JP5195482B2 - Pipeline laying method - Google Patents
Pipeline laying method Download PDFInfo
- Publication number
- JP5195482B2 JP5195482B2 JP2009026947A JP2009026947A JP5195482B2 JP 5195482 B2 JP5195482 B2 JP 5195482B2 JP 2009026947 A JP2009026947 A JP 2009026947A JP 2009026947 A JP2009026947 A JP 2009026947A JP 5195482 B2 JP5195482 B2 JP 5195482B2
- Authority
- JP
- Japan
- Prior art keywords
- pipeline
- tunnel
- rail
- forming
- laying method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
本発明は、トンネル内に単管を溶接連結して複数条のパイプラインを形成するパイプライン敷設方法に関する。 The present invention relates to a pipeline laying method for forming a plurality of pipelines by welding and connecting single pipes in a tunnel.
トンネル内において多数のパイプを軸方向に連続的に突き合わせ溶接してパイプラインを敷設する方法に関し、例えば特許文献1の従来技術の項に下記のような記載がある。
「狭隘な現場における従来の工法の代表的な例として、トンネル内における配管作業の工法を、説明する。この例は、パイプ径900A、トンネル径2,400mmの場合である。
狭隘なトンネル1内に敷設した固定側パイプ2と、継ぎ側パイプ3をパイプ円周自動溶接装置20によりパイプ継ぎ目を溶接している。また、現在の溶接作業に続いて次に接続するパイプ4をインナークランプ装置6により、継ぎ目ギャップとパイプの芯合せ設定を行っている。さらに、後続の継ぎパイプ5は、台車7に搭載されレール8上を、敷設位置に向けて搬送されているところである。」
Regarding a method of laying a pipeline by continuously butting a large number of pipes in a tunnel in a tunnel, for example, the following description is given in the section of prior art in
“As a typical example of a conventional construction method in a narrow field, a construction method for piping work in a tunnel will be described. This example is for a pipe diameter of 900A and a tunnel diameter of 2,400 mm.
The
上記の特許文献1の記載には明確に示されていないが、トンネル内の狭隘な場所において多数の単管を軸方向に連続的に突き合わせ溶接してパイプラインを敷設する方法としては、以下のように行なわれる。
シールドトンネルの施工に際して敷設された軌道上に台車を走らせ、この台車に所定の長さ(例えば9m)の単管を乗せてトンネル内に搬入する。そして、順次軸方向に一直線になるようにトンネル内に載置する。単管を所定の本数、例えば3本搬入すると、それらをトンネル内に設置されたクレーンによって吊り上げ、軸方向に突き合わせ溶接して連結する。連結された単管は所定の架台の上に載置する。このような作業を繰り返して順次トンネル入口側に単管を連結してパイプラインを形成する。
Although not clearly shown in the description of
A carriage is run on a track laid during the construction of the shield tunnel, and a single pipe having a predetermined length (for example, 9 m) is placed on the carriage and carried into the tunnel. And it mounts in a tunnel so that it may become a straight line in an axial direction sequentially. When a predetermined number of, for example, three single tubes are carried in, they are lifted by a crane installed in the tunnel, and butt-welded in the axial direction and connected. The connected single tubes are placed on a predetermined mount. By repeating such operations, a single pipe is sequentially connected to the tunnel entrance side to form a pipeline.
上記の従来のパイプライン敷設方法は、一条のパイプラインを敷設する方法であり、このような方法で狭隘なトンネル空間において二条のパイプラインを敷設しようとすると以下のような問題がある。
一条目のパイプラインは、上述した一条のパイプライン敷設で説明したように、シールドトンネルの施工の際に利用した軌条上に台車を走行させ、この台車によって単管を搬入し、これを軸方向に溶接することにより行なうことができる。
しかしながら、一条目のパイプラインの敷設によって軌条が塞がれるため、そのままでは二条目の単管を台車によって搬入することさえできない。
The above-described conventional pipeline laying method is a method of laying a single pipeline, and there are the following problems when attempting to lay two pipelines in a narrow tunnel space by such a method.
As explained in the above-mentioned one-line pipeline laying, the first pipeline runs the carriage on the rail used in the construction of the shield tunnel, carries a single pipe with this carriage, and this is axially It can be performed by welding to.
However, since the rail is blocked by the laying of the first pipeline, the single tube of the second strip cannot even be carried in by the carriage.
仮に、台車走行のための軌条が一本目のパイプラインで塞がれないようにするために、一条目のパイプラインを軌条から外れたトンネル内壁に近い箇所にて溶接しようとすると溶接のためのスペースが十分でないために溶接作業ができないという問題がある。 In order to prevent the rail for traveling on the carriage from being blocked by the first pipeline, if the first pipeline is welded at a location near the tunnel inner wall that is off the rail, the welding There is a problem that the welding operation cannot be performed due to insufficient space.
このように、トンネル内のような狭隘な場所において単管を順次突き合わせ溶接してパイプラインを敷設する従来方法においては、一条のパイプラインを敷設することしか考えられておらず、その方法では二条のパイプラインを敷設することができなかった。 Thus, in the conventional method of laying a pipeline by sequentially butting a single pipe in a narrow place such as in a tunnel, it is only considered to lay a single pipeline. The pipeline could not be laid.
本発明はかかる課題を解決するためになされたものであり、トンネル内においてパイプを順次突き合わせ溶接してパイプラインを敷設する方法において、二条のパイプラインを敷設する方法、及び該方法に用いる架台を提供することを目的としている。 The present invention has been made to solve such a problem, and in a method for laying a pipeline by sequentially butting pipes in a tunnel, a method for laying two pipelines, and a mount used in the method are provided. It is intended to provide.
上述したように、シールドトンネル内という狭隘な空間において従来のパイプライン敷設方法では一条のパイプラインの敷設しかできない。そこで、発明者はこのような狭い空間において二条のパイプライン敷設を可能にするにはいかなる課題があり、その課題をいかにして解決するかを鋭意検討し、本発明を完成したものである。
以下においては、二条のパイプライン敷設に伴う課題を説明すると共にその課題を解決するためにどのような手段を講じたかを詳細に説明する。
As described above, the conventional pipeline laying method can only lay a single pipeline in a narrow space inside the shield tunnel. Therefore, the inventor has completed any problems to make it possible to lay two pipelines in such a narrow space, and intensively studied how to solve the problems.
In the following, the problems associated with the laying of the two pipelines will be described, and what measures have been taken to solve the problems will be described in detail.
(1−1)第1の課題
まず、第1の課題として、一条目のパイプラインを敷設したときに、従来方法では既設の軌道が敷設された一条目のパイプラインによって使用不能になるため、このままでは既設の軌道上に台車を走行させて台車によって二条目のパイプライン用の単管を搬入することができない点である。
(1−2)第1の課題解決手段の考え方
シールドトンネルの施工の際に敷設された軌条は主として土砂の搬出のためのトロッコを走行させるためのものであり、幅広の軌条が敷設されている。
したがって、この軌条をそのまま生かして上記課題を解決するのは困難であると考え、できるだけ既設の軌条を生かしつつ上記の課題を解決するにはどうすべきかを考えた。
そして、二本の平行に敷設されている既設の軌条のうちの一本を生かし、他の一本の軌条をパイプ搬送が可能な程度の軌条幅でかつトンネルの片側の内壁に寄せて盛りかえることを考えた。つまり、既設の軌条をそのまま利用するのではなく、既設の軌条を利用しつつもパイプ搬入に必要とされる程度の幅狭の態様に変形することで、搬入した一条目のパイプ載置位置および一条目パイプラインの形成場所を軌条以外の場所に確保することを考えた。
(1-1) First problem First, as a first problem, when the first pipeline is laid, in the conventional method, the existing track becomes unusable by the first pipeline laid, In this state, the carriage cannot be carried on the existing track and the single pipe for the second pipeline cannot be carried by the carriage.
(1-2) Concept of the first problem solving means The rail laid during the construction of the shield tunnel is mainly for traveling a truck for carrying out sediment, and a wide rail is laid. .
Therefore, it was thought that it was difficult to solve the above problem by making use of this rail as it was, and how to solve the above problem while utilizing the existing rail as much as possible was considered.
Then, using one of the two existing rails laid in parallel, the other rail can be moved to the inner wall on one side of the tunnel with a rail width that allows pipe conveyance. I thought. In other words, instead of using the existing rail as it is, the pipe mounting position of the first strip that has been carried We considered securing the formation place of the first line pipeline in a place other than the rail.
(2−1)第2の課題
一条目の単管を軸方向に溶接するには所定の溶接スペースが必要となるため、トンネル内が狭隘空間であることを考慮すると、溶接スペースを確保するという観点から一条目の単管の溶接をトンネル中心付近で行なわざるを得ない。
しかしながら、一条目のパイプラインをトンネル中心付近で形成すると、形成された一条目のパイプラインが邪魔になって二条目のパイプライン敷設のための作業、つまり単管の搬入、単管の溶接等の作業ができないというのが第2の課題である。
(2-1) Second problem Since a predetermined welding space is required to weld the first pipe of the first tube in the axial direction, considering that the tunnel is a narrow space, it is said that the welding space is secured. From the point of view, it is necessary to weld the first single tube near the center of the tunnel.
However, if the first line is formed near the center of the tunnel, the formed first line will be in the way, and work for laying the second line, that is, carrying a single pipe, welding a single pipe, etc. The second problem is that the above work cannot be performed.
(2−2)第2の課題の解決手段の考え方
一条目のパイプライン形成のための単管の溶接作業をトンネル中央付近で行い、形成された一条目のパイプラインをトンネルの内壁方向に移動することにより、二条目のパイプライン敷設のための作業、つまり単管の搬入、単管の溶接等の作業スペースを確保することを考えた。
(2-2) Concept of solution to the second problem Welding work for a single pipe for forming the first line of the pipeline near the center of the tunnel, and moving the formed first line of the pipeline toward the inner wall of the tunnel By doing so, it was considered to secure a work space for laying the second pipeline, that is, carrying a single pipe and welding a single pipe.
以下に示す本発明は上記の「解決手段の考え方」の一方または両方に基づいてなされたものであり、具体的には以下に示す態様のものである。 The present invention described below has been made based on one or both of the above-mentioned “concepts of the solving means”, and specifically includes the following embodiments.
(1)本発明の第1の形態に係るパイプライン敷設方法は、トンネル内に搬入した単管を溶接によって連結して形成するパイプラインを、前記トンネル内に複数条形成するパイプライン敷設方法であって、トンネル内に敷設された台車走行用軌条内以外の場所にパイプラインを形成するパイプライン形成工程と、形成されたパイプラインをトンネルの壁方向に移動させるパイプライン移動工程と、パイプライン移動工程の後、既に形成されているパイプラインに併設するようにパイプラインを形成する併設パイプライン形成工程とを備えたことを特徴とするものである。 (1) The pipeline laying method according to the first embodiment of the present invention is a pipeline laying method in which a plurality of pipelines are formed in the tunnel by connecting the single pipes carried into the tunnel by welding. A pipeline forming step of forming a pipeline in a place other than the carriage traveling rail installed in the tunnel, a pipeline moving step of moving the formed pipeline toward the tunnel wall, and the pipeline And a side-by-side pipeline forming step of forming a pipeline so as to be side by side with the already formed pipeline after the moving step.
(2)本発明の第2の形態に係るパイプライン敷設方法は、上記(1)に記載のものにおいて、併設パイプライン形成工程の後、併設パイプライン形成工程によって形成されたパイプラインに対してパイプライン移動工程を行い、さらに併設パイプライン形成工程を行うことにより三条以上のパイプラインを形成することを特徴とするものである。 (2) The pipeline laying method according to the second aspect of the present invention is the one described in (1) above, with respect to the pipeline formed by the side-by-side pipeline formation step after the side-by-side pipeline formation step. A pipeline moving process is performed, and a pipeline forming process is further performed to form three or more pipelines.
(3)本発明の第3の形態に係るパイプライン敷設方法は、上記(1)または(2)に記載のものにおいて、パイプライン形成工程は、形成されたパイプラインを載置するための架台を形成する架台形成工程と、複数の単管を軸方向に溶接して連結する溶接工程と、溶接されたパイプラインを前記架台に載置する載置工程とを備えたことを特徴とするものである。 (3) The pipeline laying method according to the third aspect of the present invention is the one described in (1) or (2) above, wherein the pipeline forming step is a platform for placing the formed pipeline. A pedestal forming step, a welding step of welding and connecting a plurality of single pipes in the axial direction, and a placing step of placing the welded pipeline on the pedestal. It is.
(4)本発明の第4の形態に係るパイプライン敷設方法は、上記(1)〜(3)のいずれかに記載のものにおいて、併設パイプライン形成工程は、形成されたパイプラインを載置するための架台を形成する架台形成工程と、複数の単管を軸方向に溶接して連結する溶接工程と、溶接されたパイプラインを前記架台に載置する載置工程とを備えたことを特徴とするものである。 (4) The pipeline laying method according to the fourth aspect of the present invention is the method according to any one of the above (1) to (3), wherein the side-by-side pipeline formation step places the formed pipeline. A pedestal forming step for forming a pedestal for welding, a welding step for welding and connecting a plurality of single pipes in the axial direction, and a placing step for placing the welded pipeline on the pedestal. It is a feature.
(5)本発明の第5の形態に係るパイプライン敷設方法は、上記(3)または(4)に記載のものにおいて、架台形成工程は、トンネル内の既設の軌条上に台車を走行させて該台車によって前記架台の資材を搬入する資材搬入工程と、前記既設の軌条のレールのうちのトンネル内壁に近い側のレールを他方のレールを挟んで反対側に移設して前記既設の軌条幅よりも幅狭の新たな軌条を形成する軌条形成工程を含むことを特徴とするものである。 (5) The pipeline laying method according to the fifth aspect of the present invention is the method according to the above (3) or (4), wherein the gantry forming step includes running a carriage on an existing rail in the tunnel. The material carrying-in process of carrying in the material of the gantry by the carriage, and the rail closer to the tunnel inner wall of the existing rails of the rail is moved to the opposite side across the other rail, and from the existing rail width Includes a rail forming step for forming a new narrow rail.
(6)本発明の第6の形態に係るパイプライン敷設方法は、上記(3)〜(5)のいずれかに記載のものにおいて、架台は、脚部と、該脚部に支持されるトンネル径方向に延びるレール部と、該レール部上に該レール部に沿って移動可能な移動台とを備えてなるものであることを特徴とするものである。 (6) The pipeline laying method according to the sixth aspect of the present invention is the method according to any one of the above (3) to (5), wherein the gantry includes a leg portion and a tunnel supported by the leg portion. It is characterized by comprising a rail part extending in the radial direction, and a moving base movable on the rail part along the rail part.
(7)本発明の第7の形態に係るパイプライン敷設方法は、上記(6)に記載のものにおいて、架台を構成するレール部は、トンネル径方向に2分割できるように構成されていることを特徴とするものである。 (7) The pipeline laying method according to the seventh aspect of the present invention is the one described in (6) above, wherein the rail portion constituting the gantry is configured to be divided into two in the tunnel radial direction. It is characterized by.
(8)本発明の第8の形態に係るパイプライン敷設方法は、上記(3)〜(7)のいずれかに記載のものにおいて、パイプライン移動工程は、トンネル軸方向に設置された複数の架台上に載置されたパイプラインを、先端側の移動距離が長くなるように各架台位置で所定の距離ずつ強制移動させる強制移動工程を有することを特徴とするものである。 (8) The pipeline laying method according to the eighth aspect of the present invention is the method according to any one of the above (3) to (7), wherein the pipeline moving process includes a plurality of pipes installed in the tunnel axial direction. It has a forcible moving step of forcibly moving the pipeline placed on the gantry by a predetermined distance at each gantry position so that the moving distance on the tip side becomes long.
(9)本発明の第9の形態に係るパイプライン敷設方法は、上記(8)に記載のものにおいて、強制移動工程は、パイプラインの先端側から順に選択された複数の架台を一組としてこれら一組の架台ごとに強制移動を行なうこととし、前記選択された架台よりも後端側の架台においてはパイプラインが移動しないようにして前記強制移動を行なうことを特徴とするものである。 (9) The pipeline laying method according to the ninth aspect of the present invention is the method described in (8) above, wherein the forcible moving step is a set of a plurality of platforms selected in order from the front end side of the pipeline. The forcible movement is performed for each set of the gantry, and the forcible movement is performed so that the pipeline does not move in the gantry on the rear end side with respect to the selected gantry.
(10)本発明の第10の形態に係るパイプライン載置移動架台は、トンネル内に単管を溶接によって連結して複数条のパイプラインを形成するパイプライン敷設方法に用いるパイプライン載置移動架台であって、脚部と、該脚部に支持されてトンネル径方向に延びるレール部と、該レール部上にレールに沿って移動可能でかつ前記パイプラインを載置できる移動台とを備えたことを特徴とするものである。 (10) A pipeline placement moving platform according to a tenth aspect of the present invention is a pipeline placement movement used in a pipeline laying method in which a single pipe is connected by welding in a tunnel to form a plurality of pipelines. A pedestal comprising: a leg portion; a rail portion supported by the leg portion and extending in a tunnel radial direction; and a movable stand that is movable along the rail and on which the pipeline can be placed on the rail portion. It is characterized by that.
(11)本発明の第11の形態に係るパイプライン載置移動架台は、上記(10)に記載のものにおいて、架台を構成するレール部は、トンネル径方向に2分割できるように構成されていることを特徴とするものである。 (11) In the pipeline mounting mobile gantry according to the eleventh aspect of the present invention, the rail portion constituting the gantry is configured to be divided into two in the tunnel radial direction in the above (10). It is characterized by being.
本発明においては、トンネル内に敷設された台車走行用軌条内以外の場所にパイプラインを形成するパイプライン形成工程と、形成されたパイプラインをトンネルの壁方向に移動させるパイプライン移動工程と、パイプライン移動工程の後、既に形成されているパイプラインに併設するようにパイプラインを形成する併設パイプライン形成工程とを備えたことにより、狭隘なトンネル空間においても複数条のパイプラインを形成することができる。 In the present invention, a pipeline forming step of forming a pipeline in a place other than the carriage traveling rail laid in the tunnel, a pipeline moving step of moving the formed pipeline in the direction of the tunnel wall, After the pipeline moving process, a plurality of pipelines are formed even in a narrow tunnel space by including a pipeline forming process for forming a pipeline so as to be installed alongside the already formed pipeline. be able to.
[実施の形態1]
まず、本実施の形態に係るパイプライン敷設方法を概説すると、本実施の形態に係るパイプライン敷設方法は、一条目のパイプラインを台車が走行する軌条以外の場所に形成する一条目パイプライン形成工程と、形成された一条目のパイプラインをトンネルの壁方向に移動させるパイプライン移動工程と、二条目のパイプラインを形成する二条目パイプライン形成工程とを備えている。
そして、一条目パイプライン形成工程には、一条目のパイプラインを載置する架台を形成する架台形成工程と、単管をトンネル内に搬入する単管搬入工程と、搬入された単管を軸方向に突き合わせて溶接する溶接工程と、溶接された単管を架台に載置する載置工程が含まれる。
さらに、架台形成工程には、架台を形成するための資材をトンネル内に搬入する架台用資材搬入工程と、架台用資材搬入工程と平行して行なわれシールドトンネルに敷設された既設レールを単管搬入用の台車走行に使用するレールに盛り変えるレール盛変え工程と、架台用資材搬入工程で搬入された架台用資材を用いて架台を組立て設置する架台組立設置工程と、が含まれる。
なお、本実施の形態における一条目パイプライン形成工程は、本発明のパイプライン形成工程に相当し、また本実施の形態における二条目パイプライン形成工程は、本発明の併設パイプライン形成工程に相当する。
[Embodiment 1]
First, the pipeline laying method according to the present embodiment will be outlined. The pipeline laying method according to the present embodiment is formed by forming the first line pipeline at a place other than the rail where the carriage travels. A process, a pipeline moving process for moving the formed first pipeline in the direction of the tunnel wall, and a second pipeline forming process for forming the second pipeline.
The first line pipeline forming process includes a frame forming process for forming a frame on which the first line pipeline is placed, a single pipe carrying-in process for carrying a single pipe into the tunnel, and a single pipe that has been loaded. A welding process of butting in the direction and welding and a mounting process of mounting the welded single pipe on the gantry are included.
Furthermore, in the gantry forming process, a single material pipe is installed in the shield tunnel, which is carried out in parallel with the gantry material carrying-in process for carrying the material for forming the gantry into the tunnel, and the gantry material carrying-in process. There are included a rail refilling process for changing to rails used for carrying carts for carrying-in, and a gantry assembling and installing process for assembling and installing the gantry using the gantry materials carried in the gantry material carrying-in process.
The first line pipeline forming process in the present embodiment corresponds to the pipeline forming process of the present invention, and the second line pipeline forming process in the present embodiment corresponds to the side-by-side pipeline forming process of the present invention. To do.
上記の説明は、本実施の形態に係るパイプライン敷設方法を上位概念から順に説明したものであるが、本実施の形態に係るパイプライン敷設方法を構成する各工程を時系列的に並べて整理すると、以下のようになる。
一条目のパイプラインを載置する架台を形成するための架台用資材をトンネル内に搬入する架台用資材搬入工程、シールドトンネルに敷設された既設レールを単管搬入用の台車走行に使用するレールに盛り変えるレール盛変え工程、架台用資材搬入工程で搬入された架台用資材を用いて架台を組立て設置する架台組立設置工程、単管をトンネル内に搬入する単管搬入工程、搬入された単管を軸方向に突き合わせて溶接する溶接工程と、溶接された単管を架台に載置する載置工程と、形成された一条目のパイプラインをトンネルの片側の内壁側へ移動するパイプライン移動工程と、二条目のパイプラインを形成する二条目パイプライン形成工程。
図1〜図13は本発明の一実施の形態に係るパイプライン敷設方法の説明図であり、該方法を時系列的に説明したものである。以下、図1〜図13を参照しながら本実施の形態の各工程を詳細に説明する。
The above description is an explanation of the pipeline laying method according to the present embodiment in order from the higher concept, but when the steps constituting the pipeline laying method according to the present embodiment are arranged in time series and arranged. It becomes as follows.
Rails used to mount the platform material to form the platform on which the first pipeline is placed into the tunnel, and to use the existing rails laid in the shield tunnel for single-carriage cart travel The rail refilling process, the rack assembly and installation process for assembling and mounting the rack using the rack material loaded in the rack material loading process, the single pipe loading process for loading a single pipe into the tunnel, Welding process for welding the pipes in the axial direction, mounting process for placing the welded single pipe on the gantry, and pipeline movement for moving the formed first line pipeline to the inner wall side on one side of the tunnel A process and a second line pipeline forming process for forming a second line pipeline.
FIGS. 1-13 is explanatory drawing of the pipeline laying method which concerns on one embodiment of this invention, and demonstrates this method in time series. Hereafter, each process of this Embodiment is demonstrated in detail, referring FIGS.
1.架台用資材搬入工程
図1は工事前のトンネル内の状態を示す説明図であり、図1(a)がトンネル軸方向に垂直な断面を示し、図1(b)が図1(a)の矢視A−A線断面図を示している。
図1に示すように、工事前の状態では、シールドトンネル1内にトンネル軸方向に敷設された平行に延びる二本の既設レール3a、3bからなる幅広の既設軌条3が設置されている。
架台用資材搬入工程では、図2に示すように、既設軌条3上に台車5を走行させ、この台車5によって一条目のパイプラインを載置する架台12を形成するための架台用資材7をトンネル内に搬入し、所定の場所に載置する。
この例では、架台12をトンネル軸方向に18m置きに設置するので、各架台12を形成するのに必要な資材をこの間隔ごとにトンネル内に載置する。
1. Fig. 1 is an explanatory view showing a state in the tunnel before construction, in which Fig. 1 (a) shows a cross section perpendicular to the tunnel axis direction, and Fig. 1 (b) shows Fig. 1 (a). The arrow AA sectional view is shown.
As shown in FIG. 1, in the state before construction, a wide existing
In the frame material carrying-in step, as shown in FIG. 2, the vehicle 5 is moved on the existing
In this example, since the
2.レール盛変え工程
レール盛変え工程は、シールドトンネル1に敷設された既設軌条3を単管搬入用の台車を走行させるのに使用する幅狭の新設軌条9に盛り変える工程である。
図3は、このレール盛変え工程を説明する説明図であり、図3(a)がトンネル軸方向に垂直な断面を示し、図3(b)が図3(a)の矢視B−B線断面図を示している。
なお、レール盛変え工程と架台用資材搬入工程とは同時に進行する。以下、図3に基づいてこれらの工程を説明する。
2. Rail refilling step The rail refilling step is a step of refilling the existing
3A and 3B are explanatory diagrams for explaining the rail refilling process, in which FIG. 3A shows a cross section perpendicular to the tunnel axis direction, and FIG. 3B is a view taken along the line B-B in FIG. A line sectional view is shown.
Note that the rail refilling process and the frame material carrying-in process proceed simultaneously. Hereinafter, these steps will be described with reference to FIG.
前述したように、既設軌条3上を走行する台車5で架台用資材7を搬入し、トンネル奥から順に所定の場所に載置する。架台用資材7を載置した箇所についてはそれ以降台車5を走行させる必要がないので、2本の既設レール3a、3bのうちの中央側のレール3bをそのまま残し、トンネル内壁寄りのレール3a(図中左側のレール3a)を撤去する。そして、撤去したレール3aを中央のレール3bの反対側に設置し、パイプライン形成用の単管を搬入等するための単管搬送台車25を走行させる新設軌条9を新に形成する。この単管搬送台車25の走行用の新設軌条9の幅は、図3に示すように既設の軌条の幅よりも幅狭に設定されている。
なお、この例では盛変え前の既設軌条3の幅W1は610mmであったのに対して盛変え後の新設軌条9の幅W2は410mmである。
このように、単管搬送台車25を走行させるための幅狭の新設軌条9を新に形成することによって、図3(b)に示すようにトンネルの図中左側には架台設置スペースが確保できると共に図中右側には幅狭の軌条を形成でき、単管搬送台車25の走行が可能となる。この新設軌条9では、主にはパイプライン形成用の資材や溶接機材の搬送をする。
As described above, the
In this example, the width W1 of the existing
Thus, by newly forming a narrow
3.架台組立設置工程
架台組立設置工程は、架台用資材搬入工程で搬入された架台用資材7を用いて架台12を組立てて設置する工程である。この工程では、図4に示すように、新設軌条9上を架台組立作業に使用する機材11を走行させて作業を行なうので極めて効率的な作業が可能である。
図4には組立後の状態の架台12が示されている。架台12は図4に示すように、脚部13と、該脚部13に支持されてトンネル径方向に延びるレール部15と、該レール部15上にレール部15に沿って移動可能に設置された移動台17とを備えている。移動台17には単管を支持するための半割り状の支持部材19が設置されている。移動台17の移動をスムーズにするために移動台17とレール部15の摺動面はフッ素樹脂加工を行なった。
なお、レール部15は軸方向すなわちトンネル径方向で2分割できるようになっている。
架台12の設置に際しては、脚部13をトンネル地面21に立設すると共にレール部15の一端を、トンネル内壁を形成しているセグメントの受部23に固定する。
3. Mount assembly installation process The mount assembly installation process is a process of assembling and installing the
FIG. 4 shows the
The
When installing the
架台12は、組立完成状態において、移動台17の上に単管または単管が連結されたパイプラインが載置され、移動台17と共にレール部15上をトンネル径方向移動できる。
なお、レール部15には移動台17の移動を規制するためのピンを挿入できるようになっており、このピンを挿入することによって移動台17を移動可能状態にしたり移動不能状態にしたりできるようになっている。
また、レール部15におけるトンネル中心側の端部15aには、後述するパイプライン移動工程においてジャッキ35の反力をとるための後述の反力部材を設置できるようになっている。
架台12の組立設置が完了すると、一条目のパイプラインの形成を行なう。
In the assembled state, the
It should be noted that a pin for restricting the movement of the movable table 17 can be inserted into the
Further, a reaction force member (to be described later) for taking a reaction force of the
When the assembly and installation of the
4.単管搬入工程
単管搬入工程は、図5に示すように、レール盛変え工程で新に形成された新設軌条9上に単管搬送台車25を走行させ、この単管搬送台車25を利用して単管27を搬入し、所定の本数(例えば3本)搬入すると、以下の溶接工程によって溶接を行なう。
4). Single Pipe Carry-In Process As shown in FIG. 5, the single pipe carry-in process is performed by running a single-
5.溶接工程
単管搬送台車25を利用して搬入した単管27はトンネル内に設置してある吊具29によって吊り上げ、吊り上げた単管同士を軸方向に突き合わせて溶接する。この溶接作業は、図6に示すように、作業員によって行なうが、溶接される単管27はトンネルのほぼ中央部に配置されており、溶接作業スペースを十部に確保できる。
また、この溶接作業においては、溶接する単管27の側方に新設軌条9が敷設されているので、図7に示すように、この新設軌条9上を利用して溶接機材31を搬送して作業を行なうことができるので、非常に効率的な作業ができる。
この点、従来のパイプライン敷設方法であれば、単管27を搬入した状態で軌条が単管27で塞がれてしまうので、溶接作業においては溶接機材31を溶接する単管27の直ぐ近くまで持っていくには人力によらなければならず、また、溶接作業においてもキャプタイヤーケーブルを延長して行なう必要があった。
これに比較して、本実施の形態では、溶接する単管27の直ぐ近くまで溶接機材31を搬送可能であるため、溶接作業にまつわる種々の作業効率を著しく向上できる。
5. Welding process
The
In this welding operation, since the
In this regard, with the conventional pipeline laying method, the rail is blocked by the
Compared to this, in the present embodiment, since the
6.載置工程
載置工程は溶接された単管27を、図7に示すように架台12上の移動台17に載置する工程である。
単管搬入工程と、溶接工程と、載置工程は、所定本数の単管27ごとにトンネル入口側に向かって移動しながら繰り返し行なわれ、これによって一条目のパイプラインが形成される。
6). Placement Step The placement step is a step of placing the welded
The single pipe carrying-in process, the welding process, and the placing process are repeated while moving toward the tunnel entrance side for each predetermined number of
7.パイプライン移動工程
パイプライン移動工程は、形成された一条目パイプライン33をトンネルの片側の内壁側(図中左側)へ移動する工程である。
パイプライン移動工程においては、架台12の移動台17上に載置された一条目パイプライン33を、トンネル奥側から順に所定の寸法ずつ徐々に順次移動する。
具体的には以下のようにする。
7). Pipeline moving process The pipeline moving process is a process of moving the formed first-
In the pipeline moving process, the first-
Specifically:
移動に際しては、一条目パイプライン33の側部をジャッキ35によって押圧するので、図8に示すように、レール部15の先端に反力部材37を設置してジャッキ35の反力を取れるようにする。
図9はパイプライン移動工程の説明図である。
以下の説明では一条目パイプライン33を溶接時の載置位置からトンネル内壁方向に400mm移動する場合を例に挙げて説明する。
まず、トンネル奥側から順に第1〜第6の6個の架台12を一つの組として捉え、この6個一組の架台単位で移動を行なう。
第6の架台12について移動台17が動かないようにピン固定する。そして、第1〜第5の架台12のレール部15の先端に反力部材37を設置し、まず第1の架台12において、反力部材37に反力を取りながらジャッキ35によってパイプラインの側面を押して強制移動させる。パイプラインの側面を押すことにより、移動台17に載置されたパイプラインが移動台17と共に移動する。この時の第1架台12での強制的に移動させる移動距離は80mmとし、第2〜第5の架台12においては自由な移動に任せる。
When moving, the side portion of the
FIG. 9 is an explanatory diagram of the pipeline moving process.
In the following description, the case where the first-
First, the first to sixth six
The
次に、第1、第2の架台12においてジャッキ35によってそれぞれ80mmの強制移動を行なう。つまり、第1の架台12においては当初の設置位置より160mmの強制移動を行い、第2の架台12においては当初の設置位置より80mmの距離になるように強制移動を行なう。なお、第2の架台12においては第1の架台12において最初の強制移動を行なったとき、この移動に伴ってすでにトンネル径方向への移動が行なわれているので、第2の架台12における実際の強制移動距離は80mmよりも少ない。このとき、第3〜第5の架台12では自由な移動にまかせる。
Next, the first and
次に、第1、第2、第3の架台12で、それぞれ80mmの強制移動を行なう。このとき、第4、第5の架台12では自由な移動にまかせる。
次に、第1〜第4の架台12でそれぞれ80mmの強制移動を行なう。このとき、第5の架台12では自由な移動に任せる。
次に、第1〜第5のそれぞれの架台12で80mmの強制移動を行なう。これによって、第1の位置ではで400mmの移動が行なわれたことになり、予定した移動が完了したことになる。そして、第1の移動台17をピン固定して移動台17がトンネル中心方向に移動しないように固定する。
Next, the first, second, and
Next, a forced movement of 80 mm is performed on each of the first to fourth mounts 12. At this time, the
Next, the first to
第1の架台12にいた作業者は第6の架台12に移動し、第6の移動台17の固定ピンを外し、第7の移動台17を固定し、さらに第6の架台12に戻って第6の架台12での強制移動を担当する。このようにして、第2〜第6の架台12での80mmずつの移動を、前述した第1〜第5の架台12での移動と同様に行なう。
以上のようにして、最終的には一条目パイプライン33を全長に亘ってトンネル内壁側に400mm移動させる。
The operator who was on the
As described above, the first-
このように、本実施の形態においては一条目パイプライン33の移動を所定の長さを単位として徐々に行なうようにしたので、安全でかつ確実なパイプラインの移動が実現できる。
As described above, in the present embodiment, since the movement of the
一条目のパイプラインのトンネル内壁側への移動が完了すると、各架台12におけるレール部15の中央側の部分を撤去する。これによって、図10に示すように、トンネル中央部に広い空間を確保でき、後述する二条目パイプライン敷設作業を円滑に行なえるようになる。
When the movement of the first line of the pipeline toward the inner wall of the tunnel is completed, the portion on the center side of the
6.二条目パイプライン形成工程
二条目パイプライン形成工程は、単管搬送台車25によって二条目パイプライン用の単管39を所定本数ずつ搬入する工程(図11参照)と、搬入した所定本数の単管39を吊具29によって吊り上げて軸方向に溶接する工程(図12参照)と、溶接した単管39をEPS(発泡スチロール)架台41に載置する工程(図13参照)と、載置した単管39と新に搬入して溶接した単管39を溶接して二条目パイプライン40を形成する工程とを有している。
6). Second line pipeline forming process The second line pipeline forming process includes a process of carrying a predetermined number of
この二条目パイプライン形成工程は、基本的には従来の一条のパイプライン形成の場合と同様に行なうことが可能である。
この点、従来の方法で二条目のパイプラインを形成しようとしても、二条目のパイプラインの形成に用いる単管の搬入さえ行なうことができなかった。これに対して、本実施の形態によれば二条目のパイプラインの形成を一条目のパイプラインの形成と同様に行なうことができるのである。
なお、二条目のパイプラインの形成において、溶接されたパイプを載置する架台41は、載置したパイプをもはや移動する必要がないので、図13に示すようにEPS(発泡スチロール)を用いた固定架台を用いている。
以上のようにして第2パイプラインをトンネル入口側に向かって順次形成してゆく。
This second-line pipeline forming step can be basically performed in the same manner as in the conventional one-line pipeline formation.
In this regard, even if an attempt was made to form a second pipeline by a conventional method, it was not possible to carry in even a single pipe used for forming the second pipeline. On the other hand, according to the present embodiment, the second pipeline can be formed in the same manner as the first pipeline.
In the formation of the second pipeline, the
As described above, the second pipeline is sequentially formed toward the tunnel entrance side.
一条目パイプライン及び二条目パイプライン40の形成が完了すると、トンネル内にモルタルを注入にして工事を完了する。
以上のように、本実施の形態によれば従来であれば不可能であった狭隘なトンネル空間において二条のパイプラインを形成することができる。
When the formation of the first and
As described above, according to the present embodiment, it is possible to form a two-line pipeline in a narrow tunnel space that was impossible in the past.
なお、上記の実施の形態1においては、狭隘なトンネル空間に二条のパイプラインを形成する場合を説明したが、この技術は一条のパイプラインを形成する場合にも適用できる。
つまり、従来の一条のパイプラインの形成方法では、一条目のパイプライン用の単管を台車で搬入し、これを軌条上に載置してゆくため、例えば搬入した3本の単管を溶接するに際しては溶接機材を溶接する単管の直ぐ横にもってくることができないため、人力での搬送や長いキャプタイヤーケーブルを用いた作業になる。
この点、上記の本実施の形態1で説明したように、台車の軌条からずらして単管を載置できるように軌条を盛り変えて形成すれば、パイプの溶接効率を向上させることができる。
In the first embodiment described above, the case where two strips of pipelines are formed in a narrow tunnel space has been described. However, this technique can also be applied to the case where one strip of pipelines is formed.
In other words, in the conventional method for forming a single pipeline, a single pipe for the first pipeline is carried by a carriage and placed on a rail. For example, three carried single pipes are welded. When doing this, it is impossible to bring the welding equipment right next to the single pipe to be welded.
In this regard, as described in the first embodiment, the welding efficiency of the pipe can be improved if the rail is reshaped so that the single pipe can be placed by shifting from the rail of the carriage.
[実施の形態2]
また、上記の実施の形態1においては、一条目パイプライン33を形成した後、二条目パイプライン40を形成して作業を終了するため、全体として二条のパイプラインを形成する例である。
しかし、本発明はこれに限られるものではなく、二条目パイプライン40を形成した後に、三条目パイプラインを形成したり、さらに、それ以上の条数のパイプラインを形成したりするようにしてもよい。
[Embodiment 2]
Moreover, in said
However, the present invention is not limited to this, and after the
図14は、例えば三条目パイプライン43を形成した場合の工事完了状態を示す模式図である。この例では、上記実施の形態で説明したように一条目パイプライン33を形成した後、一条目パイプライン形成工程と同様にして二条目パイプライン40を架台12上に形成し、その後、上記実施の形態で説明した二条目パイプライン形成工程と同様にして三条目パイプライン43をEPS架台41上に形成する。
また、図14の例では架台12上に二条のパイプラインを形成しているが、シールドトンネル1の径が大きいような場合には、架台12上に三条以上のパイプラインを形成するようにしてもよい。
FIG. 14 is a schematic diagram illustrating a construction completion state when, for example, a third-
Further, in the example of FIG. 14, two pipelines are formed on the
また、三条以上のパイプラインを形成する場合において、図14に示した例では架台12をシールドトンネル1の片側に設ける例を示しているが、本発明はこれに限られるものではなく、例えば図15に示すように、シールドトンネル1の左右両側に架台12を設置して図中左側の架台12上に一条目パイプライン33を形成し、図中右側の架台12上に二条目パイプライン40を形成し、さらにシールドトンネル1の中央部に三条目パイプライン43をEPS架台41上に形成するようにしてもよい。
なお、図15に示す例では、両側に形成した架台12上に各一条のパイプラインを形成した例を示したが、架台12をシールドトンネル1の両側に設置する場合においても、図14に示した例のように架台12上に複数条のパイプラインを形成するようにしてもよい。
Further, in the case of forming a pipeline of three or more lines, the example shown in FIG. 14 shows an example in which the
In the example shown in FIG. 15, an example in which a single pipeline is formed on the
1 シールドトンネル
3 既設軌条
3a、3b 既設レール
5 台車
7 架台用資材
9 新設軌条
11 機材
12 架台
13 脚部
15 レール部
17 移動台
19 支持部材
21 トンネル地面
33 受部
25 単管搬送台車
27 単管
29 吊具
31 溶接機材
33 一条目パイプライン
35 ジャッキ
37 反力部材
39 単管
40 二条目パイプライン
41 EPS架台
43 三条目パイプライン
DESCRIPTION OF
Claims (9)
トンネル内に敷設された台車走行用軌条内以外の場所にパイプラインを形成するパイプライン形成工程と、形成されたパイプラインをトンネルの壁方向に移動させるパイプライン移動工程と、パイプライン移動工程の後、既に形成されているパイプラインに併設するようにパイプラインを形成する併設パイプライン形成工程とを備えたことを特徴とするパイプライン敷設方法。 A pipeline laying method for forming a plurality of pipelines in the tunnel by connecting and forming single pipes carried into the tunnel by welding,
A pipeline forming process for forming a pipeline in a place other than the carriage traveling rail installed in the tunnel, a pipeline moving process for moving the formed pipeline toward the tunnel wall, and a pipeline moving process. A pipeline laying method comprising: a pipeline forming step of forming a pipeline so as to be installed alongside a pipeline that has already been formed.
In the forcible moving process, a plurality of platforms selected in order from the front end side of the pipeline are set as a set, and the forcible movement is performed for each set of the platforms. In the platform on the rear end side than the selected platform, The pipeline laying method according to claim 8, wherein the forced movement is performed so that the pipeline does not move.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2009026947A JP5195482B2 (en) | 2008-02-19 | 2009-02-09 | Pipeline laying method |
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2008036808 | 2008-02-19 | ||
| JP2008036808 | 2008-02-19 | ||
| JP2009026947A JP5195482B2 (en) | 2008-02-19 | 2009-02-09 | Pipeline laying method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2009222226A JP2009222226A (en) | 2009-10-01 |
| JP5195482B2 true JP5195482B2 (en) | 2013-05-08 |
Family
ID=41239212
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2009026947A Active JP5195482B2 (en) | 2008-02-19 | 2009-02-09 | Pipeline laying method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP5195482B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6042646B2 (en) * | 2012-06-28 | 2016-12-14 | 高砂熱学工業株式会社 | How to replace piping |
| JP6036333B2 (en) * | 2013-01-23 | 2016-11-30 | Jfeエンジニアリング株式会社 | Pipeline laying method |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3293234B2 (en) * | 1993-05-19 | 2002-06-17 | 石川島播磨重工業株式会社 | Piping installation device |
| JP2601804Y2 (en) * | 1993-12-10 | 1999-12-06 | 株式会社高田工業所 | Transport equipment for piping in tunnels |
| JP3604209B2 (en) * | 1995-09-18 | 2004-12-22 | Jfe工建株式会社 | Piping construction method in tunnel |
| JPH09253842A (en) * | 1996-03-27 | 1997-09-30 | Tokyo Gas Co Ltd | Pipeline welding construction method |
| JP3633721B2 (en) * | 1996-06-10 | 2005-03-30 | 東京瓦斯株式会社 | How to lay pipes in the cavern |
| JP4057763B2 (en) * | 2000-05-19 | 2008-03-05 | 新日鉄エンジニアリング株式会社 | Segment supply method when laying gas pipes |
-
2009
- 2009-02-09 JP JP2009026947A patent/JP5195482B2/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| JP2009222226A (en) | 2009-10-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| RU2516667C2 (en) | Device and system of pipeline installation | |
| KR102471085B1 (en) | Method and system for forming a pipeline | |
| JP5195482B2 (en) | Pipeline laying method | |
| JP2013194747A (en) | Casting method of stream tunnel and carrying device of stream tunnel pipe | |
| JP5850734B2 (en) | Non-open-cut method segment and shield tunnel and non-open-cut method | |
| JP6036333B2 (en) | Pipeline laying method | |
| JP4859697B2 (en) | Transverse moving equipment at start shaft | |
| JP6242219B2 (en) | Saddle piping method | |
| JP3239280U (en) | Carrier for pipe work | |
| JP2002188756A (en) | Method and apparatus for laying pipe in tunnel | |
| JP3897514B2 (en) | How to load a segment | |
| JP3244927B2 (en) | Penstock pipe roundness holding device | |
| JPH0637777B2 (en) | Underground pipe construction method and vehicle for underground pipe construction | |
| JP2560782B2 (en) | Underground bending device | |
| JP6574575B2 (en) | Pipe transport device and pipe connection method in a mine | |
| JP2012185099A (en) | Nondestructive inspection method and nondestructive inspection device for butt welding part of pipe on facility ship | |
| JP2016008650A (en) | Manufacturing method of new pipeline and pipe material | |
| JP4933881B2 (en) | Tube transport carriage and tube laying method | |
| JP2021147861A (en) | Conveyance device and assembly method of new structure in existing structure | |
| JP2967773B2 (en) | Pipe laying equipment | |
| CN205065143U (en) | Assemble device in big shaped steel bifurcated pipe hole | |
| CN121025290B (en) | Mould vehicle, lining pipe and use method of matching structure of mould vehicle and lining pipe | |
| EP0854007B1 (en) | Method and installation for providing a piping string in a building | |
| KR20260031573A (en) | Spiral welded steel pipe insertion propulsion system and existing pipe rehabilitation method in existing pipe | |
| JP2818840B2 (en) | Pipe laying method and pipe laying equipment in shield construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20110304 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20120813 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20120821 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20120918 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20130108 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20130121 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20160215 Year of fee payment: 3 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 5195482 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |