JP4031273B2 - Barrage with falling rock prevention clasp - Google Patents
Barrage with falling rock prevention clasp Download PDFInfo
- Publication number
- JP4031273B2 JP4031273B2 JP2002075357A JP2002075357A JP4031273B2 JP 4031273 B2 JP4031273 B2 JP 4031273B2 JP 2002075357 A JP2002075357 A JP 2002075357A JP 2002075357 A JP2002075357 A JP 2002075357A JP 4031273 B2 JP4031273 B2 JP 4031273B2
- Authority
- JP
- Japan
- Prior art keywords
- fastener
- wire
- hole
- clasp
- slope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000002265 prevention Effects 0.000 title claims description 29
- 239000011435 rock Substances 0.000 title claims description 15
- 239000000463 material Substances 0.000 claims description 27
- 239000002023 wood Substances 0.000 claims description 24
- 210000003205 muscle Anatomy 0.000 claims description 12
- 230000001681 protective effect Effects 0.000 claims description 12
- 239000012770 industrial material Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 description 14
- 239000004575 stone Substances 0.000 description 10
- 239000012779 reinforcing material Substances 0.000 description 8
- 239000002689 soil Substances 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 5
- 238000000034 method Methods 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 4
- 239000011162 core material Substances 0.000 description 3
- 239000002184 metal Substances 0.000 description 3
- 238000005096 rolling process Methods 0.000 description 3
- 239000004035 construction material Substances 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 230000007774 longterm Effects 0.000 description 2
- 230000002093 peripheral effect Effects 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000002401 inhibitory effect Effects 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 241000894007 species Species 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、山の傾斜面、堤防や道路の法面等(以下、単に「法面」という)の崩壊を防止するために、法面等に沿って設置される落石防止留付き筋工に関するものである。
【0002】
【従来の技術】
土地開発の増加とともに、山の傾斜面、堤防や道路の法面等の崩壊を防止するための土留工事の需要が急増している。
【0003】
ところで、この種の土留工事には、従来から、法面等に沿ってコンクリートを打設したり、コンクリート製ブロックを設置する工法が多用されてきたが、近年の環境保護の高まりとともに、上記従来のコンクリートを使用する工法の見直しが進められ、自然環境に適合した緑化工法の開発が要請されている。
この環境保護の要請に応えるものとして、法枠を法面等に沿って設置するとともに、該法枠内に客土を保持して緑化を図る方法が実用化されている。
【0004】
【発明が解決しようとする課題】
しかしながら、従来の落石防止留付き筋工は、型枠にコンクリートを流し込んで成型したものであるため、施工が大がかりで工事費が高くなるとともに、施行後の景観も見劣りのするという問題があった。
また、緑化工法に関しては、芝による緑化工事よりも郷土種の樹林による自然復元化の要請が高いが、この樹林による復元化には、数年に亘る長い期間が必要であり、このため、法面に浮石や転石がある場合は落石を防止しなくてはならない。
この落石に対処する方法として、法面全体を金網で覆うロック金網工事があるが、このような従来の方法では、樹林が成長していく過程において金網が樹木の幹の生育を阻害し、また、景観も悪くなる。
【0005】
本発明は、上記従来の落石防止留付き筋工が有する問題点に鑑み、森林保全や林業振興のためにその有効利用が要請されている間伐材等の木材を利用して、施工が容易で工事費が安く、また、樹木の幹の生育を阻害することなく、転石等の落下を防止することができる景観の良好な落石防止留付き筋工を提供することを目的とする。
【0006】
【課題を解決するための手段】
上記目的を達成するため、本発明の落石防止留付き筋工は、間伐材等の木材の中心部長手方向に貫通孔を形成し、該貫通孔内に索条又は線材を挿通することにより筋工材を形成し、該索条又は線材の端部に締結具を配設して、該締結具を介して複数の筋工材を連結するとともに、前記締結具から支柱を立設して、該支柱に金網等の防護壁を張設したことを特徴とする。
【0007】
この落石防止留付き筋工は、間伐材等の木材の中心部長手方向に貫通孔を形成し、該貫通孔内に索条又は線材を挿通することにより筋工材を形成し、該索条又は線材の端部に締結具を配設して、該締結具を介して複数の筋工材を連結することから、施工が容易で材料費や工事費が安く、しかも、芯材となる索条又は線材が間伐材等の木材によって覆われているため、施行後も自然に近い良好な景観を確保することができる。
そして、筋工の締結具から支柱を立設して、該支柱に金網等の防護壁を張設することから、長期に亘る樹林の復元化に対応し、樹木の幹の生育を阻害することなく、転石等の落下を防止することができる。
【0008】
この場合において、前記締結具をアースアンカー又はアンカーボルトで地面に固定することができる。
【0009】
これにより、落石防止留付き筋工を法面に簡単かつ確実に設置することができる。
【0010】
また、支柱の下端をその筋工の締結具に揺動可能に係止するとともに、支柱の上部を上段及び下段の筋工の締結具に支持部材を介して連結することができる。
ここでいう「締結具」には、アースアンカーやアンカーボルト等の固定具を含むものとする。
【0011】
これにより、支柱を容易かつ安価に立設することができる。
【0012】
【発明の実施の形態】
以下、本発明の落石防止留付き筋工の実施の形態を図面に基づいて説明する。
【0013】
図1〜図3に、本発明の落石防止留付き筋工の第1実施例を示す。
この落石防止留付き筋工1は、法面2に設置し、枠内に客土3を保持することにより法面の緑化を図るものであり、間伐材4の中心部長手方向に貫通孔5を形成し、この貫通孔5内に索条又は線材6を挿通することにより筋工材7を形成するとともに、この索条又は線材6の端部に締結具8を配設し、この締結具8を介して複数の筋工材7を連結することにより、筋状の筋工1を形成している。
そして、この落石防止留付き筋工は、筋工1の締結具8から支柱14を立設し、この支柱14に、防護壁として金網15を張設している。
【0014】
具体的には、図3に示すように、所定径の間伐材を例えば数十cm程度の適当な長さに切断し、切断した間伐材4の中心にワイヤーロープや鋼線等からなる索条又は線材6を通す貫通孔5を穿設する。
そして、切断した複数の間伐材4に索条又は線材6を挿通した後、索条又は線材6を適当な寸法で切断し、その端部に直接雄ねじを刻設するか、又は雄ねじを設けたボルト状の軸具9を固定する。
この場合、索条又は線材6に挿通する間伐材4の数量や長さ、あるいは索条又は線材6の長さ等は、施工する法面2に応じて適宜に変更することができる。
なお、切断した間伐材4は、図示のように端面を面取りしておくことが好ましい。
【0015】
締結具8としては、例えば、円形や四角形の有底筒状の締結具8を使用することができる。
すなわち、この締結具8の筒壁81にボルト孔82を穿設し、このボルト孔82に前記索条又は線材6の軸具9等を挿通してナット10により固定する。
また、締結具8の底壁83に、アースアンカー又はアンカーボルト用の貫通孔を穿設し、この締結具8をアースアンカー又はアンカーボルト(図示のものは、アースアンカー)11で地面に固定することにより、筋工材7を法面2に固定するようにする。
このように、適当な数量の筋工材7を、筋状(又は格子状)に法面上に配設し、筋工材7端部の締結具8をアースアンカー又はアンカーボルト11で地面に固定することにより、筋工1を法面2に形成することができる。
【0016】
一方、支柱14は、その筋工1の締結具8に下端を係止するとともに、上部を上段の筋工1の締結具8に索条や線材等の支持部材16を介して連結することによって立設されている。
【0017】
具体的には、支柱14は、特に限定されるものではないが、鋼管や形鋼からなり、支柱14の下端を締結具8に溶接等により強固に係止するようにしたり、本実施例に示すように、軸19を介して、揺動可能に係止することができる。
【0018】
そして、支柱14の下端を軸19を介して、揺動可能に係止するようにした場合には、締結具8(アンカーボルト11)に接続した支持部材としてのワイヤーロープ16、18をこの鋼管の中に通して、上段及び下段の筋工1の締結具8(アンカーボルト11)に接続することにより、支柱14を支持するようにしている。
なお、ワイヤーロープ16、18は、支柱14の上部に直接固定することもできる。
【0019】
そして、複数立設した支柱14の上部同士と下部同士を各々ワイヤーロープ17でつなぎ、これらワイヤーロープ17と支柱14の間に金網15等を張設している。
【0020】
かくして、本実施例の落石防止留付き筋工1は、間伐材4に索条又は線材6を挿通して筋工材7を形成するとともに、この索条又は線材6の端部に配設した締結具8を介して複数の筋工材7を連結することから、施工が容易で材料費や工事費が安く、しかも、芯材となる索条又は線材6が間伐材4によって覆われているため、施行後も自然に近い良好な景観を確保することができる。
【0021】
そして、筋工の締結具8から支柱14を立設して、該支柱14に金網15等の防護壁を張設することから、長期に亘る樹林の復元化に対応し、樹木の幹の生育を阻害することなく、転石等の落下を防止することができる。
【0022】
また、締結具8をアースアンカー又はアンカーボルト11で地面に固定して、筋工材7を法面2に固定することにより、法枠1を法面2に簡単かつ確実に設置することができる。
【0023】
そして、本実施例の落石防止留付き筋工は、以下の特性も有している。
(1)ワイヤーロープ等の索条又は線材6の柔軟性や引っ張り強さ、間伐材4の堅さ等のそれぞれの特性を利用している。間伐材4だけであれば柔軟性、引っ張り強さがなく、また、索条又は線材6だけであれば枠を作ることも、法面2を押さえることもできない。
(2)間伐材4の長さを短くすることによって、曲げやすくなり、法面2の起伏に対しても柔軟性をもって対応することができる。
(3)アースアンカー又はアンカーボルト11は、法面2の状況に対して長くしたり、強度の強いものを使うことができる。
(4)森林保全、林業振興のためにその有効利用が要請されている間伐材4の利用促進を図ることができる。
(5)図2(b)に示すように、客土3の間伐材4の上の部分12が階段状に平たくなり、また、コンクリートのようにアクが出ないこともあって、植生状態をよくすることができる(法面の階段状化)。
(6)長い時間の経過とともに間伐材4が風化して土に還り、異物の残留を極めて少なくすることができる。
(7)落石防止留付き筋工1を、格子状にしたり、筋状にしたりすることができ、設計を自由に変更することができる。
(8)締結具8の底面に水抜き穴(図示省略)を開け、締結具8の中にも客土吹付を行い、きめ細かい緑化を図ることができる。
【0024】
次に、図4に、本発明の落石防止留付き筋工の第2実施例を示す。
この落石防止留付き筋工(筋工)1は、第1実施例と同様に、間伐材4の中心部長手方向に貫通孔5を形成し、この貫通孔5内にワイヤーロープ6を挿通することにより筋工材7を形成するとともに、このワイヤーロープ6の端部に締結具8を配設し、この締結具8を介して複数の筋工材7を連結することにより、法面に沿って平行(筋状)に筋工材7を配設するようにしたものである。
そして、この落石防止留付き筋工は、例えば、図1に示すように、筋工1の締結具8から支柱14を立設し、この支柱14に、防護壁として金網15を張設している。
【0025】
なお、本実施例においては、法面に沿って平行(筋状)に配設した筋工材7と直交する方向には何も配設していないが、同様の資材を配設して、格子状の落石防止留付き格子枠とすることもでき、本発明は、これを排除するものでない。
【0026】
この場合において、締結具として、プレス成形した有底円筒状の締結具8を使用するようにしている。
そして、この締結具8の周壁85の対向する2箇所(又はクロスする4箇所)にそれぞれボルト孔82を穿設し、このボルト孔82にフック付きボルト86を挿通してナット10により固定する。
そして、このフック付きボルト86に、リング状に形成したワイヤーロープ6の一端6aを掛止するとともに、ワイヤーロープ6の他端6bを掛けて固定具87により固定する。
この固定具87は、ワイヤーロープを固定するために用いられる各種部材を使用することができるが、例えば、固定具に折り返すようにして挿通したワイヤーロープ6の端部側を一方向(緊張方向)にのみ移動可能(他方向(緩み方向)には移動不可)とし、ワイヤーロープ6の端部側を一方向(緊張方向)に引っ張ることによりワイヤーロープ6を緊張することができるようにした固定具を好適に用いることができる。
【0027】
また、締結具8の底壁83に、アースアンカー又はアンカーボルト用の貫通孔を穿設し、この締結具8をアースアンカー又はアンカーボルト(図示のものは、アンカーボルト)11で地面に固定することにより、筋工材7を法面2に固定するようにすることは、上記第1実施例と同様である。
なお、中間に位置する締結具8aは、単にワイヤーロープ6を挿通させるだけでよい。
このように、適当な数量の筋工材7を、筋状(又は格子状)に法面上に配設し、筋工材7端部の締結具8をアースアンカー又はアンカーボルト11で地面に固定することにより、筋状(格子状)の落石防止留付き筋工(格子枠)1を法面2に形成することができる。
【0028】
以上、本発明の落石防止留付き筋工について、木材として間伐材4を利用した実施例に基づいて説明したが、本発明は上記実施例に記載した構成に限定されるものではなく、例えば、直径等の寸法に制約のある間伐材4(客土3の層厚を増大させようとしても、間伐材4の直径により制約を受ける)に代えて、図5(a)に示すように、木材として角材4Aを用いることができる等、その趣旨を逸脱しない範囲において適宜その構成を変更することができるものである。
そして、木材として角材4Aを用いる場合には、例えば、2本の角材4A1、4A2を用い、少なく一方の角材4A1の他方の角材4A2との接合面に、両者を接合した状態でワイヤーロープや鋼線等からなる索条又は線材6を通す貫通孔5となる角材4A1の長手方向に伸びる溝を形成した後、図5(b)に示すような金属製等の連結具13aや図5(c)に示すような金属製等の連結ベルト13bを用いて、2本の角材4A1、4A2を接合、一体化するようにしたものを、図1〜図4に記載した一実施例と同様に用いるようにする。
なお、木材として角材4Aを用いる場合の基本的な作用効果は、木材として間伐材4を利用した場合と、同様である。
【0029】
また、本発明の名称の「落石防止留付き筋工」は、本発明の適用対象を分かりやすくするために付したものにすぎず、金網を板状のものに換えることにより、雪崩による雪の落下も防止することができる。
【0030】
【発明の効果】
本発明の落石防止留付き筋工によれば、間伐材等の木材の中心部長手方向に貫通孔を形成し、該貫通孔内に索条又は線材を挿通することにより筋工材を形成し、該索条又は線材の端部に締結具を配設して、該締結具を介して複数の筋工材を連結することから、施工が容易で材料費や工事費が安く、しかも、芯材となる索条又は線材が間伐材等の木材によって覆われているため、施行後も自然に近い良好な景観を確保することができ、間伐材の利用の促進と相俟って、自然環境に適合した工法であるということができる。
そして、筋工の締結具から支柱を立設して、該支柱に金網等の防護壁を張設することから、長期に亘る樹林の復元化に対応し、樹木の幹の生育を阻害することなく、転石等の落下を防止することができ、施工が容易で、工事費を安くすることができる。
【0031】
また、前記締結具をアースアンカー又はアンカーボルトで地面に固定することにより、落石防止留付き筋工を法面に簡単かつ確実に設置することができる。
【0032】
また、支柱の下端をその筋工の締結具に揺動可能に係止するとともに、支柱の上部を上段及び下段の筋工の締結具に支持部材を介して連結することにより、支柱を容易かつ安価に立設することができる。
【図面の簡単な説明】
【図1】 本発明の落石防止留付き筋工の第1実施例を示す正面図である。
【図2】 同実施例の落石防止留付き筋工を示し、(a)は側面図、(b)は支柱と防護壁を省略した断面側面図である。
【図3】 同実施例の落石防止留付き筋工を示し、(a)は支柱と防護壁を省略した平面図、(b)は締結具とアースアンカー又はアンカーボルトを示す断面図である。
【図4】 本発明の落石防止留付き筋工の第2実施例を示し、(a)は支柱と防護壁を省略した断面平面図、(b)はワイヤーロープと固定具を示す平面図、(c)は締結具とアースアンカー又はアンカーボルトを示す縦断面図である。
【図5】 本発明の落石防止留付き筋工の第3実施例を示し、(a)は角材の説明図、(b)及び(c)は角材を接合、一体化した状態を示す説明図、(d)は支柱と防護壁を省略した落石防止留付き筋工の断面図である。
【符号の説明】
1 落石防止留付き筋工
2 法面
3 客土
4 間伐材(木材)
4A 角材(木材)
5 貫通孔
6 索条又は線材
7 筋工材
8 締結具
81 筒壁
82 ボルト孔
83 底壁
84 アースアンカー又はアンカーボルト用貫通孔
85 周壁
86 フック付きボルト
87 固定具
9 軸具
10 ナット
11 アースアンカー(又はアンカーボルト)
12 間伐材の上の部分
13 連結具
14 支柱
15 金網(防護壁)
16 ワイヤーロープ(支持部材)
17 ワイヤーロープ
18 ワイヤーロープ(支持部材)
19 軸[0001]
BACKGROUND OF THE INVENTION
TECHNICAL FIELD The present invention relates to a rock fall prevention clasp installed along a slope, etc., in order to prevent the collapse of slopes of mountains, dikes and road slopes (hereinafter simply referred to as “slopes”). Is.
[0002]
[Prior art]
With the increase in land development, the demand for earth retaining works to prevent the collapse of mountain slopes, dikes and road slopes is increasing rapidly.
[0003]
By the way, in this type of earth retaining work, conventionally, a method of placing concrete along a slope or installing a concrete block has been frequently used. However, with the recent increase in environmental protection, A review of the construction method that uses this concrete is underway, and there is a demand for the development of a greening method suitable for the natural environment.
In response to this demand for environmental protection, a method has been put into practical use in which a legal frame is installed along a slope and the like, and the land is kept green within the legal frame.
[0004]
[Problems to be solved by the invention]
However, the conventional rock fall prevention clasps are molded by pouring concrete into the formwork, so there was a problem that the construction was large and the construction cost was high, and the landscape after enforcement was also inferior .
In addition, regarding the revegetation method, there is a higher demand for natural restoration by forests of native species than the revegetation work by lawn, but restoration by this forest requires a long period of several years. If there are floats or stones on the surface, you must prevent falling rocks.
As a method of dealing with this rock fall, there is a lock wire net construction that covers the entire slope with a wire mesh, but in such a conventional method, the wire mesh inhibits the growth of the trunk of the tree as the forest grows, and , The scenery gets worse.
[0005]
In view of the problems of the above-mentioned conventional rock fall prevention clasp, the present invention is easy to construct by using wood such as thinned wood whose effective use is required for forest conservation and forestry promotion. The purpose of the present invention is to provide a timberwork with a good rockfall prevention clasp that is inexpensive in construction and can prevent falling of rolling stones and the like without inhibiting the growth of tree trunks.
[0006]
[Means for Solving the Problems]
To achieve the above object, rockfall prevention distillate with Sujiko of the present invention, the muscle by forming a central longitudinal to the through hole of the timber, such as thinned wood, through which the rope or wire in the through hole Form a construction material, arrange a fastener at the end of the wire or wire, connect a plurality of muscle construction materials through the fastener, and stand upright from the fastener, A protective wall such as a wire mesh is stretched on the support.
[0007]
The rockfall prevention cut with Sujiko in the center longitudinal to the through hole of the timber, such as thinned wood is formed, to form a muscle Industrial Materials by inserting a rope or wire in the through hole,該索Article Alternatively, a fastener is disposed at the end of the wire, and a plurality of bracing materials are connected via the fastener. Therefore, construction is easy, material costs and construction costs are low, and the cord that becomes the core material is used. Since the strip or wire is covered with wood such as thinned wood, a good landscape close to nature can be secured even after enforcement.
And, since the pillar is erected from the brace fastener and a protective wall such as a wire mesh is stretched on the pillar, it corresponds to the restoration of the forest over the long term and inhibits the growth of the trunk of the tree In addition, it is possible to prevent falling of rolling stones.
[0008]
In this case, the fastener can be fixed to the ground with an earth anchor or an anchor bolt.
[0009]
Thereby, it is possible to easily and surely install the falling stone prevention clasp on the slope.
[0010]
Further, the lower end of the column can be rockably locked to the brace fastener, and the upper part of the column can be connected to the upper and lower brace fasteners via a support member.
The “fastener” here includes a fixture such as an earth anchor or an anchor bolt.
[0011]
Thereby, a support | pillar can be erected easily and cheaply.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the rock fall prevention clasp according to the present invention will be described with reference to the drawings.
[0013]
FIGS. 1 to 3 show a first embodiment of the faller-preventing clasp according to the present invention.
The rockfall prevention distillate with muscle Engineering 1, installed in
The falling stone prevention clasp has a
[0014]
Specifically, as shown in FIG. 3, a thinning material having a predetermined diameter is cut into an appropriate length of, for example, about several tens of centimeters, and a rope formed of a wire rope, a steel wire, or the like at the center of the cut thinning
And after inserting the line or the
In this case, the quantity and length of the thinning
In addition, it is preferable to chamfer the end surface of the cut
[0015]
As the
That is, a
Further, a through hole for an earth anchor or an anchor bolt is formed in the
In this way, an appropriate amount of the reinforcing
[0016]
On the other hand, the
[0017]
Specifically, the
[0018]
When the lower end of the
The
[0019]
And the upper part and lower part of the support |
[0020]
Thus, in the present embodiment, the falling
[0021]
Further, since the
[0022]
Further, the
[0023]
And the strutwork with falling rock prevention clasps of this example also has the following characteristics.
(1) The respective properties such as the ropes such as wire ropes or the flexibility and tensile strength of the
(2) By shortening the length of the thinned
(3) The earth anchor or
(4) It is possible to promote the use of thinned
(5) As shown in FIG. 2 (b), the
(6) The thinned
(7) The falling
(8) A water drain hole (not shown) is opened on the bottom surface of the
[0024]
Next, FIG. 4 shows a second embodiment of the falling rock prevention clasp according to the present invention.
The rockfall prevention distillate with muscle Engineering (muscle Engineering) 1, similarly to the first embodiment, the center longitudinal to the through
Then, as shown in FIG. 1, for example, as shown in FIG. 1, this shingle prevention clasp has a
[0025]
In this example, nothing is arranged in the direction orthogonal to the reinforcing
[0026]
In this case, a press-molded bottomed
Then, bolt holes 82 are drilled at two opposing (or four crossing) locations on the peripheral wall 85 of the
Then, one
This fixing
[0027]
Further, a through hole for an earth anchor or anchor bolt is formed in the
In addition, the fastener 8a located in the middle should just insert the
In this way, an appropriate amount of the reinforcing
[0028]
As described above, the falling stone prevention clasp according to the present invention has been described based on the example using the thinning
Then, when the square 4A is used as the wood, for example, two squares 4A1, 4A2 are used, and at least one square 4A1 is joined to the other square 4A2 in a state in which both are joined with a wire rope or steel. After forming a groove extending in the longitudinal direction of the square member 4A1 to be the through
In addition, the fundamental effect in the case of using the
[0029]
In addition, the name of the present invention, “Footstone prevention clasp” is only given to make the application target of the present invention easier to understand, and by replacing the wire mesh with a plate, Falling can also be prevented.
[0030]
【The invention's effect】
According to rockfall prevention distillate with muscle Engineering of the present invention, to form a center longitudinal to the through hole of the timber, such as thinnings, to form a muscle Industrial Materials by inserting a rope or wire into the through hole Since a fastener is arranged at the end of the wire or wire, and a plurality of reinforcement materials are connected via the fastener, the construction is easy, the material cost and the construction cost are low, and the core Since the ropes or wires used as the material are covered with timber such as thinned wood, it is possible to secure a good landscape close to nature even after enforcement, and in combination with the promotion of the use of thinned wood, the natural environment It can be said that the construction method is suitable for
And, since the pillar is erected from the brace fastener and a protective wall such as a wire mesh is stretched on the pillar, it corresponds to the restoration of the forest over the long term and inhibits the growth of the trunk of the tree In addition, it can prevent the fall of a boulder and the like, and the construction is easy and the construction cost can be reduced.
[0031]
Further, by fixing the fastener to the ground with an earth anchor or an anchor bolt, it is possible to easily and surely install the falling stone prevention clasp on the slope.
[0032]
In addition, the lower end of the column is swingably locked to the brace fastener, and the upper part of the column is connected to the upper and lower brace fasteners via a support member, so that the column can be easily and It can be erected at low cost.
[Brief description of the drawings]
FIG. 1 is a front view showing a first embodiment of a faller-preventing clasp according to the present invention.
FIGS. 2A and 2B are cross-sectional side views in which a strut and a protective wall are omitted, in which FIG.
FIG. 3 is a plan view of the same embodiment with a rock fall prevention clasp, in which (a) is a plan view in which a support column and a protective wall are omitted, and (b) is a cross-sectional view showing a fastener and a ground anchor or an anchor bolt.
4A and 4B show a second embodiment of the rock fall prevention clasp according to the present invention, wherein FIG. 4A is a cross-sectional plan view in which a support column and a protective wall are omitted, and FIG. 4B is a plan view showing a wire rope and a fixture. (C) is a longitudinal cross-sectional view which shows a fastener and an earth anchor or an anchor bolt.
FIGS. 5A and 5B show a third embodiment of the shingle prevention clasp according to the present invention, where FIG. 5A is an explanatory view of square bars, and FIGS. 5B and 5C are explanatory views showing a state in which square bars are joined and integrated. , (D) is a cross-sectional view of a timberwork with falling rock prevention clasps in which a support and a protective wall are omitted.
[Explanation of symbols]
1
4A Square wood (wood)
DESCRIPTION OF
12 Upper part of thinned wood 13
16 Wire rope (supporting member)
17
19 axes
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002075357A JP4031273B2 (en) | 2002-03-19 | 2002-03-19 | Barrage with falling rock prevention clasp |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002075357A JP4031273B2 (en) | 2002-03-19 | 2002-03-19 | Barrage with falling rock prevention clasp |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2003268724A JP2003268724A (en) | 2003-09-25 |
| JP4031273B2 true JP4031273B2 (en) | 2008-01-09 |
Family
ID=29204451
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002075357A Expired - Fee Related JP4031273B2 (en) | 2002-03-19 | 2002-03-19 | Barrage with falling rock prevention clasp |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4031273B2 (en) |
-
2002
- 2002-03-19 JP JP2002075357A patent/JP4031273B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2003268724A (en) | 2003-09-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3479516B2 (en) | Slope stabilization method and slope stabilization device | |
| JP3954414B2 (en) | Protective body using net | |
| JP4031273B2 (en) | Barrage with falling rock prevention clasp | |
| JP4480151B2 (en) | Underground support for wooden transplanted trees and support method | |
| KR100458928B1 (en) | Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid | |
| JP4372632B2 (en) | Slope greening method | |
| JP3096424B2 (en) | Vegetation infrastructure construction method | |
| JP3799403B2 (en) | Earth retaining structure using steel mesh | |
| JP3145458B2 (en) | How to plant trees | |
| JP2747952B2 (en) | Greening slope protection method | |
| JP4749627B2 (en) | Legal framework | |
| KR20130036032A (en) | Below ground tree supporting systems and other supplements | |
| JP2794368B2 (en) | Slope greening method | |
| JP3862606B2 (en) | Slope stabilization method using tree root bearing and its slope stabilization device | |
| JP4237697B2 (en) | River bank protection device and river bank protection method | |
| KR200354767Y1 (en) | Slope safeguard member structure for road | |
| JP5537332B2 (en) | Futon straw lifting base material and method for laying futon straw using the lifting base material | |
| KR20080112634A (en) | Cut slope support structure | |
| JP4411396B2 (en) | Sediment retaining wall structure | |
| JP2583168B2 (en) | Slope greening method | |
| JP4540032B2 (en) | Slope greening method | |
| JP2002070024A (en) | Earth retaining frame and earth retaining method of slope or the like | |
| KR20060105075A (en) | Planting method of tree and the apparatus | |
| KR200253330Y1 (en) | Reinforced Earth Retaining-Wall for using Steel-Frame and Geogrid | |
| KR101061977B1 (en) | Slope reinforcement pressure plate |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050127 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070314 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070515 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070608 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070925 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071018 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101026 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111026 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111026 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121026 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131026 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |