed until the target value is achieved (S82 to S86). Here, when the target value cannot be achieved only by the individual measures (S84), the construction method is changed (S88), the individual measures in the changed construction method are changed, and the above-described individual measures are sequentially changed. Is repeated until the amount of construction by-products is less than the target value (S82 to S88). Furthermore, if the target value cannot be achieved even if the construction method is changed here (S90), the design specifications are changed (S92), the individual measures are changed for the changed design specifications, and the individual measures described above are sequentially applied. By making the change, the process is repeated until the amount of construction by-products is less than the target value (S82 to S92).
[0050]
Here, the individual measure means a device at the procurement stage of the input materials and equipment, and it is possible to reduce construction by-products by, for example, pre-cutting gypsum board in advance. In addition, the construction method means a device at the construction stage. For example, there are a PCa construction method, a dry construction method, and the like, and the amount of construction by-products differs depending on each construction method. By-products can be reduced. Furthermore, the design specification means a device at the design stage, and it is possible to reduce construction by-products by changing the design specification itself.
[0051]
In the reduction plan calculation function 38, as described above, the priority of change is basically set in the order of individual measures → construction method → design specifications. Even if individual measures are taken, the amount of construction by-products generated is the target value. If the above is not achieved, the construction method is changed. If the amount of construction by-product generated does not reach the target value even if individual measures for the changed construction method are taken, the design specification is further changed to calculate a reduction plan for the amount of construction by-product generated. This makes it possible to calculate a reduction plan that reliably achieves the target value of the amount of construction by-products generated.
[0052]
For example, FIG. 11 shows an example of the reduction step. In FIG. 11, it is assumed that the target value of the generation amount of construction by-products is 1000 kg, and the generation amount of construction by-products calculated by default at this time is 1050 kg. Here, the lower part of FIG. 11 shows examples of the amount of construction by-products generated for each design specification, construction method, and individual measure, and shows the reduction effect in each individual measure.
[0053]
In this example, in the default state of asphalt waterproofing, A method, and A1 countermeasures, it is 1050 kg, which is 50 kg over the target value.
[0054]
Subsequently, asphalt waterproofing, A method, and A2 measures are 1030 kg, which is 30 kg over the target value, so the target value cannot be achieved.
[0055]
In the next asphalt waterproofing, B construction method, and B1 countermeasures, the target value cannot be achieved because it is 4040 over the target value at 1040 kg.
[0056]
In the next asphalt waterproofing, B method, and B2 countermeasures, 970 kg is -30 kg against the target value, and the target value is achieved. Accordingly, in the example of FIG. 11, the B2 countermeasure of the B method is adopted as a reduction plan.
[0057]
In the reduction plan calculation function 38 of the present embodiment, the reduction plan is calculated by setting priorities in the order of individual measures → construction method → design specifications as described above. However, the present invention is not limited to this. For example, without setting priority, the measures may be adopted in the order of measures with the highest reduction rate until the target value is achieved regardless of the design specification and construction method.
[0058]
In the evaluation /
[0059]
By the way, since it is difficult to input all the actual values of the amount of construction by-products generated, it may be possible to input a place where the work place is paying attention. For example, as shown in FIG. 14, the design specifications, the construction method, and the actual amount of generation for each individual measure are input using the
[0060]
Also, the input of information that was not in the
[0061]
The performance database 28A is updated by performing a series of inputs as described above (S102). As a result, the database can be updated at any time and the amount of construction by-products generated can be calculated based on the latest information, so that a high-quality plan for reducing the amount of construction by-products generated can be made.
[0062]
Then, in the
[0063]
In addition, when the actual values for the method for reducing construction by-products using the reduction plan calculation function are accumulated, the average value of the number of cases is taken, and various coefficients for calculating the amount of construction by-products are updated as needed. For example, as shown in FIG. 17, when the
[0064]
Subsequently, reflection to the next plan is performed (S112). Here, from information that was not in the
[0065]
For example, as shown in FIG. 18, the design specification, construction method, input equipment / quantity, individual measures, amount of by-products, etc. are extracted from the information on the new construction method for reducing construction by-products and newly added to the
[0066]
Note that the construction by-product generation amount
[0067]
Next, a case where the present invention is applied to a computer network system will be described.
[0068]
As shown in FIG. 19, a plurality of
[0069]
At this time, the
[0070]
Then, each of the
[0071]
【The invention's effect】
As described above, according to the present invention, based on the construction by-product generation amount corresponding to the preset building outline and the building outline to be constructed, the target value of the construction by-product generation amount in the building to be constructed is set, Calculate the input materials and equipment and the amount of construction by-products generated from the input materials and equipment, and create a reduction plan to reduce the amount of construction by-products generated based on the calculated amount of construction by-products and the target value. Therefore, in the evaluation of the amount of construction by-products generated, there is an effect that it is possible to make an efficient and high-quality study and to contribute to the reduction of the global environmental load along with the reduction of construction by-products.
[Brief description of the drawings]
FIG. 1 is a block diagram showing a configuration of a construction byproduct reduction planning system according to an embodiment of the present invention.
FIG. 2 is a functional block diagram showing each function of the construction byproduct reduction planning system according to the embodiment of the present invention.
FIG. 3 is a flowchart showing a flow of a target value setting function.
FIG. 4 is a diagram illustrating an example of data extracted from a performance database.
FIG. 5 is a flowchart showing a flow of a calculation model generation function.
FIG. 6 is a functional block diagram for explaining specification / construction method setting in a calculation model generation function;
FIG. 7 is a functional block diagram for explaining quantity calculation in a calculation model generation function.
FIG. 8 is a flowchart showing a flow of a generation amount calculation function.
FIG. 9 is a diagram illustrating an example of a database structure of an occurrence coefficient database.
FIG. 10 is a diagram showing an example of a database structure of a default / alternative database.
FIG. 11 is a diagram illustrating an example of a reduction step in a reduction plan calculation function.
FIG. 12 is a flowchart showing a flow of a reduction plan calculation function.
FIG. 13 is a flowchart showing a flow of an evaluation / management function.
FIG. 14 is a diagram illustrating an example of a result input of a generation amount for each design specification, construction method, and individual measure.
FIG. 15 is a diagram showing an example of a new matter that is not in the database.
FIG. 16 is a flowchart showing a flow of a learning function.
FIG. 17 is a diagram illustrating an example of a learning function.
FIG. 18 is a diagram illustrating another example of the learning function.
FIG. 19 is a diagram showing a schematic configuration when a construction byproduct generation amount reduction planning system is applied to a computer network system.
[Explanation of symbols]
10 Construction by-product reduction plan system
22 Input device
28 memory
32 Target value setting function
34 Calculation model generation function
36 Amount generation function
38 Reduction plan calculation function
40 Evaluation and management functions
42 Learning functions
Claims (6)
前記建物概要と、該建物概要に対応する建設副産物の標準発生量との対応関係を複数種類記憶すると共に、建設する建物に用いる投入資機材と、該投入資機材に対応する建設副産物の発生係数との対応関係を複数記憶し、かつ前記建物概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む建築処理内容と、該建築処理内容に対応する建設副産物の削減効果を表す特定係数との対応関係を複数種類記憶する記憶手段と、
前記入力手段によって入力された前記建物概要と前記記憶手段に記憶された前記標準発生量との対応関係に基づいて、建設する建物における建設副産物の標準発生量を算出し、該算出された標準発生量から建設副産物発生量が抑制されるように、建設する建物における建設副産物発生量の目標値を設定するための設定手段と、
前記入力手段によって入力された前記建物概要に基づいて、建設する建物に用いる投入資機材を算定する算定手段と、
前記算定手段によって算定された投入資機材と、前記記憶手段に記憶された前記投入資機材に対応する前記発生係数とから発生する建設副産物発生量を算出する算出手段と、
前記算出手段によって算出された建設副産物発生量と、前記設定手段によって設定された目標値と、に基づいて、前記記憶手段に記憶された複数種類の前記建築処理内容の中から前記目標値が達成されるように前記建築処理内容を選択して、選択した建築処理内容と、該建築処理内容に対応する前記特定係数との対応関係から求めた建設副産物発生量とを、建設副産物発生量を低減するための低減案として生成する生成手段と、
を備えた建設副産物発生量低減計画システム。An input means for inputting a building outline relating to the specifications and structure of the building to be constructed;
A plurality of types of correspondence relations between the building outline and the standard generation amount of construction by-products corresponding to the building outline are stored, the input equipment used for the building to be constructed, and the generation coefficient of the construction by-product corresponding to the input equipment And the contents of the building process , including the design stage devise, the construction stage devise, and the input stage equipment procurement stage devise regarding the structure of the building part of the building outline , and the building process Storage means for storing a plurality of types of correspondence with a specific coefficient representing a reduction effect of construction by-products corresponding to the content ;
Based on the correspondence between the building outline input by the input unit and the standard generation amount stored in the storage unit, a standard generation amount of construction by-products in the building to be constructed is calculated, and the calculated standard generation amount A setting means for setting a target value of the amount of construction by-products generated in the building to be constructed so that the amount of construction by-products generated is suppressed from the amount;
Based on the building outline input by the input means, calculating means for calculating input materials and equipment used for the building to be constructed;
A calculation means for calculating a construction by-product generation amount generated from the input material and equipment calculated by the calculation means and the generation coefficient corresponding to the input material and equipment stored in the storage means;
Based on the construction by-product generation amount calculated by the calculation means and the target value set by the setting means, the target value is achieved from among a plurality of types of the construction processing contents stored in the storage means. select pre SL building processing contents as the selected building process contents, and construction waste generation amount obtained from the relationship between the specific coefficient corresponding to the building process contents, the construction waste generated amount Generating means for generating as a reduction plan for reducing;
Construction by-product reduction plan system equipped with.
前記実績入力手段によって入力された建設副産物発生量に基づいて、前記記憶手段に記憶された前記建物概要に対応する建設副産物の標準発生量との対応関係を更新する更新手段と、
をさらに備えることを特徴とする請求項1に記載の建設副産物発生量低減計画システム。Actual input means for inputting the actual value of the construction by-product generation amount corresponding to the building outline;
Based on the construction by-product generation amount input by the result input unit, updating means for updating the correspondence relationship with the standard generation amount of construction by-products corresponding to the building outline stored in the storage unit;
The construction byproduct generation amount reduction planning system according to claim 1, further comprising:
前記入力ステップで入力された前記建物概要と、予め定められた前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係に基づいて、建設する建物における建設副産物の標準発生量を算出し、該算出された標準発生量から建設副産物が抑制されるように、建設する建物における建設副産物発生量の目標値を設定する設定ステップと、
前記入力ステップで入力された前記建物概要に基づいて、建設する建物に用いる投入資機材を算定する算定ステップと、
前記算定ステップで算定された投入資機材と、予め定められた建設する建物に用いる投入資機材と該投入資機材に対応する建設副産物の発生係数との対応関係から発生する建設副産物発生量を算出する算出ステップと、
前記算定ステップで算定された建設副産物発生量と、前記設定ステップで設定された目標値と、に基づいて、前記建築概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む複数種類の建築処理内容の中から前記目標値が達成されるように前記建築処理内容を選択して、選択した建築処理内容と、該建築処理内容に対応して予め定めた建設副産物の削減効果を現す特定係数との対応関係から求めた建設副産物発生量とを、建設副産物発生量を低減するための低減案として生成する生成ステップと、
を有する建設副産物発生量低減計画方法。An input step for entering a building summary for the building to be constructed;
Based on the correspondence between the building outline input in the input step and the predetermined building outline and the standard generation amount of construction by-products corresponding to the building outline, the standard generation amount of construction by-products in the building to be constructed A setting step for setting a target value of the construction by-product generation amount in the building to be constructed so that the construction by-product is suppressed from the calculated standard generation amount;
Based on the building overview input in the input step, a calculation step for calculating input materials and equipment used for the building to be constructed;
Calculate the amount of construction by-products generated from the correspondence between the input materials and equipment calculated in the above-mentioned calculation step, the input materials and equipment used in the predetermined building to be constructed, and the generation coefficient of construction by-products corresponding to the input materials and equipment A calculating step to
Based on the construction by-product generation amount calculated in the calculation step and the target value set in the setting step , the design stage ingenuity, the construction stage ingenuity regarding the structure of the building part in the building outline, and select the building process content as the target value is achieved from a plurality of types of building the processing contents including contrivance acquisition stage of the input equipment, and the selected architecture processing contents, corresponding to the building process content a generation step of generating the construction waste generation amount calculated from the correspondence between the specific coefficients representing the reduction of construction waste a predetermined, as reduction proposal for reducing construction waste generation amount and,
Construction by-product generation reduction plan method having
前記実績入力ステップで入力された建設副産物発生量に基づいて、予め定められた前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係を更新する更新ステップと、
をさらに有することを特徴とする請求項3に記載の建設副産物発生量低減計画方法。A record input step for inputting a record value of the construction by-product generation amount corresponding to the building outline;
Based on the construction by-product generation amount input in the result input step, an update step for updating a correspondence relationship between the predetermined building outline and a standard generation amount of construction by-products corresponding to the building outline;
The construction byproduct generation amount reduction planning method according to claim 3, further comprising:
前記入力ステップで入力された前記建物概要と、予め定められた前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係に基づいて、建設する建物における建設副産物の標準発生量を算出し、該算出された標準発生量から建設副産物が抑制されるように、建設する建物における建設副産物発生量の目標値を設定する設定ステップと、 Based on the correspondence between the building outline input in the input step and the predetermined building outline and the standard generation amount of construction by-products corresponding to the building outline, the standard generation amount of construction by-products in the building to be constructed A setting step for setting a target value of the construction by-product generation amount in the building to be constructed so that the construction by-product is suppressed from the calculated standard generation amount;
前記入力ステップで入力された前記建物概要に基づいて、建設する建物に用いる投入資機材を算定する算定ステップと、 Based on the building outline input in the input step, a calculation step for calculating input materials and equipment used for the building to be constructed;
前記算定ステップで算定された投入資機材と、予め定められた建設する建物に用いる投入資機材と該投入資機材に対応する建設副産物の発生係数との対応関係から発生する建設副産物発生量を算出する算出ステップと、Calculate the amount of construction by-products generated from the corresponding relationship between the input materials and equipment calculated in the calculation step, the input materials and equipment used for the building to be established in advance, and the generation coefficient of construction by-products corresponding to the input materials and equipment A calculating step to
前記算定ステップで算定された建設副産物発生量と、前記設定ステップで設定された目標値と、に基づいて、前記建築概要のうち建物部位の構造に関する、設計段階の工夫、工事段階の工夫、及び投入資機材の調達段階の工夫を含む複数種類の建築処理内容の中から前記目標値が達成されるように前記建築処理内容を選択して、選択した建築処理内容と、該建築処理内容に対応して予め定めた建設副産物の削減効果を現す特定係数との対応関係から求めた建設副産物発生量とを、建設副産物発生量を低減するための低減案として生成する生成ステップと、Based on the construction by-product generation amount calculated in the calculation step and the target value set in the setting step, the design stage ingenuity, the construction stage ingenuity regarding the structure of the building part in the building outline, and Select the building processing content so that the target value can be achieved from a plurality of types of building processing content including ideas at the procurement stage of input materials and equipment, and correspond to the selected building processing content and the building processing content A generation step of generating a construction by-product generation amount obtained from a correspondence relationship with a specific coefficient that expresses a predetermined construction by-product reduction effect as a reduction plan for reducing the construction by-product generation amount;
を含む処理をコンピュータに実行させるための建設副産物発生量低減計画プログラム。A program to reduce the amount of construction by-products generated by a computer.
前記実績入力ステップで入力された建設副産物発生量に基づいて、予め定められた前記建物概要と該建物概要に対応する建設副産物の標準発生量との対応関係を更新する更新ステップと、
をさらに含むことを特徴とする請求項5に記載の建設副産物発生量低減計画プログラム。 A record input step for inputting a record value of the construction by-product generation amount corresponding to the building outline;
Based on the construction by-product generation amount input in the results input step, an update step for updating the correspondence between the predetermined building outline and the standard generation amount of construction by-products corresponding to the building outline ;
The construction by-product generation amount reduction plan program according to claim 5, further comprising:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002186268A JP4009148B2 (en) | 2002-06-26 | 2002-06-26 | Construction by-product reduction plan system, construction by-product reduction plan method, and construction by-product reduction plan program |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002186268A JP4009148B2 (en) | 2002-06-26 | 2002-06-26 | Construction by-product reduction plan system, construction by-product reduction plan method, and construction by-product reduction plan program |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004027670A JP2004027670A (en) | 2004-01-29 |
| JP4009148B2 true JP4009148B2 (en) | 2007-11-14 |
Family
ID=31181664
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002186268A Expired - Fee Related JP4009148B2 (en) | 2002-06-26 | 2002-06-26 | Construction by-product reduction plan system, construction by-product reduction plan method, and construction by-product reduction plan program |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4009148B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101396548B1 (en) * | 2013-09-02 | 2014-05-20 | 삼성물산 주식회사 | The estimation device and method for generation of construction waste during construction and demolition phase |
| JP2016099653A (en) * | 2014-11-18 | 2016-05-30 | 秩父土建株式会社 | Environmental impact assessment device, program, and environmental impact assessment method |
| JP6950309B2 (en) * | 2017-07-11 | 2021-10-13 | 株式会社大林組 | Evacuation safety performance evaluation method, evacuation safety performance evaluation system, and program |
-
2002
- 2002-06-26 JP JP2002186268A patent/JP4009148B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004027670A (en) | 2004-01-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Burns et al. | The LP/IP hybrid method for construction time-cost trade-off analysis | |
| JP5754824B2 (en) | Data conversion method and data transformer | |
| CN111105050B (en) | Fan maintenance plan generation method, device, equipment and storage medium | |
| CN117827619A (en) | Method, device, equipment, medium and system for time-consuming prediction simulation of heterogeneous computing power | |
| WO2024152471A1 (en) | Intelligent construction task scheduling method and apparatus, and storage medium and processor | |
| CN115146416B (en) | Model parameter identification method and device for hydraulic system of engineering machinery and excavator | |
| Dzeng et al. | Critiquing contractors' scheduling by integrating rule-based and case-based reasoning | |
| JP4009148B2 (en) | Construction by-product reduction plan system, construction by-product reduction plan method, and construction by-product reduction plan program | |
| CN108767854B (en) | Electricity purchase scheme optimization method and device and electronic equipment | |
| JPH05314094A (en) | Sales forecast support device | |
| CN118133341A (en) | A digital construction method and system for typical planning scenarios of county distribution networks | |
| CN116308485A (en) | Highway bridge engineering cost prediction method, device, equipment and storage medium | |
| CN111209930A (en) | A method, device and electronic device for generating a credit policy | |
| Raja Shekharan | Solution of pavement deterioration equations by genetic algorithms | |
| CN119151256B (en) | A method and system for optimizing material allocation strategy | |
| CN114841447A (en) | Plate sample arrangement method and device | |
| CN115169089A (en) | Wind power probabilistic prediction method and device based on kernel density estimation and copula | |
| CN119005917B (en) | A project management method for elevator shaft formwork construction | |
| CN117726225A (en) | A method, device, equipment and medium for quality control and evaluation of main network construction process | |
| CN118365094A (en) | Project material demand prediction method and system for power construction | |
| CN116797263A (en) | Construction engineering cost accounting management method and system | |
| CN119731734A (en) | Material designing apparatus, material designing method, and program | |
| Bertsimas et al. | Constructing uncertainty sets from covariates in power systems | |
| Karim et al. | A new generation software for construction scheduling and management | |
| JP2021083275A (en) | Power demand prediction system and control method for power demand prediction system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20041201 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070410 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070611 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070828 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070831 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100907 Year of fee payment: 3 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110907 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120907 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130907 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |