JP4413638B2 - How to check the inside of a concrete power pole - Google Patents
[go: Go Back, main page]

JP4413638B2 - How to check the inside of a concrete power pole - Google Patents

How to check the inside of a concrete power pole Download PDF

Info

Publication number
JP4413638B2
JP4413638B2 JP2004036244A JP2004036244A JP4413638B2 JP 4413638 B2 JP4413638 B2 JP 4413638B2 JP 2004036244 A JP2004036244 A JP 2004036244A JP 2004036244 A JP2004036244 A JP 2004036244A JP 4413638 B2 JP4413638 B2 JP 4413638B2
Authority
JP
Japan
Prior art keywords
wire
electric pole
concrete electric
concrete
hollow portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2004036244A
Other languages
Japanese (ja)
Other versions
JP2005227135A (en
Inventor
博保 皆吉
正人 後山
Original Assignee
エヌ・ティ・ティ・インフラネット株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by エヌ・ティ・ティ・インフラネット株式会社 filed Critical エヌ・ティ・ティ・インフラネット株式会社
Priority to JP2004036244A priority Critical patent/JP4413638B2/en
Publication of JP2005227135A publication Critical patent/JP2005227135A/en
Application granted granted Critical
Publication of JP4413638B2 publication Critical patent/JP4413638B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Investigating Materials By The Use Of Optical Means Adapted For Particular Applications (AREA)

Description

本発明は、立設されているコンクリート製電柱の中空部内を撮像手段で撮像して確認するコンクリート製電柱内部確認方法に関する。   The present invention relates to a method for confirming the inside of a concrete electric pole in which the inside of a hollow portion of a concrete electric pole that is erected is picked up by an image pickup means and confirmed.

コンクリート製電柱の設置工事では、立設したコンクリート製電柱の中空部に補強材としての棒状部材を複数本挿入し、それから該複数本の棒状部材の隙間に例えば豆砂利や砕石を投入し、更にモルタルやコンクリートなどを順次投入することによりコンクリート製電柱を補強している。このような補強は、特にコンクリート製電柱の地中に埋設された下端部と地中から延出した地際に近い部分に対して重点的に行なわれる。   In the installation work of the concrete electric pole, a plurality of rod-shaped members as reinforcing materials are inserted into the hollow part of the concrete electric pole that is erected, and then, for example, bean gravel or crushed stone is introduced into the gap between the plurality of rod-shaped members. Concrete electric poles are reinforced by sequentially adding mortar and concrete. Such reinforcement is focused particularly on the lower end portion embedded in the ground of the concrete power pole and the portion close to the ground extending from the ground.

コンクリート製電柱の設置工事は勿論のこと、一般的な土木工事では、工事の各工程毎に現場の写真を撮って、各工程の処理が適確に行なわれたことを確認するための記録を取っている。   In general civil engineering work as well as installation work of concrete utility poles, take a photograph of the site for each process of the construction and record a record to confirm that each process was performed properly taking it.

コンクリート製電柱の設置工事では、このような写真撮影による確認処理は、従来、立設したコンクリート製電柱の中空部内にカメラをカメラコードなどで吊るしながら挿入し、所望の位置まで挿入したカメラでコンクリート製電柱の中空部内を撮影し、中空部内の工事現場の状態を写真として記録することにより行なっている。なお、このような写真撮影による工事現場の確認処理は、工事の各工程毎だけでなく、工事開始前の事前調査時にも現場の初期状態を確認記録するためにも行なわれることは勿論のことである。
特願2003−24176号
In the construction work of concrete power poles, this kind of confirmation process by taking a photograph is conventionally carried out by suspending the camera into the hollow part of a concrete power pole that has been erected while hanging it with a camera cord, etc. This is done by photographing the inside of the hollow part of the power pole and recording the state of the construction site in the hollow part as a photograph. It should be noted that such construction site confirmation processing by photography is performed not only for each process of construction, but also for confirming and recording the initial state of the site at the time of preliminary inspection before the start of construction. It is.
Japanese Patent Application No. 2003-24176

従来、コンクリート製電柱の設置工事におけるコンクリート製電柱の中空部内の写真撮影による確認処理では、カメラコードなどに吊るしたカメラをコンクリート製電柱の中空部内に挿入し、所望の位置まで挿入したカメラで中空部内を撮影しているが、このようにカメラをカメラコードなどに吊るした状態では、カメラコードなどの揺れとともにカメラも揺れてふらつくため、カメラのふらつきがなくなり、カメラが安定するまで撮影できず、1枚の写真をとるにもかなりの時間がかかり、複数の写真を撮る必要がある全作業を完了するまでに長時間を必要とし、非効率的であるという問題がある。   Conventionally, in the confirmation process by taking a picture inside the hollow part of the concrete electric pole in the installation work of the concrete electric pole, the camera suspended from the camera cord or the like is inserted into the hollow part of the concrete electric pole and hollowed with the camera inserted to the desired position I am shooting the inside of the department, but when the camera is hung on the camera cord etc., the camera also shakes and shakes with the camera cord etc., so the camera does not wobble and I can not shoot until the camera is stable, It takes a considerable amount of time to take a single photo, and there is a problem that it takes a long time to complete all the operations that require taking a plurality of photos, which is inefficient.

本発明は、上記に鑑みてなされたもので、その目的とするところは、コンクリート製電柱の中空部内を撮像する撮像手段のふらつきを防止し、撮像処理による確認作業を短時間で効率的に行ない得るコンクリート製電柱内部確認方法を提供することにある。   The present invention has been made in view of the above, and an object of the present invention is to prevent fluctuation of an imaging means for imaging the inside of a hollow portion of a concrete utility pole, and to efficiently perform confirmation work by imaging processing in a short time. It is to provide a method for confirming the inside of a concrete utility pole.

請求項1記載の本発明のコンクリート製電柱内部確認方法は、立設されているコンクリート製電柱の中空部内を確認するコンクリート製電柱内部確認方法であって、下端部に重りを取り付けたワイヤに撮像手段を取り付け、前記ワイヤを下端部の重り側からコンクリート製電柱の中空部内に垂れ下ろし、前記ワイヤの下端部の重りがコンクリート製電柱の中空部内の底部に当った状態でワイヤを上方に引き上げるようにしてワイヤを緊張させ、このワイヤを緊張させた状態において前記撮像手段でコンクリート製電柱の中空部内を確認すべく撮像することを要旨とする。   The concrete electric pole inside confirmation method of the present invention according to claim 1 is a concrete electric pole inside confirmation method for confirming the inside of a hollow portion of a standing concrete electric pole, and imaging a wire having a weight attached to a lower end portion. A means is attached, and the wire is hung down from the weight side of the lower end portion into the hollow portion of the concrete electric pole, and the wire is pulled upward while the weight of the lower end portion of the wire hits the bottom portion of the hollow portion of the concrete electric pole. The gist of the present invention is that the wire is tensioned, and that the image is taken by the imaging means to confirm the inside of the hollow portion of the concrete electric pole in a state where the wire is tensioned.

請求項2記載の本発明のコンクリート製電柱内部確認方法は、前記撮像手段のワイヤへの取り付けが、撮像手段をワイヤへ固定的に取り付けることを要旨とする。   The gist of the concrete electric pole inside confirmation method of the present invention according to claim 2 is that the imaging means is fixedly attached to the wire.

請求項3記載の本発明のコンクリート製電柱内部確認方法は、立設されているコンクリート製電柱の中空部内を確認するコンクリート製電柱内部確認方法であって、下端部に重りを取り付けたワイヤを下端部の重り側からコンクリート製電柱の中空部内に垂れ下ろし、前記ワイヤの下端部の重りがコンクリート製電柱の中空部内の底部に当った状態でワイヤを上方に引き上げるようにしてワイヤを緊張させ、この緊張させた状態のワイヤに沿って撮像手段を移動させ得るように撮像手段をワイヤに連結し、この連結状態で撮像手段をワイヤに沿って移動させながらコンクリート製電柱の中空部内を確認すべく撮像することを要旨とする。   The concrete electric pole inside confirmation method of the present invention according to claim 3 is a concrete electric pole inside confirmation method for confirming the inside of a hollow portion of a concrete electric pole that is erected, wherein a wire having a weight attached to the lower end is attached to the lower end. The wire is pulled down from the weight side of the part into the hollow part of the concrete electric pole, and the wire is pulled up so that the weight of the lower end part of the wire hits the bottom part of the hollow part of the concrete electric pole. The imaging means is connected to the wire so that the imaging means can be moved along the tensioned wire, and imaging is performed to confirm the inside of the hollow portion of the concrete electric pole while moving the imaging means along the wire in this connected state. The gist is to do.

請求項4記載の本発明のコンクリート製電柱内部確認方法は、前記撮像手段をワイヤに沿って移動させ得るように撮像手段をワイヤに連結する処理は、前記ワイヤが円滑に貫通し得るようにワイヤの直径よりも若干大きい直径を有する環状部材を撮像手段に取り付け、この環状部材にワイヤを挿入して連結することを要旨とする。   According to a fourth aspect of the present invention, there is provided a method for confirming the inside of a concrete utility pole. The process of connecting the imaging means to the wire so that the imaging means can be moved along the wire is performed so that the wire can be smoothly penetrated. The gist of the present invention is to attach an annular member having a diameter slightly larger than the diameter to the imaging means, and to insert and connect a wire to the annular member.

請求項5記載の本発明のコンクリート製電柱内部確認方法は、前記撮像手段には撮像用コードが取り付けられ、撮像手段が、該撮像用コードによりワイヤに沿って上方から吊り下げられていることを要旨とする。   The concrete electric pole inside confirmation method of the present invention according to claim 5 is that an imaging cord is attached to the imaging means, and the imaging means is suspended from above along the wire by the imaging cord. The gist.

請求項6記載の本発明のコンクリート製電柱内部確認方法は、前記ワイヤを下端部の重り側から中空部内に垂れ下ろし作業が、コンクリート製電柱の側部に形成された開口部またはコンクリート製電柱の最上端の上端末口部から行なうことを要旨とする。   In the method for confirming the inside of the concrete electric pole according to the sixth aspect of the present invention, the work of hanging the wire from the weight side of the lower end portion into the hollow portion is performed by the opening formed on the side of the concrete electric pole or the concrete electric pole. The gist is to do it from the upper end of the upper end.

請求項7記載の本発明のコンクリート製電柱内部確認方法は、前記重りおよび撮像手段を取り付けるワイヤが、強化材としての複数の棒状部材を中空部内に均等に配置するための補強材均等配置用冶具を吊り下げるワイヤを利用することを要旨とする。   8. The concrete electric pole interior confirmation method according to claim 7, wherein the wire for attaching the weight and the imaging means is a reinforcing material uniform arrangement jig for uniformly arranging a plurality of rod-shaped members as reinforcing materials in the hollow portion. The gist is to use a wire that suspends the wire.

請求項8記載の本発明のコンクリート製電柱内部確認方法は、前記ワイヤに取り付けられた重りおよび撮像手段が、コンクリート製電柱の中空部の断面においてほぼ中央に垂れ下ろされることを要旨とする。   The concrete electric pole inside confirmation method of the present invention according to claim 8 is characterized in that the weight attached to the wire and the imaging means are hung down substantially in the center in the cross section of the hollow portion of the concrete electric pole.

請求項9記載の本発明のコンクリート製電柱内部確認方法は、前記ワイヤに取り付けられた重りおよび撮像手段が、コンクリート製電柱の中空部内に配置された複数の棒状部材および補強材均等配置用冶具を避けるように中空部の縁部に沿って垂れ下ろされることを要旨とする。   According to a ninth aspect of the present invention, there is provided the concrete electric pole interior confirmation method according to the present invention, wherein the weight attached to the wire and the imaging means include a plurality of rod-like members arranged in the hollow portion of the concrete electric pole and a jig for evenly arranging reinforcing materials. The gist is to hang down along the edge of the hollow portion so as to avoid.

請求項10記載の本発明のコンクリート製電柱内部確認方法は、前記ワイヤは、重りおよび撮像手段を中空部内に円滑に繰り出すことができるようにワイヤを巻き取ったり、巻き戻すことができる巻取器を用いて中空部内への繰り出しを行なうことを要旨とする。   The concrete electric pole inside confirmation method of the present invention according to claim 10, wherein the wire is a winder capable of winding or unwinding the wire so that the weight and the imaging means can be smoothly fed into the hollow portion. The gist of this is to carry out the feeding into the hollow part.

本発明によれば、下端部に重りを取り付けたワイヤに撮像手段を取り付け、ワイヤを下端部の重り側からコンクリート製電柱の中空部内に垂れ下ろし、下端部の重りが中空部内の底部に当って倒れた場合、ワイヤの垂れ下ろしを停止し、この倒れた重りの下端のみが中空部内の底部から離れずに当った状態で重りが起立するようにワイヤを上方に引き上げてワイヤを緊張させ、このワイヤを緊張させた状態において撮像手段でコンクリート製電柱の中空部内を確認すべく撮像するので、撮像手段を取り付けて垂れ下げているワイヤが従来のように揺れてふらつくことがなく、撮像手段の撮像による確認動作を極めて短時間で迅速かつ効果的に行なうことができる。   According to the present invention, the imaging means is attached to the wire having the weight attached to the lower end, the wire is suspended from the weight side of the lower end into the hollow portion of the concrete electric pole, and the weight of the lower end is brought into contact with the bottom in the hollow portion. If it falls down, stop hanging the wire, pull the wire up so that the weight stands up with only the lower end of the fallen weight not touching the bottom of the hollow part, Since the imaging means is used to check the inside of the hollow part of the concrete electric pole with the wire being in tension, the wire hanging down with the imaging means attached does not shake and fluctuate as before, and the imaging means Can be quickly and effectively performed in a very short time.

本発明によれば、下端部に重りを取り付けたワイヤを下端部の重り側からコンクリート製電柱の中空部内に垂れ下ろし、重りが中空部内の底部に当って倒れた場合、ワイヤの垂れ下ろしを停止し、この倒れた重りの下端のみが中空部内の底部から触れずに当った状態で重りが起立するようにワイヤを上方に引き上げてワイヤを緊張させ、この緊張させた状態のワイヤに沿って撮像手段を移動させ得るように撮像手段をワイヤに連結し、この連結状態で撮像手段をワイヤに沿って移動させながらコンクリート製電柱の中空部内を確認すべく撮像するので、撮像手段を取り付けて垂れ下げているワイヤが従来のように揺れてふらつくことがなく、撮像手段の撮像による確認動作を極めて短時間で迅速かつ効果的に行なうことができるとともに、ワイヤに沿って撮像手段を移動させながら任意の位置の画像を撮像することができる。   According to the present invention, a wire with a weight attached to the lower end is suspended from the weight side of the lower end into the hollow portion of the concrete electric pole, and when the weight hits the bottom of the hollow portion, the suspension of the wire is stopped. Then, the wire is pulled up so that the weight stands up in a state where only the lower end of the fallen weight is not touched from the bottom in the hollow portion, and the wire is tensioned, and imaging is performed along the wire in the tensioned state. The imaging means is connected to the wire so that the means can be moved, and in this connected state, the imaging means is moved along the wire while taking an image to confirm the inside of the hollow portion of the concrete electric pole. Therefore, the confirmation operation by the image pickup by the image pickup means can be performed quickly and effectively in a very short time, and the It is possible to capture an image of any position while moving the imaging means along ya.

本発明によれば、重りおよび撮像手段を取り付けるワイヤは、補強材均等配置用冶具を吊り下げるワイヤを利用するので、補強材均等配置用冶具を利用する場合に効率的に行なうことができる。   According to the present invention, the wire for attaching the weight and the imaging means uses the wire for hanging the reinforcing material uniform arrangement jig, and therefore can be efficiently performed when the reinforcing material uniform arrangement jig is used.

本発明によれば、巻取器を用いてワイヤを巻き取ったり巻き戻して、重りおよび撮像手段を中空部内に円滑に繰り出すことができる。   According to the present invention, the wire can be wound or unwound using the winder, and the weight and the imaging means can be smoothly fed into the hollow portion.

以下、図面を用いて、本発明を実施するための最良の形態(以下、実施形態と称する)を説明する。   Hereinafter, the best mode for carrying out the present invention (hereinafter referred to as an embodiment) will be described with reference to the drawings.

図1(a)は、本発明の一実施形態に係わるコンクリート製電柱内部確認方法を説明するためのコンクリート製電柱の断面およびコンクリート製電柱の中空部内の確認作業に必要な関連部材および装置を示す図である。なお、本実施形態のコンクリート製電柱内部確認方法は、地中に立設された例えば長さが16〜17mの共架柱などのコンクリート製電柱を補強する工事などを行なうに当って、立設されたコンクリート製電柱の内部の状態を事前に調査して確認するために行なうものである。   Fig.1 (a) shows the related member and apparatus required for the confirmation operation in the cross section of the concrete electric pole, and the inside of the hollow part of a concrete electric pole for demonstrating the concrete electric pole inside confirmation method concerning one Embodiment of this invention. FIG. In addition, the concrete electric pole inside confirmation method of this embodiment is standing in performing the construction etc. which reinforce concrete electric poles, such as a 16-17m-long suspended pole installed in the ground, for example. This is done to investigate and confirm the internal state of the concrete pole made of concrete in advance.

図1(a)においては、コンクリート製電柱1は、地中11に埋設された下端部と地中11から延出した地際に近い部分(以下、地際延出部と称する)のみが図示されているが、実際には上方に例えば16〜17m高く延出しているものである。なお、地際とは、コンクリート製電柱1が地中11から露出した位置、すなわち地表に接するコンクリート製電柱1の位置を示すものである。   In FIG. 1 (a), the concrete utility pole 1 shows only a lower end portion embedded in the underground 11 and a portion close to the ground extending from the underground 11 (hereinafter referred to as a ground extending portion). However, it actually extends upward by 16 to 17 m, for example. The term “ground” refers to the position where the concrete electric pole 1 is exposed from the underground 11, that is, the position of the concrete electric pole 1 in contact with the ground surface.

コンクリート製電柱1は、図1(a)に示すように外周部3で囲まれた内部が空洞に形成されて中空部5を形成している。また、地上に延出したコンクリート製電柱1の外周部3の地際に比較的近い位置には、例えばアース孔と称する開口部7が形成されている。この開口部7は、例えば縦が40〜60mm、横幅が20〜40mmの小判形の孔であり、地際から例えば1000〜1200mmの位置のコンクリート製電柱1の側部に形成され、通常は例えばコンクリート製電柱1を補強するための補強材やモルタルなどを注入するために使用されるものであるが、本実施形態ではコンクリート製電柱内部確認のために使用する撮像手段であるカメラ41をコンクリート製電柱1の中空部5内に挿入するために使用される。   As shown in FIG. 1A, the concrete utility pole 1 has a hollow portion 5 formed by forming a hollow portion surrounded by the outer peripheral portion 3. In addition, an opening 7 called, for example, a ground hole is formed at a position relatively close to the ground of the outer peripheral portion 3 of the concrete utility pole 1 extending to the ground. The opening 7 is, for example, an oval hole having a length of 40 to 60 mm and a width of 20 to 40 mm, and is formed on the side portion of the concrete electric pole 1 at a position of 1000 to 1200 mm from the ground. Although used for injecting a reinforcing material or mortar for reinforcing the concrete electric pole 1, in this embodiment, the camera 41, which is an imaging means used for checking the inside of the concrete electric pole, is made of concrete. Used to insert into the hollow portion 5 of the utility pole 1.

地中11に埋設されたコンクリート製電柱1の最下端部の底には、例えばヘドロなどを含む土砂31が少し盛り上がって存在し、この土砂31の上に留水33が存在している。また、コンクリート製電柱1の最下端部近傍の外周部3はコンクリートが内側に膨出してノロが形成され、その一部にはコンクリート製電柱1の外周部3をコンクリートとともに構成している針金35が露出している。   At the bottom of the lowermost end of the concrete utility pole 1 buried in the ground 11, earth and sand 31 including sludge, for example, is slightly raised, and retained water 33 is present on the earth and sand 31. Further, the outer peripheral portion 3 near the lowermost end portion of the concrete electric pole 1 is swelled by the inside of the concrete, and a wire 35 is formed in part of the outer peripheral portion 3 of the concrete electric pole 1 together with the concrete. Is exposed.

更に、コンクリート製電柱1の中空部5内には、地中11に埋設された部分で下端が接地され、上端が上方に延出しているアース線51が中空部5の側壁に沿って設けられている。   Further, in the hollow portion 5 of the concrete utility pole 1, a ground wire 51 is provided along the side wall of the hollow portion 5 with the lower end grounded at the portion embedded in the underground 11 and the upper end extending upward. ing.

上述したように地中11に立設されたコンクリート製電柱1を補強する工事などを行なうに当って、コンクリート製電柱1の立設状態を事前に確認する調査を行なうには、コンクリート製電柱1の中空部5内に撮像手段であるカメラ41を挿入し、コンクリート製電柱1の下端部近くまでカメラ41を揺らすように移動させながらコンクリート製電柱1の中空部5内の下方をカメラ41の下向きに取り付けられたレンズで撮像するのであるが、単にカメラ41のみを中空部5内にカメラコードなどで垂らしたのでは、従来技術で説明したようにカメラ41が揺れてふらつくので、本実施形態では、図1(a)に示すように、重り25を下端部に取り付けたワイヤ20を用意する。   As described above, when conducting the work of reinforcing the concrete utility pole 1 standing in the ground 11, the concrete utility pole 1 is used to conduct a survey to confirm the standing status of the concrete utility pole 1 in advance. The camera 41 which is an imaging means is inserted into the hollow portion 5 of the concrete pole, and the camera 41 is moved so as to be swung to the vicinity of the lower end portion of the concrete electric pole 1 while the lower side of the hollow portion 5 of the concrete electric pole 1 is directed downward However, if the camera 41 alone is hung in the hollow portion 5 with a camera cord or the like, the camera 41 shakes and fluctuates as described in the prior art. As shown in FIG. 1A, a wire 20 having a weight 25 attached to the lower end is prepared.

このワイヤ20は、図1(a)に示すように、第1のワイヤ15、第2のワイヤ19、第3のワイヤ23、第1のワイヤ15と第2のワイヤ19とを連結する第1のスナップ付サルカン17、および第2のワイヤ19と第3のワイヤ23とを連結する第2のスナップ付サルカン23から構成され、このように構成されるワイヤ20の下端部、すなわち第1のワイヤ15の下端部に重り25が取り付けられている。この重り25を利用してカメラ41のふらつきを防止しようとするものであり、この重り25の重量は、例えば約360〜380gである。   As shown in FIG. 1A, the wire 20 includes a first wire 15, a second wire 19, a third wire 23, and a first wire 15 that connects the first wire 15 and the second wire 19. , And the lower end portion of the wire 20 configured as described above, that is, the first wire. A weight 25 is attached to the lower end of 15. The weight 25 is used to prevent the camera 41 from wobbling. The weight of the weight 25 is, for example, about 360 to 380 g.

なお、第1のスナップ付サルカン17および第2のスナップ付サルカン23は、詳しくは、図1(b)に示すように、例えば釣りなどによく使用されるものであって、両端にリング状部を有する金具をスナップ式に連結し得るものであり、このリング状部のそれぞれに各ワイヤを取り付けて連結するものである。   In detail, the first and second snapped salkans 17 and 23 are often used for fishing, for example, as shown in FIG. 1 (b). It is possible to connect a metal fitting having a snap-type, and attach and connect each wire to each of the ring-shaped portions.

また、上述したように構成されるワイヤ20の第2のワイヤ19の下端部寄りの部分に対して、図1(a)に示すように円筒状のカメラ41を例えばビニールテープなどの取付部材43で縛るように取り付けて固定する。また、カメラ41から上方に延出しているカメラコード47も同様に例えばビニールテープなどの取付部材45で第2のワイヤ19を縛るように固定的に取り付けられている。   Further, as shown in FIG. 1A, a cylindrical camera 41 is attached to a portion near the lower end portion of the second wire 19 of the wire 20 configured as described above, for example, a mounting member 43 such as a vinyl tape. Attach and fix it so that it is tied. Similarly, the camera cord 47 extending upward from the camera 41 is also fixedly attached so as to bind the second wire 19 with an attachment member 45 such as a vinyl tape.

なお、図1(a)に示すワイヤおよびカメラ41の状態は、カメラ41をワイヤ20に取り付け、コンクリート製電柱1の中空部5内に挿入して下端部寄りまで既に垂れ下ろし、カメラ41で中空部5内を撮像可能な状態になっているものであるが、この状態においては、上述したようにカメラ41を第2のワイヤ19に取り付けられるとともに下端部に重り25の付いたワイヤ20をカメラ41とともに中空部5の円筒形の横断面のほぼ中央に垂れ下ろすために第3のワイヤ23が挿入されるアルミなどからなるパイプ13がコンクリート製電柱1の外周部3に形成された開口部7から水平に挿入され、このパイプ13の一端がコンクリート製電柱1の中空部5内の円筒形のほぼ中央まで延出し、他端はコンクリート製電柱1の外部に延出しているように図示されるとともに、このパイプ13内に第3のワイヤ23が挿入され、第3のワイヤ23の先端はパイプ13を貫通して外部に延出している。   The wire and camera 41 shown in FIG. 1 (a) are attached to the wire 20, inserted into the hollow portion 5 of the concrete electric pole 1, and already hung down to the lower end portion. In this state, the camera 41 can be attached to the second wire 19 and the wire 20 with the weight 25 at the lower end is attached to the camera in this state. A pipe 13 made of aluminum or the like into which the third wire 23 is inserted in order to hang down at about the center of the cylindrical cross section of the hollow portion 5 together with 41 is an opening 7 formed in the outer peripheral portion 3 of the concrete utility pole 1. Is inserted horizontally, and one end of the pipe 13 extends to the center of the cylindrical shape in the hollow portion 5 of the concrete electric pole 1, and the other end extends to the outside of the concrete electric pole 1. Together are illustrated as the third wire 23 to the pipe 13 is inserted, the tip of the third wire 23 extends to the outside through the pipe 13.

また、図1(a)に示す状態では、ワイヤ20の下端部に取り付けられた重り25はコンクリート製電柱1の最下端部の土砂31に当接して起立し、第2のワイヤ19に取り付けられたカメラ41はワイヤとともに中空部5の下端部寄りまで垂れ下ろされ、カメラ41の下向きに取り付けられた撮像レンズで中空部5内の下方の画像を撮像可能になっている。また、カメラ41の上端から延出し、取付部材45で第2のワイヤ19に取り付けられたカメラコード47は、第2のワイヤ19、第2のスナップ付サルカン23、第3のワイヤ23、パイプ13に沿って開口部7から外部に延出し、モニタ49に接続され、カメラ41で撮像した中空部5内の画像がモニタ49に表示されるようになっている。   Further, in the state shown in FIG. 1A, the weight 25 attached to the lower end portion of the wire 20 stands up against the earth and sand 31 at the lowermost end portion of the concrete electric pole 1 and is attached to the second wire 19. The camera 41 is hung down to the lower end portion of the hollow portion 5 together with the wire, and a lower image in the hollow portion 5 can be taken by an imaging lens attached downward of the camera 41. The camera cord 47 that extends from the upper end of the camera 41 and is attached to the second wire 19 with the attachment member 45 includes the second wire 19, the second snapped salkan 23, the third wire 23, and the pipe 13. The image is extended to the outside from the opening 7 and connected to the monitor 49, and the image in the hollow portion 5 captured by the camera 41 is displayed on the monitor 49.

カメラ41は、詳しくは図2に示すように、直径が約25mm、長さが約150mmの円筒形のものであり、図2(b)に示すように、下端部には中央にCCDカメラ41bが中空部5内の下方の画像を撮像し得るように下向きに取り付けられ、この周囲に6個のLED41cが中空部5内を照明し得るように取り付けられている。また、カメラ41の下端部には例えば5〜225mmの範囲で2段に伸縮自在な棒状の水センサ41aが取り付けられている。この水センサ41aは、カメラ41が誤って留水33に浸漬されることを防止すべく水を検知するものである。具体的には、カメラ41が中空部5内をワイヤとともに垂れ下ろされて、中空部5内の例えば最下端部に存在している留水33などに浸漬される直前に下方に伸張した水センサ41aが留水33を検知すると、その旨をカメラ41、カメラコード47を介してモニタ49に表示し、これによりカメラ41が誤って留水33に浸漬されることを防止するものである。   Specifically, as shown in FIG. 2, the camera 41 has a cylindrical shape with a diameter of about 25 mm and a length of about 150 mm. As shown in FIG. Is attached downward so that an image of the lower part in the hollow part 5 can be taken, and around this, six LEDs 41c are attached so that the inside of the hollow part 5 can be illuminated. In addition, a rod-shaped water sensor 41 a that can be expanded and contracted in two steps within a range of 5 to 225 mm, for example, is attached to the lower end of the camera 41. This water sensor 41a detects water in order to prevent the camera 41 from being immersed in the retained water 33 by mistake. Specifically, the water sensor that extends downward immediately before the camera 41 is hung down together with the wire in the hollow portion 5 and is immersed in, for example, the retained water 33 existing in the lower end portion of the hollow portion 5. When 41a detects the retained water 33, the fact is displayed on the monitor 49 via the camera 41 and the camera code 47, thereby preventing the camera 41 from being immersed in the retained water 33 by mistake.

次に、上述した本実施形態のコンクリート製電柱内部確認方法の工事前においてコンクリート製電柱1の内部状態を事前に確認するための一連の確認動作手順について説明する。なお、開口部7は、前記アース孔などを利用するかなどして、既に形成されているものとする。   Next, a series of confirmation operation procedures for confirming in advance the internal state of the concrete power pole 1 before the construction of the concrete power pole interior confirmation method of the present embodiment described above will be described. It is assumed that the opening 7 has already been formed by using the ground hole or the like.

図1(a)に示すように、地中11に立設されたコンクリート製電柱1の立設状態、特に中空部5の内部を事前に確認する調査を行なうには、まず、第1のワイヤ15、第2のワイヤ19、第3のワイヤ23を図1(a)に示したように第1のスナップ付サルカン17、第3のワイヤ23で連結して1本のワイヤ20を作成し、このワイヤ20の下端部、すなわち第1のワイヤ15の下端部に重り25を取り付ける。   As shown in FIG. 1 (a), in order to conduct an investigation to confirm in advance the standing state of the concrete utility pole 1 standing in the ground 11, particularly the interior of the hollow portion 5, first the first wire 15, the second wire 19 and the third wire 23 are connected with the first snapped salkan 17 and the third wire 23 as shown in FIG. A weight 25 is attached to the lower end of the wire 20, that is, the lower end of the first wire 15.

次に、第2のワイヤ19の下端部にカメラ41をビニールテープなどの取付部材43で固定的に取り付けるとともに、またカメラ41の上端部に連結されているカメラコード47もビニールテープなどの取付部材45で固定的に取り付ける。なお、この場合、カメラ41のCCDカメラ41bが露出している先端、すなわち図1(a)ではカメラ41の下端に取り付けられた撮像レンズが重り25の方を向くように取り付ける。   Next, the camera 41 is fixedly attached to the lower end portion of the second wire 19 with an attachment member 43 such as a vinyl tape, and the camera cord 47 connected to the upper end portion of the camera 41 is also an attachment member such as a vinyl tape. Install fixedly at 45. In this case, the imaging lens attached to the tip of the camera 41 where the CCD camera 41b is exposed, that is, the lower end of the camera 41 in FIG. 1A, is attached to face the weight 25.

上述したように、重り25の付いたワイヤ20を用意し、このワイヤ20にカメラ41およびカメラコード47を取り付けた後、ワイヤ20の上端部、すなわち第3のワイヤ23の先端をパイプ13に挿入し、それからカメラコード47をワイヤ20およびパイプ13に沿わせる。   As described above, the wire 20 with the weight 25 is prepared, the camera 41 and the camera cord 47 are attached to the wire 20, and then the upper end of the wire 20, that is, the tip of the third wire 23 is inserted into the pipe 13. Then, the camera cord 47 is placed along the wire 20 and the pipe 13.

次に、重り25をコンクリート製電柱1の開口部7から中空部5内に挿入し、続いてワイヤ20も第1のワイヤ15から中空部5内に挿入する。第1のワイヤ15が開口部7から中空部5内に完全に挿入されると、開口部7の所には、第2のワイヤ19に取り付けられたカメラ41が位置するので、ここで、カメラ41もワイヤ20とともに開口部7から中空部5内に挿入する。続いて、互いに沿うように設けられたワイヤ20とカメラコード47とを一緒に順次取り出すように開口部7から中空部5内に挿入する。なお、このワイヤ20とカメラコード47の中空部5内への繰り出しは、ワイヤ20の下端部に取り付けた重り25により両者が引っ張られるように行なわれる。   Next, the weight 25 is inserted into the hollow portion 5 from the opening 7 of the concrete utility pole 1, and then the wire 20 is also inserted into the hollow portion 5 from the first wire 15. When the first wire 15 is completely inserted into the hollow portion 5 from the opening 7, the camera 41 attached to the second wire 19 is positioned at the opening 7. 41 is also inserted into the hollow portion 5 through the opening 7 together with the wire 20. Subsequently, the wire 20 and the camera cord 47 provided along each other are inserted into the hollow portion 5 through the opening 7 so as to be sequentially taken out together. Note that the wire 20 and the camera cord 47 are fed into the hollow portion 5 so that both are pulled by the weight 25 attached to the lower end portion of the wire 20.

このように下端部に重り25が取り付けられ、途中にカメラ41が取り付けられたワイヤ20とカメラコード47が中空部5内に下方に向かって順次繰り出され、ワイヤ20がパイプ13に挿入された位置が開口部7の所になると、パイプ13を開口部7から中空部5に挿入し、このパイプ13の先端が中空部5の断面のほぼ中央に位置するように設定し、以降はこの状態を維持するように設定する。   Thus, the position where the weight 25 is attached to the lower end portion, the wire 20 to which the camera 41 is attached, and the camera cord 47 are sequentially fed downward into the hollow portion 5 and the wire 20 is inserted into the pipe 13. Is located at the opening 7, the pipe 13 is inserted into the hollow portion 5 from the opening 7, and the tip of the pipe 13 is set so as to be located at the approximate center of the cross section of the hollow portion 5. Set to maintain.

パイプ13の先端が中空部5の断面のほぼ中央に位置するように設定されると、このパイプ13の先端から下方に垂れ下がっているワイヤ20は、重り25の重力により引っ張られて緊張しながら、真直ぐ垂直にコンクリート製電柱1の最下端部の底に向かって張られる。なお、この場合、ワイヤ20の下端部に取り付けられている重り25は、最初は若干揺れるも、最終的には中空部5の断面のほぼ中央に位置することになる。   When the tip of the pipe 13 is set so as to be positioned at the approximate center of the cross section of the hollow portion 5, the wire 20 hanging downward from the tip of the pipe 13 is pulled and tensioned by the gravity of the weight 25, It is stretched straight and vertically toward the bottom of the lowermost end of the concrete utility pole 1. In this case, the weight 25 attached to the lower end portion of the wire 20 is slightly swayed at first, but is finally located substantially at the center of the cross section of the hollow portion 5.

このようにワイヤ20が重り25の重力で下方に真直ぐ垂れ下がっているが、重り25がコンクリート製電柱1の底に達していない場合には、重り25がコンクリート製電柱1の底に到達するまで、ワイヤ20をパイプ13を介して更に中空部5内に繰り出すと同様に、またカメラコード47もワイヤ20に沿わせながらワイヤ20の繰り出しとともに開口部7を介して中空部5内に繰り出す。   In this way, the wire 20 hangs straight down due to the gravity of the weight 25, but when the weight 25 does not reach the bottom of the concrete utility pole 1, until the weight 25 reaches the bottom of the concrete utility pole 1, When the wire 20 is further fed into the hollow portion 5 through the pipe 13, the camera cord 47 is also fed into the hollow portion 5 through the opening portion 7 along with the feeding of the wire 20 along the wire 20.

このようにワイヤ20およびカメラコード47を中空部5内に繰り出す動作を継続的に行っていると、ワイヤ20の下端部に取り付けた重り25がコンクリート製電柱1の底に当り、図1(c)に示すように、重り25は一端横倒しになる。重り25がコンクリート製電柱1の底に当って横倒しになると、ワイヤ20の緊張が弛むので、ワイヤ20の上端を保持しながらパイプ13を介して繰り出していた側においては、このワイヤ20の緊張の緩みを検知することにより、重り25がコンクリート製電柱1の底に到達したことを知ることができる。なお、このワイヤ20の上端を保持しながらパイプ13を介して繰り出していた側においては、このワイヤ20の保持および繰り出しは、作業者が行なってもよいし、または機械的に装置が行なってもよく、またワイヤ20の緊張の緩みの検知も作業者自身が行なうことができるし、また装置によって自動的に行なうことも可能である。   Thus, when the operation | movement which draws out the wire 20 and the camera cord 47 in the hollow part 5 is performed continuously, the weight 25 attached to the lower end part of the wire 20 will hit the bottom of the concrete utility pole 1, and FIG. ), The weight 25 lies one side down. When the weight 25 hits the bottom of the concrete utility pole 1 and falls on its side, the tension of the wire 20 is loosened. Therefore, the tension of the wire 20 is maintained on the side that has been fed out through the pipe 13 while holding the upper end of the wire 20. By detecting the looseness, it can be known that the weight 25 has reached the bottom of the concrete utility pole 1. On the side where the upper end of the wire 20 is held and the wire 20 is fed through the pipe 13, the wire 20 may be held and fed by an operator or mechanically. In addition, the operator can detect the looseness of the tension of the wire 20 or can be automatically performed by the apparatus.

上述したように、ワイヤ20の緊張の緩みの検知により重り25がコンクリート製電柱1の底に到達して横倒しになったことを検出すると、図1(c)に示すように、横倒しになった重り25を起立させるべくパイプ13から延出しているワイヤ20、図1(a)は第3のワイヤ23をパイプ13を介して中空部5内から取り出すように引っ張る。   As described above, when it is detected that the weight 25 has reached the bottom of the concrete utility pole 1 and has been laid down by detecting the looseness of the tension of the wire 20, as shown in FIG. In order to raise the weight 25, the wire 20 extending from the pipe 13, FIG. 1A pulls the third wire 23 so as to be taken out from the hollow portion 5 through the pipe 13.

このようにして、重り25が起立すると、ワイヤ20は、再度引っ張られて緊張し、重り25とパイプ13の先端との間で緊張を維持した状態で固定され、従来のように揺れてふらつくこともなくなる。この結果、ワイヤ20に取付部材43で取り付けられているカメラ41も揺れてふらつくこともなくなる。従って、この状態でカメラ41によりコンクリート製電柱1の中空部5内を撮像することにより、鮮明な画像を得ることができる。   In this way, when the weight 25 stands up, the wire 20 is pulled and tensioned again, and is fixed in a state where the tension is maintained between the weight 25 and the tip of the pipe 13, and the wire 20 swings and staggers as in the conventional case. Also disappear. As a result, the camera 41 attached to the wire 20 by the attachment member 43 is not shaken and fluctuated. Therefore, a clear image can be obtained by imaging the inside of the hollow portion 5 of the concrete electric pole 1 with the camera 41 in this state.

なお、本実施形態の上記処理は、第1のワイヤ15、第2のワイヤ19、第3のワイヤ23を第1のスナップ付サルカン17、第2のスナップ付サルカン23で予め連結して、ワイヤ20を作成しておくとともに、このワイヤ20に重り25とカメラ41およびカメラコード47を予め取り付けて準備しておくことによりカメラ41による確認作業を迅速に行なうことができるが、予め準備しておかなくても、単に第1のワイヤ15、第2のワイヤ19、第3のワイヤ23を第1のスナップ付サルカン17、第2のスナップ付サルカン23で連結してワイヤ20を作成し、このワイヤ20に重り25とカメラ41、カメラコード47を取り付ける作業のみが従来に比較して多いだけであって、この作業は比較的に簡単なものであるため、従来、カメラ41が揺れてふらつくために、カメラ41による撮像が完了するまでにかかった従来の作業時間に比較して飛躍的に作業時間を短縮できるようになった。具体的には、従来、1時間かかった作業時間を例えば10分程度まで短縮できた。   In the above-described processing of the present embodiment, the first wire 15, the second wire 19, and the third wire 23 are connected in advance by the first snapped salkan 17 and the second snapped salkan 23, and the wire 20 is prepared, and the weight 25, the camera 41, and the camera cord 47 are attached to the wire 20 in advance, and the confirmation work by the camera 41 can be quickly performed. Even if not, the first wire 15, the second wire 19, and the third wire 23 are simply connected by the first snapped salkan 17 and the second snapped salkan 23 to form the wire 20. Since only the work of attaching the weight 25, the camera 41, and the camera cord 47 to 20 is more than the conventional work, and this work is relatively simple, To wander camera 41 is swinging, was by the camera 41 to be able to shorten dramatically the work time compared to conventional working time it took to imaging is complete. Specifically, the work time that has conventionally taken 1 hour can be reduced to, for example, about 10 minutes.

なお、上記説明では、重り25がコンクリート製電柱1の底に到達し、横倒しになった重り25を起立させてからカメラ41による中空部5内の撮像を行なっているが、本発明はこれに限定されるものでなく、重り25の重力によりワイヤ20を緊張させながらワイヤ20とともにカメラ41を下方に繰り出している最中に、下方に移動しつつあるカメラ41で中空部5内の各下方位置における撮像を適宜複数回行なってもよいものであることは勿論のことである。なお、この場合も、カメラ41を取り付けているワイヤ20は重り25により下方に引っ張られて緊張しているので、ワイヤ20およびカメラ41のふらつきはなく、カメラ41により中空部5内の画像を迅速に撮像できるものである。   In the above description, the weight 25 reaches the bottom of the concrete electric pole 1 and the weight 25 that has been laid down is raised, and then the inside of the hollow portion 5 is imaged by the camera 41. While not being limited, while the wire 20 is tensioned by the gravity of the weight 25 and the camera 41 is being fed downward together with the wire 20, each lower position in the hollow portion 5 is moved by the camera 41 moving downward. It goes without saying that the imaging in may be performed a plurality of times as appropriate. Also in this case, the wire 20 to which the camera 41 is attached is pulled downward by the weight 25 and is strained, so that there is no wobbling of the wire 20 and the camera 41, and the image in the hollow portion 5 is quickly displayed by the camera 41. Can be imaged.

更に、上記実施形態では、カメラ41はワイヤ20に取付部材43で固定的に取り付けられている場合について説明しているが、本発明はこれに限定されるものでなく、上述したようにカメラ41を最初にワイヤ20に固定的に取り付けることなく、ワイヤ20を重り25を用いて垂れ下ろして緊張させた後、この重り25を用いて緊張させた状態のワイヤ20に沿って後からカメラ41のみを下方に移動させ得るようにワイヤ20の直径よりも若干大きい直径を有するリングなどの環状部材をカメラ41に取り付け、この環状部材にワイヤ20を挿入して連結するなどしてカメラ41をワイヤ20に緩く連結し、この緩い連結状態で環状部材を用いてカメラ41をワイヤ20に沿って中空部5内を下方移動させたり、または場合によっては上方に戻るように移動させながらコンクリート製電柱1の中空部5内をカメラ41で撮像して確認してもよいものである。   Furthermore, in the above embodiment, the case where the camera 41 is fixedly attached to the wire 20 with the attachment member 43 has been described. However, the present invention is not limited to this, and as described above, the camera 41 is provided. First, the wire 20 is hung down and tensioned using the weight 25 without being fixedly attached to the wire 20, and then only the camera 41 is rearranged along the wire 20 in the tensioned state using the weight 25. An annular member such as a ring having a diameter slightly larger than the diameter of the wire 20 is attached to the camera 41, and the camera 41 is connected to the wire 20 by inserting and connecting the wire 20 to the annular member. In this loosely connected state, the camera 41 is moved downward along the wire 20 in the hollow portion 5 using the annular member, or in some cases While moving back towards the inside of the hollow portion 5 of the concrete electric pole 1 by imaging by the camera 41 is intended to be confirmed.

次に、図3を参照して、本発明の他の実施形態に係わるコンクリート製電柱内部確認方法について説明する。   Next, with reference to FIG. 3, the concrete electric pole inside confirmation method concerning other embodiment of this invention is demonstrated.

本実施形態は、図1で示したと同様な例えば長さが16〜17mの共架柱などの立設されたコンクリート製電柱1の中空部5に補強材としての棒状部材51を複数挿入する状態におけるコンクリート製電柱1の中空部5内をカメラ41で撮像して、複数の棒状部材51が適確に配置されているかなどの施工状態におけるコンクリート製電柱1の中空部5内の確認を行なうものである。   In the present embodiment, a state in which a plurality of rod-like members 51 as reinforcing materials are inserted into the hollow portion 5 of the concrete electric pole 1 erected, such as a 16 to 17 m long co-axial column, as shown in FIG. The inside of the hollow part 5 of the concrete electric pole 1 is imaged with the camera 41, and the inside of the hollow part 5 of the concrete electric pole 1 in the construction state such as whether the plurality of rod-like members 51 are properly arranged is confirmed. It is.

図3に示すように、本実施形態のコンクリート製電柱1は、前記開口部7の上方約200〜300mmの側面である外周部3に第2の開口部71が形成されている点が図1と異なっている。この第2の開口部71は、例えば縦が約250〜300mm、横が約20〜50mmのほぼ楕円形であり、補強材としての棒状部材51を複数、中空部5内に挿入するために使用される。この第2の開口部71は、例えばコンクリート製電柱1に設けられている足場ボルト部分を掘削して形成したり、またはコンクリート製電柱1の側部の外周部3を例えばコア抜きドリルなどを用いて形成してもよいものである。   As shown in FIG. 3, the concrete utility pole 1 of the present embodiment is that the second opening 71 is formed in the outer peripheral portion 3 that is a side surface of about 200 to 300 mm above the opening 7. Is different. The second opening 71 has, for example, a substantially oval shape with a length of about 250 to 300 mm and a width of about 20 to 50 mm, and is used to insert a plurality of rod-like members 51 as reinforcing materials into the hollow portion 5. Is done. The second opening 71 is formed by, for example, excavating a scaffold bolt portion provided in the concrete electric pole 1, or the outer peripheral portion 3 of the side portion of the concrete electric pole 1 using, for example, a cored drill or the like. May be formed.

なお、開口部7は、以下第1の開口部7と称することにするが、この第1の開口部7は、複数の棒状部材51を第2の開口部71から中空部5内に挿入した後、複数の棒状部材51の隙間に例えば豆砂利、砕石などの第1の隙間充填材を投入し、それからこの第1の隙間充填材の上に例えば無収縮モルタル、エポキシなどの樹脂またはコンクリートなどの第2の隙間充填材を投入するために使用されるものである。   The opening 7 is hereinafter referred to as the first opening 7, and the first opening 7 has a plurality of rod-like members 51 inserted into the hollow portion 5 from the second opening 71. Thereafter, a first gap filler such as pea gravel or crushed stone is introduced into the gaps between the plurality of rod-shaped members 51, and then, for example, non-shrink mortar, resin such as epoxy, concrete, or the like is placed on the first gap filler. The second gap filler is used.

コンクリート製電柱1の中空部5内に第1の開口部7から挿入される複数の棒状部材51は、各々図3に示すように、アラミド繊維請求項の棒状部材であるアラミドロッド51aと、この下方に連結されていて、棒状部材全体を安定化するための重りの役目を果たす異型鉄筋51bと、アラミドロッド51aを異型鉄筋51bに連結するためのアルミなどからなる連結部材51cとから構成されている。なお、図3では図示しないが、各棒状部材51を中空部5に挿入する過程において各棒状部材51を支持するためのワイヤが各棒状部材51の上端部、すなわちアラミドロッド51aの上端部に取り付けられているものである。アラミドロッド51aは、長さが例えば約1800〜3000mmであり、補強を行なう部分の条件などにより適宜調整される。また、異型鉄筋51bは、長さが例えば約700〜900mmである。   The plurality of rod-like members 51 inserted from the first opening 7 into the hollow portion 5 of the concrete electric pole 1 are each composed of an aramid rod 51a which is a rod-like member of an aramid fiber claim, as shown in FIG. It is composed of a deformed reinforcing bar 51b which is connected downward and serves as a weight for stabilizing the whole rod-shaped member, and a connecting member 51c made of aluminum or the like for connecting the aramid rod 51a to the deformed reinforcing bar 51b. Yes. Although not shown in FIG. 3, a wire for supporting each rod-like member 51 in the process of inserting each rod-like member 51 into the hollow portion 5 is attached to the upper end portion of each rod-like member 51, that is, the upper end portion of the aramid rod 51a. It is what has been. The aramid rod 51a has a length of, for example, about 1800 to 3000 mm, and is appropriately adjusted depending on conditions of a portion to be reinforced. The deformed reinforcing bar 51b has a length of about 700 to 900 mm, for example.

また、図3においては、コンクリート製電柱1の中空部5に挿入された複数の棒状部材51を中空部5において均等に配置するための補強材均等配置用冶具50が図示され、この補強材均等配置用冶具50は、前記第2の開口部71に図1と同様に挿入されたパイプ13を貫通して中空部5を下方に垂れ下ろされているワイヤ22の下端部から3本に分かれた分岐ワイヤ22aによって支持されている。なお、補強材均等配置用冶具50は、特にコンクリート製電柱1を傾斜して設置したような場合においてコンクリート製電柱1の中空部5に配置した複数の棒状部材51が中空部5内で傾斜して片方に寄ってしまったような場合、このような片方によって配置された複数の棒状部材51を中空部5内で片寄らずに均等に配置するためなどに使用されるものである。   Further, in FIG. 3, a reinforcing material uniform arrangement jig 50 for uniformly arranging a plurality of rod-like members 51 inserted into the hollow portion 5 of the concrete utility pole 1 in the hollow portion 5 is illustrated. The placement jig 50 is divided into three pieces from the lower end of the wire 22 that passes through the pipe 13 inserted into the second opening 71 in the same manner as in FIG. 1 and hangs down the hollow portion 5 downward. It is supported by the branch wire 22a. In the reinforcing material uniform arrangement jig 50, in particular, when the concrete electric pole 1 is installed in an inclined state, a plurality of rod-like members 51 arranged in the hollow part 5 of the concrete electric pole 1 are inclined in the hollow part 5. For example, when a plurality of rod-shaped members 51 arranged by one side are evenly arranged in the hollow portion 5 without being side-shifted.

補強材均等配置用冶具50は、詳しくは図4に示すように、鉄製の環状中心部材55と、この環状中心部材55の外周面に等間隔で取り付けられたU字形の複数の貫通部57とから構成され、環状中心部材55に均等に形成された3個の孔55aに前記3本の分岐ワイヤ22aの下端部が取り付けられ、この3本の分岐ワイヤ22aが1本のワイヤ22でまとめられ、上方から吊り下げられている。   As shown in detail in FIG. 4, the reinforcing material evenly-arranging jig 50 includes an iron annular center member 55 and a plurality of U-shaped through portions 57 attached to the outer peripheral surface of the annular center member 55 at equal intervals. The lower ends of the three branch wires 22 a are attached to three holes 55 a that are equally formed in the annular central member 55, and the three branch wires 22 a are combined by one wire 22. , Suspended from above.

また、環状中心部材55を吊り下げているワイヤ22の分岐ワイヤ22aに連結される下端部には、図1(b)に示したと同様なスナップ付サルカン53を介して重り59が取り付けられ、ワイヤ22を環状中心部材55とともに下方に引っ張って緊張させる役目を果たしている。すなわち、ワイヤ22に対しては、重り59のみならず、環状中心部材55の重量も重り59と同様に重りの役目を果たしているのである。なお、この場合の重り59の重量は、例えば約200gであり、環状中心部材55の重量と合わせると、全体としてワイヤ22に対する重量は、300〜350g程度である。   Further, a weight 59 is attached to the lower end portion of the wire 22 suspending the annular center member 55 connected to the branch wire 22a through a snap-in salcan 53 similar to that shown in FIG. It plays a role of pulling 22 downward together with the annular central member 55 to be tensioned. That is, not only the weight 59 but also the weight of the annular central member 55 plays the role of a weight in the same manner as the weight 59. In this case, the weight of the weight 59 is, for example, about 200 g. When combined with the weight of the annular center member 55, the weight of the wire 22 as a whole is about 300 to 350 g.

上述したように、環状中心部材55および重り59を吊り下げているワイヤ22の下端部寄り、詳しくはワイヤ22が3本の分岐ワイヤ22aに連結されるワイヤ22の下端部から例えば約20mm上方の位置のワイヤ22には、図2に示したと同様なカメラ41が撮像レンズを下向きにしてビニールテープなどの取付部材43で固定的に取り付けられている。また、カメラ41の下端部には水センサ41aが露出している。   As described above, near the lower end portion of the wire 22 suspending the annular central member 55 and the weight 59, more specifically, for example, about 20 mm above the lower end portion of the wire 22 connected to the three branch wires 22a. A camera 41 similar to that shown in FIG. 2 is fixedly attached to the position wire 22 with an attachment member 43 such as a vinyl tape with the imaging lens facing downward. A water sensor 41 a is exposed at the lower end of the camera 41.

また、カメラ41に接続されたカメラコード47は、ワイヤ22に沿って中空部5内を上方に配設され、第2の開口部71を通って外部に設けられたモニタ49に接続されている。   The camera cord 47 connected to the camera 41 is disposed upward in the hollow portion 5 along the wire 22, and is connected to a monitor 49 provided outside through the second opening 71. .

次に、上述した本実施形態のコンクリート製電柱内部確認方法の複数の棒状部材51をコンクリート製電柱1内に挿入し、補強材均等配置用冶具50を用いて均等に配置して補強する施工状態において棒状部材51の設置状態などをカメラ41で撮像して確認するための一連の確認動作手順について説明する。なお、第1の開口部7および第2の開口部71は、既に形成されているものとして説明する。   Next, a construction state in which a plurality of rod-like members 51 in the concrete electric pole internal confirmation method of the present embodiment described above are inserted into the concrete electric pole 1 and evenly arranged and reinforced using the reinforcing material uniform arrangement jig 50. A series of confirmation operation procedures for imaging and confirming the installation state of the rod-like member 51 with the camera 41 will be described. In addition, the 1st opening part 7 and the 2nd opening part 71 are demonstrated as what is already formed.

まず、補強材均等配置用冶具50に3本の分岐ワイヤ22aを介してワイヤ22を取り付けるとともに、このワイヤ22に図4で説明したようにカメラ41を取付部材43で取り付け、カメラコード47をワイヤ22に沿わせるように用意する。   First, the wire 22 is attached to the reinforcing material uniform arrangement jig 50 via the three branch wires 22a, and the camera 41 is attached to the wire 22 with the attachment member 43 as described with reference to FIG. Prepare to be along 22nd.

次に、ワイヤ22およびカメラコード47のついた補強材均等配置用冶具50を第2の開口部71からコンクリート製電柱1の中空部5に挿入する。そして、この中空部5に挿入された補強材均等配置用冶具50の各貫通部57に棒状部材51を1本ずつ第2の開口部71を介して挿入するように各棒状部材51を異型鉄筋51bのある下端部側から第2の開口部71を介して棒状部材51の各貫通部57に挿入する。なお、棒状部材51を構成するアラミドロッド51aは、比較的柔軟なアラミド繊維で形成されているものであるため、アラミドロッド51aは第2の開口部71を貫通して下方に湾曲しながら、中空部5に挿入された補強材均等配置用冶具50の各貫通部57に比較的容易に挿入することが可能である。   Next, the reinforcing material uniform arrangement jig 50 with the wire 22 and the camera cord 47 is inserted into the hollow portion 5 of the concrete utility pole 1 from the second opening 71. And each rod-shaped member 51 is deformed reinforcing bar so that one rod-shaped member 51 may be inserted into each penetration portion 57 of the reinforcing material uniform arrangement jig 50 inserted into the hollow portion 5 through the second opening 71. It inserts into each penetration part 57 of the rod-shaped member 51 through the 2nd opening part 71 from the lower end part side with 51b. In addition, since the aramid rod 51a which comprises the rod-shaped member 51 is formed with a comparatively flexible aramid fiber, the aramid rod 51a penetrates the 2nd opening part 71, is curving below, and is hollow. It is possible to insert the reinforcing material evenly arranged jig 50 inserted into the portion 5 into each through portion 57 relatively easily.

複数の棒状部材51のすべてが中空部5に挿入された補強材均等配置用冶具50の各貫通部57に挿入されると、各棒状部材51を徐々に中空部5内の下方に向けて繰り出すとともに、この繰り出しに合わせて補強材均等配置用冶具50およびカメラ41もワイヤ22およびカメラコード47を保持しながら同様に中空部5内の下方に向けて繰り出すが、この場合、カメラコード47の上端部をパイプ13に通し、このパイプ13を第2の開口部71から中空部5内の断面のほぼ中央に出すことによりカメラコード47は中空部5内の断面のほぼ中央に沿って繰り出されることになる。   When all of the plurality of rod-shaped members 51 are inserted into the respective through portions 57 of the reinforcing material evenly arranged jig 50 inserted into the hollow portion 5, the respective rod-shaped members 51 are gradually fed out downward in the hollow portion 5. At the same time, the jig 50 and the camera 41 for evenly arranging the reinforcing material are also fed downward toward the inside of the hollow portion 5 while holding the wire 22 and the camera cord 47 in accordance with this feeding. The camera cord 47 is fed out along substantially the center of the cross section in the hollow portion 5 by passing the pipe 13 through the pipe 13 and taking out the pipe 13 from the second opening 71 to the center of the cross section in the hollow portion 5. become.

なお、この繰り出しにおいては、各棒状部材51は、それぞれの下端部に連結された異型鉄筋51bの重りの重量により繰り出しが容易に行なわれ、また補強材均等配置用冶具50およびカメラ41は、補強材均等配置用冶具50自身の重量と重り59の重力により繰り出しが容易に行なわれているものである。   In this extension, each bar-shaped member 51 is easily extended by the weight of the weight of the deformed reinforcing bar 51b connected to the respective lower ends thereof, and the reinforcing material uniform arrangement jig 50 and the camera 41 are reinforced. The material is evenly fed out by the weight of the uniform material arranging jig 50 itself and the gravity of the weight 59.

このような下方への繰り出しにより、各棒状部材51が中空部5内に挿入されると、各棒状部材51の上端部に取り付けられている図示しない前記ワイヤを第2の開口部71を介して外部で保持しながら各棒状部材51を補強材均等配置用冶具50およびカメラ41とともに更に中空部5を下方に繰り出し、この繰り出しを図3に示すように、各棒状部材51の下端部がコンクリート製電柱1の最下端部の底に当るまで行なう。   When each rod-like member 51 is inserted into the hollow portion 5 by such downward feeding, the wire (not shown) attached to the upper end portion of each rod-like member 51 is passed through the second opening 71. While holding outside, each bar-shaped member 51 is further extended downward together with the reinforcing member uniform arrangement jig 50 and camera 41, and the lower end of each bar-shaped member 51 is made of concrete as shown in FIG. Continue until it hits the bottom of the lowest end of the utility pole 1.

図3に示すように、各棒状部材51の下端部がコンクリート製電柱1の底に当ると、繰り出しをここで停止する。この状態では、各棒状部材51は補強材均等配置用冶具50により中空部5内に片寄ることもなく等間隔で均等に配置される。また、補強材均等配置用冶具50を吊り下げているワイヤ22の下端部寄りに取り付けられたカメラ41は、図3に示すように撮像レンズのある下端部がコンクリート製電柱1の底の方を向いて補強材均等配置用冶具50の上方に位置しているので、この状態で撮像を行うと、カメラ41はコンクリート製電柱1の中空部5内の下方の画像、すなわち複数の棒状部材51が配置されている画像を撮像できる。この画像をカメラコード47を介してモニタ49に送ることにより、モニタ49には複数の棒状部材51が中空部5内において均等に配置されている状態の画像がモニタ49に表示され、各棒状部材51の設置状態およびコンクリート製電柱1の中空部5内の下方の状態を適確に確認することができる。   As shown in FIG. 3, when the lower end part of each bar-shaped member 51 hits the bottom of the concrete electric pole 1, the feeding is stopped here. In this state, the rod-like members 51 are evenly arranged at equal intervals without being offset into the hollow portion 5 by the reinforcing material uniform placement jig 50. Further, the camera 41 attached near the lower end of the wire 22 that suspends the reinforcing material equalizing jig 50 has a lower end with an imaging lens at the bottom of the concrete electric pole 1 as shown in FIG. Since it faces and is located above the reinforcing material uniform arrangement jig 50, when imaging is performed in this state, the camera 41 displays a lower image in the hollow portion 5 of the concrete power pole 1, that is, a plurality of rod-shaped members 51. The arranged image can be taken. By sending this image to the monitor 49 via the camera code 47, the monitor 49 displays on the monitor 49 an image in which a plurality of rod-like members 51 are evenly arranged in the hollow portion 5, and each rod-like member is displayed. The installation state of 51 and the lower state in the hollow part 5 of the concrete electric pole 1 can be confirmed appropriately.

なお、図3に示すように、各棒状部材51の下端部がコンクリート製電柱1の底に当った後、第2の開口部71を介して外部に出ているワイヤ22およびカメラコード47を適宜上方に繰り上げるなどして、補強材均等配置用冶具50およびカメラ41の上下方向の位置を調整し得ることは勿論のことである。   In addition, as shown in FIG. 3, after the lower end part of each rod-shaped member 51 hits the bottom of the concrete electric pole 1, the wire 22 and the camera cord 47 that are exposed to the outside through the second opening 71 are appropriately connected. Of course, it is possible to adjust the vertical position of the reinforcing member evenly-arranged jig 50 and the camera 41 by moving it upward.

上述したように各棒状部材51がコンクリート製電柱1の底の中空部5内において均等に配置されたことをカメラ41による画像で確認すると、次にワイヤ22およびカメラコード47を上方にたぐるように繰り上げて、補強材均等配置用冶具50およびカメラ41を中空部5内を上方に引き上げ、第2の開口部71から取り出す。   As described above, when it is confirmed from the image by the camera 41 that the rod-like members 51 are evenly arranged in the hollow portion 5 at the bottom of the concrete utility pole 1, the wire 22 and the camera cord 47 are next tapped upward. The reinforcing material evenly-arranged jig 50 and the camera 41 are pulled upward in the hollow portion 5 and taken out from the second opening 71.

このように補強材均等配置用冶具50およびカメラ41を第2の開口部71を介して中空部5から取り出した後、第1の開口部7から中空部5内に例えば豆砂利、砕石などの第1の隙間充填材を投入して各棒状部材51の透間に充填し、更にこの上に例えば無収縮モルタル、エポキシなどの樹脂またはコンクリートなどの第2の隙間充填材を投入して同様に各棒状部材51の透間に充填し、これによりコンクリート製電柱1を補強することができる。   In this way, after the reinforcing material uniform arrangement jig 50 and the camera 41 are taken out from the hollow portion 5 through the second opening 71, for example, pea gravel, crushed stone, etc. from the first opening 7 into the hollow portion 5. A first gap filler is introduced and filled between the respective rod-shaped members 51, and a second gap filler such as a non-shrink mortar, an epoxy resin, or concrete is introduced thereon in the same manner. It fills between each bar-shaped member 51, and can reinforce the concrete electric pole 1 by this.

次に、図5を参照して、本発明の別の実施形態に係わるコンクリート製電柱内部確認方法について説明する。   Next, with reference to FIG. 5, the concrete electric pole inside confirmation method concerning another embodiment of this invention is demonstrated.

本実施形態のコンクリート製電柱内部確認方法は、図1に示した実施形態における例えば共架柱などのコンクリート製電柱1の代わりに例えば長さが6〜7mの単独柱などのコンクリート製電柱10の中空部5内の状態を事前に確認するものであり、コンクリート製電柱が単独柱のコンクリート製電柱10に変更されている第1の点、および図1で説明した重り25のついたワイヤ20と、このワイヤ20に取付部材43で取り付けられたカメラ41と、このカメラ41に連結されたカメラコード47とをコンクリート製電柱10の中空部5内のほぼ中央に垂れ下ろすために、図1で説明した開口部7を使用せずに、コンクリート製電柱10の最上端に形成された上端末口部10aを使用し、この上端末口部10aからワイヤ20、カメラ41およびカメラコード47をコンクリート製電柱10の中空部5に挿入して垂れ下ろすようにした第2の点が図1の実施形態と異なるものであり、これらの点に関する以外の他の構成は図1と同じであり、同じ構成要素には同じ符号が付されている。   The concrete electric pole inside confirmation method of this embodiment is, for example, a concrete electric pole 10 such as a single pole having a length of 6 to 7 m instead of the concrete electric pole 1 such as a suspended pole in the embodiment shown in FIG. 1. The state in the hollow portion 5 is confirmed in advance, and the first point in which the concrete utility pole is changed to a single concrete utility pole 10 and the wire 20 with the weight 25 described in FIG. In order to hang down the camera 41 attached to the wire 20 with the attachment member 43 and the camera cord 47 connected to the camera 41 to substantially the center in the hollow portion 5 of the concrete electric pole 10, it will be described with reference to FIG. The upper terminal opening 10a formed at the uppermost end of the concrete electric pole 10 is used without using the opened opening 7, and the wire 20 and the camera 4 are connected to the upper terminal opening 10a. 2 is different from the embodiment shown in FIG. 1 in that the camera cord 47 is inserted into the hollow portion 5 of the concrete electric pole 10 to be hung down. Other configurations other than these points are shown in FIG. The same components are denoted by the same reference numerals.

上記第2の点を実施するために、図5に示す実施形態では、コンクリート製電柱10の最上端に形成された上端末口部10aに例えば棒状または板状の支持部材61を取り付け、この支持部材61の先端をコンクリート製電柱10の中空部5の断面のほぼ中央まで延出し、この中央に延出した支持部材61の先端に滑車などのような外周面に溝の形成された回転部材63を取り付ける。この回転部材63の溝に前記ワイヤ20をかけるとともに、このワイヤ20の先端を前記支持部材61の端部に取り付けられた例えば釣りのリールのような巻取器65に巻回し、この巻取器65をハンドルなどで回転することによりワイヤ20を巻き取ったり、巻き戻してコンクリート製電柱10の中空部5に垂れ下ろすことができるように構成している。なお、カメラ41に連結されたカメラコード47は、ワイヤ22に沿って上端末口部10aから外部に延出し、モニタ49に接続されている。   In order to implement the second point, in the embodiment shown in FIG. 5, for example, a rod-like or plate-like support member 61 is attached to the upper terminal opening 10 a formed at the uppermost end of the concrete electric pole 10, and this support is provided. A rotating member 63 in which the tip of the member 61 extends to substantially the center of the cross section of the hollow portion 5 of the concrete electric pole 10 and a groove is formed on the outer peripheral surface such as a pulley at the tip of the support member 61 extending to the center. Install. The wire 20 is put in the groove of the rotating member 63, and the tip of the wire 20 is wound around a winder 65 such as a fishing reel attached to the end of the support member 61. By rotating 65 with a handle or the like, the wire 20 can be wound or unwound and hung down to the hollow portion 5 of the concrete electric pole 10. The camera cord 47 connected to the camera 41 extends outside from the upper terminal opening 10 a along the wire 22 and is connected to the monitor 49.

このように構成される図5に示す実施形態のコンクリート製電柱内部確認方法は、図1の実施形態においてワイヤ20、カメラ41、カメラコード47を開口部7から中空部5に挿入して下方に垂れ下ろすというワイヤ20、カメラ41、カメラコード47の挿入垂下し処理がコンクリート製電柱10の上端末口部10aから巻取器65を用いて行なわれているものであり、その他の作用および効果は基本的に同じであるが、本実施形態では、巻取器65を使用しているため、図1の実施形態に比較して操作性に優れているという利点がある。   The concrete electric pole inside confirmation method of embodiment shown in FIG. 5 comprised in this way inserts the wire 20, the camera 41, and the camera cord 47 in the hollow part 5 from the opening part 7 in embodiment of FIG. The wire 20, the camera 41, and the camera cord 47, which is hanging down, is suspended from the upper terminal opening 10 a of the concrete electric pole 10 using the winder 65, and other functions and effects are as follows. Although basically the same, in this embodiment, since the winder 65 is used, there is an advantage that the operability is excellent as compared with the embodiment of FIG.

次に、図6を参照して、本発明の更に他の実施形態に係わるコンクリート製電柱内部確認方法について説明する。   Next, with reference to FIG. 6, the concrete electric pole inside confirmation method concerning other embodiment of this invention is demonstrated.

本実施形態は、図3の実施形態において例えば共架柱等のコンクリート製電柱1の代わりに図5の実施形態と同様に例えば長さが6〜7mの単独柱などのコンクリート製電柱10の中空部5内の施工状態、即ち複数の棒状部材51が適正に配置されているかなどの施工状態を確認するものであり、コンクリート製電柱が単独柱のコンクリート製電柱10に変更されている第1の点、中空部5に挿入された複数の棒状部材51を均等に配置するために前記補強材均等配置用冶具50の代わりに軸棒72に取り付けられた別の補強材均等配置用冶具70を2個用いて複数の棒状部材51を中空部5内に均等に配置する第2の点、および補強材均等配置用冶具70を中空部5内に挿入したために図5で説明したワイヤ20、カメラ41、カメラコード47を中空部5内の真中に挿入して垂れ下ろすことが困難となり、これらを中空部5内の縁部寄りの部分に上端末口部10aから垂れ下ろした第3の点の3つの点が異なることが図3および図5に示した実施形態と異なるものであり、その他の構成および作用は同じであり、同じ構成要素には同じ符号を付している。なお、本実施形態では、コンクリート製電柱10の上端の上端末口部10aに取り付けられる支持部材61の先端および回転部材63は、図5のように上端末口部10aの中程まで延出されず、上端末口部10aの縁部に固定されている。   In the embodiment shown in FIG. 3, the concrete electric pole 10 such as a single pole having a length of 6 to 7 m, for example, is used instead of the concrete electric pole 1 such as a suspended pole in the embodiment shown in FIG. 5. The construction state in the part 5, that is, the construction state such as whether or not the plurality of rod-like members 51 are properly arranged is confirmed, and the concrete power pole is changed to a single concrete power pole 10. In order to evenly arrange the plurality of rod-shaped members 51 inserted into the hollow portion 5, another reinforcing material equalizing jig 70 attached to the shaft rod 72 is used instead of the reinforcing material equalizing jig 50. The second point for evenly arranging the plurality of rod-like members 51 in the hollow portion 5 by using the individual, and the wire 20 and the camera 41 described with reference to FIG. 5 because the reinforcing material equalizing jig 70 is inserted into the hollow portion 5. , Camera cord 47 becomes difficult to insert and hang down in the middle of the hollow portion 5, and the three points of the third point that hangs down from the upper terminal opening 10 a to the portion near the edge in the hollow portion 5 are 3 and 5 is different from the embodiment shown in FIGS. 3 and 5, the other configurations and operations are the same, and the same components are denoted by the same reference numerals. In addition, in this embodiment, the front-end | tip of the supporting member 61 attached to the upper end port part 10a of the upper end of the concrete electric pole 10, and the rotation member 63 are extended to the middle of the upper end port part 10a like FIG. It is being fixed to the edge of upper terminal mouth part 10a.

本実施形態において、複数の棒状部材51を中空部5内に均等に配置するために使用される補強材均等配置用冶具70は、図6に示すように、コンクリート製電柱10の中空部5内のほぼ中央に垂直にコンクリート製電柱10の最下端部の底まで挿入された軸棒72に取り付けられて、複数の棒状部材51を中空部5内で均等に配置するようになっている。なお、図6においては、補強材均等配置用冶具70は、コンクリート製電柱10の中空部5内の最下端の底に近い位置とこの位置より少し上方の位置の2ヶ所において複数の棒状部材51を均等に配置するように2個設けられているが、両補強材均等配置用冶具70は同じ構造のものである。   In the present embodiment, the reinforcing material uniform arrangement jig 70 used for evenly arranging the plurality of rod-shaped members 51 in the hollow portion 5 is provided in the hollow portion 5 of the concrete electric pole 10 as shown in FIG. A plurality of rod-like members 51 are evenly arranged in the hollow portion 5 by being attached to a shaft rod 72 inserted to the bottom of the lowermost end portion of the concrete electric pole 10 perpendicularly to the center. In FIG. 6, the reinforcing material equalizing jig 70 has a plurality of rod-shaped members 51 at two positions, a position near the bottom of the lowermost end in the hollow portion 5 of the concrete electric pole 10 and a position slightly above this position. Are provided so as to be evenly arranged, but both reinforcing material equalizing jigs 70 have the same structure.

この補強材均等配置用冶具70は、詳しくは図7に示すように、複数の棒状部材51が貫通する複数の貫通部138を有し、この複数の貫通部138で複数の棒状部材51を支持して均等に配置するようになっている。なお、補強材均等配置用冶具70が取り付けられている軸棒72は、下端部に石突き73が取り付けられ、この石突き73がコンクリート製電柱10の最下端部の底に当って固定されている。図7に示す他の構成要素およびその配置は、先の実施形態で説明したものと同じであり、同じ構成要素には同じ符号が付されている。   As shown in detail in FIG. 7, the reinforcing material uniform arrangement jig 70 has a plurality of through portions 138 through which the plurality of rod-like members 51 penetrate, and the plurality of through-holes 138 support the plurality of rod-like members 51. And are arranged evenly. In addition, the shaft rod 72 to which the reinforcing material equalizing jig 70 is attached has a stone bump 73 attached to the lower end portion, and this stone bump 73 is fixed by hitting the bottom of the lowermost end portion of the concrete electric pole 10. Yes. The other components shown in FIG. 7 and their arrangement are the same as those described in the previous embodiment, and the same components are given the same reference numerals.

補強材均等配置用冶具70は、更に詳しくは図8に示すように、前記貫通部138が取り付けられている上腕部133と下腕部134からなる4個の腕部13Aを有し、貫通部138は上腕部133および下腕部134の中程に形成された孔部136に挿入可能な連結部139を有し、この連結部139を上腕部133または下腕部134のいずれかの孔部136に挿入することにより取り付けられている。なお、上腕部133と下腕部134を互いに可動自在に連結している肘部には、補強材均等配置用冶具70をコンクリート製電柱10の中空部5に挿入した時に、外周部3の内側面に当ることにより補強材均等配置用冶具70の水平方向への展開を容易にする平座金(プレーンワッシャ)135が可動自在に取り付けられている。   As shown in more detail in FIG. 8, the reinforcing material uniform arrangement jig 70 has four arm portions 13A including an upper arm portion 133 and a lower arm portion 134 to which the through portion 138 is attached. 138 has a connecting portion 139 that can be inserted into a hole 136 formed in the middle of the upper arm portion 133 and the lower arm portion 134, and this connecting portion 139 is a hole portion of either the upper arm portion 133 or the lower arm portion 134. It is attached by inserting in 136. It should be noted that the elbow part that movably connects the upper arm part 133 and the lower arm part 134 to each other is provided inside the outer peripheral part 3 when the reinforcing material equalizing jig 70 is inserted into the hollow part 5 of the concrete electric pole 10. A flat washer 135 that facilitates the horizontal deployment of the reinforcing material equalizing jig 70 by being in contact with the side surface is movably attached.

更に詳しくは、貫通部138は、連結部139により腕部13Aに取り付けられる場合、隣接する腕部13A同士において貫通部138が上腕部133および下腕部134の同じ側にならず、交互になるように変更して取り付けられている。換言すると、ある腕部13Aにおいて貫通部138が上腕部133に取り付けられる場合には、その腕部13Aに両隣りで隣接する腕部13Aでは貫通部138は下腕部134に取り付けられるようになっている。   More specifically, when the penetrating portions 138 are attached to the arm portions 13A by the connecting portions 139, the penetrating portions 138 do not become the same side of the upper arm portion 133 and the lower arm portion 134 between the adjacent arm portions 13A, but alternately. It is changed and attached as follows. In other words, when the penetrating portion 138 is attached to the upper arm portion 133 in a certain arm portion 13A, the penetrating portion 138 is attached to the lower arm portion 134 in the arm portion 13A adjacent to the arm portion 13A on both sides. ing.

また、複数の下腕部134の各下端部は、固定連結部132により軸棒72に固定的に取り付けられ、また各上腕部133は、可動連結部131により軸棒72に対して摺動可能に取り付けられ、この可動連結部131を固定連結部132に対して上方に移動させた場合には、補強材均等配置用冶具70は、図9に示すように、上腕部133および下腕部134からなる腕部13Aが閉じて全体的に細くなり、これによりコンクリート製電柱10の最上端の上端末口部10aから中空部5内に容易に挿入し得るようになっている。   In addition, the lower end portions of the plurality of lower arm portions 134 are fixedly attached to the shaft rod 72 by the fixed connecting portions 132, and the upper arm portions 133 are slidable with respect to the shaft rod 72 by the movable connecting portions 131. When the movable connecting portion 131 is moved upward with respect to the fixed connecting portion 132, the reinforcing member uniform arrangement jig 70 has the upper arm portion 133 and the lower arm portion 134 as shown in FIG. The arm portion 13 </ b> A is closed and becomes thinner as a whole, so that it can be easily inserted into the hollow portion 5 from the upper end port portion 10 a of the uppermost end of the concrete electric pole 10.

なお、図8に示すように、各下腕部134の下端部が取り付けられている固定連結部132の位置よりも少し上方の位置には、ストッパ137が軸棒72に固定的に取り付けられ、これにより各上腕部133の上端部を軸棒72に対して摺動可能に取り付けている可動連結部131は、このストッパ137よりも下方に移動しないようになっている。   As shown in FIG. 8, a stopper 137 is fixedly attached to the shaft rod 72 at a position slightly above the position of the fixed connecting portion 132 to which the lower end portion of each lower arm portion 134 is attached. As a result, the movable connecting portion 131 slidably attaching the upper end portion of each upper arm portion 133 to the shaft rod 72 is prevented from moving below the stopper 137.

また、各貫通部138は、同じ径を有する2個の半円環型部材138aおよび138bの端部同士を互いに可動自在に取り付けられている。そして、一方の半円環型部材138aの中程に前記連結部139が取り付けられ、この連結部139により腕部13Aの孔部136に取り付けられている。   Moreover, each penetration part 138 is attached so that the edge parts of the two semi-annular members 138a and 138b which have the same diameter can move mutually. And the said connection part 139 is attached to the middle of one semi-annular member 138a, and is attached to the hole 136 of the arm part 13A by this connection part 139.

以上のように構成される補強材均等配置用冶具70を図6に示すように2個用いて、複数の棒状部材51をコンクリート製電柱10の上端末口部10aから中空部5内に挿入して均等に配置される施工時において、この施工により複数の棒状部材51が適確かつ均等に配置されているかを確認するために、本実施形態では、コンクリート製電柱10の上端末口部10aからワイヤ20を用いてカメラ41を中空部5内に垂れ下ろし、このカメラ41で中空部5内の状態を撮像してモニタ49に表示したり記録して確認する。   As shown in FIG. 6, the two reinforcing member uniform arrangement jigs 70 configured as described above are used, and a plurality of rod-shaped members 51 are inserted into the hollow portion 5 from the upper end port portion 10a of the concrete electric pole 10. In this embodiment, in order to confirm whether or not the plurality of rod-like members 51 are properly and evenly arranged by this construction, in the present embodiment, from the upper terminal mouth portion 10a of the concrete electric pole 10 The camera 41 is hung down in the hollow portion 5 using the wire 20, and the state in the hollow portion 5 is imaged by the camera 41 and displayed on the monitor 49 or recorded and confirmed.

このカメラ41による撮像確認処理は、図5と同様に支持部材61、回転部材63、ハンドル65a付きの巻取器65を用いて垂れ下ろす重り25付きのワイヤ20にカメラ41およびカメラコード47を取付部材43、45で固定的に取り付け、このカメラ41の取り付けられたワイヤ20を中空部5内に垂れ下ろすが、本実施形態では、補強材としての複数の棒状部材51とこの複数の棒状部材51を均等に配置するための2個の補強材均等配置用冶具70が既に中空部5内に挿入されていて、中空部5の中程部分はかなり混み合っていて、この部分にワイヤ20により重り25およびカメラ41を垂れ下ろすことは困難であり、中空部5の縁寄り部分に重り25およびカメラ41を垂れ下ろす隙間があるのみであるので、この縁寄り部分の隙間に重り25およびカメラ41を垂れ下ろすために、本実施形態では、図6に示すように、コンクリート製電柱10の上端末口部10aの縁部に支持部材61の先端を設定して回転部材63を取り付け、この回転部材63から巻取器65に巻回されたワイヤ20を中空部5内に垂れ下ろすようにしている。   In this imaging confirmation process by the camera 41, the camera 41 and the camera cord 47 are attached to the wire 20 with the weight 25 that hangs down using the winder 65 with the support member 61, the rotating member 63, and the handle 65a as in FIG. The members 43 and 45 are fixedly attached, and the wire 20 to which the camera 41 is attached is suspended in the hollow portion 5. In this embodiment, a plurality of rod-shaped members 51 as reinforcing members and the plurality of rod-shaped members 51 are used. Two reinforcing material equalizing jigs 70 are arranged in the hollow portion 5 and the middle portion of the hollow portion 5 is considerably crowded. 25 and the camera 41 are difficult to hang down, and there is only a gap to hang down the weight 25 and the camera 41 at the edge portion of the hollow portion 5. In this embodiment, the tip of the support member 61 is set at the edge of the upper terminal mouth portion 10a of the concrete utility pole 10 and is rotated in order to hang the weight 25 and the camera 41 in the gap of FIG. A member 63 is attached, and the wire 20 wound around the winder 65 from the rotating member 63 is suspended in the hollow portion 5.

すなわち、本実施形態では、図6に示すように、2個の補強材均等配置用冶具70を用いて複数の棒状部材51が中空部5内に均等に配置された施工状態を確認するために、第1のワイヤ15、第2のワイヤ19、第3のワイヤ23を第1のスナップ付サルカン17、第2のスナップ付サルカン23で連結して形成されるワイヤ20の下端部に重り25を取り付けるとともに、このワイヤ20にカメラ41およびカメラコード47を取付部材43、取付部材45で固定的に取り付ける。   That is, in this embodiment, as shown in FIG. 6, in order to confirm the construction state in which the plurality of rod-shaped members 51 are evenly arranged in the hollow portion 5 using the two reinforcing material equalizing jigs 70. A weight 25 is attached to the lower end portion of the wire 20 formed by connecting the first wire 15, the second wire 19, and the third wire 23 with the first snapped salcan 17 and the second snapped salkan 23. At the same time, the camera 41 and the camera cord 47 are fixedly attached to the wire 20 with the attachment member 43 and the attachment member 45.

そして、このカメラ41の取り付けられたワイヤ20をコンクリート製電柱10の上端末口部10aから中空部5内に重り25を下にして垂れ下ろすように設定するとともに、ワイヤ20の上端部側を上端末口部10aの縁寄り部分に固定された回転部材63を介して巻取器65に巻回しておく。そして、巻取器65のハンドル65aをゆっくりと回転しながら巻取器65に巻回されたワイヤ20を巻き戻すことによりワイヤ20を上端末口部10aの縁部寄りから中空部5の縁部に沿って徐々に中空部5内に繰り出す。この結果、ワイヤ20に取り付けられたカメラ41は、下端部に取り付けられた重り25により中空部5の縁部に沿って中空部5内を下方に垂れ下ろされる。   Then, the wire 20 to which the camera 41 is attached is set so as to hang down from the upper end port portion 10a of the concrete electric pole 10 into the hollow portion 5 with the weight 25 down, and the upper end portion side of the wire 20 is turned up. It winds around the winder 65 via the rotating member 63 fixed to the edge portion of the terminal opening 10a. Then, by rewinding the wire 20 wound around the winder 65 while slowly rotating the handle 65a of the winder 65, the wire 20 is moved from the edge of the upper terminal opening 10a toward the edge of the hollow portion 5. Are gradually fed into the hollow portion 5 along As a result, the camera 41 attached to the wire 20 hangs down inside the hollow portion 5 along the edge of the hollow portion 5 by the weight 25 attached to the lower end portion.

このようにカメラ41がワイヤ20により重り25の重力で中空部5内を下方に垂れ下ろされ、重り25が中空部5の最下端部の底に当り、一旦横倒しになる。この横倒しになった重り25を起立させるべく巻取器65のハンドル65aを操作してワイヤ20を巻き取り、重り25を起立させる。   Thus, the camera 41 is hung down in the hollow portion 5 by the gravity of the weight 25 by the wire 20, and the weight 25 hits the bottom of the lowermost end portion of the hollow portion 5 and is temporarily laid down. The handle 65a of the winder 65 is operated to stand up the weight 25 that has been laid down, the wire 20 is wound up, and the weight 25 is raised up.

重り25が起立すると、ワイヤ20は、引っ張られて緊張するので、この緊張を維持した状態で巻取器65のハンドルを固定すると、ワイヤ20は従来のように揺れてふらつくこともなく固定される。この結果、ワイヤ20に取り付けられているカメラ41も揺れてふらつくこともなくなる。従って、この状態でカメラ41によりコンクリート製電柱10の中空部5内を撮像することにより、鮮明な画像を得ることができる。   When the weight 25 rises, the wire 20 is pulled and is tensioned. When the handle of the winder 65 is fixed with this tension maintained, the wire 20 is fixed without shaking and swinging as in the conventional case. . As a result, the camera 41 attached to the wire 20 does not shake and fluctuate. Therefore, a clear image can be obtained by imaging the inside of the hollow portion 5 of the concrete electric pole 10 with the camera 41 in this state.

本発明の一実施形態に係わるコンクリート製電柱内部確認方法を説明するためのコンクリート製電柱の断面およびコンクリート製電柱の中空部内の確認作業に必要な関連部材および装置を示す図である。It is a figure which shows the related member and apparatus required for the confirmation operation in the cross section of the concrete electric pole, and the hollow part of a concrete electric pole for demonstrating the concrete electric pole inside confirmation method concerning one Embodiment of this invention. 図1に示す実施形態のコンクリート製電柱内部確認方法に使用されるカメラの構成を示す図である。It is a figure which shows the structure of the camera used for the concrete electric pole inside confirmation method of embodiment shown in FIG. 本発明の他の実施形態に係わるコンクリート製電柱内部確認方法を説明するためのコンクリート製電柱の断面およびコンクリート製電柱の中空部内の確認作業に必要な関連部材および装置を示す図である。It is a figure which shows the related member and apparatus required for the confirmation operation in the cross section of the concrete electric pole, and the hollow part of a concrete electric pole for demonstrating the concrete electric pole inside confirmation method concerning other embodiment of this invention. 図3に示す実施形態のコンクリート製電柱内部確認方法に使用される補強材均等配置用冶具の構成を示す斜視図である。It is a perspective view which shows the structure of the jig for reinforcement material equal arrangement | positioning used for the concrete electric pole inside confirmation method of embodiment shown in FIG. 本発明の別の実施形態に係わるコンクリート製電柱内部確認方法を説明するためのコンクリート製電柱の断面およびコンクリート製電柱の中空部内の確認作業に必要な関連部材および装置を示す図である。It is a figure which shows the related member and apparatus required for the confirmation operation in the cross section of the concrete electric pole and the hollow part of a concrete electric pole for demonstrating the concrete electric pole inside confirmation method concerning another embodiment of this invention. 本発明の更に他の実施形態に係わるコンクリート製電柱内部確認方法を説明するためのコンクリート製電柱の断面およびコンクリート製電柱の中空部内の確認作業に必要な関連部材および装置を示す図である。It is a figure which shows the related member and apparatus required for the check operation | work in the cross section of the concrete electric pole, and the hollow part of a concrete electric pole for demonstrating the concrete electric pole inside confirmation method concerning other embodiment of this invention. 図6に示した実施形態のコンクリート製電柱内部確認方法に使用される補強材均等配置用冶具の構成を示す斜視図である。It is a perspective view which shows the structure of the jig | tool for reinforcement material equal arrangement | positioning used for the concrete electric pole inside confirmation method of embodiment shown in FIG. 図6に示した実施形態のコンクリート製電柱内部確認方法に使用される補強材均等配置用冶具の構成を更に詳しく示す斜視図である。It is a perspective view which shows in more detail the structure of the jig for reinforcement material equal arrangement | positioning used for the concrete electric pole inside confirmation method of embodiment shown in FIG. 図6に示した実施形態のコンクリート製電柱内部確認方法に使用される補強材均等配置用冶具をコンクリート製電柱の上端末口部から挿入するための補強材均等配置用冶具の閉じた状態を示す斜視図である。6 shows a closed state of the reinforcing material evenly arranged jig for inserting the reinforcing material evenly arranged jig used in the concrete electric pole inside confirmation method of the embodiment shown in FIG. 6 from the upper terminal opening of the concrete electric pole. It is a perspective view.

符号の説明Explanation of symbols

1、10 コンクリート製電柱
3 外周部
5 中空部
7 開口部
10a 上端末口部
20 ワイヤ
25、59 重り
41 カメラ
47 カメラコード
49 モニタ
50、70 補強材均等配置用冶具
51 棒状部材
71 第2の開口部
DESCRIPTION OF SYMBOLS 1,10 Concrete electric pole 3 Outer peripheral part 5 Hollow part 7 Opening part 10a Upper terminal opening part 20 Wire 25, 59 Weight 41 Camera 47 Camera code 49 Monitor 50, 70 Reinforcement material equal arrangement jig 51 Rod-shaped member 71 2nd opening Part

Claims (10)

立設されているコンクリート製電柱の中空部内を確認するコンクリート製電柱内部確認方法であって、
下端部に重りを取り付けたワイヤに撮像手段を取り付け、
前記ワイヤを下端部の重り側からコンクリート製電柱の中空部内に垂れ下ろし、
前記ワイヤの下端部の重りがコンクリート製電柱の中空部内の底部に当った状態でワイヤを上方に引き上げるようにしてワイヤを緊張させ、
このワイヤを緊張させた状態において前記撮像手段でコンクリート製電柱の中空部内を確認すべく撮像する
ことを特徴とするコンクリート製電柱内部確認方法。
A method for confirming the inside of a concrete electric pole that confirms the inside of a hollow portion of a concrete electric pole that is erected,
Attach imaging means to a wire with a weight attached to the lower end,
The wire is suspended from the weight side of the lower end portion into the hollow portion of the concrete electric pole,
Tension the wire so that the wire is pulled upward with the weight of the lower end of the wire hitting the bottom of the hollow part of the concrete utility pole,
The concrete electric pole inside confirmation method characterized by imaging in order to confirm the inside of the hollow part of a concrete electric pole with the said imaging means in the state which strained this wire.
前記撮像手段のワイヤへの取り付けは、撮像手段をワイヤ固定的に取り付けることを特徴とする請求項1記載のコンクリート製電柱内部確認方法。 Attachment to the wire of the imaging means, concrete electric pole inside verification method according to claim 1, wherein the attaching the imaging means fixedly to the wire. 立設されているコンクリート製電柱の中空部内を確認するコンクリート製電柱内部確認方法であって、
下端部に重りを取り付けたワイヤを下端部の重り側からコンクリート製電柱の中空部内に垂れ下ろし、
前記ワイヤの下端部の重りがコンクリート製電柱の中空部内の底部に当った状態でワイヤを上方に引き上げるようにしてワイヤを緊張させ、
この緊張させた状態のワイヤに沿って撮像手段を移動させ得るように撮像手段をワイヤに連結し、
この連結状態で撮像手段をワイヤに沿って移動させながらコンクリート製電柱の中空部内を確認すべく撮像する
ことを特徴とするコンクリート製電柱内部確認方法。
A concrete electric pole interior confirmation method for confirming the inside of a hollow portion of a concrete electric pole that is erected,
A wire with a weight attached to the lower end is suspended from the weight side of the lower end into the hollow part of the concrete utility pole,
Tension the wire so that the wire is pulled upward with the weight of the lower end of the wire hitting the bottom of the hollow part of the concrete utility pole,
Connecting the imaging means to the wire so that the imaging means can be moved along the tensioned wire,
A method for confirming the inside of a concrete electric pole, characterized in that an image is taken to confirm the inside of the hollow portion of the concrete electric pole while moving the imaging means along the wire in this connected state.
前記撮像手段をワイヤに沿って移動させ得るように撮像手段をワイヤに連結する処理は、
前記ワイヤが円滑に貫通し得るようにワイヤの直径よりも若干大きい直径を有する環状部材を撮像手段に取り付け、
この環状部材にワイヤを挿入して連結する
ことを特徴とする請求項3記載のコンクリート製電柱内部確認方法。
The process of connecting the imaging means to the wire so that the imaging means can be moved along the wire,
An annular member having a diameter slightly larger than the diameter of the wire is attached to the imaging means so that the wire can smoothly penetrate,
The method for confirming the inside of a concrete electric pole according to claim 3, wherein a wire is inserted into and connected to the annular member.
前記撮像手段には撮像用コードが取り付けられ、撮像手段は、該撮像用コードによりワイヤに沿って上方から吊り下げられていることを特徴とする請求項1乃至4のいずれか1項に記載のコンクリート製電柱内部確認方法。   5. The imaging cord is attached to the imaging means, and the imaging means is suspended from above along a wire by the imaging cord. How to check inside a concrete power pole. 前記ワイヤを下端部の重り側から中空部内に垂れ下ろし作業は、コンクリート製電柱の側部に形成された開口部またはコンクリート製電柱の最上端の上端末口部から行なうことを特徴とする請求項1乃至5のいずれか1項に記載のコンクリート製電柱内部確認方法。   The wire hanging down from the weight side of the lower end portion into the hollow portion is performed from an opening formed in a side portion of the concrete electric pole or an upper end opening of the uppermost end of the concrete electric pole. The concrete electric pole inside confirmation method of any one of 1 thru | or 5. 前記重りおよび撮像手段を取り付けるワイヤは、強化材としての複数の棒状部材を中空部内に均等に配置するための補強材均等配置用冶具を吊り下げるワイヤを利用することを特徴とする請求項1乃至6のいずれか1項に記載のコンクリート製電柱内部確認方法。   The wire for attaching the weight and the imaging means uses a wire that suspends a reinforcing material equalizing jig for uniformly arranging a plurality of rod-shaped members as reinforcing materials in the hollow portion. 6. A method for confirming the inside of a concrete electric pole according to any one of 6 above 前記ワイヤに取り付けられた重りおよび撮像手段は、コンクリート製電柱の中空部の断面においてほぼ中央に垂れ下ろされることを特徴とする請求項1乃至7のいずれか1項に記載のコンクリート製電柱内部確認方法。   The internal confirmation of the concrete electric pole according to any one of claims 1 to 7, wherein the weight and the imaging means attached to the wire are suspended substantially in the center in the cross section of the hollow portion of the concrete electric pole. Method. 前記ワイヤに取り付けられた重りおよび撮像手段は、コンクリート製電柱の中空部内に配置された複数の棒状部材および補強材均等配置用冶具を避けるように中空部の縁部に沿って垂れ下ろされることを特徴とする請求項1乃至7のいずれか1項に記載のコンクリート製電柱内部確認方法。   The weight attached to the wire and the imaging means are suspended along the edge of the hollow portion so as to avoid a plurality of rod-shaped members and jigs for evenly arranging reinforcing members disposed in the hollow portion of the concrete electric pole. The concrete electric pole inside confirmation method according to any one of claims 1 to 7, characterized in that: 前記ワイヤは、重りおよび撮像手段を中空部内に円滑に繰り出すことができるようにワイヤを巻き取ったり、巻き戻すことができる巻取器を用いて中空部内への繰り出しを行なうことを特徴とする請求項1乃至9のいずれか1項に記載のコンクリート製電柱内部確認方法。   The wire is fed into the hollow portion by using a winder capable of winding or unwinding the wire so that the weight and the imaging means can be smoothly fed into the hollow portion. Item 10. The method for confirming the inside of a concrete power pole according to any one of Items 1 to 9.
JP2004036244A 2004-02-13 2004-02-13 How to check the inside of a concrete power pole Expired - Fee Related JP4413638B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004036244A JP4413638B2 (en) 2004-02-13 2004-02-13 How to check the inside of a concrete power pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004036244A JP4413638B2 (en) 2004-02-13 2004-02-13 How to check the inside of a concrete power pole

Publications (2)

Publication Number Publication Date
JP2005227135A JP2005227135A (en) 2005-08-25
JP4413638B2 true JP4413638B2 (en) 2010-02-10

Family

ID=35001966

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004036244A Expired - Fee Related JP4413638B2 (en) 2004-02-13 2004-02-13 How to check the inside of a concrete power pole

Country Status (1)

Country Link
JP (1) JP4413638B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102244501B1 (en) * 2019-11-30 2021-04-26 가천대학교 산학협력단 Guide equipment and inspection device for manhole condition assessment with guide equipment

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5158913B1 (en) * 2012-06-22 2013-03-06 株式会社丸冨士 Folding cane
JP6590365B2 (en) * 2014-08-28 2019-10-16 一般財団法人電力中央研究所 Inspection method and inspection system for reinforcing bars in concrete columns
JP6598196B2 (en) * 2014-08-28 2019-10-30 一般財団法人電力中央研究所 Nondestructive inspection method and nondestructive inspection system for structures
JP6446691B2 (en) * 2015-09-28 2019-01-09 株式会社ヒューテック Embedded hollow structure inspection method and embedded hollow structure inspection apparatus
JP7254428B2 (en) * 2019-10-28 2023-04-10 一般財団法人電力中央研究所 Non-Destructive Inspection Device for Hollow Utility Pole and Non-Destructive Inspection Method for Hollow Utility Pole
JP7586703B2 (en) * 2020-12-25 2024-11-19 大和ハウス工業株式会社 Exterior wall inspection device and exterior wall inspection method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102244501B1 (en) * 2019-11-30 2021-04-26 가천대학교 산학협력단 Guide equipment and inspection device for manhole condition assessment with guide equipment

Also Published As

Publication number Publication date
JP2005227135A (en) 2005-08-25

Similar Documents

Publication Publication Date Title
JP6215553B2 (en) Compaction equipment and compaction method for cast-in-place concrete piles
JP4413638B2 (en) How to check the inside of a concrete power pole
CN112010180A (en) Working machine and method
JP6310198B2 (en) Pier construction method
JP2020186538A (en) Shape holding mechanism, installation device for strand reinforcement cage and installation method for strand reinforcement cage
JP4210242B2 (en) Method for reinforcing concrete power pole and concrete power pole
JP6523867B2 (en) Pile press-in method, reaction frame and pile press-in and pull-out machine
JP4395402B2 (en) Reinforcing method for concrete utility poles
JP5764631B2 (en) Steel pipe pile placing device
KR102208908B1 (en) File driving device and file driving method using the same
JP4342382B2 (en) Reinforcing method for concrete utility poles
JP2014111898A (en) Device and method for injecting filler
JP4459139B2 (en) Reinforcing method for concrete utility poles
JP2013227736A (en) Recovery tool and recovery method using the same
CN214942210U (en) Large-cantilever composite anchoring type steel construction platform
JP2006225987A (en) Concrete pole reinforcing method and concrete pole
KR101787544B1 (en) Fish trap separating unit and fish trap pulling-up machine including the same
JP4384088B2 (en) Reinforcing method for concrete utility poles
JP2005226337A (en) Method for reinforcing concrete electric pole and concrete electric pole reinforced by the method
JP6554196B1 (en) Photography equipment
JPH1136292A (en) Spiral muscle winding device and spiral muscle winding method
JP2009084794A (en) Built-in monitoring device, built-in method
JP3735519B2 (en) Concrete compaction method and apparatus
JP4069059B2 (en) Method for reinforcing concrete power pole and reinforcing structure for concrete power pole
JP2006348592A (en) Pile core management jig and pile core management method using the pile core management jig

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070116

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090729

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090811

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091009

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091110

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091118

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121127

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131127

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees