JP4044798B2 - Emergency-response gate pump equipment - Google Patents
[go: Go Back, main page]

JP4044798B2 - Emergency-response gate pump equipment - Google Patents

Emergency-response gate pump equipment Download PDF

Info

Publication number
JP4044798B2
JP4044798B2 JP2002193158A JP2002193158A JP4044798B2 JP 4044798 B2 JP4044798 B2 JP 4044798B2 JP 2002193158 A JP2002193158 A JP 2002193158A JP 2002193158 A JP2002193158 A JP 2002193158A JP 4044798 B2 JP4044798 B2 JP 4044798B2
Authority
JP
Japan
Prior art keywords
gate
drainage
opening
pump
emergency
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002193158A
Other languages
Japanese (ja)
Other versions
JP2004036167A (en
Inventor
国久 千綿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mizota Co Ltd
Original Assignee
Mizota Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mizota Co Ltd filed Critical Mizota Co Ltd
Priority to JP2002193158A priority Critical patent/JP4044798B2/en
Publication of JP2004036167A publication Critical patent/JP2004036167A/en
Application granted granted Critical
Publication of JP4044798B2 publication Critical patent/JP4044798B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Barrages (AREA)
  • Structures Of Non-Positive Displacement Pumps (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、河川、水路等の排水樋門に設置されるゲートポンプ設備に関する。更に詳しくは、非常時に対応が可能なように3つのゲート構成で排水樋門の開閉を行うようにしたゲートポンプ設備に関する。
【0002】
【従来の技術】
海と河川の境界部あるいは本川(下流側で外水側ともいう)と支川(上流側で内水側ともいう)との境界部に設けられる排水樋門のゲートは、通常は水位が高い上流の支川の水を水位の低い下流の本川に流すため開放されているが、例えば台風等で下流の本川の水位が高くなって逆流する場合(支川側水位が規定以上になるとき)は閉じなければならない。通常は支川側の水位が本川側の水位より高くなっており、支川側から本川側に向かって自然排水が行われる。
【0003】
又、本川側の水位が支川側の水位より高くなり逆流する場合は、排水樋門のゲートを閉じ逆流を防止している。又、排水樋門等のゲートに排水ポンプを組み込んだゲートポンプがある。この場合には、本川側の水位が支川側の水位より規定以上に高くなる逆流のときに排水樋門等のゲートを閉じ、水中ポンプで強制的に排水を行っている。従来から自然排水はゲートを開いて行い、逆流のときはポンプで強制排水を行っている。又、ゲートポンプにおいては、排水ポンプに逆止弁が設けられていて、排水ポンプが排水運転操作を停止した場合に、吐出口から逆流するのを防止している。
【0004】
本川側と支川側との水位差が頻繁に交互に変わるような場合、例えば、降雨の場合は本川側の水位と支川側の水位との差が不安定になり、どちらの水位が高いか判断がつきにくい場合がある。さらに、短時間で本川側と支川側の水位の変動が繰り返し行われることがある。その場合でも、その都度ゲートの開閉動作を排水樋門上部と水路底間において繰り返し行っている。
【0005】
このように本川側と支川側の水位の差が微妙で交互に高低を繰り返し、高低差の一定しない不安定な状態においても、通常は支川側の水位が高くなればゲートを排水樋門上部の高所まで持ち上げゲートを開いて自然排水を行っている。本川側の水位が高くなればゲートを水路底まで下降させゲートを閉じ、水中ポンプにより強制排水を行っている。しかしこのように不安定な状態の場合においても、開閉動作を頻繁に行わねばならないので、管理、操作上問題である。本来ゲートは頻繁に開閉操作を行うものでないのに、頻繁に操作を繰り返すことで、結果的に運転回数が多くなりメンテナンス等運転管理上の負担が増大する。
【0006】
さらに、水位差のない場合においても運転と停止を繰り返すことになるので、水中ポンプへの負担が大きく、水中ポンプを機械的に損傷してしまうおそれも生じていた。このようなトラブルの際には、水中ポンプを水路から上方へ引き上げ、水路上方の高所でメンテナンスを行う必要がある。排水が流れている状態の場合は特に危険であり、困難な作業が伴う。
【0007】
又、排水ポンプを引き上げないタイプのゲートポンプにトラブルが発生した場合においては、ポンプの運転を停止して逆止弁の閉鎖で逆流を防止し、水位が下がったところでメンテナンス作業を行っている。又、排水ポンプはできるだけ低い水位まで排水のできることが要求され、そのために吸い込み渦の防止対策の施された方法も実施されている。
【0008】
更に、このようなゲート設備は、一般に住宅に隣接する狭い場所に設置されることが多く、引き上げ開閉形式の場合は、開閉装置を排水樋門の上部に据え付けるため、コンクリート製の排水樋門構造物が高くなって周囲の景観を損なっている。又、開閉装置を設置するために鋼製架台も必要であるが、これを住宅地等の狭い場所に設置するのは困難な工事を必要とし危険が伴い、費用もかかる。一方水路の状態によって排水口を適切に段階的に開閉のできるゲートであることも要望されている。
【0009】
【発明が解決しようとする課題】
現状で特にゲートポンプの水中ポンプにトラブルが発生した場合は、前述のように引き上げて行えばトラブルに対し直ぐ対処できる。しかし、排水は常時流れており、水路に水中ポンプがない状態であると、逆流を防止できない問題点がある。又、トラブル処理が長期間になる場合は、排水管理の上でも問題が生じ、どうしても何らかの形で排水を止めねばならぬ事態も出てくる。排水の流れはトラブルの有無に関わらず変化しているので、トラブルがあっても正常に近い排水管理の状態を維持することが理想である。本発明は前述のような背景のもとに、従来実施されている方法等の特徴点を生かし、従来の問題点を解決し新しい設備として創案されたもので、以下の目的を達する。
【0010】
本発明の目的は、第1ゲートに第2ゲートを案内させて第1ゲートと相対的に開閉が可能な構成にして、上流側、下流側の水位差に応じて段階的に相互のゲートを開閉し、排水能率を高めたゲートポンプ設備の提供にある。
【0011】
本発明の他の目的は、第1ゲートと第2ゲートに対し独立して水中ポンプを有する第3ゲートを設け、低水位であっても吸い込み渦の発生を防止し、安定してしかも確実に排水のできるゲートポンプ設備の提供にある。
【0012】
本発明の更に他の目的は、水中ポンプにトラブルが発生しても水路を閉じることができ、逆流等の排水流れを防止できるゲートポンプ設備の提供にある。
【0013】
本発明の更に他の目的は、水中ポンプにトラブルが発生した場合は、水中ポンプを水路上に引き上げることができ、メンテナンスを容易にし、コスト低減を図ったゲートポンプ設備の提供にある。
【0014】
本発明の更に他の目的は、設備の高さを低くして、周辺の景観を損なわず、環境保全を配慮したゲートポンプ設備の提供にある。
【0015】
【課題を解決するための手段】
前記課題を解決するため、次の手段を採る。即ち、
本発明1の非常時対応型ゲートポンプ設備は、排水口を有する排水樋門に設置されるゲートポンプ設備であって、前記排水樋門の昇降方向に案内され下部にゲート排水口を有して前記排水樋門の排水口を開閉する第1ゲートと、前記第1ゲートに案内され、この第1ゲートに相対的に昇降動作して前記第1ゲートのゲート排水口を開閉し且つ前記第1ゲートと係合して昇降する第2ゲートと、前記排水樋門上部に設けられ一端が前記第2ゲートに結合し前記第1ゲートと前記第2ゲートを段階的に昇降開閉させる第1開閉装置と、前記第1ゲートに沿って昇降し前記ゲート排水口を開閉する第3ゲートと、前記排水樋門上部に設けられ前記第3ゲートを昇降開閉させる第2開閉装置と、前記第3ゲートに設けられ前記ゲート排水口が開放されたとき上流から下流への自然排水または、強制排水を可能とする水中ポンプと、この水中ポンプの吐出口側に設けられ、自然排水又は強制排水のときに開き自然排水の流れに逆流するときに閉じる逆止弁とから構成されている。
【0016】
ゲート構成を第1ゲートと第2ゲートを1つの開閉装置で、第3ゲートを他の開閉装置で各々独立して開閉のできる多段階の開閉構成にした。第3ゲートにトラブル等が発生しても一方の開閉装置で排水樋門の排水口を閉じることができるので、逆流の防止を行い、排水流れのない状態で安全にトラブル処理ができる。
【0017】
また、前記発明1において、前記第3ゲートにゲート排水口を有して相対し、排水止水のための止水体を前記第1ゲートに一体的に設けてもよい。この止水体は第1ゲートの一部であってもよく、又、第1ゲートと同形状のものであってもよい。
【0018】
止水体は第3ゲートの案内部を構成し、第3ゲートが下降してゲート排水口を閉鎖したときゲート上部を外板構造で閉鎖し、止水体と第3ゲートとの間には水密装置が設けられ止水する。この止水体を設けることでゲート排水口は厚くなり、自然排水が第1ゲート側から第3ゲート側へ流れる場合の実施例に適用したときは、排水の吸い込み流れはゲート排水路の壁面に沿う流れになるため、吸い込み渦発生の防止に効果的である。
【0019】
さらに、前記発明1において、前記第2ゲートが上昇時に当接し前記第1ゲートを前記第2ゲートとともに上昇させる当接体を前記第1ゲートに設けてもよい。第1ゲートの開閉は第2ゲートの開閉動作を利用する。第1ゲートの上部にストッパーの役目をなす当接体を設けた構成にし、第1ゲートと第2ゲートを相対的に動作させ段階的な開閉を行う。第2ゲートが下降し第1ゲートが排水口を閉じた後、続いて第2ゲートでゲート排水口を閉じることが可能な構成である。
【0020】
さらに、前記発明1において、前記第3ゲートが前記第1ゲートを離れて前記排水樋門上部に移動することを可能とするための案内部材を、前記排水樋門に設けてもよい。第3ゲートを第1ゲートから離れた上部位置に引き上げることで、第3ゲートの水中ポンプのメンテナンスが容易に行える構成である。
【0021】
さらに、前記発明1において、前記第1開閉装置には、一端が前記第2ゲートに連結し他端が開閉機構部に連結するラック棒が含まれていてもよい。構成が簡素でゲートを上昇、下降とも強制的に開閉ができる構成なので、開閉動作を確実に行うことができる。
【0022】
さらに、前記発明1において、前記第2開閉装置には、一端が前記第3ゲートに連結し他端が開閉機構部に連結するラック棒が含まれていてもよい。構成が簡素でゲートを上昇、下降とも強制的に開閉ができる構成なので、開閉動作を確実に行うことができる。
【0023】
さらに、前記発明1において、前記第2ゲートは、前記第3ゲートが異常になったときこの第3ゲートが下降状態であっても下降して前記ゲート排水口を閉鎖する構成になっていてもよい。非常時の対応に好適で、排水流れを止めて第3ゲートを引き上げることが可能である。
【0024】
【発明の実施の形態】
以下、本発明の実施の形態を図面に従って説明する。
(実施の形態1)
図1は、本発明の非常時対応型ゲートポンプ設備1の全体構成を示した側面断面図である。本発明のゲートは3つのゲートで構成され、図1は、第3ゲートが排水樋門水路底の最下位置に設置され、又第1ゲートも水路底に設置された第1段階の開閉状態を示す。第2ゲートは開放状態である。この図の場合、排水は水中ポンプのみを通過して流れる。ゲートは閉鎖状態にあるが、排水が少ない場合に、排水を第3ゲートに設けられた水中ポンプ内を通過させることで、自然排水は可能である。
【0025】
図2は、図1同様の側面断面図で、第3ゲートが上昇して開放し、自然排水状態を示した第2段階の開閉構成図である。図1の場合の構成では、自然排水を続けていて水量が多くなると、排水は水中ポンプ内の通過のみで行っているので、水中ポンプの通過能力を越えると水中ポンプに塵芥がかかり水中ポンプを損傷するおそれがある。又、逆流であった流れが急に上流からの流れに変わり、水中ポンプの通過排水のみで自然排水を行うことができないような場合に、水中ポンプを引き上げて第2段階の開閉状態とする。
【0026】
図3は、図1同様の側面断面図で、第3ゲートを更に上昇させ上方へ引き上げるとともに、第1,第2ゲートをも上昇させた状態を示している。この場合は排水樋門の排水口全部が開放される状態となる。排水の量が多い場合に対応するものである。図4は第3ゲートを尚も上昇させ排水樋門の最上部に位置させた状態である。この図の場合は、第3ゲートのトラブルやメンテナンス等に対応する構成である。第1ゲートと第2ゲートは、逆流を防止するため水路底に位置し、排水口を閉じる。
【0027】
図5は図1の正面図で、図6は部分平面図で、中心線を境に(a)部の図は、図2のX−X断面図を示し、(b)部の図は、図1のY−Y断面図を示している。平面図においては左右対称図となるので、説明の便宜上、2つの部分の分割表示としている。図7は上部フレームの構成を示した部分図で、図1のZ−Z断面図である。概略以上のような構成になっているが、次に、本発明のゲートポンプ設備1の詳細な構成を図に従って説明する。
【0028】
通常、水路の排水は上流側(内水側)Aから下流側(外水側)Bへ自然排水の形で流れている。ゲートポンプ設備1の基体である排水樋門2はコンクリートで構成され、この排水樋門2は略四角形状の門体を構成し、下部が排水口3になっている。この排水樋門2の上部には、ゲートを開閉するための2つの開閉装置4,5が取り付けられている。
【0029】
ゲートは3つ有し、1つは、親ゲートに相当する第1ゲート6を構成し、排水樋門2の側壁に直接案内され上下方向に昇降する。第1ゲート6は排水樋門2の排水口3を閉鎖する状態で設置されているが、上部は鋼板で構成され水の通過の出来ない構成で、下部は開放されゲート排水口7を有し水の通過が可能な構成になっている。従って図1の状態は、排水樋門2の排水口3の上半分は、閉じられ、下半分が開放された状態になっている。又、第1ゲート6には水密装置6gが設けられ、この排水樋門2に対して水密状態を構成している。
【0030】
この第1ゲート6は、上流側に止水フレーム8が設けられ、この止水フレーム8と第1ゲート6の間に挟持された状態で第2ゲート9が設けられている。この第2ゲート9は、第1ゲート6上を相対的に上下方向に移動可能である。第2ゲート9が上部に移動したときは、第1ゲート6の下部即ちゲート排水口7が開放状態となる。又、第2ゲート9が下方向に移動したときは、第1ゲート6のゲート排水口7は閉鎖される。
【0031】
従ってこの場合は、排水口3を全て閉鎖する状態となる。第2ゲート9の上部にはラック棒10の一端が吊り金具11を介して取り付けられている。このラック棒10の他端は第1開閉装置4の駆動機構に連結している。このラック棒10の先端部は第1開閉装置4の外部に張り出すので外側をカバー10aで覆っている。又、第1ゲート6と止水フレーム8との間に跨って上部フレーム12が設けられている。ラック棒10はこの上部フレーム12を貫通させているが、第2ゲート9の上端部はこの第2ゲート9が上昇するとき、上部フレーム12に当接するようになっている。
【0032】
この上部フレーム12はストッパーになっていて、第2ゲート9が上昇したとき第2ゲート9の上端部はこの上部フレーム12に当接し、尚も上昇したときは第1ゲート6を吊り下げた状態で、図3に示すように排水口3を開放する。逆に第2ゲート9が下降するときは第1ゲート6も自重で第2ゲート9とともに底部が水路底に達するまで下降する。第1ゲート6が水路底に達した後は、第2ゲート9のみが下降することになる。
【0033】
又、この第2ゲート9には第1ゲート6に相対して水密装置9gが設けられ、第1ゲート6との間に水密状態を構成する。この第2ゲート9の移動は排水樋門2上部に設けられた第1開閉装置4によって行われる。この第1開閉装置4の開閉機構は公知の手段によっている。第1開閉装置4は、モーター、減速機構等を有していて、自動的に駆動できる装置であり、その構造は図示していないが、ハンドルの手動操作によってもラック棒10を上下させゲートを開閉させることができる装置である。開閉の伝達手段にラック棒を使用することは、チェーンと異なり上昇、下降とも剛体による押し引き可能な動作となるので、確実なゲート開閉動作ができる。簡素な伝達手段である。
【0034】
更に、この排水樋門2の上流側は壁がなく開放状態になっていて、第1ゲート6は排水樋門2の壁側に設けられた案内部を構成する戸当金物13を介して案内され、昇降方向に移動可能である。第1ゲート6が下降すると、第1ゲート6は矩形状の排水口3の上半分を覆って閉じているが、排水口3から上昇すると上半分は開かれる。
【0035】
この排水樋門2には、前述のとおり、第1ゲート6の案内及び水密のための戸当金物13がコンクリートに埋設されて取り付けられている。この戸当金物13は、排水樋門2の水路底に第1ゲート6の側底部及び第3ゲート14の底部が当接するための水底戸当金物と、排水口3の上部には上部戸当金物と、排水樋門2の各側壁にあって第1ゲート3の昇降方向案内のため凹状の側壁戸当金物とで構成されている。
【0036】
戸当金物13は、鋼板及び型鋼等の構成でコンクリートに埋設されている。一方第1ゲート6の側板両側部及び上部には、水密装置6gが取り付けられている。排水樋門2の戸当金物13の側壁戸当金物及び上部戸当金物に接して第1ゲート6が降下し、排水口3の上半分を閉じたとき、排水口3周囲に下流側から上流側に跨って水が隙間を通して戸当金物13と第1ゲート6の水密装置6gとの間で浸水するのを防止している。但し、ゲート排水口7の水の移動は内外水位差によって発生する。
【0037】
第1ゲート6は、桁構造になっていて、排水樋門2側に位置する端縦桁6dに、摺動材6eが第1ゲート6の側面に取り付けられている。この摺動材6eは、排水樋門2の案内ガイドである戸当金物13に対し摺動し、第1ゲート6は規制されながら昇降方向に案内される。この第1ゲート6は、上、下流側が外板6aとなっていて、排水の流れを直接受ける。内部には縦桁6c、横桁6b等で補強され水圧に耐えるようになっている。
【0038】
上流側の外板6aは摺動材9eとして、第2ゲート9の水密装置9gの摺動板となっている。第1ゲート6の端縦桁6d側にはクサビ6hが設けられている。第1ゲート6が下降し排水樋門2の下部に位置決めされ排水口3を閉じるとき、排水樋門2の戸当金物13との間でこのクサビ6hが相互にくい込む構成となり、第1ゲート6が排水樋門2に押圧し固定された状態となる。クサビ6hがあることで、第1ゲート6と排水樋門2との間のガタを解消することになる。
【0039】
従って、第3ゲート14上の水中ポンプ17が運転したとき、第1ゲート6の振動を防止させることができ、振動に伴う悪影響が避けられる。又、この第1ゲート6に対しては、上流側に端縦桁6dを介して止水フレーム8が設けられ、第1ゲート6と一体化されている。この止水フレーム8も断面形状は第1ゲート6と略同じ構成になっている。外側に外板8aが設けられ、内部に縦桁8c、横桁8bで補強されている。又、端縦桁8dが設けられ第1ゲート6の端縦桁6dとの間で案内溝15を形成している。
【0040】
又、上流側の外板8aは摺動材8eとして、第3ゲート14の水密装置14gの摺動板となっている。この止水フレーム8は、端縦桁6dを介して第1ゲート6と一体的に設けられているが、第1ゲート6と同様の機能を有し第1ゲート6の一部と見なしてもよい。第1ゲート6と略同形の構成としたことで厚みを有し、ゲート排水口7の水路行程は長くなっている。第1ゲート6の上方部は、第2ゲート9が引き上げられるときの上昇端となっていて上部フレーム12が設けられ、引き上げ時のストッパーを構成している。
【0041】
この上部フレーム12は剛性のある構成となっていて、鋼板12a、補強桁12b及び水密装置12cを有する鋼板及び型鋼の構成である。この上部フレーム12は、第1ゲート6と止水フレーム8に跨って固定されている。又、第1ゲート6の下端部6iは、第3ゲート14が降下したときの降下端になっていて、降下ストッパーの役目をなす端桁を構成し、第3ゲート14が第1ゲート6から外れないようになっている。
【0042】
第1ゲート6と止水フレーム8との間に挟まれて、第2ゲート9が昇降方向移動自在に設けられている。第1ゲート6には、止水フレーム8との間に案内溝15が設けられ、この案内溝15に沿って第2ゲート9が第1ゲート6と同方向に案内され昇降移動する。この第2ゲート9も第1ゲート6と同様に桁構造をなし、外側に外板9aを構成し、排水樋門2に近い部分の端縦桁9dが第1ゲート6の案内溝15にはまり込んでいる。
【0043】
この第2ゲート9と相対する第1ゲート6の面は、摺動材9eが設けられていて、水密装置9gの摺動面となっている。第2ゲート9が閉じたとき水の出入りを防止する。更に、この第2ゲート9は、第1ゲート6と同様に縦桁9cと横桁9bによって補強されている。第2ゲート9の端縦桁9dにはクサビ9hが設けられている。第2ゲート9が下降し第1ゲート6の下部に位置決めされゲート排水口7を閉じるとき、第1ゲート6との間でこのクサビ9hが相互にくい込む構成となり、第2ゲート9が第1ゲート6に押圧し固定された状態となる。
【0044】
この結果、第2ゲート9と第1ゲート6との間にはガタが解消され、前述のクサビ6hと合わせ2つのゲートは排水樋門2にしっくりと固定された状態になり、第3ゲート14上の水中ポンプ17が運転したとき振動を防止でき、振動に伴う悪影響が避けられる。
【0045】
この第2ゲート9上部には、前述のように吊り金具11を介してラック棒10が取り付けられている。このラック棒10は水路幅方向に沿って2個取り付けられ、排水樋門2上部に設けられた第1開閉装置4に連結している。実施の形態では、水路幅が広いことを考慮して2個のラック棒を介させているが、水路幅が狭い場合は、1個であってもよい。止水フレーム8の上流側には、上下方向に昇降する第3ゲート14が設けられている。この第3ゲート14は止水フレーム8とガイドフレーム16間の案内溝15aに規制され上下方向に移動する。
【0046】
又、この第3ゲート14は排水樋門2に設けられた2本の案内バー21によっても案内されている。第3ゲート14も鋼板及び型鋼による構造になっていて、前述の第1ゲート6,第2ゲート9と同様に、外板14a、横桁14b、縦桁14c、端縦桁14d、吊り金具14f、水密装置14g、ポンプ取り付け枠14h及びクサビ14iより構成されている。
【0047】
この第3ゲート14の上流側壁面に水中ポンプ17が取り付けられている。この水中ポンプ17は第3ゲート14に取り付けられていることで、この設備はゲートポンプ構成をなしている。この水中ポンプ17は横軸ポンプで、吸い込み口17c側がフランジ17aを介して第3ゲート14の壁面であるポンプ取り付け枠14hに取り付けられ、吐出口17bが下流側に向けられている。水中ポンプ17が停止しているときは、排水はこの水中ポンプ17内を通過でき自然排水が可能である。
【0048】
又吐出口17b側には、フラップ弁18(逆止弁)が取り付けられていて、フラップ弁18の弁が上下方向に揺動する。流れが自然排水あるいは強制排水の場合には上下方向に揺動して開放し、流れが下流から上流に逆流する場合には弁が閉じて排水の逆流を防止する。
【0049】
本実施の形態においては、水中ポンプ17を横形としているが、横形に限定されるものではない。立軸水中ポンプであってもよい。また、サンドポンプ等のものであってもよく、この場合は河床の清掃もできる。水中ポンプ17が駆動し内蔵する羽根が回転すると、水は水中ポンプ内を上流側Aから下流側Bに流れる。
【0050】
このフラップ弁18は、揺動動作が横方向に揺動して開閉する観音開きのようなタイプであってもよい。このフラップ弁18は一種の蓋を構成し、水中ポンプ17が運転され前述の方向に水が水中ポンプ17内を流れる場合は、フラップ弁18は水流の勢いで上方に持ち上げられる。下流側Bの水位が上流側Aの水位より高くなり、水中ポンプ17の運転を停止したときは、フラップ弁18は下がり水中ポンプ17の吐出口17bを塞ぎ、逆流を防止する。
【0051】
次に第3ゲート14の第2開閉装置5について説明する。この第2開閉装置5の基本構造は、基本的に第1開閉装置4と同様の機構になっている。水中ポンプ17を搭載した第3ゲート14の上部には、吊り金具14fが取り付けられている。この吊り金具14fには、吊りピン19が設けられ、この吊りピン19にラック棒20が連結されている。ラック棒20には、長手方向にラックが設けられている。このラック棒20の移動機構は第2開閉装置5内にあり、図示していないが、公知の手段、例えば歯車等でラック棒20を第2開閉装置5によって上下方向に移動させる。
【0052】
ハンドルで操作、あるいはモータ駆動等で操作すると、ラック棒20が上下方向に移動するようになっている。ラック棒20は前述のとおり2つ設けられていて、2つのラック棒20の駆動系は連結手段により連結されている。このラック棒20の場合も前述同様に2個としているが、水路幅が狭い場合は1個であってもよい。一方のラック棒20を駆動すると他方のラック棒20も一体的に動作し上下動する。このラック棒20の上端部は排水樋門2の上部に設けられたカバー20aで覆われている。この第3ゲート14の開閉伝達手段にラック棒20を使用することで、前述のラック棒10と同様の効果を奏し、確実な開閉動作ができる。
【0053】
従って、第3ゲート14の開閉操作は、第2開閉装置5によりラック棒20が上下方向に移動することにより行われる。また、上流側の水路には、図示しない除塵機が設けられ、上流から流れてくる流木等の塵芥類を除去し、水中ポンプ17へ塵芥類が侵入するのを防止している。第3ゲート14は2本のラック棒20により支持され、前述のように止水フレーム8とガイドフレーム16との案内溝15aに沿って上下方向に移動可能である。次にゲートの開閉状態について説明する。
【0054】
図1の第1段階の開閉状態は、逆流があって水中ポンプを運転する場合、あるいは例えば降雨が弱まり下流の水位が下がり、上流水位と同じかわずかに下流水位が下がるような水量が少ないとき、水中ポンプ17の運転を止めて水中ポンプ17内を通して自然排水を行うような状態の場合である。逆流があったときは、フラップ弁18により阻止することができる。第1ゲート6が排水樋門2の排水口3を塞いでいるが、ゲート排水口7は開放されている。第3ゲート14が第1ゲート6のゲート排水口7を塞ぎ、逆流を防止する構成になっている。
【0055】
降雨が続き、下流側の水が上流側に逆流する危険が生じたときは、第3ゲート14を降下させ図1の状態にして強制排水を行う。水密装置を有効に機能させるため止水フレーム8の下端に設けられた下端部6iに第3ゲート14が当接し、第1ゲート6及び止水フレーム8は一層強く水路を閉じる。
【0056】
この場合、第1ゲート6及び第2ゲート9の各水密装置6g,9gにより排水口3,ゲート排水口7は水密状態となっている。第1ゲート6,第3ゲート14が閉じた状態で排水を行うときは、前述のとおり水中ポンプ17で強制排水を行う。このとき、上部フレーム12は、水密装置12cによりラック棒10通過に伴う第1ゲート6及び止水フレーム8上部の水密状態を維持する。又、急に水流が自然流に変わったときは、水中ポンプ17を停止させて、排水を水中ポンプ17を通過させて上流から下流へ流す。このときフラップ弁18は水流の勢いで揺動し上方に持ち上げられ開放状態となる。
【0057】
このフラップ弁18は、水平軸を支点に上下方向に揺動するフラップ型の弁である。下流側の水位が上流側より高くなり逆流するときは、このフラップ型のゲートを構成するフラップ弁18が自重と逆流の水圧で下って水中ポンプ17の吐出口17bを塞ぎ、流れが水中ポンプ17内に逆流するのを防止している。
【0058】
次に第2段階の開閉状態は、第3ゲート14を第2開閉装置5の駆動で上方へ移動させ、第1ゲート6のゲート排出口7のみが開放された状態である。前述のように、自然排水の水量が多くなり、水中ポンプの通過能力を越えるため、水中ポンプ17に負担を与えないように水中ポンプ17を上方へ退避させた状態である。従ってこの場合、水中ポンプ17は運転されない。
【0059】
続いて第3段階の開閉状態は、引き続き第3ゲート14を上方へ引き上げ、同時に第2ゲート9を引き上げて上部フレーム12とともに第1ゲート6を引き上げ排水口3を完全に開放させ、第3ゲート14を水路上で停止させた状態である。この状態は、排水樋門2の排水口3が全面開放され、第1ゲート6のゲート排水口7も開放された状態となる。
【0060】
次に第4段階の場合は、非常時又はメンテナンスのときの開閉状態を示している。この第4段階の開閉状態において、第3ゲート14を独立して第1ゲート6から離し、排水樋門2の上部に引き上げることができる。この状態は、メンテナンスを含め非常時の場合である。即ち、トラブル等が発生したとき先ず第2ゲート9を降下させ、続いて第3ゲート14上の水中ポンプ17を排水樋門2上部に上昇させる。
【0061】
第2ゲート9の降下に伴い第1ゲート6を降下させ排水口3を閉鎖する。尚も第2ゲート9を降下させ第1ゲート6のゲート排水口7を閉鎖する。実際の動作は、図1の状態で水中ポンプ17が強制排水中にトラブルを発生した場合、水中ポンプ17の引き上げに合わせて第2ゲート9を降下させるだけでよい。このようにして、ゲート排水口7を閉じ排水の流れを完全に停止させる。
【0062】
第2ゲート9を降下させた後第3ゲート14を引き上げるが、このとき始めはガイドフレーム16と止水フレーム8との案内溝15aをガイドにして、第3ゲート14は引き上げられる。この位置以上に尚も排水樋門2上部へ引き上げるときは、第3ゲート14を案内溝15aを離れて移動させ、案内バー21を利用してメンテナンスのできる位置まで引き上げる。その後トラブル等が解消したならば、再び第3ゲート14を降下させゲート排水口7を閉じ、第2ゲート9を引き上げ強制排水の可能な状態にする。
【0063】
トラブル等がなく通常の場合、排水口3の全面開放のためには、第1ゲート6の下半分はゲート排水口7になっているので、第1ゲート6を第1ゲート6高さの半分のみ引き上げるだけでよい。これにより、従来に比べ排水樋門2の高さを低くすることができ、メンテナンスが極めて容易に行うことができる。
【0064】
(実施の形態2)
図8から図13は、非常時対応型ゲートポンプ設備の他の実施例を示す図である。排水樋門2に対する第1ゲート6の取り付け構成及び第1ゲート6に対する第2ゲート9の取り付けの基本構成は、前述の場合と同様であり、又、第3ゲート14の取り付け構成も前述同様であるので詳細説明は省略する。
実施の形態1との相違点は、排水流れの方向が上流側と下流側が反対になっていることである。実施の形態2においては、第1ゲート6側を上流とし、第3ゲート14側を下流としている。この場合第3ゲート14の水中ポンプ17の取り付け方向は逆になる。又、吐出口17bが外側に配置されることで、第3ゲート14に対する取り付け位置が実施の形態1と異なる。
【0065】
従って第3ゲート14は実施の形態1の第3ゲート14とは形状が異なる。排水は第1ゲート6側から第3ゲート14側に流れ、ゲート排水口7から水中ポンプ17側に向かって流れ込むことになる。前述のように、ゲート排水口7近傍は、第1ゲート6,第2ゲート9,止水フレーム8の重なり部分となっていて、壁面は厚みのある流路を形成している。このため、水中ポンプ17による吸い込みの際、空気吸い込みに伴う渦発生を防止している。ゲート排水口7の側壁が厚みを有していることから、空気吸い込み渦発生を防止する効果がある。
【0066】
図8は図1に相当する図で、前述のように第3ゲート14の水中ポンプ17の取り付け位置は異なる。自然排水は矢印のように流れるので流れによる押圧力は止水フレーム8側にかかり、各水密装置に対しては浮き方向に力がかかることになる。フラップ弁18は実施の形態1においては第3ゲート14に内蔵された状態であったが、本実施の形態では第3ゲート14の外方に位置する。
【0067】
図9は図2に相当する図であり、図10は図3に相当する図であり、基本的には、前述の構成のとおりである。又、図11は、図4に相当する図である。この例の場合も基本的には前述のとおりであるが、フラップ弁関係が外方にあることから、フラップ弁関係のメンテナンスを容易に行える構成である。図12は図5に相当する図で、水中ポンプ17部分の向きが異なるが、その他の構成は図5同様である。図13は図6に相当する図で、図13の(c)部は図9のU−U断面図を示し、図13の(d)は、図8のV−V断面図を示している。
【0068】
以上、本発明の実施の形態をスライドゲートで説明したが、本発明は上記実施の形態に限定されるものではなく、ローラゲートでも可能である。又、止水フレームを別部材として構成したが、第1ゲートの一部として一体的に構成されたものでもよい。特許請求の範囲及び明細書と図面に記載された技術的思想の範囲内において種々の変形が可能である。尚、直接明細書及び図面に記載がないいずれの形状や材質であっても、本願発明の作用、効果を奏する以上、本願発明の技術的思想の範囲である。実施の形態に限定されないことはいうまでもない。
【0069】
【発明の効果】
以上説明したように、ゲートポンプによる水路の開閉方式を2系統の昇降多段のゲートポンプ構成にしたので、以下のような優れた効果を奏する。メンテナンスを含めゲートポンプの水中ポンプにトラブルが発生したとき等の非常時の場合、水中ポンプ側と独立して設置されているゲートを直ちに閉じて水流を止め、水中ポンプに損傷を与えることが回避でき、トラブル等が解消したときは、直ちに元の状態に復帰でき、内外水位差に応じた操作が容易に行えるようになった。
【0070】
又、特に川表設置の場合に、水中ポンプの吸い込みによる渦発生の防止できる構造になった。更に、排水樋門の高さを低くすることが可能となり、ゲートポンプ設備を低く構成することができた。このため、工事費がかからずコスト低減となった。水中ポンプをゲート上方の開放された側へ引き上げることを可能としたので、水中ポンプのメンテナンス等が容易に且つ安全に行うことができる。排水樋門を低くすることができたので、美観を損ねることのない設備となった。
【図面の簡単な説明】
【図1】図1は、実施の形態1におけるゲート開閉第1段階を示す本発明のゲートポンプ設備の側面断面図である。
【図2】図2は、実施の形態1におけるゲート開閉第2段階を示す本発明のゲートポンプ設備の側面断面図である。
【図3】図3は、実施の形態1におけるゲート開閉第3段階を示す本発明のゲートポンプ設備の側面断面図である。
【図4】図4は、実施の形態1におけるゲート開閉第4段階を示す本発明のゲートポンプ設備の側面断面図である。
【図5】図5は、図1の正面図である。
【図6】図6は、部分平面図で、(a)は、図2のX−X断面図を、(b)は図1のY−Y断面図を示す。
【図7】図7は、部分平面図で、図1のZ−Z断面図を示す。
【図8】図8は、実施の形態2におけるゲート開閉第1段階を示す本発明のゲートポンプ設備の側面断面図である。
【図9】図9は、実施の形態2におけるゲート開閉第2段階を示す本発明のゲートポンプ設備の側面断面図である。
【図10】図10は、実施の形態2におけるゲート開閉第3段階を示す本発明のゲートポンプ設備の側面断面図である。
【図11】図11は、実施の形態2におけるゲート開閉第4段階を示す本発明のゲートポンプ設備の側面断面図である。
【図12】図12は、図8の正面図である。
【図13】図13は、部分平面図で、(c)は、図9のU−U断面図を、(d)は図8のV−V断面図を示す。
【符号の説明】
1…非常時対応型ゲートポンプ設備
2…排水樋門
3…排水口
4…第1開閉装置
5…第2開閉装置
6…第1ゲート
7…ゲート排水口
8…止水フレーム
9…第2ゲート
10…ラック棒
12…上部フレーム
14…第3ゲート
17…水中ポンプ
18…フラップ弁
20…ラック棒
21…案内バー
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a gate pump facility installed in a drainage lock such as a river or a waterway. More particularly, the present invention relates to a gate pump facility that opens and closes a drainage lock gate with a three-gate configuration so that it can cope with an emergency.
[0002]
[Prior art]
The gate of the drainage lock gate at the boundary between the sea and river or the boundary between the main river (also called the outside water side on the downstream side) and the tributary (also called the inside water side on the upstream side) usually has a high water level. It is opened to flow the water of the upstream tributary to the downstream main river with a low water level, but when the water level of the downstream main river becomes high due to, for example, a typhoon, etc. (when the tributary side water level exceeds the specified level) Must be closed. Normally, the water level on the tributary side is higher than the water level on the main river side, and natural drainage is performed from the tributary side toward the main river side.
[0003]
In addition, when the water level on the main river side becomes higher than the water level on the tributary river side, the drainage gate is closed to prevent backflow. There is also a gate pump in which a drainage pump is incorporated in a gate such as a drainage lock. In this case, the gate such as the drainage lock is closed and the water is forcibly drained by the submersible pump when the water level on the main river side becomes higher than the water level on the tributary side. Conventionally, natural drainage is performed by opening the gate, and forced drainage is performed by a pump during reverse flow. Further, in the gate pump, a check valve is provided in the drain pump, and when the drain pump stops the drain operation, it is prevented from flowing backward from the discharge port.
[0004]
When the water level difference between the main river side and the tributary river side changes frequently, for example, in the case of rain, the difference between the water level on the main river side and the water level on the tributary side becomes unstable, and which water level is higher It may be difficult to judge. Furthermore, the water level on the main river side and the tributary side may be repeatedly changed in a short time. Even in such a case, the gate is repeatedly opened and closed between the upper part of the drainage gate and the bottom of the waterway.
[0005]
In this way, the difference in water level between the main river side and the tributary river side is subtle, and alternately rises and falls, and even if the water level on the tributary river side becomes high, the gate is usually located above the drainage lock gate. The gate is lifted up to a high point and the natural drainage is carried out. When the water level on the main river side rises, the gate is lowered to the bottom of the waterway, the gate is closed, and forced drainage is performed by a submersible pump. However, even in such an unstable state, opening and closing operations must be frequently performed, which is a management and operational problem. Although the gate does not frequently perform opening and closing operations, repeating the operation frequently results in an increase in the number of operations and an increase in operation management burden such as maintenance.
[0006]
Furthermore, since the operation and the stop are repeated even when there is no difference in water level, the load on the submersible pump is large, and there is a possibility that the submersible pump is mechanically damaged. In case of such trouble, it is necessary to lift the submersible pump upward from the water channel and perform maintenance at a high place above the water channel. When drainage is flowing, it is particularly dangerous and involves difficult work.
[0007]
When trouble occurs in a gate pump that does not pull up the drainage pump, the pump operation is stopped and the check valve is closed to prevent backflow, and maintenance work is performed when the water level drops. In addition, the drainage pump is required to be able to drain to the lowest possible water level, and for this reason, a method with measures for preventing suction vortex has been implemented.
[0008]
In addition, such gate facilities are generally installed in a narrow space adjacent to a house, and in the case of a pull-up opening / closing type, a concrete drainage lock structure is used to install the switchgear on top of the drainage lock. Things get higher and damage the surrounding landscape. In addition, a steel mount is also required to install the switchgear, but installing it in a narrow place such as a residential area requires difficult construction and is dangerous and expensive. On the other hand, there is a demand for a gate that can open and close the drain port appropriately in stages depending on the state of the water channel.
[0009]
[Problems to be solved by the invention]
If trouble occurs in the submersible pump of the gate pump at present, the trouble can be dealt with immediately if it is raised as described above. However, drainage always flows, and there is a problem that backflow cannot be prevented if there is no submersible pump in the water channel. In addition, when the trouble processing is for a long period of time, a problem also arises in wastewater management, and there is a situation that the drainage must be stopped in some way. Since the flow of wastewater changes regardless of whether or not there is a trouble, it is ideal to maintain the state of wastewater management close to normal even if there is a trouble. The present invention has been created as a new facility by solving the problems of the prior art by making use of the features of the conventional methods and the like based on the background described above, and achieves the following objects.
[0010]
The object of the present invention is to guide the second gate to the first gate so that it can be opened and closed relative to the first gate, and to connect the gates in stages according to the water level difference between the upstream side and the downstream side. The purpose is to provide gate pump equipment that opens and closes to improve drainage efficiency.
[0011]
Another object of the present invention is to provide a third gate having a submersible pump independently for the first gate and the second gate, to prevent the generation of suction vortices even at low water levels, stably and reliably. To provide a gate pump facility that can drain water.
[0012]
Still another object of the present invention is to provide a gate pump facility that can close a water channel even if a trouble occurs in a submersible pump and can prevent a drainage flow such as a reverse flow.
[0013]
Still another object of the present invention is to provide a gate pump facility that can raise a submersible pump onto a water channel when trouble occurs in the submersible pump, facilitates maintenance, and reduces costs.
[0014]
Still another object of the present invention is to provide a gate pump facility that takes environmental conservation into consideration without lowering the height of the facility and damaging the surrounding landscape.
[0015]
[Means for Solving the Problems]
In order to solve the above problems, the following means are adopted. That is,
The emergency response type gate pump facility of the present invention 1 is a gate pump facility installed in a drainage gate having a drainage port, and is guided in the ascending / descending direction of the drainage gate and has a gate drainage port in the lower part. A first gate that opens and closes a drain port of the drain gate, and is guided by the first gate, and moves up and down relative to the first gate to open and close the gate drain port of the first gate and the first gate. A second gate that moves up and down by engaging with the gate; and a first opening and closing device that is provided at an upper portion of the drainage gate and that has one end coupled to the second gate and that lifts and lowers the first gate and the second gate stepwise. A third gate that moves up and down along the first gate to open and close the gate drain, a second opening and closing device that is provided above the drain gate and opens and closes the third gate, and the third gate Provided and the gate drain is opened. When the submersible pump that enables natural drainage or forced drainage from upstream to downstream and the discharge port side of this submersible pump, it opens during natural drainage or forced drainage and closes when it reverses the flow of natural drainage And a check valve.
[0016]
The gate configuration is a multi-stage open / close configuration in which the first gate and the second gate can be opened / closed independently by one open / close device, and the third gate can be opened / closed independently by another open / close device. Even if trouble occurs in the third gate, the drainage gate of the drainage gate can be closed with one switchgear, so that backflow can be prevented and the trouble can be handled safely without drainage flow.
[0017]
In the first aspect of the present invention, the third gate may have a gate drain port and face the third gate, and a water stop body for drain water stop may be provided integrally with the first gate. The waterstop may be a part of the first gate or may have the same shape as the first gate.
[0018]
The waterstop constitutes a guide part of the third gate, and when the third gate descends and the gate drainage port is closed, the upper part of the gate is closed with an outer plate structure, and a watertight device is provided between the waterstop and the third gate. Is provided to stop the water. By providing this water stop, the gate drain becomes thicker, and when applied to the embodiment where natural drainage flows from the first gate side to the third gate side, the suction flow of drainage follows the wall surface of the gate drainage channel. Since it becomes a flow, it is effective in preventing suction vortex generation.
[0019]
Furthermore, in the first aspect of the present invention, a contact body may be provided in the first gate that makes contact when the second gate is raised and raises the first gate together with the second gate. The opening and closing operation of the first gate uses the opening and closing operation of the second gate. A contact body serving as a stopper is provided on the upper portion of the first gate, and the first gate and the second gate are operated relatively to perform stepwise opening and closing. After the second gate descends and the first gate closes the drain, the gate drain can be closed by the second gate.
[0020]
Furthermore, in the said invention 1, you may provide the guide member for enabling the said 3rd gate to leave the said 1st gate and to move to the said drainage lock upper part in the said drainage lock. By pulling up the third gate to an upper position away from the first gate, the submersible pump of the third gate can be easily maintained.
[0021]
Further, in the first aspect of the invention, the first opening / closing device may include a rack bar having one end connected to the second gate and the other end connected to the opening / closing mechanism. Since the configuration is simple and the gate can be forcibly opened and closed both when it is raised and lowered, the opening and closing operation can be performed reliably.
[0022]
Further, in the first aspect of the invention, the second opening / closing device may include a rack bar having one end connected to the third gate and the other end connected to the opening / closing mechanism. Since the configuration is simple and the gate can be forcibly opened and closed both when it is raised and lowered, the opening and closing operation can be performed reliably.
[0023]
Furthermore, in the first aspect of the invention, the second gate may be configured to descend and close the gate drain when the third gate becomes abnormal even if the third gate is in the lowered state. Good. It is suitable for emergency, and it is possible to stop the drainage flow and raise the third gate.
[0024]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
(Embodiment 1)
FIG. 1 is a side sectional view showing the overall configuration of an emergency response type gate pump facility 1 according to the present invention. The gate of the present invention is composed of three gates. FIG. 1 shows a first stage opening / closing state in which the third gate is installed at the lowest position of the drainage lock channel and the first gate is also installed at the channel bottom. Indicates. The second gate is in an open state. In this case, the drainage flows through only the submersible pump. Although the gate is in a closed state, when there is little drainage, natural drainage is possible by passing the drainage through a submersible pump provided at the third gate.
[0025]
FIG. 2 is a side cross-sectional view similar to FIG. 1, and is a second-stage opening / closing configuration diagram in which the third gate is lifted and opened to show a natural drainage state. In the configuration shown in FIG. 1, when natural drainage continues and the amount of water increases, drainage is performed only by passing through the submersible pump. There is a risk of damage. In addition, when the flow that has been a reverse flow suddenly changes to a flow from the upstream, and natural drainage cannot be performed only with the drainage water of the submersible pump, the submersible pump is pulled up to the second stage open / close state.
[0026]
FIG. 3 is a side sectional view similar to FIG. 1 and shows a state where the third gate is further raised and pulled upward, and the first and second gates are also raised. In this case, all drain outlets of the drainage gate are opened. This corresponds to the case where the amount of drainage is large. FIG. 4 shows the state in which the third gate is still raised and positioned at the top of the drainage lock. In the case of this figure, it is the structure corresponding to the trouble, maintenance, etc. of a 3rd gate. The first gate and the second gate are located at the bottom of the water channel to prevent backflow and close the drain.
[0027]
FIG. 5 is a front view of FIG. 1, FIG. 6 is a partial plan view, the figure of (a) part shows the XX sectional view of FIG. The YY sectional view of FIG. 1 is shown. Since the plan view is a left-right symmetric diagram, for convenience of explanation, the two parts are divided and displayed. FIG. 7 is a partial view showing the configuration of the upper frame, and is a ZZ cross-sectional view of FIG. The configuration is roughly as described above. Next, the detailed configuration of the gate pump facility 1 of the present invention will be described with reference to the drawings.
[0028]
Usually, the drainage of the water channel flows from the upstream side (inside water side) A to the downstream side (outside water side) B in the form of natural drainage. The drainage lock 2 that is the base of the gate pump facility 1 is made of concrete, the drainage lock 2 forms a substantially rectangular gate body, and the lower part is a drainage port 3. Two opening and closing devices 4 and 5 for opening and closing the gate are attached to the upper part of the drainage lock 2.
[0029]
There are three gates, one of which constitutes the first gate 6 corresponding to the parent gate, which is directly guided by the side wall of the drainage lock 2 and moves up and down. The first gate 6 is installed in a state where the drain port 3 of the drainage lock 2 is closed, but the upper part is made of a steel plate and cannot pass water, and the lower part is opened and has a gate drain port 7. It is configured to allow water to pass through. Therefore, in the state shown in FIG. 1, the upper half of the drainage port 3 of the drainage lock 2 is closed and the lower half is opened. Further, the first gate 6 is provided with a watertight device 6g and constitutes a watertight state with respect to the drainage lock 2.
[0030]
The first gate 6 is provided with a water stop frame 8 on the upstream side, and a second gate 9 is provided in a state of being sandwiched between the water stop frame 8 and the first gate 6. The second gate 9 is relatively movable on the first gate 6 in the vertical direction. When the second gate 9 moves to the upper part, the lower part of the first gate 6, that is, the gate drain port 7 is opened. When the second gate 9 moves downward, the gate drain port 7 of the first gate 6 is closed.
[0031]
Therefore, in this case, all the drain ports 3 are closed. One end of a rack bar 10 is attached to the upper part of the second gate 9 via a hanging metal fitting 11. The other end of the rack bar 10 is connected to the drive mechanism of the first opening / closing device 4. Since the front end of the rack bar 10 protrudes outside the first opening / closing device 4, the outer side is covered with a cover 10a. Further, an upper frame 12 is provided between the first gate 6 and the water stop frame 8. The rack bar 10 penetrates through the upper frame 12, but the upper end of the second gate 9 comes into contact with the upper frame 12 when the second gate 9 is raised.
[0032]
The upper frame 12 serves as a stopper, and when the second gate 9 is raised, the upper end of the second gate 9 is in contact with the upper frame 12, and when the second gate 9 is raised, the first gate 6 is suspended. Then, the drain port 3 is opened as shown in FIG. Conversely, when the second gate 9 descends, the first gate 6 also descends with its own weight until the bottom reaches the water channel bottom together with the second gate 9. After the first gate 6 reaches the water channel bottom, only the second gate 9 is lowered.
[0033]
The second gate 9 is provided with a water-tight device 9 g opposite to the first gate 6, and forms a water-tight state between the second gate 9 and the first gate 6. The movement of the second gate 9 is performed by the first opening / closing device 4 provided at the upper part of the drainage lock 2. The opening / closing mechanism of the first opening / closing device 4 is a known means. The first opening / closing device 4 includes a motor, a speed reduction mechanism, and the like, and can be automatically driven. The structure of the first opening / closing device 4 is not illustrated, but the rack bar 10 can be moved up and down by manual operation of the handle. It is a device that can be opened and closed. The use of a rack bar as the transmission means for opening and closing makes it possible to push and pull with a rigid body both when it is raised and lowered unlike a chain, so that a reliable gate opening and closing operation can be performed. It is a simple transmission means.
[0034]
Further, the upstream side of the drainage lock 2 has no walls and is in an open state, and the first gate 6 is guided through a door fitting 13 constituting a guide part provided on the wall side of the drainage lock 2. And is movable in the up-and-down direction. When the first gate 6 descends, the first gate 6 covers and closes the upper half of the rectangular drainage port 3, but when the first gate 6 rises from the drainage port 3, the upper half is opened.
[0035]
As described above, the door metal fitting 13 for guiding the first gate 6 and watertight is embedded in the drainage lock 2 and is attached to the concrete. This door metal fitting 13 includes a water bottom door metal fitting for the side bottom of the first gate 6 and the bottom of the third gate 14 to contact the water channel bottom of the drainage lock 2, and an upper door It consists of hardware and concave side wall door hardware for guiding the first gate 3 in the up-and-down direction on each side wall of the drainage lock 2.
[0036]
The door-to-door hardware 13 is embedded in concrete with a structure such as a steel plate and mold steel. On the other hand, a watertight device 6g is attached to both side portions and the upper part of the side plate of the first gate 6. When the first gate 6 descends in contact with the side wall door metal and upper wall hardware of the drainage lock gate 2 of the drainage lock gate 2 and closes the upper half of the drainage port 3, it is upstream from the downstream side around the drainage port 3. Water is prevented from entering between the door hardware 13 and the watertight device 6g of the first gate 6 through the gap across the side. However, the movement of the water at the gate drain 7 is caused by the difference in water level between the inside and outside.
[0037]
The first gate 6 has a girder structure, and a sliding member 6e is attached to a side surface of the first gate 6 on an end vertical girder 6d located on the drainage lock 2 side. The sliding member 6e slides relative to the door hardware 13 which is a guide for the drainage lock 2, and the first gate 6 is guided in the up-and-down direction while being regulated. The first gate 6 has an outer plate 6a on the upper and downstream sides, and directly receives the flow of drainage. The interior is reinforced with vertical girders 6c, horizontal girders 6b, etc. so as to withstand water pressure.
[0038]
The upstream outer plate 6a serves as a sliding plate for the watertight device 9g of the second gate 9 as a sliding member 9e. A wedge 6h is provided on the end string 6d side of the first gate 6. When the first gate 6 descends and is positioned below the drainage lock 2 and closes the drainage port 3, the wedge 6 h is difficult to interleave with the door hardware 13 of the drainage lock 2. Is pressed and fixed to the drainage lock 2. The presence of the wedge 6h eliminates the play between the first gate 6 and the drainage lock 2.
[0039]
Therefore, when the submersible pump 17 on the third gate 14 is operated, the vibration of the first gate 6 can be prevented, and adverse effects associated with the vibration can be avoided. Further, a water stop frame 8 is provided upstream of the first gate 6 via an end stringer 6 d and is integrated with the first gate 6. The water stop frame 8 also has substantially the same cross-sectional configuration as the first gate 6. An outer plate 8a is provided on the outside, and the inside is reinforced with a vertical beam 8c and a horizontal beam 8b. Further, an end stringer 8 d is provided, and a guide groove 15 is formed between the end stringer 6 d of the first gate 6.
[0040]
The upstream outer plate 8a serves as a sliding plate for the watertight device 14g of the third gate 14 as a sliding member 8e. The water stop frame 8 is provided integrally with the first gate 6 through the end stringers 6d, but has the same function as the first gate 6 and can be regarded as a part of the first gate 6. Good. By having a configuration substantially the same as that of the first gate 6, the gate drainage port 7 has a long waterway stroke. The upper part of the first gate 6 serves as a rising end when the second gate 9 is pulled up, and an upper frame 12 is provided to constitute a stopper for lifting.
[0041]
The upper frame 12 has a rigid configuration, and is a configuration of a steel plate and a steel plate having a steel plate 12a, a reinforcing girder 12b, and a watertight device 12c. The upper frame 12 is fixed across the first gate 6 and the water stop frame 8. The lower end 6 i of the first gate 6 is a lower end when the third gate 14 is lowered, and constitutes an end girder that functions as a lowering stopper. The third gate 14 extends from the first gate 6. It is designed not to come off.
[0042]
A second gate 9 is provided between the first gate 6 and the water stop frame 8 so as to be movable in the up-and-down direction. A guide groove 15 is provided between the first gate 6 and the water stop frame 8, and the second gate 9 is guided in the same direction as the first gate 6 and moves up and down along the guide groove 15. Similarly to the first gate 6, the second gate 9 also has a girder structure, an outer plate 9 a is formed on the outer side, and an end vertical girder 9 d near the drainage lock 2 is fitted in the guide groove 15 of the first gate 6. It is crowded.
[0043]
A surface of the first gate 6 facing the second gate 9 is provided with a sliding material 9e, which is a sliding surface of the watertight device 9g. When the second gate 9 is closed, entry and exit of water is prevented. Further, the second gate 9 is reinforced by the vertical beam 9c and the horizontal beam 9b in the same manner as the first gate 6. A wedge 9h is provided at the end stringer 9d of the second gate 9. When the second gate 9 descends and is positioned below the first gate 6 and closes the gate drain port 7, the wedge 9 h is not easily inserted into the first gate 6, and the second gate 9 becomes the first gate. 6 is pressed and fixed.
[0044]
As a result, the backlash is eliminated between the second gate 9 and the first gate 6, and the two gates together with the wedge 6 h are fixed to the drainage lock gate 2, and the third gate 14 When the upper submersible pump 17 is operated, vibration can be prevented and adverse effects associated with vibration can be avoided.
[0045]
The rack bar 10 is attached to the upper part of the second gate 9 via the hanging metal fitting 11 as described above. Two rack bars 10 are attached along the width direction of the water channel, and are connected to a first opening / closing device 4 provided at the upper part of the drainage lock 2. In the embodiment, two rack rods are interposed in consideration of the wide channel width, but one may be used when the channel width is narrow. A third gate 14 that moves up and down is provided on the upstream side of the water stop frame 8. The third gate 14 is regulated by a guide groove 15a between the water stop frame 8 and the guide frame 16, and moves in the vertical direction.
[0046]
The third gate 14 is also guided by two guide bars 21 provided in the drainage lock 2. Similarly to the first gate 6 and the second gate 9, the third gate 14 has a structure made of a steel plate and a steel plate. The outer plate 14a, the horizontal beam 14b, the vertical beam 14c, the end vertical beam 14d, and the hanging bracket 14f are used. , A watertight device 14g, a pump mounting frame 14h, and a wedge 14i.
[0047]
A submersible pump 17 is attached to the upstream side wall surface of the third gate 14. This submersible pump 17 is attached to the third gate 14, so that this equipment has a gate pump configuration. This submersible pump 17 is a horizontal shaft pump, and the suction port 17c side is attached to a pump mounting frame 14h which is a wall surface of the third gate 14 via a flange 17a, and the discharge port 17b is directed downstream. When the submersible pump 17 is stopped, drainage can pass through the submersible pump 17 and natural drainage is possible.
[0048]
A flap valve 18 (check valve) is attached to the discharge port 17b side, and the flap valve 18 swings in the vertical direction. When the flow is natural drainage or forced drainage, it swings up and down and opens, and when the flow backflows from downstream to upstream, the valve is closed to prevent backflow of drainage.
[0049]
In the present embodiment, the submersible pump 17 has a horizontal shape, but is not limited to a horizontal shape. It may be a vertical shaft submersible pump. Further, a sand pump or the like may be used. In this case, the riverbed can be cleaned. When the submersible pump 17 is driven and the built-in blade rotates, water flows from the upstream side A to the downstream side B in the submersible pump.
[0050]
This flap valve 18 may be of a double door type that swings in a lateral direction and opens and closes. The flap valve 18 constitutes a kind of lid, and when the submersible pump 17 is operated and water flows through the submersible pump 17 in the aforementioned direction, the flap valve 18 is lifted upward by the force of the water flow. When the water level on the downstream side B becomes higher than the water level on the upstream side A and the operation of the submersible pump 17 is stopped, the flap valve 18 is lowered to block the discharge port 17b of the submersible pump 17 and prevent backflow.
[0051]
Next, the second opening / closing device 5 of the third gate 14 will be described. The basic structure of the second opening / closing device 5 is basically the same mechanism as that of the first opening / closing device 4. A suspension fitting 14f is attached to the upper part of the third gate 14 on which the submersible pump 17 is mounted. A hanging pin 19 is provided on the hanging bracket 14 f, and a rack bar 20 is connected to the hanging pin 19. The rack bar 20 is provided with a rack in the longitudinal direction. The moving mechanism of the rack bar 20 is provided in the second opening / closing device 5, and although not shown, the rack bar 20 is moved in the vertical direction by the second opening / closing device 5 using known means such as a gear.
[0052]
When operated with a handle or driven by a motor, the rack bar 20 moves up and down. Two rack bars 20 are provided as described above, and the drive systems of the two rack bars 20 are connected by a connecting means. The number of rack bars 20 is also two as described above, but may be one when the channel width is narrow. When one rack bar 20 is driven, the other rack bar 20 also moves integrally and moves up and down. The upper end of the rack bar 20 is covered with a cover 20 a provided on the upper part of the drainage lock 2. By using the rack bar 20 as the opening / closing transmission means of the third gate 14, the same effect as the rack bar 10 described above can be obtained and a reliable opening / closing operation can be performed.
[0053]
Therefore, the opening / closing operation of the third gate 14 is performed by the rack bar 20 being moved in the vertical direction by the second opening / closing device 5. Further, a dust remover (not shown) is provided in the upstream water channel to remove dust such as driftwood flowing from the upstream, and prevent dust from entering the submersible pump 17. The third gate 14 is supported by the two rack bars 20 and is movable in the vertical direction along the guide groove 15a between the water stop frame 8 and the guide frame 16 as described above. Next, the open / close state of the gate will be described.
[0054]
The first stage open / closed state of FIG. 1 is when the submersible pump is operated due to backflow, or when the amount of water is low, for example, when the rainfall is weakened and the downstream water level is lowered and the downstream water level is the same or slightly lower than the upstream water level. This is a case where the operation of the submersible pump 17 is stopped and natural drainage is performed through the submersible pump 17. When there is a backflow, it can be blocked by the flap valve 18. The first gate 6 blocks the drain port 3 of the drainage lock 2, but the gate drain port 7 is open. The third gate 14 is configured to block the gate drain port 7 of the first gate 6 and prevent backflow.
[0055]
When rain continues and there is a danger that the downstream water will flow backward to the upstream side, the third gate 14 is lowered to perform the forced drainage in the state of FIG. In order for the watertight device to function effectively, the third gate 14 comes into contact with the lower end portion 6i provided at the lower end of the water stop frame 8, and the first gate 6 and the water stop frame 8 close the water path more strongly.
[0056]
In this case, the drainage port 3 and the gate drainage port 7 are in a watertight state by the watertight devices 6g and 9g of the first gate 6 and the second gate 9, respectively. When draining with the first gate 6 and the third gate 14 closed, forced draining is performed with the submersible pump 17 as described above. At this time, the upper frame 12 maintains the watertight state of the upper part of the first gate 6 and the water stop frame 8 as the rack bar 10 passes by the watertight device 12c. When the water flow suddenly changes to a natural flow, the submersible pump 17 is stopped, and the wastewater is passed through the submersible pump 17 to flow from upstream to downstream. At this time, the flap valve 18 swings with the momentum of the water flow and is lifted upward to be in an open state.
[0057]
The flap valve 18 is a flap type valve that swings in the vertical direction about a horizontal axis. When the downstream water level becomes higher than that of the upstream side and the reverse flow occurs, the flap valve 18 constituting the flap-type gate descends with its own weight and the reverse water pressure to block the discharge port 17b of the submersible pump 17, and the flow is submerged. Prevents backflow.
[0058]
Next, the open / close state of the second stage is a state in which only the gate discharge port 7 of the first gate 6 is opened by moving the third gate 14 upward by driving the second open / close device 5. As described above, since the amount of natural wastewater increases and exceeds the passage capacity of the submersible pump, the submersible pump 17 is retracted upward so as not to impose a burden on the submersible pump 17. Therefore, in this case, the submersible pump 17 is not operated.
[0059]
Subsequently, in the third stage opening / closing state, the third gate 14 is continuously lifted upward, and at the same time, the second gate 9 is lifted to lift the first gate 6 together with the upper frame 12 to completely open the drainage port 3. 14 is stopped on the water channel. In this state, the drainage port 3 of the drainage lock 2 is fully opened, and the gate drainage port 7 of the first gate 6 is also opened.
[0060]
Next, in the case of the fourth stage, an open / close state at the time of emergency or maintenance is shown. In the fourth open / close state, the third gate 14 can be independently separated from the first gate 6 and pulled up to the top of the drainage lock 2. This state is an emergency case including maintenance. That is, when trouble occurs, the second gate 9 is first lowered, and then the submersible pump 17 on the third gate 14 is raised to the upper part of the drainage lock 2.
[0061]
As the second gate 9 is lowered, the first gate 6 is lowered to close the drain port 3. The second gate 9 is lowered to close the gate drain port 7 of the first gate 6. In actual operation, when the submersible pump 17 has trouble during forced drainage in the state of FIG. 1, it is only necessary to lower the second gate 9 as the submersible pump 17 is pulled up. In this way, the gate drain port 7 is closed to completely stop the drainage flow.
[0062]
The third gate 14 is pulled up after the second gate 9 is lowered. At this time, the third gate 14 is first lifted using the guide groove 15a between the guide frame 16 and the water stop frame 8 as a guide. When the upper part of the drainage lock 2 is still pulled up beyond this position, the third gate 14 is moved away from the guide groove 15a and pulled up to a position where maintenance can be performed using the guide bar 21. After that, if the trouble is resolved, the third gate 14 is lowered again to close the gate drain port 7 and the second gate 9 is pulled up to allow forced drainage.
[0063]
When there is no trouble or the like, the lower half of the first gate 6 is the gate drainage port 7 in order to open the drainage port 3 entirely, so the first gate 6 is half the height of the first gate 6. Just pull it up. Thereby, compared with the past, the height of the drainage lock 2 can be made low, and maintenance can be performed very easily.
[0064]
(Embodiment 2)
8 to 13 are diagrams showing other embodiments of the emergency-response gate pump facility. The basic configuration for mounting the first gate 6 to the drainage gate 2 and the basic configuration for mounting the second gate 9 to the first gate 6 is the same as described above, and the mounting configuration for the third gate 14 is also the same as described above. Detailed explanation is omitted here.
The difference from Embodiment 1 is that the direction of the drainage flow is opposite between the upstream side and the downstream side. In the second embodiment, the first gate 6 side is upstream, and the third gate 14 side is downstream. In this case, the mounting direction of the submersible pump 17 of the third gate 14 is reversed. Moreover, the attachment position with respect to the 3rd gate 14 differs from Embodiment 1 by arrange | positioning the discharge outlet 17b on the outer side.
[0065]
Therefore, the shape of the third gate 14 is different from that of the third gate 14 of the first embodiment. Waste water flows from the first gate 6 side to the third gate 14 side, and flows from the gate drain port 7 toward the submersible pump 17 side. As described above, the vicinity of the gate drain port 7 is an overlapping portion of the first gate 6, the second gate 9, and the water stop frame 8, and the wall surface forms a thick channel. For this reason, when suction is performed by the submersible pump 17, vortex generation due to air suction is prevented. Since the side wall of the gate drain port 7 has a thickness, there is an effect of preventing air suction vortex generation.
[0066]
FIG. 8 is a view corresponding to FIG. 1, and the attachment position of the submersible pump 17 of the third gate 14 is different as described above. Since the natural drainage flows as shown by the arrows, the pressing force due to the flow is applied to the water stop frame 8 side, and a force is applied to each watertight device in the floating direction. The flap valve 18 is in a state incorporated in the third gate 14 in the first embodiment, but is located outside the third gate 14 in the present embodiment.
[0067]
FIG. 9 is a diagram corresponding to FIG. 2, and FIG. 10 is a diagram corresponding to FIG. 3, basically having the above-described configuration. FIG. 11 corresponds to FIG. The case of this example is basically the same as described above, but since the flap valve relationship is outside, the flap valve-related maintenance can be easily performed. FIG. 12 is a view corresponding to FIG. 5, and the direction of the submersible pump 17 portion is different, but the other configuration is the same as FIG. 13 is a view corresponding to FIG. 6. FIG. 13 (c) shows a U-U cross-sectional view of FIG. 9, and FIG. 13 (d) shows a V-V cross-sectional view of FIG. .
[0068]
As mentioned above, although embodiment of this invention was described with the slide gate, this invention is not limited to the said embodiment, A roller gate is also possible. Moreover, although the water stop frame is configured as a separate member, it may be configured integrally as a part of the first gate. Various modifications can be made within the scope of the technical idea described in the claims and the description and the drawings. It should be noted that any shape or material not directly described in the specification and drawings is within the scope of the technical idea of the present invention as long as the effects and effects of the present invention are exhibited. Needless to say, the present invention is not limited to the embodiment.
[0069]
【The invention's effect】
As described above, the water channel opening and closing method by the gate pump is configured as a two-line multi-stage gate pump configuration, and therefore, the following excellent effects are obtained. In case of an emergency such as when a trouble occurs in the submersible pump of the gate pump including maintenance, the gate installed independently of the submersible pump side is immediately closed to stop the water flow and avoid damaging the submersible pump. When troubles were resolved, it was possible to immediately return to the original state and to easily perform operations according to the difference in water level inside and outside.
[0070]
In particular, especially in the case of riverside installation, the structure can prevent the generation of vortices due to suction of the submersible pump. Further, the height of the drainage lock can be lowered, and the gate pump equipment can be configured low. For this reason, construction costs were not incurred and the costs were reduced. Since the submersible pump can be pulled up to the open side above the gate, maintenance of the submersible pump can be performed easily and safely. Since the drainage gate was able to be lowered, it became a facility that did not impair the beauty.
[Brief description of the drawings]
FIG. 1 is a side sectional view of a gate pump facility of the present invention showing a first stage of gate opening / closing in Embodiment 1. FIG.
FIG. 2 is a side cross-sectional view of the gate pump equipment of the present invention showing a second stage of gate opening and closing in the first embodiment.
FIG. 3 is a side cross-sectional view of the gate pump equipment of the present invention showing a third stage of gate opening and closing in the first embodiment.
FIG. 4 is a side cross-sectional view of the gate pump facility of the present invention showing a fourth stage of gate opening / closing in the first embodiment.
FIG. 5 is a front view of FIG. 1;
6 is a partial plan view, FIG. 6A is a sectional view taken along line XX in FIG. 2, and FIG. 6B is a sectional view taken along line YY in FIG.
7 is a partial plan view and shows a ZZ cross-sectional view of FIG. 1; FIG.
FIG. 8 is a side cross-sectional view of the gate pump facility of the present invention showing a first stage of gate opening and closing in the second embodiment.
FIG. 9 is a side cross-sectional view of the gate pump equipment of the present invention showing a second stage of gate opening and closing in the second embodiment.
FIG. 10 is a side cross-sectional view of the gate pump facility of the present invention showing a third stage of gate opening and closing in the second embodiment.
FIG. 11 is a side cross-sectional view of the gate pump equipment of the present invention showing a fourth stage of gate opening and closing in the second embodiment.
FIG. 12 is a front view of FIG. 8;
13 is a partial plan view, FIG. 13C is a sectional view taken along the line U-U in FIG. 9, and FIG. 13D is a sectional view taken along the line V-V in FIG.
[Explanation of symbols]
1 ... Emergency emergency gate pump equipment
2 ... Drainage gate
3 ... Drain outlet
4. First opening / closing device
5. Second opening / closing device
6 ... 1st gate
7 ... Gate drain
8 ... still water frame
9 ... Second gate
10 ... Rack bar
12 ... Upper frame
14 ... Third gate
17 ... Submersible pump
18 ... flap valve
20 ... Rack bar
21 ... Guide bar

Claims (7)

排水口を有する排水樋門に設置されるゲートポンプ設備であって、
前記排水樋門の昇降方向に案内され下部にゲート排水口を有して前記排水樋門の排水口を開閉する第1ゲートと、
前記第1ゲートに案内され、この第1ゲートに相対的に昇降動作して前記第1ゲートのゲート排水口を開閉し且つ前記第1ゲートと係合して昇降する第2ゲートと、
前記排水樋門上部に設けられ一端が前記第2ゲートに結合し前記第1ゲートと前記第2ゲートを段階的に昇降開閉させる第1開閉装置と、
前記第1ゲートに沿って昇降し前記ゲート排水口を開閉する第3ゲートと、
前記排水樋門上部に設けられ前記第3ゲートを昇降開閉させる第2開閉装置と、
前記第3ゲートに設けられ前記ゲート排水口が開放されたとき上流から下流への自然排水または、強制排水を可能とする水中ポンプと、
この水中ポンプの吐出口側に設けられ、自然排水又は強制排水のときに開き自然排水の流れに逆流するときに閉じる逆止弁と
からなる非常時対応型ゲートポンプ設備。
A gate pump facility installed in a drainage gate having a drainage port,
A first gate that is guided in the raising and lowering direction of the drainage gate and has a gate drainage port at a lower portion thereof to open and close the drainage gate of the drainage gate;
A second gate that is guided by the first gate, moves up and down relative to the first gate, opens and closes the gate drain of the first gate, and moves up and down by engaging with the first gate;
A first opening / closing device provided at an upper portion of the drainage gate and having one end coupled to the second gate and opening / closing the first gate and the second gate stepwise;
A third gate that moves up and down along the first gate to open and close the gate drain;
A second opening / closing device provided above the drainage gate to open and close the third gate;
Natural drainage from upstream to downstream when the gate drain opening provided at the third gate is opened, or a submersible pump that enables forced drainage,
An emergency type gate pump facility that is provided on the discharge port side of this submersible pump and that has a check valve that opens when natural drainage or forced drainage is closed and closes when it flows back to the flow of natural drainage.
請求項1に記載の非常時対応型ゲートポンプ設備において、
前記第3ゲートにゲート排水口を有して相対し、排水止水のための止水体を前記第1ゲートに一体的に設けたことを特徴とする非常時対応型ゲートポンプ設備。
In the emergency response type gate pump equipment according to claim 1,
An emergency type gate pump facility characterized in that the third gate has a gate drain opening and is opposed to the third gate, and a water stop body for drain water stop is provided integrally with the first gate.
請求項1に記載の非常時対応型ゲートポンプ設備において、
前記第2ゲートが上昇時に当接し前記第1ゲートを前記第2ゲートとともに上昇させる当接体を、前記第1ゲートに設けたことを特徴とする非常時対応型ゲートポンプ設備。
In the emergency response type gate pump equipment according to claim 1,
An emergency response type gate pump facility, wherein the first gate is provided with an abutting body that abuts when the second gate is raised and raises the first gate together with the second gate.
請求項1に記載の非常時対応型ゲートポンプ設備において、
前記第3ゲートが前記第1ゲートを離れて前記排水樋門上部に移動することを可能とするための案内部材を、前記排水樋門に設けたことを特徴とする非常時対応型ゲートポンプ設備。
In the emergency response type gate pump equipment according to claim 1,
The emergency gate pump facility characterized in that a guide member is provided on the drainage gate to allow the third gate to move away from the first gate and move to the upper part of the drainage gate. .
請求項1に記載の非常時対応型ゲートポンプ設備において、
前記第1開閉装置には、一端が前記第2ゲートに連結し他端が開閉機構部に連結するラック棒が含まれていることを特徴とする非常時対応型ゲートポンプ設備。
In the emergency response type gate pump equipment according to claim 1,
The emergency opening type gate pump facility, wherein the first opening / closing device includes a rack bar having one end connected to the second gate and the other end connected to the opening / closing mechanism.
請求項1に記載の非常時対応型ゲートポンプ設備において、
前記第2開閉装置には、一端が前記第3ゲートに連結し他端が開閉機構部に連結するラック棒が含まれていることを特徴とする非常時対応型ゲートポンプ設備。
In the emergency response type gate pump equipment according to claim 1,
The emergency opening type gate pump equipment, wherein the second opening / closing device includes a rack bar having one end connected to the third gate and the other end connected to the opening / closing mechanism.
請求項1に記載の非常時対応型ゲートポンプ設備において、
前記第2ゲートは、前記第3ゲートが異常になったときこの第3ゲートが下降状態であっても下降して前記ゲート排水口を閉鎖する構成になっていることを特徴とする非常時対応型ゲートポンプ設備。
In the emergency response type gate pump equipment according to claim 1,
The second gate is configured to be lowered and close the gate drain port even when the third gate is in a lowered state when the third gate becomes abnormal. Type gate pump equipment.
JP2002193158A 2002-07-02 2002-07-02 Emergency-response gate pump equipment Expired - Lifetime JP4044798B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002193158A JP4044798B2 (en) 2002-07-02 2002-07-02 Emergency-response gate pump equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002193158A JP4044798B2 (en) 2002-07-02 2002-07-02 Emergency-response gate pump equipment

Publications (2)

Publication Number Publication Date
JP2004036167A JP2004036167A (en) 2004-02-05
JP4044798B2 true JP4044798B2 (en) 2008-02-06

Family

ID=31702179

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002193158A Expired - Lifetime JP4044798B2 (en) 2002-07-02 2002-07-02 Emergency-response gate pump equipment

Country Status (1)

Country Link
JP (1) JP4044798B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101397190B1 (en) 2012-03-05 2014-05-30 (주)덕유 Automatic floodgate

Also Published As

Publication number Publication date
JP2004036167A (en) 2004-02-05

Similar Documents

Publication Publication Date Title
AU2020246272B2 (en) Watertight structure for flap gate and flap gate comprising same
KR101577977B1 (en) Floodgate using hydraulic cylinder
KR200355906Y1 (en) Construction of Floodgate
JP4044798B2 (en) Emergency-response gate pump equipment
KR102198358B1 (en) Safety device that can prevent damage to screen and water gate using fixing pin and water gates including the same
JP4046517B2 (en) Staged opening and closing type gate pump equipment
CN209323480U (en) One-piece steel gate
KR102684147B1 (en) Water-gate
KR200308598Y1 (en) Sluice gate opening and shutting using float
JP4495999B2 (en) Gate facility with movable channel floor
JP4115380B2 (en) Peerless gate
JP4486765B2 (en) Drainage drainage system
JP3088524U (en) Gate pump equipment with auxiliary gate
JP3086085U (en) Compound gate pump equipment
KR20110000337U (en) Pulling up floodgate
CN221589476U (en) A drainage structure for entrances and exits of intercity railway stations
JP2000073345A (en) Forced drainage equipment
JP4307683B2 (en) Gate pump equipment
CN219260924U (en) Lifting water conservancy gate for water conservancy engineering
JP7125138B2 (en) Water stop device
JPH0120968Y2 (en)
JPH0437946Y2 (en)
JP7125139B2 (en) Water stoppage device and installation and removal method of water stoppage device
KR100897619B1 (en) Sewer backflow prevention facility in residential land development complex
KR102121767B1 (en) a movable weir for easily maintenance

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050624

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070515

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071022

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071116

R150 Certificate of patent or registration of utility model

Ref document number: 4044798

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101122

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131122

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term