JP4286737B2 - Construction method of pier - Google Patents
Construction method of pier Download PDFInfo
- Publication number
- JP4286737B2 JP4286737B2 JP2004204825A JP2004204825A JP4286737B2 JP 4286737 B2 JP4286737 B2 JP 4286737B2 JP 2004204825 A JP2004204825 A JP 2004204825A JP 2004204825 A JP2004204825 A JP 2004204825A JP 4286737 B2 JP4286737 B2 JP 4286737B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- girder
- bridge
- pier
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 35
- 239000004567 concrete Substances 0.000 claims description 36
- 229910000831 Steel Inorganic materials 0.000 claims description 34
- 239000010959 steel Substances 0.000 claims description 34
- 238000000034 method Methods 0.000 claims description 15
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 239000011150 reinforced concrete Substances 0.000 claims description 5
- 230000002093 peripheral effect Effects 0.000 description 4
- 230000008030 elimination Effects 0.000 description 3
- 238000003379 elimination reaction Methods 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 230000000116 mitigating effect Effects 0.000 description 2
- 229910001208 Crucible steel Inorganic materials 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000275 quality assurance Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Images
Landscapes
- Foundations (AREA)
- Bridges Or Land Bridges (AREA)
Description
この発明は、道路橋や鉄道橋などの橋脚を構築する方法の技術分野に属し、更に云うと、上部工を施工可能な段階まで急速に橋脚を構築する方法に関する。 The present invention belongs to a technical field of a method for constructing a pier such as a road bridge and a railway bridge, and more specifically, relates to a method for constructing a pier rapidly to a stage where superstructure can be constructed.
上部工を施工可能な段階まで急速に橋脚を構築する方法として、非特許文献1には、鋼管杭を打設した後、同鋼管杭に仮支柱として外面リブ付き鋼管を直接溶接して立ち上げ、上部工を施工可能な橋脚とすることが記載されている。
非特許文献1の構築方法は、打設した鋼管杭に仮支柱として外面リブ付き鋼管を溶接して立ち上げるだけで上部工を施工可能な橋脚とする点を注目できるが、鋼管杭と外面リブ付き鋼管との現地での溶接作業は天候に左右されるので、工期短縮の障害となっている上に、溶接の品質保証にも問題がある。 The construction method of Non-Patent Document 1 can be noted that the steel pier pile and the outer rib can be constructed by simply welding the steel pipe with the outer rib as a temporary support to the cast steel pipe pile and starting it up. Since welding work with steel pipes in the field depends on the weather, it is an obstacle to shortening the construction period and there is also a problem in quality assurance of welding.
本発明の目的は、基礎杭の構造体の一部として、橋桁を支持する構真柱を建て込み剛強に一体化させることで、橋脚として要求される強度、剛性を確保し、速やかに橋桁を架設するなどの上部工を施工可能にする、急速な橋脚の構築方法を提供することである。 The purpose of the present invention is to secure the strength and rigidity required for the bridge pier as a part of the structure of the foundation pile by building a structural pillar that supports the bridge girder and integrating it into a rigid structure. The purpose is to provide a rapid pier construction method that enables superstructure work such as erection.
本発明の目的は、コンクリートフーチングを無用とし、又は必要最小限度に小さいものとすることができ、したがって、橋の橋脚として地上の道路幅を制約することが少なく、交通渋滞の緩和ないし解消に寄与する橋脚の構築方法を提供することである。 The object of the present invention is to eliminate the need for concrete footing, or to make it as small as necessary. Therefore, it is less likely to limit the road width on the ground as a pier of a bridge, contributing to the mitigation or elimination of traffic congestion. It is to provide a method for building a pier.
上記従来技術の課題を解決するための手段として、請求項1に記載した発明に係る橋脚の構築方法は、
道路橋1や鉄道橋などの橋脚2を構築する方法であって、
地盤を掘削し、その中に鉄筋篭4を挿入しコンクリート5を充填して橋脚2の基礎杭3を打設すると共に、前記コンクリート5を養生する当初の段階で構真柱6を前記コンクリート5の鉄筋篭4の中へ建て込み鉄骨鉄筋コンクリート造杭と成す段階と、
前記コンクリート5が一定の強度を発現した段階で、橋脚2の構真柱6、6相互の上端部を桁受け7で連結して、前記基礎杭3と構真柱6および桁受け7を構造体として含む橋脚2を、前記桁受け7の上に橋桁8を架設する等の上部工の施工が可能に構築することを特徴とする。
As a means for solving the problems of the prior art, the construction method of the pier according to the invention described in claim 1 is:
A method for constructing a
The ground is excavated, a reinforcing bar 4 is inserted therein, the
At the stage where the
請求項2に記載した発明に係る橋脚の構築方法は、
道路橋1や鉄道橋などの橋脚2を構築する方法であって、
地盤を掘削し、その中に鉄筋篭4を挿入しコンクリート5を充填して橋脚2の基礎杭3を打設すると共に、前記コンクリート5を養生する当初の段階で構真柱6を前記コンクリート5の鉄筋篭4の中へ建て込み鉄骨鉄筋コンクリート造杭と成す段階と、
前記コンクリート5が一定の強度を発現した段階で、橋脚2の構真柱6、6相互の上端部を桁受け7で連結して、前記基礎杭3と構真柱6および桁受け7を構造体として含む橋脚2を、前記桁受け7の上に橋桁8架設する等の上部工の施工が可能に構築する段階と、
前記基礎杭3、3相互をフーチング10で連結し、更に構真柱6、6を相互にコンクリート11で固めて補強する施工と、前記桁受け7の上に橋桁8を架設する等の上部工の施工とを並行して進めることを特徴とする。
請求項3に記載した発明は、請求項2に記載した橋脚の構築方法において、
基礎杭3、3相互をフーチング10で連結し、更に構真柱6、6を相互に鉄骨梁12及び筋交い13により強固に連結して補強する施工と、桁受け7の上に橋桁8を架設する等の上部工の施工とを並行して進めることを特徴とする。
請求項4に記載した発明は、請求項2又は3に記載した橋脚の構築方法において、
基礎杭3、3相互をフーチングで連結することなく、構真柱6、6を相互にコンクリート10で固めるか、又は鉄骨梁12及び筋交い13により構真柱6、6を強固に連結して補強することを特徴とする。
The construction method of the pier according to the invention described in
A method for constructing a
The ground is excavated, a reinforcing bar 4 is inserted therein, the
At the stage where the
Construction work in which the
The invention described in
The
The invention described in claim 4 is the construction method of the pier according to
Without connecting the
本発明に係る橋脚の構築方法は、基礎杭の構造体の一部として、橋桁を支持する構真柱を建て込み剛強に一体化させたので、橋脚として要求される強度、剛性を構真柱で確保することができ、この構真柱相互の上端部を桁受けで連結すると、直ちに橋桁を架設するなどの上部工を施工可能な段階にまで構築を急速に進めることができる。したがって、その後は上部工の施工と橋脚を完成する作業とを並行して進め、工期を飛躍的に短縮することができる。 In the method for constructing a pier according to the present invention, a structural pillar supporting a bridge girder is built as a part of a structure of a foundation pile, and the strength and rigidity required for a pier are integrated. By connecting the upper ends of the structural pillars with a girder, the construction can be rapidly advanced to the stage where the superstructure such as a bridge girder can be constructed immediately. Therefore, after that, the construction work for the superstructure and the work for completing the pier can be carried out in parallel, and the construction period can be dramatically shortened.
橋脚として要求される強度、剛性は、基本的に基礎杭と構真柱とで確保できるため、コンクリートフーチングを無用とし、又は必要最小限度に小さいものとすることができる。よって、橋の橋脚として道路幅を制約することが少なく、交通渋滞の緩和ないし解消に寄与できる。 Since the strength and rigidity required for the pier can be basically secured by the foundation pile and the structural pillar, the concrete footing can be made useless or can be made as small as necessary. Therefore, there is little restriction on the road width as a pier of the bridge, and it can contribute to alleviation or elimination of traffic congestion.
請求項1、2に記載した発明に係る橋脚の構築方法(以下、単に構築方法と云う場合がある。)の実施形態を、図1〜図8に基づいて説明する。本発明の構築方法は、例えば図1に示すような道路橋1(但し、鉄道橋などでも同様に実施できる。)の橋脚2を構築する方法として好適に実施される。
An embodiment of a pier construction method (hereinafter sometimes simply referred to as a construction method) according to the invention described in
具体的には、図2に示すように、先ずは基礎杭3…を打設するべく、所定の位置の地盤を掘削し、その中に鉄筋籠4を挿入してコンクリート5を充填する。
Specifically, as shown in FIG. 2, first, in order to place
前記コンクリート5を養生する当初の段階で、図3に示すように、構真柱として例えばH形鋼6を建て込む。その結果、基礎杭3は鉄骨鉄筋コンクリート造杭と成り、その構造体の一部として前記H形鋼6が強固に一体化されるので、橋脚2として要求される強度、剛性を確保することができる。コンクリート5が一定の強度を発現した段階で、上記H形鋼6、6相互の上端部を桁受け7で連結する(図4を参照)。かくすると、桁受け7の上に橋桁8を架設するなどの所謂上部工の施工が可能な段階まで急速に構築が進んだことになる。したがって、工期を飛躍的に短縮することができる。
At the initial stage of curing the
ちなみに、本実施形態のH形鋼6は、図5に示すようにフランジ等にスタッド9を有するものとし、コンクリート5へのH形鋼6の外周面の付着力、及びスタッド9の抵抗力によって前記コンクリート5と強固に一体化させている。
Incidentally, the H-
その後は、図6に示すように、桁受け7の上に橋桁8を架設するなどの上部工の施工と、基礎杭3、3相互をフーチング10で連結し、更にはH形鋼6、6相互をコンクリート11で固めて補強する下部工の施工とを、同時並行に進めることができる。上述したように、橋脚2として要求される強度、剛性は、基礎杭3とH形鋼6とから成る構造で既に確保されているため、フーチング10は必要最小限度に小さいものとすることができる。よって、道路橋1の橋脚として道路幅を制約することが少なく、施工時に交通渋滞の緩和ないし解消に寄与できる。
After that, as shown in FIG. 6, superstructure work such as erection of
もっとも、フーチング10は構真柱の設計強度及び構真柱を補強するコンクリート等の補強効果に応じて省略することもできる。
However, the
上記実施形態では橋脚2をコンクリート11で固めて補強する構成としたが、この限りでない。図7に示すように、構真柱として隣接するH形鋼6、6相互を鋼材による梁12及び筋交い13により強固に連結して補強した鉄骨造としても同様に実施できる(請求項3記載の発明)。なお、梁12により補強するだけで、橋脚2として要求される強度、剛性を確保することができる場合は、筋交い13を省略することができる。
In the embodiment described above, the
上記実施形態では構真柱としてH形鋼6を採用しているが、この限りではない。通例、構真柱として採用される鋼材であれば良く、例えば、図8に示すように、外周面にスタッド9を有する角形(但し、断面形状は丸形などでも良い。)鋼管14を採用しても良い。この場合でも、コンクリート5への鋼管14の外周面の付着力、及びスタッド9の抵抗力によって基礎杭3の構造体の一部として強固に一体化される。
In the above embodiment, the H-
上記実施形態では、特に言及していないが、一個の橋脚2に対して複数本の基礎杭3…を打設する場合は、前記基礎杭3…に、向かい合う配置で少なくとも2本を一組とする構真柱を建て込む。
Although not particularly mentioned in the above embodiment, when placing a plurality of
上記実施形態ではH形鋼6及び鋼管14の外周面にスタッド9…を設けているが、コンクリート5への付着力が大きい場合は、省略しても良い。
In the above embodiment, the
なお、以上に本発明の実施形態を説明したが、本発明はこうした実施形態に何ら限定されるものではなく、本発明の要旨を逸脱しない範囲において、種々の形態で実施し得る。 Although the embodiments of the present invention have been described above, the present invention is not limited to these embodiments, and can be implemented in various forms without departing from the gist of the present invention.
1 道路橋
2 橋脚
3 基礎杭
6 H形鋼(構真柱)
7 桁受け
8 橋桁
11 コンクリート
12 鋼材
14 鋼管(構真柱)
1
7
Claims (4)
地盤を掘削し、その中に鉄筋篭を挿入しコンクリートを充填して橋脚の基礎杭を打設すると共に、前記コンクリートを養生する当初の段階で構真柱を前記コンクリートの鉄筋篭の中へ建て込み鉄骨鉄筋コンクリート造杭と成す段階と、
前記コンクリートが一定の強度を発現した段階で、橋脚の構真柱相互の上端部を桁受けで連結して、前記基礎杭と構真柱および桁受けを構造体として含む橋脚を、前記桁受けの上に橋桁を架設する等の上部工の施工が可能に構築することを特徴とする、橋脚の構築方法。 A method of building piers such as road bridges and railway bridges,
Excavate the ground, insert a reinforcing bar into it, fill the concrete and drive the foundation pile of the pier, and build the built-up column into the concrete reinforcing bar at the initial stage of curing the concrete A stage with a built-in steel-framed reinforced concrete pile,
At the stage where the concrete has developed a certain strength, the upper ends of the bridge pillars are connected with a girder, and the bridge pier including the foundation pile, the mast column and the girder as a structure is included in the girder. A construction method for bridge piers, which is constructed to allow construction of superstructure such as erection of bridge girder on top of the bridge.
地盤を掘削し、その中に鉄筋篭を挿入しコンクリートを充填して橋脚の基礎杭を打設すると共に、前記コンクリートを養生する当初の段階で構真柱を前記コンクリートの鉄筋篭の中へ建て込み鉄骨鉄筋コンクリート造杭と成す段階と、
前記コンクリートが一定の強度を発現した段階で、橋脚の構真柱相互の上端部を桁受けで連結して、前記基礎杭と構真柱および桁受けを構造体として含む橋脚を、前記桁受けの上に橋桁を架設する等の上部工の施工が可能に構築する段階と、
前記基礎杭相互をフーチングで連結し、更に構真柱を相互にコンクリートで固めて補強する施工と、前記桁受けの上に橋桁を架設する等の上部工の施工とを並行して進めることを特徴とする、橋脚の構築方法。 A method of building piers such as road bridges and railway bridges,
Excavate the ground, insert a reinforcing bar into it, fill the concrete and drive the foundation pile of the pier, and build the built-up column into the concrete reinforcing bar at the initial stage of curing the concrete A stage with a built-in steel-framed reinforced concrete pile,
At the stage where the concrete has developed a certain strength, the upper ends of the bridge pillars are connected with a girder, and the bridge pier including the foundation pile, the mast column and the girder as a structure is included in the girder. A stage where construction of superstructure such as erection of a bridge girder on top of it is possible,
The foundation piles are connected to each other by footing, and the construction column is fixed with concrete and reinforced, and the construction of the superstructure such as erection of bridge girder on the girder is advanced in parallel. The construction method of the bridge pier that is characteristic.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2004204825A JP4286737B2 (en) | 2004-07-12 | 2004-07-12 | Construction method of pier |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2004204825A JP4286737B2 (en) | 2004-07-12 | 2004-07-12 | Construction method of pier |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| JP2006028750A JP2006028750A (en) | 2006-02-02 |
| JP2006028750A5 JP2006028750A5 (en) | 2006-10-19 |
| JP4286737B2 true JP4286737B2 (en) | 2009-07-01 |
Family
ID=35895444
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2004204825A Expired - Fee Related JP4286737B2 (en) | 2004-07-12 | 2004-07-12 | Construction method of pier |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4286737B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102493343A (en) * | 2011-11-25 | 2012-06-13 | 中铁五局(集团)有限公司 | Construction method for building trestle bridge piers in bedrock-exposed riverbed |
| CN103422445B (en) * | 2013-09-04 | 2015-04-01 | 中建六局土木工程有限公司 | Constructing method of high temporary bridge crossing river in extremely cold area |
| CN110485258B (en) * | 2019-06-25 | 2021-09-07 | 中交第三航务工程勘察设计院有限公司 | Full-assembly type steel structure approach bridge and construction method thereof |
-
2004
- 2004-07-12 JP JP2004204825A patent/JP4286737B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2006028750A (en) | 2006-02-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6329702B2 (en) | Assembling-type reinforced concrete pier column member | |
| KR101325245B1 (en) | Bridge Post which is assembled by precasted units | |
| JP4992042B2 (en) | Precast horizontal beam and pier using it | |
| KR101198286B1 (en) | Non-wale strut system for top-down construction and top-down construction method thereby | |
| KR101011252B1 (en) | Frame of Reinforcement Ramen Structure for Parental Section and Ramen Structure Having the Same | |
| JP2004263467A (en) | Reconstruction method using existing underground structure | |
| KR20120053869A (en) | Bridge construction method using precast end-block with girder connection member | |
| KR100383268B1 (en) | method for underground construction of building by using permanent structural member as strut for support retaining wall | |
| JP7329432B2 (en) | Rahmen Viaduct and Construction Method of Rahmen Viaduct | |
| KR102392517B1 (en) | Top-down method using by double beam system | |
| JP2010261270A (en) | Construction method of composite structure and composite structure building | |
| JP4286737B2 (en) | Construction method of pier | |
| CN100441782C (en) | Novel prestressed scaffold system | |
| KR200381303Y1 (en) | Form system for joint between retaining wall and slab of basement floor | |
| JP4550534B2 (en) | Building basic structure | |
| CN111648400B (en) | Construction method for civil air defense engineering to meet thick-layer water-bearing sand layer through reverse method | |
| JP5480744B2 (en) | Foundation for structure and its construction method | |
| JP2004263501A (en) | Beam-column joint structure | |
| JP2002030672A (en) | Joint structure between foundation pile and column base and its construction method | |
| KR101219995B1 (en) | A temporary brace and a composite steel girder, a shift section steel girder used an building structure and thereof construction method | |
| JP5259638B2 (en) | Construction method of viaduct portal ramen structure | |
| KR101028695B1 (en) | PC beam connection structure combined with steel frame or steel pipe column in underground reverse drilling method | |
| JP5201719B2 (en) | Column construction method and column structure | |
| JP7001271B2 (en) | Pile, correction material | |
| CN220767747U (en) | Railway basket arch bridge construction structure with large inclined span longitudinal slope underground double parallel structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060831 |
|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060831 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20081117 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20081125 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090119 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090303 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090325 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120403 Year of fee payment: 3 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 4286737 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130403 Year of fee payment: 4 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140403 Year of fee payment: 5 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |