JP4636404B2 - Control equipment for private power generation facilities - Google Patents
Control equipment for private power generation facilities Download PDFInfo
- Publication number
- JP4636404B2 JP4636404B2 JP2004344043A JP2004344043A JP4636404B2 JP 4636404 B2 JP4636404 B2 JP 4636404B2 JP 2004344043 A JP2004344043 A JP 2004344043A JP 2004344043 A JP2004344043 A JP 2004344043A JP 4636404 B2 JP4636404 B2 JP 4636404B2
- Authority
- JP
- Japan
- Prior art keywords
- power
- power generation
- private
- received
- generation facility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
本発明は、自家用発電設備の始動停止および発電電力制御を行う制御装置に関する。 The present invention relates to a control device that performs start-stop of a private power generation facility and control of generated power.
系統連系する自家用発電設備の基本的な構成は図5に示すように、発電機1、原動機2、調速機3、発電コントローラ4、自動電圧調整器(AVR)5から成り、遮断器6を介して構内系統に接続され需要家電力負荷8(一つの負荷に集約して表記しているが実際は複数の負荷から成る)に電力供給し、さらに遮断器9を介して電力系統と連系されている。また、保護装置として発電機異常を保護する発電機保護装置10および電力系統との連系保護のための系統連系保護装置11が設置されている。このような系統連系する自家用発電設備において発電機出力の制御は発電コントローラ4により行われる。発電電力制御は、自家用発電設備電力計12および受電電力計13による電力計測値のフィードバック信号と、受電電力設定器30により設定される受電電力設定値とを用いて、発電コントローラ4が発電電力指令値を決定し、調速機3を動作させ、発電機出力が制御される。ここで、受電電力設定値とは、需要家電力負荷8の必要とする電力に対して電力会社から受電して供給する電力を意味している。発電機出力は、需要家電力負荷8の電力から受電電力設定値を差し引いた電力を出力するように制御することになる。
As shown in FIG. 5, the basic configuration of the grid-connected private power generation facility includes a generator 1, a
このとき、需要家電力負荷8に電力供給するに際して、電力会社から受電する電力と自家用発電設備を使っての電力との両方を利用することになるので、より安価な電力を利用することは、重要な検討事項となる。昼間の電力ピーク時(一般的に電力負荷のピークは昼にある)には、電力会社からの購入電力価格が高いため自家用発電設備を出来るだけ運転するように制御する。一方、夜間の購入電力価格は昼間より安価な価格に設定されており、それは自家用発電設備の電力価格よりも安価であることから、出来るだけ電力会社から受電する電力を利用するように制御する。このような背景から、従来、夜間においては基本的に自家用発電設備は停止状態にあり、需要家電力負荷8の電力が電力会社との契約電力を超えそうな場合に自家用発電設備を運転している。 At this time, when power is supplied to the consumer power load 8, both the power received from the power company and the power using the private power generation facility are used. An important consideration. At the time of daytime power peak (generally, the peak of power load is in the daytime), since the price of power purchased from the power company is high, control is performed so that the private power generation facility is operated as much as possible. On the other hand, the purchased power price at night is set to a price that is cheaper than that of the daytime, which is cheaper than the power price of the private power generation facility, so that the power received from the power company is controlled as much as possible. Against this background, in the past, private power generation facilities have basically been stopped at night, and when the power of the customer power load 8 is likely to exceed the contract power with the power company, the private power generation facilities are operated. Yes.
自家用発電設備の始動停止および発電電力制御には、図5の発電機始動設定器31からの発電機始動設定値、発電機停止設定器32からの発電機停止設定値を用いている。図6のフロー図に示すように、判定1の受電電力設定値と発電機始動設定値の合計値に対して受電電力(自家用発電設備は停止中なので、この場合の受電電力は需要家電力負荷8の負荷電力と等しい)が上回ったときに、自家用発電設備を始動する。発電機始動設定値は、発電機の運転に際してエンジンの寿命を考慮して定められている下限の運転出力を考慮して、例えば下限の運転出力が発電機定格出力の30%であれば、10%プラスして40%を発電機始動設定値とする。自家用発電設備を始動後は、受電電力設定値どおりの受電電力となるように自家用発電設備側の出力を変化させる受電電力一定制御で運転する。さらに、判定2の負荷電力(=受電電力+発電電力)が受電電力設定値と発電機停止設定値の合計を下回ったときに、自家用発電設備を停止させる。発電機停止設定値は、先に述べた発電機の下限の運転出力値とする。
The generator start setting value from the generator
関連する先行技術文献として、商用電力系統と連系して需要家電力負荷に給電する自家用発電設備を備えるシステムにおいて、商用電力系統からの受電電力の制御手法について特許文献1および特許文献2に開示されている。
このように図6のフローに従った従来の自家用発電設備の始動停止および発電電力制御では、電力会社の安価な電力をできるだけ利用したい夜間において、自家用発電設備を始動せざるを得なくなった時にも、昼間と同様に負荷が増えていくと受電電力一定制御で自家用発電設備側の出力を増やす自家用発電設備側を主とする運転を行っていたため、安価な電力会社の電力を充分に利用できていないという問題がある。また、自家用発電設備は低い負荷率で運転することになるので、自家用発電設備にとっては燃費効率が悪く高コストな領域で運転するという問題がある。 As described above, in the conventional start / stop of the private power generation facility and the generated power control according to the flow of FIG. 6, when the private power generation facility has to be started at night when it is desired to use cheap power of the power company as much as possible. As in the daytime, when the load increases, the operation of the private power generation facility side, which increases the output of the private power generation facility side with constant control of the received power, was performed, so the power from cheap power companies could be fully utilized. There is no problem. In addition, since the private power generation facility is operated at a low load factor, there is a problem that the private power generation facility operates in a high-cost area with low fuel efficiency.
さらに、自家用発電設備のメンテナンスコストは、運転時間に伴うので、出来るだけ運転したくない夜間に運転することはメンテナンスコストの点からも問題である。 Furthermore, since the maintenance cost of the private power generation facility is associated with the operation time, it is problematic from the viewpoint of maintenance cost to operate at night when you do not want to operate as much as possible.
本発明は、上記のような事情に鑑みてなされたもので、その課題は電力会社からの電力購入を主とする時間帯における自家用発電設備の始動停止および発電電力制御に関して、電力会社の電力をより多く利用し、自家用発電設備の燃費コストやメンテナンスコストに対しても配慮した自家用発電設備の制御装置を提供することにある。 The present invention has been made in view of the circumstances as described above, and the problem is that the power company's power is related to the start / stop of the private power generation facility and the generated power control in the time zone mainly for power purchase from the power company. The purpose is to provide a control device for a private power generation facility that is used more frequently and takes into account the fuel cost and maintenance cost of the private power generation facility.
前記課題を解決するために、請求項1記載の発明は、電力会社商用電力系統と連系して需要家電力負荷に電力供給する自家用発電設備を備え、電力会社からの購入電力の価格が自家発電設備の電力価格よりも安価なとき、商用電力系統側の電力を優先して使用するように制御する自家用発電設備の制御装置において、需要家が電力会社から受電する受電電力を検出する受電電力計と、規定された30分間で需要家が電力会社から受電する受電電力量を検出する受電電力量計と、自家用発電設備からの出力電力を検出する自家用発電設備電力計と、規定された30分間における自家用発電設備からの出力電力量を検出する自家用発電設備電力量計と、規定された30分間の最初の5分間程度から10分間程度にて前記受電電力量計で検出される受電電力量から規定された30分間における受電電力量を予測する受電電力量予測手段と、前記受電電力量予測手段により、予測された30分間の受電電力量予測値を2倍することで算出される30分間平均の受電電力予測値とレベル判定設定器によるレベル判定値とを比較し、前記受電電力予測値の方が大きい場合に自家発電設備に始動指令を出力する比較器と、自家用発電設備の発電出力値を設定する発電出力設定器と、前記受電電力量予測手段により予測された30分間における受電電力量から前記レベル判定値設定器によるレベル判定値を2で除した値を減じる減算手段と、前記比較器から始動指令が出力されたとき、前記減算手段による減算結果を後続する手段に出力するスイッチと、前記スイッチを介して得られた前記減算手段による減算結果を前記発電出力設定器による発電出力値で除することで自家用発電設備が前記需要家負荷に電力供給する時間間隔を導出する負荷給電時間設定手段と、前記負荷給電時間設定手段により設定された時間間隔で自家用発電設備が前記需要家電力負荷に電力供給すると自家用発電設備に停止指令を出力するタイマーとを具備し、前記比較器からの出力により自家発電設備を始動し、前記発電出力設定器にて設定された発電出力値を発電電力目標値として運転し、前記タイマーからの出力により自家用発電設備を停止することを特徴とする。 In order to solve the above-mentioned problem, the invention according to claim 1 is provided with a private power generation facility that is connected to a commercial power grid of a power company and supplies power to a consumer power load, and the price of purchased power from the power company is private. Received power that detects the received power received by the customer from the power company in the control device of the private power generation facility that controls to use the power on the commercial power system with priority when it is cheaper than the power price of the power generation facility A power meter for detecting the amount of power received by the consumer from the power company in the specified 30 minutes, a power generation facility power meter for detecting the output power from the private power generation facility, and the specified 30 The power generation equipment watt-hour meter for detecting the amount of output power from the private power generation equipment for a minute and the received power watt-hour meter for about 10 minutes from the first 5 minutes of the specified 30 minutes Calculated by doubling the predicted received power amount for 30 minutes by the received power amount prediction means for predicting the received power amount for 30 minutes specified from the amount of electric power, and the received power amount prediction means. Comparing the average received power predicted value for 30 minutes with the level determination value by the level determination setter, and when the received power predicted value is larger, a comparator that outputs a start command to the private power generation facility, and the private power generation facility A power generation output setter for setting a power generation output value; and a subtracting unit for subtracting a value obtained by dividing the level determination value by the level determination value setter by 2 from the received power amount for 30 minutes predicted by the received power amount prediction unit; A switch for outputting a result of subtraction by the subtracting means to a subsequent means when a start command is output from the comparator; and the subtracting means obtained via the switch The power supply time setting means for deriving a time interval for supplying power to the consumer load by the private power generation facility by dividing the subtraction result by the power generation output value by the power generation output setting device, and the load power supply time setting means A timer that outputs a stop command to the private power generation facility when the private power generation facility supplies power to the consumer power load at a predetermined time interval, and starts the private power generation facility by the output from the comparator, and the power generation output The power generation output value set by the setting device is operated as the generated power target value, and the private power generation facility is stopped by the output from the timer.
本発明によると、電力会社の商用電力系統と連系して需要家電力負荷に電力供給する自家用発電設備において、電力会社からの購入電力が安価な時間帯は出来るだけ電力会社の電力を利用しつつ、自家用発電設備においても燃費コストやメンテナンスコストの低減を可能とする自家用発電設備の始動停止および発電電力制御を行う制御装置を提供することができる。 According to the present invention, in a private power generation facility that supplies power to a consumer power load in conjunction with a commercial power system of an electric power company, the electric power of the electric power company is used as much as possible during times when the purchased electric power from the electric power company is inexpensive. On the other hand, it is possible to provide a control device for starting and stopping the private power generation facility and controlling the generated power, which enables reduction in fuel cost and maintenance cost even in the private power generation facility.
本発明を実施するための最良の形態を図を参照して説明する。
(第1実施形態)
図1は、本発明の第1実施形態の構成図であり、従来の自家用発電設備を示す図5と異なる構成は、発電コントローラ4への入力として、受電電力設定器30からの受電電力設定値と発電機始動設定器31からの発電機始動設定値および発電機停止設定器32は用いずに、レベル判定値設定器36からのレベル判定値とヒステリシス設定器33からのヒステリシス設定値を用いている点と、自家用発電設備始動後は、最低発電出力設定器34による最低発電出力設定値を用いる点である。
The best mode for carrying out the present invention will be described with reference to the drawings.
(First embodiment)
FIG. 1 is a configuration diagram of the first embodiment of the present invention. A configuration different from FIG. 5 showing a conventional private power generation facility is a received power set value from a received
図2は第1実施形態における自家用発電設備の始動停止を示すフロー図である。
図6の従来の自家用発電設備の始動停止のフロー図と異なり、自家用発電設備の始動の判定を下記(1)式で行っており、また自家用発電設備の停止の判定を下記(2)式で行っている。(1)式は比較器1の働きを有し、(2)式は比較器2の働きを有している。
受電電力>レベル判定値 …(1)
(レベル判定値−ヒステリシス設定値)>負荷電力 …(2)
FIG. 2 is a flowchart showing start and stop of the private power generation facility in the first embodiment.
Unlike the conventional flow chart for starting and stopping the private power generation facility shown in FIG. 6, the determination of the start of the private power generation facility is performed by the following equation (1), and the determination of the stop of the private power generation facility is performed by the following equation (2). Is going. The expression (1) has the function of the comparator 1, and the expression (2) has the function of the
Received power> level judgment value (1)
(Level judgment value-Hysteresis set value)> Load power (2)
本実施形態では、(1)式のように受電電力がレベル判定値を上回ったときに自家用発電設備を始動する。始動後は、最低発電出力設定器34による最低発電出力設定値を用いて発電電力一定制御で運転し、(2)式のように負荷電力がレベル判定値からヒステリシス設定値分少ない値よりも下回ったときに自家用発電設備を停止する。最低発電出力設定値は、これ以下ではエンジンの寿命の点から発電機を運転させない限界を示しているもので、図5における発電機停止設定器32による発電機停止設定値と同じ値となる。ヒステリシス設定値の意味は、負荷電力が十分に低下した場合に自家用発電設備を停止させることで、停止からすぐに始動となることを防止することにある。
In the present embodiment, the private power generation facility is started when the received power exceeds the level determination value as expressed by equation (1). After start-up, operation is performed with constant generated power control using the minimum generated output set value by the minimum generated
本実施形態によると、発電機は最低発電出力一定で運転しているので、負荷電力の変動分は電力会社の電力で賄うことになり、電力会社の電力の利用分が増加し、従来の方式よりもより効果的(経済的)である。 According to this embodiment, since the generator is operating at a constant minimum power output, the fluctuation of the load power will be covered by the power company's power, the power company's power usage will increase, and the conventional method More effective (economic) than
(第2実施形態)
図3は本発明の第2実施形態の構成図である。
図3に示すように、本実施形態が図1の第1実施形態と異なる構成は、発電コントローラ4に対してレベル判定値設定器36からのレベル判定値と発電出力設定器35からの発電出力設定値を入力し、発電コントローラ4の内部では図4に示す処理ブロックを構築している。また、自家用発電設備からの出力電力量を検出する自家用発電設備電力量計14と電力会社からの受電電力量を検出する受電電力量計15を設けている点である。なお、最低発電出力設定器は設置していない。
(Second Embodiment)
FIG. 3 is a block diagram of the second embodiment of the present invention.
As shown in FIG. 3, this embodiment is different from the first embodiment of FIG. 1 in that the level judgment value from the level judgment
図4は本発明に係る自家用発電設備の始動停止の処理を示す構成図である。
図に示すように、受電電力量計15からの受電電力量(自家用発電設備は運転していないので、このとき受電電力量は負荷電力量と等しい)の信号を受け取り、受電電力量予測手段21で当該30分区間の受電電力量を予測する。予測は例えば、当該30分区間の最初の10分間の受電電力量から当該30分全体の受電電力量を予測する。この場合、3倍して受電電力量予測値とすれば良い。さらに、これを2倍することで30分区間平均の受電電力予測値とみなし、レベル判定値と比較器22にて比較し、受電電力予測値の方が大きい場合に始動指令を出力する。また、受電電力量の予測値からレベル判定値を2で除した値を減じて自家用発電設備側にて賄う電力量dとし、その電力量dを発電出力設定値eで除することで自家用発電設備から需要家電力負荷に電力供給する時間を設定する負荷給電時間設定手段d/eを設ける。タイマー23にて自家用発電設備から電力供給する時間が経過すれば、停止指令を出力する。スイッチ24は、始動指令が出力された後、自家用発電設備から需要家電力負荷8に電力供給する時間をタイマー23にセットするために設けている。すなわち、タイマー23は負荷給電時間設定手段d/eにより設定された時間間隔で自家用発電設備が需要家電力負荷に電力供給すると自家用発電設備に停止指令を出力する。
FIG. 4 is a configuration diagram showing a start / stop process of the private power generation facility according to the present invention.
As shown in the figure, a signal of the received power amount from the received power meter 15 (the private power generation facility is not in operation, so the received power amount is equal to the load power amount at this time) is received, and the received power amount prediction means 21 To predict the amount of received power in the 30-minute section. For example, the prediction is made by predicting the received power amount for the entire 30 minutes from the received power amount for the first 10 minutes of the 30-minute section. In this case, the received power amount prediction value may be multiplied by three. Further, this assumes that the power receiving electric Chikara予 Hakachi of 30 minutes interval average doubling, compared with level
発電出力設定値を自家用発電設備の燃費効率の良い高負荷率となる設定とすることで、自家用発電設備の燃費の改善になる。また、燃費の悪い低負荷率で30分運転する場合よりも短時間の運転で済むため、自家用発電設備のトータル運転時間の短縮にも繋がり、トータル運転時間に基づき行うメンテナンスのタイミングを遅らせることが出来るのでメンテナンスコスト低減にも効果がある。 By setting the power generation output set value to a high load factor with good fuel efficiency of the private power generation facility, the fuel efficiency of the private power generation facility is improved. In addition, since it takes only a short time to drive for 30 minutes at a low load factor with low fuel consumption, it leads to a reduction in the total operation time of the private power generation facility, and the timing of maintenance based on the total operation time can be delayed. This is effective in reducing maintenance costs.
本実施形態は、電力会社との契約電力が規定された30分毎の受電電力量の値を2倍することで得られる30分区間の平均の電力値に基づき決定される点に着目し、30分の受電電力量が契約電力相当分電力量を超過しなければ良いことになるので、自家用発電設備を燃費効率の良い高負荷率で短時間運転することで負荷電力の増加に対応しつつ、自家用発電設備の発電コストを抑制するものである。 This embodiment pays attention to the point determined based on the average power value of the 30-minute section obtained by doubling the value of the received power amount every 30 minutes in which the contract power with the power company is defined, Since the amount of power received for 30 minutes does not exceed the amount equivalent to the amount of contracted power, it would be good to operate the private power generation facility for a short time at a high load factor with good fuel efficiency while responding to the increase in load power. The power generation cost of private power generation facilities is suppressed.
1…発電機、2…原動機、3…調速機、4…発電コントローラ、5…AVR、6,7,9…遮断器、8…需要家電力負荷、10…発電機保護装置、11…系統連系保護装置、12…自家用発電設備電力計、13…受電電力計、14…自家用発電設備電力量計、15…受電電力量計、21…受電電力量予測手段、22…比較器、23…タイマー、24…スイッチ、30…受電電力設定器、31…発電機始動設定器、32…発電機停止設定器、33…ヒステリシス設定器、34…最低発電出力設定器、35…発電出力設定器、36…レベル判定値設定器。 DESCRIPTION OF SYMBOLS 1 ... Generator, 2 ... Prime mover, 3 ... Speed governor, 4 ... Power generation controller, 5 ... AVR, 6, 7, 9 ... Circuit breaker, 8 ... Consumer power load, 10 ... Generator protection device, 11 ... System Interconnection protection device, 12 ... private power generation equipment watt meter, 13 ... received power meter, 14 ... private power generation equipment watt meter, 15 ... received power meter, 21 ... received power amount prediction means, 22 ... comparator, 23 ... Timer ... 24 ... Switch, 30 ... Received power setting device, 31 ... Generator start setting device, 32 ... Generator stop setting device, 33 ... Hysteresis setting device, 34 ... Minimum power generation output setting device, 35 ... Power generation output setting device, 36: Level judgment value setting device.
Claims (1)
需要家が電力会社から受電する受電電力を検出する受電電力計と、
規定された30分間で需要家が電力会社から受電する受電電力量を検出する受電電力量計と、
自家用発電設備からの出力電力を検出する自家用発電設備電力計と、
規定された30分間における自家用発電設備からの出力電力量を検出する自家用発電設備電力量計と、
規定された30分間の最初の5分間程度から10分間程度にて前記受電電力量計で検出される受電電力量から規定された30分間における受電電力量を予測する受電電力量予測手段と、前記受電電力量予測手段により、予測された30分間の受電電力量予測値を2倍することで算出される30分間平均の受電電力予測値とレベル判定設定器によるレベル判定値とを比較し、前記受電電力予測値の方が大きい場合に自家発電設備に始動指令を出力する比較器と、
自家用発電設備の発電出力値を設定する発電出力設定器と、
前記受電電力量予測手段により予測された30分間における受電電力量から前記レベル判定値設定器によるレベル判定値を2で除した値を減じる減算手段と、
前記比較器から始動指令が出力されたとき、前記減算手段による減算結果を後続する手段に出力するスイッチと、
前記スイッチを介して得られた前記減算手段による減算結果を前記発電出力設定器による発電出力値で除することで自家用発電設備が前記需要家負荷に電力供給する時間間隔を導出する負荷給電時間設定手段と、
前記負荷給電時間設定手段により設定された時間間隔で自家用発電設備が前記需要家電力負荷に電力供給すると自家用発電設備に停止指令を出力するタイマーとを具備し、
前記比較器からの出力により自家発電設備を始動し、前記発電出力設定器にて設定された発電出力値を発電電力目標値として運転し、前記タイマーからの出力により自家用発電設備を停止することを特徴とする自家用発電設備の制御装置。 A private power generation facility that supplies power to the consumer power load in conjunction with the commercial power grid of the power company is provided, and when the price of purchased power from the power company is lower than the power price of the private power generation facility, In the control device for private power generation equipment that controls to use power preferentially,
A receiving wattmeter for detecting received power received from a power company by a consumer;
A watt-hour meter that detects the amount of power received by a consumer from a power company in a specified 30 minutes;
A power generation equipment wattmeter for detecting the output power from the private power generation equipment;
A private power generation facility watt-hour meter for detecting the amount of output power from the private power generation facility for a prescribed 30 minutes;
The received power amount predicting means for predicting the received power amount for 30 minutes specified from the received power amount detected by the received power meter in about 10 minutes from the first 5 minutes of the specified 30 minutes; The received power amount prediction means compares the predicted received power amount of 30 minutes calculated by doubling the predicted received power amount of 30 minutes with the level determination value by the level determination setter, A comparator that outputs a start command to the private power generation facility when the received power predicted value is larger;
A power generation output setting device for setting a power generation output value of a private power generation facility;
Subtracting means for subtracting a value obtained by dividing the level judgment value by the level judgment value setting unit by 2 from the received power quantity for 30 minutes predicted by the received power quantity prediction means;
When a start command is output from the comparator, a switch that outputs a subtraction result by the subtracting unit to a subsequent unit;
A load power supply time setting for deriving a time interval at which a private power generation facility supplies power to the customer load by dividing a subtraction result obtained by the subtracting means obtained through the switch by a power generation output value by the power generation output setting device Means,
A timer for outputting a stop command to the private power generation facility when the private power generation facility supplies power to the consumer power load at a time interval set by the load power supply time setting means,
Starting the private power generation facility by the output from the comparator, operating the power generation output value set by the power generation output setting device as the generated power target value, and stopping the private power generation facility by the output from the timer. A control device for private power generation facilities.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2004344043A JP4636404B2 (en) | 2004-11-29 | 2004-11-29 | Control equipment for private power generation facilities |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2004344043A JP4636404B2 (en) | 2004-11-29 | 2004-11-29 | Control equipment for private power generation facilities |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2006158069A JP2006158069A (en) | 2006-06-15 |
| JP4636404B2 true JP4636404B2 (en) | 2011-02-23 |
Family
ID=36635680
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2004344043A Expired - Lifetime JP4636404B2 (en) | 2004-11-29 | 2004-11-29 | Control equipment for private power generation facilities |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4636404B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008086163A (en) * | 2006-09-28 | 2008-04-10 | Osaka Gas Co Ltd | Demand controller |
| CN103259288B (en) * | 2013-05-13 | 2016-06-01 | 国家电网公司 | A kind of conventional power supply is the appraisal procedure of wind-powered peak regulation economy |
| CN105514971B (en) * | 2015-11-02 | 2018-02-02 | 湘潭大学 | A kind of tidal current computing method suitable for various operational mode micro-capacitance sensors |
| JP7041777B1 (en) * | 2021-07-21 | 2022-03-24 | 東京瓦斯株式会社 | Controls, power generation systems, and control programs |
| KR102608280B1 (en) * | 2021-11-26 | 2023-11-30 | 옴니시스템 주식회사 | Systems for detecting and switching power outages in urban building environments |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH05146092A (en) * | 1991-09-24 | 1993-06-11 | Fuji Electric Co Ltd | Charge control circuit for multiple units standby redundant operation system uninterruptible power supply |
| JPH06284572A (en) * | 1993-03-31 | 1994-10-07 | Nisshin Steel Co Ltd | Controlling method for power demand |
| JP3325863B2 (en) * | 1999-09-20 | 2002-09-17 | 大洋電機株式会社 | Receiving power control device |
| JP2001197662A (en) * | 1999-10-25 | 2001-07-19 | Soshiodaiya Systems Kk | Power amount calculation device, power amount calculation method, and power amount information processing system |
| JP3773929B2 (en) * | 2002-08-29 | 2006-05-10 | 寺崎電気産業株式会社 | Demand control device |
-
2004
- 2004-11-29 JP JP2004344043A patent/JP4636404B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2006158069A (en) | 2006-06-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7388364B2 (en) | Device for covering the peak load | |
| JP6216377B2 (en) | Power adjustment device, power adjustment method, power adjustment system, power storage device, server, program | |
| JP5738212B2 (en) | Power storage type power generation system | |
| JP4628386B2 (en) | Distributed power supply operating status detection device, watt-hour meter, and distribution system control device | |
| JP4606389B2 (en) | Distributed generator control system | |
| JP3726265B2 (en) | Distributed home power supply device using DC interconnection and control method thereof | |
| JP2015073433A (en) | Load control device | |
| JP6414870B1 (en) | Reverse power flow prevention type self-consumption renewable energy storage control system | |
| WO2014167928A1 (en) | Storage battery charge/discharge control device and storage battery charge/discharge control method | |
| JP2003244840A (en) | Load leveling device | |
| JP3801910B2 (en) | Fuel cell system control method | |
| JP3775134B2 (en) | Private power generation facilities | |
| JP4636404B2 (en) | Control equipment for private power generation facilities | |
| AU2021206016B2 (en) | Method and system for controlling an electrical installation | |
| JPWO2004100337A1 (en) | Power supply device including grid interconnection inverter | |
| KR100665540B1 (en) | 3-Phase I / O All IGBIS System | |
| JP6187920B2 (en) | Power supply control device and power distribution system | |
| KR20170073916A (en) | Controlling method for ESS | |
| JPWO2020080006A1 (en) | Energy management system, independent system, and how to operate the independent system | |
| JP2007244155A (en) | Micro hydroelectric generator | |
| JPH1080061A (en) | Generated output controller for nonutility power generation facility | |
| JP2015050783A (en) | Power feeding system and power feeding method | |
| JP4093481B2 (en) | Self-generator control method and control device | |
| KR102543115B1 (en) | Diesel generator power control apparatus and method for controlling generation power based on power consumption and predicted power use of diesel generator | |
| JP2007236193A (en) | Power supply device including grid interconnection inverter |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20071128 |
|
| RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20071128 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090713 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090818 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20091016 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100817 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20101007 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20101026 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20101112 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131203 Year of fee payment: 3 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 4636404 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| EXPY | Cancellation because of completion of term |