Floor panel laying equipment Download PDF

Info

Publication number
JP4122383B2
JP4122383B2 JP236099A JP236099A JP4122383B2 JP 4122383 B2 JP4122383 B2 JP 4122383B2 JP 236099 A JP236099 A JP 236099A JP 236099 A JP236099 A JP 236099A JP 4122383 B2 JP4122383 B2 JP 4122383B2
Authority
JP
Japan
Prior art keywords
floor panel
floor
hangar
carrier
room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP236099A
Other languages
Japanese (ja)
Other versions
JP2000204780A (en
Inventor
久 相馬
純二 小野
為久 山口
清秀 春日井
博 大山
聡 藤田
忍 山崎
浩徳 在田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP236099A priority Critical patent/JP4122383B2/en
Publication of JP2000204780A publication Critical patent/JP2000204780A/en
Application granted granted Critical
Publication of JP4122383B2 publication Critical patent/JP4122383B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Floor Finish (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、任意の用途の室を一時的に他の用途の室に変更するに際して該室の床面を全面的に覆うように設置される床パネルを敷設するための床パネル敷設装置に関する。
【0002】
【従来の技術】
近年、各種のスポーツ競技施設が各地に設けられているが、この種の施設は特定の競技のみを対象とする単機能なものではなく多目的なものであることが望まれる傾向にあり、たとえば屋内プールを主たる用途とする施設を水泳以外の他のスポーツを行なうための体育館や各種イベントを開催するための会場としても使用したいという要請がある。
【0003】
そのような要請に応じるために、プールの底面を昇降可能な可動床としておいてそれをプールサイドのレベルまで上昇させることでプール室内の床全体をフラットにできるようしておき、その上に床板を全面的に敷きつめることで体育館として使用可能な床を形成することが従来より行なわれている。
【0004】
【発明が解決しようとする課題】
しかし、従来における上記のような床敷設作業は多数の作業員による人力に頼って行なうしかなく、したがって床板としては作業員が容易に持ち運びできる程度の軽量かつ小サイズのものを用いるしかない。そのため、従来においては膨大な数の床板が必要となるのみならず、それら床板をそれぞれ段差が生じることがないように、かつ全体としてフラットに敷き並べる必要があるから、そのような作業は必ずしも容易に行なえるものではなく、室内プール全体に床を設ける作業に数日を要してしまうものであった。このことは、室内プールを体育館に変更する場合のみならず、各種用途の室を一時的に他の用途の室に変更する場合全般に共通することであり、有効な改善策が要望されていた。
【0005】
本発明は上記事情に鑑みてなされたもので、任意の用途の室を一時的に他の用途に使用するに際して床敷設作業やその復旧作業を迅速かつ容易に行ない得る有効な手段を提供することを目的とする。
【0009】
【課題を解決するための手段】
請求項1の発明は、任意の用途の室を一時的に他の用途の室に変更するべく、該室の全幅もしくは全長にわたる長さを有する長尺の床パネルを該室の床面上に全面的に敷設するための床パネル敷設装置であって、前記室の内部もしくは該室に面する位置に設けられて前記床パネルを積層状態で多数格納する格納庫と、前記床パネルを搭載して前記室内において前進後退可能に走行することにより該床パネルを前記格納庫と敷設位置との間にわたって搬送するキャリアと、前記格納庫内に格納されている床パネルを前記キャリアに積み込みかつ該キャリアに搭載されている床パネルを格納庫に格納する格納装置とを具備してなり、前記格納庫は前記室の床面より下方に掘り下げられて形成されていて、その上部に前記床パネルを搬出入するための横長スリット状の取出口が設けられ、前記格納装置は、該格納庫内において前記床パネルを把持して昇降するリフタと、前記格納庫内の上部に進退可能に設けられたスライド床を有し、該スライド床は前記格納庫の上部に進出することで前記取出口から前記格納庫内に進入してくる前記キャリアを支持し、かつ、格納庫の後方に退避することで前記リフタの昇降を許容する構成としたことを特徴とする。
【0010】
請求項2の発明は、請求項1の発明の床パネル敷設装置において、前記キャリアは複数の走行台車を所定間隔をおいて横方向に並べて連結することにより前記床パネルの全長にわたる長さとされ、前記走行台車には床パネルを昇降可能に支持するリフト機構を搭載してなるものである。
【0011】
請求項3の発明は、請求項2記載の床パネル敷設装置において、前記リフト機構は起倒自在な揺動アームからなり、該揺動アームを起立させて床パネルを持ち上げた状態から該揺動アームを前方に倒すことで床パネルを前方に移動させつつ降下させる構成としたものである。
【0012】
請求項4の発明は、請求項2または3記載の床パネル敷設装置において、前記リフト機構は前記床パネルを持ち上げた状態で該床パネルをその長さ方向にスライドさせるスライド機構を具備してなるものである。
【0013】
請求項5の発明は、請求項2,3または4記載の床パネル敷設装置において、前記キャリアの少なくとも両端部における位置を検出してその結果に基づき前記各走行台車の速度調整を行う制御手段を具備してなるものである。
【0015】
【発明の実施の形態】
図1〜図3は本発明の実施形態である床パネル敷設装置2を用いて床パネル1をプール室3の床面に敷設することにより、プール室3を体育館に転換している状況を示すものである。本例のプール室3は公式競技用の50mプールが設けられたもので、そのプールの底面は4分割された昇降可能な可動床4とされ、体育館に転換する際にはプールの水を抜いて可動床4をプールサイド5のレベルまで上昇させ、その上に床パネル1を隙間無く敷き並べることができるようになっている。なお、図示は省略しているが、可動床4を昇降させるための液圧シリンダがプールの底部に設けられているとともに、可動床4を上昇させた状態でそれを安定に支持固定して積載荷重を受けるための支柱がプール内に設置されている。
【0016】
床パネル1の詳細を図4〜図7に示す。床パネル1はプール室3の形状と寸法に対応して予め所定の形状、寸法に製作されたもので、本例では全長がプール室3の全幅にわたる長さの40m程度とされ、幅は2m程度とされている。その床パネル1は、たとえばアルミ型材からなる下地フレーム6上にフローリング材等の床板7が取り付けられ、かつ多数の折り込み可能な支持脚8が所定間隔で設けられたものである。
【0017】
それら床パネル1のうちプール室3の最前部に設置される1台の床パネル1aは、図5(a)に示すようにその前後両側部に支持脚8が設けられていてそれ自体で安定に設置されるものであるが、その後方側に順次設置される他の床パネル1は設置済みの床パネル1に対して係合部材15(詳細後述)により係合してその荷重が受けられるようになっており、したがって最前部に設置される上記の床パネル1a以外の床パネル1は図5(b)に示すように支持脚8は後部側にのみ設けられて前部側の支持脚は省略されている。
【0018】
その支持脚8は下地フレーム6の内側に折り込み可能とされていて、床パネル1を格納庫20(詳細後述)に積層状態で格納しておく際やキャリア22(詳細後述)により搬送する際には支持脚8を折り込んでおくことで格納スペースの節約が図られかつ搬送の邪魔になることが回避されている。図6は支持脚8を折り込むための機構の詳細を示すもので、支持脚8の上端部を下地フレーム6に対して軸9により回転可能に連結し、かつストッパ10により支持脚8をロックする構成とされている。ストッパ10はL形の金具であって、その角部が軸11により支持脚8に回転可能に連結され、その両端部のいずれか一方を下地フレーム6に取り付けられている固定板12に対してピン13により連結することで、支持脚8を倒した状態と起こした状態の双方でロックすることができるようになっている。符号14は支持脚8の先端に取り付けられている緩衝ゴムである。なお、各床パネル1がプール室3内に設置された際にその上面が自ずと水平となるように、各支持脚8の高さ寸法はその設置位置に応じて、つまりプールサイド5の床勾配や可動床4のレベルに対応して予め調節できるようになっている。
【0019】
また、各床パネル1には他の床パネル1との連結のための係合部材15が取り付けられている。係合部材15は図5に示すように床パネル1の後部側に設けられた支持部15aと、前部側に設けられた被支持部15bとが対になるもので、既に設置されている前方側の床パネル1の支持部15aに対して新たに設置する後方側の床パネル1の被支持部15bを係合せしめることで、それら床パネル1どうしが自ずと連結されるとともに前方側の床パネル1により後方側の床パネル1の荷重を受けることができるようになっており、これにより上述のように最前部に設置される床パネル1a以外の床パネル1の前部側の支持脚の省略が可能となっているのである。
【0020】
さらに、図7に示すように支持部15aおよび被支持部15bにはいずれも緩衝ゴム16が取り付けられているとともに、それら緩衝ゴム16の双方には対のテーパ面17が形成されており、支持部15aに被支持部15bを係合させたときには双方のテーパ面17が相互に密着して双方の床パネル1どうしが自ずと接近する方向に変位しかつそれらの上面レベルが自ずと合致して、双方の床パネル1の上面が自ずと隙間無くかつ段差なく連続するようになっている。
【0021】
上記のように構成された床パネル1は、プール室3を本来の用途であるプール室として使用しているときには図1に示すようにプール室3内の一端側に設けられている格納庫20内に積み重ねられた状態で格納されており、プール室3を体育館に転換する際にはそこから順次取り出されて前方に搬送されて敷設されるものである。したがって格納庫20における床パネル1の積み重ね順序は、プール室3の最前部に配置される床パネル1aが最上段となり、その手前側に順次設置されるものがその順番どうりに積み重ねられ、最も手前側(格納庫20側)に配置されるものが最下段となる。
【0022】
プール室3から体育館への転換に際して床パネル1を格納庫20から取り出して敷設する作業、および体育館からプール室3への再転換に際して床パネル1を格納庫20に格納する作業の全ては、本実施形態の敷設装置2により機械的かつほぼ自動的に行うものである。敷設装置2は上記の格納庫20とそれに付設されている格納装置21、およびキャリア22からなる。
【0023】
キャリア22は、図1に示すように、全10台の走行台車23を横方向に並べて連結ビーム24により連結することで床パネル1の全長にわたる長さとされたものである。それら10台の走行台車23のうち両側2台および中央部2台が走行駆動源を搭載している駆動走行台車23aであり、他の6台はそれに従動する従動走行台車23bである。駆動走行台車23aは図8に示すように8輪の車輪25を有するシャーシ26に走行用モータ27と動力伝達機構28を搭載してなるものであり、従動走行台車23bは走行用モータ27および動力伝達機構28が省略されている他は駆動走行台車23aと同様に構成されている。
【0024】
上記のキャリア22はプール室3内の両側に設けられている排水用の側溝29をガイドレールとして利用して安定に走行するものとなっている。すなわち、連結ビーム24の両端部は側溝29に対して係合可能とされており、キャリア22を走行させる際には側溝29に取り付けられているグレーチングを取り外してそこに連結ビーム24の先端部を案内可能に係合させ、各駆動走行台車23aの走行用モータ27を同期運転することでキャリア22を側溝29により案内して走行させるようになっている。なお、連結ビーム24の先端部には側溝29に対して係合しつつ転動するガイドローラ等の案内部材を取り付けておくと良い。
【0025】
また、キャリア22の位置や速度、走行方向等を正確かつ厳密に監視して制御しつつ予め設定したプログラムに従って自動運転を行うための適宜の制御システムを設けることが好ましく、たとえばレーザー光を利用する位置制御システムが好適に採用可能である。具体的な一例を挙げれば、キャリア22の少なくとも両端部の2箇所、もしくは両端部に加えて中間部の任意の箇所においてキャリア22の位置をレーザー式距離センサにより刻々と検出し、その結果に基づき4台の駆動走行台車23aの速度調整を適正に行うことにより、キャリア22の走行方向が横方向にずれることを防止し、かつキャリア22全体を常に真っ直ぐな状態に維持するような制御システムが考えられる。
【0026】
そして、それら走行台車23の全てには、床パネル1を昇降可能に支持するリフト機構30が搭載されている。リフト機構30は図8に示すように起倒自在な揺動アーム31とその駆動用モータ32および動力伝達機構33からなり、揺動アーム31を倒した状態で床パネル1を支持し、その状態でキャリア22を走行させるとともに、床パネル1を床面に設置するに際しては揺動アーム31を起立させて床パネル1を持ち上げ、床パネル1の支持脚8を起こした後、揺動アーム31を前方に倒すことで床パネル1を前方に若干移動させつつ降下させる構成となっている。また、図示は省略しているが、リフト機構30には床パネル1を持ち上げた状態でその床パネル1を長さ方向(キャリア22の走行方向と直交する方向)にスライドさせることでその位置調整を行うためのスライド機構が設けられている。そのスライド機構としてはたとえば床パネル1を支持した状態で回転するローラが好適に採用可能である。
【0027】
なお、キャリア22への電源供給は、図1に示すようにプール室3内に仮設的に設置されるケーブル支持レール34により給電ケーブル35を移動可能に吊り支持することで行われる。
【0028】
格納庫20およびそれに付設されている格納装置21について図9を参照して説明する。格納庫20はプール室3の床面より下方に掘り下げられて形成されていて、その上部には床パネル1を搬出入するための横長スリット状の取出口40が床面のレベルにおいて開口している。格納庫20内には床パネル1を積層状態で支持する支持フレーム41が設置され、その支持フレーム41は起倒可能なフック42により床パネル1を5台ずつ支持することで荷重分散を図っている。
【0029】
格納装置21は、格納庫20内において床パネル1を把持して昇降可能なリフタ43と、格納庫20の後方からその上部に進退可能に設けられたスライド床44を有している。リフタ43は昇降用モータ45により駆動され支持フレーム41に案内されて昇降するもので、その下部には床パネル1を両側から把持するフック46とその操作用シリンダ47を有する。スライド床44はモータ48により駆動されて進退し、格納庫20の上部に進出した状態では取出口40から格納庫20内に進入してくるキャリア22の各走行台車23を支持可能であり、かつ格納庫20の後方に退避して受台49上に位置することで格納庫20内におけるリフタ43の昇降を許容する構成としたものである。
【0030】
プール室3を体育館に転換するに際して上記の敷設装置2により床パネル1を敷設するための作業手順を図10を参照して説明する。(a)は作業開始時点の初期状態を示す。この状態では、リフタ43は格納庫20の上部に配置されており、スライド床44は受台49上にある。キャリア22は格納庫20の取出口40の前方に停止して待機しており、そのリフト機構30の揺動アーム31は倒伏状態にある。プールは既に水が抜かれており、可動床4はプールサイド5のレベルまで上昇して固定されている。
【0031】
その状態から(b)に示すようにリフタ43を降下させて最上段の床パネル1(1a)を把持し、(c)に示すようにリフタ43を上昇させたらスライド床44を前進させる。(d)に示すようにキャリア22を取出口40から格納庫20内に進入させてスライド床44上に配置し、リフタ43を降下させて床パネル1をキャリア22上に載置したらフック42を開いて床パネル1をキャリア22に搭載する。リフタ43を上昇させた後、(e)に示すようにキャリア22を待機位置まで前進させ、(f)に示すようにスライド床44を後退させてリフタ43を降下させ、(g)に示すように次の床パネル1をリフタ43により把持する。同時に床パネル1を搭載したキャリア22は前進していってその床パネル1の設置位置において停止し、リフト機構30を操作して揺動アーム31を起立させ、作業員の手作業により支持脚8を起こしてストッパ10によりロックした後、必要に応じてキャリア22を前後方向にわずかに移動させかつ上記スライド機構により床パネル1を長さ方向にスライドさせて設置位置の微調整を行い、揺動アーム31を倒して床パネル1を設置し、キャリア22を後退させて待機位置に戻す。
【0032】
以降は以上の手順を繰り返し、設置済みの床パネル1の後方に順次他の床パネル1を設置して相互に連結していけば良い。また、上記のようにして転換した体育館を再びプール室3に戻す際には上記の手順を逆に行って床パネル1を手前側のものから順次格納庫20に格納していけば良い。なお、作業完了後にはキャリア22をスライド床44上に配置することで格納庫20内に格納しておくことができる。
【0033】
以上で説明した床パネル1は、プール室3の全幅にわたる長さを有する長尺のものであるので、転換作業に際してはわずか30台程度の床パネル1を敷き並べるだけで良く、したがって床パネル1の敷設作業自体は1日もあれば行うことが可能であり、きわめて効率的である。しかも、各床パネル1の支持脚8を折り込み可能としたので、支持脚8を下地フレーム7の内側に折り込んだ状態で格納および搬送を行うことにより格納スペースを節約できるとともに搬送の際に支持脚8が邪魔になることがない。
【0034】
さらに、上記の床パネル1は隣接して設置されるものどうしを連結する係合部材15を有し、その係合部材15は前方側の床パネルにより後方側の床パネルの荷重を受けるべく支持部15aと被支持部15bとにより構成されているので、支持脚8は床パネル1の片側(すなわち支持部15aの下方)にのみ設ければ良く、しかも、それら支持部15aおよび被支持部15bの双方に互いに密着するテーパ面17を有する緩衝ゴム16を設けたので、隣接する床パネル1どうしが自ずと隙間無くかつ段差無く連続することになる。
【0035】
なお、床パネル1はプール室3の全幅にわたる長尺のものであるので、その製作は所定長さのユニットを工場製作して現場に搬入し、それらユニットを現場にて所定台数連結することで床パネル1を完成させることが現実的である。たとえば上記のように床パネル1の全長が40m程度である場合には、10m程度の長さのユニットを工場製作してプール室3に搬入し、そこで4台のユニットを連結して床パネル1を完成させれば良い。その場合、ユニットを連結することなくユニットのままで格納庫20に格納しておき、それを連結しながら敷設することも考えられようが、その場合はユニットの敷設作業やユニットどうしの連結作業に多大の手間を要してしまい、効率的な作業は望めるものではない。したがって、上記実施形態のように床パネル1はあくまでプール室3の全幅にわたる長さのものとして完成させた状態で格納しておき、それを一括して敷設する必要がある。
【0036】
また、本実施形態の敷設装置2は、上記のようなプール室3の全幅にわたるような長尺の床パネル1を積層状態で多数格納する格納庫と、そのような長尺の床パネル1を搭載して前進後退可能に走行するキャリア22と、床パネル1をキャリア22に積み込みかつ格納庫20に格納するための格納装置21とを備えるので、長尺の床パネル1を機械的かつほぼ自動的に搬送して敷設しかつ格納することが可能であり、その作業を効率的かつ短時間で行うことが可能である。
【0037】
特に本実施形態の敷設装置2は、複数の走行台車23を横方向に並べて連結した構成のキャリア22を採用しているので、簡便な構成で長尺の床パネル1を安定に搬送可能であり、各走行台車23には床パネル1を昇降可能に支持するリフト機構30を搭載しているので、そのリフト機構30の操作により床パネル1をキャリア22から床面へ下ろす作業や床面に設置されている床パネル1をキャリア22に積み込む作業を簡便に行い得るし、そのリフト機構30として起倒自在な揺動アーム31を採用し、それを前方に倒すことで床パネル1を前方に移動させつつ降下させる構成としているので、床パネル1の設置に際して係合部材15の支持部15aと被支持部15bとを確実に係合させることができる。しかも、リフト機構30は床パネル1を長さ方向にスライドさせるスライド機構を備えるので、床パネル1の長さ方向の位置の微調整も容易に行い得る。
【0038】
その上、本実施形態の敷設装置2は、格納庫20を床面より下方に掘り下げて形成してその上部に床パネル1を搬出入するための横長スリット状の取出口40を設けるとともに、格納装置21は格納庫20内において床パネル1を把持して昇降させるリフタ43と格納庫20内の上部に進退可能に設けられたスライド床44を有するものであるので、スライド床44とリフタ43とキャリア22との協動により床パネル1の敷設作業と格納作業を効率的かつ確実に実施できるものである。
【0039】
以上で本発明の実施形態を説明したが、本発明は上記実施形態に限定されるものでは勿論なく、プール室以外の任意の用途の室、たとえばスケートリンク等の競技施設、さらにはイベント施設等に対して広く適用できるものである。そして、要は、実質的に室の全幅もしくは全長にわたるような長尺の床パネルを室内やそれに面する位置に設けた格納庫に積層状態で格納しておき、それを順次搬出して順次敷き並べていくように構成すれば良いのであり、その限りにおいて室の用途や規模、平面形状に対応して床パネルの寸法や形態を適宜変更すれば良い。たとえば、上記実施形態では床パネルの全長をプール室の全幅にわたるものとしてそれをプール室の長さ方向に順次敷き並べることとしたが、床パネルを室の全長にわたる長さのものとしてそれを室の幅方向に順次敷き並べることでも勿論良い。また、支持脚や係合部材の構成も種々の変更が可能であるし、用途に応じて床パネル上にリノリウムやカーペット等の床仕上材をさらに敷き込むことは任意である。
【0040】
また、敷設装置の構成も、長尺の床パネルを積層状態で格納する格納庫と、それに付設された格納装置と、床パネルを搬送するキャリアとを具備し、かつ格納庫の上部に床パネルを搬出入するための取出口を設けるとともに、格納庫内において床パネルを把持して昇降させるリフタと、格納庫内の上部に進退可能に設けられたスライド床を有する構成とする限りにおいて、対象室の用途や形態、床パネルの形状、寸法、形態等に応じて適宜の設計的変更を行い得ることは言うまでもない。
【0044】
【発明の効果】
請求項1の発明の床パネル敷設装置は、長尺の床パネルを積層状態で多数格納する格納庫と、その長尺の床パネルを搭載して前記室内において前進後退可能に走行するキャリアと、床パネルをキャリアに積み込みかつ格納庫に格納するための格納装置とを備えるので、長尺の床パネルを機械的かつほぼ自動的に搬送して敷設しかつ格納することが可能であり、その作業を効率的かつ短時間で行うことが可能である。
また、この床パネル敷設装置は、格納庫の上部に床パネルを搬出入するための取出口を設けるとともに、格納庫内において床パネルを把持して昇降させるリフタと、格納庫内の上部に進退可能に設けられたスライド床を有するので、スライド床とリフタとキャリアとの協動により床パネルの敷設作業および格納作業を効率的かつ確実に実施できる。
【0045】
請求項2の発明の床パネル敷設装置は、複数の走行台車を横方向に並べて連結した構成のキャリアを採用しているので、簡便な構成で長尺の床パネルを安定に搬送可能であり、かつ各走行台車には床パネルを昇降可能に支持するリフト機構を搭載しているので、そのリフト機構の操作により床パネルをキャリアから床面へ下ろす作業や床面に設置されている床パネルをキャリアに積み込む作業を簡便に行い得る。
【0046】
請求項3の発明の床パネル敷設装置は、リフト機構として起倒自在な揺動アームを採用し、それを前方に倒すことで床パネルを前方に移動させつつ降下させて床面に設置する構成としているので、床パネルの設置に際して係合部材どうしを確実に係合させることができる。
【0047】
請求項4の発明の床パネル敷設装置は、リフト機構に床パネルを持ち上げた状態で長さ方向にスライドさせるスライド機構を具備しているので、床パネルを設置するに際してその長さ方向の位置決めを容易に行い得る。
【0048】
請求項5の発明の床パネル敷設装置は、キャリアの少なくとも両端部における位置を検出してその結果に基づき各走行台車の速度調整を行う制御手段を具備しているので、キャリアを常に真っ直ぐに維持できかつ走行方向のずれを防止できる。
【図面の簡単な説明】
【図1】 本発明の実施形態である床パネル敷設装置により床パネルをプール室に敷設している状況を示す図である。
【図2】 同、平面図である。
【図3】 同、断面図である。
【図4】 同床パネルを示す図である。
【図5】 同、拡大図である。
【図6】 同、支持脚の拡大図である。
【図7】 同、係合部材の拡大図である。
【図8】 本発明の実施形態である床パネル敷設装置におけるキャリアを示す図である。
【図9】 同、格納庫と格納装置を示す図である。
【図10】 同、敷設作業工程を示す図である。
【符号の説明】
1 床パネル
2 床パネル敷設装置
3 プール室
6 下地フレーム
7 床板
8 支持脚
15 係合部材
15a 支持部
15b 被支持部
17 テーパ面
20 格納庫
21 格納装置
22 キャリア
23 走行台車
30 リフト機構
31 揺動アーム
40 取出口
43 リフタ
44 スライド床
[0001]
BACKGROUND OF THE INVENTION
  The present invention provides a floor panel that is installed so as to cover the entire floor surface of a room when a room for an arbitrary use is temporarily changed to a room for another use.Floor panel laying equipment for layingAbout.
[0002]
[Prior art]
In recent years, various sports competition facilities have been established in various places, but this type of facility tends to be more versatile rather than a single function only for specific competitions. There is a demand to use a facility mainly for swimming pools as a gymnasium for performing sports other than swimming and as a venue for holding various events.
[0003]
In order to meet such demands, the floor of the pool is made a movable floor that can be raised and lowered, and it is raised to the level of the pool side so that the entire floor of the pool room can be made flat, and the floor board is placed on it. It has been conventionally practiced to form a floor that can be used as a gymnasium by laying down the entire surface.
[0004]
[Problems to be solved by the invention]
However, the conventional floor laying work as described above can only be performed with the help of a large number of workers, and therefore, the floorboard must be light and small in size so that the worker can easily carry it. For this reason, in the past, not only a huge number of floorboards are required, but also the floorboards need to be laid flat so as not to cause steps, and such work is not always easy. However, it took several days to install the floor in the entire indoor pool. This is common not only when changing the indoor pool to a gymnasium, but also when changing a room for various purposes to a room for other purposes temporarily, and effective improvement measures have been desired. .
[0005]
The present invention has been made in view of the above circumstances, and provides an effective means capable of quickly and easily performing floor laying work and restoration work when a room for any use is temporarily used for another use. With the goal.
[0009]
[Means for Solving the Problems]
  In the invention of claim 1, in order to temporarily change a room for any use to a room for another use, a long floor panel having a length over the entire width or the entire length of the room is provided on the floor surface of the room. A floor panel laying device for laying the entire surface, comprising a hangar provided inside the chamber or at a position facing the chamber and storing a large number of the floor panels in a stacked state, and the floor panel mounted thereon A carrier that transports the floor panel between the hangar and the laying position by traveling forward and backward in the room, and a floor panel stored in the hangar is loaded onto the carrier and mounted on the carrier. And a storage device for storing the floor panel in the hangarThe hangar is formed by digging down below the floor of the chamber, and a horizontally long slit-shaped outlet for carrying the floor panel in and out is provided at an upper portion thereof, and the storage device includes the hangar A lifter that grips and lifts the floor panel inside, and a slide floor that is provided in an upper part of the hangar so as to be able to advance and retreat, and the slide floor advances from the outlet to the upper part of the hangar. The carrier entering the hangar is supported and retracted to the rear of the hangar to allow the lifter to move up and down.
[0010]
  Claim 2The invention ofClaim 1In the floor panel laying apparatus according to the invention, the carrier has a length extending over the entire length of the floor panel by connecting a plurality of traveling carriages arranged in a horizontal direction at a predetermined interval, and the floor panel can be moved up and down on the traveling carriage. And a lift mechanism for supporting the motor.
[0011]
  Claim 3The invention ofClaim 2In the floor panel laying device described above, the lift mechanism includes a swingable swingable arm, and the swingable arm is lifted up and the floor panel is lifted forward from the lifted floor panel. It is configured to be lowered while being moved forward.
[0012]
  Claim 4The invention ofClaim 2 or 3In the floor panel laying device described above, the lift mechanism includes a slide mechanism that slides the floor panel in the length direction in a state where the floor panel is lifted.
[0013]
  Claim 5The invention ofClaim 2, 3 or 4In the floor panel laying apparatus described above, a control means for detecting the positions of at least both ends of the carrier and adjusting the speed of each traveling carriage based on the results is provided.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
  1 to 3 show an embodiment of the present invention.By laying the floor panel 1 on the floor surface of the pool room 3 using the floor panel laying device 2,This shows the situation where the pool room 3 is converted into a gymnasium. The pool room 3 in this example is provided with a 50 m pool for official competitions, and the bottom of the pool is a movable floor 4 that can be raised and lowered into four parts, and when it is converted into a gymnasium, the pool water is drained. Thus, the movable floor 4 is raised to the level of the pool side 5, and the floor panel 1 can be laid on the floor without any gaps. Although not shown, a hydraulic cylinder for raising and lowering the movable floor 4 is provided at the bottom of the pool, and the movable floor 4 is lifted and stably supported and loaded. A strut to receive the load is installed in the pool.
[0016]
Details of the floor panel 1 are shown in FIGS. The floor panel 1 is manufactured in advance in a predetermined shape and size corresponding to the shape and size of the pool room 3, and in this example, the total length is about 40 m of the total width of the pool room 3, and the width is 2 m. It is said to be about. The floor panel 1 is such that a floor plate 7 such as a flooring material is mounted on a base frame 6 made of, for example, an aluminum mold, and a large number of foldable support legs 8 are provided at predetermined intervals.
[0017]
Among the floor panels 1, one floor panel 1a installed at the foremost part of the pool room 3 is provided with support legs 8 on both front and rear sides as shown in FIG. However, the other floor panels 1 sequentially installed on the rear side of the floor panel 1 are engaged with the installed floor panel 1 by an engagement member 15 (details will be described later) to receive the load. Accordingly, the floor panel 1 other than the above-described floor panel 1a installed at the foremost part is provided with the support legs 8 only on the rear side as shown in FIG. Is omitted.
[0018]
The support legs 8 can be folded inside the base frame 6. When the floor panel 1 is stored in a stacked state in the storage 20 (described later in detail) or when it is transported by the carrier 22 (described later in detail). By folding the support leg 8, the storage space can be saved and it is avoided that it interferes with conveyance. FIG. 6 shows details of a mechanism for folding the support leg 8. The upper end of the support leg 8 is rotatably connected to the base frame 6 by a shaft 9, and the support leg 8 is locked by a stopper 10. It is configured. The stopper 10 is an L-shaped metal fitting, the corner of which is rotatably connected to the support leg 8 by the shaft 11, and either one of the both ends is fixed to the fixing plate 12 attached to the base frame 6. By connecting with the pin 13, the support leg 8 can be locked both in the tilted state and in the raised state. Reference numeral 14 denotes a cushion rubber attached to the tip of the support leg 8. In addition, when each floor panel 1 is installed in the pool chamber 3, the height dimension of each support leg 8 depends on the installation position, that is, the floor slope of the pool side 5, so that the upper surface thereof is naturally horizontal. And can be adjusted in advance corresponding to the level of the movable floor 4.
[0019]
Each floor panel 1 is provided with an engaging member 15 for connection to another floor panel 1. As shown in FIG. 5, the engaging member 15 is a pair of a support portion 15 a provided on the rear side of the floor panel 1 and a supported portion 15 b provided on the front side, and has already been installed. By engaging the supported portion 15b of the rear floor panel 1 newly installed with the support portion 15a of the front floor panel 1, the floor panels 1 are connected to each other and the front floor The load of the rear floor panel 1 can be received by the panel 1, and as a result, the support legs on the front side of the floor panel 1 other than the floor panel 1 a installed at the foremost part as described above. It can be omitted.
[0020]
Further, as shown in FIG. 7, the support rubber 15a is attached to both the support part 15a and the supported part 15b, and a pair of tapered surfaces 17 are formed on both of the buffer rubbers 16, and the support rubber 15 is supported. When the supported portion 15b is engaged with the portion 15a, both the tapered surfaces 17 are brought into close contact with each other, and both floor panels 1 are displaced in a direction in which they approach each other, and their upper surface levels naturally match each other. The upper surface of the floor panel 1 is naturally continuous without a gap and without a step.
[0021]
The floor panel 1 configured as described above has an inside of a hangar 20 provided on one end side in the pool room 3 as shown in FIG. 1 when the pool room 3 is used as a pool room which is the original use. When the pool room 3 is converted into a gymnasium, the pool room 3 is sequentially taken out from the pool room 3 and conveyed forward and laid. Therefore, the stacking order of the floor panels 1 in the hangar 20 is that the floor panel 1a arranged at the foremost part of the pool room 3 is the uppermost stage, and the floor panels 1a that are sequentially installed on the front side are stacked in that order. What is arranged on the side (the hangar 20 side) is the lowest level.
[0022]
All of the work of taking out and laying the floor panel 1 from the hangar 20 during the conversion from the pool room 3 to the gymnasium, and the work of storing the floor panel 1 in the hangar 20 during the reconversion from the gymnasium to the pool room 3 are performed in this embodiment. This is performed mechanically and almost automatically by the laying device 2. The laying device 2 includes the hangar 20 described above, a storage device 21 attached thereto, and a carrier 22.
[0023]
As shown in FIG. 1, the carrier 22 has a length extending over the entire length of the floor panel 1 by arranging a total of 10 traveling carriages 23 in the horizontal direction and connecting them with a connecting beam 24. Of these ten traveling carts 23, two on both sides and two central portions are driving traveling carts 23a on which traveling driving sources are mounted, and the other six are driven traveling carts 23b that follow them. As shown in FIG. 8, the driving traveling carriage 23a is configured by mounting a traveling motor 27 and a power transmission mechanism 28 on a chassis 26 having eight wheels 25. The driven traveling carriage 23b includes a traveling motor 27 and power. Except that the transmission mechanism 28 is omitted, it is configured in the same manner as the drive traveling carriage 23a.
[0024]
The carrier 22 is configured to run stably by using drainage side grooves 29 provided on both sides in the pool chamber 3 as guide rails. That is, both end portions of the connecting beam 24 can be engaged with the side groove 29, and when the carrier 22 travels, the grating attached to the side groove 29 is removed and the front end portion of the connecting beam 24 is placed there. The carrier 22 is guided and driven by the side groove 29 by being engaged so that it can be guided and by synchronously driving the traveling motor 27 of each driving traveling carriage 23a. A guide member such as a guide roller that rolls while engaging with the side groove 29 is preferably attached to the distal end portion of the connecting beam 24.
[0025]
In addition, it is preferable to provide an appropriate control system for performing automatic operation according to a preset program while accurately and strictly monitoring and controlling the position, speed, traveling direction, and the like of the carrier 22, for example, using laser light A position control system can be suitably employed. As a specific example, the position of the carrier 22 is detected by a laser type distance sensor at least at two locations at both ends of the carrier 22 or at any location in the middle in addition to both ends, and based on the results. A control system that prevents the traveling direction of the carrier 22 from shifting laterally by appropriately adjusting the speed of the four driving traveling carriages 23a and that keeps the entire carrier 22 in a straight state is considered. It is done.
[0026]
All of these traveling carriages 23 are equipped with a lift mechanism 30 that supports the floor panel 1 so as to be movable up and down. As shown in FIG. 8, the lift mechanism 30 includes a swingable arm 31 that can be raised and lowered, a driving motor 32 thereof, and a power transmission mechanism 33. The lift mechanism 30 supports the floor panel 1 while the swinging arm 31 is tilted. When the carrier 22 is run and the floor panel 1 is installed on the floor surface, the swing arm 31 is raised to lift the floor panel 1 and the support leg 8 of the floor panel 1 is raised. By falling forward, the floor panel 1 is lowered slightly while moving forward. Although not shown, the lift mechanism 30 is adjusted in position by sliding the floor panel 1 in the length direction (direction perpendicular to the traveling direction of the carrier 22) while the floor panel 1 is lifted. A slide mechanism for performing the above is provided. As the slide mechanism, for example, a roller that rotates while supporting the floor panel 1 can be suitably used.
[0027]
The power supply to the carrier 22 is performed by suspending and supporting the power supply cable 35 by a cable support rail 34 temporarily installed in the pool chamber 3 as shown in FIG.
[0028]
The storage 20 and the storage device 21 attached thereto will be described with reference to FIG. The hangar 20 is formed by being dug down below the floor surface of the pool room 3, and a horizontally long slit-like outlet 40 for carrying the floor panel 1 in and out is opened at the upper part of the hangar 20. . A support frame 41 for supporting the floor panel 1 in a stacked state is installed in the hangar 20, and the support frame 41 supports load distribution by supporting the floor panel 1 by five by a tiltable hook 42. .
[0029]
The storage device 21 has a lifter 43 that can move up and down by grasping the floor panel 1 in the storage 20 and a slide floor 44 that can be moved forward and backward from the rear of the storage 20. The lifter 43 is driven by an elevating motor 45 and is guided up and down by a support frame 41, and has a hook 46 for holding the floor panel 1 from both sides and an operating cylinder 47 at the lower part thereof. The slide floor 44 is driven by a motor 48 to advance and retreat, and in the state where the slide floor 44 has advanced to the upper part of the hangar 20, it can support each traveling carriage 23 of the carrier 22 entering the hangar 20 from the outlet 40, and the hangar 20. The lifter 43 is allowed to move up and down in the hangar 20 by being retracted rearwardly and positioned on the cradle 49.
[0030]
An operation procedure for laying the floor panel 1 by the laying device 2 when the pool room 3 is converted into a gymnasium will be described with reference to FIG. (A) shows the initial state at the time of starting work. In this state, the lifter 43 is disposed on the upper part of the hangar 20, and the slide floor 44 is on the cradle 49. The carrier 22 stops and stands in front of the outlet 40 of the hangar 20, and the swing arm 31 of the lift mechanism 30 is in a lying state. The pool has already been drained and the movable floor 4 is raised and fixed to the level of the pool side 5.
[0031]
From that state, the lifter 43 is lowered as shown in (b) to grip the uppermost floor panel 1 (1a), and when the lifter 43 is raised as shown in (c), the slide floor 44 is advanced. As shown in (d), the carrier 22 is inserted into the hangar 20 through the outlet 40 and placed on the slide floor 44. When the lifter 43 is lowered and the floor panel 1 is placed on the carrier 22, the hook 42 is opened. The floor panel 1 is mounted on the carrier 22. After raising the lifter 43, the carrier 22 is advanced to the standby position as shown in (e), the slide floor 44 is moved backward as shown in (f), and the lifter 43 is lowered, as shown in (g). The next floor panel 1 is held by the lifter 43. At the same time, the carrier 22 carrying the floor panel 1 moves forward and stops at the position where the floor panel 1 is installed, operates the lift mechanism 30 to raise the swing arm 31, and manually supports the support leg 8 by the operator. Is raised and locked by the stopper 10, and the carrier 22 is slightly moved in the front-rear direction as necessary, and the floor panel 1 is slid in the length direction by the slide mechanism to finely adjust the installation position and swing. The arm 31 is tilted to install the floor panel 1, and the carrier 22 is moved backward to return to the standby position.
[0032]
Thereafter, the above procedure is repeated, and other floor panels 1 may be sequentially installed behind the installed floor panel 1 and connected to each other. Moreover, when returning the gymnasium converted as described above to the pool room 3 again, the above procedure may be reversed to store the floor panel 1 in the hangar 20 sequentially from the front side. In addition, the carrier 22 can be stored in the hangar 20 by placing it on the slide floor 44 after the work is completed.
[0033]
  Explained aboveFloor panel 1Is a long one having a length extending over the entire width of the pool room 3, so that only about 30 floor panels 1 need to be laid out during the conversion work. It is possible to do it, and it is very efficient. Moreover, since the support legs 8 of each floor panel 1 can be folded, the storage legs can be saved and stored by storing and transporting the support legs 8 in the state where the support legs 8 are folded inside the base frame 7, and the support legs 8 can be used when transporting. 8 will not get in the way.
[0034]
  further,the aboveThe floor panel 1 has an engaging member 15 for connecting adjacently installed members, and the engaging member 15 is connected to the support portion 15a so as to receive the load of the rear floor panel by the front floor panel. Since it is constituted by the supported portion 15b, the supporting leg 8 may be provided only on one side of the floor panel 1 (that is, below the supporting portion 15a), and on both the supporting portion 15a and the supported portion 15b. Since the buffer rubber 16 having the tapered surfaces 17 that are in close contact with each other is provided, the adjacent floor panels 1 are continuously continuous without any gaps and steps.
[0035]
Since the floor panel 1 is long over the entire width of the pool room 3, its production is carried out by manufacturing a unit of a predetermined length in the factory, carrying it to the site, and connecting a predetermined number of these units at the site. It is realistic to complete the floor panel 1. For example, when the total length of the floor panel 1 is about 40 m as described above, a unit having a length of about 10 m is manufactured at the factory and loaded into the pool room 3, and four units are connected there to connect the floor panel 1. Can be completed. In that case, it is conceivable to store the units in the hangar 20 without connecting the units, and lay them while connecting the units. In this case, however, it is very difficult to install the units or connect the units. Efficient work is not hoped for. Therefore, it is necessary to store the floor panel 1 in a state where the floor panel 1 is completed over the entire width of the pool room 3 as in the above embodiment, and lay it in a lump.
[0036]
Moreover, the laying apparatus 2 of the present embodiment is equipped with a hangar that stores a large number of long floor panels 1 in a stacked state that extend over the entire width of the pool room 3 as described above, and such a long floor panel 1. And the storage device 21 for loading the floor panel 1 onto the carrier 22 and storing it in the hangar 20 so that the long floor panel 1 is mechanically and almost automatically provided. It can be transported, laid and stored, and the work can be performed efficiently and in a short time.
[0037]
In particular, the laying apparatus 2 of the present embodiment employs the carrier 22 having a configuration in which a plurality of traveling carriages 23 are arranged side by side and connected, so that the long floor panel 1 can be stably conveyed with a simple configuration. Since each traveling carriage 23 is equipped with a lift mechanism 30 that supports the floor panel 1 so that it can be raised and lowered, the floor panel 1 is lowered from the carrier 22 to the floor surface by operation of the lift mechanism 30 or installed on the floor surface. The floor panel 1 can be easily loaded into the carrier 22 and the swing mechanism 31 that can be tilted up and down is adopted as the lift mechanism 30, and the floor panel 1 is moved forward by tilting it forward. Therefore, when the floor panel 1 is installed, the support portion 15a and the supported portion 15b of the engagement member 15 can be reliably engaged. Moreover, since the lift mechanism 30 includes a slide mechanism that slides the floor panel 1 in the length direction, fine adjustment of the position of the floor panel 1 in the length direction can be easily performed.
[0038]
In addition, the laying device 2 of the present embodiment is formed by digging the storage 20 downward from the floor surface, and provided with a horizontally long slit-shaped outlet 40 for loading and unloading the floor panel 1 at the top thereof. 21 has a lifter 43 that holds and lifts the floor panel 1 in the hangar 20 and a slide floor 44 that can be moved forward and backward in the upper part of the hangar 20, so that the slide floor 44, the lifter 43, the carrier 22, Thus, the floor panel 1 can be laid and stored efficiently and reliably.
[0039]
Although the embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments. Of course, rooms for any use other than a pool room, for example, a sports facility such as a skating rink, and an event facility, etc. Is widely applicable. And in short, long floor panels that cover substantially the entire width or length of the room are stored in a stacked state in a room or a hangar provided at the position facing the room, and are sequentially transported and laid out in sequence. As long as it is configured, the dimensions and form of the floor panel may be changed as appropriate in accordance with the use, scale, and planar shape of the room. For example, in the above embodiment, the entire length of the floor panel extends over the entire width of the pool room, and the floor panel is sequentially laid out in the length direction of the pool room. Of course, it is also possible to sequentially lay out in the width direction. Further, the configuration of the support legs and the engaging members can be variously changed, and it is optional to further lay a floor finishing material such as linoleum or carpet on the floor panel according to the use.
[0040]
  The construction of the laying device also includes a hangar for storing long floor panels in a stacked state, a storage device attached thereto, and a carrier for transporting the floor panels.In addition, an outlet for carrying the floor panel in and out of the hangar is provided, a lifter that holds the floor panel in the hangar and moves up and down, and a slide floor provided in the upper part of the hangar so as to be able to advance and retreat. ConfigureIt goes without saying that appropriate design changes can be made according to the use and form of the target room, the shape, dimensions, form, etc. of the floor panel.
[0044]
【The invention's effect】
  Claim 1The floor panel laying apparatus of the invention includes a hangar that stores a large number of long floor panels in a stacked state, a carrier that is mounted with the long floor panels and travels forward and backward in the room, and the floor panel as a carrier. A storage device for loading and storing in a hangar, so that long floor panels can be mechanically and almost automatically transported for laying and storing, which makes the work efficient and short It can be done in time.
In addition, this floor panel laying device is provided with an outlet for loading / unloading the floor panel at the top of the hangar, a lifter that holds the floor panel in the hangar and moves up and down, and can be moved forward and backward at the top of the hangar Since the slide floor is provided, the floor panel laying operation and the storage operation can be carried out efficiently and reliably by the cooperation of the slide floor, the lifter and the carrier.
[0045]
  Claim 2The floor panel laying apparatus of the invention adopts a carrier having a configuration in which a plurality of traveling carriages are arranged side by side and connected, so that a long floor panel can be stably conveyed with a simple configuration, and each traveling The dolly is equipped with a lift mechanism that supports the floor panel so that it can be raised and lowered, so that the floor panel is lowered from the carrier to the floor by operating the lift mechanism and the floor panel installed on the floor is loaded onto the carrier. Work can be done easily.
[0046]
  Claim 3The floor panel laying device of the invention adopts a swing arm that can be tilted up and down as a lift mechanism, and is configured to be lowered and moved to the front by tilting it forward and installed on the floor surface. In the installation of the floor panel, the engaging members can be reliably engaged with each other.
[0047]
  Claim 4The floor panel laying device of the invention has a slide mechanism that slides in the length direction while the floor panel is lifted up by the lift mechanism. Therefore, when the floor panel is installed, it is easily positioned in the length direction. obtain.
[0048]
  Claim 5The floor panel laying device of the invention includes a control means for detecting the positions of at least both ends of the carrier and adjusting the speed of each traveling carriage based on the result, so that the carrier can always be kept straight and travel. Directional deviation can be prevented.
[Brief description of the drawings]
FIG. 1 is an embodiment of the present invention.By floor panel laying equipmentIt is a figure which shows the condition which has laid the floor panel in the pool room.
FIG. 2 is a plan view of the same.
FIG. 3 is a sectional view of the same.
FIG. 4 is a view showing the same floor panel.
FIG. 5 is an enlarged view of the same.
FIG. 6 is an enlarged view of the support leg.
FIG. 7 is an enlarged view of the engaging member.
FIG. 8 is a diagram showing a carrier in the floor panel laying apparatus according to the embodiment of the present invention.
FIG. 9 is a diagram showing a hangar and a storage device.
FIG. 10 is a diagram showing a laying work process.
[Explanation of symbols]
1 Floor panel
2 Floor panel laying equipment
3 Pool room
6 Ground frame
7 Floor boards
8 Support legs
15 Engagement member
15a support part
15b Supported part
17 Tapered surface
20 Hangar
21 Enclosure
22 Career
23 Traveling cart
30 Lift mechanism
31 Swing arm
40 outlet
43 Lifter
44 slide floor

Claims (5)

任意の用途の室を一時的に他の用途の室に変更するべく、該室の全幅もしくは全長にわたる長さを有する長尺の床パネルを該室の床面上に全面的に敷設するための床パネル敷設装置であって、
前記室の内部もしくは該室に面する位置に設けられて前記床パネルを積層状態で多数格納する格納庫と、
前記床パネルを搭載して前記室内において前進後退可能に走行することにより該床パネルを前記格納庫と敷設位置との間にわたって搬送するキャリアと、
前記格納庫内に格納されている床パネルを前記キャリアに積み込みかつ該キャリアに搭載されている床パネルを格納庫に格納する格納装置とを具備してなり、
前記格納庫は前記室の床面より下方に掘り下げられて形成されていて、その上部に前記床パネルを搬出入するための横長スリット状の取出口が設けられ、
前記格納装置は、該格納庫内において前記床パネルを把持して昇降するリフタと、前記格納庫内の上部に進退可能に設けられたスライド床を有し、該スライド床は前記格納庫の上部に進出することで前記取出口から前記格納庫内に進入してくる前記キャリアを支持し、かつ、格納庫の後方に退避することで前記リフタの昇降を許容する構成としたことを特徴とする床パネル敷設装置。
In order to temporarily change a room for any use into a room for another use, a long floor panel having a length over the entire width or the entire length of the room is laid on the floor surface of the room. A floor panel laying device,
A hangar that is provided inside the chamber or at a position facing the chamber and stores a large number of the floor panels in a stacked state;
A carrier that carries the floor panel between the hangar and the laying position by mounting the floor panel and traveling forward and backward in the room;
A storage device for loading the floor panel stored in the hangar into the carrier and storing the floor panel mounted on the carrier in the hangar ;
The hangar is formed by being dug down below the floor surface of the chamber, and a horizontally long slit-shaped outlet for carrying the floor panel in and out is provided on the upper part,
The storage device includes a lifter that lifts and lowers by grasping the floor panel in the hangar, and a slide floor that can be moved forward and backward in the upper portion of the hangar, and the slide floor advances to the upper portion of the hangar. Thus , the floor panel laying apparatus is configured to support the carrier entering the hangar from the take-out port and to allow the lifter to move up and down by retracting to the rear of the hangar.
前記キャリアは複数の走行台車を所定間隔をおいて横方向に並べて連結することにより前記床パネルの全長にわたる長さとされ、前記走行台車には床パネルを昇降可能に支持するリフト機構を搭載してなることを特徴とする請求項1記載の床パネル敷設装置。  The carrier has a length extending over the entire length of the floor panel by connecting a plurality of traveling carts arranged side by side at a predetermined interval, and the traveling cart is equipped with a lift mechanism that supports the floor panel so that it can be raised and lowered. The floor panel laying apparatus according to claim 1, wherein 前記リフト機構は起倒自在な揺動アームからなり、該揺動アームを起立させて床パネルを持ち上げた状態から該揺動アームを前方に倒すことで床パネルを前方に移動させつつ降下させる構成としたことを特徴とする請求項2記載の床パネル敷設装置。  The lift mechanism is composed of a swingable swing arm, and is configured to move down the floor panel while moving the floor panel forward by tilting the swing arm forward from a state where the swing arm is raised and the floor panel is lifted. The floor panel laying apparatus according to claim 2, wherein 前記リフト機構は前記床パネルを持ち上げた状態で該床パネルをその長さ方向にスライドさせるスライド機構を具備してなることを特徴とする請求項2または3記載の床パネル敷設装置。  The floor panel laying apparatus according to claim 2 or 3, wherein the lift mechanism includes a slide mechanism that slides the floor panel in a length direction in a state in which the floor panel is lifted. 前記キャリアの少なくとも両端部における位置を検出してその結果に基づき前記各走行台車の速度調整を行う制御手段を具備してなることを特徴とする請求項2,3または4記載の床パネル敷設装置。  5. The floor panel laying apparatus according to claim 2, further comprising control means for detecting positions at at least both ends of the carrier and adjusting the speed of each traveling carriage based on the result. .
JP236099A 1999-01-07 1999-01-07 Floor panel laying equipment Expired - Lifetime JP4122383B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP236099A JP4122383B2 (en) 1999-01-07 1999-01-07 Floor panel laying equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP236099A JP4122383B2 (en) 1999-01-07 1999-01-07 Floor panel laying equipment

Publications (2)

Publication Number Publication Date
JP2000204780A JP2000204780A (en) 2000-07-25
JP4122383B2 true JP4122383B2 (en) 2008-07-23

Family

ID=11527104

Family Applications (1)

Application Number Title Priority Date Filing Date
JP236099A Expired - Lifetime JP4122383B2 (en) 1999-01-07 1999-01-07 Floor panel laying equipment

Country Status (1)

Country Link
JP (1) JP4122383B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115680249A (en) * 2021-07-28 2023-02-03 广东博智林机器人有限公司 Floor storage device and floor installation equipment

Also Published As

Publication number Publication date
JP2000204780A (en) 2000-07-25

Similar Documents

Publication Publication Date Title
KR970003868B1 (en) Multi-level parking facility
WO2025026413A1 (en) Material distribution unit, longitudinal-bar material distribution apparatus and longitudinal-bar material distribution method
JP4122383B2 (en) Floor panel laying equipment
JP6740439B1 (en) Luggage storage system
CN113882638B (en) Scaffold for building construction and construction method thereof
JP7057916B2 (en) Conveyor for stairs
US3055518A (en) Rack loading method and apparatus
JP7321200B2 (en) A loading and unloading device, a loading and unloading system using the device, a loading and unloading method thereof, a structure construction system using the device and a construction method thereof
JPH08217211A (en) Board manufacturing equipment
RU2146432C1 (en) Agricultural complex
JP4295383B2 (en) Stadium facilities
JPS63300100A (en) Heavy goods transport equipment
JPH081278Y2 (en) Heavy goods carrier
CN105109938B (en) Iron plate is automatically credited system and method
JP4552102B2 (en) Work cart
CN120946128B (en) Positioning structure for mounting laminated plate
GB2433955A (en) Method of laying a plurality of railway sleepers
JP4588832B2 (en) Slide unit and method of shifting heavy objects using it
JP3433464B2 (en) Nursery box stacking equipment in nursery facilities
JPH07324487A (en) Horizontal transport system
JPH0941667A (en) A dolly with an undulating device for transporting a building member, and a method for transporting a building member by the trolley
JP2023183669A (en) Mobile scaffolding for automated warehouse rack assembly and automated warehouse rack assembly method
JPH11280279A (en) Floor laying method and apparatus, and floor panel
JPH07324490A (en) Transport system and construction method of building using the same
JPH0434885B2 (en)

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050513

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061026

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070605

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070802

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071009

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071204

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20071204

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20071204

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080212

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080310

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110516

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110516

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120516

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120516

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130516

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140516

Year of fee payment: 6

EXPY Cancellation because of completion of term