Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP5575619B2 - Construction structure of composite viaduct and construction method of the composite viaduct - Google Patents
[go: Go Back, main page]

JP5575619B2 - Construction structure of composite viaduct and construction method of the composite viaduct - Google Patents

Construction structure of composite viaduct and construction method of the composite viaduct Download PDF

Info

Publication number
JP5575619B2
JP5575619B2 JP2010265346A JP2010265346A JP5575619B2 JP 5575619 B2 JP5575619 B2 JP 5575619B2 JP 2010265346 A JP2010265346 A JP 2010265346A JP 2010265346 A JP2010265346 A JP 2010265346A JP 5575619 B2 JP5575619 B2 JP 5575619B2
Authority
JP
Japan
Prior art keywords
steel box
box girder
composite
cft
beam steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010265346A
Other languages
Japanese (ja)
Other versions
JP2012117217A (en
Inventor
一朗 杉本
学 池田
望 谷口
淳一 平尾
忠久 山本
衛 山下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Railway Technical Research Institute
Original Assignee
Obayashi Corp
Railway Technical Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Railway Technical Research Institute filed Critical Obayashi Corp
Priority to JP2010265346A priority Critical patent/JP5575619B2/en
Publication of JP2012117217A publication Critical patent/JP2012117217A/en
Application granted granted Critical
Publication of JP5575619B2 publication Critical patent/JP5575619B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、鉄道、道路の複合高架橋の構築構造およびその複合高架橋の施工方法に関するものである。   The present invention relates to a construction structure of a composite viaduct for railways and roads and a construction method for the composite viaduct.

従来、高架橋の建設にあたって、鋼とコンクリートを用いた複合構造物の積極的活用は少なかった。また、都市内では、狭隘な箇所での施工が要求されるケースが増えてきている。   Conventionally, in the construction of viaducts, there has been little active utilization of composite structures using steel and concrete. In cities, there are increasing cases where construction is required in narrow spaces.

図16は従来の高架橋の側面図、図17はその正面図である。   FIG. 16 is a side view of a conventional viaduct, and FIG. 17 is a front view thereof.

これらの図において、100は高架橋、101はRC柱、102はRC柱101上に構築されるRC(鉄筋コンクリート)〔又はPC(プレストレストコンクリート)〕梁、103は高架橋100上を走行する車両である。   In these drawings, 100 is a viaduct, 101 is an RC column, 102 is an RC (steel reinforced concrete) beam (or PC (prestressed concrete)) built on the RC column 101, and 103 is a vehicle traveling on the viaduct 100.

特許第3837390号公報Japanese Patent No. 3837390

「橋梁と基礎」,株式会社建設図書,2009年11月号,第43巻,第11号(通巻第515号)“Bridge and Foundation”, Construction Books, Inc., November 2009, Volume 43, Volume 11 (Volume 515)

従来の高架橋の施工・構築方法では、時間・費用がかかりすぎるという課題があった。特に、狭隘な箇所での施工には、時間・費用がさらに増大する傾向が強い。   The conventional viaduct construction / construction method has a problem that it takes too much time and money. In particular, construction in a narrow area tends to further increase time and cost.

本発明は、上記状況に鑑みて、短い期間で施工でき、かつ費用を低減して構築することができる、複合高架橋の構築構造およびその複合高架橋の施工方法を提供することを目的とする。   In view of the above circumstances, an object of the present invention is to provide a composite viaduct construction structure and a composite viaduct construction method that can be constructed in a short period of time and can be constructed at a reduced cost.

本発明は、上記目的を達成するために、
〔1〕コンクリートを充填した鋼管からなるCFT柱と、このCFT柱上に配置され水平方向に移動させて構築可能な上層梁鋼箱桁を含む上層梁鋼箱桁部材と、前記CFT柱と前記上層梁鋼箱桁部材とを接合するCFT柱接合部と、前記上層梁鋼箱桁部材上に配置されるコンクリートからなる合成梁床版とを具備する複合高架橋の構築構造であって、前記上層梁鋼箱桁部材は、前記上層梁鋼箱桁と、この上層梁鋼箱桁内に配置されるコンクリートブロックと、このコンクリートブロックの上面に設置される上部アンカーフレームとからなり、前記CFT柱接合部は、前記CFT柱に設置されたアンカーフレームと前記上部アンカーフレームをアンカーボルトで固定することを特徴とする。
In order to achieve the above object, the present invention provides
[1] co and CFT column consisting of the steel pipe packed with Nkurito, the upper beam steel box girder member including an upper beam steel box girder that can be constructed this CFT disposed on the pillar is moved in the horizontal direction, the CFT pillar and the upper beam steel box girder A composite viaduct construction structure comprising a CFT column joint for joining members and a composite beam floor slab made of concrete arranged on the upper beam steel box girder member, wherein the upper beam steel box girder member is the upper layer It consists of a beam steel box girder, a concrete block arranged in the upper beam steel box girder, and an upper anchor frame installed on the upper surface of the concrete block, and the CFT column joint is formed by an anchor frame installed on the CFT column. The upper anchor frame is fixed with an anchor bolt .

〕上記〔〕記載の複合高架橋の構築構造において、前記アンカーボルトにグラウトを施工することを特徴とする。 [ 2 ] The composite viaduct construction structure according to [ 1 ], wherein a grout is applied to the anchor bolt.

〕上記〔〕記載の複合高架橋の構築構造において、前記グラウトを施工した後、前記上部アンカーフレームの上部にグラウトを施工することを特徴とする。 [ 3 ] The composite viaduct construction structure according to [ 2 ], wherein after the grout is constructed, the grout is constructed on the upper anchor frame.

4〕コンクリートを充填した鋼管からなるCFT柱を建て込み、このCFT柱上に上層梁鋼箱桁を含む上層梁鋼箱桁部材を水平方向に移動させて配置し、前記CFT柱と前記上層梁鋼箱桁部材とを接合し、前記上層梁鋼箱桁部材上にコンクリートからなる合成梁床版を配置する複合高架橋の施工方法であって、前記CFT柱の上部に設置されたアンカーフレームと前記上層梁鋼箱桁とを、この上層梁鋼箱桁を水平方向に移動させることにより位置合わせし、前記上層梁鋼箱桁内にコンクリートブロックと上部アンカーフレームを配置し、前記アンカーフレームと前記上部アンカーフレームとをアンカーボルトで固定することを特徴とする。 [4] concrete like an anchor the CFT columns consisting of the steel tube filled with, this CFT on pillars upper beam steel box girder member including an upper beam steel box girder is moved horizontally arranged, the upper beam steel box girder member and the CFT Column And a composite viaduct construction method in which a composite beam floor slab made of concrete is disposed on the upper beam steel box girder member, the anchor frame installed on the upper part of the CFT pillar and the upper beam steel box girder, The upper-layer beam steel box girder is aligned by moving in the horizontal direction, a concrete block and an upper anchor frame are arranged in the upper-layer beam steel box girder, and the anchor frame and the upper anchor frame are fixed with anchor bolts. And

〕上記〔〕記載の複合高架橋の施工方法において、前記アンカーボルトにグラウトを施工することを特徴とする。 [ 5 ] The composite viaduct construction method according to [ 4 ], wherein grout is constructed on the anchor bolt.

〕上記〔〕記載の複合高架橋の施工方法において、前記グラウトを施工した後、前記アンカーフレームの上部にグラウトを施工することを特徴とする。 [ 6 ] The composite viaduct construction method according to [ 5 ], wherein after the grout is constructed, the grout is constructed on an upper portion of the anchor frame.

〕上記〔〕記載の複合高架橋の施工方法において、前記CFT柱の建て込みおよび前記上層梁鋼箱桁の配置は、高架橋施工予定位置近傍に配置された作業機械により行うことを特徴とする。 [ 7 ] The composite viaduct construction method according to [ 4 ] above, wherein the CFT column is erected and the upper beam beam box girders are arranged by a work machine arranged in the vicinity of the planned location of the viaduct construction.

〕上記〔〕記載の複合高架橋の施工方法において、前記作業機械を移動させ、前記CFT柱の建て込みと前記上層梁鋼箱桁の配置を順次行うことを特徴とする。 [ 8 ] The composite viaduct construction method according to [ 7 ], wherein the work machine is moved, and the CFT column is built and the upper beam steel box girders are sequentially arranged.

本発明によれば、狭隘な箇所での施工でも、期間を短縮し、かつ費用を低減して構築することができる複合高架橋の構築構造およびその複合高架橋の施工方法を提供することができる。すなわち、剛性の高いCFT柱の活用により、柱・基礎の数を減少させることができるので、コストの低減を図ることができる。また、合成梁とCFT柱との接合構造により、狭隘な箇所での施工も可能であり、施工期間を短縮しコストを縮減することができる。   ADVANTAGE OF THE INVENTION According to this invention, the construction structure of the composite viaduct and the construction method of the composite viaduct which can be constructed by shortening the period and reducing the cost even in construction in a narrow place can be provided. That is, since the number of columns and foundations can be reduced by utilizing a highly rigid CFT column, cost can be reduced. In addition, the joint structure between the composite beam and the CFT column enables construction in a narrow area, shortening the construction period and reducing the cost.

特に、本発明のCFT柱を用いた複合高架橋の施工方法では、コンクリートの固化を待たずにCFT柱に荷重をかけることができるので、柱建て込みからの作業時間を短縮することができ、急速施工が可能になる利点がある。   In particular, in the construction method of the composite viaduct using the CFT pillar of the present invention, it is possible to apply a load to the CFT pillar without waiting for the solidification of the concrete. There is an advantage that construction is possible.

本発明の複合高架橋の施工の第1工程を示す模式図である。It is a schematic diagram which shows the 1st process of construction of the composite viaduct of this invention. 本発明の複合高架橋の施工の第2工程を示す模式図である。It is a schematic diagram which shows the 2nd process of construction of the composite viaduct of this invention. 本発明の複合高架橋の施工の第3工程を示す模式図である。It is a schematic diagram which shows the 3rd process of construction of the composite viaduct of this invention. 本発明の複合高架橋の施工の第4工程を示す模式図である。It is a schematic diagram which shows the 4th process of construction of the composite viaduct of this invention. 本発明の複合高架橋の施工の第5工程を示す模式図である。It is a schematic diagram which shows the 5th process of construction of the composite viaduct of this invention. 本発明の複合高架橋の施工の第6工程を示す模式図である。It is a schematic diagram which shows the 6th process of construction of the composite viaduct of this invention. 本発明の実施例を示す複合高架橋の側面図である。It is a side view of the composite viaduct which shows the Example of this invention. 本発明の実施例を示す複合高架橋の正面図である。It is a front view of the composite viaduct which shows the Example of this invention. 本発明の実施例を示す複合高架橋のCFT柱の先端部の斜視図である。It is a perspective view of the front-end | tip part of the composite high bridge | crosslinking CFT pillar which shows the Example of this invention. 本発明の実施例を示す複合高架橋のCFT柱接合部の施工の第1工程を示す図である。It is a figure which shows the 1st process of construction of the composite high bridge | crosslinking CFT column junction part which shows the Example of this invention. 本発明の実施例を示す複合高架橋のCFT柱接合部の施工の第2工程を示す図である。It is a figure which shows the 2nd process of construction of the composite high bridge | crosslinking CFT column junction part which shows the Example of this invention. 本発明の実施例を示す複合高架橋のCFT柱接合部の施工の第3工程を示す図である。It is a figure which shows the 3rd process of construction of the composite high bridge | crosslinking CFT column junction part which shows the Example of this invention. 本発明の実施例を示す複合高架橋のCFT柱接合部の施工の第4工程を示す図である。It is a figure which shows the 4th process of construction of the composite high bridge | crosslinking CFT column junction part which shows the Example of this invention. 本発明の実施例を示す複合高架橋のCFT柱接合部の施工の第5工程を示す図である。It is a figure which shows the 5th process of construction of the composite high bridge | crosslinking CFT column junction part which shows the Example of this invention. 本発明の実施例を示す複合高架橋の施工時の模式図である。It is a schematic diagram at the time of construction of the composite viaduct which shows the Example of this invention. 従来の高架橋を示す側面図である。It is a side view which shows the conventional viaduct. 従来の高架橋を示す正面図である。It is a front view which shows the conventional viaduct.

本発明の複合高架橋の構築構造は、コンクリートを充填した鋼管からなるCFT柱と、このCFT柱上に配置され水平方向に移動させて構築可能な上層梁鋼箱桁を含む上層梁鋼箱桁部材と、前記CFT柱と前記上層梁鋼箱桁部材とを接合するCFT柱接合部と、前記上層梁鋼箱桁部材上に配置されるコンクリートからなる合成梁床版とを具備する複合高架橋の構築構造であって、前記上層梁鋼箱桁部材は、前記上層梁鋼箱桁と、この上層梁鋼箱桁内に配置されるコンクリートブロックと、このコンクリートブロックの上面に設置される上部アンカーフレームとからなり、前記CFT柱接合部は、前記CFT柱に設置されたアンカーフレームと前記上部アンカーフレームをアンカーボルトで固定するThe construction structure of the composite viaduct of the present invention includes a CFT column made of a steel pipe filled with concrete, an upper beam steel box girder member including an upper beam steel box girder arranged on the CFT column and movable in the horizontal direction, and the CFT column A composite viaduct construction structure comprising a CFT column joint that joins a column and the upper beam steel box girder member, and a composite beam floor slab made of concrete disposed on the upper beam steel box girder member , the upper beam steel box The girder member is composed of the upper beam steel box girder, a concrete block disposed in the upper beam steel box girder, and an upper anchor frame installed on the upper surface of the concrete block, and the CFT column joint portion is connected to the CFT column. The installed anchor frame and the upper anchor frame are fixed with anchor bolts .

以下、本発明の実施の形態について詳細に説明する。   Hereinafter, embodiments of the present invention will be described in detail.

図1〜図6は本発明の複合高架橋の施工の各工程を示す模式図であり、図1(a)〜図6(a)は正面図、図1(b)〜図6(b)は側面図である。   1-6 is a schematic diagram which shows each process of the construction of the composite viaduct of this invention, FIG.1 (a)-FIG.6 (a) are front views, FIG.1 (b)-FIG.6 (b) are FIG. It is a side view.

図1〜図6において、1は作業規制区域、2は車両、3は高架橋施工予定位置に設置されるCFT(Concrete Filled Tubular)柱、4はCFT柱3上に構築される合成梁である。   In FIG. 1 to FIG. 6, 1 is a work regulation area, 2 is a vehicle, 3 is a CFT (Concrete Filled Tubular) column installed at a viaduct construction planned position, and 4 is a composite beam constructed on the CFT column 3.

そこで、高架橋の施工は以下のような手順により行われる。   Therefore, the construction of the viaduct is performed according to the following procedure.

(1)まず、図1に示すように、車両2の走行領域等を含む作業規制区域1を避けるようにして作業領域を設定する。   (1) First, as shown in FIG. 1, the work area is set so as to avoid the work regulation area 1 including the travel area of the vehicle 2 and the like.

(2)図2に示すように、作業機械(図示なし)により高架橋施工予定位置にCFT柱3の建て込みを一部行う。   (2) As shown in FIG. 2, the CFT pillar 3 is partially built at the viaduct construction planned position by a work machine (not shown).

(3)図3に示すように、CFT柱3上に合成梁4を作業機械(図示なし)により構築する。   (3) As shown in FIG. 3, the composite beam 4 is constructed on the CFT column 3 by a work machine (not shown).

(4)次いで、図4に示すように、上記(2)でCFT柱3の建て込みを行っていない位置まで作業機械(図示なし)を移動させ、CFT柱3の建て込みを行う。   (4) Next, as shown in FIG. 4, the work machine (not shown) is moved to a position where the CFT pillar 3 is not built in (2), and the CFT pillar 3 is built.

(5)図5に示すように、上記(4)で建て込んだCFT柱3上に作業機械(図示なし)により合成梁4を構築する。   (5) As shown in FIG. 5, the composite beam 4 is constructed by a work machine (not shown) on the CFT pillar 3 built in (4) above.

(6)図6に示すように、車両2の線路を構築した高架橋上に切り替える。   (6) As shown in FIG. 6, the vehicle 2 is switched over to the viaduct constructed.

図7は本発明の実施例を示す複合高架橋の側面図、図8はその複合高架橋の正面図、図9は本発明の実施例を示す複合高架橋のCFT柱の先端部の斜視図である。   FIG. 7 is a side view of a composite viaduct showing an embodiment of the present invention, FIG. 8 is a front view of the composite viaduct, and FIG. 9 is a perspective view of a tip portion of a CFT column of the composite viaduct showing an embodiment of the present invention.

これらの図において、11は高架橋、12はCFT柱であり、このCFT柱12は、図9に示すように、コンクリート12Aを充填した鋼管12Bからなり、高い剛性を持ち、急速施工が可能である。13はCFT柱12上に構築される上層梁鋼箱桁部材、14は合成梁床版(合成梁からなる床版)であり、この上層梁鋼箱桁部材13と合成梁床版14によって図6に示す合成梁4を形成している。15は高架橋11上を走行する車両、16はCFT柱接合部である。 In these drawings, 11 is a viaduct and 12 is a CFT column. As shown in FIG. 9, this CFT column 12 is made of a steel pipe 12B filled with concrete 12A, has high rigidity, and can be rapidly constructed. . 13 upper beam steel box girder member built on CFT pillars 12, 14 is a synthetic beam floor slab (slab consisting of composite beam), synthesis shown in FIG. 6 and the upper beam steel box girder member 13 by the composite beam slab 14 A beam 4 is formed. Reference numeral 15 denotes a vehicle traveling on the viaduct 11, and 16 denotes a CFT column joint.

本発明に用いるCFT柱12は、上記したように、コンクリート12Aを充填した鋼管12Bからなり、高い剛性を有しており、かつ従来のRC柱に比べて強度が高く、したがって、設置する本数を減少させることができる。例えば、従来のRC柱を6本で構成していたところを、CFT柱4本に代えることができる。   As described above, the CFT column 12 used in the present invention is made of the steel pipe 12B filled with the concrete 12A, has high rigidity, and has a higher strength than the conventional RC column. Can be reduced. For example, the place where the conventional RC pillar is composed of six can be replaced with four CFT pillars.

このように、CFT柱を活用することにより、柱・基礎の数を減少させることができ、コストの低減を図ることができる。   Thus, by utilizing the CFT pillars, the number of pillars / foundations can be reduced, and the cost can be reduced.

また、本発明のCFT柱を用いた複合高架橋の施工方法では、急速施工が可能である。すなわち、従来のRC柱を用いた高架橋の施工方法では、RC柱を打設後コンクリートが固化するまでに1週間程度を要し、その間はRC柱に荷重をかけることができないため、コンクリートが固化するまで作業を中断せざるを得なかった。一方、本発明のCFT柱を用いた複合高架橋の施工方法では、鋼管を使用し、その鋼管は溶接やボルトを使用して接合することができるため、コンクリートの固化を待たずにCFT柱に荷重をかけることができ、作業を中断する必要がない。そのため、柱建て込みからの大幅な作業時間の短縮が可能になる。   Moreover, in the construction method of the composite viaduct using the CFT pillar of the present invention, rapid construction is possible. That is, in the conventional viaduct construction method using RC columns, it takes about one week for the concrete to solidify after placing the RC columns, and during that time it is impossible to apply a load to the RC columns, so the concrete is solidified. I had to suspend my work until. On the other hand, in the construction method of the composite viaduct using the CFT column of the present invention, a steel pipe is used, and the steel pipe can be joined using welding or a bolt, so that the load is applied to the CFT column without waiting for solidification of the concrete. Without having to interrupt the work. For this reason, it is possible to greatly shorten the work time from the pillar construction.

次に、上記図1〜6で説明した複合高架橋の施工方法における、CFT柱とその上に構築される合成梁との接続について説明する。   Next, the connection between the CFT column and the composite beam constructed thereon in the composite viaduct construction method described with reference to FIGS.

図10〜図14は本発明の実施例を示す複合高架橋のCFT柱接合部の施工方法(アンカーフレーム方式)の説明図である。   FIGS. 10-14 is explanatory drawing of the construction method (anchor frame system) of the composite viaduct CFT column junction part which shows the Example of this invention.

(1)まず、図10に示すように、CFT柱21の建て込みを行う。つまり、工場において、上端にアンカーフレーム22を設けた鋼管を、現場に搬入し、コンクリートを打設する。   (1) First, as shown in FIG. 10, the CFT pillar 21 is built. That is, in a factory, a steel pipe provided with an anchor frame 22 at the upper end is carried into the site and concrete is laid.

(2)図11に示すように、CFT柱21のアンカーフレーム22上に上層梁鋼箱桁23Aを載せる。この上層梁鋼箱桁23Aは、図11(a)に示すような長尺状の鋼箱桁として形成されており、その断面は、図11(b)に示すように四角形状に形成されている。この上層梁鋼箱桁23AをCFT柱21のアンカーフレーム22上で水平移動させ、アンカーフレーム22と位置合わせする。   (2) As shown in FIG. 11, the upper beam steel box girder 23 </ b> A is placed on the anchor frame 22 of the CFT column 21. This upper beam steel box girder 23A is formed as a long steel box girder as shown in FIG. 11 (a), and its cross section is formed in a quadrangular shape as shown in FIG. 11 (b). The upper beam steel box girder 23 </ b> A is moved horizontally on the anchor frame 22 of the CFT pillar 21 and aligned with the anchor frame 22.

(3)図12に示すように、上層梁鋼箱桁23A内にコンクリートブロック24とその上に上部アンカーフレーム25とを設置する。つまり、図12(a),(b)に示すように、上層梁鋼箱桁23A内に配置した四角形状のコンクリートブロック24の上面に、図12(c)に示すような等間隔に配置された孔25Aが形成されたリング状の上部アンカーフレーム25を配置することにより、上層梁鋼箱桁部材23とする。なお、上層梁鋼箱桁23Aの上面には開口部が設けられているため、上層梁鋼箱桁23Aの配置後にコンクリートブロック24および上部アンカーフレーム25を設置することが可能になっている。   (3) As shown in FIG. 12, the concrete block 24 and the upper anchor frame 25 are installed on it in the upper beam steel box girder 23A. That is, as shown in FIGS. 12A and 12B, holes arranged at equal intervals as shown in FIG. 12C are formed on the upper surface of the rectangular concrete block 24 arranged in the upper beam steel box girder 23A. By arranging the ring-shaped upper anchor frame 25 formed with 25A, the upper beam steel box girder member 23 is obtained. In addition, since the opening part is provided in the upper surface of upper-layer beam steel box girder 23A, it is possible to install the concrete block 24 and the upper anchor frame 25 after arrangement | positioning of upper-layer beam steel box girder 23A.

(4)図13に示すように、CFT柱21のアンカーフレーム22とコンクリートブロック24と上部アンカーフレーム25とを貫通させてアンカーボルト26を設置し、グラウト27の施工を行い、上層梁鋼箱桁部材23をCFT柱21へ強固に固定する。   (4) As shown in FIG. 13, anchor bolts 26 are installed through the anchor frame 22, the concrete block 24, and the upper anchor frame 25 of the CFT pillar 21, and the grout 27 is constructed. Is firmly fixed to the CFT pillar 21.

(5)そして、図14に示すように、上層梁鋼箱桁部材23にグラウト28を施工し、その上層梁鋼箱桁部材23上に合成梁床版29を施工して、合成梁を完成させる。   (5) Then, as shown in FIG. 14, a grout 28 is constructed on the upper beam steel box girder member 23, and a composite beam floor slab 29 is constructed on the upper beam steel box girder member 23 to complete the composite beam.

このように構成することにより、CFT柱21に対して上層梁鋼箱桁部材23と合成梁床版29とからなる合成梁を強固に固定することができる。   By comprising in this way, the composite beam which consists of the upper beam steel box girder member 23 and the composite beam floor slab 29 with respect to the CFT pillar 21 can be firmly fixed.

図15は本発明の実施例を示す複合高架橋の施工時の模式図であり、図15(a)はその平面図、図15(b)は上層梁鋼箱桁の右方の断面図、図15(c)は上層梁鋼箱桁の分岐部の断面の一例を示す図である。   FIG. 15 is a schematic view of the construction of the composite viaduct showing an embodiment of the present invention, FIG. 15 (a) is a plan view thereof, FIG. 15 (b) is a cross-sectional view on the right side of the upper beam steel box girder, FIG. c) is a figure which shows an example of the cross section of the branch part of an upper beam steel box girder.

図3に示すような先に構築した合成梁4に対して図5に示すような後から構築する合成梁4を接続する際には、添接継手を用いる。図15に示すように、CFT柱21へアンカーボルト26を用いて接合された上層梁鋼箱桁23Aは、添接板32,33およびボルト34,35からなる添接継手31によって互いに接続される。また、上層梁鋼箱桁23Aの分岐部と、上層梁横桁23Bとが添接板36とボルト37からなる添接継手によって接続される。   When connecting the composite beam 4 constructed later as shown in FIG. 5 to the composite beam 4 constructed earlier as shown in FIG. 3, an articulated joint is used. As shown in FIG. 15, the upper beam steel box girder 23 </ b> A joined to the CFT column 21 by using anchor bolts 26 is connected to each other by an attachment joint 31 including attachment plates 32 and 33 and bolts 34 and 35. Further, the branch portion of the upper beam beam box girder 23 </ b> A and the upper beam beam girder 23 </ b> B are connected to each other by an attachment joint including an attachment plate 36 and a bolt 37.

このように、本発明ではCFT柱と合成梁を強固に固定し、堅牢な複合高架橋を構築することができる。また、本発明は狭隘な箇所での施工が可能であり、施工期間の短縮とコストの縮減を図ることができる。   Thus, in the present invention, the CFT pillar and the composite beam can be firmly fixed, and a robust composite viaduct can be constructed. In addition, the present invention can be applied in a narrow area, and can shorten the construction period and reduce the cost.

なお、本発明は上記実施例に限定されるものではなく、本発明の趣旨に基づき種々の変形が可能であり、これらを本発明の範囲から排除するものではない。   In addition, this invention is not limited to the said Example, Based on the meaning of this invention, a various deformation | transformation is possible and these are not excluded from the scope of the present invention.

本発明の複合高架橋の構築構造およびその複合高架橋の施工方法は、狭隘な箇所でも短い期間で施工することができ、かつ費用を低減することができる複合高架橋の施工方法として利用可能である。   The construction structure of the composite viaduct and the construction method of the composite viaduct of the present invention can be used as a construction method of the composite viaduct which can be constructed in a short period even in a narrow place and can reduce the cost.

1 作業規制区域
2,15 車両
3,12,21 CFT柱
4 合成梁
11 高架橋
12A コンクリート
12B 鋼管
13,23 上層梁鋼箱桁部材
14,29 合成梁床版
16 CFT柱接合部
22 CFT柱のアンカーフレーム
23A 上層梁鋼箱桁
23B 上層梁横桁
24 コンクリートブロック
25 上部アンカーフレーム
25A 孔
26 アンカーボルト
27,28 グラウト
31 添接継手
32,33,36 添接板
34,35,37 ボルト
DESCRIPTION OF SYMBOLS 1 Work regulation area 2,15 Vehicle 3,12,21 CFT column 4 Composite beam 11 Viaduct 12A Concrete 12B Steel pipe 13,23 Upper beam steel box girder member 14,29 Composite beam floor slab 16 CFT column joint 22 CFT column anchor frame 23A Upper beam steel box girder 23B Upper beam girder 24 Concrete block 25 Upper anchor frame 25A Hole 26 Anchor bolt 27, 28 Grout 31 Joint joint 32, 33, 36 Joint plate 34, 35, 37 Bolt

Claims (8)

ンクリートを充填した鋼管からなるCFT柱と、該CFT柱上に配置され水平方向に移動させて構築可能な上層梁鋼箱桁を含む上層梁鋼箱桁部材と、前記CFT柱と前記上層梁鋼箱桁部材とを接合するCFT柱接合部と、前記上層梁鋼箱桁部材上に配置されるコンクリートからなる合成梁床版とを具備する複合高架橋の構築構造であって、前記上層梁鋼箱桁部材は、前記上層梁鋼箱桁と、該上層梁鋼箱桁内に配置されるコンクリートブロックと、該コンクリートブロックの上面に設置される上部アンカーフレームとからなり、前記CFT柱接合部は、前記CFT柱に設置されたアンカーフレームと前記上部アンカーフレームをアンカーボルトで固定することを特徴とする複合高架橋の構築構造。 And CFT columns consisting of steel tube filled with concrete, and an upper beam steel box girder member including an upper beam steel box girder that can be constructed by moving horizontally disposed on the CFT pillars, the front Symbol CFT columns and the upper beam steel box girder member and CFT column joint for joining, a building structure of a composite viaduct comprising a composite beam floor slab made of concrete arranged in front Symbol upper beam steel box girder member, said upper beam steel box girder member, said upper beam steel box A girder, a concrete block disposed in the upper beam steel box girder, and an upper anchor frame installed on an upper surface of the concrete block, wherein the CFT column joint portion includes the anchor frame installed on the CFT column and the anchor frame A composite viaduct construction structure characterized by fixing the upper anchor frame with anchor bolts. 請求項記載の複合高架橋の構築構造において、前記アンカーボルトにグラウトを施工することを特徴とする複合高架橋の構築構造。 2. The composite viaduct construction structure according to claim 1 , wherein a grout is applied to the anchor bolt. 請求項記載の複合高架橋の構築構造において、前記グラウトを施工した後、前記上部アンカーフレームの上部にグラウトを施工することを特徴とする複合高架橋の構築構造。 3. The composite viaduct construction structure according to claim 2 , wherein after the grout is constructed, a grout is constructed on an upper portion of the upper anchor frame. ンクリートを充填した鋼管からなるCFT柱を建て込み、該CFT柱上に上層梁鋼箱桁を含む上層梁鋼箱桁部材を水平方向に移動させて配置し、前記CFT柱と前記上層梁鋼箱桁部材とを接合し、前記上層梁鋼箱桁部材上にコンクリートからなる合成梁床版を配置する複合高架橋の施工方法であって、前記CFT柱の上部に設置されたアンカーフレームと前記上層梁鋼箱桁とを、該上層梁鋼箱桁を水平方向に移動させることにより位置合わせし、前記上層梁鋼箱桁内にコンクリートブロックと上部アンカーフレームを配置し、前記アンカーフレームと前記上部アンカーフレームとをアンカーボルトで固定することを特徴とする複合高架橋の施工方法。 Like an anchor the CFT columns consisting of steel tube filled with concrete, on the CFT pillars upper beam steel box girder member including an upper beam steel box girder is moved horizontally disposed, the front Symbol CFT pillars and the upper beam steel box girder member bonded, a method of constructing a composite viaduct placing composite beam floor slab made of concrete before Symbol upper beam steel box girder member, an anchor frame was placed on top of the CFT pillars and the upper beam steel box girder, the The upper-layer beam steel box girder is aligned by moving in the horizontal direction, a concrete block and an upper anchor frame are arranged in the upper-layer beam steel box girder, and the anchor frame and the upper anchor frame are fixed with anchor bolts. Construction method of composite viaduct. 請求項記載の複合高架橋の施工方法において、前記アンカーボルトにグラウトを施工することを特徴とする複合高架橋の施工方法。 5. The composite viaduct construction method according to claim 4 , wherein a grout is constructed on the anchor bolt. 請求項記載の複合高架橋の施工方法において、前記グラウトを施工した後、前記上部アンカーフレームの上部にグラウトを施工することを特徴とする複合高架橋の施工方法。 6. The composite viaduct construction method according to claim 5 , wherein after the grout is constructed, a grout is constructed on an upper portion of the upper anchor frame. 請求項記載の複合高架橋の施工方法において、前記CFT柱の建て込みおよび前記上層梁鋼箱桁の配置は、高架橋施工予定位置近傍に配置された作業機械により行うことを特徴とする複合高架橋の施工方法。 5. The construction method of a composite viaduct according to claim 4 , wherein the construction of the CFT pillar and the arrangement of the upper beam steel box girder are performed by a work machine arranged in the vicinity of the planned location of the viaduct construction. . 請求項記載の複合高架橋の施工方法において、前記作業機械を移動させ、前記CFT柱の建て込みと前記上層梁鋼箱桁の配置を順次行うことを特徴とする複合高架橋の施工方法。 The construction method of a composite viaduct according to claim 7 , wherein the work machine is moved, and the construction of the CFT pillar and the arrangement of the upper beam steel box girder are sequentially performed.
JP2010265346A 2010-11-29 2010-11-29 Construction structure of composite viaduct and construction method of the composite viaduct Active JP5575619B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010265346A JP5575619B2 (en) 2010-11-29 2010-11-29 Construction structure of composite viaduct and construction method of the composite viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010265346A JP5575619B2 (en) 2010-11-29 2010-11-29 Construction structure of composite viaduct and construction method of the composite viaduct

Publications (2)

Publication Number Publication Date
JP2012117217A JP2012117217A (en) 2012-06-21
JP5575619B2 true JP5575619B2 (en) 2014-08-20

Family

ID=46500375

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010265346A Active JP5575619B2 (en) 2010-11-29 2010-11-29 Construction structure of composite viaduct and construction method of the composite viaduct

Country Status (1)

Country Link
JP (1) JP5575619B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103306205A (en) * 2013-06-09 2013-09-18 中国十七冶集团有限公司 Construction method of longitudinal wet joint formwork of prefabricated T beam or box beam

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60258311A (en) * 1984-06-01 1985-12-20 株式会社 間組 Construction of high structure
JPH0719130B2 (en) * 1985-03-26 1995-03-06 コニカ株式会社 Image display device
JPH0718130B2 (en) * 1990-08-03 1995-03-01 首都高速道路公団 Compound pier
JPH08302619A (en) * 1995-04-30 1996-11-19 Nippon Steel Corp Bonding structure of composite members
JPH11264190A (en) * 1998-03-17 1999-09-28 Shimizu Corp Connection structure of filled steel tube concrete column
JP3924192B2 (en) * 2002-04-16 2007-06-06 前田建設工業株式会社 Bridge superstructure and substructure connection structure and its construction method
JP2010138643A (en) * 2008-12-12 2010-06-24 Ohbayashi Corp Construction method for column-beam joint part of viaduct, and viaduct

Also Published As

Publication number Publication date
JP2012117217A (en) 2012-06-21

Similar Documents

Publication Publication Date Title
CN103215894B (en) Portable interim prestressed stretch-draw anchor block
CN104032854B (en) Assembled T-shaped mixing coupled wall and construction method thereof
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN110184903B (en) A truss-type prefabricated pipe column assembled bridge pier
CN101629409B (en) Synchronous and continuous jacking construction method of long steel box girder
JP5680385B2 (en) Construction structure of composite viaduct and construction method of the composite viaduct
CN112282207A (en) A composite beam, a spliced beam and a subway station
JP5575619B2 (en) Construction structure of composite viaduct and construction method of the composite viaduct
JP4307109B2 (en) Beam-column joint structure
CN102155095B (en) Arrangement method of steel rib concrete steel bars of large metallurgical industry factory building
JP4363542B2 (en) Bridge construction method
JP4996370B2 (en) Frame assembly method and building frame
CN104032855A (en) Assembly-type cross-shaped mixed coupled wall and construction method thereof
JPH0633627B2 (en) New construction method on existing facility
JP5587149B2 (en) Construction structure of composite viaduct and construction method of the composite viaduct
JP2006265976A (en) Corrugated steel-plate web u component bridge and its construction method
JP5634839B2 (en) Construction structure of composite viaduct and construction method of the composite viaduct
CN104032862A (en) Assembly-type steel beam joint L-shaped mixed coupled wall and construction method thereof
CN203905215U (en) Assembled type steel beam joint straight-line-shaped blend coupled wall
CN103981810A (en) Steel tube arch main arch splicing and supporting system
JP2000104220A (en) Construction method of composite truss bridge
CN104032863B (en) Assembled in-line mixing coupled wall and construction method thereof
CN104047380B (en) Assembled girder steel seam T-shaped mixing coupled wall and construction method thereof
JP2011185013A (en) Construction method for portal rahmen structure of high bridge
CN203834740U (en) Assembly type steel beam joint T-shaped mixed limb wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130611

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140127

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140225

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140401

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140701

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140702

R150 Certificate of patent or registration of utility model

Ref document number: 5575619

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350