JP6960771B2 - Construction method of cast-in-place concrete pile - Google Patents
[go: Go Back, main page]

JP6960771B2 - Construction method of cast-in-place concrete pile - Google Patents

Construction method of cast-in-place concrete pile Download PDF

Info

Publication number
JP6960771B2
JP6960771B2 JP2017101047A JP2017101047A JP6960771B2 JP 6960771 B2 JP6960771 B2 JP 6960771B2 JP 2017101047 A JP2017101047 A JP 2017101047A JP 2017101047 A JP2017101047 A JP 2017101047A JP 6960771 B2 JP6960771 B2 JP 6960771B2
Authority
JP
Japan
Prior art keywords
concrete
pile
pile head
super
delayed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017101047A
Other languages
Japanese (ja)
Other versions
JP2018193834A (en
Inventor
信之 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2017101047A priority Critical patent/JP6960771B2/en
Publication of JP2018193834A publication Critical patent/JP2018193834A/en
Application granted granted Critical
Publication of JP6960771B2 publication Critical patent/JP6960771B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Description

本発明は、場所打ちコンクリート杭の施工方法に関するものである。 The present invention relates to a method of constructing a cast-in-place concrete pile.

従来、場所打ちコンクリート杭を構築する際のコンクリート打設においては、コンクリート上部にスライムという脆弱層が形成されるため、計画の杭コンクリート天端から若干量(概ね800mm程度)コンクリートを高めに打ち上げている。こうしてコンクリート上部に設けた余盛コンクリートを、一般的には根切後に斫り取っているが、その時に生じる騒音や振動、埃が近隣へ環境問題を引き起こすおそれがあった。 Conventionally, in concrete placing when constructing cast-in-place concrete piles, a fragile layer called slime is formed on the upper part of the concrete, so a small amount (about 800 mm) of concrete is launched higher than the planned pile concrete top. There is. In this way, the surplus concrete provided on the upper part of the concrete is generally scraped off after root cutting, but the noise, vibration, and dust generated at that time may cause environmental problems in the neighborhood.

そこで、こうした問題に対処するために、例えばコンクリート硬化前にバキュームで余盛コンクリートを吸い取る方法や、杭鉄筋にコンクリート破砕材をセットして根切後に破砕された余盛コンクリートを除去する方法などが従来より採用されている。 Therefore, in order to deal with these problems, for example, a method of sucking up excess concrete by vacuum before hardening of concrete, a method of setting concrete crushing material on pile reinforcing bars and removing the excess concrete crushed after root cutting, etc. It has been used in the past.

一方、こうした場所打ちコンクリート杭の杭頭処理方法に関連して、例えば特許文献1、2に記載の技術が知られている。特許文献1は、計画杭の天端近傍までコンクリート打設した後、コンクリート上のスライム等を除去し、その後、最終コンクリートを計画杭の天端面よりも上方部分にまで打設し、その余盛部をバキュームホースによって吸引、除去するものである。特許文献2は、コンクリート硬化前に杭頭部の余盛部に注入管を挿入し、注入管から空気を注入してコンクリートの強度を低下させた後に、余盛部を斫り取るものである。 On the other hand, in relation to such a pile head processing method for cast-in-place concrete piles, for example, the techniques described in Patent Documents 1 and 2 are known. In Patent Document 1, after concrete is placed near the top of the planned pile, slime and the like on the concrete are removed, and then the final concrete is placed above the top of the planned pile, and the surplus thereof is obtained. The part is sucked and removed by a vacuum hose. Patent Document 2 inserts an injection pipe into the surplus portion of the pile head before hardening the concrete, injects air from the injection pipe to reduce the strength of the concrete, and then scrapes the surplus portion. ..

特開2004−263559号公報Japanese Unexamined Patent Publication No. 2004-263559 特開2001−288743号公報Japanese Unexamined Patent Publication No. 2001-288743

しかしながら、上記の従来のバキュームで吸い取る方法では、コンクリートの流動性が低下している場合や杭鉄筋が邪魔となる場合などに、効率的な施工を妨げるおそれがあった。また、上記の破砕材をセットする方法でも、計画通りに破砕できずに、結局、斫り作業を実施しなければならなくなる場合があり、信頼性が低いという問題があった。 However, the above-mentioned conventional vacuum suction method may hinder efficient construction when the fluidity of concrete is low or when the pile reinforcing bars are an obstacle. Further, even with the method of setting the above-mentioned crushing material, there is a problem that the crushing material cannot be crushed as planned and the chipping work may have to be carried out in the end, resulting in low reliability.

このため、コンクリートの砕り作業を行わずに余盛部を容易に除去することのできる施工性に優れた施工方法が求められていた。 Therefore, there has been a demand for a construction method having excellent workability, which can easily remove the surplus portion without crushing the concrete.

本発明は、上記に鑑みてなされたものであって、砕り作業を行わずに余盛部を容易に除去することのできる場所打ちコンクリート杭の施工方法を提供することを目的とする。 The present invention has been made in view of the above, and an object of the present invention is to provide a method for constructing a cast-in-place concrete pile in which a surplus portion can be easily removed without performing a crushing operation.

上記した課題を解決し、目的を達成するために、本発明に係る場所打ちコンクリート杭の施工方法は、場所打ちコンクリート杭を施工する方法であって、杭頭部とその上の余盛部の設置予定箇所に、コンクリートに超遅延剤を混入してなる超遅延コンクリートを打設して、超遅延コンクリートからなる杭頭部と余盛部を構築するステップと、余盛部の超遅延コンクリートの硬化開始前に、余盛部の超遅延コンクリートを除去するステップと、余盛部の超遅延コンクリートを除去した後、杭頭部の超遅延コンクリートの硬化開始前に、杭頭部と杭の上部に設置される構造物とを連結するための連結部材を杭頭部の超遅延コンクリートの中に挿入するステップとを備えることを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the method of constructing a cast-in-place concrete pile according to the present invention is a method of constructing a cast-in-place concrete pile, and the pile head and the surplus portion above it. At the planned installation location, a step of placing a super-delayed concrete made by mixing a super-delaying agent into concrete to construct a pile head and a surplus part made of super-delayed concrete, and a step of super-delayed concrete in the surplus part. Before the start of hardening, the step of removing the super-delayed concrete in the surplus part, and after removing the super-delayed concrete in the surplus part, and before the start of hardening of the super-delayed concrete in the pile head, the pile head and the upper part of the pile It is characterized by including a step of inserting a connecting member for connecting the structure to be installed in the pile head into the ultra-delayed concrete of the pile head.

また、本発明に係る他の場所打ちコンクリート杭の施工方法は、上述した発明において、連結部材として、杭頭鉄筋、柱主筋、柱鉄骨の少なくとも一つを挿入することを特徴とする。 Further, another method of constructing a cast-in-place concrete pile according to the present invention is characterized in that at least one of a pile head reinforcing bar, a column main bar, and a column steel frame is inserted as a connecting member in the above-described invention.

また、本発明に係る他の場所打ちコンクリート杭の施工方法は、上述した発明において、杭頭部と杭の上部に設置される構造物とを、連結部材を介して半剛接合またはピン接合することを特徴とする。 Further, in another method of constructing a cast-in-place concrete pile according to the present invention, in the above-mentioned invention, the pile head and the structure installed on the upper part of the pile are semi-rigidly joined or pin-joined via a connecting member. It is characterized by that.

本発明に係る場所打ちコンクリート杭の施工方法によれば、場所打ちコンクリート杭を施工する方法であって、杭頭部とその上の余盛部の設置予定箇所に、コンクリートに超遅延剤を混入してなる超遅延コンクリートを打設して、超遅延コンクリートからなる杭頭部と余盛部を構築するステップと、余盛部の超遅延コンクリートの硬化開始前に、余盛部の超遅延コンクリートを除去するステップと、余盛部の超遅延コンクリートを除去した後、杭頭部の超遅延コンクリートの硬化開始前に、杭頭部と杭の上部に設置される構造物とを連結するための連結部材を杭頭部の超遅延コンクリートの中に挿入するステップとを備えるので、余盛部の除去が容易でコンクリートの砕り作業がなくなるため施工性が向上するという効果を奏する。 According to the method for constructing cast-in-place concrete piles according to the present invention, it is a method for constructing cast-in-place concrete piles, in which a super-delaying agent is mixed in concrete at the pile head and the planned installation location of the surplus portion above the pile head. The step of placing the super-delayed concrete to build the pile head and the surplus part made of the super-delayed concrete, and the super-delayed concrete of the surplus part before the start of hardening of the super-delayed concrete of the surplus part. For connecting the pile head and the structure installed on the top of the pile after removing the super-delayed concrete in the surplus part and before the start of hardening of the super-delayed concrete in the pile head. Since the connecting member is provided with a step of inserting the connecting member into the ultra-delayed concrete of the pile head, it is easy to remove the surplus portion and the concrete crushing work is eliminated, so that the workability is improved.

また、本発明に係る他の場所打ちコンクリート杭の施工方法によれば、連結部材として、杭頭鉄筋、柱主筋、柱鉄骨の少なくとも一つを挿入するので、こうした連結部材を介して杭頭部と杭の上部の構造物とを連結することができるという効果を奏する。 Further, according to another method of constructing a cast-in-place concrete pile according to the present invention, at least one of a pile head reinforcing bar, a column main bar, and a column steel frame is inserted as a connecting member, so that the pile head is inserted through such a connecting member. It has the effect of being able to connect and the structure above the pile.

また、本発明に係る他の場所打ちコンクリート杭の施工方法によれば、杭頭部と杭の上部に設置される構造物とを、連結部材を介して半剛接合またはピン接合するので、半剛接合構法やピン接合構法により構築される杭にも適用することができるという効果を奏する。 Further, according to another method of constructing a cast-in-place concrete pile according to the present invention, the pile head and the structure installed on the upper part of the pile are semi-rigidly joined or pin-joined via a connecting member. It has the effect that it can be applied to piles constructed by the rigid joint construction method and the pin joint construction method.

図1は、本発明に係る場所打ちコンクリート杭の施工方法の実施の形態を示す概略手順図(前半)である。FIG. 1 is a schematic procedure diagram (first half) showing an embodiment of a cast-in-place concrete pile construction method according to the present invention. 図2は、本発明に係る場所打ちコンクリート杭の施工方法の実施の形態を示す概略手順図(後半)である。FIG. 2 is a schematic procedure diagram (second half) showing an embodiment of a cast-in-place concrete pile construction method according to the present invention.

本発明に係る場所打ちコンクリート杭の施工方法は、超遅延剤の採用でコンクリートの凝結開始時間が調整できることを利用した施工合理化工法である。杭天端部をなすコンクリートとして超遅延剤を混入した超遅延コンクリートを採用するとともに、これと、従来より広く用いられているバキューム工法を組み合わせることで、杭頭コンクリートの斫り作業をなくすことができる。 The method of constructing a cast-in-place concrete pile according to the present invention is a construction rationalization method utilizing the fact that the setting start time of concrete can be adjusted by adopting an ultra-delaying agent. By adopting super-delayed concrete mixed with a super-delaying agent as the concrete forming the top of the pile and combining this with the vacuum method that has been widely used in the past, it is possible to eliminate the chipping work of pile head concrete.

以下に、本発明に係る場所打ちコンクリート杭の施工方法の実施の形態を図面に基づいて詳細に説明する。なお、この実施の形態によりこの発明が限定されるものではない。 Hereinafter, embodiments of the method for constructing cast-in-place concrete piles according to the present invention will be described in detail with reference to the drawings. The present invention is not limited to this embodiment.

図1(1)に示すように、本発明の実施の形態では、まず、地面GL上に配置した図示しない圧入装置を用いて、地盤G内に筒状のケーシングチューブ10を圧入する(ステップS1)。続いて、ケーシングチューブ10で孔壁12を保護しながら、グラブバケット等を用いてケーシングチューブ10内の掘削および土砂の排出を行う(ステップS2)。このようにして杭孔14を施工する。なお、地表面近くの地盤から杭の支持層の上にある層が軟弱な地盤である場合は、支持層近くまで鋼管を入れて杭孔を施工する。 As shown in FIG. 1 (1), in the embodiment of the present invention, first, a cylindrical casing tube 10 is press-fitted into the ground G by using a press-fitting device (not shown) arranged on the ground GL (step S1). ). Subsequently, while protecting the hole wall 12 with the casing tube 10, excavation in the casing tube 10 and discharge of earth and sand are performed using a grab bucket or the like (step S2). In this way, the pile hole 14 is constructed. If the layer above the support layer of the pile from the ground near the ground surface is soft ground, a steel pipe is inserted up to the vicinity of the support layer to construct a pile hole.

次に、図1(2)に示すように、杭孔14内に鉄筋籠16を建て込む(ステップS3)。この鉄筋籠16は、上端が設置予定の杭頭部18の天端面TLに収まるように建て込む。続いて、杭頭部18とその上方の余盛部20に、コンクリートにあらかじめ超遅延剤を混入してなる超遅延コンクリート22を打設する(ステップS4)。このようにして、超遅延コンクリート22からなる杭頭部18と余盛部20を構築する。 Next, as shown in FIG. 1 (2), the reinforcing bar cage 16 is built in the pile hole 14 (step S3). The reinforcing bar cage 16 is built so that the upper end fits in the top end surface TL of the pile head 18 to be installed. Subsequently, the super-delayed concrete 22 in which the super-delaying agent is mixed in advance with the concrete is placed in the pile head 18 and the surplus portion 20 above the pile head 18 (step S4). In this way, the pile head 18 and the surplus portion 20 made of the ultra-delayed concrete 22 are constructed.

次に、図1(3)に示すように、余盛部20の超遅延コンクリート22の硬化(凝結)開始前に、余盛部20の超遅延コンクリート22を図示しないバキュームホース等によって吸引して、杭孔14から除去する(ステップS5)。 Next, as shown in FIG. 1 (3), before the start of hardening (condensation) of the super-delayed concrete 22 of the surplus portion 20, the super-delayed concrete 22 of the surplus portion 20 is sucked by a vacuum hose or the like (not shown). , Remove from the pile hole 14 (step S5).

次に、例えば図2(1)に示すように、杭頭部18の超遅延コンクリート22の硬化開始前に、杭頭部18と杭100の上部に設置される基礎等の構造物24とを連結するための連結部材26(杭頭鉄筋26A)の下側部分を、杭頭部18の超遅延コンクリート22の中に挿入する(ステップS6)。 Next, for example, as shown in FIG. 2 (1), before the start of hardening of the ultra-delayed concrete 22 of the pile head 18, the pile head 18 and the structure 24 such as a foundation installed on the upper part of the pile 100 are connected. The lower portion of the connecting member 26 (pile head reinforcing bar 26A) for connecting is inserted into the ultra-delayed concrete 22 of the pile head 18 (step S6).

続いて、超遅延コンクリート22が硬化する前にケーシングチューブ10(不図示)を引き抜き、杭頭部18の上に地盤面GLまでコンクリートを打設する。このようにすることで、場所打ちコンクリート杭100を構築することができる。 Subsequently, before the ultra-delayed concrete 22 hardens, the casing tube 10 (not shown) is pulled out, and concrete is poured onto the pile head 18 up to the ground surface GL. By doing so, the cast-in-place concrete pile 100 can be constructed.

なお、上記のステップS6で挿入する連結部材26としては、図2(1)のような杭頭鉄筋26Aに限るものではなく、柱鉄筋、柱鉄骨など杭の上部に設置される構造物24に応じて選定することができる。例えば連結部材26として、図2(2)に示すように柱主筋26Bを挿入してもよいし、(3)に示すように柱鉄骨26Cを挿入してもよい。 The connecting member 26 to be inserted in step S6 is not limited to the pile head reinforcing bar 26A as shown in FIG. 2 (1), but is not limited to the pile head reinforcing bar 26A as shown in FIG. It can be selected according to the situation. For example, as the connecting member 26, the column main bar 26B may be inserted as shown in FIG. 2 (2), or the column steel frame 26C may be inserted as shown in (3).

連結部材26は余盛部20の超遅延コンクリートの吸引除去後に挿入するため、コンクリートの付着はない。このため、従来より実施されている杭頭定着鉄筋の清掃等の作業もなくせる。ただし、埋戻土に対する連結部材26の養生は行うことが望ましい。 Since the connecting member 26 is inserted after the super-delayed concrete of the surplus portion 20 is sucked and removed, no concrete adheres. For this reason, it is possible to eliminate the work such as cleaning of the pile head fixing reinforcing bar, which has been conventionally performed. However, it is desirable to cure the connecting member 26 with respect to the backfill soil.

本実施の形態の施工方法によれば、杭頭部18と余盛部20のコンクリートとして超遅延コンクリート22を打設した後、杭頭部18の天端面TLまで余盛部20を除去し、その後、連結部材26(杭頭鉄筋26A、柱主筋26B、柱鉄骨26C)を建て込むので、余盛部18の除去が容易でコンクリートの砕り作業がなくなるため施工性が向上する。特に、コンクリートに超遅延剤を混入してなる超遅延コンクリートを使用し、吸い取るのは硬化開始前の超遅延コンクリートとなるため、周知のバキューム工法を有効に適用することができる。 According to the construction method of the present embodiment, after placing the super-delayed concrete 22 as the concrete of the pile head 18 and the surplus portion 20, the surplus portion 20 is removed up to the top end surface TL of the pile head 18. After that, since the connecting member 26 (pile head reinforcing bar 26A, column main reinforcing bar 26B, column steel frame 26C) is built, the surplus portion 18 can be easily removed and the concrete crushing work is eliminated, so that the workability is improved. In particular, since super-delayed concrete obtained by mixing a super-delaying agent with concrete is used and the super-delayed concrete is absorbed before the start of hardening, a well-known vacuum method can be effectively applied.

また、本実施の形態の施工方法によっても、上記の従来の方法により施工される杭と同等の構造性能の杭を得ることができる。この施工方法は、上記の従来の方法に比べてコンクリートに混入する超遅延剤などのコストは掛かるものの、近隣対応が必要な施工地域では杭頭コンクリートの斫り工事や騒音対策に掛かるコストが不要になるため、トータルコストの低減が図れる。また、杭頭コンクリートの斫り工事がなくなるため、斫り工事を行う従来の方法と比較して施工期間を短縮することができる。さらに、斫り工事に伴う騒音や振動、埃を発生しないので環境にやさしい施工方法となる。また、斫り工事を行う従来の方法に比べて施工時の作業安全性を高めることができる。また、杭頭鉄筋等の基礎部材との連結材は、余盛コンクリート等が付着しないため、構造性能の向上も図れる。 Further, also by the construction method of the present embodiment, it is possible to obtain a pile having the same structural performance as the pile constructed by the above-mentioned conventional method. Compared to the above-mentioned conventional method, this construction method costs more such as super-delaying agent mixed in concrete, but in the construction area where neighborhood measures are required, there is no need for the cost of scraping pile head concrete and noise countermeasures. Therefore, the total cost can be reduced. In addition, since the chipping work of the pile head concrete is eliminated, the construction period can be shortened as compared with the conventional method of performing the chipping work. Furthermore, since it does not generate noise, vibration, or dust associated with chipping work, it is an environmentally friendly construction method. In addition, work safety during construction can be improved as compared with the conventional method of performing chipping work. Further, since the connecting material with the foundation member such as the pile head reinforcing bar does not adhere to the surplus concrete or the like, the structural performance can be improved.

なお、上記の実施の形態においては、杭頭部18とその上部に設置する基礎などの構造物24を連結部材26を介して完全に固定する剛接合の場合を例にとり説明したが、本発明はこれに限るものではなく、杭頭部18とその上部の構造物24を完全に固定しない半剛接合構法やピン接合構法によって構築される杭にも適用可能である。 In the above embodiment, the case of rigid joining in which the pile head 18 and the structure 24 such as the foundation installed on the pile head 18 and the structure 24 such as the foundation installed on the pile head 18 are completely fixed via the connecting member 26 has been described as an example. Is not limited to this, and is also applicable to piles constructed by a semi-rigid joint construction method or a pin joint construction method in which the pile head 18 and the structure 24 above the pile head 18 are not completely fixed.

以上説明したように、本発明に係る場所打ちコンクリート杭の施工方法によれば、場所打ちコンクリート杭を施工する方法であって、杭頭部とその上の余盛部の設置予定箇所に、コンクリートに超遅延剤を混入してなる超遅延コンクリートを打設して、超遅延コンクリートからなる杭頭部と余盛部を構築するステップと、余盛部の超遅延コンクリートの硬化開始前に、余盛部の超遅延コンクリートを除去するステップと、余盛部の超遅延コンクリートを除去した後、杭頭部の超遅延コンクリートの硬化開始前に、杭頭部と杭の上部に設置される構造物とを連結するための連結部材を杭頭部の超遅延コンクリートの中に挿入するステップとを備えるので、余盛部の除去が容易でコンクリートの砕り作業がなくなるため施工性が向上する。 As described above, according to the method for constructing cast-in-place concrete piles according to the present invention, it is a method for constructing cast-in-place concrete piles, and concrete is placed at the pile head and the planned installation location of the surplus portion above the pile head. Before the step of placing the super-delayed concrete mixed with the super-delaying agent to construct the pile head and the surplus part made of the super-delayed concrete, and the start of hardening of the super-delayed concrete in the surplus part, the surplus A structure to be installed on the pile head and the top of the pile after the step of removing the super-delayed concrete in the ridge and before the start of hardening of the super-delay concrete in the pile head after removing the super-delay concrete in the surplus. Since the step of inserting the connecting member for connecting with and into the ultra-delayed concrete of the pile head is provided, the surplus portion can be easily removed and the concrete crushing work is eliminated, so that the workability is improved.

また、本発明に係る他の場所打ちコンクリート杭の施工方法によれば、連結部材として、杭頭鉄筋、柱主筋、柱鉄骨の少なくとも一つを挿入するので、こうした連結部材を介して杭頭部と杭の上部の構造物とを連結することができる。 Further, according to another method of constructing a cast-in-place concrete pile according to the present invention, at least one of a pile head reinforcing bar, a column main bar, and a column steel frame is inserted as a connecting member, so that the pile head is inserted through such a connecting member. Can be connected to the structure above the pile.

また、本発明に係る他の場所打ちコンクリート杭の施工方法によれば、杭頭部と杭の上部に設置される構造物とを、連結部材を介して半剛接合またはピン接合するので、半剛接合構法やピン接合構法により構築される杭にも適用することができる。 Further, according to another method of constructing a cast-in-place concrete pile according to the present invention, the pile head and the structure installed on the upper part of the pile are semi-rigidly joined or pin-joined via a connecting member. It can also be applied to piles constructed by the rigid joint construction method and the pin joint construction method.

以上のように、本発明に係る場所打ちコンクリート杭の施工方法は、場所打ちコンクリート杭の杭頭部の余盛の処理に有用であり、特に、コンクリートの砕り作業を行わずに余盛部を除去するのに適している。 As described above, the method for constructing a cast-in-place concrete pile according to the present invention is useful for treating the surplus of the pile head of the cast-in-place concrete pile, and in particular, the surplus portion without crushing the concrete. Suitable for removing.

10 ケーシングチューブ
12 孔壁
13 杭孔
16 鉄筋籠
18 杭頭部
20 余盛部
22 超遅延コンクリート
24 構造物
26 連結部材
26A 杭頭鉄筋(連結部材)
26B 柱主筋(連結部材)
26C 柱鉄骨(連結部材)
100 場所打ちコンクリート杭
G 地盤
GL 地面
TL 天端面
10 Casing tube 12 Hole wall 13 Pile hole 16 Reinforcing bar cage 18 Pile head 20 Overlay part 22 Super delay concrete 24 Structure 26 Connecting member 26A Pile head reinforcing bar (connecting member)
26B Column main bar (connecting member)
26C column steel frame (connecting member)
100 cast-in-place concrete pile G ground GL ground TL top surface

Claims (2)

場所打ちコンクリート杭を施工する方法であって、
杭頭部とその上の余盛部の設置予定箇所に、コンクリートに超遅延剤を混入してなる超遅延コンクリートを打設して、超遅延コンクリートからなる杭頭部と余盛部を構築するステップと、
余盛部の超遅延コンクリートの硬化開始前に、余盛部の超遅延コンクリートを除去するステップと、
余盛部の超遅延コンクリートを除去した後、杭頭部の超遅延コンクリートの硬化開始前に、杭頭部と杭の上部に設置される構造物とを連結するための連結部材として、杭頭鉄筋、柱主筋、柱鉄骨の少なくとも一つの下側部分を杭頭部の超遅延コンクリートの中に挿入するステップとを備えることを特徴とする場所打ちコンクリート杭の施工方法。
It is a method of constructing cast-in-place concrete piles.
A super-delayed concrete made by mixing a super-delaying agent with concrete is placed at the planned installation location of the pile head and the surplus part above it to construct the pile head and the surplus part made of super-delayed concrete. Steps and
Before the start of hardening of the super-delayed concrete in the surplus part, the step of removing the super-delayed concrete in the surplus part and
After removing the super-delayed concrete in the surplus part, before the start of hardening of the super-delayed concrete in the pile head, the pile head is used as a connecting member for connecting the pile head and the structure installed on the upper part of the pile. A method for constructing cast-in-place concrete piles, which comprises a step of inserting at least one lower portion of a reinforcing bar, a pillar main bar, and a pillar steel frame into ultra-delayed concrete of a pile head.
杭頭部と杭の上部に設置される構造物とを、連結部材を介して半剛接合またはピン接合することを特徴とする請求項1に記載の場所打ちコンクリート杭の施工方法。 The method for constructing a cast-in-place concrete pile according to claim 1, wherein the pile head and the structure installed on the upper part of the pile are semi-rigidly joined or pin-joined via a connecting member.
JP2017101047A 2017-05-22 2017-05-22 Construction method of cast-in-place concrete pile Active JP6960771B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017101047A JP6960771B2 (en) 2017-05-22 2017-05-22 Construction method of cast-in-place concrete pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017101047A JP6960771B2 (en) 2017-05-22 2017-05-22 Construction method of cast-in-place concrete pile

Publications (2)

Publication Number Publication Date
JP2018193834A JP2018193834A (en) 2018-12-06
JP6960771B2 true JP6960771B2 (en) 2021-11-05

Family

ID=64571580

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017101047A Active JP6960771B2 (en) 2017-05-22 2017-05-22 Construction method of cast-in-place concrete pile

Country Status (1)

Country Link
JP (1) JP6960771B2 (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58146621A (en) * 1982-02-26 1983-09-01 Takenaka Komuten Co Ltd Top treatment of on-site concrete pile
JPS6136418A (en) * 1984-07-27 1986-02-21 Nippon Kokan Kk <Nkk> Construction method of cast-in-place steel pipe concrete piles
JPH0718152B2 (en) * 1988-04-13 1995-03-01 株式会社淺沼組 Excessive concrete treatment method using a screw pump and excess concrete removing device used therefor
JPH08158360A (en) * 1994-12-07 1996-06-18 Nissan Kensetsu Kk Treating method for extra-fill concrete on cast-in place concrete pile
JP4675101B2 (en) * 2004-12-20 2011-04-20 株式会社竹中工務店 Semi-rigid joint structure between concrete pile and foundation slab or foundation beam and its construction method
JP2012107443A (en) * 2010-11-18 2012-06-07 Takenaka Komuten Co Ltd Semi-rigid junction structure of pile head of cast-in-place pile and concrete foundation

Also Published As

Publication number Publication date
JP2018193834A (en) 2018-12-06

Similar Documents

Publication Publication Date Title
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
JP2010281185A (en) Method for reconstructing existing building with basement
JP5378066B2 (en) Mountain fastening method
CN104060616B (en) A kind of construction formwork of retaining engineering and construction method
KR101524303B1 (en) The wall members and underground wall, underground wall construction method using the same
JP4623574B2 (en) How to build a pile
KR102023135B1 (en) Cast-In place concrete Pile method using Octangle-casing
JP6960771B2 (en) Construction method of cast-in-place concrete pile
JP4373824B2 (en) Joining method of cast-in-place pile and steel pipe column
JP2020007735A (en) Method for reinforcing foundation structure and structure for reinforcing foundation structure
JP2004232436A (en) Pier foundation reinforcing method and pier foundation reinforcing structure
JP7053402B2 (en) Rectangular shaft and its construction method
JP6006004B2 (en) Pile head space formation auxiliary tool, hollow ready-made pile provided with the same, pile head processing method using the hollow ready-made pile, and pile head space forming method
KR101406865B1 (en) Extension of foundation structure and constructing method for extension of foundaion structure using the same
JP2000045265A (en) How to form ground vibration isolation grooves
KR100446586B1 (en) Soil-Nail able to Withdraw Itself by Blasting
JP2006328666A (en) Integrated construction method of pile and column
JP6506902B2 (en) Pile foundation structure and construction method of pile foundation structure
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
JP5285440B2 (en) Construction method of structure
KR101685114B1 (en) Underground diaphragm wall using embedded plates and coupler and contructing method thereof
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
KR101135652B1 (en) Pulling method of pile
JP2005036636A (en) Method for repairing masonry
JP2002146774A (en) Soil cement column wall method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200514

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210329

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210406

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210514

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211005

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211012

R150 Certificate of patent or registration of utility model

Ref document number: 6960771

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150