JP4606389B2 - Distributed generator control system - Google Patents
Distributed generator control system Download PDFInfo
- Publication number
- JP4606389B2 JP4606389B2 JP2006177764A JP2006177764A JP4606389B2 JP 4606389 B2 JP4606389 B2 JP 4606389B2 JP 2006177764 A JP2006177764 A JP 2006177764A JP 2006177764 A JP2006177764 A JP 2006177764A JP 4606389 B2 JP4606389 B2 JP 4606389B2
- Authority
- JP
- Japan
- Prior art keywords
- power
- distributed generator
- output
- storage battery
- predicted
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
本発明は、停電時に電源として利用可能な分散型発電機の制御システムに関する。 The present invention relates to a control system for a distributed generator that can be used as a power source during a power failure.
ガスコージェネレーションシステム等の分散型発電機には、系統電源の正常時に系統電源(商用電源)と連系して電力を供給し、非常停電時には防災負荷に対して電力を供給する非常用電源として利用される常用防災兼用コージェネレーションシステムがある。ここで、非常停電は火災等の災害に伴う系統電源の停電であり、系統電源の停電としては、他に、台風、落雷若しくは事故等による一般停電がある。ここでは、火災警報器や防災設備の起動信号等を伴う停電を非常停電とし、非常停電以外の停電を一般停電として説明する。防災負荷としては、消火栓、スプリンクラー、非常用エレベータ及び消化ポンプ等が規定されている。常用防災兼用コージェネレーションシステムは、例えば、火災が発生した際に、初期消火を目的とした消防設備(防災負荷)に電気を供給する。 For distributed generators such as gas cogeneration systems, supply power to the grid power supply (commercial power supply) when the grid power supply is normal, and use it as an emergency power supply to supply power to the disaster prevention load during an emergency power outage There is a regular disaster prevention cogeneration system. Here, the emergency power failure is a power failure of the system power supply due to a disaster such as a fire, and the power failure of the system power supply includes a general power failure due to a typhoon, a lightning strike or an accident. Here, a power outage accompanied by a start signal of a fire alarm or disaster prevention equipment will be referred to as an emergency power outage, and a power outage other than an emergency power outage will be described as a general power outage. Fire hydrants, sprinklers, emergency elevators, digestion pumps, etc. are specified as disaster prevention loads. For example, when a fire occurs, the common disaster prevention cogeneration system supplies electricity to a fire fighting facility (disaster prevention load) for the purpose of initial fire extinguishing.
従来の停電対応仕様のコージェネレーションシステムは、例えば、系統電源が停電になった際に、予め固定的に設定された重要電力負荷に対してのみ電力を供給し、一般電力負荷に対する電力供給を停止する制御を行なっている(例えば、特許文献1参照)。このコージェネレーションシステムは、落雷の虞がある場合等、系統電源の停電が予測される場合に、コージェネレーションシステムの出力を重要負荷の電力需要に応じて設定し、停電時における急激な出力変動を防止することで重要負荷に対して安定して電力を供給するものである。 For example, when a power failure occurs in a system power supply, a conventional cogeneration system that supports power outages supplies power only to important power loads that are fixedly set in advance, and stops power supply to general power loads. (For example, refer to Patent Document 1). This cogeneration system sets the output of the cogeneration system according to the power demand of the important load when a power failure of the system power supply is predicted, such as when there is a possibility of a lightning strike, and abrupt output fluctuation at the time of the power failure By preventing this, power is stably supplied to the important load.
しかしながら、特許文献1に記載のコージェネレーションシステムは、停電時に予め固定的に設定された重要電力負荷に対してのみ電力供給を行なう構成であるため、分散型発電機の電力供給能力に余力がある場合であっても他の一般電力負荷に対し電力を供給することができないという問題があった。更に、集合住宅では、時期や時間帯によって、電源供給が必要な重要電力負荷の対象とすべき電力負荷が異なることや、重要電力負荷が必要とする電力量が変化することから、予め固定的に設定された重要電力負荷への給電だけでは、系統電源の停電時に居住者の生活が制限されてしまう虞があった。 However, since the cogeneration system described in Patent Document 1 is configured to supply power only to an important power load that is fixedly set in advance at the time of a power failure, there is a surplus in power supply capacity of the distributed generator. Even in this case, there is a problem that power cannot be supplied to other general power loads. Furthermore, in apartment buildings, the power load that should be the target of the important power load that requires power supply differs depending on the time and time zone, and the amount of power required by the important power load changes. There is a possibility that the resident's life may be limited when the power supply of the system power supply is cut off only by supplying power to the important power load set to.
また、非常停電時における非常用電源としては利用できないコージェネレーションシステムにおいても、停電時に電源として利用できるコージェネレーションシステムは、時期や時間帯等の状況に適切に対応して各電力負荷への電源供給を適切に行なえる技術が望まれている。 In addition, even in a cogeneration system that cannot be used as an emergency power source in the event of an emergency power failure, the cogeneration system that can be used as a power source in the event of a power failure supplies power to each power load in an appropriate manner depending on the situation such as time and time zone. There is a demand for a technology that can appropriately perform the above.
本発明は上記の問題に鑑みてなされたものであり、その目的は、停電時における分散型発電機の電力供給能力の有効活用を図り、集合住宅の居住者の利便性の低下を軽減することができる分散型発電機の制御システムを提供する点にある。 The present invention has been made in view of the above problems, and its purpose is to effectively utilize the power supply capability of the distributed generator at the time of a power outage, and to reduce the decrease in convenience for residents of apartment buildings. It is in the point of providing a control system for a distributed generator.
上記目的を達成するための本発明に係る分散型発電機の制御システムは、集合住宅に系統電源と連系可能に設置された1または複数の分散型発電機と蓄電池による前記集合住宅内の複数の電力負荷に対する電力供給を制御する分散型発電機の制御システムであって、前記系統電源の停電が発生した際に、該停電が火災等の災害に伴う非常停電であるかそれ以外の一般停電であるかを認識する停電判定手段と、前記一般停電発生時に、前記一般停電の予測停電期間の入力を受け付ける停電期間入力手段と、前記一般停電発生時に、前記複数の電力負荷毎の単位時間別予測電力需要の入力を受け付ける予測電力需要入力手段と、前記一般停電発生時に、前記予測停電期間を分割した単位制御時間毎に、次の前記単位制御時間における前記分散型発電機からの電力供給対象となる全ての前記電力負荷の前記単位時間別予測電力需要を合計した総予測電力需要に基づいて、前記電力負荷に対する電力供給を制御する制御手段と、を備え、前記制御手段は、前記単位制御時間における前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を下回る場合に、前記総予測電力需要が前記分散型発電機と前記蓄電池の合計出力を下回るように、前記分散型発電機からの電力供給対象となる前記電力負荷を所定の負荷選択ルールに基づいて選択し、前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を下回り、且つ、前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を上回る場合に、前記分散型発電機を全出力運転に設定し、前記蓄電池の出力を前記総予測電力需要と前記分散型発電機の出力の差に追従させる制御を行い、前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合に、前記予測停電期間全体での前記蓄電池の必要蓄電池出力量を算出し、前記蓄電池の貯蓄電力量が前記必要電池出力量を下回る場合に、前記分散型発電機を全出力運転に設定するとともに、前記分散型発電機の余剰電力を前記蓄電池に蓄電し、前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合であって、前記蓄電池の貯蓄電力量が前記必要電池出力量を上回る場合に、前記分散型発電機の出力を前記電力負荷に追従させる制御を行なうことを第1の特徴とする。 In order to achieve the above object, a control system for a distributed generator according to the present invention includes a plurality of power generators in the collective housing including one or a plurality of distributed power generators and storage batteries installed in the collective housing so as to be connected to a system power source. A control system for a distributed generator that controls power supply to a power load of the system, and when a power failure occurs in the system power supply, the power failure is an emergency power failure due to a disaster such as a fire or other general power failure A power failure determination means for recognizing whether a general power failure occurs, a power failure period input means for receiving an input of a predicted power failure period of the general power failure, and a unit time for each of the plurality of power loads when the general power failure occurs A predicted power demand input means for receiving an input of predicted power demand, and the distributed generation in the next unit control time for each unit control time obtained by dividing the predicted power failure period when the general power failure occurs. Control means for controlling power supply to the power load based on a total predicted power demand obtained by summing the unit time predicted power demands of all the power loads to be supplied from a machine, the control The means is such that when the total output of the distributed generator and the storage battery in the unit control time is lower than the total predicted power demand, the total predicted power demand is lower than the total output of the distributed generator and the storage battery. In addition, the power load to be supplied from the distributed generator is selected based on a predetermined load selection rule, the output of the distributed generator in the unit control time is less than the total predicted power demand, And, when the total output of the distributed generator and the storage battery exceeds the total predicted power demand, the distributed generator is set to full output operation, and the output of the storage battery is set to the total output Control is performed to follow the difference between the power measurement demand and the output of the distributed generator, and when the output of the distributed generator in the unit control time exceeds the total predicted power demand, The required storage battery output amount of the storage battery is calculated, and when the stored power amount of the storage battery is lower than the required battery output amount, the distributed generator is set to full output operation, and the surplus power of the distributed generator is set. Is stored in the storage battery, and the output of the distributed generator in the unit control time exceeds the total predicted power demand, and when the stored power amount of the storage battery exceeds the required battery output amount, The first feature is that control is performed to cause the output of the distributed generator to follow the power load.
上記目的を達成するための本発明に係る分散型発電機の制御システムは、集合住宅に系統電源と連系可能に設置された1または複数の分散型発電機と蓄電池による前記集合住宅内の複数の電力負荷に対する電力供給を制御する分散型発電機の制御システムであって、 前記系統電源の停電を認識する停電判定手段と、停電発生時に、該停電の予測停電期間の入力を受け付ける停電期間入力手段と、停電発生時に、前記複数の電力負荷毎の単位時間別予測電力需要の入力を受け付ける予測電力需要入力手段と、停電発生時に、前記予測停電期間を分割した単位制御時間毎に、次の前記単位制御時間における前記分散型発電機からの電力供給対象となる全ての前記電力負荷の前記単位時間別予測電力需要を合計した総予測電力需要に基づいて、前記電力負荷に対する電力供給を制御する制御手段と、を備え、前記制御手段は、前記単位制御時間における前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を下回る場合に、前記総予測電力需要が前記分散型発電機と前記蓄電池の合計出力を下回るように、前記分散型発電機からの電力供給対象となる前記電力負荷を所定の負荷選択ルールに基づいて選択し、前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を下回り、且つ、前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を上回る場合に、前記分散型発電機を全出力運転に設定し、前記蓄電池の出力を前記総予測電力需要と前記分散型発電機の出力の差に追従させる制御を行い、前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合に、前記予測停電期間全体での前記蓄電池の必要蓄電池出力量を算出し、前記蓄電池の貯蓄電力量が前記必要電池出力量を下回る場合に、前記分散型発電機を全出力運転に設定するとともに、前記分散型発電機の余剰電力を前記蓄電池に蓄電し、前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合であって、前記蓄電池の貯蓄電力量が前記必要電池出力量を上回る場合に、前記分散型発電機の出力を前記電力負荷に追従させる制御を行なうことを第2の特徴とする。 In order to achieve the above object, a control system for a distributed generator according to the present invention includes a plurality of power generators in the collective housing including one or a plurality of distributed power generators and storage batteries installed in the collective housing so as to be connected to a system power source. A power generation determination means for recognizing a power failure of the system power supply and a power failure period input for receiving an input of a predicted power failure period of the power failure when a power failure occurs Means, a predicted power demand input means for receiving an input of predicted power demand by unit time for each of the plurality of power loads when a power failure occurs, and for each unit control time obtained by dividing the predicted power failure period at the time of power failure, Based on the total predicted power demand obtained by totaling the predicted power demand by unit time of all the power loads to be supplied with power from the distributed generator in the unit control time, Control means for controlling power supply to the power load, wherein the control means is configured to calculate the total forecast when a total output of the distributed generator and the storage battery in the unit control time is less than the total forecast power demand. Selecting the power load to be supplied from the distributed generator based on a predetermined load selection rule so that the power demand is less than the total output of the distributed generator and the storage battery, and the unit control time When the output of the distributed generator in the system is less than the total predicted power demand, and the total output of the distributed generator and the storage battery exceeds the total predicted power demand, the distributed generator is operated at full power And setting the output of the storage battery to follow the difference between the total predicted power demand and the output of the distributed generator, and the output of the distributed generator in the unit control time is When the total predicted power demand is exceeded, the required storage battery output amount of the storage battery for the entire predicted power outage period is calculated, and when the stored power amount of the storage battery is less than the required battery output amount, the distributed generator is In the case of setting to full output operation, the surplus power of the distributed generator is stored in the storage battery, and the output of the distributed generator in the unit control time exceeds the total predicted power demand, and the storage battery The second feature is that when the stored power amount exceeds the required battery output amount, control is performed to cause the output of the distributed generator to follow the power load.
上記第1または第2の特徴の本発明によれば、一般停電時において、単位制御時間毎に、総予測電力需要が分散型発電機の電力供給能力を上回る場合に、動的に電力供給を行なう電力負荷を選択するように構成したので、電力需要に応じて分散型発電機の電力供給能力の有効活用を図ることができる。より具体的には、集合住宅では、時期や時間帯によって電源供給対象とすべき電力負荷や必要とされる電力量が変化するため、電源供給対象を予め固定的に設定するのではなく、時期や時間帯等、状況に応じて適切に電源供給対象を選択し、選択された電源供給対象に対して電源供給を行なうことで、集合住宅の居住者の利便性の低下を軽減することが可能になる。 According to the first or second aspect of the present invention, in a general power failure, when the total predicted power demand exceeds the power supply capacity of the distributed generator every unit control time, the power supply is dynamically performed. Since the power load to be performed is selected, the power supply capability of the distributed generator can be effectively utilized according to the power demand. More specifically, in an apartment house, the power load to be supplied and the amount of power to be changed vary depending on the time and time zone. By selecting the appropriate power supply target according to the situation, such as the time of day and time, and supplying power to the selected power supply target, it is possible to reduce the decline in convenience for residents in apartment buildings become.
更に、蓄電池を備えるので、蓄電池の貯蓄電力量及び必要電池出力量に基づいて蓄電池の充放電を行なう構成にすれば、蓄電池の有効活用を図ることが可能になる。 Furthermore, since the storage battery is provided, the storage battery can be effectively used by charging and discharging the storage battery based on the stored power amount and the required battery output amount of the storage battery.
上記何れかの特徴の本発明に係る分散型発電機の制御システムは、前記負荷選択ルールが、前記電力負荷の用途、種別或いは設置場所毎に設定された優先順位であることを第3の特徴とする。 Above any feature control system of a distributed power generator according to the present invention, the load selection rule, the power load applications, the third being a priority set for each type or location And
上記特徴の本発明によれば、電力負荷の用途、種別或いは設置場所毎に優先順位を設定するので、例えば、集合住宅内の共用部に設置された照明等の重要度の高い電力負荷について優先順位を高く設定することで、重要度の高い電力負荷に対する電力供給を安定して実施することができ、停電時における電力供給を適切に行なうことが可能になる。 According to the present invention having the above characteristics, priority is set for each use, type, or installation location of the power load. For example, priority is given to a power load with high importance such as lighting installed in a common part in an apartment house. By setting the rank higher, it is possible to stably supply power to a power load with high importance, and to appropriately supply power during a power outage.
上記特徴の本発明に係る分散型発電機の制御システムは、前記優先順位が、時間帯毎に設定されていることを第4の特徴とする。 The control system of the distributed generator according to the present invention having the above characteristics, the priority, the fourth feature that it is set for each time zone.
上記特徴の本発明によれば、優先順位が時間帯毎に設定されているので、時間帯によって重要度や必要電力量が変化する電力負荷に適切に対応することが可能になる。優先順位が固定されている場合は、電力供給の必要性が低くなった電力負荷に対して電力供給が継続して実施されることになるが、本発明の如く構成することにより、電力供給の必要性が低くなった電力負荷から電力供給の必要性のより高い電力負荷に電力供給を切り替えることが可能になり、集合住宅の居住者の利便性の低下をより軽減することが可能になる。 According to the present invention having the above characteristics, since the priority order is set for each time zone, it is possible to appropriately cope with a power load whose importance level and required power amount change depending on the time zone. When the priority order is fixed, the power supply is continuously performed on the power load whose necessity for power supply is low. However, by configuring as in the present invention, the power supply It becomes possible to switch the power supply from a power load that has become less necessary to a power load that has a higher need for power supply, and it is possible to further reduce a decrease in convenience for residents of the apartment house.
上記第3または第4の特徴の本発明に係る分散型発電機の制御システムは、前記優先順位が、動的に変化することを第5の特徴とする。 The distributed generator control system according to the third or fourth aspect of the present invention has a fifth characteristic that the priority is dynamically changed.
上記特徴の本発明によれば、優先順位を動的に変化させるように構成したので、電力供給の必要性が動的に変化する場合に適切に対応することが可能になる。優先順位が固定されている場合は、電力供給の必要性が動的に変化する電力負荷に対して電力供給が常時実施されることになるが、本発明の如く構成することにより、電力供給の必要が低くなった電力負荷から電力供給の必要性のより高い電力負荷に電力供給を切り替えることが可能になり、集合住宅の居住者の利便性の低下をより軽減することが可能になる。 According to the present invention having the above characteristics, since the priority order is dynamically changed, it is possible to appropriately cope with a case where the necessity of power supply dynamically changes. When the priority order is fixed, power supply is always performed for a power load in which the necessity for power supply changes dynamically. It becomes possible to switch the power supply from a power load that has become less necessary to a power load that has a higher need for power supply, and it is possible to further reduce a decrease in convenience for residents of the apartment house.
上記何れかの特徴の本発明に係る分散型発電機の制御システムは、前記制御手段が、前記電力負荷毎に設けられたスイッチのオンオフ制御により、前記電力負荷毎に電力供給を行なうか否かを制御することを第6の特徴とする。 In the distributed generator control system according to the present invention having any one of the above characteristics, whether or not the control means supplies power for each power load by on / off control of a switch provided for each power load. The sixth feature is to control the above.
上記特徴の本発明によれば、電力負荷毎に設けられたスイッチのオンオフ制御により電力供給を制御するので、電力供給の制御を簡素化でき、本発明をより簡易に構築することが可能になる。 According to the present invention having the above characteristics, power supply is controlled by on / off control of a switch provided for each power load. Therefore, control of power supply can be simplified, and the present invention can be constructed more easily. .
上記何れかの特徴の本発明に係る分散型発電機の制御システムは、前記複数の電力負荷毎の単位時間別予測電力需要を算出する予測手段を備えることを第7の特徴とする。 The distributed generator control system according to the present invention having any one of the above characteristics has a seventh characteristic that includes a prediction unit that calculates a predicted power demand per unit time for each of the plurality of power loads.
上記特徴の本発明によれば、単位時間別予測電力需要を予測する予測手段を設けたので、本発明が設置される集合住宅の電力負荷の電力需要を適切に予測することができ、分散型発電機の制御を適切に実施することが可能になる。 According to the present invention having the above characteristics, since the prediction means for predicting the predicted power demand by unit time is provided, the power demand of the power load of the apartment house where the present invention is installed can be appropriately predicted, and the distributed type It becomes possible to appropriately control the generator.
上記特徴の本発明に係る分散型発電機の制御システムは、前記予測手段が、前記系統電源の正常時における過去の前記複数の電力負荷毎の単位時間別の電力需要の推移を示す実績データに基づいて、前記単位時間別予測電力需要を算出することを第8の特徴とする。 In the control system for a distributed generator according to the present invention having the above characteristics, the predicting unit is configured to record actual data indicating a transition of power demand per unit time for each of the plurality of power loads in the past when the system power supply is normal. Based on this, it is an eighth feature to calculate the predicted power demand by unit time.
上記特徴の本発明によれば、過去の実績データに基づいて単位時間別予測電力需要を予測するので、本発明が設置される集合住宅の電力負荷の電力需要に応じて分散型発電機の制御を適切に実施することが可能になる。 According to the present invention having the above characteristics, the predicted power demand for each unit time is predicted based on past performance data. Therefore, the control of the distributed generator is performed according to the power demand of the power load of the apartment house where the present invention is installed. Can be implemented appropriately.
上記特徴の本発明に係る分散型発電機の制御システムは、前記予測手段が、前記集合住宅の住戸数、設備、延べ床面積、立地条件の少なくとも何れか一つを含む物件情報に基づいて、前記単位時間別予測電力需要を算出することを第9の特徴とする。 In the distributed generator control system according to the present invention having the above characteristics, the prediction means is based on property information including at least one of the number of dwelling units, facilities, total floor area, and location conditions of the apartment house, It is a ninth feature that the predicted power demand per unit time is calculated.
上記特徴の本発明によれば、住戸数等の物件情報に基づいて単位時間別電力需要を予測するので、例えば、集合住宅における実績データが蓄積されていない場合であっても適切に単位時間別電力需要を予測することが可能になる。 According to the above-described feature of the present invention, since the power demand by unit time is predicted based on the property information such as the number of units, for example, even when the performance data in the apartment is not accumulated, It becomes possible to predict the power demand.
上記何れかの特徴の本発明に係る分散型発電機の制御システムは、前記分散型発電機が、外部から供給される燃料を使用して電力を発生する発電機ユニットと、前記発電機ユニットの排出する排熱を回収する排熱回収装置とを備えたコージェネレーションシステムであることを第10の特徴とする。
The distributed generator control system according to the present invention having any one of the above features is characterized in that the distributed generator generates power using fuel supplied from the outside, and the generator unit that the cogeneration system comprising a heat recovery device for recovering exhaust heat discharged to the features of the first 0.
上記特徴の本発明によれば、分散型発電機として、コージェネレーションシステムを制御するので、非常用電源や停電対応電源として利用されるコージェネレーションシステムに本発明を適用することができ、コージェネレーションシステムの発電能力の有効活用を図ることが可能になる。 According to the present invention having the above characteristics, since the cogeneration system is controlled as a distributed generator, the present invention can be applied to a cogeneration system used as an emergency power supply or a power supply for power failure. It is possible to make effective use of the power generation capacity.
以下、本発明に係る分散型発電機の制御システム(以下、適宜「本発明システム1」と略称する)の実施形態を図面に基づいて説明する。 Embodiments of a distributed generator control system according to the present invention (hereinafter abbreviated as “the present system 1” as appropriate) will be described below with reference to the drawings.
〈第1実施形態〉
本発明システムの第1実施形態について図1〜図4を基に説明する。図1は、本発明システム1及び本発明システム1が設置された集合住宅の電源構成を示す概略ブロック図である。本実施形態では、分散型発電機として、常用防災兼用ガスコージェネレーションシステムに設けられた発電機ユニットを想定している。
<First Embodiment>
A first embodiment of the system of the present invention will be described with reference to FIGS. FIG. 1 is a schematic block diagram showing a power supply configuration of the present invention system 1 and an apartment house in which the present invention system 1 is installed. In this embodiment, the generator unit provided in the common disaster prevention gas cogeneration system is assumed as a distributed generator.
図1に示すように、本実施形態の集合住宅は、系統電源からの電力を受電点2を介して単相変圧器31、単相変圧器32及び動力三相変圧器4で受けて集合住宅内の電力負荷Lに供給するように構成されており、単相変圧器32及び動力三相変圧器4はスイッチ5を介して受電点2に接続されている。動力三相変圧器4には、電力負荷L1〜LNが電力計Wh1〜WhN及びスイッチα1〜αNを介して接続され、蓄電池Bが電力計WhB及びスイッチαBを介して接続され、ガスコージェネレーションシステムが電力計WhGを介して接続されている。ガスコージェネレーションシステムは、外部から供給される燃料を使用して電力を発生する発電機ユニットGと、発電機ユニットGの排出する排熱を回収する排熱回収装置とを備えて構成されている。電力負荷L1〜LNとしては、集合住宅の共用部に設置されたエレベータ、給水ポンプ、暖房ポンプ、及び、給湯ポンプ等の動力関係の電力負荷Lを想定している。単相変圧器32には、電力負荷LN+1〜LMが電力計WhN+1〜WhM及びスイッチαN+1〜αMを介して接続されている。電力負荷LN+1〜LMとしては、共用部の照明、ITリモコン、セキュリティ設備、及び、専有部(住戸)等を想定している。尚、図1では集合住宅内に1つの蓄電池Bを設置した場合について図示しているが、蓄電池Bは各住戸に設置する等、集合住宅内に複数設置するように構成しても良い。 As shown in FIG. 1, the apartment house of this embodiment receives the power from the system power supply via the power receiving point 2 by the single-phase transformer 31, the single-phase transformer 32, and the power three-phase transformer 4. The single-phase transformer 32 and the power three-phase transformer 4 are connected to the power receiving point 2 via the switch 5. Power loads L 1 to L N are connected to power three-phase transformer 4 via power meters Wh 1 to Wh N and switches α 1 to α N , and storage battery B is connected to power meter Wh B and switch α B. The gas cogeneration system is connected via a power meter Wh G. The gas cogeneration system includes a generator unit G that generates electric power using fuel supplied from the outside, and an exhaust heat recovery device that recovers exhaust heat discharged from the generator unit G. As the power loads L 1 to L N , power-related power loads L such as an elevator, a water supply pump, a heating pump, and a hot water supply pump installed in a common part of the apartment house are assumed. Power loads L N + 1 to L M are connected to the single-phase transformer 32 via power meters Wh N + 1 to Wh M and switches α N + 1 to α M. As the power loads L N + 1 to L M, it is assumed that the lighting of the common part, the IT remote controller, the security equipment, the exclusive part (dwelling unit), and the like. In addition, although FIG. 1 illustrates the case where one storage battery B is installed in the apartment house, a plurality of storage batteries B may be installed in the apartment house, for example, installed in each dwelling unit.
本発明システム1は、集合住宅に系統電源と連系可能に設置された発電機ユニットGと蓄電池Bによる集合住宅内の複数の電力負荷Lに対する電力供給を制御する。図1に示すように、本発明システム1は、系統電源の停電が発生した際に、該停電が火災等の災害に伴う非常停電であるか一般停電であるかを認識する停電判定手段11と、一般停電発生時に、一般停電の予測停電期間の入力を受け付ける停電期間入力手段12と、一般停電発生時に、複数の電力負荷L毎の単位時間別予測電力需要の入力を受け付ける予測電力需要入力手段13と、一般停電発生時に、予測停電期間を分割した単位制御時間毎に、次の単位制御時間における発電機ユニットGからの電力供給対象となる全ての電力負荷Lの単位時間別予測電力需要を合計した総予測電力需要に基づいて、電力負荷Lに対する電力供給を制御する制御手段14と、を備えて構成されている。 The system 1 of the present invention controls power supply to a plurality of power loads L in an apartment house by a generator unit G and a storage battery B that are installed in the apartment house so as to be connected to a system power supply. As shown in FIG. 1, the system 1 of the present invention includes a power failure determination means 11 that recognizes whether a power failure is an emergency power failure or a general power failure due to a disaster such as a fire when a power failure occurs in a system power supply. A power outage period input means 12 for receiving an input of a predicted power outage period of a general power outage when a general power outage occurs, and a predicted power demand input means for receiving an input of a predicted power demand by unit time for each of the plurality of power loads L when the general power outage occurs 13 and for each unit control time obtained by dividing the predicted power outage period when a general power outage occurs, the predicted power demand by unit time of all the power loads L to be supplied with power from the generator unit G in the next unit control time is calculated. And control means 14 for controlling the power supply to the power load L based on the total estimated power demand.
停電判定手段11は、火災警報器や防災設備の起動信号等に連動して動作するように構成され、停電発生時、火災警報器や防災設備の起動信号が発信されている場合は非常停電であると判定し、火災警報器や防災設備の起動信号が発信されていない場合は一般停電であると判定する。 The power failure determination means 11 is configured to operate in conjunction with a start signal of a fire alarm or disaster prevention equipment, and when a power failure occurs, an emergency power failure occurs when a start signal of the fire alarm or disaster prevention equipment is transmitted. If it is determined that there is no fire alarm or disaster prevention equipment start signal, it is determined that there is a general power outage.
停電期間入力手段12は、予測停電期間を本発明システム1の操作手段によって手入力するように構成されており、例えば、集合住宅の管理人等による操作入力に基づいて予測停電期間を取得する。予測停電期間は、数時間以内(例えば3時間以内)の短期停電、1日未満の中期停電、1日以上の長期停電に大別して入力するように構成されている。尚、停電発生時から一定時間を経過しても予測停電期間が入力されない場合には、長期停電とみなすように設定されている。 The power failure period input means 12 is configured to manually input the predicted power failure period by the operation means of the system 1 of the present invention. For example, the power failure period input means 12 acquires the predicted power failure period based on the operation input by the manager of the apartment house. The predicted power outage period is configured to be classified into a short-term power outage within several hours (for example, within 3 hours), a medium-term power outage less than one day, and a long-term power outage over one day. It should be noted that if a predicted power outage period is not input after a certain time has elapsed since the occurrence of the power outage, it is set to be regarded as a long-term power outage.
予測電力需要入力手段13は、一般停電発生時に、電力負荷L毎の単位時間別予測電力需要の入力を受け付ける。本実施形態では、本発明システム1外に設置された電力需要の予測ツールが予測した単位時間別予想電力需要を取得する。 The predicted power demand input means 13 receives an input of predicted power demand by unit time for each power load L when a general power failure occurs. In the present embodiment, the predicted power demand by unit time predicted by the power demand prediction tool installed outside the system 1 of the present invention is acquired.
制御手段14は、一般停電発生時に、予測停電期間を分割した単位制御時間毎に、次の単位制御時間における発電機ユニットGからの電力供給対象となる全ての電力負荷Lの単位時間別予測電力需要を合計した総予測電力需要に基づいて、電力負荷Lに対する電力供給を制御する。ここでの単位制御時間は、例えば、10分である。本実施形態の制御手段14は、電力負荷L毎に設けられたスイッチαのオンオフ制御により、電力負荷L毎に電力供給を行なうか否かを制御する。 When the general power failure occurs, the control means 14 generates the predicted power by unit time of all the power loads L to be supplied with power from the generator unit G in the next unit control time for each unit control time obtained by dividing the predicted power failure period. The power supply to the power load L is controlled based on the total predicted power demand that is the sum of the demands. The unit control time here is, for example, 10 minutes. The control means 14 of this embodiment controls whether or not to supply power for each power load L by on / off control of the switch α provided for each power load L.
次に、本発明システム1の処理について図2を基に説明する。 Next, the processing of the system 1 of the present invention will be described with reference to FIG.
停電が発生し、停電判定手段11によって一般停電であることが認識されると、停電期間入力手段12は、予測停電期間を取得する(ステップ#101)。続いて、予測電力需要入力手段13は、電力需要の予測ツールから電力負荷L毎の単位時間別予測電力需要を取得する(ステップ#102)。ここで、図3は、一般停電発生前後の集合住宅の電力需要の推移と、発電機ユニットGの出力と、蓄電池B出力の関係を示している。 When a power failure occurs and the power failure determination means 11 recognizes that it is a general power failure, the power failure period input means 12 acquires a predicted power failure period (step # 101). Subsequently, the predicted power demand input unit 13 acquires the predicted power demand by unit time for each power load L from the power demand prediction tool (step # 102). Here, FIG. 3 shows the transition of the power demand of the apartment house before and after the occurrence of a general power failure, the output of the generator unit G, and the output of the storage battery B.
制御手段14は、先ず、発電機ユニットGの出力と単位時間別予測電力需要を比較し(ステップ#103)、発電機ユニットGの出力が単位時間別予測電力需要より低い場合(ステップ#103でNo分岐)に発電機ユニットGを全出力運転に設定する(ステップ#104)。続いて、制御手段14は、単位制御時間における発電機ユニットGと蓄電池Bの合計出力と単位時間別予測電力需要を比較し(ステップ#105)、発電機ユニットGと蓄電池Bの合計出力が総予測電力需要を下回る場合に(ステップ#105でNo分岐、図3の破線a参照)、総予測電力需要が発電機ユニットGと蓄電池Bの合計出力を下回るように、発電機ユニットGからの電力供給対象となる電力負荷Lを所定の負荷選択ルールに基づいて選択する(ステップ#106)。 The control means 14 first compares the output of the generator unit G with the predicted power demand per unit time (step # 103), and if the output of the generator unit G is lower than the predicted power demand per unit time (in step # 103) In No branch), the generator unit G is set to full output operation (step # 104). Subsequently, the control means 14 compares the total output of the generator unit G and the storage battery B in the unit control time with the predicted power demand by unit time (step # 105), and the total output of the generator unit G and the storage battery B is the total output. When the predicted power demand is lower (No branch at step # 105, see broken line a in FIG. 3), the power from the generator unit G is set so that the total predicted power demand is lower than the total output of the generator unit G and the storage battery B. The power load L to be supplied is selected based on a predetermined load selection rule (step # 106).
制御手段14は、電力負荷Lの選択を予め設定された負荷選択ルールに基づいて実施する。本実施形態では、負荷選択ルールは、電力負荷Lの用途、種別或いは設置場所毎に設定された優先順位である。また、優先順位は、時間帯毎(例えば、1時間毎、30分毎等)に、更に、動的に変化するように設定されている。制御手段14は、優先順位の高い電力負荷Lから順に発電機ユニットGによる電力供給対象とし、総予測電力需要が発電機ユニットG及び蓄電池Bの合計出力を超えない範囲で電力負荷Lを選択する。尚、本実施形態では、負荷選択ルールは、時間帯毎に動的に変化するように構成したが、季節や月等の時期毎に動的に変化するように構成しても良い。 The control means 14 selects the power load L based on a preset load selection rule. In the present embodiment, the load selection rule is a priority set for each use, type, or installation location of the power load L. Further, the priority order is set so as to dynamically change every time zone (for example, every hour, every 30 minutes, etc.). The control unit 14 selects the power load L in a range in which the total predicted power demand does not exceed the total output of the generator unit G and the storage battery B, in order from the power load L having the highest priority. . In the present embodiment, the load selection rule is configured to change dynamically every time zone, but may be configured to change dynamically every time such as season or month.
ここで、図4は、負荷選択ルールの一例を示す表である。図4では、電力負荷Lとして、共用部のエレベータ、災害情報や集合住宅コミュニティの情報等を取得するためのITリモコン、共用部の照明、給水ポンプ、住戸、セキュリティ設備、コージェネレーションの排熱回収装置による温水供給を行なう暖房ポンプ、及び、コージェネレーションの排熱回収装置による給湯を行なう給湯ポンプが設定されている。エレベータは、停電発生直後には、避難が必要な場合に備えて、停電直後の優先順位が高く設定され、その後は、使用回数を制限して稼動可能となるように優先順位が設定されている。具体的には、例えば、30分に15回稼動可能に設定する。ITリモコンは、停電期間中常時稼動するように、常時優先順位が高く設定されている。共用部の照明は、夜間に限り常時稼動するように、夜間の優先順位が高く設定されている。給水ポンプは、定期的に稼動させるように、定期的に優先順位が高く設定されている。尚、給水ポンプは、断水している場合には、受水槽内の生活水を集合住宅の各住戸に対し必要最低生活水量を供給できるように分配し、受水槽の水位が所定の最低水位以下になった場合には稼動を停止する。各住戸は、電力量を制限して一定電力を給電する。セキュリティ設備は、被害状況に応じて機能を復旧させるように、被害状況に応じて優先順位が設定される。暖房ポンプは、厳冬期に限り、例えば、共有部の集会室等に限定して温水供給を行なうように設定されている。給湯ポンプは、例えば、共用部の入浴設備に対する入浴時の給湯等、時間を指定して稼動させるように設定されている。 Here, FIG. 4 is a table showing an example of the load selection rule. In FIG. 4, as an electric load L, an elevator in a common area, an IT remote controller for acquiring disaster information and information on a housing complex, etc., lighting in a common area, water supply pump, dwelling unit, security equipment, cogeneration waste heat recovery A heating pump that supplies hot water by the apparatus and a hot water supply pump that supplies hot water by the exhaust heat recovery device of the cogeneration are set. The elevator is set to have a high priority immediately after a power failure, and then set to a priority so that it can be operated with a limited number of uses. . Specifically, for example, it is set to be operable 15 times in 30 minutes. The IT remote control is always set high in priority so that it always operates during a power failure. The priority of nighttime lighting is set high so that the lighting in the common area always operates only at nighttime. The water supply pump is regularly set to have a high priority so as to operate periodically. The water supply pump distributes the domestic water in the water receiving tank to each dwelling unit of the apartment house so that the required minimum living water volume can be supplied to each dwelling unit when the water supply is shut off. If it becomes, the operation is stopped. Each dwelling unit supplies a certain amount of power while limiting the amount of power. The security equipment is prioritized according to the damage situation so that the function is restored according to the damage situation. The heating pump is set so as to supply hot water only in a severe winter season, for example, limited to a meeting room of a shared section. The hot water supply pump is set so as to be operated at a specified time, for example, hot water supply at the time of bathing with respect to the bathing facilities in the common part.
制御手段14は、発電機ユニットGの出力が総予測電力需要を下回り、且つ、発電機ユニットGと蓄電池Bの合計出力が総予測電力需要を上回る場合に(ステップ#105でYes分岐、図3の破線b参照)、電力需要に応じて蓄電池Bの出力を制御する。 When the output of the generator unit G falls below the total predicted power demand and the total output of the generator unit G and the storage battery B exceeds the total predicted power demand (Yes in step # 105, FIG. 3). The output of the storage battery B is controlled according to the power demand.
制御手段14は、単位制御時間における発電機ユニットGの出力が総予測電力需要を上回る場合に(ステップ#103でYes分岐)、予測停電期間全体での蓄電池Bの必要蓄電池出力量を算出し(ステップ#108)、蓄電池Bの貯蓄電力量と必要蓄電池出力量を比較する(ステップ#109)。 When the output of the generator unit G in the unit control time exceeds the total predicted power demand (Yes in step # 103), the control unit 14 calculates the necessary storage battery output amount of the storage battery B in the entire predicted power outage period ( Step # 108), the stored power amount of the storage battery B is compared with the required storage battery output amount (step # 109).
制御手段14は、ステップ#109において、蓄電池Bの貯蓄電力量が必要蓄電池出力量を下回る場合に(ステップ#109でNo分岐)、発電機ユニットGを全出力運転に設定するとともに、発電機ユニットGの余剰電力を蓄電池Bに蓄電する(ステップ#110、図3の破線c参照)。 When the stored power amount of the storage battery B is less than the required storage battery output amount in Step # 109 (No branch at Step # 109), the control means 14 sets the generator unit G to full output operation and sets the generator unit. The surplus power of G is stored in the storage battery B (step # 110, see broken line c in FIG. 3).
制御手段14は、蓄電池Bの貯蓄電力量が必要蓄電池出力量を上回る場合に(ステップ#109でYes分岐)、発電機ユニットGの出力を電力負荷Lに追従させる制御を行なう(ステップ#111)。 When the stored power amount of the storage battery B exceeds the required storage battery output amount (Yes in step # 109), the control means 14 performs control for causing the output of the generator unit G to follow the power load L (step # 111). .
制御手段14は、ステップ#106、#107、#110、#111の実施後、所定時間、例えば10分経過すると、ステップ#103に移行して、次の単位制御時間における発電機ユニットGの出力と単位時間別予測電力需要の比較を行なう。系統電源の停電が解消された場合は、系統電源の正常時の制御に移行する。 When a predetermined time, for example, 10 minutes elapses after the execution of steps # 106, # 107, # 110, and # 111, the control means 14 proceeds to step # 103 and outputs the generator unit G in the next unit control time. Compare the predicted power demand by unit time. When the power failure of the system power supply is resolved, the control shifts to the normal control of the system power supply.
〈第2実施形態〉
本発明システム1の第2実施形態について図5を基に説明する。本実施形態の本発明システム1は、上記第1実施形態とは、蓄電池Bを備えない点で相違する。
Second Embodiment
A second embodiment of the system 1 of the present invention will be described with reference to FIG. The system 1 of the present embodiment is different from the first embodiment in that the storage battery B is not provided.
本実施形態における本発明システム1の制御手段14の処理について図5を基に説明する。 Processing of the control means 14 of the system 1 of the present invention in the present embodiment will be described with reference to FIG.
停電が発生し、停電判定手段11によって一般停電であることが認識されると、停電期間入力手段12は、予測停電期間を取得する(ステップ#201)。続いて、予測電力需要入力手段13は、電力需要の予測ツールから電力負荷L毎の単位時間別予測電力需要を取得する(ステップ#202)。 When a power failure occurs and the power failure determination means 11 recognizes that the power failure is a general power failure, the power failure period input means 12 acquires a predicted power failure period (step # 201). Subsequently, the predicted power demand input unit 13 acquires the predicted power demand by unit time for each power load L from the power demand prediction tool (step # 202).
本実施形態の制御手段14は、先ず、発電機ユニットGの出力と単位時間別予測電力需要を比較する(ステップ#203)。制御手段14は、発電機ユニットGの出力が単位時間別予測電力需要より低い場合(ステップ#203でNo分岐)、総予測電力需要が発電機ユニットGの出力を下回るように、発電機ユニットGからの電力供給対象となる電力負荷Lを所定の負荷選択ルールに基づいて選択する(ステップ#204)。続いて、制御手段14は、発電機ユニットGの出力を総予測電力需要に応じて制御する(ステップ#205)。 First, the control means 14 of the present embodiment compares the output of the generator unit G with the predicted power demand per unit time (step # 203). When the output of the generator unit G is lower than the predicted power demand per unit time (No branch at step # 203), the control means 14 causes the generator unit G so that the total predicted power demand falls below the output of the generator unit G. Is selected based on a predetermined load selection rule (step # 204). Subsequently, the control unit 14 controls the output of the generator unit G according to the total predicted power demand (step # 205).
制御手段14は、発電機ユニットGの出力が総予測電力需要を上回る場合に(ステップ#203でYes分岐)、電力需要に応じて発電機ユニットGの出力を制御する(ステップ#206)。 When the output of the generator unit G exceeds the total predicted power demand (Yes in step # 203), the control unit 14 controls the output of the generator unit G according to the power demand (step # 206).
制御手段14は、ステップ#205、#206の実施後、所定時間、例えば10分経過すると、ステップ#203に移行して、次の単位制御時間における発電機ユニットGの出力と単位時間別予測電力需要の比較を行なう。系統電源の停電が解消された場合は、系統電源の正常時の制御に移行する。 When a predetermined time, for example, 10 minutes elapses after the execution of steps # 205 and # 206, the control means 14 proceeds to step # 203, and the output of the generator unit G and the predicted power per unit time in the next unit control time. Compare demand. When the power failure of the system power supply is resolved, the control shifts to the normal control of the system power supply.
〈第3実施形態〉
本発明システム1の第3実施形態について図6を基に説明する。本実施形態の本発明システム1は、第1または第2実施形態の各構成に加え、複数の電力負荷L毎の単位時間別予測電力需要を算出する予測手段15を備えて構成されている。より具体的には、上記第1及び第2実施形態では、予測電力需要入力手段13が本発明システム1外に設置された電力需要の予測ツールが予測した単位時間別予想電力需要を取得する場合について説明したが、本実施形態では、予測電力需要入力手段13が本発明システム1内に設置された予測手段15が予測した単位時間別予想電力需要を取得する場合について説明する。
<Third Embodiment>
A third embodiment of the system 1 of the present invention will be described with reference to FIG. The system 1 of the present embodiment of the present embodiment is configured to include a prediction unit 15 that calculates a predicted power demand by unit time for each of the plurality of power loads L in addition to the components of the first or second embodiment. More specifically, in the first and second embodiments, the predicted power demand input unit 13 acquires the predicted power demand by unit time predicted by the power demand prediction tool installed outside the system 1 of the present invention. However, in the present embodiment, a case where the predicted power demand input unit 13 acquires the predicted power demand by unit time predicted by the prediction unit 15 installed in the system 1 of the present invention will be described.
本実施形態の予測電力需要入力手段13は、一般停電発生時に、後述する予測手段15から電力負荷L毎の単位時間別予測電力需要の入力を受け付ける。 The predicted power demand input means 13 of this embodiment accepts input of predicted power demand by unit time for each power load L from the prediction means 15 described later when a general power failure occurs.
予測手段15は、系統電源の正常時における過去の複数の電力負荷L毎の単位時間別の電力需要の推移を示す実績データに基づいて、単位時間別予測電力需要を算出する。より具体的には、過去の実績データに基づいて季節別、曜日別(平日休日別)の単位時間別予測電力需要のパターンを作成する。 The prediction unit 15 calculates the predicted power demand by unit time based on the actual data indicating the transition of the power demand by unit time for each of the past plurality of power loads L when the system power supply is normal. More specifically, a pattern of predicted power demand by unit time for each season and each day of the week (by weekday holiday) is created based on past performance data.
更に、本実施形態の予測手段15は、単位時間別予測電力需要を算出するために必要な実績データが蓄積されていない場合及び実績データの蓄積が不十分である場合に、集合住宅の住戸数、設備、延べ床面積、立地条件等の情報を含む物件情報に基づいて、単位時間別予測電力需要を算出する。より具体的には、予め設定された予測電力需要のモデル式に物件情報にかかるパラメータを適用することで、単位時間別予測電力需要を算出する。 Furthermore, the predicting means 15 of the present embodiment is configured so that the number of dwelling units in the housing complex is not obtained when the actual data necessary for calculating the predicted power demand per unit time is not accumulated and when the actual data is insufficiently accumulated. Based on property information including information on facilities, total floor area, location conditions, etc., the predicted power demand by unit time is calculated. More specifically, the predicted power demand for each unit time is calculated by applying a parameter relating to the property information to a preset model formula of the predicted power demand.
また、本実施形態の予測手段15は、停電発生後、受水槽の水位センサ、照明センサ、外気温センサ等からの情報に基づいて単位時間別予測電力需要の補正を行う。より具体的には、断水が発生し、受水槽の水位が所定の最低水位以下になり給水ポンプを停止させる場合には、給水ポンプに係る電力需要を単位時間別予測電力需要から除外する。また、照明センサからのデータにより、日中であっても雨天等により予測より日照量が少ないと認識される場合には、共用部の照明を点灯する必要がある。この場合には、共用部の照明を点灯するために必要な電力量を単位時間別予測電力需要に加える。更に、気温センサにより、例えば、予測より気温が低いと認識される場合は、暖房による電力需要が増すと考えられるため、単位時間別予測電力需要に暖房による電力需要の増加分を加味する。また、停電時の電力需要を電力負荷毎に測定し、所定の単位時間における測定値と単位時間別予測電力需要の値を比較し、比較結果に基づいて、単位時間別予測電力需要の補正を行う。このように構成することで、より精度良く単位時間別予測電力需要を予測することが可能になる。 Moreover, the prediction means 15 of this embodiment correct | amends the prediction electric power demand according to unit time based on the information from the water level sensor of a receiving tank, an illumination sensor, an external temperature sensor, etc. after a power failure generate | occur | produces. More specifically, when a water outage occurs and the water level in the water receiving tank is below a predetermined minimum water level and the feed water pump is stopped, the power demand related to the feed water pump is excluded from the unit time predicted power demand. Further, when it is recognized from the data from the illumination sensor that the amount of sunlight is less than expected due to rain or the like even during the daytime, it is necessary to turn on the illumination of the common part. In this case, the amount of power required to turn on the lighting of the common unit is added to the predicted power demand by unit time. Furthermore, when the temperature sensor recognizes that the temperature is lower than predicted, for example, it is considered that the power demand due to heating is increased. Therefore, the increase in power demand due to heating is added to the predicted power demand by unit time. In addition, the power demand at the time of a power outage is measured for each power load, the measured value in a predetermined unit time is compared with the value of the predicted power demand by unit time, and the predicted power demand by unit time is corrected based on the comparison result. Do. By comprising in this way, it becomes possible to predict the prediction electric power demand according to unit time with more accuracy.
〈別実施形態〉
〈1〉上記各実施形態では、集合住宅の電源構成が、エレベータ等の動力系、蓄電池B及びガスコージェネレーションシステムが接続された系統と、専有部の電力負荷L等が接続された系統と、停電時に発電機ユニットGからの電力供給を行なわない系統に分割され、各系統毎に変圧器を介して系統電源に接続されている場合について説明したが、これに限るものではない。
<Another embodiment>
<1> In each of the embodiments described above, the power source configuration of the apartment building includes a power system such as an elevator, a system to which the storage battery B and the gas cogeneration system are connected, a system to which the dedicated power load L and the like are connected, and a power failure Although the case where the system is sometimes divided into systems that do not supply power from the generator unit G and each system is connected to the system power supply via a transformer has been described, the present invention is not limited to this.
例えば、図7に示すように、系統電源21からの電力と、発電機ユニットGからの電力を、並列に接続された異なるノードを介して電力負荷L(L1、L2、・・・)に供給するように構成する。ここでは、電力負荷L毎に設けられたインバータ41、42を制御することで、電力負荷Lへの発電機ユニットGからの電力供給を制御している。インバータ41、42は、ガスエンジンEに接続された発電機ユニットGとコンバータ40を介して接続されている。また、インバータ41、42の入力側のノードには蓄電池Bが接続されている。インバータ41と電力負荷L1は、スイッチα11を介して、及び、スイッチα11と並列に設けられたスイッチα12及びスイッチα13を介して接続されている。スイッチα12及びスイッチα13の中間のノード43はスイッチ5を介して系統電源21に接続されている。同様に、インバータ42と電力負荷L2は、スイッチα21を介して、及び、スイッチα21と並列に設けられたスイッチα22及びスイッチα23を介して接続されている。スイッチα22及びスイッチα23の中間のノード43はスイッチ5を介して系統電源21に接続されている。インバータ41、42、及び、スイッチα(α11、α12、α13、α21、α22、α23、・・・)は制御手段14に接続されている。 For example, as shown in FIG. 7, the power load L (L 1 , L 2 ,...) Is supplied from the system power supply 21 and the power from the generator unit G via different nodes connected in parallel. It is configured to be supplied to. Here, the power supply from the generator unit G to the power load L is controlled by controlling the inverters 41 and 42 provided for each power load L. The inverters 41 and 42 are connected to the generator unit G connected to the gas engine E via the converter 40. In addition, a storage battery B is connected to an input side node of the inverters 41 and 42. Inverter 41 and power load L 1 via the switch alpha 11, and are connected via a switch alpha 12 and switches alpha 13 provided in parallel with the switch alpha 11. An intermediate node 43 between the switch α 12 and the switch α 13 is connected to the system power supply 21 via the switch 5. Similarly, the inverter 42 and the power load L 2 via the switch alpha 21, and are connected via the switches alpha 22 and switches alpha 23 provided in parallel with the switch alpha 21. An intermediate node 43 between the switch α 22 and the switch α 23 is connected to the system power supply 21 via the switch 5. The inverters 41 and 42 and the switch α (α 11 , α 12 , α 13 , α 21 , α 22 , α 23 ,...) Are connected to the control means 14.
尚、図7は系統電源21の停電時の電源構成を示している。停電時、制御手段14は、スイッチα11をオンに、スイッチα12及びスイッチα13をオフに制御して、電力負荷L1にインバータ41のみを接続し、電力負荷L1に発電機ユニットGからの電力のみを供給する。同様に、停電時、制御手段14は、スイッチα21をオンに、スイッチα22及びスイッチα23をオフに制御して、電力負荷L2にインバータ42のみを接続し、電力負荷L2に発電機ユニットGからの電力のみを供給する。このように構成することで、インバータの制御のみで各電力負荷Lへの電力供給を制御することができる。 FIG. 7 shows the power supply configuration of the system power supply 21 when a power failure occurs. During a power failure, the control means 14, turns on the switch alpha 11, switches alpha 12 and controls to turn off the switch alpha 13, the power load L 1 to connect only the inverter 41, the generator unit to the power load L 1 G Only power from is supplied. Similarly, during a power failure, the control means 14, turns on the switch alpha 21, and controls the switch off alpha 22 and switch alpha 23, connect only the inverter 42 to power the load L 2, the power generation in the electric power load L 2 Only power from the machine unit G is supplied. By comprising in this way, the electric power supply to each electric power load L is controllable only by control of an inverter.
系統電源21の正常時、制御手段14は、スイッチα11をオフに、スイッチα12及びスイッチα13をオンに制御して、電力負荷L1に系統電源21とインバータ41を接続し、系統電源21と発電機ユニットGの出力を系統連系して電力負荷L1に電力を供給する。同様に、系統電源21の正常時、制御手段14は、スイッチα21をオフに、スイッチα22及びスイッチα23をオンに制御して、電力負荷L2に系統電源21とインバータ42を接続し、系統電源21と発電機ユニットGの出力を系統連系して電力負荷L2に電力を供給する。 Normal of the system power source 21, control means 14, turns off the switch alpha 11, and controls to turn on the switch alpha 12 and switch alpha 13, and connect the system power supply 21 and the inverter 41 to power the load L 1, the system power supply 21 and supplies power output of the generator unit G to the power load L 1 and system interconnection. Similarly, when the system power source 21 is normal, the control unit 14 controls the switch α 21 to be turned off and the switch α 22 and the switch α 23 to be turned on to connect the system power source 21 and the inverter 42 to the power load L 2. supplies power to the power load L 2 the output of the generator unit G and the system power source 21 to the system interconnection.
〈2〉上記各実施形態では、1台のガスコージェネレーションシステム(発電機ユニットG)を設けた集合住宅の場合について説明したが、これに限るものではなく、発電機ユニットGが複数設けられている集合住宅に本発明システム1を設置しても良い。また、常用防災兼用ではない停電対応仕様の分散型発電機を利用して本発明システム1を構築しても良い。この場合には、停電判定手段11は、系統電源の停電を認識するように構成する。 <2> In each of the above embodiments, the case of an apartment house provided with one gas cogeneration system (generator unit G) has been described. However, the present invention is not limited to this, and a plurality of generator units G are provided. You may install this invention system 1 in a housing complex. Moreover, you may construct | assemble this invention system 1 using the distributed generator of a power failure response specification which is not combined with a regular disaster prevention. In this case, the power failure determination means 11 is configured to recognize a power failure of the system power supply.
〈3〉上記第1〜第3実施形態では、停電時、各住戸に対し電力量を制限して給電するように構成したが、例えば、停電時における各住戸への電源供給を、系統電源の正常時に使用する正常時用電気幹線とは別に停電時にのみ使用する停電時用電気幹線を設けて実施しても良い。 <3> In the first to third embodiments, the power supply is limited and supplied to each dwelling unit at the time of a power failure. For example, power supply to each dwelling unit at the time of a power outage is You may carry out by providing the electric trunk for power failure used only at the time of a power failure separately from the electric trunk for normal time used at the time of normal.
具体的には、図8に示すように、第1実施形態(図1参照)の各構成に加え、スイッチ5を介して受電点2に単相変圧器33を接続し、単相変圧器33から各住戸LDK(K=1、2、・・・)に対し電源供給を行なう。各住戸LDKは、系統電源の停電時は、系統電源の停電時に使用する停電時用電気幹線である配線Waから、系統電源の正常時は、系統電源の正常時に使用する正常時用電気幹線である配線Wbから電源供給されるように構成されており、配線Wa及び配線Wbは、電力計WhE及びスイッチαEを介して単相変圧器33に接続されている。 Specifically, as shown in FIG. 8, in addition to the components of the first embodiment (see FIG. 1), a single-phase transformer 33 is connected to the power receiving point 2 via the switch 5. To supply power to each dwelling unit L DK (K = 1, 2,...). Each dwelling unit LDK has a normal electric trunk line that is used when the system power supply is normal, when the system power supply is normal. The wiring Wb and the wiring Wb are connected to the single-phase transformer 33 via the wattmeter Wh E and the switch α E.
各住戸LDKには、停電時に電力供給を行なう重要負荷、停電時に電力供給を行わない電力負荷、系統電源の正常時に配線Wbからの電力を受ける分電盤DK、及び、系統電源の停電時に配線Waからの電力を受けるブレーカBRKが設置されている。分電盤DKは、主幹ブレーカ及び分岐ブレーカを備え、主幹ブレーカに配線Wbが接続されている。
ブレーカBRKは、停電時において、予め定められた所定の電力量を重要負荷に給電するように、定格電力量が設定されている。所定の電力量は、例えば、発電機ユニットGの発電量を総住戸数で除算した値に基づいて設定する。重要負荷は、スイッチαDKを介して分電盤DKの分岐ブレーカ及びブレーカBRKの何れか一方に接続される。電力負荷は、分電盤DKの分岐ブレーカに接続されている。
Each dwelling unit L DK, important load for supplying power during a power outage and does not supply power to power failure power load distribution board D K receiving power from wire Wb during normal system power source, and, a power failure of the system power source breaker BR K is installed to at receive power from the wiring Wa. Panelboard D K is provided with a main breaker and the branch breakers, wire Wb are connected to the master breaker.
Breaker BR K, during a power failure, so as to feed a predetermined amount of power to a predetermined critical load, is set rated power. The predetermined power amount is set based on, for example, a value obtained by dividing the power generation amount of the generator unit G by the total number of dwelling units. Critical load is connected to one of the branch breakers and breaker BR K distribution board D K via the switch alpha DK. Power load is connected to the branch breaker panelboard D K.
系統電源の停電時は、スイッチαEを配線Waを選択するように切り替え、スイッチαDKをブレーカBRKを選択するように切り替える。更に、系統電源の正常時は、スイッチαEを配線Wbを選択するように切り替え、スイッチαDKを分電盤DKを選択するように切り替える。このようにスイッチαE及びスイッチαDKを切り替えることで、系統電源の停電時は各住戸LDKの重要負荷に対し、系統電源の正常時は各住戸LDKの重要負荷及び電力負荷に対して電源供給を行なうことが可能になる。 During a power failure of the system power source is changed over to select the wire Wa switches alpha E, switches the switch alpha DK to select the breaker BR K. Furthermore, when normal system power source switches the switch alpha E to select the wire Wb, it switched so as to select the distribution board D K switches alpha DK. By switching the switch α E and the switch α DK in this way, for the important load of each dwelling unit L DK at the time of power failure of the system power supply, for the important load and power load of each dwelling unit L DK when the system power supply is normal Power supply can be performed.
〈4〉上記各実施形態では、非常停電時に防災負荷に対して電源供給を行なう常用防災兼用コージェネレーションシステムに本発明を適用する場合について説明したが、一般停電及び非常停電を区別しない停電対応仕様コージェネレーションシステムに本発明を適用しても良い。より具体的には、停電対応仕様コージェネレーションシステムの場合、図1の停電判定手段11を系統電源の停電の発生を判定するように構成し、停電発生時に、上記各実施形態における一般停電の場合と同様の制御を行なうように構成する。 <4> In each of the above embodiments, the case where the present invention is applied to a common disaster prevention cogeneration system that supplies power to a disaster prevention load at the time of an emergency power failure has been described. The present invention may be applied to a cogeneration system. More specifically, in the case of a power outage specification cogeneration system, the power outage determination means 11 in FIG. 1 is configured to determine the occurrence of a power outage of the system power supply. The same control as that described above is performed.
〈5〉上記各実施形態では、非常停電時に防災負荷に対して電源供給を行なう常用防災兼用コージェネレーションシステムを想定し、一般停電時に電源供給対象となる電力負荷を選択する場合について説明したが、常用防災兼用コージェネレーションシステムにおいて、非常停電時の場合にも電源供給対象となる電力負荷を防災負荷に追加して選択可能に構成しても良い。例えば、常用防災兼用コージェネレーションシステムにおいて、発電容量が防災負荷容量よりも大きく、余力がある場合、火災警報器や防災設備の起動信号を受信した時に、発電容量から防災負荷容量を差し引いた余力発電容量(蓄電池を備えるコージェネレーションシステムの場合は、余力発電容量と蓄電池出力)分については、上記各実施形態における一般停電の場合と同様の制御を行うように構成しても良い。 <5> In each of the above embodiments, a case has been described in which a common disaster prevention cogeneration system that supplies power to a disaster prevention load at the time of an emergency power failure is selected, and a power load that is a power supply target at the time of a general power failure is selected. The common disaster prevention cogeneration system may be configured so that the power load to be supplied with power can be added to the disaster prevention load even in the event of an emergency power failure. For example, in a common disaster prevention cogeneration system, if the power generation capacity is larger than the disaster prevention load capacity and there is surplus capacity, the surplus power generation that subtracts the disaster prevention load capacity from the power generation capacity when receiving a start signal of a fire alarm or disaster prevention equipment For the capacity (in the case of a cogeneration system including a storage battery, surplus power generation capacity and storage battery output), the same control as in the case of the general power failure in each of the above embodiments may be performed.
1 本発明に係る分散型発電機の制御システム
2 受電点
3 単相変圧器
4 動力三相変圧器
5 スイッチ
11 停電判定手段
12 停電期間入力手段
13 予測電力需要入力手段
14 制御手段
15 予測手段
21 系統電源
31 単相変圧器
32 単相変圧器
33 単相変圧器
40 コンバータ
41 インバータ
42 インバータ
43 ノード
B 蓄電池
BR ブレーカ
D 分電盤
E ガスエンジン
G 発電機ユニット
L 電力負荷
Wh 電力計
Wa 配線
Wb 配線
α スイッチ
DESCRIPTION OF SYMBOLS 1 Control system of the distributed generator which concerns on this invention 2 Power receiving point 3 Single phase transformer 4 Power three phase transformer 5 Switch 11 Power failure determination means 12 Power failure period input means 13 Predictive power demand input means 14 Control means 15 Predictive means 21 System power supply 31 Single-phase transformer 32 Single-phase transformer 33 Single-phase transformer 40 Converter 41 Inverter 42 Inverter 43 Node B Storage battery BR Breaker D Distribution board E Gas engine G Generator unit L Power load Wh Power meter Wa Wiring Wb Wiring α switch
Claims (10)
前記系統電源の停電が発生した際に、該停電が火災等の災害に伴う非常停電であるかそれ以外の一般停電であるかを認識する停電判定手段と、
前記一般停電発生時に、前記一般停電の予測停電期間の入力を受け付ける停電期間入力手段と、
前記一般停電発生時に、前記複数の電力負荷毎の単位時間別予測電力需要の入力を受け付ける予測電力需要入力手段と、
前記一般停電発生時に、前記予測停電期間を分割した単位制御時間毎に、次の前記単位制御時間における前記分散型発電機からの電力供給対象となる全ての前記電力負荷の前記単位時間別予測電力需要を合計した総予測電力需要に基づいて、前記電力負荷に対する電力供給を制御する制御手段と、を備え、
前記制御手段は、前記単位制御時間における前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を下回る場合に、前記総予測電力需要が前記分散型発電機と前記蓄電池の合計出力を下回るように、前記分散型発電機からの電力供給対象となる前記電力負荷を所定の負荷選択ルールに基づいて選択し、
前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を下回り、且つ、前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を上回る場合に、前記分散型発電機を全出力運転に設定し、前記蓄電池の出力を前記総予測電力需要と前記分散型発電機の出力の差に追従させる制御を行い、
前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合に、前記予測停電期間全体での前記蓄電池の必要蓄電池出力量を算出し、前記蓄電池の貯蓄電力量が前記必要電池出力量を下回る場合に、前記分散型発電機を全出力運転に設定するとともに、前記分散型発電機の余剰電力を前記蓄電池に蓄電し、
前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合であって、前記蓄電池の貯蓄電力量が前記必要電池出力量を上回る場合に、前記分散型発電機の出力を前記電力負荷に追従させる制御を行なうことを特徴とする分散型発電機の制御システム。 A distributed generator control system for controlling power supply to a plurality of power loads in the apartment house by one or a plurality of distributed generators and a storage battery installed in an apartment house so as to be connected to a system power source,
When a power failure occurs in the system power supply, a power failure determination means for recognizing whether the power failure is an emergency power failure due to a disaster such as a fire or other general power failure,
When the general power failure occurs, a power failure period input means for receiving an input of the predicted power failure period of the general power failure;
Predicted power demand input means for receiving input of predicted power demand by unit time for each of the plurality of power loads when the general power failure occurs,
For each unit control time obtained by dividing the predicted power outage period when the general power outage occurs, the predicted power per unit time of all the power loads to be supplied with power from the distributed generator in the next unit control time Control means for controlling the power supply to the power load based on the total predicted power demand obtained by summing the demands,
The control means, when the total output of the distributed generator and the storage battery in the unit control time is less than the total predicted power demand, the total predicted power demand is the total output of the distributed generator and the storage battery. To select the power load to be supplied from the distributed generator based on a predetermined load selection rule,
When the output of the distributed generator in the unit control time is less than the total predicted power demand, and the total output of the distributed generator and the storage battery exceeds the total predicted power demand, the distributed generator Is set to full output operation, the output of the storage battery is controlled to follow the difference between the total predicted power demand and the output of the distributed generator,
When the output of the distributed generator in the unit control time exceeds the total predicted power demand, the required storage battery output amount of the storage battery in the entire predicted power outage period is calculated, and the stored power amount of the storage battery is the required power When the battery output amount is lower, the distributed generator is set to full output operation, and the surplus power of the distributed generator is stored in the storage battery,
When the output of the distributed generator in the unit control time exceeds the total predicted power demand, and the stored power amount of the storage battery exceeds the required battery output amount, the output of the distributed generator is A control system for a distributed generator, which performs control to follow the power load.
前記系統電源の停電を認識する停電判定手段と、
停電発生時に、該停電の予測停電期間の入力を受け付ける停電期間入力手段と、
停電発生時に、前記複数の電力負荷毎の単位時間別予測電力需要の入力を受け付ける予測電力需要入力手段と、
停電発生時に、前記予測停電期間を分割した単位制御時間毎に、次の前記単位制御時間における前記分散型発電機からの電力供給対象となる全ての前記電力負荷の前記単位時間別予測電力需要を合計した総予測電力需要に基づいて、前記電力負荷に対する電力供給を制御する制御手段と、を備え、
前記制御手段は、前記単位制御時間における前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を下回る場合に、前記総予測電力需要が前記分散型発電機と前記蓄電池の合計出力を下回るように、前記分散型発電機からの電力供給対象となる前記電力負荷を所定の負荷選択ルールに基づいて選択し、
前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を下回り、且つ、前記分散型発電機と前記蓄電池の合計出力が前記総予測電力需要を上回る場合に、前記分散型発電機を全出力運転に設定し、前記蓄電池の出力を前記総予測電力需要と前記分散型発電機の出力の差に追従させる制御を行い、
前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合に、前記予測停電期間全体での前記蓄電池の必要蓄電池出力量を算出し、前記蓄電池の貯蓄電力量が前記必要電池出力量を下回る場合に、前記分散型発電機を全出力運転に設定するとともに、前記分散型発電機の余剰電力を前記蓄電池に蓄電し、
前記単位制御時間における前記分散型発電機の出力が前記総予測電力需要を上回る場合であって、前記蓄電池の貯蓄電力量が前記必要電池出力量を上回る場合に、前記分散型発電機の出力を前記電力負荷に追従させる制御を行なうことを特徴とする分散型発電機の制御システム。 A distributed generator control system for controlling power supply to a plurality of power loads in the apartment house by one or a plurality of distributed generators and a storage battery installed in an apartment house so as to be connected to a system power source,
A power failure determination means for recognizing a power failure of the system power supply,
A power failure period input means for receiving an input of a predicted power failure period of the power failure when a power failure occurs
Predictive power demand input means for receiving input of predicted power demand by unit time for each of the plurality of power loads when a power failure occurs,
For each unit control time obtained by dividing the predicted power outage period when a power outage occurs, the predicted power demand by unit time of all the power loads to be supplied with power from the distributed generator in the next unit control time is calculated. Control means for controlling power supply to the power load based on the total estimated power demand,
The control means, when the total output of the distributed generator and the storage battery in the unit control time is less than the total predicted power demand, the total predicted power demand is the total output of the distributed generator and the storage battery. To select the power load to be supplied from the distributed generator based on a predetermined load selection rule,
When the output of the distributed generator in the unit control time is less than the total predicted power demand, and the total output of the distributed generator and the storage battery exceeds the total predicted power demand, the distributed generator Is set to full output operation, the output of the storage battery is controlled to follow the difference between the total predicted power demand and the output of the distributed generator,
When the output of the distributed generator in the unit control time exceeds the total predicted power demand, the required storage battery output amount of the storage battery in the entire predicted power outage period is calculated, and the stored power amount of the storage battery is the required power When the battery output amount is lower, the distributed generator is set to full output operation, and the surplus power of the distributed generator is stored in the storage battery,
When the output of the distributed generator in the unit control time exceeds the total predicted power demand, and the stored power amount of the storage battery exceeds the required battery output amount, the output of the distributed generator is A control system for a distributed generator, which performs control to follow the power load.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2006177764A JP4606389B2 (en) | 2006-06-28 | 2006-06-28 | Distributed generator control system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2006177764A JP4606389B2 (en) | 2006-06-28 | 2006-06-28 | Distributed generator control system |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2008011612A JP2008011612A (en) | 2008-01-17 |
| JP4606389B2 true JP4606389B2 (en) | 2011-01-05 |
Family
ID=39069288
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2006177764A Expired - Fee Related JP4606389B2 (en) | 2006-06-28 | 2006-06-28 | Distributed generator control system |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4606389B2 (en) |
Families Citing this family (33)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20110182094A1 (en) | 2007-08-13 | 2011-07-28 | The Powerwise Group, Inc. | System and method to manage power usage |
| JP5400441B2 (en) * | 2009-03-23 | 2014-01-29 | 大阪瓦斯株式会社 | Cogeneration system and its control device |
| JP2011010471A (en) * | 2009-06-26 | 2011-01-13 | Tamura Seisakusho Co Ltd | Power control system during power failure |
| JP5712476B2 (en) * | 2009-09-10 | 2015-05-07 | ダイキン工業株式会社 | Demand control system |
| KR100951580B1 (en) | 2009-09-30 | 2010-04-09 | 오영권 | Overload driving method for an auto-switching apparatus based on a real-time power flow |
| KR100972841B1 (en) * | 2009-09-30 | 2010-07-28 | 오영권 | Auto switching apparatus based on a real-time power flow and a power distributor with the same |
| KR100941401B1 (en) | 2009-09-30 | 2010-02-10 | 오영권 | Real-time switching method on a reserve power supply condition for an auto-switching apparatus based on a real-time power flow |
| KR100941397B1 (en) | 2009-09-30 | 2010-02-10 | 오영권 | Auto switching apparatus based on a real-time power flow and a power distributor with the same |
| JP5807171B2 (en) * | 2009-09-30 | 2015-11-10 | パナソニックIpマネジメント株式会社 | Energy management system and power supply control device |
| WO2011107846A1 (en) * | 2010-03-01 | 2011-09-09 | パナソニック電工株式会社 | Electric power supply system |
| JP5548061B2 (en) * | 2010-08-05 | 2014-07-16 | トヨタホーム株式会社 | Apartment house power supply system |
| GB2483305A (en) * | 2010-09-06 | 2012-03-07 | Sony Corp | Managing consumption of renewable energy |
| US9583941B2 (en) | 2011-09-26 | 2017-02-28 | Nec Corporation | Power connection control system and method |
| JP5729764B2 (en) * | 2011-09-28 | 2015-06-03 | 京セラ株式会社 | Apartment house power system and control device |
| JP2013143816A (en) * | 2012-01-10 | 2013-07-22 | Ntt Facilities Inc | Power supply system, power supply control device, power supply method and program |
| JP2013247751A (en) | 2012-05-25 | 2013-12-09 | Sony Corp | Power controller, power supply control method and power supply control program |
| JP5964668B2 (en) * | 2012-06-18 | 2016-08-03 | トヨタホーム株式会社 | Backup power supply system |
| JP5851359B2 (en) * | 2012-07-18 | 2016-02-03 | トヨタホーム株式会社 | Storage battery control system |
| JP5978865B2 (en) * | 2012-09-05 | 2016-08-24 | 沖電気工業株式会社 | Power supply / demand control device, power supply / demand system, power supply / demand control method, and program |
| WO2014092195A1 (en) | 2012-12-10 | 2014-06-19 | 日本電気株式会社 | Distributed power generation system, control station, and control method therefor |
| CN105144537A (en) | 2013-03-28 | 2015-12-09 | 中国电力株式会社 | Power supply control device |
| JP5586811B1 (en) | 2013-03-28 | 2014-09-10 | 中国電力株式会社 | Power supply control device |
| JP6099545B2 (en) * | 2013-11-15 | 2017-03-22 | 株式会社日立製作所 | Recovery support system and recovery support method |
| JP6246091B2 (en) * | 2014-07-24 | 2017-12-13 | トヨタホーム株式会社 | Power supply system |
| JP6659222B2 (en) * | 2015-02-13 | 2020-03-04 | 株式会社東芝 | Generator monitoring device, generator monitoring method and program |
| JP6462411B2 (en) * | 2015-02-26 | 2019-01-30 | 株式会社東芝 | Load control test apparatus, load control test system, load control test method, and program |
| JP6029713B1 (en) * | 2015-06-17 | 2016-11-24 | 三菱電機株式会社 | POWER MANAGEMENT DEVICE, DEVICE SYSTEM, POWER MANAGEMENT METHOD, AND PROGRAM |
| JP6609520B2 (en) * | 2016-06-21 | 2019-11-20 | 株式会社日立製作所 | Microgrid control apparatus and method |
| TWI710192B (en) * | 2019-07-26 | 2020-11-11 | 許俊吉 | Disaster prevention circuit breaker system for solar power transmission |
| JP7354720B2 (en) * | 2019-09-25 | 2023-10-03 | 住友電気工業株式会社 | Judgment device, judgment method and computer program |
| WO2022034650A1 (en) * | 2020-08-12 | 2022-02-17 | 三菱電機株式会社 | Power management device and power management method |
| JP2023032750A (en) * | 2021-08-27 | 2023-03-09 | 株式会社シンテック | Power supply support system |
| JP7836218B2 (en) * | 2022-04-06 | 2026-03-26 | 旭化成ホームズ株式会社 | Power supply system |
Family Cites Families (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3259296B2 (en) * | 1991-11-29 | 2002-02-25 | 株式会社明電舎 | Reverse power prevention method for cogeneration system |
| JPH06335171A (en) * | 1993-05-18 | 1994-12-02 | Yaskawa Electric Corp | Load control method |
| JP2000184600A (en) * | 1998-12-16 | 2000-06-30 | Meidensha Corp | Selected load cut-off apparatus |
| JP2004040930A (en) * | 2002-07-04 | 2004-02-05 | Osaka Gas Co Ltd | Power generation system |
| WO2004023625A1 (en) * | 2002-09-04 | 2004-03-18 | Hitachi, Ltd. | Power supply system and power supply method upon interruption of electric service |
| JP3782074B2 (en) * | 2003-06-25 | 2006-06-07 | グリーンエナジー株式会社 | Uninterruptible power system and method using emergency generator |
| JP2005086984A (en) * | 2003-09-11 | 2005-03-31 | Osaka Gas Co Ltd | Power supply system and facility |
| JP2005168125A (en) * | 2003-12-01 | 2005-06-23 | Hitachi Ltd | Distributed power system in home |
-
2006
- 2006-06-28 JP JP2006177764A patent/JP4606389B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2008011612A (en) | 2008-01-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4606389B2 (en) | Distributed generator control system | |
| JP7101744B2 (en) | Power supply system and power supply method | |
| JP5837322B2 (en) | Control device, power control system, and power control method | |
| CN107425518B (en) | Load management in a hybrid power system | |
| EP2475060B1 (en) | Energy storage system | |
| US9620990B2 (en) | Electricity supply management device | |
| JP6604327B2 (en) | Distributed power supply system, station control device, control method, and storage medium storing program | |
| JP5729764B2 (en) | Apartment house power system and control device | |
| JP6426922B2 (en) | Electric power system, control device and charge / discharge control method | |
| JP6592360B2 (en) | Power management method | |
| JP2011250673A (en) | Energy controller and control method | |
| JP2013038838A (en) | Collective housing power system | |
| JP3756020B2 (en) | Power management equipment | |
| KR102145323B1 (en) | Monitoring System and Method for Management of Distributed Generation Plant | |
| JP5933318B2 (en) | Building power control system and residential power management system | |
| JP6055198B2 (en) | Power control system | |
| JP2007028735A (en) | Distributed power supply system and method | |
| JP7712018B2 (en) | Power management system, power management device, power management method, and computer program | |
| WO2018088967A1 (en) | System and method for operating a mains power grid | |
| JP2014174769A (en) | Energy controller, control method and control program | |
| JP2012151977A (en) | Load leveling system | |
| JP2017195752A (en) | Power control system and power control method | |
| JP2020068555A (en) | Power management system and housing | |
| JP2022025698A (en) | Renewable energy power generation system | |
| JP6316786B2 (en) | Power supply control unit and power supply system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20081209 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20100624 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100706 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100806 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100914 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20101005 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 4606389 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131015 Year of fee payment: 3 |
|
| LAPS | Cancellation because of no payment of annual fees |