JP5609053B2 - Tunnel construction method and tunnel constructed by the construction method - Google Patents
[go: Go Back, main page]

JP5609053B2 - Tunnel construction method and tunnel constructed by the construction method - Google Patents

Tunnel construction method and tunnel constructed by the construction method Download PDF

Info

Publication number
JP5609053B2
JP5609053B2 JP2009228009A JP2009228009A JP5609053B2 JP 5609053 B2 JP5609053 B2 JP 5609053B2 JP 2009228009 A JP2009228009 A JP 2009228009A JP 2009228009 A JP2009228009 A JP 2009228009A JP 5609053 B2 JP5609053 B2 JP 5609053B2
Authority
JP
Japan
Prior art keywords
tunnel
existing
widening
section
end side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2009228009A
Other languages
Japanese (ja)
Other versions
JP2011074676A (en
Inventor
好信 居相
好信 居相
有佐 斎藤
有佐 斎藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2009228009A priority Critical patent/JP5609053B2/en
Publication of JP2011074676A publication Critical patent/JP2011074676A/en
Application granted granted Critical
Publication of JP5609053B2 publication Critical patent/JP5609053B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、既設トンネルを利用して新たなトンネルを構築するトンネルの構築工法及びその構築工法にて構築されたトンネルに関する。   The present invention relates to a tunnel construction method for constructing a new tunnel using an existing tunnel and a tunnel constructed by the construction method.

近年、車の通行量増加による渋滞を緩和するために、既設トンネルと並行するように新たなトンネルを構築したり、既設トンネルを拡幅したりして、車線を増加させる工事が行われている。   In recent years, in order to alleviate traffic congestion due to increased traffic of vehicles, new tunnels have been constructed in parallel with existing tunnels, or existing tunnels have been widened to increase lanes.

既設トンネルと並行するように新たなトンネルを構築する場合には、一般的に、図9に示すように、既設トンネルに影響を与えない距離、例えば、20m以上離れた位置に新たなトンネルを構築する。   When constructing a new tunnel in parallel with the existing tunnel, generally, as shown in FIG. 9, a new tunnel is constructed at a distance that does not affect the existing tunnel, for example, 20 m or more away. To do.

また、特許文献1には、既設トンネルに接続される新たなアプローチトンネルを構築する方法として、シールド機で徐々に既設トンネルに近づきながら、既設トンネルの側部を貫通させることにより、アプローチトンネルを構築する方法が開示されている。   In Patent Document 1, as a method for constructing a new approach tunnel connected to an existing tunnel, an approach tunnel is constructed by penetrating the side of the existing tunnel while gradually approaching the existing tunnel with a shield machine. A method is disclosed.

また、既設トンネルを拡幅する方法として、特許文献2には、既設トンネル内全線にわたってプロテクタを設置し、そのプロテクタ内に車を走行させながら、既設トンネルの内周面の地盤を掘削してトンネルを拡幅する方法が開示されている。   In addition, as a method for widening an existing tunnel, Patent Document 2 discloses that a protector is installed over the entire line in the existing tunnel, and the ground is excavated on the inner peripheral surface of the existing tunnel while the vehicle is running in the protector. A method of widening is disclosed.

特開2005−60968号公報JP 2005-60968 A 特開2002−4756号公報JP 2002-4756 A

しかしながら、上述した各方法には、それぞれ次のような問題点があった。   However, each method described above has the following problems.

既設トンネルと並行するように新たなトンネルを構築する方法では、新たなトンネル用道路Aを造るための用地(図9中のハッチング部分)を買収しなければならないが、特に、公共事業では用地買収に多大な時間と費用がかかってしまう。   In the method of constructing a new tunnel in parallel with the existing tunnel, the site for building a new tunnel road A (hatched part in Fig. 9) must be acquired. Takes a lot of time and money.

また、特許文献1に記載の方法では、シールド機を利用しているので、硬い地盤の地山を掘削できない。   Moreover, in the method of patent document 1, since the shield machine is utilized, the ground of a hard ground cannot be excavated.

さらに、特許文献2に記載の方法では、高価なプロテクタを既設トンネル内全線にわたって設置するため、施工費が高くなる。   Furthermore, in the method described in Patent Document 2, since the expensive protector is installed over the entire existing tunnel, the construction cost becomes high.

そこで、本発明は上記の点に鑑みてなされたものであり、地質の影響を受けることなく、経済性に優れたトンネルの構築工法及びその工法にて構築されたトンネルを提供することを目的とする。   Therefore, the present invention has been made in view of the above points, and aims to provide a tunnel construction method excellent in economic efficiency and a tunnel constructed by the construction method without being affected by geology. To do.

本発明は、既設トンネルを利用して新たなトンネルを地山内に山岳工法にて構築するトンネルの構築工法において、
前記既設トンネルの一端側坑口から前記地山内の、断面の大きさが変化する空間を形成しても地山の安定性が確保できる地点として決定された所定の地点までは、前記既設トンネルを拡幅することにより、前記既設トンネルよりも大きい断面を有する一定断面の第1の拡幅トンネル部を構築し、
前記所定の地点から、前記地山の深部に向けて次第に断面が大きくなる第2の拡幅トンネル部を、当該第2の拡幅トンネル部の断面が前記新たなトンネルを掘削できる大きさとなるまで構築し、
前記第2の拡幅トンネル部の終点から前記新たなトンネルの到達側坑口までは、前記第2の拡幅トンネル部より分岐する分岐トンネル部を構築することを特徴とする。
The present invention is a tunnel construction method in which a new tunnel is constructed in a natural mountain using an existing tunnel by a mountain construction method.
The existing tunnel is widened from one end of the existing tunnel to a predetermined point determined as a point where the stability of the natural mountain can be secured even if a space in the natural mountain where the size of the cross section changes is formed. By constructing a first widening tunnel portion having a constant cross section having a larger cross section than the existing tunnel,
A second widened tunnel portion having a cross section that gradually increases from the predetermined point toward the deep part of the natural ground is constructed until the cross section of the second widened tunnel portion is large enough to excavate the new tunnel. ,
A branch tunnel portion that branches from the second widened tunnel portion is constructed from the end point of the second widened tunnel portion to the arrival side wellhead of the new tunnel.

本発明によれば、既設トンネルの一端側坑口を拡幅してその拡幅した部分を新たなトンネルの坑口とすることにより、図9に示すように、従来の既設トンネルに並行するように新たなトンネルを構築する場合に比べて、新たなトンネル用道路Aを造るための買収用地が狭くてすむので、用地買収に係る時間と費用を低減することができる。   According to the present invention, as shown in FIG. 9, a new tunnel is formed in parallel with the existing existing tunnel by widening the one-end side wellhead of the existing tunnel and using the widened portion as a new tunnel wellhead. Compared to the construction of the road, the land for acquisition for building the new tunnel road A can be made narrower, so the time and cost for the land acquisition can be reduced.

また、所定の地点から新たなトンネルの到達側坑口までは、既設トンネルより分岐する分岐トンネル部を新たに構築するため、既設トンネル内での作業が無くなり、既設トンネル内を安全に車両を走行させることができる。   In addition, since a new branch tunnel branching from the existing tunnel is built from the predetermined point to the new tunnel arrival side wellhead, there is no work in the existing tunnel, and the vehicle is safely driven in the existing tunnel. be able to.

また、拡幅部及び分岐トンネル部を山岳工法で構築するので、軟弱な地盤だけでなく、硬い地盤の地山にも新たなトンネルを構築することができる。   In addition, since the widened portion and the branch tunnel portion are constructed by the mountain method, a new tunnel can be constructed not only on soft ground but also on solid ground.

また、本発明において、前記分岐トンネル部が前記既設トンネルの幅方向に所定の距離以上離れたら、前記分岐トンネル部を前記既設トンネルに対して平行となるように構築することとしてもよい。 In the present invention, the branch tunnel portion may be constructed to be parallel to the existing tunnel when the branch tunnel portion is separated by a predetermined distance or more in the width direction of the existing tunnel.

また、本発明は、既設トンネルを利用して新たなトンネルを地山内に山岳工法にて構築するトンネルの構築工法において、
前記既設トンネルの一端側坑口から前記地山内の所定の一端側地点までは、前記既設トンネルを拡幅することにより、前記既設トンネルよりも大きい断面を有する一端側拡幅トンネル部を構築する第一の拡幅工程と、
前記既設トンネルの他端側坑口から前記地山内の所定の他端側地点までは、前記既設トンネルを拡幅することにより、前記既設トンネルよりも大きい断面を有する他端側拡幅トンネル部を構築する第二の拡幅工程と、
前記所定の一端側地点から前記所定の他端側地点までは、両端部がそれぞれ前記一端側拡幅トンネル部及び前記他端側拡幅トンネル部より分岐した新たな分岐トンネル部を構築する分岐トンネル構築工程と、を備えること特徴とする。
Further, the present invention relates to a tunnel construction method in which a new tunnel is constructed in a natural mountain using an existing tunnel by a mountain construction method.
From the one end side wellhead of the existing tunnel to the predetermined one end side point in the natural ground, the first widening for constructing the one end side widening tunnel portion having a larger cross section than the existing tunnel by widening the existing tunnel Process,
From the other end side of the existing tunnel to the predetermined other end side point in the natural ground, the other end side widened tunnel portion having a larger cross section than the existing tunnel is constructed by widening the existing tunnel. Two widening steps;
A branch tunnel construction process for constructing a new branch tunnel section in which both ends are branched from the one end side widened tunnel section and the other end side widened tunnel section from the predetermined one end side point to the predetermined other end side point, respectively. It is characterized by providing these.

また、本発明において、前記第一の拡幅工程を実施した後に、前記分岐トンネル構築工程及び前記第二の拡幅工程を実施することとしてもよい。   Moreover, in this invention, after implementing said 1st widening process, it is good also as implementing the said branch tunnel construction process and said 2nd widening process.

本発明によれば、第一の拡幅工程を実施した後に、分岐トンネル構築工程を実施しながら第二の拡幅工程を実施することにより、迎え堀りを行うこととなるので、施工期間を大幅に短縮することができる。したがって、施工費を低減することができる。   According to the present invention, after carrying out the first widening step, the second widening step is carried out while carrying out the branch tunnel construction step, so that the construction period is greatly increased. It can be shortened. Therefore, construction costs can be reduced.

また、本発明において、前記第一の拡幅工程及び前記第二の拡幅工程を実施した後に、前記分岐トンネル構築工程を実施することとしてもよい。   Moreover, in this invention, it is good also as implementing the said branch tunnel construction process, after implementing said 1st widening process and said 2nd widening process.

本発明によれば、第一の拡幅工程を実施しながら第二の拡幅工程を実施することにより、迎え堀りを行うこととなるので、施工期間を大幅に短縮することができる。したがって、施工費を低減することができる。   According to the present invention, by performing the second widening step while performing the first widening step, the digging is performed, so that the construction period can be greatly shortened. Therefore, construction costs can be reduced.

また、本発明のトンネルは、上述したトンネルの構築工法にて構築されたことを特徴とする。   The tunnel of the present invention is constructed by the tunnel construction method described above.

本発明によれば、地質の影響を受けることなく、経済性に優れたトンネルの構築工法及びその工法にて構築されたトンネルを提供できる。   ADVANTAGE OF THE INVENTION According to this invention, the tunnel constructed | assembled by the construction method of the tunnel excellent in economical efficiency, and the construction method can be provided, without receiving to the influence of geology.

本発明の第一実施形態に係るトンネルの構築工法にて構築した新たなトンネルを示す平面図である。It is a top view which shows the new tunnel constructed | assembled with the construction method of the tunnel which concerns on 1st embodiment of this invention. 図1のA−A’断面図である。It is A-A 'sectional drawing of FIG. 図1のB−B’断面図である。It is B-B 'sectional drawing of FIG. 図1のC−C’断面図である。It is C-C 'sectional drawing of FIG. 図1のD−D’断面図である。It is D-D 'sectional drawing of FIG. 図1のF−F’断面図である。It is F-F 'sectional drawing of FIG. 分岐トンネル部の他端側坑口付近を示す正面図である。It is a front view which shows the other end side wellhead vicinity of a branch tunnel part. 本発明の第二実施形態に係るトンネルの構築工法にて構築した新たなトンネルを示す平面図である。It is a top view which shows the new tunnel constructed | assembled with the construction method of the tunnel which concerns on 2nd embodiment of this invention. 従来工法にて既設トンネルの側方に新たなトンネルを構築する状態を示す平面図であり、坑口付近の拡大図である。It is a top view which shows the state which builds a new tunnel to the side of the existing tunnel by a conventional construction method, and is an enlarged view of the vicinity of a wellhead.

以下、本発明の好ましい実施形態について図面を用いて詳細に説明する。下記の実施形態においては、本発明を道路トンネルに適用した場合について説明するが、これに限定されるものではなく、例えば、列車用トンネルにも適用可能である。   Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings. In the following embodiment, a case where the present invention is applied to a road tunnel will be described. However, the present invention is not limited to this, and can be applied to, for example, a train tunnel.

図1は、本発明の第一実施形態に係るトンネルの構築工法にて構築した新たなトンネル1を示す平面図である。
図1に示すように、トンネル1は、既設トンネル3を拡幅した拡幅トンネル部4と、この拡幅トンネル部4より分岐した分岐トンネル部5と、から構成される。以下に、このトンネル1の構築方法について説明する。最初に、拡幅トンネル部4の構築方法について説明し、次に、分岐トンネル部5の構築方法について説明する。
FIG. 1 is a plan view showing a new tunnel 1 constructed by the tunnel construction method according to the first embodiment of the present invention.
As shown in FIG. 1, the tunnel 1 includes a widened tunnel portion 4 that widens an existing tunnel 3 and a branch tunnel portion 5 that branches from the widened tunnel portion 4. Below, the construction method of this tunnel 1 is demonstrated. First, a construction method of the widening tunnel unit 4 will be described, and then a construction method of the branch tunnel unit 5 will be described.

拡幅トンネル部4は、既設トンネル3の一端側坑口2から所定の地点6までの区間に、既設トンネル3を拡幅することにより構築される。   The widening tunnel portion 4 is constructed by widening the existing tunnel 3 in a section from one end-side wellhead 2 of the existing tunnel 3 to a predetermined point 6.

拡幅作業を行う前に、拡幅トンネル部4の既設トンネル3内にプロテクタ7(図1中の左下がり斜線ハッチング部分)を設置して、車両が既設トンネル3内を走行できるようにする。安全上の観点からプロテクタ7を上記所定の地点6よりもやや坑内側に突出するように長めに設置することが望ましい。   Before performing the widening operation, a protector 7 (a hatched portion with a left-downward slanted line in FIG. 1) is installed in the existing tunnel 3 of the widening tunnel portion 4 so that the vehicle can travel in the existing tunnel 3. From the viewpoint of safety, it is desirable to install the protector 7 so as to protrude slightly inward from the predetermined point 6.

次に、発破や機械掘削等による山岳工法にて、既設トンネル3を拡幅することにより、既設トンネル3よりも大きい断面を有する空間S(後ほど図2に示す)を構築する。   Next, a space S (shown later in FIG. 2) having a larger cross section than the existing tunnel 3 is constructed by widening the existing tunnel 3 by a mountain method such as blasting or mechanical excavation.

拡幅トンネル部4は、断面の大きさが一定である第一区間Mと、断面の大きさが次第に大きくなる第二区間Nと、から構成される。最初に、第一区間Mの構築方法について説明し、次に、第二区間Nの構築方法について説明する。   The widening tunnel portion 4 includes a first section M having a constant cross-sectional size and a second section N in which the cross-sectional size gradually increases. First, the construction method of the first section M will be described, and then the construction method of the second section N will be described.

図2は、図1のA−A’断面図である。
図2に示すように、一端側坑口2より地山Eの深部に向かって、既設トンネル3を拡幅して、新たな車道8を設置可能な大きさの上記空間Sを有する第一区間Mを構築する。
2 is a cross-sectional view taken along line AA ′ of FIG.
As shown in FIG. 2, the first section M having the above-described space S having a size capable of installing a new roadway 8 by widening the existing tunnel 3 from the one end side wellhead 2 toward the deep part of the natural ground E. To construct.

第一区間Mは、一端側坑口2から地山Eの安定度が低い地層、例えば、未固結層又は風化層を通過する地点まで構築される。   The first section M is constructed from the one-end side wellhead 2 to a point where the stability of the natural ground E is low, for example, a point passing through an unconsolidated layer or a weathered layer.

第一区間Mの断面の大きさを一定にする理由は、地山Eの安定度が低い地層内に、断面の大きさが変化する空間Sを構築することは、技術的に可能であるが、落盤等が生ずる可能性が高くなるため、既設トンネル3を活線として利用していることを考慮して、危険性の少ない工法、すなわち、断面の大きさを一定にする工法を選択したためである。   The reason why the cross section size of the first section M is made constant is that it is technically possible to construct the space S in which the cross section size changes in the formation where the stability of the natural ground E is low. Because there is a high possibility of falling, etc., considering that the existing tunnel 3 is used as a live line, a construction method with a low risk, that is, a construction method with a constant cross-sectional size was selected. is there.

次に、第二区間Nの構築方法について説明する。   Next, the construction method of the second section N will be described.

図3及び図4は、それぞれ図1のB−B’、C−C’断面図である。
図3及び図4に示すように、第一区間Mの終点より更に地山Eの深部に向かって、既設トンネル3を拡幅して、深部へ進むにつれて断面が次第に大きくなる第二区間Nを構築する。
3 and 4 are BB ′ and CC ′ sectional views of FIG. 1, respectively.
As shown in FIG. 3 and FIG. 4, the existing tunnel 3 is widened from the end point of the first section M toward the deep part of the natural ground E, and a second section N whose section gradually increases as it goes deeper is constructed. To do.

第二区間Nは、第一区間Mの終点から地山Eの強度が確保できる安定した地層、例えば、中硬岩となりはじめる地点から構築される。これは、地山Eの強度が確保できる安定した地層内であれば、断面の大きさが変化する空間Sを構築しても、安全性を確保できるからである。   The second section N is constructed from a stable formation in which the strength of the natural ground E can be secured from the end point of the first section M, for example, a point where it becomes a medium hard rock. This is because safety can be ensured even if the space S in which the size of the cross section changes is constructed within a stable formation where the strength of the natural ground E can be ensured.

第二区間Nの終点付近では、既設トンネル3の側方に分岐トンネル5’(図1参照)を掘削できる程度の大きさの断面を形成する。   In the vicinity of the end point of the second section N, a cross section having a size enough to excavate the branch tunnel 5 ′ (see FIG. 1) is formed on the side of the existing tunnel 3.

上述したように、拡幅トンネル部4のうちの第一区間Mは、安定度が低い地層内に空間Sを安全に構築することを目的として設けられるものであって、第一区間Mと第二区間Nとの境界、すなわち、地山強度境界点6’は、地山E内の安定度が低い地層と強度が確保できる安定した地層との境目に設けられる。なお、この地山強度境界点6’は、地質調査等の結果に基づいて設計等により現場毎に適宜決定される。   As described above, the first section M of the widening tunnel portion 4 is provided for the purpose of safely constructing the space S in the formation with low stability. The boundary with the section N, that is, the natural ground strength boundary point 6 ′ is provided at the boundary between the low-level formation in the natural ground E and the stable formation capable of securing the strength. The natural ground strength boundary point 6 'is appropriately determined for each site by design or the like based on the result of geological survey or the like.

図5は、図1のD−D’断面図である。
図5に示すように、上記所定の地点6より更に地山Eの深部に向かって、既設トンネル3の側方に、拡幅トンネル部4より分岐する分岐トンネル部5を山岳工法により、既設トンネル3に対して離間する向きへ(図1参照)所定の角度で構築する。
5 is a cross-sectional view taken along the line DD ′ of FIG.
As shown in FIG. 5, a branch tunnel portion 5 that branches off from the widening tunnel portion 4 is formed by a mountain construction method on the side of the existing tunnel 3 toward the deep part of the natural mountain E from the predetermined point 6. (See FIG. 1) at a predetermined angle.

具体的には、上記所定の地点6では、既設トンネル3から側方へ、例えば、3m離れた位置から分岐トンネル5’の掘削を開始し、既設トンネル3に対して並行するように、かつ、地山Eの深部へ進むにつれて徐々に既設トンネル3より離れるように分岐トンネル部5を構築する。そして、既設トンネル3から側方へ水平距離で、例えば、約20m離れる位置に分岐トンネル5’が到達するまで、上記所定の角度で分岐トンネル5’を掘削する。   Specifically, at the predetermined point 6, excavation of the branch tunnel 5 ′ is started from the existing tunnel 3 to the side, for example, from a position 3 m away, and parallel to the existing tunnel 3, and The branch tunnel portion 5 is constructed so as to gradually move away from the existing tunnel 3 as it goes deeper in the natural ground E. Then, the branch tunnel 5 ′ is excavated at the predetermined angle until the branch tunnel 5 ′ reaches a horizontal distance from the existing tunnel 3, for example, about 20 m away.

図6は、図1のF−F’断面図である。
図6に示すように、分岐トンネル5’が既設トンネル3から約20m離れた位置に到達したら、分岐トンネル5’の向きを変えて、既設トンネル3に対して平行に掘削することにより、分岐トンネル部5を構築する。
6 is a cross-sectional view taken along the line FF ′ of FIG.
As shown in FIG. 6, when the branch tunnel 5 ′ reaches a position about 20 m away from the existing tunnel 3, the direction of the branch tunnel 5 ′ is changed and excavated in parallel to the existing tunnel 3, thereby Build part 5.

そして、分岐トンネル5’の他端側坑口11aを、図7に示すように、既設トンネル3の他端側坑口11bの側方に構築する。   And the other end side wellhead 11a of branch tunnel 5 'is constructed in the side of the other end side wellhead 11b of the existing tunnel 3, as shown in FIG.

その後、第一区間M内に新たな車道8を敷設し、拡幅した部分をトンネル1の一部として利用する。
最後に、プロテクタ7を撤去し、走行可能な状態とする。
Thereafter, a new carriageway 8 is laid in the first section M, and the widened portion is used as a part of the tunnel 1.
Finally, the protector 7 is removed to make it possible to run.

以上説明した本実施形態におけるトンネル1の構築工法によれば、既設トンネル3の一端側坑口2から地山E内の所定の地点6までは、既設トンネル3内にプロテクタ7を設置して既設トンネル3の拡幅作業を行うので、車両の通行止めはプロテクタ7を設置する短い期間ですみ、設置後は、常に車両を走行させながら拡幅作業を実施することができる。さらに、所定の地点6から地山Eの深部へ向かっては、拡幅トンネル部4から分岐される分岐トンネル部5を新たに構築するので、既設トンネル3内を通行止めにすることなく車両を安全に走行させることができる。   According to the construction method of the tunnel 1 in the present embodiment described above, the protector 7 is installed in the existing tunnel 3 from the one-end wellhead 2 of the existing tunnel 3 to the predetermined point 6 in the natural ground E. Therefore, the vehicle can be closed only for a short period of time when the protector 7 is installed. After the installation, the vehicle can always be run while the vehicle is running. Furthermore, from the predetermined point 6 toward the deep part of the natural ground E, the branch tunnel part 5 branched from the widening tunnel part 4 is newly constructed, so that the vehicle can be safely kept without blocking the existing tunnel 3. It can be run.

また、プロテクタ7を設置するのは、既設トンネル3の一端側坑口2から地山E内の所定の地点6までなので、既設トンネル3全線にプロテクタ7を設置する場合よりも、経済性に優れる。   Moreover, since the protector 7 is installed from the one-end wellhead 2 of the existing tunnel 3 to the predetermined point 6 in the ground E, it is more economical than the case where the protector 7 is installed on the entire existing tunnel 3 line.

また、一端側坑口2を拡幅してトンネル1を構築することにより、従来の既設トンネル3に並行するようにトンネルを構築する場合に比べて、新たなトンネル用道路A(図9参照)を造るための買収用地が狭くてすむので、特に、公共事業では、用地買収に係る時間と費用を低減することができる。   In addition, by constructing the tunnel 1 by widening the one-end side wellhead 2, a new tunnel road A (see FIG. 9) is constructed as compared with the case where the tunnel is constructed in parallel with the existing existing tunnel 3. In order to reduce the time and cost for acquiring a land, particularly in public works, it is possible to reduce the size of the land for acquisition.

また、拡幅トンネル部4及び分岐トンネル部5を山岳工法で構築するので、軟弱な地盤だけでなく、硬い地盤の地山Eにもトンネル1を構築することができる。   Moreover, since the widening tunnel part 4 and the branch tunnel part 5 are constructed by the mountain method, the tunnel 1 can be constructed not only on the soft ground but also on the ground E of the hard ground.

なお、本実施形態においては、既設トンネル3から水平方向に約20m離れた位置より分岐トンネル部5を平行に構築した場合について説明したが、この数値に限定されるものではなく、分岐トンネル部5は、分岐トンネル5’の掘削時に既設トンネル3に影響を及ぼさない程度に離れていればよく、地質調査等の結果に基づいて設計等により現場毎に適宜決定される。したがって、分岐トンネル部5を平行に構築することなく、既設トンネル3に対して離間する向きへ上記所定の角度をもって並行するように構築し続けてもよい。   In the present embodiment, the case where the branch tunnel portion 5 is constructed in parallel from a position approximately 20 m away from the existing tunnel 3 in the horizontal direction has been described. However, the present invention is not limited to this value. It is only necessary to be far enough so as not to affect the existing tunnel 3 when the branch tunnel 5 ′ is excavated, and is appropriately determined for each site by design based on the result of geological survey or the like. Therefore, the branch tunnel portion 5 may be continuously constructed in parallel with the predetermined angle in the direction away from the existing tunnel 3 without being constructed in parallel.

次に、本発明の第二実施形態について説明する。以下の説明において、第一実施形態に対応する部分には同一の符号を付して説明を省略し、主に相違点について説明する。第二実施形態は、他端側坑口11も一端側坑口2と同様に、既設トンネル3を拡幅工法にて拡幅し、この拡幅した部分を新たなトンネル21の一部として利用するものである。   Next, a second embodiment of the present invention will be described. In the following description, portions corresponding to the first embodiment are denoted by the same reference numerals, description thereof is omitted, and differences are mainly described. In the second embodiment, similarly to the one end side wellhead 2, the other end side wellhead 11 widens the existing tunnel 3 by the widening method, and uses this widened portion as a part of the new tunnel 21.

図8は、本発明の第二実施形態に係るトンネルの構築工法にて構築した新たなトンネル21を示す平面図である。
図8に示すように、トンネル21は、既設トンネル3を拡幅した第1拡幅トンネル部24a及び第2拡幅トンネル部24bと、これらの拡幅トンネル部24a、24b同士を連結する分岐トンネル部25と、から構成される。以下に、この新たなトンネル21の構築方法について説明する。
FIG. 8 is a plan view showing a new tunnel 21 constructed by the tunnel construction method according to the second embodiment of the present invention.
As shown in FIG. 8, the tunnel 21 includes a first widened tunnel portion 24a and a second widened tunnel portion 24b that widen the existing tunnel 3, and a branched tunnel portion 25 that connects these widened tunnel portions 24a and 24b, Consists of Below, the construction method of this new tunnel 21 is demonstrated.

まず、第1実施形態で示したように、既設トンネル3の一端側坑口2から所定の一端側地点26aまでを、既設トンネル3を拡幅することにより第1拡幅トンネル部24aを構築する(第一の拡幅工程)。   First, as shown in the first embodiment, the first widened tunnel portion 24a is constructed by widening the existing tunnel 3 from the one end side wellhead 2 of the existing tunnel 3 to the predetermined one end side point 26a (first). Widening process).

また、既設トンネル3の他端側坑口11から所定の他端側地点26bまで、第1実施形態と同様の工法にて、既設トンネル3を拡幅することにより第2拡幅トンネル部24bを構築する(第二の拡幅工程)。すなわち、第1拡幅トンネル部24aを構築するとともに、第2拡幅トンネル部24bを構築する、いわゆる、迎え堀りを行う。
なお、一端側の地山強度境界点26a’及び他端側の地山強度境界点26b’は、第1実施形態と同様に、地山E内の安定度が低い地層と強度が確保できる安定した地層との境目に設けられる。
Moreover, the 2nd widening tunnel part 24b is constructed | assembled by widening the existing tunnel 3 by the same construction method as 1st Embodiment from the other end side wellhead 11 of the existing tunnel 3 to the predetermined | prescribed other end side point 26b ( Second widening step). In other words, the first widening tunnel portion 24a is constructed, and the second widening tunnel portion 24b is constructed, so-called digging is performed.
It should be noted that the natural ground strength boundary point 26a 'on one end side and the natural ground strength boundary point 26b' on the other end side are stable and can secure a stratum and low strength in the natural ground E, as in the first embodiment. It is established at the boundary with the stratum.

第1及び第2拡幅トンネル部24a、24bを構築した後、第1実施形態と同様に、第1及び第2拡幅トンネル部24a、24b内からそれぞれ分岐トンネル25’を掘削し、地山Eの中央部付近で連結して分岐トンネル部25を構築する(分岐トンネル構築工程)。   After the construction of the first and second widened tunnel portions 24a and 24b, the branch tunnel 25 'is excavated from the first and second widened tunnel portions 24a and 24b, respectively, as in the first embodiment. The branch tunnel part 25 is constructed in the vicinity of the central part (branch tunnel construction process).

以上説明した本実施形態におけるトンネル21の構築工法によれば、迎え堀りを行うことにより、施工期間を大幅に短縮することができる。したがって、施工費を低減することができる。   According to the construction method of the tunnel 21 in the present embodiment described above, the construction period can be significantly shortened by performing the digging. Therefore, construction costs can be reduced.

また、一端側坑口2及び他端側坑口11を拡幅して新たなトンネル21を構築することにより、従来の既設トンネル3に並行するようにトンネルを構築する場合に比べて、トンネル21の両側で、新たなトンネル用道路A(図9参照)を造るための買収用地が狭くてすむので、特に、公共事業では、用地買収に係る時間と費用を低減することができる。   Further, by constructing a new tunnel 21 by widening the one end side wellhead 2 and the other end side wellhead 11, compared with the case where a tunnel is constructed in parallel with the existing existing tunnel 3, the both sides of the tunnel 21. Since the site for acquisition for building a new tunnel road A (see FIG. 9) can be small, particularly in public works, the time and cost for acquiring the site can be reduced.

さらに、上述した効果に加えて、本実施形態においても、第1実施形態と同様の効果を得ることができる。   Furthermore, in addition to the effects described above, the present embodiment can provide the same effects as those of the first embodiment.

なお、本実施形態においては、第一の拡幅工程及び第二拡幅工程を実施した後に、分岐トンネル構築工程を実施する場合について説明したが、これに限定されるものではなく、第一の拡幅工程を実施した後に、分岐トンネル構築工程及び第二の拡幅工程を実施してもよい。   In addition, in this embodiment, although the case where a branch tunnel construction process is implemented after implementing a 1st widening process and a 2nd widening process was demonstrated, it is not limited to this, The 1st widening process After carrying out, the branch tunnel construction step and the second widening step may be carried out.

1 トンネル
2 一端側坑口
3 既設トンネル
4 拡幅トンネル部
5 分岐トンネル部
5’分岐トンネル
6 所定の地点
6’地山強度境界点
7 プロテクタ
8 新たな車道
11 他端側坑口
11a 新たなトンネルの他端側坑口
11b 既設トンネルの他端側坑口
21 トンネル
24a 第1拡幅トンネル部
24b 第2拡幅トンネル部
25 分岐トンネル部
25’ 分岐トンネル
26a 所定の一端側地点
26b 所定の他端側地点
26a’ 一端側の地山強度境界点
26b’ 他端側の地山強度境界点
E 地山
M 第一区間
N 第二区間
S 空間
DESCRIPTION OF SYMBOLS 1 Tunnel 2 One end side wellhead 3 Existing tunnel 4 Widening tunnel part 5 Branch tunnel part 5 'Branch tunnel 6 Predetermined point 6' Ground strength boundary point 7 Protector 8 New roadway 11 Other end side wellhead 11a The other end of a new tunnel Side wellhead 11b Other end wellhead of existing tunnel 21 Tunnel 24a First widened tunnel portion 24b Second widened tunnel portion 25 Branch tunnel portion 25 'Branch tunnel 26a Predetermined one end side point 26b Predetermined other end side point 26a' One end side Natural ground strength boundary point 26b 'Natural ground strength boundary point E on the other end side Natural ground M First section N Second section S Space

Claims (6)

既設トンネルを利用して新たなトンネルを地山内に山岳工法にて構築するトンネルの構築工法において、
前記既設トンネルの一端側坑口から前記地山内の、断面の大きさが変化する空間を形成しても地山の安定性が確保できる地点として決定された所定の地点までは、前記既設トンネルを拡幅することにより、前記既設トンネルよりも大きい断面を有する一定断面の第1の拡幅トンネル部を構築し、
前記所定の地点から、前記地山の深部に向けて次第に断面が大きくなる第2の拡幅トンネル部を、当該第2の拡幅トンネル部の断面が前記新たなトンネルを掘削できる大きさとなるまで構築し、
前記第2の拡幅トンネル部の終点から前記新たなトンネルの到達側坑口までは、前記第2の拡幅トンネル部より分岐する分岐トンネル部を構築することを特徴とするトンネルの構築工法。
In the tunnel construction method that uses the existing tunnel to build a new tunnel in the natural mountain by the mountain method,
The existing tunnel is widened from one end of the existing tunnel to a predetermined point determined as a point where the stability of the natural mountain can be secured even if a space in the natural mountain where the size of the cross section changes is formed. By constructing a first widening tunnel portion having a constant cross section having a larger cross section than the existing tunnel,
A second widened tunnel portion having a cross section that gradually increases from the predetermined point toward the deep part of the natural ground is constructed until the cross section of the second widened tunnel portion is large enough to excavate the new tunnel. ,
A tunnel construction method characterized by constructing a branch tunnel portion that branches from the second widened tunnel portion from the end point of the second widened tunnel portion to the arrival side wellhead of the new tunnel.
前記分岐トンネル部が前記既設トンネルの幅方向に所定の距離以上離れたら、前記分岐トンネル部を前記既設トンネルに対して平行となるように構築することを特徴とする請求項1に記載のトンネルの構築工法。 2. The tunnel according to claim 1, wherein when the branch tunnel portion is separated by a predetermined distance or more in the width direction of the existing tunnel, the branch tunnel portion is constructed to be parallel to the existing tunnel. Construction method. 既設トンネルを利用して新たなトンネルを地山内に山岳工法にて構築するトンネルの構築工法において、
前記既設トンネルの一端側坑口から前記地山内の所定の一端側地点までは、前記既設トンネルを拡幅することにより、前記既設トンネルよりも大きい断面を有する一端側拡幅トンネル部を構築する第一の拡幅工程と、
前記既設トンネルの他端側坑口から前記地山内の所定の他端側地点までは、前記既設トンネルを拡幅することにより、前記既設トンネルよりも大きい断面を有する他端側拡幅トンネル部を構築する第二の拡幅工程と、
前記所定の一端側地点から前記所定の他端側地点までは、両端部がそれぞれ前記一端側拡幅トンネル部及び前記他端側拡幅トンネル部より分岐した新たな分岐トンネル部を構築する分岐トンネル構築工程と、を備えること特徴とするトンネルの構築工法。
In the tunnel construction method that uses the existing tunnel to build a new tunnel in the natural mountain by the mountain method,
From the one end side wellhead of the existing tunnel to the predetermined one end side point in the natural ground, the first widening for constructing the one end side widening tunnel portion having a larger cross section than the existing tunnel by widening the existing tunnel Process,
From the other end side of the existing tunnel to the predetermined other end side point in the natural ground, the other end side widened tunnel portion having a larger cross section than the existing tunnel is constructed by widening the existing tunnel. Two widening steps;
A branch tunnel construction process for constructing a new branch tunnel section in which both ends are branched from the one end side widened tunnel section and the other end side widened tunnel section from the predetermined one end side point to the predetermined other end side point, respectively. A tunnel construction method characterized by comprising:
前記第一の拡幅工程を実施した後に、前記分岐トンネル構築工程及び前記第二の拡幅工程を実施することを特徴とする請求項に記載のトンネルの構築工法。 The tunnel construction method according to claim 3 , wherein the branch tunnel construction step and the second widening step are performed after the first widening step. 前記第一の拡幅工程及び前記第二の拡幅工程を実施した後に、前記分岐トンネル構築工程を実施することを特徴とする請求項3に記載のトンネルの構築工法。   The tunnel construction method according to claim 3, wherein the branch tunnel construction step is performed after the first widening step and the second widening step. 請求項1〜のうち、何れか一項に記載のトンネルの構築工法にて構築されたことを特徴とするトンネル。 A tunnel constructed by the tunnel construction method according to any one of claims 1 to 5 .
JP2009228009A 2009-09-30 2009-09-30 Tunnel construction method and tunnel constructed by the construction method Expired - Fee Related JP5609053B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009228009A JP5609053B2 (en) 2009-09-30 2009-09-30 Tunnel construction method and tunnel constructed by the construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009228009A JP5609053B2 (en) 2009-09-30 2009-09-30 Tunnel construction method and tunnel constructed by the construction method

Publications (2)

Publication Number Publication Date
JP2011074676A JP2011074676A (en) 2011-04-14
JP5609053B2 true JP5609053B2 (en) 2014-10-22

Family

ID=44018933

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009228009A Expired - Fee Related JP5609053B2 (en) 2009-09-30 2009-09-30 Tunnel construction method and tunnel constructed by the construction method

Country Status (1)

Country Link
JP (1) JP5609053B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794756A (en) * 2020-07-16 2020-10-20 四川省交通勘察设计研究院有限公司 Construction method for multi-arch connection small-static-distance tunnel of mountain highway

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6405768B2 (en) * 2014-07-24 2018-10-17 株式会社大林組 Tunnel cross-section expansion method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3096643B2 (en) * 1996-10-23 2000-10-10 稔 山本 Tunnel widening method
JP3677699B2 (en) * 1997-04-04 2005-08-03 清水建設株式会社 Construction method of tunnel junction
JP2001123798A (en) * 1999-10-25 2001-05-08 Maeda Corp Work method in tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794756A (en) * 2020-07-16 2020-10-20 四川省交通勘察设计研究院有限公司 Construction method for multi-arch connection small-static-distance tunnel of mountain highway

Also Published As

Publication number Publication date
JP2011074676A (en) 2011-04-14

Similar Documents

Publication Publication Date Title
CN104278993B (en) A kind of bias voltage Skew Tunnel enters the constructional method in hole
KR101834847B1 (en) Echo-environmental construction method of tunnel portal area using mini pipe-roof
CN101775988B (en) Construction method of inclined shaft turning to normal tunnel in weak surrounding rock
CN104389606B (en) A kind of mine reduction-type based on environmental protection many well connection mining method
CN103939105B (en) A kind of construction method and structure laying construction shaft above underground construction
CN104533426B (en) An ultra shallow buries the method for tunnel construction of underpass of freeways large span cap excavation method
CN103032097B (en) Be applicable to tunnel drainage structure and the construction method thereof of bias voltage water rich strata
CN103510520A (en) Sectionalized construction method of deep and large foundation pit
CN102182465A (en) Tunnel-entering construction method for tunnel
CN102865084B (en) Expanding excavation method of underground tunnel from fracture surface of double-track tunnel to ultra-large fracture surface of triple-track tunnel
CN101915118A (en) Method for progressive gas drainage in high gas medium-hard coal seam
CN105909262B (en) A kind of underground tunnel excavation method
JP5609053B2 (en) Tunnel construction method and tunnel constructed by the construction method
CN102839980A (en) Highway tunnel structure and construction method thereof
KR100986312B1 (en) Propulsion guide device of steel pipe loop structure
KR101065458B1 (en) Arm and tunnel structure for cutting cut slope protection structure and construction method
KR20200026221A (en) Environmentally-friendly enlarged tunnel with integrated substructure and tunnel portal and construction method thereof
CN114482001A (en) Protection method for surface structure of stress-blocking mining subsidence area
RU2501912C2 (en) Method to erect underwater tunnels
CN201635745U (en) A rib-arch multi-arch tunnel
KR20060083740A (en) Piam tunnel construction method using anchor support
CN111577331A (en) Construction method of expressway steep-dip phyllite IV-V-level surrounding rock tunnel
CN213898989U (en) Buffer structure portal suitable for limited conditions of bridge-tunnel connection site
JP4746506B2 (en) Landslide prevention method
WO2012017314A3 (en) Closed trench tunnels

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120817

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130626

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20131210

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140805

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140818

R150 Certificate of patent or registration of utility model

Ref document number: 5609053

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees