JP4357639B2 - Schedule creation apparatus and system, and recording medium recording schedule creation program - Google Patents
[go: Go Back, main page]

JP4357639B2 - Schedule creation apparatus and system, and recording medium recording schedule creation program - Google Patents

Schedule creation apparatus and system, and recording medium recording schedule creation program Download PDF

Info

Publication number
JP4357639B2
JP4357639B2 JP17262599A JP17262599A JP4357639B2 JP 4357639 B2 JP4357639 B2 JP 4357639B2 JP 17262599 A JP17262599 A JP 17262599A JP 17262599 A JP17262599 A JP 17262599A JP 4357639 B2 JP4357639 B2 JP 4357639B2
Authority
JP
Japan
Prior art keywords
work
schedule
worker
workers
auditor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP17262599A
Other languages
Japanese (ja)
Other versions
JP2001005859A (en
Inventor
隆生 三好
一郎 道正
賢哲 数井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujitsu FIP Corp
Original Assignee
Fujitsu FIP Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujitsu FIP Corp filed Critical Fujitsu FIP Corp
Priority to JP17262599A priority Critical patent/JP4357639B2/en
Publication of JP2001005859A publication Critical patent/JP2001005859A/en
Application granted granted Critical
Publication of JP4357639B2 publication Critical patent/JP4357639B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、スケジュール作成装置及びシステム並びにスケジュール作成プログラムを記録した記録媒体に係り、特に、所定条件に基づいて複数の作業人が係わるスケジュールを作成するスケジュール作成装置及びシステム並びにスケジュール作成プログラムを記録した記録媒体に関する。
【0002】
【従来の技術】
例えば、複数の作業人が係わるプロジェクト等のスケジュールの作成は、作業人ごとの都合等を考慮して作成する必要がある。また、プロジェクト等によっては、スケジュールの作成時に考慮すべき制約条件を有する場合がある。例えば、考慮すべき制約条件としては、プロジェクト等が有する作業人適格等が該当する。
【0003】
従来、複数の作業人が係わるプロジェクト等のスケジュールの作成は、作業人ごとの都合等を電話,FAX等により収集し、制約条件等を考慮して行われていた。そして、作成されたスケジュールはFAX,郵便等により作業人に届けられていた。
【0004】
【発明が解決しようとする課題】
しかしながら、作業人ごとの都合等を電話,FAX等により収集してスケジュールを作成する場合、作成されたスケジュールを作業人が受け取るまでに相当の時間が経過しており、作業人の都合,プロジェクトの内容等が変わっている場合がある。この場合、再度スケジュールを作成する必要が生じ非常に手間がかかるという問題があった。
【0005】
また、プロジェクト等が有する制約条件が多い場合、制約条件を考慮しつつスケジュールを作成することは非常に手間がかかり、人為的ミスが発生しやすいという問題がある。さらに、作成されたスケジュールがFAX,郵便等により作業人に届けられていたため、作業人は過去に作成されたスケジュールのデータをコンピュータ上で直接利用することができないという問題があった。
【0006】
本発明は、上記の点に鑑みなされたもので、複数の作業人が係わるスケジュールを容易且つ短時間に作成でき、作成されたスケジュールの達成度を管理することができるスケジュール作成装置及びシステム並びにスケジュール作成プログラムを記録した記録媒体を提供することを目的とする。
【0007】
【課題を解決するための手段】
そこで、上記課題を解決するため、請求項1記載の本発明は、決定した作業期間を複数の部署に送信する第1送信手段と、前記複数の部署の作業可能日及び複数の作業人の予定情報を受信する第1受信手段と、前記複数の部署の作業可能日,複数の作業人の予定情報,その作業に基づく作業人適格条件に従ってスケジュールを作成する第1スケジュール作成手段と、前記作成したスケジュールを前記複数の部署に送信する第2送信手段とを有し、前記第1スケジュール作成手段は、複数の作業人から作業人を選択する条件である作業人適格条件として作業人の所属部署及び勤務地を条件テーブルから読み出すと共に、監査人テーブルから所属部署及び勤務地を読み出して比較し、前記複数の作業人から前記所属部署及び勤務地を満たす作業人を選択する選択手段と、前記選択された作業人の予定情報と前記複数の部署の作業可能日との関係に基づき作業を行なう作業予定日及び作業人を設定する設定手段とを有することを特徴とする。
【0008】
このように、第1送信手段,第1受信手段,第1スケジュール作成手段,及び第2送信手段を有することにより、本発明のスケジュール作成装置は決定した作業期間における複数の部署の作業可能日及び複数の作業人の予定情報を短時間で入手することができる。したがって、本発明のスケジュール作成装置は複数の部署の作業可能日,複数の作業人の予定情報,作業人適格条件に従ってスケジュールを容易且つ短時間に作成することが可能である。
【0009】
また、作成したスケジュールを複数の部署に短時間で送信することが可能である。なお、作成したスケジュールの送信先は、複数の所属部署に限ることなく複数の作業人に送信することも可能である。つまり、スケジュール作成に関係する部署及び作業人に適宜送信できる。
また、請求項2記載の本発明は、前記作成したスケジュールに従って作業を行なうことにより生じる作業結果を受信する第2受信手段と、前記作業結果を出力する出力手段とを更に有することを特徴とする。
【0010】
このように、作業結果を受信する第2受信手段と作業結果を出力する出力手段とを有することにより、作成されたスケジュールの進捗状況を的確に把握することができ、作成されたスケジュールの管理が容易になる。
また、請求項3記載の本発明は、前記選択手段は、前記複数の作業人が前回作業を行ったか否かの情報を読み出し、前記複数の作業人のうち、前回作業を行っていない作業人から前記所属部署及び勤務地を満たす作業人を選択することを特徴とする。
【0011】
このように、選択手段及び設定手段を有することにより、スケジュール作成に作業人適格条件を反映することができる。この作業人適格条件としては、例えば作業人の過去の経験,勤務地,職種,職務等の条件が考えられる。したがって、作業人適格条件,作業人の予定情報,複数の部署の作業可能日の関係を考慮した最適なスケジュールを容易に作成できる。
【0012】
また、請求項4記載の本発明は、複数の作業人が係わる作業のスケジュールを作成するスケジュール作成システムにおいて、前記スケジュールを作成/管理する管理部署と前記複数の作業人が所属する複数の部署との間でファイルを送受信する通信手段と、前記作業及び作業人の情報が記録されている第1記録手段と、前記作業の作業人適格条件が記録されている第2記録手段と、前記作業及び作業人の情報,前記作業の作業人適格条件に従ってスケジュールを作成する第2スケジュール作成手段とを有し、前記第2スケジュール作成手段は、複数の作業人から作業人を選択する条件である作業人適格条件として作業人の所属部署及び勤務地を前記第2記録手段から読み出すと共に、第1記録手段から所属部署及び勤務地を読み出して比較し、前記複数の作業人から前記所属部署及び勤務地を満たす作業人を選択する選択手段と、前記選択された作業人の予定情報と前記複数の部署の作業可能日との関係に基づき作業を行なう作業予定日及び作業人を設定する設定手段とを有することを特徴とする。
【0013】
このように、通信手段,第1記録手段,第2記録手段,及び第2スケジュール作成手段を有することにより、本発明のスケジュール作成システムは管理部署と複数の作業人が所属する複数の部署との間でファイルを送受信して、スケジュール作成に必要な情報を収集することができる。したがって、本発明のスケジュール作成システムは、収集した情報,作業及び作業人の情報,作業の作業人適格条件に従ってスケジュールを容易且つ短時間に作成することが可能である。
【0014】
さらに、本発明のスケジュール作成システムは、過去に作成したスケジュール,作業及び作業人の情報,作業の作業人適格条件を管理部署又は複数の作業人が所属する複数の部署等において必要に応じて参照することが可能である。
また、請求項5記載の本発明は、前記選択手段は、前記複数の作業人が前回作業を行ったか否かの情報を読み出し、前記複数の作業人のうち、前回作業を行っていない作業人から前記所属部署及び勤務地を満たす作業人を選択することを特徴とする。
【0015】
このように、本発明のスケジュール作成システムは管理部署と複数の作業人が所属する複数の部署との間でファイルを送受信して、スケジュール作成に必要な情報を順次作成していくことができる。したがって、スケジュール作成に必要な情報を容易且つ短時間に収集することができ、スケジュールを容易且つ短時間に作成することが可能である。
【0016】
また、請求項6記載の本発明は、コンピュータを、決定した作業期間を複数の部署に送信する第1送信手段と、前記複数の部署の作業可能日及び複数の作業人の予定情報を受信する第1受信手段と、前記複数の部署の作業可能日,複数の作業人の予定情報,その作業に基づく作業人適格条件に従ってスケジュールを作成する第1スケジュール作成手段と、前記作成したスケジュールを前記複数の部署に送信する第2送信手段として機能させ、前記第1スケジュール作成手段は、複数の作業人から作業人を選択する条件である作業人適格条件として作業人の所属部署及び勤務地を条件テーブルから読み出すと共に、監査人テーブルから所属部署及び勤務地を読み出して比較し、前記複数の作業人から前記所属部署及び勤務地を満たす作業人を選択する選択手段と、前記選択された作業人の予定情報と前記複数の部署の作業可能日との関係に基づき作業を行なう作業予定日及び作業人を設定する設定手段とを有するように機能させるためのプログラムを記録している。
【0017】
上記の請求項6の記録媒体を使用することにより、請求項1乃至5の発明を実現できる。なお、このプログラムを記録する記録媒体は、CD−ROM、フロッピーディスク、光磁気ディスク(MO)等の様に情報を磁気的に記録する磁気記録媒体、ROM、フラッシュメモリ等の様に情報を電気的に記録する半導体メモリ等、様々なタイプの記録媒体を用いることができる。
【0018】
【発明の実施の形態】
以下に、本発明の実施例を図面に基づいて説明する。なお、本実施例では一例として、企業が行なっている監査のスケジュールを作成する場合について説明する。
監査は、法人の財産状況・業務執行等につき、監督・検査をすることであり、選任された監査人により行われる。監査人の選任は、監査人候補者のリスト(以下、監査人テーブルという)から必要な人数の監査人を選択することにより行われる。なお、監査人の選任には、監査人候補者の予定及び各監査ごとに設定されている監査人の条件のリスト(以下、条件テーブルという)が考慮される。また、監査は、その監査内容,監査場所(例えば、事業部)等に基づいた監査プロジェクトに分類されている。
【0019】
以下、本発明のスケジュール作成装置の構成について図1を参照して説明する。図1は、本発明のスケジュール作成装置を実現するコンピュータシステムの一実施例の構成図を示す。
図1において、このコンピュータシステム10は、それぞれバスBで相互に接続されている入力装置20と,表示装置30と,ドライブ装置40と,記録媒体50と,補助記憶装置60と,メモリ装置70と,演算処理装置80と,印刷装置90と,通信装置100とで構成される。
【0020】
入力装置20は、コンピュータシステム10の使用者が操作するキーボード及びマウス等で構成され、コンピュータシステム10に各種操作信号を入力するために用いられる。表示装置30は、コンピュータシステム10を操作するのに必要な各種ウインドウやデータ等を表示する。
スケジュール作成装置に関するスケジュール作成プログラムは、例えば、CD−ROM等の記録媒体50によって提供される。スケジュール作成プログラムを記録した記録媒体50はドライブ装置40にセットされ、プログラムが記録媒体50からドライブ装置40を介して補助記憶装置60にインストールされる。
【0021】
補助記憶装置60は、インストールされたスケジュール作成プログラムを格納すると共に、必要なファイル,データ等を格納する。メモリ装置70は、コンピュータシステム10の起動時に補助記憶装置60からスケジュール作成プログラムを読み出し、格納する。演算処理装置80は、メモリ装置70に読み出され格納されたスケジュール作成プログラムに従って、スケジュール作成装置に係る処理を実行する。
【0022】
本発明のスケジュール作成装置の処理は、例えば、補助記憶装置60にインストールされたスケジュール作成プログラムがメモリ装置70に読み出され、演算処理装置80により図3,15に示す手順に従って実行される。
次に、本発明のスケジュール作成装置を含むシステムについて図2を参照して説明する。図2は、本発明のスケジュール作成装置を含むシステムの一例の構成図を示す。
【0023】
本発明のスケジュール作成装置1は、監査のスケジュールを作成/管理する管理部署102に設置される。また、スケジュール作成装置1は後述する全社の監査人テーブル112と全社の監査プロジェクトテーブル114とが接続されている。
一方、監査人候補が所属している所属部署(例えば、医療事業部,公共事業部等)104−1〜104nには、端末装置120−1〜120−nが夫々設置されている。また、端末装置120−1〜120−nは、所属部署別監査人テーブル122−1〜122−nと所属部署別監査プロジェクトテーブル124−1〜124−nとが夫々接続されている。なお、所属部署別監査人テーブル122−1〜122−nと所属部署別監査プロジェクトテーブル124−1〜124−nとは、必ずしも所属部署104−1〜104nに設置しておく必要はなく、適宜設置される。
【0024】
本発明のスケジュール作成装置1と端末装置120−1〜120−nとは、ネットワーク網110に接続されており、電子メール等のファイルを送受信することが可能となっている。したがって、電子メール等のファイルを管理部署102及び所属部署104−1〜104−nの間で送受信しながら図3に示す手順に従ってスケジュール作成処理が行われる。
【0025】
図3は、本発明のスケジュール作成装置を含むシステムが実行する処理の一実施例のフローチャートを示す。同図中、ステップS100では、スケジュール作成装置1は決定された監査期間に基づいて初期の全社監査人テーブル112に各監査人候補者の予定情報を入力する欄を追加する。また、スケジュール作成装置1は決定された監査期間に基づいて初期の全社監査プロジェクトテーブル114に各所属部署の監査可能日を入力する欄を追加する。
【0026】
そして、その監査人候補者の予定情報を入力する欄及び各所属部署の監査可能日を入力する欄を追加した全社監査人テーブル及び全社監査プロジェクトテーブルを電子メール等に添付して、端末装置120−1〜120−nに送信する。なお、電子メールに添付されて送信される場合、その電子メールの宛先は各所属部署104−1〜104−nの電子メールアドレスでもよいし、各監査人候補者毎の電子メールアドレスでもよい。つまり、スケジュール作成に関係する部署及び監査人候補者に適宜送信される。
【0027】
ここで、初期の全社監査人テーブル112は、例えば図4に示すように構成される。図4は、初期の全社監査人テーブル112の一例の構成図を示す。初期の全社監査人テーブル112は、例えば監査人番号,所属,監査人氏名,勤務地,監査回数,委員,E−mailアドレス,前回監査有無,今回受審有無等の情報から構成される。
【0028】
また、初期の全社監査プロジェクトテーブル114は、例えば図5に示すように構成される。図5は、初期の全社監査プロジェクトテーブル114の一例の構成図を示す。初期の全社監査プロジェクトテーブル114は、例えば監査番号,所属,プロジェクト名,受審者,リーダの所属,リーダ,サブリーダの所属,サブリーダ,不適合,観察事項等の記載欄及び情報から構成される。
【0029】
ステップS100での処理により、監査人候補者の予定情報を入力する欄及び各所属部署の監査可能日を入力する欄を追加した全社監査人テーブル及び全社監査プロジェクトテーブルは、例えば図6,7に示すように構成される。図6は、予定情報を入力する欄を追加した全社監査人テーブルの一例の構成図を示す。また、図7は監査可能日を入力する欄を追加した全社監査プロジェクトテーブルの一例の構成図を示す。
【0030】
ステップS100に続いてステップS110に進み、各所属部署104−1〜104−nでは、図6に示すような予定情報を入力する欄を追加した全社監査人テーブル及び図7に示すような監査可能日を入力する欄を追加した全社監査プロジェクトテーブルを端末装置120−1〜120−nで受信する。
そして、各所属部署では受信した図6の全社監査人テーブル及び図7の全社監査プロジェクトテーブルの該当箇所に各監査人候補者の予定情報及びその所属部署に関係する監査の監査可能日が入力される。このように、各監査人候補者の予定情報及びその所属部署に関係する監査の監査可能日が入力された全社監査人テーブル及び全社監査プロジェクトテーブルは、例えば図8,9に示すように構成される。図8は、各監査人候補者の予定情報が入力された全社監査人テーブルの一例の構成図を示す。また、図9は監査可能日が入力された全社監査プロジェクトテーブルの一例の構成図を示す。
【0031】
例えば、図8の全社監査人テーブルでは、決定された監査期間が1/21〜1/25であり、監査人番号1のL氏は1/22〜1/24であれば都合が良いことが分かる。また、図9の全社監査プロジェクトテーブルでは、決定された監査期間が1/21〜1/25であり、監査番号1の「□□PRJ」は1/23以外であれば監査が可能であることが分かる。
【0032】
そして、各監査人候補者の予定情報及びその所属部署に関係する監査の監査可能日が入力された全社監査人テーブル及び全社監査プロジェクトテーブルは、電子メール等に添付されてスケジュール作成装置1に送信される。
ステップS110に続いてステップS120に進み、スケジュール作成装置1は受信した図8,9に示すような各監査人候補者の予定情報及びその所属部署に関係する監査の監査可能日が入力された全社監査人テーブル及び全社監査プロジェクトテーブルを利用して後述する処理により監査スケジュールを作成する。
【0033】
スケジュール作成装置1により作成される監査スケジュールは、例えば図10,11に示すように構成される。図10は、監査スケジュールが作成された全社監査人テーブルの一例の構成図を示す。また、図11は監査スケジュールが作成された全社監査プロジェクトテーブルの一例の構成図を示す。
例えば、図10の全社監査人テーブルでは、スケジュール作成装置1により作成された最適なスケジュールに基づいて監査予定日が”●”により表されている。したがって、監査人番号1のL氏は1/23の監査人として選択されていることが分かる。
【0034】
また、図11の全社監査プロジェクトテーブルでは、スケジュール作成装置1により作成された最適なスケジュールに基づいて監査予定日が”●”により表され、各監査プロジェクト毎にリーダ監査人及びサブリーダ監査人が記載されている。例えば、監査番号1の「□□PRJ」は監査予定日が1/21であり、リーダ監査人がH氏,サブリーダ監査人がD氏であることが分かる。
【0035】
このように、監査スケジュールが作成された全社監査人テーブル及び全社監査プロジェクトテーブルは、電子メール等に添付されて端末装置120−1〜120−nに送信される。
ステップS120に続いてステップS130に進み、各所属部署104−1〜104−nでは、受信した図10,11に示すような監査スケジュールが作成された全社監査人テーブル及び全社監査プロジェクトテーブルに従って、監査を行なう。
【0036】
そして、監査結果は例えば図12に示すように、全社監査プロジェクトテーブルの「不適合」,「観察事項」の欄に入力される。図12は、監査結果が入力された全社監査プロジェクトテーブルの一例の構成図を示す。例えば、監査番号1の「□□PRJ」では、監査結果が重度不適合0件,軽度不適合2件,観察事項3件であったことが分かる。このように、監査結果が入力された全社監査プロジェクトテーブルは、電子メール等に添付されてスケジュール作成装置1に送信される。
【0037】
したがって、スケジュール作成装置1は監査結果が入力された全社監査プロジェクトテーブルを受信することにより、必要に応じて監査結果を出力することが可能となる。図13,図14は、監査結果の一例の出力図を示す。
次に、スケジュール作成装置1の処理について更に具体的に説明する。図15は、スケジュール作成装置1が実行する処理の一実施例のフローチャートを示す。同図中、ステップS200では、決定された監査期間に基づいて図4に示す初期の全社監査人テーブル112に各監査人候補者の予定情報を入力する欄を追加する。また、スケジュール作成装置1は決定された監査期間に基づいて図5に示す初期の全社監査プロジェクトテーブル114に各所属部署の監査可能日を入力する欄を追加する。
【0038】
ここで、監査人候補者の予定情報を入力する欄及び各所属部署の監査可能日を入力する欄を追加した全社監査人テーブル及び全社監査プロジェクトテーブルは、例えば図6,7に示すように構成される。
ステップS200に続いてステップS210に進み、スケジュール作成装置1は図6に示すような全社監査人テーブル及び図7に示すような全社監査プロジェクトテーブルを所属部署104−1〜104−nの端末装置120−1〜120−nに送信する。なお、端末装置120−1〜120−nでは前述したステップS110にて説明したように、図6に示すような全社監査人テーブル及び図7に示すような全社監査プロジェクトテーブルの該当箇所に各監査人候補者の予定情報及びその所属部署に関係する監査の監査可能日が入力される。
【0039】
ここで、各監査人候補者の予定情報及びその所属部署に関係する監査の監査可能日が入力された全社監査人テーブル及び全社監査プロジェクトテーブルは、例えば図8,9に示すように構成される。
ステップS210に続いてステップS220に進み、スケジュール作成装置1は、端末装置120−1〜120−nから送信された図8に示すような全社監査人テーブル及び図9に示すような全社監査プロジェクトテーブルを受信する。
【0040】
ステップS220に続いてステップS230に進み、スケジュール作成装置1は、テーブル並び替え条件に従って、図8に示すような全社監査人テーブル及び図9に示すような全社監査プロジェクトテーブルを構成するデータを並び替える。テーブル並び替え条件としては、所属,監査回数,xの数,前回監査有無等に基づいて行われる。なお、図8の全社監査人テーブルでは、所属(昇順),監査回数(昇順),xの数(降順),前回監査有無(昇順)により並び替えが行われている。
【0041】
ステップS230に続いてステップS240に進み、図8の全社監査人テーブルから監査を受ける監査プロジェクトの監査対応者(受審者)を除外する。これは、監査を受ける受審者と監査人とが同一になることを避けるために行われる処理である。
ステップS240に続いてステップS250に進み、スケジュール作成装置1は図16に示すような条件テーブルを例えば補助記憶装置60又はメモリ装置70から読み出す。図16は、条件テーブルの一例の構成図を示す。ここで、条件テーブルとは全社監査人テーブルから監査人を選択する条件のリストである。
【0042】
例えば、図16の条件テーブルでは、医療事業部に関係する監査プロジェクトの監査人は企業事業部,公共事業部,又は産業事業部に所属している必要があることが分かる。また、医療事業部に関係する監査プロジェクトは東京又は神奈川で行なう必要があることが分かる。
ステップS250に続いてステップS260に進み、スケジュール作成装置1は、図9の全社監査プロジェクトテーブルから1件の監査プロジェクトの情報を読み出す。例えば、図9の全社監査プロジェクトテーブルでは、監査番号1の「□□PRJ」が読み出される。
【0043】
ステップS260に続いてステップS270に進み、図9の全社監査プロジェクトテーブルの読み出しが全て終了したか否かを判定する。終了していないと判定すると(S270においてNO)、ステップS280に進む。なお、終了したと判定すると(S270においてYES)、ステップS370に進む。
ステップS280では、図8の全社監査人テーブルから一人の監査人候補者の情報を読み出す。例えば、図9の全社監査人テーブルでは、監査人番号1のL氏が読み出される。ステップS280に続いてステップS290に進み、図8の全社監査人テーブルからの読み出しが全て終了したか否かを判定する。
【0044】
終了していないと判定すると(S290においてNO)、ステップS300に進む。なお、終了したと判定すると(S290においてYES)、ステップS390に進む。
ステップS300では、ステップS280にて読み出した監査人候補者が前回の監査時に監査人に選任されていたか否かを判定する。なお、監査人候補者が前回の監査時に監査人に選任されていたか否かは、図8の前回監査有無の欄に記載されている内容から判断できる。例えば、図8の全社監査人テーブルでは、監査人番号8のG氏は前回の監査時に監査人に選任されていたことが分かる。
【0045】
ステップS280にて読み出した監査人候補者が前回の監査時に監査人に選任されていたと判定すると(S300において有)、ステップS280に進み、次の監査人候補者の情報を読み出す。また、ステップS280にて読み出した監査人候補者が前回の監査時に監査人に選任されていないと判定すると(S300において無)、ステップS310に進む。
【0046】
ステップS310では、図16の条件テーブルを満足しているか否かを判定する。条件を満足していると判定すると(S310においてYES)、ステップS320に進む。条件を満たしていないと判定すると(S310においてNO)、ステップS280に進み、次の監査人候補者の情報を読み出す。
例えば、監査番号1の「□□PRJ」のスケジュールを作成する場合、図16の条件テーブルにより監査人は企業事業部,公共事業部,又は産業事業部に所属している必要がある。また、医療事業部に関係する監査プロジェクトは東京又は神奈川で行なう必要がある。
【0047】
図8の監査人番号1から順番に条件を満たしている監査人候補者を検索していくと、監査人番号1〜6の監査人候補者は企業事業部,公共事業部,又は産業事業部に所属していないので図16の条件テーブルを満足していない。一方、監査人番号7の監査人候補者は企業事業部に所属しており、又、勤務地が東京であるので、図16の条件テーブルを満足していることになる。
【0048】
ステップS320では、ステップS260にて読み出した1件の監査プロジェクトの情報とステップS280にて読み出した一人の監査人候補者の情報とから監査予定日を設定し、図10に示すように該当する日付の”○”を”●”に変更する。また、S320に続いてステップS330に進み、設定した監査予定日に基づいて図11に示すように該当する日付の”○”を”●”に変更する。
【0049】
ステップS330に続いてステップS340に進み、ステップS280にて読み出した一人の監査人候補者の情報から過去に行なった監査回数を読み出す。ここで、図16の条件テーブルによれば過去に行なった監査回数が0回以上,言い換えればサブリーダ監査人になるために過去の監査回数が無関係であることが分かる。また、過去に行なった監査回数が2回以上でなければリーダ監査人になることができないことが分かる。
【0050】
例えば、監査人番号7のD氏は過去に行なった監査回数が0回であり、リーダ監査人になることができないのでサブリーダ監査人に設定する。もちろん、過去に行なった監査回数が2回以上であってもサブリーダ監査人に設定することも可能である。サブリーダ監査人の設定は、図11に示すように該当する所属,サブリーダの欄に情報を入力することにより行われる。
【0051】
ステップS340に続いてステップS350に進み、ステップS280にて読み出した一人の監査人候補者の情報から過去に行なった監査回数を読み出し、図16の条件テーブルに応じてリーダ監査人に設定する。リーダ監査人の設定は、図11に示すように該当する所属,リーダの欄に情報を入力することにより行われる。なお、リーダ監査人及びサブリーダ監査人の設定のどちらを優先するかは適宜設定すれば良い。
【0052】
ステップS350に続いてステップS360に進み、ステップS260にて読み出した1件の監査プロジェクトのリーダ監査人及びサブリーダ監査人の設定が終了したか否かが判定される。リーダ監査人及びサブリーダ監査人の設定が終了していないと判定すると(S360においてNO)、ステップS280に進む。リーダ監査人及びサブリーダ監査人の設定が終了していると判定すると(S360においてYES)、ステップS410に進む。ステップS410では、ステップS260にて読み出した1件の監査プロジェクトのスケジュールが作成済みであることを示す後述の設定を行ない、ステップS260に進む。
【0053】
なお、ステップS270にて図9の全社監査プロジェクトテーブルの読み出しが全て終了したと判定した場合(S270においてYES)、ステップS370では監査スケジュールが作成された図10の全社監査人テーブル及び図11の全社監査プロジェクトテーブルを所属部署104−1〜104−nに送信する。なお、各所属部署104−1〜104−nでは、受信した図10,11の全社監査人テーブル及び全社監査プロジェクトテーブルに従って監査を行ない、その監査結果を例えば図12に示すように全社監査プロジェクトテーブルの「不適合」,「観察事項」の欄に入力する。
【0054】
そして、ステップS370に続いてステップS380に進み、スケジュール作成装置1は各所属部署104−1〜104−nから電子メール等に添付されて送信された図12の全社監査プロジェクトテーブルを受信する。
また、ステップS290にて図8の全社監査人テーブルの読み出しが全て終了したと判定した場合(S290においてYES)、ステップS390では条件を満たすスケジュールの作成ができない旨を表示装置30等に出力する。そして、ステップS390に続いてステップS400に進み、図16の条件テーブルを再設定してステップS250に進む。
【0055】
以上のように、図15のフローチャートによれば、図8の全社監査人テーブル及び図9の全社監査プロジェクトテーブルから最適なスケジュールを作成することが可能である。
次に、本発明では管理部署102と所属部署104−1〜104−nとの間でファイルの送受信が頻繁に行われるため、情報管理に図17,図18に示すテーブルを利用してもよい。
【0056】
図17は、全社監査人管理用テーブルの一例の構成図を示す。また、図18は全社監査プロジェクト管理用テーブルの一例の構成図を示す。図17の全社監査人管理用テーブル及び図18の全社監査プロジェクト管理用テーブルは、管理部署102から所属部署104−1〜104−nに通知が済んだときにその旨を表示する欄,所属部署104−1〜104−nから管理部署102に通知が済んだときにその旨を表示する欄,スケジュールの作成が終了したときにその旨を表示する欄等から構成される。
【0057】
したがって、スケジュール作成のための情報の収集状況が的確に把握できると供に、必要な通知等を忘れずに送付することができる。なお、監査スケジュールの作成においては、監査の進捗情報を容易に把握できると供に、監査のスケジュール管理が容易になる。
なお、特許請求の範囲に記載した第1送信手段はステップS210での処理に対応し、第1受信手段はステップS220での処理に対応し、第1スケジュール作成手段はステップS230〜S360,S390〜410での処理に対応し、第2送信手段はステップS370での処理に対応し、第2受信手段はステップS380での処理に対応し、出力手段は表示装置30,印刷装置90に対応し、選択手段はステップS310での処理に対応し、設定手段はステップS320,330での処理に対応し、通信手段は通信装置100,端末装置120−1〜120−nに対応し、第1記録手段は全社監査人テーブル112及び全社監査プロジェクトテーブル114に対応し、第2記録手段はステップS250での処理に対応し、第2スケジュール作成手段はステップS120での処理に対応する。
【0058】
【発明の効果】
上述の如く、請求項1記載の本発明によれば、第1送信手段,第1受信手段,第1スケジュール作成手段,及び第2送信手段を有することにより、本発明のスケジュール作成装置は決定した作業期間における複数の部署の作業可能日及び複数の作業人の予定情報を短時間で入手することができる。したがって、本発明のスケジュール作成装置は複数の部署の作業可能日,複数の作業人の予定情報,作業人適格条件に従ってスケジュールを容易且つ短時間に作成することが可能である。
【0059】
また、作成したスケジュールを複数の部署に短時間で送信することが可能である。なお、作成したスケジュールの送信先は、複数の所属部署に限ることなく複数の作業人に送信することも可能である。つまり、スケジュール作成に関係する部署及び作業人に適宜送信できる。
また、請求項2記載の本発明によれば、作業結果を受信する第2受信手段と作業結果を出力する出力手段とを有することにより、作成されたスケジュールの進捗状況を的確に把握することができ、作成されたスケジュールの管理が容易になる。
【0060】
また、請求項3記載の本発明によれば、選択手段及び設定手段を有することにより、スケジュール作成に作業人適格条件を反映することができる。この作業人適格条件としては、例えば作業人の過去の経験,勤務地,職種,職務等の条件が考えられる。したがって、作業人適格条件,作業人の予定情報,複数の部署の作業可能日の関係を考慮した最適なスケジュールを容易に作成できる。
【0061】
また、請求項4記載の本発明によれば、通信手段,第1記録手段,第2記録手段,及び第2スケジュール作成手段を有することにより、本発明のスケジュール作成システムは管理部署と複数の作業人が所属する複数の部署との間でファイルを送受信して、スケジュール作成に必要な情報を収集することができる。したがって、本発明のスケジュール作成システムは、収集した情報,作業及び作業人の情報,作業の作業人適格条件に従ってスケジュールを容易且つ短時間に作成することが可能である。
【0062】
さらに、本発明のスケジュール作成システムは、過去に作成したスケジュール,作業及び作業人の情報,作業の作業人適格条件を管理部署又は複数の作業人が所属する複数の部署等において必要に応じて参照することが可能である。
また、請求項5記載の本発明によれば、本発明のスケジュール作成システムは管理部署と複数の作業人が所属する複数の部署との間でファイルを送受信して、スケジュール作成に必要な情報を順次作成していくことができる。したがって、スケジュール作成に必要な情報を容易且つ短時間に収集することができ、スケジュールを容易且つ短時間に作成することが可能である。
【0063】
また、請求項6記載の本発明によれば、コンピュータを、決定した作業期間を複数の部署に送信する第1送信手段と、前記複数の部署の作業可能日及び複数の作業人の予定情報を受信する第1受信手段と、前記複数の部署の作業可能日,複数の作業人の予定情報,その作業に基づく作業人適格条件に従ってスケジュールを作成する第1スケジュール作成手段と、前記作成したスケジュールを前記複数の部署に送信する第2送信手段と、前記作成したスケジュールに従って作業を行なうことにより生じる作業結果を受信する第2受信手段と、前記作業結果を出力する出力手段として機能させるためのプログラムを記録している。
【0064】
上記の請求項6の記録媒体を使用することにより、請求項1乃至5の発明を実現できる。なお、このプログラムを記録する記録媒体は、CD−ROM、フロッピーディスク、光磁気ディスク(MO)等の様に情報を磁気的に記録する磁気記録媒体、ROM、フラッシュメモリ等の様に情報を電気的に記録する半導体メモリ等、様々なタイプの記録媒体を用いることができる。
【図面の簡単な説明】
【図1】本発明のスケジュール作成装置を実現するコンピュータシステムの一実施例の構成図である。
【図2】本発明のスケジュール作成装置を含むシステムの一例の構成図である。
【図3】本発明のスケジュール作成装置を含むシステムが実行する処理の一実施例のフローチャートである。
【図4】初期の全社監査人テーブルの一例の構成図である。
【図5】初期の全社監査プロジェクトテーブルの一例の構成図である。
【図6】予定情報を入力する欄を追加した全社監査人テーブルの一例の構成図である。
【図7】監査可能日を入力する欄を追加した全社監査プロジェクトテーブルの一例の構成図である。
【図8】各監査人候補者の予定情報が入力された全社監査人テーブルの一例の構成図である。
【図9】監査可能日が入力された全社監査プロジェクトテーブルの一例の構成図である。
【図10】監査スケジュールが作成された全社監査人テーブルの一例の構成図である。
【図11】監査スケジュールが作成された全社監査プロジェクトテーブルの一例の構成図である。
【図12】監査結果が入力された全社監査プロジェクトテーブルの一例の構成図である。
【図13】監査結果の一例の出力図である。
【図14】監査結果の一例の出力図である。
【図15】スケジュール作成装置が実行する処理の一実施例のフローチャートである。
【図16】条件テーブルの一例の構成図である。
【図17】全社監査人管理用テーブルの一例の構成図である。
【図18】全社監査プロジェクト管理用テーブルの一例の構成図である。
【符号の説明】
1 スケジュール作成装置
10 コンピュータシステム
20 入力装置
30 表示装置
40 ドライブ装置
50 記録媒体
60 補助記憶装置
70 メモリ装置
80 演算処理装置
90 印刷装置
100 通信装置
102 管理部署
104−1〜104−n 所属部署
110 ネットワーク網
112 全社監査人テーブル
114 全社監査プロジェクトテーブル
120−1〜120−n 端末装置
122−1〜122−n 所属部署別監査人テーブル
124−1〜124−n 所属部署別監査プロジェクトテーブル
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a schedule creation device and system, and a recording medium on which a schedule creation program is recorded, and in particular, a schedule creation device and system for creating a schedule related to a plurality of workers based on a predetermined condition and a schedule creation program are recorded. The present invention relates to a recording medium.
[0002]
[Prior art]
For example, a schedule for a project involving a plurality of workers needs to be created in consideration of the convenience of each worker. Further, depending on the project or the like, there may be a constraint condition to be considered when creating a schedule. For example, the constraint condition to be considered corresponds to the worker qualification that the project has.
[0003]
Conventionally, the creation of a schedule for a project involving a plurality of workers, etc., has been performed in consideration of constraints and the like by collecting the convenience of each worker by telephone, FAX, or the like. The created schedule was delivered to the worker by FAX, mail or the like.
[0004]
[Problems to be solved by the invention]
However, when a schedule is created by collecting the circumstances of each worker by telephone, FAX, etc., a considerable amount of time has passed before the worker receives the created schedule. The contents may have changed. In this case, there is a problem that it is necessary to create a schedule again, which is very time-consuming.
[0005]
In addition, when there are many constraint conditions of a project or the like, it is very troublesome to create a schedule while considering the constraint conditions, and there is a problem that human error is likely to occur. Furthermore, since the created schedule is delivered to the worker by FAX, mail or the like, there is a problem that the worker cannot directly use the schedule data created in the past on the computer.
[0006]
The present invention has been made in view of the above points. A schedule creation apparatus and system that can easily create a schedule related to a plurality of workers in a short time and can manage the degree of achievement of the created schedule, and the schedule It is an object of the present invention to provide a recording medium on which a creation program is recorded.
[0007]
[Means for Solving the Problems]
Accordingly, in order to solve the above-mentioned problem, the present invention according to claim 1 is a first transmission means for transmitting the determined work period to a plurality of departments, work days of the plurality of departments, and schedules of a plurality of workers. A first receiving means for receiving information; a first schedule creating means for creating a schedule according to work days of the plurality of departments; schedule information of a plurality of workers; and worker eligibility conditions based on the work; A second transmission means for transmitting the schedule to the plurality of departments; The first schedule creation means reads out the department and work location of the worker from the condition table as a worker qualification condition that is a condition for selecting a worker from a plurality of workers, A selection means for reading out and comparing a work location, selecting a worker satisfying the department and work location from the plurality of workers, schedule information of the selected worker, and work possible dates of the plurality of departments And setting means for setting the scheduled work date and worker to perform work based on It is characterized by doing.
[0008]
Thus, by having the first transmission means, the first reception means, the first schedule creation means, and the second transmission means, the schedule creation device of the present invention can perform work days and days of a plurality of departments in the determined work period. Schedule information of a plurality of workers can be obtained in a short time. Therefore, the schedule creation device of the present invention can create a schedule easily and in a short time according to work days of a plurality of departments, schedule information of a plurality of workers, and worker eligibility conditions.
[0009]
In addition, the created schedule can be transmitted to a plurality of departments in a short time. The transmission destination of the created schedule is not limited to a plurality of departments, and can be transmitted to a plurality of workers. That is, it can be appropriately transmitted to a department and a worker who are involved in schedule creation.
The present invention according to claim 2 further includes second receiving means for receiving work results generated by performing work according to the created schedule, and output means for outputting the work results. .
[0010]
Thus, by having the second receiving means for receiving the work result and the output means for outputting the work result, the progress of the created schedule can be accurately grasped, and the created schedule can be managed. It becomes easy.
Further, the present invention described in claim 3 The selection means reads information on whether or not the plurality of workers performed the previous work, and among the plurality of workers, a worker who satisfies the belonging department and work place from a worker who has not performed the previous work. Select It is characterized by that.
[0011]
As described above, by including the selection unit and the setting unit, it is possible to reflect worker qualification conditions in schedule creation. As the worker eligibility conditions, for example, conditions such as the worker's past experience, place of work, type of job, and duties can be considered. Therefore, it is possible to easily create an optimal schedule that takes into consideration the relationship between worker eligibility conditions, worker schedule information, and work availability dates of a plurality of departments.
[0012]
According to a fourth aspect of the present invention, in a schedule creation system for creating a schedule of work involving a plurality of workers, a management department that creates / manages the schedule, a plurality of departments to which the plurality of workers belong, Communication means for transmitting and receiving files between the first recording means, the first recording means in which information of the work and the worker is recorded, the second recording means in which the worker eligibility condition of the work is recorded, the work and A second schedule creation means for creating a schedule according to the worker information and the worker eligibility conditions for the work; The second schedule creating means reads out the department and work location of the worker from the second recording means as the worker qualification condition which is a condition for selecting a worker from a plurality of workers, and the first recording means A selection means for selecting a worker satisfying the belonging department and work location from the plurality of workers, schedule information of the selected worker, and the plurality of departments There is a setting means to set the scheduled work date and the worker to perform work based on the relationship with the work day. It is characterized by doing.
[0013]
As described above, by having the communication means, the first recording means, the second recording means, and the second schedule creation means, the schedule creation system of the present invention has a management department and a plurality of departments to which a plurality of workers belong. Send and receive files between them to collect the information needed to create a schedule. Therefore, the schedule creation system of the present invention can create a schedule easily and in a short time according to the collected information, work and worker information, and worker qualification conditions.
[0014]
Furthermore, the schedule creation system of the present invention refers to schedules created in the past, work and worker information, and worker qualification conditions as necessary in a management department or a plurality of departments to which a plurality of workers belong. Is possible.
Further, the present invention according to claim 5 provides: The selection means reads information on whether or not the plurality of workers performed the previous work, and among the plurality of workers, a worker who satisfies the belonging department and work place from a worker who has not performed the previous work. choose It is characterized by doing.
[0015]
Thus, the schedule creation system of the present invention can sequentially create information necessary for schedule creation by transmitting and receiving files between a management department and a plurality of departments to which a plurality of workers belong. Therefore, information necessary for creating a schedule can be collected easily and in a short time, and a schedule can be created easily and in a short time.
[0016]
According to a sixth aspect of the present invention, the computer receives the first transmission means for transmitting the determined work period to a plurality of departments, work availability dates of the plurality of departments, and schedule information of a plurality of workers. First receiving means, first schedule creation means for creating a schedule according to work availability dates of the plurality of departments, schedule information of a plurality of workers, worker qualification conditions based on the work, and the created schedules Function as the second transmission means to send to The first schedule creation means reads out the department and work location of the worker from the condition table as a worker qualification condition that is a condition for selecting a worker from a plurality of workers, and also belongs to the department and work from the auditor table. A selection means for selecting a worker satisfying the department and work location from among the plurality of workers, reading out and comparing the locations, schedule information of the selected workers, and work days available for the plurality of departments And a setting means for setting a scheduled work date and a worker to perform work based on the relationship. The program to make it function is recorded.
[0017]
By using the recording medium of the sixth aspect, the inventions of the first to fifth aspects can be realized. The recording medium for recording this program is a magnetic recording medium for recording information magnetically, such as a CD-ROM, floppy disk, magneto-optical disk (MO), etc., a ROM, a flash memory, etc. Various types of recording media, such as a semiconductor memory for recording data, can be used.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings. In this embodiment, as an example, a case of creating a schedule for an audit performed by a company will be described.
The audit is to supervise and inspect the corporate property status, business execution, etc., and is conducted by a designated auditor. Auditors are selected by selecting a required number of auditors from a list of auditor candidates (hereinafter referred to as an auditor table). In selecting auditors, a schedule of auditor candidates and a list of auditor conditions set for each audit (hereinafter referred to as a condition table) are considered. Audits are classified into audit projects based on the audit content, audit location (for example, business division), and the like.
[0019]
The configuration of the schedule creation device of the present invention will be described below with reference to FIG. FIG. 1 shows a configuration diagram of an embodiment of a computer system that implements the schedule creation device of the present invention.
In FIG. 1, the computer system 10 includes an input device 20, a display device 30, a drive device 40, a recording medium 50, an auxiliary storage device 60, and a memory device 70 that are connected to each other via a bus B. , An arithmetic processing unit 80, a printing unit 90, and a communication unit 100.
[0020]
The input device 20 includes a keyboard and a mouse that are operated by a user of the computer system 10 and is used to input various operation signals to the computer system 10. The display device 30 displays various windows and data necessary for operating the computer system 10.
A schedule creation program related to the schedule creation device is provided by a recording medium 50 such as a CD-ROM, for example. The recording medium 50 on which the schedule creation program is recorded is set in the drive device 40, and the program is installed from the recording medium 50 to the auxiliary storage device 60 via the drive device 40.
[0021]
The auxiliary storage device 60 stores the installed schedule creation program and stores necessary files, data, and the like. The memory device 70 reads and stores the schedule creation program from the auxiliary storage device 60 when the computer system 10 is activated. The arithmetic processing device 80 executes processing related to the schedule creation device in accordance with the schedule creation program read and stored in the memory device 70.
[0022]
The processing of the schedule creation device of the present invention is executed, for example, by a schedule creation program installed in the auxiliary storage device 60 being read into the memory device 70 and executed by the arithmetic processing device 80 according to the procedure shown in FIGS.
Next, a system including the schedule creation device of the present invention will be described with reference to FIG. FIG. 2 shows a configuration diagram of an example of a system including the schedule creation device of the present invention.
[0023]
The schedule creation apparatus 1 of the present invention is installed in a management department 102 that creates / manages an audit schedule. Further, the schedule creation device 1 is connected to a company-wide auditor table 112 and a company-wide audit project table 114 described later.
On the other hand, terminal devices 120-1 to 120-n are installed in the departments (for example, medical business department, public business department, etc.) 104-1 to 104n to which the auditor candidate belongs, respectively. The terminal devices 120-1 to 120-n are connected to the department-by-affiliation department auditor tables 122-1 to 122-n and the department-to-affiliation department audit project tables 124-1 to 124-n, respectively. The department-specific auditor tables 122-1 to 122-n and the department-specific audit project tables 124-1 to 124-n are not necessarily installed in the departments 104-1 to 104n. Installed.
[0024]
The schedule creation device 1 and the terminal devices 120-1 to 120-n of the present invention are connected to the network 110 and can send and receive files such as e-mails. Therefore, a schedule creation process is performed according to the procedure shown in FIG. 3 while transmitting / receiving a file such as an electronic mail between the management department 102 and the departments 104-1 to 104-n.
[0025]
FIG. 3 shows a flowchart of an embodiment of processing executed by a system including the schedule creation device of the present invention. In the figure, in step S100, the schedule creation device 1 adds a column for inputting schedule information of each auditor candidate to the initial company-wide auditor table 112 based on the determined audit period. Also, the schedule creation device 1 adds a column for inputting the auditable date of each department to the initial company-wide audit project table 114 based on the determined audit period.
[0026]
Then, a company-wide auditor table and a company-wide audit project table to which a column for inputting schedule information of the auditor candidate and a column for inputting the auditable date of each department are added are attached to an e-mail or the like, and the terminal device 120 -1 to 120-n. In the case of being sent as an attachment to an e-mail, the e-mail destination may be the e-mail address of each department 104-1 to 104-n, or the e-mail address of each auditor candidate. That is, it is appropriately transmitted to the department and auditor candidate related to schedule creation.
[0027]
Here, the initial company-wide auditor table 112 is configured as shown in FIG. 4, for example. FIG. 4 shows a configuration diagram of an example of the initial corporate auditor table 112. The initial company-wide auditor table 112 includes, for example, information such as an auditor number, affiliation, auditor name, work location, number of audits, committee member, e-mail address, previous audit status, current audit status.
[0028]
The initial company-wide audit project table 114 is configured as shown in FIG. 5, for example. FIG. 5 shows a configuration diagram of an example of the initial company-wide audit project table 114. The initial company-wide audit project table 114 includes, for example, description columns and information such as an audit number, affiliation, project name, auditor, reader affiliation, leader, sub-leader affiliation, sub-leader, nonconformity, and observation items.
[0029]
The company-wide auditor table and company-wide audit project table to which a column for inputting schedule information of auditor candidates and a column for inputting the auditable date of each department are added by the processing in step S100 are shown in FIGS. Configured as shown. FIG. 6 shows a configuration diagram of an example of the company auditor table to which a column for inputting schedule information is added. FIG. 7 shows a configuration diagram of an example of a company-wide audit project table to which a column for inputting an auditable date is added.
[0030]
Progressing to step S110 following step S100, each department 104-1 to 104-n can perform auditing as shown in FIG. 7 and a company-wide auditor table to which a column for inputting schedule information as shown in FIG. 6 is added. The company-wide audit project table to which the column for inputting the date is added is received by the terminal devices 120-1 to 120-n.
In each department, the schedule information of each auditor candidate and the auditable date related to the department to which the candidate belongs are entered in the corresponding locations in the company-wide auditor table shown in FIG. 6 and the company-wide audit project table shown in FIG. The As described above, the company-wide auditor table and the company-wide audit project table in which the schedule information of each auditor candidate and the auditable date related to the department to which the auditor belongs are input are configured as shown in FIGS. The FIG. 8 shows a configuration diagram of an example of a company-wide auditor table in which schedule information of each auditor candidate is input. FIG. 9 is a block diagram showing an example of a company-wide audit project table in which the auditable date is input.
[0031]
For example, in the company-wide auditor table of FIG. 8, it is convenient if the determined audit period is 1/21 to 1/25, and Mr. L of the auditor number 1 is 1/22 to 1/24. I understand. Further, in the company-wide audit project table of FIG. 9, the determined audit period is 1/21 to 1/25, and auditing is possible if “□□ PRJ” of audit number 1 is other than 1/23. I understand.
[0032]
The company-wide auditor table and company-wide audit project table in which the auditable date of each auditor candidate's schedule information and audits related to the department to which the audit candidate is entered are attached to an e-mail or the like and sent to the schedule creation device 1 Is done.
Progressing to step S120 following step S110, the schedule creation device 1 receives the schedule information of each auditor candidate received as shown in FIGS. 8 and 9 and the auditable date of audit related to the department to which the schedule is created. An audit schedule is created by the process described later using the auditor table and the company-wide audit project table.
[0033]
The audit schedule created by the schedule creation device 1 is configured as shown in FIGS. FIG. 10 shows a configuration diagram of an example of a company-wide auditor table in which an audit schedule is created. FIG. 11 is a block diagram showing an example of a company-wide audit project table in which an audit schedule is created.
For example, in the company-wide auditor table of FIG. 10, the scheduled audit date is represented by “●” based on the optimum schedule created by the schedule creation device 1. Therefore, it can be seen that Mr. L of the auditor number 1 is selected as 1/23 auditor.
[0034]
Further, in the company-wide audit project table of FIG. 11, the scheduled audit date is represented by “●” based on the optimum schedule created by the schedule creation device 1, and the leader auditor and the sub-leader auditor are described for each audit project. Has been. For example, “□□ PRJ” of audit number 1 has a scheduled audit date of 1/21, and it can be seen that the leader auditor is Mr. H and the sub-leader auditor is Mr. D.
[0035]
In this way, the company-wide auditor table and company-wide audit project table for which an audit schedule has been created are attached to e-mails and transmitted to the terminal devices 120-1 to 120-n.
Progressing to step S130 following step S120, each department 104-1 to 104-n performs auditing according to the received company-wide auditor table and company-wide audit project table in which the audit schedule as shown in FIGS. To do.
[0036]
Then, for example, as shown in FIG. 12, the audit result is input to the “nonconformity” and “observation items” columns of the company-wide audit project table. FIG. 12 shows a configuration diagram of an example of a company-wide audit project table in which audit results are input. For example, in the audit number “□□ PRJ”, it can be seen that the audit results were 0 non-conformities, 2 non-conformities, and 3 observations. Thus, the company-wide audit project table in which the audit result is input is attached to an e-mail or the like and transmitted to the schedule creation device 1.
[0037]
Therefore, the schedule creation device 1 can output the audit result as necessary by receiving the company-wide audit project table in which the audit result is input. 13 and 14 show output diagrams of examples of audit results.
Next, the process of the schedule creation device 1 will be described more specifically. FIG. 15 is a flowchart illustrating an example of processing executed by the schedule creation device 1. In the figure, in step S200, a column for inputting schedule information of each auditor candidate is added to the initial company-wide auditor table 112 shown in FIG. 4 based on the determined audit period. Also, the schedule creation device 1 adds a column for inputting the auditable date of each department to the initial company-wide audit project table 114 shown in FIG. 5 based on the determined audit period.
[0038]
Here, the company-wide auditor table and the company-wide audit project table to which a column for inputting schedule information of auditor candidates and a field for inputting the auditable date of each department are added are configured as shown in FIGS. Is done.
Progressing to step S210 following step S200, the schedule creation apparatus 1 stores the company-wide auditor table as shown in FIG. 6 and the company-wide audit project table as shown in FIG. -1 to 120-n. In the terminal devices 120-1 to 120-n, as described in step S110 described above, each audit is performed at a corresponding place in the company-wide auditor table as shown in FIG. 6 and the company-wide audit project table as shown in FIG. The schedule information of the candidate and the auditable date related to the department to which the candidate belongs are entered.
[0039]
Here, the company-wide auditor table and the company-wide audit project table in which the schedule information of each auditor candidate and the auditable date related to the department to which the auditor belongs are input are configured as shown in FIGS. .
Progressing to step S220 following step S210, the schedule creation device 1 transmits the company-wide auditor table as shown in FIG. 8 and the company-wide audit project table as shown in FIG. 9 transmitted from the terminal devices 120-1 to 120-n. Receive.
[0040]
Progressing to step S230 following step S220, the schedule creation device 1 rearranges the data constituting the company-wide auditor table as shown in FIG. 8 and the company-wide audit project table as shown in FIG. 9 according to the table rearrangement condition. . The table sorting condition is performed based on the affiliation, the number of audits, the number of x, the presence / absence of the previous audit, and the like. In the company-wide auditor table of FIG. 8, the sorting is performed according to affiliation (ascending order), number of audits (ascending order), number of x (descending order), and presence / absence of previous audit (ascending order).
[0041]
Progressing to step S240 following step S230, the audit responder (auditor) of the audit project to be audited is excluded from the companywide auditor table of FIG. This is a process performed to avoid the auditee being audited and the auditor being the same.
Progressing to step S250 following step S240, the schedule creation device 1 reads a condition table as shown in FIG. 16 from, for example, the auxiliary storage device 60 or the memory device. FIG. 16 shows a configuration diagram of an example of a condition table. Here, the condition table is a list of conditions for selecting an auditor from the company-wide auditor table.
[0042]
For example, in the condition table of FIG. 16, it can be seen that an auditor of an audit project related to the medical business department needs to belong to the corporate business department, the public business department, or the industrial business department. It can also be seen that audit projects related to the Medical Division need to be conducted in Tokyo or Kanagawa.
Progressing to step S260 following step S250, the schedule creation device 1 reads information on one audit project from the company-wide audit project table of FIG. For example, in the company-wide audit project table of FIG. 9, “□□ PRJ” with audit number 1 is read.
[0043]
Progressing to step S270 following step S260, it is determined whether all reading of the company-wide audit project table in FIG. 9 has been completed. If it is determined that the process has not been completed (NO in S270), the process proceeds to step S280. If it is determined that the process has been completed (YES in S270), the process proceeds to step S370.
In step S280, information on one auditor candidate is read from the companywide auditor table of FIG. For example, in the companywide auditor table of FIG. 9, Mr. L with auditor number 1 is read. Progressing to step S290 following step S280, it is determined whether or not all the reading from the corporate auditor table of FIG. 8 has been completed.
[0044]
If it is determined that the process has not been completed (NO in S290), the process proceeds to step S300. If it is determined that the process has been completed (YES in S290), the process proceeds to step S390.
In step S300, it is determined whether the auditor candidate read in step S280 has been appointed by the auditor at the previous audit. Whether or not the auditor candidate has been appointed as the auditor at the previous audit can be determined from the contents described in the column of whether or not the previous audit is performed in FIG. For example, in the company-wide auditor table of FIG. 8, it can be seen that Mr. G with auditor number 8 was appointed as the auditor at the time of the previous audit.
[0045]
If it is determined that the auditor candidate read in step S280 has been appointed as an auditor at the time of the previous audit (Yes in S300), the process proceeds to step S280, and information on the next auditor candidate is read. If it is determined that the auditor candidate read in step S280 is not appointed as the auditor at the previous audit (no in S300), the process proceeds to step S310.
[0046]
In step S310, it is determined whether the condition table of FIG. 16 is satisfied. If it is determined that the condition is satisfied (YES in S310), the process proceeds to step S320. If it is determined that the condition is not satisfied (NO in S310), the process proceeds to step S280, and information on the next auditor candidate is read.
For example, when creating a schedule of “□□ PRJ” of audit number 1, the auditor needs to belong to the corporate business department, public business department, or industrial business department according to the condition table of FIG. In addition, audit projects related to the Medical Division need to be conducted in Tokyo or Kanagawa.
[0047]
When searching for auditor candidates who satisfy the conditions in order from auditor number 1 in FIG. 8, the auditor candidates of auditor numbers 1 to 6 are enterprise division, public division, or industrial division. 16 does not satisfy the condition table of FIG. On the other hand, the auditor candidate of the auditor number 7 belongs to the corporate division and the work place is Tokyo, so the condition table of FIG. 16 is satisfied.
[0048]
In step S320, the scheduled audit date is set from the information of one audit project read out in step S260 and the information of one auditor candidate read out in step S280, and the corresponding date as shown in FIG. Change “○” to “●”. Further, following S320, the process proceeds to step S330, where “◯” of the corresponding date is changed to “●” as shown in FIG. 11 based on the set scheduled audit date.
[0049]
Progressing to step S340 following step S330, the number of audits performed in the past is read from the information of one auditor candidate read in step S280. Here, according to the condition table of FIG. 16, it can be seen that the number of audits performed in the past is 0 or more, in other words, the number of past audits is irrelevant in order to become a sublead auditor. Further, it can be seen that a leader auditor cannot be performed unless the number of audits performed in the past is two or more.
[0050]
For example, Mr. D of auditor number 7 has set the number of audits performed in the past as 0 and cannot be a leader auditor, and is set as a sub leader auditor. Of course, even if the number of audits performed in the past is two or more, it can be set as a sub-leader auditor. The setting of the sub-leader auditor is performed by inputting information in the corresponding affiliation and sub-leader fields as shown in FIG.
[0051]
Progressing to step S350 following step S340, the number of audits performed in the past is read out from the information of one auditor candidate read out in step S280, and set as a leader auditor according to the condition table of FIG. As shown in FIG. 11, setting of the leader auditor is performed by inputting information in the corresponding affiliation and leader fields. It should be noted that which of the settings of the leader auditor and the sub-leader auditor is to be prioritized may be appropriately set.
[0052]
Progressing to step S360 following step S350, it is determined whether or not the setting of the leader auditor and the sub-leader auditor of one audit project read in step S260 is completed. If it is determined that the settings of the leader auditor and the subleader auditor have not been completed (NO in S360), the process proceeds to step S280. If it is determined that the settings of the leader auditor and the sub-leader auditor have been completed (YES in S360), the process proceeds to step S410. In step S410, the setting which will be described later indicating that the schedule of one audit project read in step S260 has been created is performed, and the process proceeds to step S260.
[0053]
If it is determined in step S270 that all of the reading of the company-wide audit project table in FIG. 9 has been completed (YES in S270), in step S370, the company-wide auditor table in FIG. The audit project table is transmitted to the departments 104-1 to 104-n to which the audit project table belongs. Each department 104-1 to 104-n performs an audit according to the received company-wide auditor table and company-wide audit project table in FIGS. 10 and 11, and the audit results are shown in FIG. 12, for example, as shown in FIG. In the “Nonconformity” and “Observation Items” fields.
[0054]
Then, the process proceeds to step S380 following step S370, and the schedule creation device 1 receives the company-wide audit project table of FIG. 12 transmitted from each of the departments 104-1 to 104-n attached to an e-mail or the like.
If it is determined in step S290 that all reading of the company-wide auditor table in FIG. 8 has been completed (YES in S290), in step S390, a message indicating that a schedule that satisfies the condition cannot be created is output to the display device 30 or the like. Then, following step S390, the process proceeds to step S400, the condition table of FIG. 16 is reset, and the process proceeds to step S250.
[0055]
As described above, according to the flowchart of FIG. 15, it is possible to create an optimal schedule from the companywide auditor table of FIG. 8 and the companywide audit project table of FIG.
Next, in the present invention, since files are frequently transmitted and received between the management department 102 and the departments 104-1 to 104-n, the tables shown in FIGS. 17 and 18 may be used for information management. .
[0056]
FIG. 17 shows a configuration diagram of an example of the company auditor management table. FIG. 18 is a block diagram showing an example of a company audit project management table. The company-wide auditor management table in FIG. 17 and the company-wide audit project management table in FIG. 18 are a column for displaying that when the management department 102 has notified the departments 104-1 to 104-n. This is composed of a column for displaying the notification when the management department 102 has been notified from 104-1 to 104-n, a column for displaying that when the creation of the schedule is completed, and the like.
[0057]
Therefore, it is possible to send a necessary notification and the like without forgetting that the collection status of information for creating a schedule can be accurately grasped. In creating an audit schedule, the audit progress can be easily managed and the audit schedule can be easily managed.
The first transmission means described in the claims corresponds to the process in step S210, the first reception means corresponds to the process in step S220, and the first schedule creation means corresponds to steps S230 to S360, S390. Corresponding to the processing at 410, the second transmission means corresponds to the processing at step S370, the second receiving means corresponds to the processing at step S380, the output means corresponds to the display device 30 and the printing device 90, The selection means corresponds to the processing in step S310, the setting means corresponds to the processing in steps S320 and 330, the communication means corresponds to the communication device 100 and the terminal devices 120-1 to 120-n, and the first recording means. Corresponds to the company-wide auditor table 112 and company-wide audit project table 114, and the second recording means corresponds to the processing in step S250, and the second schedule Creating means corresponds to the processing in step S120.
[0058]
【The invention's effect】
As described above, according to the first aspect of the present invention, the schedule creation device of the present invention is determined by having the first transmission means, the first reception means, the first schedule creation means, and the second transmission means. Workable days of a plurality of departments during a work period and schedule information of a plurality of workers can be obtained in a short time. Therefore, the schedule creation device of the present invention can create a schedule easily and in a short time according to work days of a plurality of departments, schedule information of a plurality of workers, and worker eligibility conditions.
[0059]
In addition, the created schedule can be transmitted to a plurality of departments in a short time. The transmission destination of the created schedule is not limited to a plurality of departments, and can be transmitted to a plurality of workers. That is, it can be appropriately transmitted to a department and a worker who are involved in schedule creation.
According to the second aspect of the present invention, it is possible to accurately grasp the progress status of the created schedule by including the second receiving means for receiving the work result and the output means for outputting the work result. This makes it easy to manage the created schedule.
[0060]
According to the third aspect of the present invention, since the selection means and the setting means are provided, the worker eligibility conditions can be reflected in the schedule creation. As the worker eligibility conditions, for example, conditions such as the worker's past experience, place of work, type of job, and duties can be considered. Therefore, it is possible to easily create an optimal schedule that takes into consideration the relationship between worker eligibility conditions, worker schedule information, and work availability dates of a plurality of departments.
[0061]
According to the fourth aspect of the present invention, the schedule creation system of the present invention includes a communication section, a first recording means, a second recording means, and a second schedule creation means. Information necessary for schedule creation can be collected by sending and receiving files to and from multiple departments to which people belong. Therefore, the schedule creation system of the present invention can create a schedule easily and in a short time according to the collected information, work and worker information, and worker qualification conditions.
[0062]
Furthermore, the schedule creation system of the present invention refers to schedules created in the past, work and worker information, and worker qualification conditions as necessary in a management department or a plurality of departments to which a plurality of workers belong. Is possible.
According to the present invention as set forth in claim 5, the schedule creation system of the present invention transmits and receives files between a management department and a plurality of departments to which a plurality of workers belong to obtain information necessary for schedule creation. Can be created sequentially. Therefore, information necessary for creating a schedule can be collected easily and in a short time, and a schedule can be created easily and in a short time.
[0063]
According to the present invention as set forth in claim 6, the computer transmits the determined transmission period to the plurality of departments, the work availability dates of the plurality of departments, and the schedule information of the plurality of workers. First receiving means for receiving, first schedule creating means for creating a schedule according to work possible dates of the plurality of departments, schedule information of a plurality of workers, worker qualification conditions based on the work, and the created schedule A program for functioning as second transmitting means for transmitting to the plurality of departments, second receiving means for receiving work results generated by performing work according to the created schedule, and output means for outputting the work results It is recorded.
[0064]
By using the recording medium of the sixth aspect, the inventions of the first to fifth aspects can be realized. The recording medium for recording this program is a magnetic recording medium for recording information magnetically, such as a CD-ROM, floppy disk, magneto-optical disk (MO), etc., a ROM, a flash memory, etc. Various types of recording media, such as a semiconductor memory for recording data, can be used.
[Brief description of the drawings]
FIG. 1 is a configuration diagram of an embodiment of a computer system that implements a schedule creation device of the present invention.
FIG. 2 is a configuration diagram of an example of a system including a schedule creation device of the present invention.
FIG. 3 is a flowchart of an embodiment of processing executed by a system including the schedule creation device of the present invention.
FIG. 4 is a configuration diagram of an example of an initial company-wide auditor table.
FIG. 5 is a configuration diagram of an example of an initial company-wide audit project table.
FIG. 6 is a configuration diagram of an example of a company auditor table to which a column for inputting schedule information is added.
FIG. 7 is a configuration diagram of an example of a company-wide audit project table to which a column for inputting an auditable date is added.
FIG. 8 is a configuration diagram of an example of a company-wide auditor table in which schedule information of each auditor candidate is input.
FIG. 9 is a configuration diagram of an example of a company-wide audit project table in which an auditable date is input.
FIG. 10 is a configuration diagram of an example of a company-wide auditor table in which an audit schedule is created.
FIG. 11 is a configuration diagram of an example of a company-wide audit project table in which an audit schedule is created.
FIG. 12 is a configuration diagram of an example of a company-wide audit project table in which an audit result is input.
FIG. 13 is an output diagram of an example of an audit result.
FIG. 14 is an output diagram of an example of an audit result.
FIG. 15 is a flowchart of an embodiment of processing executed by the schedule creation device.
FIG. 16 is a configuration diagram of an example of a condition table.
FIG. 17 is a configuration diagram of an example of a company-wide auditor management table.
FIG. 18 is a configuration diagram of an example of a company audit project management table.
[Explanation of symbols]
1 Schedule creation device
10 Computer system
20 input devices
30 Display device
40 Drive device
50 recording media
60 Auxiliary storage
70 Memory device
80 arithmetic processing unit
90 Printing device
100 Communication device
102 Administrative department
104-1 to 104-n
110 network
112 Company-wide auditor table
114 Company-wide audit project table
120-1 to 120-n terminal device
122-1 to 122-n Auditor table by department
124-1 to 124-n Audit project table by department

Claims (6)

決定した作業期間を複数の部署に送信する第1送信手段と、
前記複数の部署の作業可能日及び複数の作業人の予定情報を受信する第1受信手段と、
前記複数の部署の作業可能日,複数の作業人の予定情報,その作業に基づく作業人適格条件に従ってスケジュールを作成する第1スケジュール作成手段と、
前記作成したスケジュールを前記複数の部署に送信する第2送信手段と
を有し、
前記第1スケジュール作成手段は、複数の作業人から作業人を選択する条件である作業人適格条件として作業人の所属部署及び勤務地を条件テーブルから読み出すと共に、監査人テーブルから所属部署及び勤務地を読み出して比較し、前記複数の作業人から前記所属部署及び勤務地を満たす作業人を選択する選択手段と、
前記選択された作業人の予定情報と前記複数の部署の作業可能日との関係に基づき作業を行なう作業予定日及び作業人を設定する設定手段と
を有することを特徴とするスケジュール作成装置。
First transmission means for transmitting the determined work period to a plurality of departments;
First receiving means for receiving work days of the plurality of departments and schedule information of a plurality of workers;
First schedule creation means for creating a schedule according to work days of the plurality of departments, schedule information of a plurality of workers, and worker eligibility conditions based on the work;
Have a second transmission means for transmitting the schedule to the created plurality of departments,
The first schedule creation means reads out a worker's affiliation and work location from the condition table as worker qualification conditions, which are conditions for selecting a worker from a plurality of workers, and also assigns the department and work location from the auditor table. And selecting means for selecting a worker satisfying the department and work location from the plurality of workers,
Setting means for setting a scheduled work date and a worker to perform work based on the relationship between the schedule information of the selected worker and work days of the plurality of departments;
Schedule creation device which is characterized in that have a.
前記作成したスケジュールに従って作業を行なうことにより生じる作業結果を受信する第2受信手段と、
前記作業結果を出力する出力手段と
を更に有することを特徴とする請求項1記載のスケジュール作成装置。
Second receiving means for receiving a work result generated by performing work according to the created schedule;
The schedule creation apparatus according to claim 1, further comprising output means for outputting the work result.
前記選択手段は、前記複数の作業人が前回作業を行ったか否かの情報を読み出し、前記複数の作業人のうち、前回作業を行っていない作業人から前記所属部署及び勤務地を満たす作業人を選択することを特徴とする請求項1記載のスケジュール作成装置。 The selection means reads information on whether or not the plurality of workers performed the previous work, and among the plurality of workers, a worker who satisfies the belonging department and work place from a worker who has not performed the previous work. scheduling apparatus according to claim 1, wherein the selecting. 複数の作業人が係わる作業のスケジュールを作成するスケジュール作成システムにおいて、
前記スケジュールを作成/管理する管理部署と前記複数の作業人が所属する複数の部署との間でファイルを送受信する通信手段と、
前記作業及び作業人の情報が記録されている第1記録手段と、
前記作業の作業人適格条件が記録されている第2記録手段と、
前記作業及び作業人の情報,前記作業の作業人適格条件に従ってスケジュールを作成する第2スケジュール作成手段と
を有し、
前記第2スケジュール作成手段は、複数の作業人から作業人を選択する条件である作業人適格条件として作業人の所属部署及び勤務地を前記第2記録手段から読み出すと共に、第1記録手段から所属部署及び勤務地を読み出して比較し、前記複数の作業人から前記所属部署及び勤務地を満たす作業人を選択する選択手段と、
前記選択された作業人の予定情報と前記複数の部署の作業可能日との関係に基づき作業を行なう作業予定日及び作業人を設定する設定手段と
を有することを特徴とするスケジュール作成システム。
In a schedule creation system that creates a schedule of work involving multiple workers,
Communication means for transmitting and receiving files between a management department that creates / manages the schedule and a plurality of departments to which the plurality of workers belong;
First recording means in which information of the work and the worker is recorded;
Second recording means in which worker qualification conditions of the work are recorded;
The work and the work's information, have a second schedule creating means for creating a schedule in accordance with the work's eligibility conditions of the work,
The second schedule creation means reads out the department and work location of the worker from the second recording means as the worker qualification condition, which is a condition for selecting a worker from a plurality of workers, and belongs from the first recording means. A selection means for reading out and comparing a department and work location, and selecting a worker satisfying the department and work location from the plurality of workers,
Setting means for setting a scheduled work date and a worker to perform work based on the relationship between the schedule information of the selected worker and work days of the plurality of departments;
Scheduling system, characterized in that to have a.
前記選択手段は、前記複数の作業人が前回作業を行ったか否かの情報を読み出し、前記複数の作業人のうち、前回作業を行っていない作業人から前記所属部署及び勤務地を満たす作業人を選択することを特徴とする請求項4記載のスケジュール作成システム。 The selection means reads information on whether or not the plurality of workers performed the previous work, and among the plurality of workers, a worker who satisfies the belonging department and work place from a worker who has not performed the previous work. scheduling system according to claim 4, wherein the selecting. コンピュータを、
決定した作業期間を複数の部署に送信する第1送信手段と、
前記複数の部署の作業可能日及び複数の作業人の予定情報を受信する第1受信手段と、
前記複数の部署の作業可能日,複数の作業人の予定情報,その作業に基づく作業人適格条件に従ってスケジュールを作成する第1スケジュール作成手段と、
前記作成したスケジュールを前記複数の部署に送信する第2送信手段と
して機能させ
前記第1スケジュール作成手段は、複数の作業人から作業人を選択する条件である作業人適格条件として作業人の所属部署及び勤務地を条件テーブルから読み出すと共に、監査人テーブルから所属部署及び勤務地を読み出して比較し、前記複数の作業人から前記所属部署及び勤務地を満たす作業人を選択する選択手段と、
前記選択された作業人の予定情報と前記複数の部署の作業可能日との関係に基づき作業を行なう作業予定日及び作業人を設定する設定手段と
を有するように機能させるためのプログラムを記録したコンピュータ読み取り可能な記録媒体。
Computer
First transmission means for transmitting the determined work period to a plurality of departments;
First receiving means for receiving work days of the plurality of departments and schedule information of a plurality of workers;
First schedule creation means for creating a schedule according to work days of the plurality of departments, schedule information of a plurality of workers, and worker eligibility conditions based on the work;
Function as a second transmission means for transmitting the created schedule to the plurality of departments ;
The first schedule creation means reads out a worker's affiliation and work location from the condition table as worker qualification conditions, which are conditions for selecting a worker from a plurality of workers, and also assigns the department and work location from the auditor table. And selecting means for selecting a worker satisfying the department and work location from the plurality of workers,
Setting means for setting a scheduled work date and a worker to perform work based on the relationship between the schedule information of the selected worker and work days of the plurality of departments;
The computer-readable recording medium which recorded the program for functioning so that it may have .
JP17262599A 1999-06-18 1999-06-18 Schedule creation apparatus and system, and recording medium recording schedule creation program Expired - Fee Related JP4357639B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17262599A JP4357639B2 (en) 1999-06-18 1999-06-18 Schedule creation apparatus and system, and recording medium recording schedule creation program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17262599A JP4357639B2 (en) 1999-06-18 1999-06-18 Schedule creation apparatus and system, and recording medium recording schedule creation program

Publications (2)

Publication Number Publication Date
JP2001005859A JP2001005859A (en) 2001-01-12
JP4357639B2 true JP4357639B2 (en) 2009-11-04

Family

ID=15945356

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17262599A Expired - Fee Related JP4357639B2 (en) 1999-06-18 1999-06-18 Schedule creation apparatus and system, and recording medium recording schedule creation program

Country Status (1)

Country Link
JP (1) JP4357639B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5012453B2 (en) * 2007-11-26 2012-08-29 日本電気株式会社 Audit system, audit method and program

Also Published As

Publication number Publication date
JP2001005859A (en) 2001-01-12

Similar Documents

Publication Publication Date Title
US20240273433A1 (en) Reminder system
JP5694200B2 (en) Method and system for workflow integration
US20060085245A1 (en) Team collaboration system with business process management and records management
US20160048806A1 (en) Computer-based project management methods and systems
JP2013524347A (en) Remote portal for billing, docketing and document management
KR101845417B1 (en) Task management system and method for intellectual property right
JP4357639B2 (en) Schedule creation apparatus and system, and recording medium recording schedule creation program
US7809598B2 (en) Computer-implemented method, tool, and program product for scheduling an information technology (IT) migration
Mohamed et al. Quantifying the time and cost associated with the request for information (RFI) process in construction
Van der Aalst et al. Emailanalyzer: an e-mail mining plug-in for the prom framework
JP2003331113A (en) System and method for autonomous improvement of business process
US8499043B2 (en) Reports for email processing in an email response management system
JP2006139760A (en) Operational control system
JP2005293049A (en) E-mail management program, e-mail management apparatus, and e-mail management method
JP2022105616A (en) Server equipment, methods, and programs
Ott Conceptual design and implementation of a graphical workflow-modelling editor in the context of distributed groupware-databases
JP2010224687A (en) Management device
US20260073330A1 (en) Information processing apparatus and information processing method
JP5685999B2 (en) Server apparatus, mail transmission method and program
JPH07141439A (en) Group work supporting system
JP4344605B2 (en) Document transmission / reception system and transmission / reception control program
JP2004102650A (en) Sales support system, sales support method and sales support program
US20080126162A1 (en) Integrated activity logging and incident reporting
JP2000172702A (en) Minutes management method and minutes management system
Marcenko Automating B2B/B2C Transfer Dispatch with Zoho Creator CRM

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060518

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090210

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090410

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090804

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090805

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120814

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120814

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120814

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120814

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150814

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees