Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP4806370B2 - Vertical shaft construction method - Google Patents
[go: Go Back, main page]

JP4806370B2 - Vertical shaft construction method - Google Patents

Vertical shaft construction method Download PDF

Info

Publication number
JP4806370B2
JP4806370B2 JP2007099961A JP2007099961A JP4806370B2 JP 4806370 B2 JP4806370 B2 JP 4806370B2 JP 2007099961 A JP2007099961 A JP 2007099961A JP 2007099961 A JP2007099961 A JP 2007099961A JP 4806370 B2 JP4806370 B2 JP 4806370B2
Authority
JP
Japan
Prior art keywords
pile material
pile
steel wire
support member
corner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2007099961A
Other languages
Japanese (ja)
Other versions
JP2008255688A (en
Inventor
常松 向谷
敏嗣 堀崎
利博 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tobishima Corp
Original Assignee
Tobishima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tobishima Corp filed Critical Tobishima Corp
Priority to JP2007099961A priority Critical patent/JP4806370B2/en
Publication of JP2008255688A publication Critical patent/JP2008255688A/en
Application granted granted Critical
Publication of JP4806370B2 publication Critical patent/JP4806370B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Description

本発明は、地盤を掘削して縦方向へ延びる掘削坑を形成し、掘削坑に養生充填材を充填するとともに杭材を建て込んで立坑を構築する立坑構築方法に関する。   The present invention relates to a shaft construction method for constructing a vertical shaft by excavating the ground to form an excavation shaft extending in the vertical direction, filling the excavation shaft with a curing filler, and building a pile material.

地盤を掘削して縦方向へ延びる掘削坑を形成し、掘削坑にソイルモルタルを充填し、下部杭材を掘削坑の下方に建て込んだ後、上部杭材を掘削坑の上方に建て込んで立坑を構築する立坑構築方法がある(特許文献1参照)。この立坑構築方法の詳細を説明すると、以下のとおりである。下部杭材の頂部を支持部材で支持し、支持部材とともに下部杭材を掘削坑の下方へ向かって建て込む。下部杭材を掘削坑に建て込んだ後、支持部材を下部杭材から外し、支持部材を掘削坑から引き抜く。次に、上部杭材を掘削坑に建て込み、下部杭材の頂部と上部杭材の底部とを縦方向へ所定寸法離間させた状態で、上部杭材の頂部を地上において固定し、下部杭材の頂部と上部杭材の底部との離間状態を維持する。ソイルモルタルを所定期間養生固結させた後、上部杭材の頂部の固定を解除する。この立坑構築方法は、下部杭材の頂部と上部杭材の底部との間に杭材が存在しないソイルモルタルのみの領域を作ることができ、下部杭材と上部杭材との間にシールド機がそのまま通過可能な領域を形成することができる。
特開平5−187184号公報
After excavating the ground to form an excavation pit that extends in the vertical direction, the excavation pit is filled with soil mortar, the lower pile material is built below the excavation mine, and then the upper pile material is installed above the excavation pit There is a shaft construction method for constructing a shaft (see Patent Document 1). The details of this shaft construction method will be described as follows. The top of the lower pile material is supported by a support member, and the lower pile material is built downward along the excavation mine together with the support member. After the lower pile material is built in the excavation mine, the support member is removed from the lower pile material, and the support member is pulled out from the excavation mine. Next, the upper pile material is built in the excavation pit, the top of the lower pile material and the bottom of the upper pile material are spaced apart by a predetermined dimension in the vertical direction, and the top of the upper pile material is fixed on the ground. Maintain a separated state between the top of the material and the bottom of the upper pile. After the soil mortar is cured and cured for a predetermined period, the top of the upper pile material is released. This shaft construction method can create an area of only soil mortar where there is no pile material between the top of the lower pile material and the bottom of the upper pile material, and a shield machine between the lower pile material and the upper pile material Can be formed as it is.
JP-A-5-187184

前記特許文献1に開示の立坑構築方法は、掘削坑の下方に建て込まれた下部杭材を建て込み位置において保持固定する手段がなく、掘削坑に充填されたソイルモルタルが養生するまでの間に下部杭材がモルタル中を徐々に沈降するから、下部杭材を掘削坑の建て込み位置に設置することができないばかりか、下部杭材の頂部と上部杭材の底部との離間寸法が一定せず、シールド機が通過可能な一定形状の領域を作ることができない場合がある。また、この立坑構築方法は、下部杭材の姿勢を安定させることができず、掘削坑に充填されたソイルモルタルが養生するまでの間に下部杭材が掘削坑において不用意にずれ動き、掘削坑に下部芯材を直立させた状態で設置することができない場合がある。この立坑構築方法は、上部杭材とその下方に連なる下部杭材との位置決めが難しく、上部杭材の直下に下部杭材を位置させることができない場合がある。   In the shaft construction method disclosed in Patent Document 1, there is no means for holding and fixing the lower pile material built below the excavation mine at the erection position until the soil mortar filled in the excavation mine is cured. Since the lower pile material gradually settles in the mortar, the lower pile material cannot be installed at the digging pit position, and the distance between the top of the lower pile material and the bottom of the upper pile material is constant. Without a certain shape of the area through which the shield machine can pass. Also, this vertical shaft construction method cannot stabilize the posture of the lower pile material, and the lower pile material moves inadvertently in the excavation mine until the soil mortar filled in the excavation mine is cured, and excavation It may not be possible to install the lower core material upright in the mine. In this shaft construction method, it is difficult to position the upper pile material and the lower pile material connected below the upper pile material, and the lower pile material may not be positioned directly below the upper pile material.

本発明の目的は、杭材を掘削坑の建て込み位置に略直立させた姿勢で設置することができ、杭材の間にシールド機が通過可能な一定形状の領域を作ることができる立坑構築方法を提供することにある。   The object of the present invention is to construct a vertical shaft that can be installed in a posture in which the pile material is substantially upright at the position where the excavation mine is built, and that allows a shielded machine to pass between the pile materials. It is to provide a method.

前記課題を解決するための本発明の前提は、地盤を掘削して縦方向へ延びる掘削坑を形成し、掘削坑に養生充填材を充填するとともに縦方向に杭材を建て込んで立坑を構築する立坑構築方法である。   The premise of the present invention to solve the above problems is that the excavation pit is formed by excavating the ground and filling the excavation mine with a curing filler, and a vertical pile is built in the vertical direction. It is a vertical shaft construction method.

前記前提における本発明の特徴は、杭材が、互いに当接する対向端部を有して軸方向へ並ぶ第1杭材および第2杭材と、軸方向へ延びていて第1杭材の非対向端部からそれら杭材の対向端部を越えて第2杭材の所定の位置に達する第1鋼線と、軸方向へ延びていて第1杭材の非対向端部からそれら杭材の対向端部を越えて第2杭材の所定の位置に達する第2鋼線と、第1杭材に取り付けられて第1鋼線を摺動可能に支持する第1支持部材と、第2杭材に取り付けられて第1鋼線を支持可能かつ第1鋼線を切り離し可能な第2支持部材と、第2杭材に取り付けられて第2鋼線を支持可能かつ第2鋼線を切り離し可能な第3支持部材とから形成され、第1鋼線を第1支持部材と第2支持部材との間において緊張させた状態で、掘削坑に第1および第2杭材を建て込む杭材建て込み工程と、第2鋼線を地上において支持しつつ第1鋼線を第2支持部材から切り離し、第1鋼線を掘削坑から引き抜くとともに第1杭材を縦方向上方へ引き上げて第1杭材と第2杭材との対向端部を縦方向へ所定寸法離間させる第1杭材引き上げ工程と、充填材を養生させた後、第2鋼線を第3支持部材から切り離して第2鋼線を掘削坑から引き抜く第2鋼線引き抜き工程とを有することにある。   The feature of the present invention based on the above premise is that the pile material has first and second pile materials that are opposed to each other and are arranged in the axial direction, and extends in the axial direction. A first steel wire that reaches a predetermined position of the second pile material from the opposed end portion beyond the opposed end portion of the pile material, and extends in the axial direction from the non-opposed end portion of the first pile material. A second steel wire that reaches a predetermined position of the second pile material across the opposite end, a first support member that is attached to the first pile material and supports the first steel wire slidably, and a second pile A second support member that can be attached to the material and can support the first steel wire and can be separated from the first steel wire, and a second support member that can be attached to the second pile material and can support the second steel wire and can be separated from the second steel wire The first steel wire in the state where the first steel wire is tensioned between the first support member and the second support member. 2 Pile material erection process to build the pile material, and while supporting the second steel wire on the ground, the first steel wire is separated from the second support member, the first steel wire is pulled out from the excavation mine and the first pile material is The first pile material pulling step for pulling upward in the vertical direction and separating the opposing ends of the first pile material and the second pile material in the vertical direction by a predetermined dimension, and curing the filler, 3 to have a second steel wire drawing step of separating the second steel wire from the excavation mine by separating from the support member.

本発明の一例としては、第1および第2杭材が、互いに並行離間して軸方向へ延びる第1および第2対向壁と、それら対向壁の間に位置して軸方向へ延びる連結壁とを有するH形綱であり、第1対向壁と連結壁との交点に形成された第1角部および第2角部と、第2対向壁と連結壁との交点に形成されて第1角部に対向する第3角部および第2角部に対向する第4角部とを備え、第1鋼線が第1角部と第4角部とに配置され、第2鋼線が第2角部と第3角部とに配置されている。   As an example of the present invention, the first and second pile members are first and second opposing walls that are spaced apart from each other and extend in the axial direction, and a connecting wall that is positioned between the opposing walls and extends in the axial direction. H-shaped rope having a first corner and a second corner formed at the intersection of the first opposing wall and the connecting wall, and a first corner formed at the intersection of the second opposing wall and the connecting wall. A third corner portion that opposes the second corner portion and a fourth corner portion that opposes the second corner portion, wherein the first steel wire is disposed at the first corner portion and the fourth corner portion, and the second steel wire is the second corner portion. It arrange | positions at the corner | angular part and the 3rd corner | angular part.

本発明の他の一例としては、第1杭材が互いに当接する対向端部を有して軸方向へ並ぶ主杭材と仮設杭材とから形成され、第1杭材引き上げ工程では、仮設杭材の長さ寸法が第1および第2杭材における対向端部どうしの離間寸法に一致するように、仮設杭材を地上に引き上げた後、主杭材から仮設杭材を取り外す。   As another example of the present invention, the first pile material is formed from a main pile material and a temporary pile material that have opposing end portions that contact each other and are arranged in the axial direction. The temporary pile material is removed from the main pile material after the temporary pile material is pulled up to the ground so that the length dimension of the material matches the distance between the opposing end portions of the first and second pile materials.

本発明の他の一例としては、杭材が第1杭材と第2杭材との対向端部に跨って軸方向へ延びる支持板を含み、支持板は、第1杭材と第2杭材とのいずれか一方に取り付けられてそれら杭材をその軸方向から支持している。   As another example of the present invention, the pile material includes a support plate that extends in the axial direction across the opposite end portions of the first pile material and the second pile material, and the support plate includes the first pile material and the second pile. It is attached to either one of the materials and supports these pile materials from the axial direction.

本発明の他の一例として、第2支持部材と第3支持部材とには、高周波誘導加熱コイルが設置され、高周波誘導加熱コイルが、第1および第2鋼線に渦電流を発生させてそれら鋼線自体を発熱破断させることで、それら鋼線を第2および第3支持部材から切り離す。   As another example of the present invention, a high frequency induction heating coil is installed in the second support member and the third support member, and the high frequency induction heating coil generates eddy currents in the first and second steel wires to generate them. The steel wires are separated from the second and third support members by causing the steel wires themselves to break by exothermic heat.

本発明にかかる立坑構築方法によれば、充填材が養生するまでの間、掘削坑の下方に位置する第2杭材が第2鋼線によって支持されるから、第2杭材が充填材中を沈降することはなく、第2杭材を掘削坑の建て込み位置に確実に設置することができる。また、第1杭材の対向端部と第2杭材の対向端部との離間寸法を一定に保持することができ、第1杭材と第2杭材との間にシールド機が通過可能な一定形状の領域を作ることができる。この立坑構築方法は、第2杭材が第2鋼線によって支持されるから、第2杭材の姿勢を安定させることができ、第2杭材が掘削坑において不用意にずれ動くことはなく、第2杭材を掘削坑の建て込み位置に略直立させた姿勢で設置することができる。この立坑構築方法は、第1杭材とそれの下方の連なる第2杭材との位置決めが容易であり、第1杭材の直下に第2杭材を確実に位置させることができる。   According to the shaft construction method according to the present invention, since the second pile material located below the excavation mine is supported by the second steel wire until the filler is cured, the second pile material is in the filler. The second pile material can be reliably installed at the position where the excavation mine is built. Moreover, the separation | spacing dimension of the opposing edge part of a 1st pile material and the opposing edge part of a 2nd pile material can be kept constant, and a shield machine can pass between a 1st pile material and a 2nd pile material. An area with a uniform shape can be created. In this shaft construction method, since the second pile material is supported by the second steel wire, the posture of the second pile material can be stabilized, and the second pile material does not move inadvertently in the excavation mine. The second pile material can be installed in a posture in which the second pile material is substantially upright at the position where the excavation mine is built. In this shaft construction method, positioning of the first pile material and the second pile material continuous below the first pile material is easy, and the second pile material can be surely positioned directly below the first pile material.

第1および第2杭材がH形綱であり、第1鋼線がH形綱の第1角部と第4角部とに配置され、第2鋼線がH形綱の第2角部と第3角部とに配置された立坑構築方法は、一対の第1鋼線がH形綱の対角線に位置するとともに、一対の第2鋼線がH形綱の対角線に位置するから、第1鋼線や第2鋼線を掘削坑から引き抜くときの力が第1杭材や第2杭材に偏って作用することはなく、掘削坑に建て込まれた第1および第2杭材の鋼線引き抜き時におけるずれ動きを防ぐことができる。この立坑構築方法は、第1および第2杭材を掘削坑の建て込み位置に略直立させた姿勢で確実に設置することができ、第1杭材の直下に第2杭材を確実に位置させることができる。   The first and second pile members are H-shaped ropes, the first steel wire is disposed at the first corner and the fourth corner of the H-shaped rope, and the second steel wire is the second corner of the H-shaped rope. Since the pair of first steel wires are located on the diagonal of the H-shaped rope and the pair of second steel wires are located on the diagonal of the H-shaped rope, The force when pulling out the 1 steel wire or the 2nd steel wire from the excavation mine does not act on the first pile material or the second pile material, and the first and second pile materials built in the excavation mine It is possible to prevent the displacement movement at the time of drawing the steel wire. In this shaft construction method, the first and second pile members can be reliably installed in a posture in which the first and second pile members are substantially upright at the position where the excavation shaft is built, and the second pile member is surely positioned directly below the first pile member. Can be made.

第1杭材が主杭材と仮設杭材とから形成され、仮設杭材の長さ寸法が第1および第2杭材における対向端部どうしの離間寸法に一致するように、仮設杭材を地上に引き上げた後、主杭材から仮設杭材を取り外す立坑構築方法は、仮設杭材を地上に引き上げることで第1および第2杭材における対向端部どうしの離間寸法が決まり、第1杭材の引き上げ高さを調節しつつ第1および第2杭材における対向端部どうしの離間寸法を調節する必要はなく、仮設杭材を利用することで第1および第2杭材における対向端部どうしの離間寸法を正確に調節することができる。この立坑構築方法は、仮設杭材の長さ寸法を変えることで、第1および第2杭材における対向端部どうしの離間寸法を容易に変えることができ、第1杭材と第2杭材との間に杭材が存在しない一定形状の領域を確実に作ることができる。   The temporary pile material is formed so that the first pile material is formed from the main pile material and the temporary pile material, and the length dimension of the temporary pile material matches the separation dimension between the opposed end portions in the first and second pile materials. The shaft construction method to remove the temporary pile material from the main pile material after raising it to the ground is determined by raising the temporary pile material to the ground to determine the distance between the opposing ends of the first and second pile materials. It is not necessary to adjust the distance between the opposing ends of the first and second pile materials while adjusting the lifting height of the material, and the opposing ends of the first and second pile materials by using a temporary pile material The distance between the two can be adjusted accurately. This shaft construction method can change easily the separation dimension of the opposing edge parts in the 1st and 2nd pile materials by changing the length dimension of temporary pile materials, and the 1st pile material and the 2nd pile material A region having a fixed shape in which no pile material is present can be surely formed.

支持板が第1および第2杭材のいずれか一方に取り付けられてそれら杭材をその軸方向から支持する立坑構築方法は、第1および第2杭材の連結や姿勢が支持板によって保持されるから、それら杭材を掘削坑に建て込むときにそれら杭材の連結が不用意に解除されてしまうことはなく、それら杭材を掘削坑の建て込み位置に略直立させた姿勢で確実に設置することができる。   In the shaft construction method in which the support plate is attached to one of the first and second pile members and supports the pile members from the axial direction, the connection and posture of the first and second pile members are held by the support plate. Therefore, when the pile materials are built in the excavation mine, the connection of the pile materials is not inadvertently released, and the pile materials are surely kept in an upright position at the construction position of the excavation mine. Can be installed.

高周波誘導加熱コイルが第1および第2鋼線に渦電流を発生させてそれら鋼線自体を発熱破断させる立坑構築方法は、渦電流によって第1および第2鋼線自体が発熱するから、外部熱源からそれら鋼線に熱を加える場合と比較し、それら鋼線を確実に破断させることができ、それら鋼線の第2および第3支持部材からの切り離し不能を防ぐことができる。   The shaft construction method in which the high-frequency induction heating coil generates eddy currents in the first and second steel wires and heats and breaks the steel wires themselves generates heat from the first and second steel wires by the eddy current. Compared with the case where heat is applied to these steel wires, the steel wires can be reliably broken, and the steel wires can be prevented from being separated from the second and third support members.

添付の図面を参照し、本発明に係る立坑構築方法の詳細を説明すると、以下のとおりである。図1は、杭材10Aの一例を示す図であり、図2は、図1のA−A線端面図である。図3は、図1のB−B線端面図であり、図4は、図1のC−C線端面図である。図5は、第2および第3支持部材17,18の一例を示す図である。図1では、軸方向を矢印L1で示す。この立坑構築方法は、掘削機を利用して地盤38を掘削し、地表39から地中40に向かって縦方向へ延びる掘削坑41を形成するとともに、その掘削坑41にソイルモルタル42(養生充填材)を充填し、掘削坑41に杭材10Aを建て込んで立坑仮壁43を構築する(図6参照)。立坑構築方法に使用する杭材10Aは、第1杭材11および第2杭材12と、それら杭材11,12を支持する一対の支持板13と、第1鋼線14および第2鋼線15と、それら鋼線14,15を支持する第1〜第3支持部材16,17,18とから形成されている。   The details of the shaft construction method according to the present invention will be described below with reference to the accompanying drawings. FIG. 1 is a diagram illustrating an example of a pile material 10A, and FIG. 2 is an end view taken along line AA in FIG. 3 is an end view taken along the line BB of FIG. 1, and FIG. 4 is an end view taken along the line CC of FIG. FIG. 5 is a diagram illustrating an example of the second and third support members 17 and 18. In FIG. 1, the axial direction is indicated by an arrow L1. In this shaft construction method, the ground 38 is excavated by using an excavator to form an excavation pit 41 extending in the vertical direction from the surface 39 to the underground 40, and a soil mortar 42 (curing filling) is provided in the excavation mine 41. Material) and the pile material 10A is built in the excavation pit 41 to construct the vertical shaft 43 (see FIG. 6). The pile material 10A used for the shaft construction method includes a first pile material 11 and a second pile material 12, a pair of support plates 13 that support the pile materials 11 and 12, a first steel wire 14 and a second steel wire. 15 and first to third support members 16, 17, 18 that support the steel wires 14, 15.

第1杭材11と第2杭材12とは、それらの一方の端部19,20(対向端部)どうしが互いに当接した状態で軸方向へ直状に並んでいる。それら杭材11,12は、軸方向へ長いH形綱であり、互いに並行離間して軸方向へ延びる第1および第2対向壁21,22と、それら対向壁21,22の間に位置して軸方向へ延びる連結壁23とを有する。それら杭材11,12は、第1対向壁21と連結壁23との交差箇所(交点)に形成された略直角の第1角部24と、第1対向壁21と連結壁23との交差箇所(交点)に形成されて第1角部24の反対側に位置する略直角の第2角部25と、第2対向壁22と連結壁23との交差箇所(交点)に形成されて第1角部24に対向する略直角の第3角部26と、第2対向壁22と連結壁23との交差箇所(交点)に形成されて第2角部25に対向する略直角の第4角部27とを有する。   The first pile material 11 and the second pile material 12 are arranged in a straight line in the axial direction in a state where their one end portions 19 and 20 (opposing end portions) are in contact with each other. The pile members 11 and 12 are H-shaped ropes that are long in the axial direction, and are positioned between the first and second opposing walls 21 and 22 that are spaced apart from each other and extend in the axial direction, and the opposing walls 21 and 22. And a connecting wall 23 extending in the axial direction. The pile members 11, 12 are formed by intersecting the first opposing wall 21 and the connecting wall 23 with a substantially right-angled first corner 24 formed at the intersection (intersection) between the first opposing wall 21 and the connecting wall 23. Formed at a point (intersection) and formed at a crossing point (intersection) between the second corner 25 having a substantially right angle located on the opposite side of the first corner 24 and the second opposing wall 22 and the connecting wall 23. A substantially right-angled fourth corner formed at the intersection (intersection) of the substantially right-angled third corner portion 26 facing the corner portion 24 and the second facing wall 22 and the connecting wall 23 and facing the second corner portion 25. And corners 27.

それら支持板13には、軸方向へ長い矩形の綱板が使用されている。支持板13は、第1および第2杭材11,12の端部19,20に跨って軸方向へ延びている。支持板13は、それら杭材11,12の端部19,20において対向壁21,22に当接し、第1杭材11の対向壁21,22に固定手段(図示せず)を介して固定されている。支持板13は、それら杭材11,12をその軸方向から支持し、それら杭材11,12のずれ動きを防いでそれら杭材11,12どうしの連結を維持する。なお、支持板13は、第1杭材11に固定されずに、第2杭材12の対向壁21,22に固定されていてもよい。   The support plates 13 are rectangular steel plates that are long in the axial direction. The support plate 13 extends in the axial direction across the end portions 19 and 20 of the first and second pile members 11 and 12. The support plate 13 abuts against the opposing walls 21 and 22 at the end portions 19 and 20 of the pile members 11 and 12, and is fixed to the opposing walls 21 and 22 of the first pile member 11 via fixing means (not shown). Has been. The support plate 13 supports the pile members 11 and 12 from the axial direction, prevents the displacement of the pile members 11 and 12, and maintains the connection between the pile members 11 and 12. The support plate 13 may be fixed to the opposing walls 21 and 22 of the second pile material 12 without being fixed to the first pile material 11.

第1鋼線14および第2鋼線15には、PC綱撚線が使用されている。第1鋼線14は、第1および第2杭材11,12の第1角部24と第4角部27とに配置され、それら杭材11,12に沿って軸方向へ延びている。第1鋼線14は、一対のそれらがH形綱の対角線に位置している。第1鋼線14は、第1杭材11の他方の端部28(非対向端部)からそれら杭材11,12の端部19,20を越えて第2杭材12の端部20の内側(杭材12の中央部)に達している。第1鋼線14は、第1杭材11の端部28の側に位置する端部分29が杭材11の端部28から軸方向外方に延出している。第2鋼線15は、第1および第2杭材11,12の第2角部25と第3角部26とに配置され、それら杭材11,12に沿って軸方向へ延びている。第2鋼線15は、一対のそれらがH形綱の対角線に位置している。第2鋼線15は、第1杭材11の他方の端部28(非対向端部)からそれら杭材11,12の端部19,20を越えて第2杭材12の端部20の内側(杭材12の中央部)に達している。第2鋼線15は、第1杭材11の端部28の側に位置する端部分30が杭材11の端部28から軸方向外方に延出している。   PC steel twisted wires are used for the first steel wire 14 and the second steel wire 15. The first steel wire 14 is disposed at the first corner portion 24 and the fourth corner portion 27 of the first and second pile members 11 and 12, and extends in the axial direction along the pile members 11 and 12. As for the 1st steel wire 14, a pair of them is located in the diagonal of an H-shaped rope. The first steel wire 14 extends from the other end portion 28 (non-opposing end portion) of the first pile member 11 to the end portions 19 and 20 of the pile members 11 and 12 and the end portion 20 of the second pile member 12. It has reached the inside (the center of the pile material 12). In the first steel wire 14, an end portion 29 located on the end portion 28 side of the first pile material 11 extends axially outward from the end portion 28 of the pile material 11. The second steel wire 15 is disposed at the second corner portion 25 and the third corner portion 26 of the first and second pile members 11 and 12, and extends in the axial direction along the pile members 11 and 12. As for the 2nd steel wire 15, a pair of them is located in the diagonal of an H-shaped rope. The second steel wire 15 extends from the other end portion 28 (non-opposing end portion) of the first pile member 11 to the end portions 19 and 20 of the pile members 11 and 12 and the end portion 20 of the second pile member 12. It has reached the inside (the center of the pile material 12). In the second steel wire 15, an end portion 30 located on the end portion 28 side of the first pile material 11 extends outward from the end portion 28 of the pile material 11 in the axial direction.

第1支持部材16は、第1杭材11の端部19の内側に配置され、杭材11の連結壁23における第1角部24と第4角部27とに固定手段(図示せず)を介して固定されている(図3参照)。第1支持部材16は、第1鋼線14をその周方向から圧着し、鋼線14を支持している。ただし、鋼線14は支持部材16において摺動可能かつ支持部材16から抜脱可能である。ゆえに、第1鋼線14の端部29を軸方向外方へ強く引っ張ると、鋼線14が第1支持部材16を摺動し、鋼線14が支持部材16から徐々に引き抜かれる。第2支持部材17は、第2杭材12の端部20の内側(杭材12の中央部)に配置され、杭材12の連結壁23における第1角部24と第4角部27とに固定手段(図示せず)を介して固定されている(図2参照)。第2支持部材17は、第1鋼線14を固定支持する固定部31と、鋼線14を支持部材17から切り離す高周波誘導加熱コイル32とから形成されている。固定部31では、第1鋼線14が抜脱不能に支持されている。第1鋼線14の第1支持部材16と第2支持部材17との間の部材間部分33は、軸方向外方へ引っ張られた状態でそれら支持部材16,17に支持されている。ゆえに、部材間部分33が緊張した状態にあり、第1および第2杭材11,12どうしの連結が鋼線14によって維持されている。   The first support member 16 is disposed inside the end portion 19 of the first pile material 11, and is fixed to the first corner portion 24 and the fourth corner portion 27 of the connection wall 23 of the pile material 11 (not shown). (See FIG. 3). The first support member 16 presses the first steel wire 14 from the circumferential direction and supports the steel wire 14. However, the steel wire 14 can slide on the support member 16 and can be removed from the support member 16. Therefore, when the end portion 29 of the first steel wire 14 is pulled strongly outward in the axial direction, the steel wire 14 slides on the first support member 16, and the steel wire 14 is gradually pulled out from the support member 16. The second support member 17 is disposed inside the end portion 20 of the second pile member 12 (the center portion of the pile member 12), and the first corner portion 24 and the fourth corner portion 27 in the connection wall 23 of the pile member 12 are It is fixed via a fixing means (not shown) (see FIG. 2). The second support member 17 is formed of a fixing portion 31 that fixes and supports the first steel wire 14 and a high-frequency induction heating coil 32 that separates the steel wire 14 from the support member 17. In the fixing portion 31, the first steel wire 14 is supported so that it cannot be removed. The inter-member portion 33 between the first support member 16 and the second support member 17 of the first steel wire 14 is supported by the support members 16 and 17 while being pulled outward in the axial direction. Therefore, the inter-member portion 33 is in a tensioned state, and the connection between the first and second pile members 11 and 12 is maintained by the steel wire 14.

第3支持部材18は、第2杭材12の端部20の内側(杭材12の中央部)に配置され、杭材12の連結壁23における第2角部25と第3角部26とに固定手段(図示せず)を介して固定されている(図2参照)。第3支持部材18は、第2鋼線15を固定支持する固定部34と、鋼線15を支持部材18から切り離す高周波誘導加熱コイル35とから形成されている。固定部34では、第2鋼線15が抜脱不能に支持されている。第2および第3支持部材17,18の高周波誘導加熱コイル32,35には、配線57を介して高周波発生装置(図示せず)が接続されている。高周波誘導加熱コイル32,35に高周波発生装置から高周波電圧を印加すると、コイル32,35に高周波電流が流れ、高周波電流と鎖交する方向へ磁束が発生する。発生した磁束が第1および第2鋼線14,15に作用すると、それら鋼線14,15に渦電流が発生し、それによってそれら鋼線14,15自体が発熱(ジュール熱)する。発熱した部位36,37では、鋼線14,15の強度が著しく低下する。鋼線14,15に張力をかけた状態で、それら鋼線14,15の部位36,37が高温に発熱すると、部位36,37に作用する張力によって鋼線14,15が部位36,37おいて破断し、第2および第3支持部材17,18から切り離される。   The third support member 18 is disposed inside the end portion 20 of the second pile material 12 (the center portion of the pile material 12), and the second corner portion 25 and the third corner portion 26 in the connection wall 23 of the pile material 12. It is fixed via a fixing means (not shown) (see FIG. 2). The third support member 18 is formed of a fixing portion 34 that fixes and supports the second steel wire 15 and a high-frequency induction heating coil 35 that separates the steel wire 15 from the support member 18. In the fixing portion 34, the second steel wire 15 is supported so as not to be removable. A high frequency generator (not shown) is connected to the high frequency induction heating coils 32, 35 of the second and third support members 17, 18 via a wiring 57. When a high frequency voltage is applied to the high frequency induction heating coils 32 and 35 from the high frequency generator, a high frequency current flows through the coils 32 and 35, and a magnetic flux is generated in a direction interlinking with the high frequency current. When the generated magnetic flux acts on the first and second steel wires 14 and 15, eddy currents are generated in the steel wires 14 and 15, and the steel wires 14 and 15 themselves generate heat (Joule heat). In the heated parts 36 and 37, the strength of the steel wires 14 and 15 is significantly reduced. When the portions 36 and 37 of the steel wires 14 and 15 are heated to a high temperature in a state where tension is applied to the steel wires 14 and 15, the steel wires 14 and 15 are moved to the portions 36 and 37 due to the tension acting on the portions 36 and 37. And is separated from the second and third support members 17 and 18.

図6は、杭材10Aを掘削坑41に建て込む杭材建て込み工程の説明図であり、図7は、第1杭材11を引き上げる第1引き上げ工程の説明図である。図8は、図7のD−D線端面図である。図6では、縦方向を矢印L2で示す。杭材10Aを掘削坑38に建て込む前の準備として、掘削機(図示せず)を使用して地盤38を掘削し、縦方向へ延びる掘削坑41を作り、その掘削坑41にソイルモルタル42(養生充填材)を充填する。あわせて、図1の杭材10Aを用意する。それらの準備が完了した後、杭材10Aを掘削坑41に建て込む(杭材建て込み工程)。クレーン44の玉掛け45で杭材10Aの端部(第1杭材11の端部28)を支持し、クレーン44によって杭材10Aを垂直に立てて空中に吊り上げ、杭材10Aを掘削坑41の上部に移動させる。   FIG. 6 is an explanatory diagram of a pile material building process for building the pile material 10 </ b> A into the excavation mine 41, and FIG. 7 is an explanatory diagram of a first pulling process for pulling up the first pile material 11. 8 is an end view taken along the line DD of FIG. In FIG. 6, the vertical direction is indicated by an arrow L2. As a preparation before the pile material 10A is built in the excavation pit 38, an excavator (not shown) is used to excavate the ground 38 to create a vertical excavation pit 41. Fill with (curing filler). In addition, the pile material 10A of FIG. 1 is prepared. After those preparations are completed, the pile material 10A is built in the excavation mine 41 (pile material building step). The end of the pile material 10A (the end portion 28 of the first pile material 11) is supported by the sling 45 of the crane 44, and the pile material 10A is vertically raised by the crane 44 and lifted in the air. Move to the top.

クレーン44に保持された杭材10Aでは、第1杭材11が上方に位置し、杭材11の下方に第2杭材12が位置する。杭材10Aを掘削坑41の上部に位置させた後、クレーン44によって杭材10Aをその端部(第2杭材12の端部46)から掘削坑41に徐々に建て込み、図6に示すように、杭材10Aの端部(第1杭材11の端部28)を地上に露出させた状態で杭材10Aの大部分を掘削坑41(ソイルモルタル42)に埋設させる。杭材建て込み工程では、第1鋼線14の第1および第2支持部材16,17の間に延びる部材間部分33が緊張状態にあり、さらに、支持板13が第1および第2杭材11,12の端部19,20を支持しているから、それら杭材11,12どうしの不用意なずれ動きがなく、それら杭材11,12の連結が維持される。   In the pile material 10 </ b> A held by the crane 44, the first pile material 11 is located above, and the second pile material 12 is located below the pile material 11. After the pile material 10A is positioned at the upper portion of the excavation mine 41, the pile material 10A is gradually built into the excavation mine 41 from its end portion (end portion 46 of the second pile material 12) by the crane 44, as shown in FIG. In this way, most of the pile material 10A is embedded in the excavation mine 41 (soil mortar 42) with the end portion of the pile material 10A (end portion 28 of the first pile material 11) exposed to the ground. In the pile material building step, the inter-member portion 33 extending between the first and second support members 16 and 17 of the first steel wire 14 is in a tension state, and the support plate 13 is the first and second pile materials. Since the end portions 19 and 20 of the 11 and 12 are supported, there is no inadvertent displacement between the pile materials 11 and 12, and the connection of the pile materials 11 and 12 is maintained.

杭材建て込み工程が終了すると、次に、第1杭材11を縦方向上方へ所定高さまで引き上げる(第1杭材引き上げ工程)。第1杭材引き上げ工程では、第2鋼線15の地上に露出した端部分30を地上において固定手段47を介して固定した状態で、第2支持部材17の高周波誘導加熱コイル32に高周波発生装置から高周波電圧を印加する。コイル32に高周波電圧を印加すると、コイル32に発生した磁束により、第1鋼線14の部材間部分33のうちのコイル32に対向する部位36に渦電流が発生し、部位36が発熱して高温になる。第1鋼線14では、緊張状態にある部材間部分33のうちのコイル32に対向する部位36が高温に発熱するとともに、部位36に作用する張力によって部位36が破断し、第1鋼線14が第2支持部材17から切り離される。第1鋼線14が切り離されると、鋼線14の部材間部分33が第2支持部材17から外れ、部分33の緊張状態が解除されるとともに、鋼線14による第1および第2杭材11,12の連結が解除される。なお、杭材建て込み工程や第1杭材引き上げ工程においてソイルモルタル42は固結していないが、第2杭材12が第2鋼線15によって吊り下げられるから、杭材12の掘削坑41における沈降が防止される。   When the pile material building process is finished, the first pile material 11 is then pulled up to a predetermined height in the vertical direction (first pile material pulling process). In the first pile material lifting step, the high frequency generator is applied to the high frequency induction heating coil 32 of the second support member 17 in a state where the end portion 30 exposed to the ground of the second steel wire 15 is fixed on the ground via the fixing means 47. A high frequency voltage is applied. When a high frequency voltage is applied to the coil 32, an eddy current is generated in a portion 36 facing the coil 32 in the inter-member portion 33 of the first steel wire 14 due to the magnetic flux generated in the coil 32, and the portion 36 generates heat. It becomes hot. In the first steel wire 14, the portion 36 facing the coil 32 in the inter-member portion 33 in a tension state generates heat at a high temperature, and the portion 36 is broken by the tension acting on the portion 36, so that the first steel wire 14 Is separated from the second support member 17. When the first steel wire 14 is cut, the inter-member portion 33 of the steel wire 14 is detached from the second support member 17, the tension state of the portion 33 is released, and the first and second pile members 11 by the steel wire 14 are released. , 12 are released. The soil mortar 42 is not consolidated in the pile material building process and the first pile material pulling process, but the second pile material 12 is suspended by the second steel wire 15. Settling in is prevented.

第1鋼線14を第2支持部材17から切り離した後、クレーン44の玉掛け45で第1杭材11の端部28を支持し、第1杭材11を縦方向上方に引き上げる。第1杭材11を引き上げると、杭材11の端部19が第2杭材12の端部20から縦方向上方へ離間し、第1杭材11と第2杭材12との間にそれら杭材11,12が存在しないソイルモルタル42のみの領域48が形成される。領域48の縦方向の寸法L3は、第1杭材11の引き上げ高さによって調節する。第1杭材11は、クレーン44によって吊り下げられ、第1杭材11と第2杭材12との離間状態(領域48の寸法L3)が維持される。杭材11を引き上げた後は、他のクレーン(図示せず)の玉掛けで第1鋼線14の端部分29を支持して鋼線14を縦方向上方へ引っ張る。第1鋼線14は、第1支持部材16を摺動しつつ部材16から徐々に引き抜かれて部材16から離脱し、さらに、掘削坑41から地上に引き抜かれる。なお、それら鋼線14は、掘削坑41から同時に引き抜かれる。   After separating the first steel wire 14 from the second support member 17, the end portion 28 of the first pile material 11 is supported by the sling 45 of the crane 44, and the first pile material 11 is pulled up in the vertical direction. When the 1st pile material 11 is pulled up, the edge part 19 of the pile material 11 will space apart from the edge part 20 of the 2nd pile material 12 to the vertical direction upper direction, and between them, between the 1st pile material 11 and the 2nd pile material 12 A region 48 of only the soil mortar 42 in which the pile materials 11 and 12 are not present is formed. The vertical dimension L3 of the region 48 is adjusted by the lifting height of the first pile material 11. The 1st pile material 11 is suspended by the crane 44, and the separation state (dimension L3 of the area | region 48) of the 1st pile material 11 and the 2nd pile material 12 is maintained. After the pile material 11 is pulled up, the end portion 29 of the first steel wire 14 is supported by a sling of another crane (not shown) and the steel wire 14 is pulled upward in the vertical direction. The first steel wire 14 is gradually pulled out from the member 16 while sliding on the first support member 16, is detached from the member 16, and is further pulled out from the excavation mine 41 to the ground. These steel wires 14 are drawn from the excavation pit 41 at the same time.

図9は、第2鋼線15を引き抜く第2鋼線引き抜き工程の説明図であり、図10は、立坑仮壁43の完成図である。図11は、図10のE−E線端面図である。第1杭材引き上げ工程が終了すると、次に、ソイルモルタル42を所定期間養生し、第2鋼線15を掘削坑41(ソイルモルタル42)から引き抜く(第2鋼線引き抜き工程)。ソイルモルタル42を養生すると、モルタル42が固結し、モルタル42によって第1杭材11や第2杭材12が掘削坑41に固定される。第2鋼線引き抜き工程では、第1杭材11の地上に露出する余分な部分を切断した後、第2鋼線15の地上に露出する端部分30をクレーン(図示せず)の玉掛けで支持しつつ、クレーンで鋼線15を矢印L4で示す縦方向上方へ引っ張り、鋼線15を緊張状態に保持する。なお、第1杭材11の余分な部分の切断時には、第2鋼線15が固定手段47を介して固定されている。   FIG. 9 is an explanatory diagram of a second steel wire drawing process for drawing the second steel wire 15, and FIG. 10 is a completed drawing of the shaft temporary wall 43. FIG. 11 is an end view taken along line EE of FIG. When the first pile material pulling process is completed, the soil mortar 42 is then cured for a predetermined period, and the second steel wire 15 is pulled out from the excavation mine 41 (soil mortar 42) (second steel wire pulling process). When the soil mortar 42 is cured, the mortar 42 is consolidated, and the first pile material 11 and the second pile material 12 are fixed to the excavation mine 41 by the mortar 42. In the second steel wire drawing process, after cutting an excess portion of the first pile material 11 exposed on the ground, the end portion 30 exposed on the ground of the second steel wire 15 is supported by a sling of a crane (not shown). However, the steel wire 15 is pulled upward in the vertical direction indicated by the arrow L4 with a crane, and the steel wire 15 is held in a tension state. Note that the second steel wire 15 is fixed via the fixing means 47 when the excess portion of the first pile material 11 is cut.

次に、第3支持部材18の高周波誘導加熱コイル35に高周波発生装置から高周波電圧を印加する。コイル35に高周波電圧を印加すると、コイル35に発生した磁束により、第2鋼線15のコイル35に対向する部位37に渦電流が発生し、部位37が発熱して高温になる。緊張状態にある第2鋼線15のうちのコイル35に対向する部位37が高温に発熱するとともに、部位37に作用する張力によって部位37が破断し、第2鋼線15が第3支持部材18から切り離される。第2鋼線15が切り離されると、鋼線15が第3支持部材18から外れ、鋼線15の緊張状態が解除される。鋼線15は、掘削坑41から徐々に引き上げられ、掘削坑41から地上に引き抜かれる。第2鋼線15を引き抜くと、図10に示すように、第1および第2杭材11,12の間に領域48が形成された立坑仮壁43が構築される。   Next, a high frequency voltage is applied to the high frequency induction heating coil 35 of the third support member 18 from a high frequency generator. When a high frequency voltage is applied to the coil 35, an eddy current is generated in a portion 37 of the second steel wire 15 facing the coil 35 due to the magnetic flux generated in the coil 35, and the portion 37 generates heat and becomes high temperature. The portion 37 of the second steel wire 15 in the tension state facing the coil 35 generates heat to a high temperature, and the portion 37 is broken by the tension acting on the portion 37, so that the second steel wire 15 becomes the third support member 18. Detached from. When the second steel wire 15 is cut off, the steel wire 15 is detached from the third support member 18 and the tension state of the steel wire 15 is released. The steel wire 15 is gradually pulled up from the excavation mine 41 and pulled out from the excavation mine 41 to the ground. When the 2nd steel wire 15 is pulled out, as shown in FIG. 10, the shaft temporary wall 43 in which the area | region 48 was formed between the 1st and 2nd pile materials 11 and 12 will be constructed | assembled.

図12は、この立坑構築方法によって作られた立坑仮壁43のユニット49の一例を示す図であり、図13は、杭材11,12の間の領域48を通るシールド装置50を模式的に示す図である。前記各工程をトンネルの進行方向と交差する方向へ繰り返すことで、図12に示すように、複数の杭材11,12,51から形成された1つのユニット49を作ることができる。さらに、トンネルの進行方向へ各ユニット49を隣接させることで、杭材11,12,51に囲繞された円形の領域48をトンネルの進行方向へ並べることができる。それらユニット49には、杭材11,12,51が存在しない円形の領域48が画成されている。この立坑構築方法では、第1杭材11の引き上げ高さを調節することで、領域48を円形にすることができる。なお、ユニット49の両側に位置する杭材51は、1本のそれを使用しており、前記各工程によって建て込まれたものではなく、掘削坑41に単に建て込んだものである。この立坑構築方法によって作られた立坑仮壁43では、第1杭材11と第2杭材12との間にそれら杭材11,12が存在しないソイルモルタル42のみの領域48が形成されるから、ユニット49においてシールド機50がそのまま通過可能な円形の領域48を容易に作ることができ、シールド機50の通過領域を確保するための杭材の切断、撤去(鏡切り)を行う必要はない。   FIG. 12 is a view showing an example of the unit 49 of the shaft temporary wall 43 made by this shaft construction method, and FIG. 13 schematically shows the shield device 50 passing through the region 48 between the pile members 11 and 12. FIG. By repeating each step in the direction intersecting with the traveling direction of the tunnel, as shown in FIG. 12, one unit 49 formed from a plurality of pile members 11, 12, 51 can be made. Furthermore, by making each unit 49 adjacent to the traveling direction of the tunnel, the circular regions 48 surrounded by the pile members 11, 12, 51 can be arranged in the traveling direction of the tunnel. In these units 49, circular regions 48 in which the pile materials 11, 12, 51 are not present are defined. In this shaft construction method, the region 48 can be made circular by adjusting the lifting height of the first pile material 11. In addition, the pile material 51 located in the both sides of the unit 49 is using one, and is not built by the said each process, but is simply built in the excavation mine 41. FIG. In the shaft temporary wall 43 made by this shaft construction method, the region 48 of only the soil mortar 42 in which the pile materials 11 and 12 do not exist is formed between the first pile material 11 and the second pile material 12. In the unit 49, the circular region 48 through which the shield machine 50 can pass as it is can be easily created, and it is not necessary to cut and remove (mirror cut) the pile material for securing the passage region of the shield machine 50. .

この立坑構築方法は、ソイルモルタル42が養生するまでの間、掘削坑41の下方に位置する第2杭材12が第2鋼線15に吊り下げられ、第2杭材12が第2鋼線15によって支持されるから、第2杭材12が掘削坑41を沈降することはなく、第2杭材12を掘削坑41の建て込み位置に確実に設置することができる。また、第1杭材11の端部19と第2杭材12の端部20との離間寸法L3を一定に保持することができ、第1杭材11と第2杭材12との間にシールド機50が通過可能な円形の領域48を作ることができる。立坑構築方法は、第2杭材12が第2鋼線15によって支持されるから、第2杭材12の姿勢を安定させることができ、杭材12が掘削坑41において不用意にずれ動くことはなく、杭材12を掘削坑41の建て込み位置に略直立させた姿勢で設置することができる。立坑構築方法は、第1杭材11とそれの下方の連なる第2杭材12との位置決めが容易であり、第1杭材11の直下に第2杭材12を確実に位置させることができる。   In this shaft construction method, until the soil mortar 42 is cured, the second pile material 12 located below the excavation mine 41 is suspended from the second steel wire 15, and the second pile material 12 is suspended from the second steel wire. 15, the second pile material 12 does not sink the excavation mine 41, and the second pile material 12 can be reliably installed at the position where the excavation mine 41 is built. Further, the separation dimension L3 between the end portion 19 of the first pile material 11 and the end portion 20 of the second pile material 12 can be kept constant, and between the first pile material 11 and the second pile material 12 A circular region 48 through which the shield machine 50 can pass can be created. In the shaft construction method, since the second pile material 12 is supported by the second steel wire 15, the posture of the second pile material 12 can be stabilized, and the pile material 12 moves inadvertently in the excavation mine 41. Rather, the pile material 12 can be installed in a posture in which it is substantially upright at the position where the excavation mine 41 is built. The shaft construction method is easy to position the first pile material 11 and the second pile material 12 connected below the first pile material 11, and can reliably position the second pile material 12 directly below the first pile material 11. .

立坑構築方法は、第1杭材11に取り付けられた支持板13が第1および第2杭材11,12をその軸方向から支持し、それら杭材11,12の連結や姿勢が支持板13によって保持されるから、それら杭材11,12を掘削坑41に建て込むときに杭材11,12の連結が不用意に解除されてしまうことはなく、それら杭材11,12を掘削坑41の建て込み位置に略直立させた姿勢で確実に設置することができる。立坑構築方法は、第1鋼線14が第1および第2杭材11,12の第1角部24と第4角部27とに配置され、第2鋼線15が第1および第2杭材11,12の第2角部25と第3角部26とに配置されることで、一対の第1鋼線14がH形綱の対角線に位置するとともに、一対の第2鋼線15がH形綱の対角線に位置するから、第1鋼線14や第2鋼線15を掘削坑41から引き抜くときの力が第1杭材11や第2杭材12に偏って作用することはなく、掘削坑41の建て込み位置における第1および第2杭材11,12の不用意なずれ動きを防ぐことができる。   In the shaft construction method, the support plate 13 attached to the first pile material 11 supports the first and second pile materials 11 and 12 from the axial direction, and the connection and posture of the pile materials 11 and 12 are the support plate 13. Therefore, when the pile members 11 and 12 are built in the excavation pit 41, the connection of the pile members 11 and 12 is not inadvertently released. It can be reliably installed in a posture that is substantially upright at the built-in position. In the shaft construction method, the first steel wire 14 is disposed at the first corner portion 24 and the fourth corner portion 27 of the first and second pile members 11, 12, and the second steel wire 15 is disposed at the first and second piles. By being arranged at the second corner 25 and the third corner 26 of the materials 11 and 12, the pair of first steel wires 14 is located on the diagonal of the H-shaped rope, and the pair of second steel wires 15 Since it is located on the diagonal line of the H-shaped rope, the force when pulling out the first steel wire 14 and the second steel wire 15 from the excavation mine 41 does not act on the first pile material 11 and the second pile material 12 in a biased manner. Inadvertent shifting of the first and second pile members 11 and 12 at the position where the excavation mine 41 is built can be prevented.

図14は、杭材10Bの他の一例を示す図であり、図15は、杭材10Bを掘削坑41に建て込む杭材建て込み工程の説明図である。図16は、第1杭材11を引き上げる第1杭材引き上げ工程の説明図であり、図17は、第2鋼線15を引き抜く第2鋼線引き抜き工程の説明図である。図14では、軸方向を矢印L1で示し、図15では、縦方向を矢印L2で示す。なお、図1の杭材10Aの各端面を示す各端面図は、この杭材10Bの各端面を示す端面図として援用することができる。   FIG. 14 is a diagram illustrating another example of the pile material 10B, and FIG. 15 is an explanatory diagram of a pile material building process for building the pile material 10B into the excavation mine 41. FIG. 16 is an explanatory diagram of a first pile material pulling step for pulling up the first pile material 11, and FIG. 17 is an explanatory diagram of a second steel wire pulling step for pulling out the second steel wire 15. In FIG. 14, the axial direction is indicated by an arrow L1, and in FIG. 15, the vertical direction is indicated by an arrow L2. In addition, each end view which shows each end surface of 10 A of pile materials of FIG. 1 can be used as an end view which shows each end surface of this pile material 10B.

杭材10Bは、第1杭材11および第2杭材12と、それら杭材11,12を支持する一対の支持板13と、第1鋼線14および第2鋼線15と、それら鋼線14,15を支持する第1〜第3支持部材16,17,18とから形成されている。この杭材10Bが図1のそれと異なるところは第1杭材11が主杭材52と仮設杭材53とから形成されている点にあり、この杭材10Bのその他の構成は図1の杭材10Aのそれと同様であるから、図1と同一の符号を付すことで、この杭材10Bにおけるその他の構成の説明は省略する。   The pile material 10B includes a first pile material 11 and a second pile material 12, a pair of support plates 13 that support the pile materials 11 and 12, a first steel wire 14 and a second steel wire 15, and the steel wires. 14 and 15 are formed from first to third support members 16, 17 and 18. This pile material 10B is different from that of FIG. 1 in that the first pile material 11 is formed of a main pile material 52 and a temporary pile material 53, and the other structure of this pile material 10B is the pile of FIG. Since it is the same as that of the material 10A, description of the other structure in this pile material 10B is abbreviate | omitted by attaching | subjecting the same code | symbol as FIG.

第1杭材11は、主杭材52と、主杭材52よりも軸方向の長さ寸法が短い仮設杭材53とから作られている。主杭材52と仮設杭材53とは、それらの端部54,55(対向端部)どうしが互いに当接した状態で軸方向へ直状に並んでいる。それら杭材52,53は、端部54,55どうしが固定手段(図示せず)を介して連結されている。それら杭材52,53は、図1のそれと同様に、第1および第2対向壁21,22と連結壁23とを有するH形綱である。なお、杭材53は、角柱状のコンクリート柱であってもよい。杭材10Bでは、主杭材52の一方の端部19(対向端部)と第2杭材12の一方の端部20(対向端部)とが当接した状態で、それら杭材12,52が軸方向へ直状に並んでいる。   The first pile material 11 is made of a main pile material 52 and a temporary pile material 53 whose axial length is shorter than that of the main pile material 52. The main pile material 52 and the temporary pile material 53 are arranged in a straight line in the axial direction with their end portions 54 and 55 (opposing end portions) in contact with each other. The pile members 52 and 53 are connected to each other between end portions 54 and 55 through fixing means (not shown). These pile members 52 and 53 are H-shaped ropes having first and second opposing walls 21 and 22 and a connecting wall 23, similarly to that of FIG. 1. The pile material 53 may be a prismatic concrete column. In the pile material 10B, in a state where one end portion 19 (opposing end portion) of the main pile material 52 and one end portion 20 (opposing end portion) of the second pile material 12 are in contact with each other, 52 are arranged in a straight line in the axial direction.

この杭材10Bを使用して立坑仮壁43を構築する手順は、以下のとおりである。掘削坑41にソイルモルタル42(養生充填材)を充填するとともに、図14の杭材10Bを用意する。それらの準備が完了した後、杭材10Bを掘削坑41に建て込む(杭材建て込み工程)。クレーン44の玉掛け45で杭材10Bの端部(仮設杭材53の端部56)を支持し、クレーン44によって杭材10Bを垂直に立てて空中に吊り上げ、杭材10Bを掘削坑41の上部に移動させる。クレーン44に保持された杭材10Bでは、仮設杭材53が上方に位置し、杭材53の下方に主杭材52が位置するとともに、杭材52の下方に第2杭材12が位置する。杭材10Bを掘削坑41の上部に位置させた後、クレーン44によって杭材10Bをその端部(第2杭材12の端部46)から掘削坑41に徐々に建て込み、図15に示すように、仮設杭材53の端部56を地上に露出させた状態で杭材10Bの大部分を掘削坑41(ソイルモルタル42)に埋設させる。杭材建て込み工程では、第1鋼線14の第1および第2支持部材16,17の間に延びる部材間部分33が緊張状態にあり、さらに、支持板13が第1および第2杭材11,12の端部19,20を支持しているから、それら杭材11,12どうしの不用意なずれ動きがなく、それら杭材11,12の連結が維持される。   The procedure for constructing the vertical shaft temporary wall 43 using this pile material 10B is as follows. While filling the excavation pit 41 with the soil mortar 42 (curing filler), the pile material 10B of FIG. 14 is prepared. After those preparations are completed, the pile material 10B is built in the excavation mine 41 (pile material building process). The end of the pile material 10B (the end 56 of the temporary pile material 53) is supported by the sling 45 of the crane 44, and the pile material 10B is vertically raised by the crane 44 and lifted in the air. Move to. In the pile material 10 </ b> B held by the crane 44, the temporary pile material 53 is located above, the main pile material 52 is located below the pile material 53, and the second pile material 12 is located below the pile material 52. . After the pile material 10B is positioned at the upper part of the excavation mine 41, the pile material 10B is gradually built into the excavation mine 41 from its end (the end 46 of the second pile material 12) by the crane 44, as shown in FIG. In this way, most of the pile material 10B is embedded in the excavation mine 41 (soil mortar 42) with the end portion 56 of the temporary pile material 53 exposed to the ground. In the pile material building step, the inter-member portion 33 extending between the first and second support members 16 and 17 of the first steel wire 14 is in a tension state, and the support plate 13 is the first and second pile materials. Since the end portions 19 and 20 of the 11 and 12 are supported, there is no inadvertent displacement between the pile materials 11 and 12, and the connection of the pile materials 11 and 12 is maintained.

杭材建て込み工程が終了すると、次に、第1杭材11を縦方向上方へ所定高さまで引き上げる(第1杭材引き上げ工程)。第1杭材引き上げ工程では、第2鋼線15の地上に露出した端部分30を地上において固定手段47を介して固定した状態で、第2支持部材の高周波誘導加熱コイル32に高周波発生装置から高周波電圧を印加する。第1鋼線14では、緊張状態にある部材間部分33のうちのコイル32に対向する部位36が高温に発熱するとともに、部位36に作用する張力によって部位36が破断し、第1鋼線14が第2支持部材17から切り離される。第1鋼線14が切り離されると、鋼線14の部材間部分33が第2支持部材17から外れ、部分33の緊張状態が解除されるとともに、鋼線14による第1および第2杭材11,12の連結が解除される。第2杭材12は第2鋼線15によって吊り下げられるから、杭材15の掘削坑41における沈降が防止される。   When the pile material building process is finished, the first pile material 11 is then pulled up to a predetermined height in the vertical direction (first pile material pulling process). In the first pile material pulling step, the end portion 30 exposed to the ground of the second steel wire 15 is fixed on the ground via the fixing means 47, and the high frequency induction heating coil 32 of the second support member is fed from the high frequency generator. Apply high frequency voltage. In the first steel wire 14, the portion 36 facing the coil 32 in the inter-member portion 33 in a tension state generates heat at a high temperature, and the portion 36 is broken by the tension acting on the portion 36, so that the first steel wire 14 Is separated from the second support member 17. When the first steel wire 14 is cut, the inter-member portion 33 of the steel wire 14 is detached from the second support member 17, the tension state of the portion 33 is released, and the first and second pile members 11 by the steel wire 14 are released. , 12 are released. Since the second pile material 12 is suspended by the second steel wire 15, settling of the pile material 15 in the excavation mine 41 is prevented.

第1鋼線14を第2支持部材17から切り離した後、クレーン44の玉掛け45で仮設杭材53の端部56を支持し、仮設杭材53を縦方向上方に引き上げ、杭材53すべてを掘削坑41から地上に引き上げるとともに、主杭材52の端部55を地上に露出させる。主杭材52の端部55の露出寸法は、建て込み工程終了時における仮設杭材53の端部56の露出寸法と同一である。仮設杭材53を地上に引き上げると、第1杭材11の端部19が第2杭材12の端部20から縦方向上方へ離間し、第1杭材11と第2杭材12との間にそれら杭材11,12が存在しないソイルモルタル42のみの領域48が形成される。領域48の縦方向の寸法L3は、引き上げられた仮設杭材53のそれと同一となる。仮設杭材53を引き上げた後、第1杭材11がクレーン44によって吊り下げられ、第1杭材11と第2杭材12との離間状態(領域48の寸法L3)が維持される。杭材11を引き上げた後は、他のクレーン(図示せず)の玉掛けで第1鋼線14の端部29を支持して鋼線14を縦方向上方へ引っ張る。第1鋼線14は、第1支持部材17を摺動しつつ部材17から徐々に引き抜かれて部材17から離脱し、さらに、掘削坑41から地上に引き抜かれる。鋼線14を引き抜いた後は、主杭材52と仮設杭材53との固定が解除され、仮設杭材53が主杭材52から取り外される。   After the first steel wire 14 is separated from the second support member 17, the end 56 of the temporary pile material 53 is supported by the sling 45 of the crane 44, the temporary pile material 53 is pulled up in the vertical direction, and the entire pile material 53 is removed. While pulling up from the excavation pit 41 to the ground, the end 55 of the main pile material 52 is exposed to the ground. The exposed dimension of the end portion 55 of the main pile material 52 is the same as the exposed dimension of the end portion 56 of the temporary pile material 53 at the end of the erection process. When the temporary pile material 53 is pulled up to the ground, the end portion 19 of the first pile material 11 is separated vertically upward from the end portion 20 of the second pile material 12, and the first pile material 11 and the second pile material 12 are separated from each other. A region 48 of only the soil mortar 42 in which the pile materials 11 and 12 are not present is formed therebetween. The vertical dimension L3 of the region 48 is the same as that of the raised temporary pile material 53. After pulling up the temporary pile material 53, the first pile material 11 is suspended by the crane 44, and the separated state (the dimension L3 of the region 48) between the first pile material 11 and the second pile material 12 is maintained. After the pile material 11 is pulled up, the end portion 29 of the first steel wire 14 is supported by a sling of another crane (not shown) and the steel wire 14 is pulled upward in the vertical direction. The first steel wire 14 is gradually pulled out of the member 17 while sliding on the first support member 17, is detached from the member 17, and is further pulled out from the excavation mine 41 to the ground. After the steel wire 14 is pulled out, the fixing of the main pile material 52 and the temporary pile material 53 is released, and the temporary pile material 53 is removed from the main pile material 52.

第1杭材引き上げ工程が終了すると、次に、ソイルモルタル42を所定期間養生し、第2鋼線15を掘削坑41から引き抜く(第2鋼線引き抜き工程)。ソイルモルタル42を養生すると、モルタル42が固結し、モルタル42によって第1杭材11(主杭材52)や第2杭材12が掘削坑41に固定される。第2鋼線引き抜き工程では、第2鋼線15の地上に露出する端部分30をクレーン(図示せず)の玉掛けで支持しつつ、クレーンで鋼線15を矢印L4で示す縦方向上方へ引っ張り、鋼線15を緊張状態に保持する。次に、第3支持部材18の高周波誘導加熱コイル35に高周波発生装置から高周波電圧を印加する。コイル35に高周波電圧を印加すると、緊張状態にある第2鋼線15のうちのコイル35に対向する部位37が高温に発熱するとともに、部位37に作用する張力によって部位37が破断し、第2鋼線15が第3支持部材18から切り離される。第2鋼線15が切り離されると、鋼線15が第3支持部材18から外れ、鋼線15の緊張状態が解除される。鋼線15は、掘削坑41から徐々に引き上げられ、掘削坑41から地上に引き抜かれる。第2鋼線15を引き抜くと、第1および第2杭材11,12の間に領域48が形成された立坑仮壁43が構築される(図10参照)。   When the first pile material pulling process is completed, the soil mortar 42 is then cured for a predetermined period, and the second steel wire 15 is pulled out from the excavation mine 41 (second steel wire pulling process). When the soil mortar 42 is cured, the mortar 42 is consolidated, and the first pile material 11 (main pile material 52) and the second pile material 12 are fixed to the excavation mine 41 by the mortar 42. In the second steel wire drawing step, the end portion 30 exposed on the ground of the second steel wire 15 is supported by a sling of a crane (not shown), and the steel wire 15 is pulled upward in the vertical direction indicated by the arrow L4 with the crane. The steel wire 15 is held in a tension state. Next, a high frequency voltage is applied to the high frequency induction heating coil 35 of the third support member 18 from a high frequency generator. When a high frequency voltage is applied to the coil 35, the portion 37 of the second steel wire 15 that is in tension is opposed to the coil 35 and heats up to a high temperature, and the portion 37 is broken by the tension acting on the portion 37. The steel wire 15 is separated from the third support member 18. When the second steel wire 15 is cut off, the steel wire 15 is detached from the third support member 18 and the tension state of the steel wire 15 is released. The steel wire 15 is gradually pulled up from the excavation mine 41 and pulled out from the excavation mine 41 to the ground. When the 2nd steel wire 15 is pulled out, the shaft temporary wall 43 in which the area | region 48 was formed between the 1st and 2nd pile materials 11 and 12 will be constructed | assembled (refer FIG. 10).

前記各工程をトンネルの進行方向と交差する方向へ繰り返すことで、複数の杭材11,12,51から形成された1つのユニット49を作ることができる(図12参照)。さらに、トンネルの進行方向へ各ユニット49を隣接させることで、杭材11,12,51に囲繞された円形の領域48をトンネルの進行方向へ並べることができる。この杭材10Bを使用する立坑構築方法は、図1の杭材10Aを使用する立坑構築方法が有する効果に加え、以下の効果を有する。仮設杭材53を地上に引き上げることで第1および第2杭材11,12における端部19,20どうしの離間寸法L3が決まり、図1の杭材10Aのように第1杭材11の引き上げ高さを調節しつつ第1および第2杭材11,12における端部19,20どうしの離間寸法L3を調節する必要はなく、仮設杭材53を利用することで第1および第2杭材11,12における端部どうし19,20の離間寸法L3を正確に調節することができる。この立坑構築方法は、仮設杭材53の長さ寸法を変えることで、第1および第2杭材11,12における端部19,20どうしの離間寸法L3を容易に変えることができ、第1杭材11と第2杭材12との間に杭材11,12が存在しない一定形状の領域48を確実に作ることができる。   By repeating each step in the direction intersecting with the traveling direction of the tunnel, one unit 49 formed from a plurality of pile members 11, 12, 51 can be made (see FIG. 12). Furthermore, by making each unit 49 adjacent to the traveling direction of the tunnel, the circular regions 48 surrounded by the pile members 11, 12, 51 can be arranged in the traveling direction of the tunnel. The shaft construction method using the pile material 10B has the following effects in addition to the effects of the shaft construction method using the pile material 10A of FIG. By pulling up the temporary pile material 53 to the ground, the separation dimension L3 between the end portions 19 and 20 in the first and second pile materials 11 and 12 is determined, and the first pile material 11 is pulled up like the pile material 10A in FIG. It is not necessary to adjust the separation dimension L3 between the end portions 19 and 20 of the first and second pile members 11 and 12 while adjusting the height, and the first and second pile members can be obtained by using the temporary pile member 53. It is possible to accurately adjust the separation dimension L3 of the end portions 19 and 20 at 11 and 12. In this shaft construction method, the separation dimension L3 between the end portions 19 and 20 in the first and second pile members 11 and 12 can be easily changed by changing the length dimension of the temporary pile member 53. A region 48 having a certain shape where the pile materials 11 and 12 do not exist can be reliably formed between the pile material 11 and the second pile material 12.

杭材の一例を示す図。The figure which shows an example of a pile material. 図1のA−A線端面図。FIG. 2 is an end view taken along line AA in FIG. 1. 図1のB−B線端面図。FIG. 3 is an end view taken along line BB in FIG. 1. 図1のC−C線端面図。The CC sectional view taken on the line of FIG. 第2および第3支持部材の一例を示す図。The figure which shows an example of a 2nd and 3rd support member. 杭材を掘削坑に建て込む杭材建て込み工程の説明図。Explanatory drawing of the pile material construction process which builds a pile material in an excavation mine. 第1杭材を引き上げる第1引き上げ工程の説明図。Explanatory drawing of the 1st raising process which raises a 1st pile material. 図7のD−D線端面図。The DD line end view of FIG. 第2鋼線を引き抜く第2鋼線引き抜き工程の説明図。Explanatory drawing of the 2nd steel wire drawing process which draws out the 2nd steel wire. 立坑の完成図。The completed drawing of the shaft. 図10のE−E線端面図。The EE line | wire end view of FIG. 立坑構築方法によって作られた立坑のユニットの一例を示す図。The figure which shows an example of the unit of the shaft made by the shaft construction method. 杭材の間の領域を通るシールド装置を模式的に示す図。The figure which shows typically the shield apparatus which passes along the area | region between pile materials. 杭材の他の一例を示す図。The figure which shows another example of a pile material. 杭材を掘削坑に建て込む杭材建て込み工程の説明図。Explanatory drawing of the pile material construction process which builds a pile material in an excavation mine. 第1杭材を引き上げる第1杭材引き上げ工程の説明図。Explanatory drawing of the 1st pile material raising process which raises a 1st pile material. 第2鋼線を引き抜く第2鋼線引き抜き工程の説明図。Explanatory drawing of the 2nd steel wire drawing process which draws out the 2nd steel wire.

符号の説明Explanation of symbols

10A 杭材
10B 杭材
11 第1杭材
12 第2杭材
13 支持板
14 第1鋼線
15 第2鋼線
16 第1支持部材
17 第2支持部材
18 第3支持部材
19 端部(対向端部)
20 端部(対向端部)
21 第1対向壁
22 第2対向壁
23 連結壁
24 第1角部
25 第2角部
26 第3角部
27 第4角部
31 固定部
32 高周波誘導加熱コイル
33 部材間部分
34 固定部
35 高周波誘導加熱コイル
41 掘削坑
42 ソイルモルタル(養生充填材)
43 立坑仮壁
48 領域
52 主杭材
53 仮設杭材
DESCRIPTION OF SYMBOLS 10A Pile material 10B Pile material 11 1st pile material 12 2nd pile material 13 Support plate 14 1st steel wire 15 2nd steel wire 16 1st support member 17 2nd support member 18 3rd support member 19 End (opposite end) Part)
20 end (opposite end)
21 First opposing wall 22 Second opposing wall 23 Connecting wall 24 First corner 25 Second corner 26 Third corner 27 Fourth corner 31 Fixed portion 32 High frequency induction heating coil 33 Inter-member portion 34 Fixed portion 35 High frequency Induction heating coil 41 Drilling pit 42 Soil mortar (curing filler)
43 Temporary tunnel wall 48 Area 52 Main pile material 53 Temporary pile material

Claims (5)

地盤を掘削して縦方向へ延びる掘削坑を形成し、前記掘削坑に養生充填材を充填するとともに前記縦方向に杭材を建て込んで立坑を構築する立坑構築方法において、
前記杭材が、互いに当接する対向端部を有して軸方向へ並ぶ第1杭材および第2杭材と、前記軸方向へ延びていて前記第1杭材の非対向端部からそれら杭材の対向端部を越えて前記第2杭材の所定の位置に達する第1鋼線と、前記軸方向へ延びていて前記第1杭材の非対向端部からそれら杭材の対向端部を越えて前記第2杭材の所定の位置に達する第2鋼線と、前記第1杭材に取り付けられて前記第1鋼線を摺動可能に支持する第1支持部材と、前記第2杭材に取り付けられて前記第1鋼線を支持可能かつ該第1鋼線を切り離し可能な第2支持部材と、前記第2杭材に取り付けられて前記第2鋼線を支持可能かつ該第2鋼線を切り離し可能な第3支持部材とから形成され、
前記第1鋼線を前記第1支持部材と前記第2支持部材との間において緊張させた状態で、前記掘削坑に前記第1および第2杭材を建て込む杭材建て込み工程と、前記第2鋼線を地上において支持しつつ前記第1鋼線を前記第2支持部材から切り離し、該第1鋼線を前記掘削坑から引き抜くとともに前記第1杭材を縦方向上方へ引き上げて第1杭材と第2杭材との対向端部を縦方向へ所定寸法離間させる第1杭材引き上げ工程と、前記充填材を養生させた後、前記第2鋼線を前記第3支持部材から切り離して該第2鋼線を前記掘削坑から引き抜く第2鋼線引き抜き工程とを有することを特徴とする立坑構築方法。
In the shaft construction method of excavating the ground to form a drilling mine extending in the vertical direction, filling the excavation mine with a curing filler, and building a vertical shaft by building a pile material in the vertical direction,
The pile material has first and second pile materials arranged in the axial direction and having opposed end portions that contact each other, and the piles extending from the non-opposed end portion of the first pile material in the axial direction. A first steel wire that reaches a predetermined position of the second pile material beyond the opposed end portion of the material, and extends in the axial direction from the non-opposed end portion of the first pile material to the opposed end portions of the pile material A second steel wire that reaches a predetermined position of the second pile material over the first pile, a first support member that is attached to the first pile material and slidably supports the first steel wire, and the second A second support member attached to a pile material and capable of supporting the first steel wire and capable of separating the first steel wire; and a second support member attached to the second pile material and capable of supporting the second steel wire. Formed from a third support member capable of separating two steel wires,
In the state where the first steel wire is tensioned between the first support member and the second support member, a pile material erection step of erected the first and second pile materials in the excavation mine, While supporting the second steel wire on the ground, the first steel wire is separated from the second support member, the first steel wire is pulled out from the excavation mine, and the first pile material is pulled up in the vertical direction to be first. The first pile material pulling up step for separating the opposite ends of the pile material and the second pile material in the vertical direction by a predetermined dimension, and after curing the filler, the second steel wire is separated from the third support member. And a second steel wire drawing step of drawing the second steel wire from the excavation pit.
前記第1および第2杭材が、互いに並行離間して軸方向へ延びる第1および第2対向壁と、それら対向壁の間に位置して軸方向へ延びる連結壁とを有するH形綱であり、前記第1対向壁と前記連結壁との交点に形成された第1角部および第2角部と、前記第2対向壁と前記連結壁との交点に形成されて前記第1角部に対向する第3角部および前記第2角部に対向する第4角部とを備え、前記第1鋼線が、前記第1角部と前記第4角部とに配置され、前記第2鋼線が、前記第2角部と前記第3角部とに配置されている請求項1記載の立坑構築方法。   In the H-shaped rope, the first and second pile members have first and second opposing walls extending in the axial direction and spaced apart from each other, and a connecting wall extending between the opposing walls and extending in the axial direction. And the first corner and the second corner formed at the intersection of the first opposing wall and the connecting wall, and the first corner formed at the intersection of the second opposing wall and the connecting wall. A third corner portion facing the second corner portion and a fourth corner portion facing the second corner portion, wherein the first steel wire is disposed at the first corner portion and the fourth corner portion, and the second corner portion. The shaft construction method of Claim 1 with which the steel wire is arrange | positioned at the said 2nd corner | angular part and the said 3rd corner | angular part. 前記第1杭材が、互いに当接する対向端部を有して軸方向へ並ぶ主杭材と仮設杭材とから形成され、前記第1杭材引き上げ工程では、前記仮設杭材の長さ寸法が第1および第2杭材における対向端部どうしの離間寸法に一致するように、前記仮設杭材を地上に引き上げた後、前記主杭材から前記仮設杭材を取り外す請求項1または請求項2に記載の立坑構築方法。   The first pile material is formed from a main pile material and a temporary pile material that have opposing end portions that contact each other and are arranged in the axial direction. In the first pile material pulling step, the length dimension of the temporary pile material The said temporary pile material is removed from the said main pile material, after pulling up the said temporary pile material to the ground so that it may correspond to the separation dimension of the opposing edge parts in a 1st and 2nd pile material. 2. The shaft construction method according to 2. 前記杭材が、前記第1杭材と前記第2杭材との対向端部に跨って前記軸方向へ延びる支持板を含み、前記支持板は、前記第1杭材と前記第2杭材とのいずれか一方に取り付けられてそれら杭材をその軸方向から支持する請求項1ないし請求項3いずれかに記載の立坑構築方法。   The pile material includes a support plate extending in the axial direction across opposing ends of the first pile material and the second pile material, and the support plate includes the first pile material and the second pile material. The shaft construction method according to any one of claims 1 to 3, wherein the pile material is attached to either one of the two and supports the pile material from the axial direction. 前記第2支持部材と前記第3支持部材とには、高周波誘導加熱コイルが設置され、前記高周波誘導加熱コイルが、前記第1および第2鋼線に渦電流を発生させてそれら鋼線自体を発熱破断させることで、それら鋼線を前記第2および第3支持部材から切り離す請求項1ないし請求項4いずれかに記載の立坑構築方法。   The second support member and the third support member are provided with a high-frequency induction heating coil, and the high-frequency induction heating coil generates eddy currents in the first and second steel wires so that the steel wires themselves are The shaft construction method according to any one of claims 1 to 4, wherein the steel wires are separated from the second and third support members by heat-breaking.
JP2007099961A 2007-04-06 2007-04-06 Vertical shaft construction method Active JP4806370B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007099961A JP4806370B2 (en) 2007-04-06 2007-04-06 Vertical shaft construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007099961A JP4806370B2 (en) 2007-04-06 2007-04-06 Vertical shaft construction method

Publications (2)

Publication Number Publication Date
JP2008255688A JP2008255688A (en) 2008-10-23
JP4806370B2 true JP4806370B2 (en) 2011-11-02

Family

ID=39979542

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007099961A Active JP4806370B2 (en) 2007-04-06 2007-04-06 Vertical shaft construction method

Country Status (1)

Country Link
JP (1) JP4806370B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806916A (en) * 2012-11-07 2014-05-21 北京市市政四建设工程有限责任公司 Process for constructing shield rapid inspection shaft

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5210221B2 (en) * 2009-03-30 2013-06-12 大成建設株式会社 Separation structure of core material and method for constructing start shaft of shield excavator using the same
JP7079645B2 (en) * 2018-04-13 2022-06-02 鹿島建設株式会社 How to remove piles and upper piles
CN113090272A (en) * 2021-04-26 2021-07-09 中国恩菲工程技术有限公司 Deep shaft and partition supporting method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0833005B2 (en) * 1989-04-25 1996-03-29 戸田建設株式会社 Construction method of soil pile row mountain retaining wall
JP3125153B2 (en) * 1992-01-09 2001-01-15 東京電力株式会社 Shaft structure and construction method
CH681835A5 (en) * 1992-08-17 1993-05-28 Toni Baer
JP4091756B2 (en) * 2001-08-03 2008-05-28 日鉄コンポジット株式会社 Construction method of shaft wall part and member for shaft wall in shield excavation
JP4359700B2 (en) * 2005-06-03 2009-11-04 飛島建設株式会社 Precast concrete pile core and method for removing reinforced concrete structure using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103806916A (en) * 2012-11-07 2014-05-21 北京市市政四建设工程有限责任公司 Process for constructing shield rapid inspection shaft

Also Published As

Publication number Publication date
JP2008255688A (en) 2008-10-23

Similar Documents

Publication Publication Date Title
KR101859367B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
CN104264902B (en) Steel pipe concrete column and pile foundation connection structure
JP4806370B2 (en) Vertical shaft construction method
CN104264682B (en) A kind of anchor draws the lagging pile first floor to add concrete beam method for supporting
KR101840226B1 (en) The guide holes of the form for soil auger dredges
KR102548904B1 (en) Casing guide block for tilting facility and construction method of overlapping concrete pile using the same
KR102003448B1 (en) Reinforced solider pile apparatus of long span&#39;s soil retaining wall
KR101150597B1 (en) Apparatus for file construction corresponding height restriction to and the method thereof
JP2008013926A (en) Existing building foundation reinforcing method
KR20220001424A (en) Method for constructing vertical structure in vertical tunnel using top down method
KR101534641B1 (en) The method for constructing the basement
JP5925231B2 (en) Building construction method and underground building of new building
JP4806375B2 (en) Vertical wall construction method
JP7007691B1 (en) Casting method for spring spacers, reinforcing bar cages and underground piles
JP5977412B2 (en) Basement of new building using existing building
JP6220659B2 (en) Position adjustment method of reaction force receiving member and top of column
KR101383817B1 (en) Top down method
JP5506057B2 (en) Building construction method
JP5904585B2 (en) Pile concrete placement method
JP6266411B2 (en) Ground excavation method
JP6130991B2 (en) Foundation structure
JP5207086B2 (en) Construction method of underground tank
JP2023079235A (en) Underpass construction method under railroad track
JP5027752B2 (en) Construction method of underground floor pillar and underground floor pillar
KR101650291B1 (en) Constructing mehtod for portal frame structufre in the underground having supporting pile embedded therein

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090317

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101116

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110726

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110812

R150 Certificate of patent or registration of utility model

Ref document number: 4806370

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140819

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250