Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP4064837B2 - Housing construction method and housing - Google Patents
[go: Go Back, main page]

JP4064837B2 - Housing construction method and housing - Google Patents

Housing construction method and housing Download PDF

Info

Publication number
JP4064837B2
JP4064837B2 JP2003037866A JP2003037866A JP4064837B2 JP 4064837 B2 JP4064837 B2 JP 4064837B2 JP 2003037866 A JP2003037866 A JP 2003037866A JP 2003037866 A JP2003037866 A JP 2003037866A JP 4064837 B2 JP4064837 B2 JP 4064837B2
Authority
JP
Japan
Prior art keywords
underground
existing
new
housing
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003037866A
Other languages
Japanese (ja)
Other versions
JP2004244978A (en
Inventor
俊平 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2003037866A priority Critical patent/JP4064837B2/en
Publication of JP2004244978A publication Critical patent/JP2004244978A/en
Application granted granted Critical
Publication of JP4064837B2 publication Critical patent/JP4064837B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、躯体構築方法および躯体に関するものである。
【0002】
【従来の技術】
従来、既存の躯体が残存している敷地に建物を建設する場合は、既存の躯体を地上躯体、地下躯体の順に解体して敷地を更地にし、従来の建物構築方法で新規建物を構築する。または、施工の合理化や地下躯体を有効利用するために、既存躯体の一部を残して解体し、従来の建物構築方法で新規建物を構築している。
【0003】
地下躯体を解体するには、(1)解体される地下躯体が抵抗していた土水圧に抵抗させるために、既存躯体の周囲に新規に山留め壁を構築してから解体する方法がある。また、既存の地下躯体が敷地一杯に構築されている場合は、新規の山留め壁を構築するスペースを確保するために、(2)施工上の障害となる既存地下躯体を地上から部分的に削り取り、更地にしてから山留め壁を構築した後、残りの既存躯体を解体する方法が用いられている。
【0004】
さらに、解体される地下躯体をできる限り有効に利用してそのまま土水圧に抵抗させる場合には、(3)地上躯体を解体し、発生するコンクリート殻を浮力による地下躯体の浮き上がりを防ぐために地下躯体中に充填し、既存地下躯体の周囲に遮水壁を造った後、揚水により地下水位を低下させて浮力を低減し、地下躯体中のコンクリート殻を搬出し、新規の地下躯体を構築する方法が用いられる。
【0005】
既存躯体のない敷地に地下構造物を構築する場合には、地下構築物の外壁に当たる箇所に山留め壁を構築し、山留め壁の内部の地盤を揚水しながら掘削した後、山留め壁内部に形成した密封空間を圧気し、密封空間を用いて構築物を構築する方法がある(例えば、特許文献1参照)。
【0006】
【特許文献1】
特開平11−6164号公報
【0007】
【発明が解決しようとする課題】
しかしながら、(1)の方法では、新規に山留め壁を構築するため建設コストが高くなる。(2)の方法では、(1)の方法よりさらに工程が複雑になるため、建設コストは一層高くなり、工事期間も長くなる。(3)の方法は、既存の地下躯体を土水圧に抵抗させて新規躯体を構築するものであるが、既存の地下躯体を解体して新規躯体を構築する方法である(1)や(2)の方法と比べて建設コストがより高く、工事期間も長くなり、既存躯体の有効利用にはつながっていない。
【0008】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、敷地内に残存する既存の地下躯体を有効利用し、短期間で経済的に新規構造物を構築できる躯体構築方法および躯体を提供することにある。
【0009】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、既存躯体を用いて新規躯体を構築する方法であって、既存地下躯体内の空間を密閉して圧気する工程(a)と、前記既存地下躯体の内部を解体する工程(b)と、前記既存地下躯体内に新規地下躯体を構築する工程(c)と、前記既存地下躯体内の空間の圧気を終了する工程(d)とを具備することを特徴とする躯体構築方法である。
【0010】
工程(a)では、既存地下躯体の圧力バランス階の床を耐圧補強し、既存地下躯体内の所定の部分を密閉して圧気する。圧気圧は、地下底盤に作用する水圧、地下壁に作用する土水圧から決定する。既存地下躯体内には、必要に応じて圧力調整空間を設置する。工程(d)では、新規地下躯体が地下壁に作用する土水圧を支持できることを確認してから圧気を終了する。
【0011】
工程(b)と工程(d)の間には、既存躯体の解体後に浮力で躯体が浮き上がるのを防ぐために、地下躯体の下方に地盤アンカまたは引抜杭を設置する工程(e)をさらに設けてもよい。この場合、工程(d)の後、必要に応じて、既存躯体の地上部分を解体し、新規地上躯体を構築する工程(f)を実施する。
【0012】
工程(e)を実施しない場合、代わりの浮力対応策として、新規躯体の構築に重量コンクリートを用いて建物重量の増加を図る。または、工程(f)で、浮力と建物荷重のバランスを考慮して、既存地上躯体の解体と新規地上躯体の構築を並行して行う。
【0013】
第1の発明では、既存躯体を用いて新規躯体を構築する際に、まず、既存地下躯体内の空間を密閉して圧気し、既存地下躯体の内部を解体する。このとき、既存地下躯体内の空間の圧気圧で、地下外壁、地下底盤に作用する土水圧に抵抗する。また、既存地下躯体に作用する浮力には、既存地上躯体を含む既存躯体の重量で抵抗する。次に、構造部材の解体によって確保された既存地下躯体内に新規地下躯体を構築し、既存地下躯体内の空間の圧気を終了する。
【0014】
第2の発明は、既存躯体を用いて新規躯体を構築する方法であって、既存地下躯体内の空間を密閉して圧気する工程(a)と、前記既存地下躯体の下方に山留め壁を造成する工程(b)と、前記既存地下躯体の底盤を解体し、前記山留め壁の内部を掘削する工程(c)と、前記山留め壁の内部に新規地下躯体を構築する工程(d)と、前記既存地下躯体内と前記新規地下躯体内の空間の圧気を終了する工程(e)とを具備することを特徴とする躯体構築方法である。
【0015】
工程(a)では、既存地下躯体の圧力バランス階の床を耐圧補強し、既存地下躯体内の所定の部分を密閉して圧気する。圧気圧は、地下底盤に作用する水圧、地下壁に作用する土水圧から決定する。既存地下躯体内には、必要に応じて圧力調整空間を設置する。工程(e)では、地下躯体が地下壁に作用する土水圧を支持できることを確認してから圧気を終了する。
【0016】
工程(a)と工程(b)の間には、既存地下躯体の内部を解体する工程(f)をさらに設けてもよい。この場合、工程(d)で、既存地下躯体内部にも新規地下躯体を構築する。工程(d)と工程(e)の間には、浮力で躯体が浮き上がるのを防ぐために、地下躯体の下方に地盤アンカまたは引抜杭を設置する工程(g)をさらに設けてもよい。この場合、工程(e)の後、必要に応じて、既存躯体の地上部分を解体し、新規地上躯体を構築する工程(h)を実施する。
【0017】
工程(g)を実施しない場合、代わりの浮力対応策として、新規躯体の構築に重量コンクリートを用いて建物重量の増加を図る。または、工程(h)で、浮力と建物荷重のバランスを考慮して、既存地上躯体の解体と新規地上躯体の構築を並行して行う。
【0018】
工程(b)および工程(c)は、既存地下躯体の底盤の一部を解体して行われる。この際、既存地下躯体内の圧気圧を変化させ、工程(b)では地下水位が底盤より高くならないように、工程(c)では山留め壁内の掘削をドライワークで行えるように、地下水位を制御する。
【0019】
工程(c)、工程(d)における地下水位の制御方法は、地下水の移動が難しい難透水性地盤の有無により異なる。工程(b)で造成された山留め壁の範囲内にない場合は、圧気圧の変化による方法が効果的である。難透水性地盤が山留め壁先端までの間に存在する場合は、井戸を設けて、掘削に影響する領域内の地下水を揚水する方法が効果的である。
【0020】
第2の発明では、既存躯体を用いて新規躯体を構築する際に、既存地下躯体内の空間を密閉して圧気する。このとき、既存地下躯体内の空間の圧気圧で、地下外壁、地下底盤に作用する土水圧に抵抗する。また、既存地下躯体に作用する浮力には、既存地上躯体を含む既存躯体の重量で抵抗する。次に、既存地下躯体の下方に山留め壁を造成し、既存地下躯体の底盤を解体し、山留め壁の内部を掘削して山留め壁の内部に新規地下躯体を構築する。このとき、既存地下躯体の下方に山留め壁を造成し、山留め壁の内部の地下水位を低下させることで、既存地下躯体の底盤以深においてもドライ条件を確保する。そして、既存地下躯体内の空間の圧気を終了する。
【0021】
第3の発明は、第1の発明の躯体構築方法または第2の発明の躯体構築方法を用いて構築された躯体である。
【0022】
【発明の実施の形態】
以下、図面に基づいて、本発明の第1の実施の形態について詳細に説明する。図1は、既存の躯体Aの断面図である。図1に示すように、躯体Aは、地盤5内に構築された地下躯体1と、地下躯体1上に構築された地上躯体3から成る。地下躯体1は、最低階の床である底盤13、その他の地下階の床15、地下内壁11、地下外壁23等で構成される。地下水位7は、地下躯体1の底盤13より高い位置にある。
【0023】
既存の地下躯体1を用いて新規躯体を構築するには、まず、図1に示すように、既存の地下躯体1の圧力バランス階を1階として、1階床17に床増厚補強9などの耐圧補強を施す。後述するように、1階床17には、底盤13の設計浮力相当の圧力が上向きに作用することになるため、床増厚補強9は、この圧力に抵抗できるように行う。図1では、1階床17の上部のみを補強したが、1階床17の上・下位置で補強を行ってもよい。
【0024】
図2は、圧力調整空間19を設置した既存の躯体Aの断面図である。床増厚補強9を行った後、エレベータシャフト等を利用して、地下躯体1から地上躯体3に通じる圧力調整空間19を確保する。圧力調整空間19は、例えば、作業員の出入りのための圧力調整空間19aと、資機材・材料・廃材・掘削土搬出入のための圧力調整空間19bから成る。
【0025】
圧力調整空間19を確保した後、地下躯体1内の既存地下空間6を密閉し、既存地下空間6内を加圧(圧気)する。既存地下空間6の圧気圧は、地下の底盤13に作用する水圧や地下外壁23に作用する土水圧から決定する。地下外壁23には、既存地下空間6内の圧気圧と地下外壁にかかる土水圧との差圧が、地下躯体1の内側から外向きに作用する。
【0026】
図3は、地下躯体1の一部を解体した既存の躯体Aの断面図である。図2に示す加圧された既存地下空間6内で、図3に示すように、既存の地下躯体23の一部を解体する。既存の地下躯体23の一部とは、地盤5に接する底盤13と地下外壁23を除く、地下内壁11や床15等の全部または一部である。地下内壁11や床15等を解体しても、既存地下空間6内の圧気圧で地下外壁23に作用する土水圧に抵抗できるため、仮設支保工は不要である。
【0027】
そして、新設の地下躯体26(図4)の造成に必要な既存地下空間6aを確保する。既存地下空間6a内の空気は、地下の底盤13位置に作用する水圧に相当する圧力で加圧され、これにより、地上と地下の境界階である1階床17に底盤13の設計浮力相当の圧力が上向きに作用する。
【0028】
次に、確保された既存地下空間6a内で、底盤13に地盤アンカ21を造成する。地下底盤13位置に作用する浮力には、既存躯体Aの重量で抵抗するが、地盤アンカ21は、地上躯体3の解体時に浮力により躯体Aが浮き上がるのを防ぐためのものである。
【0029】
図4は、新設の地下躯体26を造成した躯体Aの断面図である。図3に示すように地盤アンカ21を造成した後、既存地下空間6a内に新規の地下躯体26を造成する。そして、新規の地下躯体26が地下外壁23に作用する土圧を支持できることを確認して、既存地下空間6aの圧気を終了する。新規の地下躯体26は、地下内壁25、床27等から成る。
【0030】
図5は、圧力調整空間19と既設の地上躯体3を撤去した躯体Aの断面図である。既存地下空間6aの圧気を終了した後、図5に示すように、圧力調整空間19等の仮設資機材を撤去する。そして、既存の地上躯体3を解体する。
【0031】
図6は、新規の地上躯体29を構築した躯体Aの断面図である。図6に示すように、既存の地上躯体3に加えて1階床17の床増厚補強9も解体し、地下躯体1の上部に新規の地上躯体29を構築し、躯体Aを完成させる。
【0032】
このように、第1の実施の形態では、既存の地上躯体3を解体せずに、既存の地下躯体1の一部を解体して新規の地下躯体26を構築する。そのため、既存の地下躯体1に大きな浮力が作用している場合でも、浮力に対して既存の躯体Aの重量をそのまま利用でき、必要に応じて地盤アンカ21等の浮力対応策を施すだけで、特別な対応が不要となる。
【0033】
また、既存の地下外壁23に作用する土水圧には既存地下空間6内の圧気圧で抵抗できるため、土水圧抵抗部材であった床15や梁などの水平部材を、仮設支保工なしで解体できる。水平部材が解体された既存地下空間6aは、大空間が確保され、容易に新規の地下躯体26を構築できる。
【0034】
さらに、地下外壁23や底盤13は解体せずに再利用するため、既存の地下躯体1を有効利用でき、建設廃棄物の発生量が減少する。そして、従来の構築方法に比べて、工期、コストを大幅に削減できる。
【0035】
なお、第1の実施の形態では、地下部分が2層の躯体Aを用いて説明したが、地下の階数はこれに限らない。図1では、圧力バランス階である1階床17に床増厚補強9を行ったが、仮設桁補強により耐圧補強を行ってもよい。図2では、既存地下空間6全体を加圧空間としているが、地下躯体1の立ち上がり部については、外周の限られた領域の空間のみを加圧空間としてもよい。
【0036】
また、図3では、浮力対応策として地盤アンカ21を造成したが、これは必要に応じて行う。地盤アンカ21を造成するかわりに、引抜杭を造成する、重量コンクリートを用いて建物重量を増加させる、浮力と建物荷重のバランスを考慮して既存の地上躯体3の解体と新規の地上躯体29の構築を同時に行う等の方法を浮力対応策としてもよい。
【0037】
次に、第2の実施の形態について説明する。第2の実施の形態の新規躯体の構築方法では、既存の地下躯体の一部の解体までは、第1の実施の形態と同様の手順で行う。すなわち、図1に示す既存の躯体Bの地下躯体1の圧力バランス階を1階として、1階床17に床増厚補強9などの耐圧補強を施し、図2に示すように地下躯体1から地上躯体3に通じる圧力調整空間19を確保した後、地下躯体1内の既存地下空間6を密閉し、を地下の底盤13に作用する水圧や地下外壁23に作用する土水圧から決定される圧力に既存地下空間6内を加圧(圧気)する。
【0038】
図7は、地下躯体1の一部を解体した既存の躯体Bの断面図である。図2に示す加圧された既存地下空間6内で、図7に示すように、既存の地下躯体23の一部を解体する。地下躯体23の一部とは、第1の実施の形態と同様に、底盤13と地下外壁23を除く地下内壁11や床15等である。これらの解体の際、既存地下空間6内の圧気圧で地下外壁23に作用する土水圧に抵抗できるため、仮設支保工は不要である。
【0039】
そして、新規の地下躯体等の造成に必要な既存地下空間6bを確保する。既存地下空間6b内の空気は、地下の底盤13位置の圧力で加圧され、これにより、地上と地下の境界階である1階床17に底盤13位置での設計浮力相当の圧力が上向きに作用する。
【0040】
次に、新規躯体の地下壁41(図9)の計画位置の外側位置に溝31を掘削し、新規山留め壁33を造成する。新規山留め壁33を造成するため、図7に示すように、既存の地下躯体1の底盤13の一部が解体されるが、溝31の掘削時には、地下水位35が底盤13の上面以浅にならないよう、既存地下空間6b内の空気を増圧する。
【0041】
図8は、地下躯体構築空間37が確保された躯体Bの断面図である。新規山留め壁33の造成が終了した後、図8に示すように、既存の底盤13のうち、新規山留め壁33の内側の部分を解体する。そして、新規山留め壁33の内側の地下水位34が掘削面36以浅にならないよう、既存地下空間6b内の圧気圧を制御しつつ、新規山留め壁33の内側の掘削をドライワークで行い、地下躯体構築空間37を確保する。
【0042】
新規山留め壁33の上部部分、すなわち、新規地下躯体39(図9)と既存地下躯体13とにはさまれる部分である新規山留め壁32は、新規地下躯体39と既存地下躯体13を接合できるようにしている。
【0043】
図9は、新規の地下躯体39を構築した躯体Bの断面図を示す。新規山留め壁33の内側を掘削した後、地下躯体構築空間37内に、新規の地下躯体39を造成する。新規の地下躯体39は、底盤45、地下外壁41等から成る。新規の地下躯体39の底盤45には、地盤アンカ43が造成される。地盤アンカ43は、地上躯体3の解体時に浮力により躯体Bが浮き上がるのを防ぐためのものである。また、既設の地下躯体1の既存地下空間6b内に、新規の地下躯体26を造成する。
【0044】
そして、新規の地下躯体39、地下躯体26が、それぞれ地下外壁41、地下外壁23に作用する土圧を支持できることを確認して、既存地下空間6b、地下躯体構築空間37の圧気を終了する。
【0045】
図10は、圧力調整空間19を撤去し、新規の地上躯体29を構築した躯体Bの断面図である。既存地下空間6bの圧気を終了した後、図10に示すように、圧力調整空間19等の仮設資機材を撤去する。そして、既存の地上躯体3、1階床17の床増厚補強9を解体し、地下躯体1の上部に新規の地上躯体29を構築して、躯体Bを完成させる。
【0046】
このように、第2の実施の形態では、既存の地上躯体3を解体せずに、既存の地下躯体1の一部を解体し、地下躯体1の下方に新規山留め壁33を造成して、新規の地下躯体26、地下躯体39を構築する。そのため、既存の地下躯体1に大きな浮力が作用している場合でも、浮力に対して既存の躯体Bの重量をそのまま利用でき、必要に応じて地盤アンカ43等の浮力対応策を施すだけで、特別な対応が不要となる。
【0047】
また、既存の地下外壁23に作用する土水圧には、既存地下空間6内の圧気圧で抵抗できるため、仮設支保工なしで土水圧抵抗部材であった床や梁などの水平部材の解体ができる。水平部材が解体された既存地下空間6bは、大空間が確保され、新規の地下躯体26、新規山留め壁33、地下躯体39等を容易に構築できる。
【0048】
さらに、地下外壁23や底盤13の一部は解体せずに再利用するため、既存の地下躯体1を有効利用でき、建設廃棄物の発生量が減少する。そして、従来の構築方法に比べて、工期、コストを大幅に削減できる。
【0049】
第2の実施の形態では、地下水圧に既存地下空間6bの内部気圧を対抗させるので、既存の地下底盤13よりも深い位置に計画された新規の地下躯体39の構築に必要な新規山留め壁33を、ドライな既存地下空間6bを用いて造成できる。
【0050】
また、新規山留め壁33を既存の底盤13の下方に造成し、新規山留め壁33の内部の地下水位34を低下させることにより、既存の底盤13を解体しても、ドライワークで新規の地下躯体39を造成することができる。このとき、地下水位34を地下躯体構築空間37内部の圧気圧や揚水により制御するので、新規山留め壁33の規模は小規模でよい。
【0051】
なお、第2の実施の形態では、地下部分が2層の躯体Bの下方にさらに2層の地下躯体39を形成する例について説明したが、地下の階数はこれに限らない。図1では、圧力バランス階である1階床17に床増厚補強9を行ったが、仮設桁補強により耐圧補強を行ってもよい。図2では、既存地下空間6全体を加圧空間としているが、地下躯体1の立ち上がり部については、外周の限られた領域の空間のみを加圧空間としてもよい。
【0052】
また、図9では、浮力対応策として地盤アンカ43を造成したが、これは必要に応じて行う。地盤アンカ43を設置するかわりに、引抜杭を造成する、重量コンクリートを用いて建物重量を増加させる、浮力と建物荷重のバランスを考慮して既存の地上躯体3の解体と新規の地上躯体29構築を同時に行う等の方法を浮力対応策としてもよい。
【0053】
さらに、図7、図8についての説明では、既存地下空間6bや地下躯体構築空間37の圧気圧を増圧することで地下水位35、地下水位34を制御したが、溝31や新規山留め壁33の内部の地下水を揚水することで水位を制御し、掘削範囲のドライ条件を確保してもよい。
【0054】
【発明の効果】
以上、詳細に説明したように、本発明によれば、敷地内に残存する既存の地下躯体を有効利用し、短期間で経済的に新規構造物を構築できる躯体構築方法および躯体を提供できる。
【図面の簡単な説明】
【図1】既存の躯体Aの断面図
【図2】圧力調整空間19を設置した既存の躯体Aの断面図
【図3】地下躯体1の一部を解体した既存の躯体Aの断面図
【図4】新設の地下躯体26を造成した躯体Aの断面図
【図5】圧力調整空間19と既設の地上躯体3を撤去した躯体Aの断面図
【図6】新規の地上躯体29を構築した躯体Aの断面図
【図7】地下躯体1の一部を解体した既存の躯体Bの断面図
【図8】地下躯体構築空間37が確保された躯体Bの断面図
【図9】新規の地下躯体39を構築した躯体Bの断面図
【図10】圧力調整空間19を撤去し、新規の地上躯体29を構築した躯体Bの断面図
【符号の説明】
1、26、39………地下躯体
3、29………地上躯体
5………地盤
7、34、35………地下水位
13、45………底盤
19、19a、19b………圧力調整空間
21、43………地盤アンカ
23、41………地下外壁
32、33………新規山留め壁
37………地下躯体構築空間
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a housing construction method and a housing.
[0002]
[Prior art]
Conventionally, when building a building on the site where the existing building remains, the existing building is dismantled in the order of the ground frame and the underground frame, and the site is reclaimed, and a new building is built using the conventional building construction method. . Or, in order to rationalize the construction and effectively use the underground structure, the existing structure is partly dismantled and a new building is constructed by the conventional building construction method.
[0003]
In order to dismantle the underground structure, (1) there is a method of dismantling after constructing a new retaining wall around the existing structure in order to resist the soil water pressure that the underground structure to be dismantled has resisted. In addition, when the existing underground structure is built to fill the entire site, in order to secure a space for constructing a new retaining wall, (2) the existing underground structure that is an obstacle to construction is partially scraped from the ground. After building the retaining wall after clearing the ground, a method of dismantling the remaining existing structures is used.
[0004]
Furthermore, when using the underground structure to be demolished as effectively as possible and resisting soil pressure as it is, (3) dismantling the ground structure and preventing the concrete shell that is generated from lifting due to buoyancy. After filling the interior and building a water-impervious wall around the existing underground enclosure, the groundwater level is lowered by pumping to reduce buoyancy, and the concrete shell in the underground enclosure is carried out to construct a new underground enclosure Is used.
[0005]
When building an underground structure on a site that does not have an existing structure, build a retaining wall at a location that hits the outer wall of the underground structure, excavate the ground inside the retaining wall while pumping water, and then form a seal formed inside the retaining wall. There is a method in which a space is pressurized and a structure is constructed using a sealed space (see, for example, Patent Document 1).
[0006]
[Patent Document 1]
Japanese Patent Laid-Open No. 11-6164
[Problems to be solved by the invention]
However, in the method (1), the construction cost increases because a new retaining wall is constructed. In the method (2), since the process becomes more complicated than the method (1), the construction cost becomes higher and the construction period becomes longer. The method of (3) is a method of constructing a new structure by disassembling an existing underground structure by constructing a new structure by resisting the existing underground structure to soil water pressure. ), The construction cost is higher and the construction period is longer, which does not lead to effective use of the existing frame.
[0008]
The present invention has been made in view of such problems, and the object of the present invention is to effectively utilize an existing underground structure remaining in the site and to construct a new structure economically in a short period of time. It is to provide a construction method and a housing.
[0009]
[Means for Solving the Problems]
A first invention for achieving the above-described object is a method of constructing a new chassis using an existing chassis, the step (a) of sealing and compressing a space in the existing underground chassis, and the existing underground A step (b) of dismantling the interior of the enclosure, a step (c) of constructing a new underground enclosure in the existing underground enclosure, and a step (d) of ending the pressure in the space in the existing underground enclosure It is the housing construction method characterized by this.
[0010]
In the step (a), the pressure balance floor of the existing underground enclosure is pressure-proof reinforced, and a predetermined portion in the existing underground enclosure is sealed and pressurized. The pressure and pressure are determined from the water pressure acting on the underground floor and the earth water pressure acting on the underground wall. A pressure adjustment space will be installed in the existing underground enclosure as needed. In the step (d), after confirming that the new underground frame can support the earth pressure acting on the underground wall, the pressurized air is finished.
[0011]
Between step (b) and step (d), in order to prevent the case from being lifted by buoyancy after dismantling of the existing case, a step (e) is further provided in which a ground anchor or a drawn pile is installed below the underground case. Also good. In this case, after the step (d), if necessary, a step (f) of dismantling the ground portion of the existing housing and constructing a new ground housing is performed.
[0012]
When the step (e) is not performed, the weight of the building is increased by using heavy concrete for the construction of a new frame as an alternative buoyancy countermeasure. Alternatively, in the step (f), considering the balance between buoyancy and building load, the dismantling of the existing ground frame and the construction of the new ground frame are performed in parallel.
[0013]
In 1st invention, when constructing | assembling a new housing using an existing housing, first, the space in an existing underground housing is sealed and pressurized, and the inside of the existing underground housing is disassembled. At this time, the pressure and pressure of the space in the existing underground enclosure resists the soil pressure acting on the underground outer wall and the underground floor. Also, the buoyancy acting on the existing underground frame is resisted by the weight of the existing frame including the existing ground frame. Next, a new underground structure is constructed in the existing underground structure secured by the dismantling of the structural members, and the pressure in the space in the existing underground structure is terminated.
[0014]
The second invention is a method for constructing a new frame using an existing frame, the step (a) of sealing and compressing the space in the existing underground frame, and forming a retaining wall below the existing underground frame Step (b), dismantling the bottom plate of the existing underground structure, excavating the interior of the retaining wall, constructing a new underground structure in the interior of the retaining wall (d), A method for constructing a housing, comprising: an existing underground housing and a step (e) of ending pressure in a space in the new underground housing.
[0015]
In the step (a), the pressure balance floor of the existing underground enclosure is pressure-proof reinforced, and a predetermined portion in the existing underground enclosure is sealed and pressurized. The pressure and pressure are determined from the water pressure acting on the underground floor and the earth water pressure acting on the underground wall. A pressure adjustment space will be installed in the existing underground enclosure as needed. In the step (e), after confirming that the underground frame can support the earth and water pressure acting on the underground wall, the pressurized air is finished.
[0016]
Between the step (a) and the step (b), a step (f) for dismantling the inside of the existing underground frame may be further provided. In this case, in the step (d), a new underground structure is constructed inside the existing underground structure. Between the step (d) and the step (e), a step (g) of installing a ground anchor or a drawn pile below the underground frame may be further provided in order to prevent the frame from being lifted by buoyancy. In this case, after the step (e), the step (h) of disassembling the ground portion of the existing housing and constructing a new ground housing is performed as necessary.
[0017]
When step (g) is not performed, as an alternative countermeasure for buoyancy, heavy concrete is used to construct a new frame to increase the building weight. Alternatively, in the step (h), considering the balance between buoyancy and building load, the dismantling of the existing ground frame and the construction of the new ground frame are performed in parallel.
[0018]
Step (b) and step (c) are performed by disassembling a part of the bottom plate of the existing underground structure. At this time, the pressure and pressure in the existing underground enclosure are changed, and in step (b), the groundwater level is set so that excavation in the retaining wall can be performed by dry work in step (c) so that the groundwater level does not become higher than the bottom plate. Control.
[0019]
The control method of the groundwater level in the step (c) and the step (d) differs depending on the presence or absence of a hardly permeable ground where movement of the groundwater is difficult. In the case where it is not within the range of the retaining wall created in the step (b), a method based on a change in pressure and pressure is effective. In the case where the hardly permeable ground exists between the tip of the retaining wall, a method of providing a well and pumping up groundwater in an area that affects excavation is effective.
[0020]
In 2nd invention, when building a new housing using an existing housing, the space in the existing underground housing is sealed and pressurized. At this time, the pressure and pressure of the space in the existing underground enclosure resists the soil pressure acting on the underground outer wall and the underground floor. Also, the buoyancy acting on the existing underground frame is resisted by the weight of the existing frame including the existing ground frame. Next, a retaining wall is created below the existing underground structure, the bottom of the existing underground structure is dismantled, and the interior of the retaining wall is excavated to construct a new underground structure. At this time, a mountain retaining wall is formed below the existing underground frame, and the groundwater level inside the mountain retaining wall is lowered to ensure dry conditions even deeper than the bottom of the existing underground frame. And the pressure of the space in the existing underground enclosure is terminated.
[0021]
A third invention is a chassis constructed using the chassis construction method of the first invention or the chassis construction method of the second invention.
[0022]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a first embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a cross-sectional view of an existing housing A. FIG. As shown in FIG. 1, the frame A is composed of an underground frame 1 built in the ground 5 and an above-ground frame 3 built on the underground frame 1. The underground frame 1 is composed of a floor 13 which is the floor of the lowest floor, a floor 15 of the other underground floor, an underground inner wall 11, an underground outer wall 23, and the like. The groundwater level 7 is at a position higher than the bottom 13 of the underground frame 1.
[0023]
In order to construct a new structure using the existing underground structure 1, first, as shown in FIG. 1, the pressure balance floor of the existing underground structure 1 is set as the first floor, and the floor thickening reinforcement 9 is provided on the first floor 17. Apply pressure-proof reinforcement. As will be described later, since the pressure equivalent to the design buoyancy of the bottom board 13 acts upward on the first floor 17, the floor thickening reinforcement 9 is performed so as to resist this pressure. In FIG. 1, only the upper part of the first floor 17 is reinforced, but reinforcement may be performed at the upper and lower positions of the first floor 17.
[0024]
FIG. 2 is a cross-sectional view of an existing case A in which the pressure adjustment space 19 is installed. After the floor thickening reinforcement 9 is performed, a pressure adjustment space 19 that leads from the underground skeleton 1 to the ground skeleton 3 is secured using an elevator shaft or the like. The pressure adjustment space 19 includes, for example, a pressure adjustment space 19a for entering / exiting workers and a pressure adjustment space 19b for carrying in / out materials / materials / waste materials / excavated soil.
[0025]
After securing the pressure adjustment space 19, the existing underground space 6 in the underground enclosure 1 is sealed, and the existing underground space 6 is pressurized (pressured). The pressure and pressure in the existing underground space 6 is determined from the water pressure acting on the underground floor 13 and the soil water pressure acting on the underground outer wall 23. On the underground outer wall 23, a differential pressure between the pressure and pressure in the existing underground space 6 and the earth and water pressure applied to the underground outer wall acts outward from the underground frame 1.
[0026]
FIG. 3 is a cross-sectional view of an existing case A in which a part of the underground case 1 is dismantled. In the pressurized existing underground space 6 shown in FIG. 2, as shown in FIG. 3, a part of the existing underground enclosure 23 is dismantled. The part of the existing underground skeleton 23 is all or a part of the underground inner wall 11, the floor 15, etc., excluding the bottom 13 and the underground outer wall 23 in contact with the ground 5. Even if the underground inner wall 11, the floor 15, etc. are disassembled, temporary support work is unnecessary because the pressure and pressure in the existing underground space 6 can resist the earth and water pressure acting on the underground outer wall 23.
[0027]
And the existing underground space 6a required for creation of the newly installed underground frame 26 (FIG. 4) is ensured. The air in the existing underground space 6a is pressurized with a pressure corresponding to the water pressure acting on the position of the base 13 in the basement, and thus, the first floor 17 which is a boundary floor between the ground and the basement is equivalent to the design buoyancy of the base 13. Pressure acts upward.
[0028]
Next, the ground anchor 21 is created in the bottom board 13 within the secured existing underground space 6a. The buoyancy acting on the position of the underground floor 13 is resisted by the weight of the existing chassis A, but the ground anchor 21 is for preventing the chassis A from being lifted by buoyancy when the ground chassis 3 is disassembled.
[0029]
FIG. 4 is a cross-sectional view of a case A in which a newly installed underground case 26 is created. After the ground anchor 21 is created as shown in FIG. 3, a new underground frame 26 is created in the existing underground space 6a. And it confirms that the new underground frame 26 can support the earth pressure which acts on the underground outer wall 23, and the pressure air of the existing underground space 6a is complete | finished. The new underground structure 26 includes an underground inner wall 25, a floor 27, and the like.
[0030]
FIG. 5 is a cross-sectional view of the housing A from which the pressure adjusting space 19 and the existing ground housing 3 are removed. After the pressure in the existing underground space 6a is finished, the temporary equipment such as the pressure adjustment space 19 is removed as shown in FIG. Then, the existing ground frame 3 is dismantled.
[0031]
FIG. 6 is a cross-sectional view of the chassis A in which a new ground chassis 29 is constructed. As shown in FIG. 6, in addition to the existing ground frame 3, the floor thickening reinforcement 9 of the first floor 17 is also dismantled, and a new ground frame 29 is constructed above the underground frame 1 to complete the frame A.
[0032]
Thus, in the first embodiment, a new underground structure 26 is constructed by disassembling a part of the existing underground structure 1 without disassembling the existing ground structure 3. Therefore, even when a large buoyancy is acting on the existing underground skeleton 1, the weight of the existing skeleton A can be used as it is for the buoyancy, and if necessary, just apply countermeasures such as the ground anchor 21 No special action is required.
[0033]
Further, since the earth and water pressure acting on the existing underground outer wall 23 can be resisted by the pressure and pressure in the existing underground space 6, the horizontal members such as the floor 15 and the beams, which were earth and water resistance members, are dismantled without temporary support work. it can. A large space is secured in the existing underground space 6a where the horizontal member is disassembled, and a new underground structure 26 can be easily constructed.
[0034]
Furthermore, since the underground outer wall 23 and the base 13 are reused without being dismantled, the existing underground enclosure 1 can be used effectively, and the amount of construction waste generated is reduced. And, compared with the conventional construction method, the construction period and cost can be greatly reduced.
[0035]
In the first embodiment, the underground part has been described using the two-layered housing A, but the number of underground floors is not limited to this. In FIG. 1, the floor thickening reinforcement 9 is performed on the first floor 17 which is a pressure balance floor, but pressure-resistant reinforcement may be performed by temporary girder reinforcement. In FIG. 2, the entire existing underground space 6 is a pressurized space, but only the space in a limited area on the outer periphery may be used as the pressurized space for the rising portion of the underground housing 1.
[0036]
Moreover, in FIG. 3, although the ground anchor 21 was created as a countermeasure for buoyancy, this is performed as necessary. Instead of creating the ground anchor 21, create a pull-out pile, increase the building weight using heavy concrete, dismantle the existing ground structure 3 and the new ground structure 29 in consideration of the balance between buoyancy and building load A method such as simultaneous construction may be used as a countermeasure for buoyancy.
[0037]
Next, a second embodiment will be described. In the method for constructing a new skeleton in the second embodiment, a part of the existing underground skeleton is disassembled in the same procedure as in the first embodiment. That is, the pressure balance floor of the underground housing 1 of the existing housing B shown in FIG. 1 is set as the first floor, and pressure-proof reinforcement such as the floor thickening reinforcement 9 is applied to the first floor 17, and as shown in FIG. After securing the pressure adjustment space 19 leading to the ground frame 3, the existing underground space 6 in the underground frame 1 is sealed, and the pressure determined from the water pressure acting on the underground bottom 13 and the earth water pressure acting on the underground outer wall 23 The existing underground space 6 is pressurized (pressured).
[0038]
FIG. 7 is a cross-sectional view of an existing frame B in which a part of the underground frame 1 is dismantled. In the pressurized existing underground space 6 shown in FIG. 2, as shown in FIG. 7, a part of the existing underground enclosure 23 is dismantled. A part of the underground skeleton 23 is the underground inner wall 11 and the floor 15 other than the bottom plate 13 and the underground outer wall 23 as in the first embodiment. During these dismantling, it is possible to resist the earth and water pressure acting on the underground outer wall 23 by the pressure and pressure in the existing underground space 6, so that temporary support work is unnecessary.
[0039]
And the existing underground space 6b required for creation of a new underground frame etc. is ensured. The air in the existing underground space 6b is pressurized by the pressure at the position of the bottom base 13 so that the pressure equivalent to the design buoyancy at the position of the bottom 13 is upward on the first floor 17 which is the boundary floor between the ground and the basement. Works.
[0040]
Next, a groove 31 is excavated at a position outside the planned position of the underground wall 41 (FIG. 9) of the new frame, and a new retaining wall 33 is created. In order to create the new retaining wall 33, as shown in FIG. 7, a part of the bottom base 13 of the existing underground skeleton 1 is dismantled. The air in the existing underground space 6b is increased.
[0041]
FIG. 8 is a cross-sectional view of the frame B in which the underground frame construction space 37 is secured. After the creation of the new retaining wall 33 is completed, as shown in FIG. 8, the part inside the new retaining wall 33 of the existing bottom board 13 is disassembled. Then, the inside of the new retaining wall 33 is excavated by dry work while controlling the pressure and pressure in the existing underground space 6b so that the groundwater level 34 inside the new retaining wall 33 is not shallower than the excavation surface 36, and the underground frame A construction space 37 is secured.
[0042]
The upper part of the new retaining wall 33, that is, the new retaining wall 32, which is a portion sandwiched between the new underground structure 39 (FIG. 9) and the existing underground structure 13, can join the new underground structure 39 and the existing underground structure 13. I have to.
[0043]
FIG. 9 shows a cross-sectional view of a frame B in which a new underground frame 39 is constructed. After excavating the inside of the new retaining wall 33, a new underground structure 39 is created in the underground structure building space 37. The new underground skeleton 39 includes a bottom board 45, an underground outer wall 41, and the like. A ground anchor 43 is formed on the bottom 45 of the new underground structure 39. The ground anchor 43 is for preventing the chassis B from being lifted by buoyancy when the ground chassis 3 is disassembled. In addition, a new underground structure 26 is created in the existing underground space 6 b of the existing underground structure 1.
[0044]
And it confirms that the new underground skeleton 39 and the underground skeleton 26 can support the earth pressure which acts on the underground outer wall 41 and the underground outer wall 23, respectively, and the pressure of the existing underground space 6b and the underground skeleton construction space 37 is complete | finished.
[0045]
FIG. 10 is a cross-sectional view of the chassis B in which the pressure control space 19 is removed and a new ground chassis 29 is constructed. After the pressure in the existing underground space 6b is finished, the temporary equipment such as the pressure adjustment space 19 is removed as shown in FIG. And the floor thickening reinforcement 9 of the existing ground frame 3 and the 1st floor 17 is disassembled, and a new ground frame 29 is constructed on the upper part of the underground frame 1 to complete the frame B.
[0046]
As described above, in the second embodiment, without dismantling the existing ground frame 3, a part of the existing underground frame 1 is disassembled, and a new retaining wall 33 is formed below the underground frame 1, A new underground structure 26 and underground structure 39 are constructed. Therefore, even if a large buoyancy is acting on the existing underground skeleton 1, the weight of the existing skeleton B can be used as it is for the buoyancy, and if necessary, just apply buoyancy countermeasures such as the ground anchor 43, No special action is required.
[0047]
In addition, since the soil water pressure acting on the existing underground outer wall 23 can be resisted by the pressure and pressure in the existing underground space 6, horizontal members such as floors and beams, which were soil water resistance members, can be disassembled without temporary support. . A large space is secured in the existing underground space 6b where the horizontal members are disassembled, and a new underground structure 26, a new retaining wall 33, an underground structure 39, and the like can be easily constructed.
[0048]
Furthermore, since a part of the underground outer wall 23 and the bottom base 13 is reused without being dismantled, the existing underground enclosure 1 can be used effectively, and the amount of construction waste generated is reduced. And, compared with the conventional construction method, the construction period and cost can be greatly reduced.
[0049]
In the second embodiment, since the internal air pressure of the existing underground space 6b is opposed to the underground water pressure, the new retaining wall 33 necessary for the construction of the new underground frame 39 planned deeper than the existing underground floor 13 is provided. Can be created using the existing dry underground space 6b.
[0050]
Moreover, even if the existing bottom plate 13 is disassembled by creating a new mountain retaining wall 33 below the existing bottom plate 13 and lowering the groundwater level 34 inside the new mountain retaining wall 33, a new underground frame is obtained by dry work. 39 can be created. At this time, since the groundwater level 34 is controlled by the pressure and pressure inside the underground building construction space 37, the scale of the new retaining wall 33 may be small.
[0051]
In addition, although 2nd Embodiment demonstrated the example in which the underground part forms the two-layered underground skeleton 39 under the two-layered skeleton B, the number of underground floors is not restricted to this. In FIG. 1, the floor thickening reinforcement 9 is performed on the first floor 17 which is a pressure balance floor, but pressure-resistant reinforcement may be performed by temporary girder reinforcement. In FIG. 2, the entire existing underground space 6 is a pressurized space, but only the space in a limited area on the outer periphery may be used as the pressurized space for the rising portion of the underground housing 1.
[0052]
Moreover, in FIG. 9, although the ground anchor 43 was created as a buoyancy countermeasure, this is performed as needed. Instead of installing the ground anchor 43, create a pull-out pile, increase the building weight using heavy concrete, dismantle the existing ground frame 3 and build a new ground frame 29 in consideration of the balance between buoyancy and building load It is good also as a buoyancy countermeasure.
[0053]
Further, in the description of FIGS. 7 and 8, the groundwater level 35 and the groundwater level 34 are controlled by increasing the pressure and pressure of the existing underground space 6 b and the underground frame construction space 37. The water level may be controlled by pumping up internal groundwater to ensure dry conditions in the excavation range.
[0054]
【The invention's effect】
As described above in detail, according to the present invention, it is possible to provide a housing construction method and a housing that can effectively use an existing underground housing remaining in a site and can economically construct a new structure in a short period of time.
[Brief description of the drawings]
1 is a cross-sectional view of an existing case A. FIG. 2 is a cross-sectional view of an existing case A in which a pressure adjustment space 19 is installed. FIG. 3 is a cross-sectional view of an existing case A in which a part of an underground case 1 is dismantled. FIG. 4 is a cross-sectional view of the case A in which the newly installed underground case 26 is formed. FIG. 5 is a cross-sectional view of the case A in which the pressure adjusting space 19 and the existing ground case 3 are removed. Cross-sectional view of skeleton A [Fig. 7] Cross-sectional view of existing skeleton B with part of underground skeleton 1 disassembled [Fig. 8] Cross-sectional view of skeleton B in which underground skeleton construction space 37 is secured [Fig. 9] New underground Cross-sectional view of the chassis B constructed of the chassis 39 [FIG. 10] Cross-sectional view of the chassis B constructed by removing the pressure adjusting space 19 and constructing the new ground chassis 29 [Explanation of Symbols]
1, 26, 39 ......... Underground frame 3, 29 ......... Ground frame 5 ......... Ground 7, 34, 35 ......... Ground water level 13, 45 ......... Bottom plate 19, 19a, 19b ......... Pressure adjustment Spaces 21 and 43 ... Ground anchors 23 and 41 ... Basement outer walls 32 and 33 ... New mountain retaining wall 37 ... Basement building construction space

Claims (9)

既存躯体を用いて新規躯体を構築する方法であって、
既存地下躯体内の空間を密閉して圧気する工程(a)と、
前記既存地下躯体の内部を解体する工程(b)と、
前記既存地下躯体内に新規地下躯体を構築する工程(c)と、
前記既存地下躯体内の空間の圧気を終了する工程(d)と、
を具備することを特徴とする躯体構築方法。
A method of constructing a new chassis using an existing chassis,
A process (a) for sealing and sealing the space in the existing underground enclosure;
Dismantling the inside of the existing underground structure (b);
A step (c) of constructing a new underground structure in the existing underground structure;
A step (d) of ending the pressure of the space in the existing underground enclosure;
The housing construction method characterized by comprising.
前記工程(b)と前記工程(d)の間に、前記既存地下躯体に地盤アンカまたは引抜杭を設置する工程(e)をさらに具備することを特徴とする請求項1記載の躯体構築方法。The method according to claim 1, further comprising a step (e) of installing a ground anchor or a drawn pile in the existing underground frame between the step (b) and the step (d). 前記工程(d)の後に、前記既存躯体の既存地上躯体を解体し、新規地上躯体を構築する工程(f)をさらに具備することを特徴とする請求項1記載の躯体構築方法。The housing construction method according to claim 1, further comprising a step (f) of dismantling the existing ground housing of the existing housing and constructing a new ground housing after the step (d). 既存躯体を用いて新規躯体を構築する方法であって、
既存地下躯体内の空間を密閉して圧気する工程(a)と、
前記既存地下躯体の下方に山留め壁を造成する工程(b)と、
前記既存地下躯体の底盤を解体し、前記山留め壁の内部を掘削する工程(c)と、
前記山留め壁の内部に新規地下躯体を構築する工程(d)と、
前記既存地下躯体内と前記新規地下躯体内の空間の圧気を終了する工程(e)と、
を具備することを特徴とする躯体構築方法。
A method of constructing a new chassis using an existing chassis,
A process (a) for sealing and sealing the space in the existing underground enclosure;
A step (b) of creating a retaining wall below the existing underground structure;
Dismantling the bottom of the existing underground structure and excavating the interior of the retaining wall (c);
A step (d) of constructing a new underground frame inside the retaining wall;
A step (e) of ending pressure in the space in the existing underground enclosure and the new underground enclosure;
The housing construction method characterized by comprising.
前記工程(a)と前記工程(b)の間に前記既存地下躯体の内部を解体する工程(f)をさらに具備し、前記工程(d)で前記既存地下躯体内部に新規地下躯体を構築することを特徴とする請求項4記載の躯体構築方法。The method further comprises a step (f) of disassembling the inside of the existing underground structure between the step (a) and the step (b), and constructing a new underground structure inside the existing underground structure in the step (d). The housing construction method according to claim 4. 前記工程(d)と前記工程(e)の間に、前記新規地下躯体に地盤アンカまたは引抜杭を設置する工程(g)をさらに具備することを特徴とする請求項4記載の躯体構築方法。5. The housing construction method according to claim 4, further comprising a step (g) of installing a ground anchor or a drawn pile in the new underground housing between the step (d) and the step (e). 前記工程(e)の後に、前記既存躯体の既存地上躯体を解体し、新規地上躯体を構築する工程(h)をさらに具備することを特徴とする請求項4記載の躯体構築方法。5. The housing construction method according to claim 4, further comprising a step (h) of dismantling the existing ground housing of the existing housing and constructing a new ground housing after the step (e). 前記工程(b)から前記工程(d)は、前記既存地下躯体内の圧気圧を変化させて地下水位を制御しつつ行われることを特徴とする請求項4記載の躯体構築方法。5. The housing construction method according to claim 4, wherein steps (b) to (d) are performed while controlling the groundwater level by changing the pressure and pressure in the existing underground housing. 請求項1から請求項8のいずれかに記載された躯体構築方法を用いて構築されたことを特徴とする躯体。A housing constructed using the housing construction method according to any one of claims 1 to 8.
JP2003037866A 2003-02-17 2003-02-17 Housing construction method and housing Expired - Fee Related JP4064837B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003037866A JP4064837B2 (en) 2003-02-17 2003-02-17 Housing construction method and housing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003037866A JP4064837B2 (en) 2003-02-17 2003-02-17 Housing construction method and housing

Publications (2)

Publication Number Publication Date
JP2004244978A JP2004244978A (en) 2004-09-02
JP4064837B2 true JP4064837B2 (en) 2008-03-19

Family

ID=33022543

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003037866A Expired - Fee Related JP4064837B2 (en) 2003-02-17 2003-02-17 Housing construction method and housing

Country Status (1)

Country Link
JP (1) JP4064837B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6424060B2 (en) * 2014-10-10 2018-11-14 株式会社竹中工務店 How to rebuild a structure
JP6726036B2 (en) * 2016-06-24 2020-07-22 大成建設株式会社 Reconstruction method for existing buildings
CN113089399B (en) * 2021-05-11 2024-10-08 湖南省交通规划勘察设计院有限公司 Underground interchange structure with intensive underground substation
CN113309142A (en) * 2021-06-21 2021-08-27 王书理 Conveying pipeline production device and production method
KR102755330B1 (en) * 2022-11-16 2025-01-21 (주)에스앤피이엔씨 basement floor connection construction method

Also Published As

Publication number Publication date
JP2004244978A (en) 2004-09-02

Similar Documents

Publication Publication Date Title
KR101034398B1 (en) Underground structure construction method that combines underground clogging method
KR101014796B1 (en) Top-down construction method using ready-made concrete pillar member
KR100722665B1 (en) Steel guide wall for underground continuous wall construction and underground continuous wall construction method
CN107035159B (en) A method of suitable for frame structure isolated footing building underground increasing layer
JP5285254B2 (en) Rebuilding method
KR100967497B1 (en) Method for constructing an underground structure
JP6229294B2 (en) Method of rebuilding a structure having an underground structure and underground structure
JP4064837B2 (en) Housing construction method and housing
KR102645823B1 (en) Top-down and bottom-up parallel decommissioning of existing building
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
JP2011246910A (en) Construction method of underground structure
JP3641227B2 (en) Construction method of underground structure
JP2018044339A (en) How to dismantle existing underground structures
JP7565256B2 (en) How to rebuild a building
KR100967496B1 (en) Device for constructing an underground structure
JP6827256B2 (en) How to rebuild the building
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
JP4475116B2 (en) Vertical shaft structure and its construction method
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP4440799B2 (en) Ground excavation method
JP2571426B2 (en) Construction method of retaining wall
JP7762605B2 (en) Reconstruction methods for existing buildings and reconstructed buildings
CN224063498U (en) High tower crane combined foundation structure
JP7398609B2 (en) Concrete frame construction method and underground structure
KR100981061B1 (en) Method for backfill gap of structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051205

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20071212

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071225

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071227

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4064837

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110111

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110111

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140111

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees