JP7254752B2 - power management device - Google Patents
[go: Go Back, main page]

JP7254752B2 - power management device - Google Patents

power management device Download PDF

Info

Publication number
JP7254752B2
JP7254752B2 JP2020136050A JP2020136050A JP7254752B2 JP 7254752 B2 JP7254752 B2 JP 7254752B2 JP 2020136050 A JP2020136050 A JP 2020136050A JP 2020136050 A JP2020136050 A JP 2020136050A JP 7254752 B2 JP7254752 B2 JP 7254752B2
Authority
JP
Japan
Prior art keywords
power
storage battery
amount
facility
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020136050A
Other languages
Japanese (ja)
Other versions
JP2020182381A (en
Inventor
幸人 奥田
剛文 松永
英明 片野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from JP2017207524A external-priority patent/JP2018014888A/en
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP2020136050A priority Critical patent/JP7254752B2/en
Publication of JP2020182381A publication Critical patent/JP2020182381A/en
Priority to JP2022030166A priority patent/JP7334287B2/en
Application granted granted Critical
Publication of JP7254752B2 publication Critical patent/JP7254752B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)

Description

本発明は、電力管理装置に関する。 The present invention relates to power management devices.

太陽光発電などの自然エネルギー発電に関連して、余剰電力を蓄電して電力を有効活用するための幾つかの技術が提案されている。
例えば、特許文献1に記載の蓄電池運用制御装置は、電力負荷で使用される使用電力の時間変化と、自然エネルギー発電電力の時間変化とによって予測される蓄電池の容量の時間変化に基づいて、蓄電池の容量の最大ピーク値を予測し、設定された蓄電池の容量の上限値と、蓄電池の容量の最大ピーク値との差分である上限側差分電力量を算出する。そして、当該蓄電池運用制御装置は、時間変化における所定の初期時刻での蓄電池の容量の予測値を、少なくとも上限側差分電力量に基づく補正容量に基づいて補正した値である、初期時刻における必要蓄電容量を算出し、初期時刻において蓄電池の容量が必要蓄電容量となるよう蓄電池を制御する。
これにより、余剰電力の外部給電系統への逆潮を低減し、また外部給電系統からの電力の供給を低減することができる。
In relation to natural energy power generation such as photovoltaic power generation, several techniques have been proposed for storing surplus power and making effective use of the power.
For example, the storage battery operation control device described in Patent Document 1 is based on the time change in the capacity of the storage battery predicted by the time change in the power used by the power load and the time change in the power generated by natural energy. The maximum peak value of the capacity of the storage battery is predicted, and the upper limit side differential power amount, which is the difference between the set upper limit value of the storage battery capacity and the maximum peak value of the storage battery capacity, is calculated. Then, the storage battery operation control device corrects the predicted value of the capacity of the storage battery at a predetermined initial time in the change over time based on at least the corrected capacity based on the upper limit side differential power amount. The capacity is calculated, and the storage battery is controlled so that the capacity of the storage battery reaches the required storage capacity at the initial time.
As a result, reverse flow of surplus power to the external power supply system can be reduced, and power supply from the external power supply system can be reduced.

また、自然エネルギー発電にて車載の蓄電池への充電を行うための幾つかの技術が提案されている。
例えば、特許文献2に記載の電力供給配分制御装置は、予想太陽光発電量、車両用蓄電池の予想充電量を算出して充電が必要な場合に太陽光発電が車両用蓄電池へ供給されるように電力の配分を制御する。また、予想太陽光発電量の方が予想充電量より多い場合には、余剰電力が住宅負荷へ供給されるように電力の配分を制御し、予想太陽光発電量が、予想充電量と住宅負荷を加算した電力量より大きい場合に、余剰電力が住宅用蓄電池へ供給されるように電力の配分を制御し、さらに余剰電力がある場合に売電されるように電力の配分を制御する。
これにより、太陽電池の発電電力により自動車に搭載される蓄電池を確実に充電することができる、とされている。
In addition, several techniques have been proposed for charging an in-vehicle storage battery with natural energy power generation.
For example, a power supply distribution control device described in Patent Document 2 calculates an expected amount of photovoltaic power generation and an expected charge amount of a vehicle storage battery so that the photovoltaic power is supplied to the vehicle storage battery when charging is required. control the distribution of power to If the expected amount of photovoltaic power generation is greater than the expected charging amount, the power distribution is controlled so that the surplus power is supplied to the residential load. When the power amount is greater than the sum of , power distribution is controlled so that surplus power is supplied to the residential storage battery, and further, power distribution is controlled so that surplus power is sold when there is surplus power.
It is said that this enables the electric power generated by the solar cell to reliably charge the storage battery mounted on the automobile.

特開2012-120419号公報JP 2012-120419 A 特開2010-268576号公報JP 2010-268576 A

特許文献1では、蓄電池の施設外使用に際しての充電方法までは示されていない。電気自動車での電気の使用など、充放電機構を備えた施設の外部へ移動して蓄電池を使用する場合、電気不足を生じないように予め充電しておく必要がある。
また、特許文献2では、車両用蓄電池と住宅用蓄電池との両方を具備する必要がある。設備コスト低減の観点から、1つの蓄電池にて運用できることが望まれる。従って、1つの蓄電池にて電力供給対象の施設における電力負荷に電力を供給しつつ、蓄電池の施設外使用において電気不足を回避できることが望まれる。
Patent Literature 1 does not disclose a method of charging the storage battery when it is used outside the facility. When using a storage battery outside a facility equipped with a charging/discharging mechanism, such as when using electricity in an electric vehicle, it is necessary to charge the battery in advance so as not to cause a shortage of electricity.
Moreover, in Patent Document 2, it is necessary to provide both a vehicle storage battery and a residential storage battery. From the viewpoint of equipment cost reduction, it is desirable to be able to operate with one storage battery. Therefore, it is desirable to be able to supply power to power loads in a facility to which power is to be supplied with a single storage battery, while avoiding power shortages when the storage battery is used outside the facility.

本発明は、このような事情を考慮してなされたものであり、その目的は、1つの蓄電池にて電力供給対象の施設における電力負荷に電力を供給しつつ、蓄電池の施設外使用において電気不足を回避することのできる電力管理装置を提供することにある。 The present invention has been made in consideration of such circumstances, and its object is to supply power to the power load in the facility to which power is supplied with one storage battery, and to solve the problem of power shortage when the storage battery is used outside the facility. To provide a power management device capable of avoiding

この発明は上述した課題を解決するためになされたもので、本発明の一態様による電力管理装置は、自然エネルギー発電装置と、電力負荷と、蓄電池とを具備する施設において電力の管理を行う電力管理装置であって、前記蓄電池の前記施設外での使用を開始する予定時刻である施設外使用開始予定時刻と、当該使用を終了する予定時刻である施設外使用終了予定時刻と、当該使用に要する電力量の予測である施設外使用電力量予測とを含む施設外使用予定を取得する施設外使用予定取得部と、前記電力負荷の消費電力の予測を取得する消費電力予測取得部と、前記自然エネルギー発電装置の発電電力の予測を取得する発電電力予測取得部と、前記施設外使用予定と、前記消費電力の予測と、前記発電電力の予測とに基づいて、時刻毎の前記蓄電池の蓄電量を算出する蓄電量予測算出部と、得られた時刻毎の蓄電量における最大値が所定の蓄電量最大値となるように、電力料金が比較的安価な時間帯における外部供給電力を用いての前記蓄電池の充電を計画する最大蓄電量調整部と、前記施設外使用終了予定時刻における前記蓄電池の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値以上となるように前記蓄電池の充放電を計画する施設外使用時蓄電量調整部と、得られた計画に基づいて前記蓄電池の充放電を制御する充放電制御部と、を具備することを特徴とする。 The present invention has been made to solve the above-described problems, and a power management device according to one aspect of the present invention is a power management device that manages power in a facility that includes a natural energy power generation device, a power load, and a storage battery. A management device comprising: a scheduled time to start using the storage battery outside the facility, a scheduled time to start using the storage battery outside the facility; a scheduled time to finish using the storage battery outside the facility; an out-of-facility usage schedule acquisition unit that acquires an out-of-facility usage schedule including an out-of-facility usage prediction that is a prediction of required power; a power consumption prediction acquisition unit that acquires a prediction of power consumption of the power load; A generated power prediction acquisition unit that acquires a prediction of the generated power of the natural energy power generation device, and based on the schedule for use outside the facility, the prediction of the power consumption, and the prediction of the generated power, the power storage of the storage battery for each time. and an externally supplied electric power during a period when the power rate is relatively low so that the maximum value of the obtained electric storage amount for each time becomes a predetermined maximum electric storage amount. and a maximum power storage amount adjustment unit that plans charging of the storage battery, and the power storage amount at the end of outside use, which is the amount of power stored in the storage battery at the scheduled end time of use outside the facility, is equal to or greater than a predetermined minimum power storage amount. It is characterized by comprising an outside-use power storage amount adjusting unit that plans charging and discharging of the storage battery, and a charging and discharging control unit that controls charging and discharging of the storage battery based on the obtained plan.

また、本発明の他の一態様による電力管理装置は、上述の電力管理装置であって、前記施設外使用時蓄電量調整部は、前記施設外使用終了時蓄電量と、前記蓄電量最小値とを比較して蓄電量の調整要否を判定する調整要否判定部と、前記調整要否判定部が調整必要と判定すると、前記施設外使用終了予定時刻が、前記蓄電池の蓄電量が最大となる時刻より早いか否かを判定する前後判定部と、前記施設外使用終了予定時刻が、前記蓄電池の蓄電量が最大となる時刻より早いと前記前後判定部が判定すると、外部供給電力を用いての前記蓄電池の充電を計画する充電計画部と、前記施設外使用終了予定時刻が、前記蓄電池の蓄電量が最大となる時刻以後であると前記前後判定部が判定すると、前記蓄電池の放電の抑制を計画する放電抑制計画部と、を具備することを特徴とする。 Further, a power management device according to another aspect of the present invention is the power management device described above, wherein the stored power amount adjustment unit for use outside the facility controls the stored power amount at the end of use outside the facility and the minimum stored power amount and when the adjustment necessity determination unit determines that adjustment is necessary, the scheduled end time of use outside the facility is set to the maximum storage battery amount. and a before/after determination unit that determines whether or not it is earlier than the time at which externally supplied power is supplied when the scheduled end time of use outside the facility is earlier than the time at which the storage battery reaches its maximum storage capacity. and when the before/after determination unit determines that the scheduled time of completion of use outside the facility is after the time when the amount of electricity stored in the storage battery reaches its maximum, the storage battery is discharged. and a discharge suppression planning unit that plans suppression of the discharge.

また、本発明の他の一態様による電力管理装置は、上述の電力管理装置であって、前記充電計画部は、前記施設外使用開始予定時刻を充電終了時刻として時刻を遡る時間帯において、外部供給電力を用いての前記蓄電池の充電を継続するよう計画し、当該時間帯の時間幅を、前記施設外使用終了時蓄電量が前記蓄電量最小値以上となる時間幅とすることを特徴とする。 Further, a power management device according to another aspect of the present invention is the power management device described above, wherein the charging planning unit performs external The storage battery is planned to be continuously charged using the supplied power, and the time width of the time period is set to a time width in which the amount of electricity stored at the end of use outside the facility is equal to or greater than the minimum amount of electricity storage. do.

また、本発明の他の一態様による電力管理装置は、上述の電力管理装置であって、前記充電計画部は、充放電計画対象時間帯の開始時刻を充電開始時刻とする時間帯において、外部供給電力を用いての前記蓄電池の充電を継続するよう計画し、当該時間帯の時間幅を、前記施設外使用終了時蓄電量が前記蓄電量最小値以上となる時間幅とすることを特徴とする。 Further, a power management apparatus according to another aspect of the present invention is the power management apparatus described above, wherein the charging planning unit performs external The storage battery is planned to be continuously charged using the supplied power, and the time width of the time period is set to a time width in which the amount of electricity stored at the end of use outside the facility is equal to or greater than the minimum amount of electricity storage. do.

また、本発明の他の一態様による電力管理装置は、上述の電力管理装置であって、前記充放電制御部は、前記施設外使用開始予定時刻から前記施設外使用終了予定時刻までの時間帯において前記蓄電池が接続されている状態を検出すると、外部供給電力を用いての前記蓄電池の充電を行うことを特徴とする。 Further, a power management device according to another aspect of the present invention is the power management device described above, wherein the charge/discharge control unit controls the time period from the scheduled start time of use outside the facility to the scheduled end time of use outside the facility. is detected that the storage battery is connected, the storage battery is charged using the external power supply.

また、本発明の他の一態様による充放電計画装置は、自然エネルギー発電装置と、電力負荷と、蓄電池とを具備する施設における前記蓄電池の充放電を計画する充放電計画装置であって、前記蓄電池の前記施設外での使用を開始する予定時刻である施設外使用開始予定時刻と、当該使用を終了する予定時刻である施設外使用終了予定時刻と、当該使用に要する電力量の予測である施設外使用電力量予測とを含む施設外使用予定を取得する施設外使用予定取得部と、前記電力負荷の消費電力の予測を取得する消費電力予測取得部と、前記自然エネルギー発電装置の発電電力の予測を取得する発電電力予測取得部と、前記施設外使用予定と、前記消費電力の予測と、前記発電電力の予測とに基づいて、時刻毎の前記蓄電池の蓄電量を算出する蓄電量予測算出部と、得られた時刻毎の蓄電量における最大値が所定の蓄電量最大値となるように、電力料金が比較的安価な時間帯における外部供給電力を用いての前記蓄電池の充電を計画する最大蓄電量調整部と、前記施設外使用終了予定時刻における前記蓄電池の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値以上となるように前記蓄電池の充放電を計画する施設外使用時蓄電量調整部と、を具備することを特徴とする。 Further, a charge/discharge planning device according to another aspect of the present invention is a charge/discharge planning device for planning charging and discharging of the storage battery in a facility including a natural energy power generation device, an electric power load, and a storage battery, A scheduled time to start using the storage battery outside the facility, a scheduled time to end the use outside the facility, a scheduled time to end the use, and a prediction of the amount of power required for the use. an out-of-facility usage schedule acquisition unit that acquires an out-of-facility usage schedule including an out-of-facility usage forecast, a power consumption prediction acquisition unit that acquires a prediction of power consumption of the power load, and power generated by the natural energy power generation device a generated power prediction acquisition unit that acquires a prediction of the power generation amount prediction that calculates the power storage amount of the storage battery at each time based on the out-of-facility use schedule, the power consumption prediction, and the power generation prediction A calculating unit and a plan to charge the storage battery using externally supplied power during a time period when the power rate is relatively low so that the maximum value of the obtained power storage amount for each time becomes a predetermined maximum power storage amount. and a maximum storage amount adjustment unit that plans charging and discharging of the storage battery so that the storage amount at the end of outside use, which is the amount of storage in the storage battery at the scheduled end time of use outside the facility, is equal to or greater than a predetermined minimum storage amount. and an out-of-facility use power storage amount adjusting unit.

また、本発明の他の一態様による充放電計画方法は、自然エネルギー発電装置と、電力負荷と、蓄電池とを具備する施設における前記蓄電池の充放電を計画する充放電計画装置の充放電計画方法であって、前記蓄電池の前記施設外での使用を開始する予定時刻である施設外使用開始予定時刻と、当該使用を終了する予定時刻である施設外使用終了予定時刻と、当該使用に要する電力量の予測である施設外使用電力量予測とを含む施設外使用予定を取得する施設外使用予定取得ステップと、前記電力負荷の消費電力の予測を取得する消費電力予測取得ステップと、前記自然エネルギー発電装置の発電電力の予測を取得する発電電力予測取得ステップと、前記施設外使用予定と、前記消費電力の予測と、前記発電電力の予測とに基づいて、時刻毎の前記蓄電池の蓄電量を算出する蓄電量予測算出ステップと、得られた時刻毎の蓄電量における最大値が所定の蓄電量最大値となるように、電力料金が比較的安価な時間帯における外部供給電力を用いての前記蓄電池の充電を計画する最大蓄電量調整ステップと、前記施設外使用終了予定時刻における前記蓄電池の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値以上となるように前記蓄電池の充放電を計画する施設外使用時蓄電量調整ステップと、を具備することを特徴とする。 A charging/discharging planning method according to another aspect of the present invention is a charging/discharging planning method for a charging/discharging planning device that plans charging/discharging of a storage battery in a facility that includes a natural energy power generation device, an electric power load, and a storage battery. The scheduled time to start using the storage battery outside the facility, which is the scheduled time to start using the storage battery outside the facility, the scheduled time to end the use outside the facility, which is the scheduled time to end the use, and the power required for the use an out-of-facility usage schedule acquisition step of acquiring an out-of-facility usage schedule including an out-of-facility usage forecast that is an estimate of the amount of power consumption; a power consumption prediction acquisition step of acquiring a prediction of the power consumption of the power load; Based on a generated power prediction obtaining step of obtaining a predicted generated power of a power generation device, the schedule for use outside the facility, the prediction of the power consumption, and the prediction of the generated power, the amount of power stored in the storage battery for each time is calculated. and the step of calculating the stored electricity amount prediction calculation step, and the above-mentioned using the externally supplied electric power in a time period when the electricity rate is relatively low so that the maximum value of the obtained accumulated electricity amount for each time becomes a predetermined maximum value of the accumulated electricity amount. a maximum storage amount adjustment step of planning charging of the storage battery; and an out-of-facility storage amount adjustment step for planning charging and discharging.

また、本発明の他の一態様によるプログラムは、自然エネルギー発電装置と、電力負荷と、蓄電池とを具備する施設における前記蓄電池の充放電を計画する充放電計画装置としてのコンピュータに、前記蓄電池の前記施設外での使用を開始する予定時刻である施設外使用開始予定時刻と、当該使用を終了する予定時刻である施設外使用終了予定時刻と、当該使用に要する電力量の予測である施設外使用電力量予測とを含む施設外使用予定を取得する施設外使用予定取得ステップと、前記電力負荷の消費電力の予測を取得する消費電力予測取得ステップと、前記自然エネルギー発電装置の発電電力の予測を取得する発電電力予測取得ステップと、前記施設外使用予定と、前記消費電力の予測と、前記発電電力の予測とに基づいて、時刻毎の前記蓄電池の蓄電量を算出する蓄電量予測算出ステップと、得られた時刻毎の蓄電量における最大値が所定の蓄電量最大値となるように、電力料金が比較的安価な時間帯における外部供給電力を用いての前記蓄電池の充電を計画する最大蓄電量調整ステップと、前記施設外使用終了予定時刻における前記蓄電池の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値以上となるように前記蓄電池の充放電を計画する施設外使用時蓄電量調整ステップと、を実行させるためのプログラムである。 Further, a program according to another aspect of the present invention provides a computer as a charge/discharge planning device that plans charging and discharging of the storage battery in a facility that includes a natural energy power generation device, an electric load, and a storage battery, and stores the storage battery in the computer. The scheduled time to start using outside the facility, which is the scheduled time to start using outside the facility, the scheduled ending time for using outside the facility, which is the scheduled time to end the use, and the estimated amount of power required for the use. an out-of-facility usage schedule acquisition step of acquiring an out-of-facility usage schedule including a forecast of power consumption; a power consumption prediction acquisition step of acquiring a prediction of the power consumption of the power load; and a prediction of the power generated by the natural energy power generation device. a power generation prediction obtaining step of obtaining a power generation prediction obtaining step of calculating the power storage amount of the storage battery for each time based on the out-of-facility use schedule, the power consumption prediction, and the power generation prediction calculation step Then, the maximum value for charging the storage battery using the externally supplied power in the time period when the power rate is relatively low so that the maximum value of the obtained power storage amount for each time becomes the predetermined maximum power storage amount a step of adjusting the amount of stored electricity, and planning the charging and discharging of the storage battery so that the amount of electricity stored in the storage battery at the scheduled end time of the use outside the facility, which is the amount of electricity stored in the storage battery at the time when the usage outside the facility ends, is equal to or greater than a predetermined minimum amount of storage. and an in-use power storage amount adjustment step.

また、本発明の他の一態様による蓄電池は、自然エネルギー発電装置と、電力負荷と、蓄電池とを具備する施設において電力の管理を行う電力管理装置により制御される蓄電池であって、前記電力管理装置は、前記蓄電池の前記施設外での使用を開始する予定時刻である施設外使用開始予定時刻、当該使用を終了する予定時刻である施設外使用終了予定時刻、および当該使用に要する電力量の予測である施設外使用電力量予測を含む施設外使用予定と、前記電力負荷の消費電力の予測と、前記自然エネルギー発電装置の発電電力の予測とに基づいて、時刻毎の前記蓄電池の蓄電量を算出する蓄電量予測算出部と、得られた時刻毎の蓄電量における最大値が所定の蓄電量最大値となるように、電力料金が比較的安価な時間帯における外部供給電力を用いての前記蓄電池の充電を計画する最大蓄電量調整部と、前記施設外使用終了予定時刻における前記蓄電池の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値以上となるように前記蓄電池の充放電を計画する施設外使用時蓄電量調整部と、得られた計画に基づいて前記蓄電池の充放電を制御する充放電制御部と、を具備し、前記蓄電池は、前記外部供給電力を含めて強制的に一定の電力で充電する充電モードと、充電および放電ともに行わない待機モードと、前記自然エネルギー発電装置の発電電力が前記電力負荷の消費電力より大きい場合に充電を行うオートモードとを有し、前記電力管理装置は、時刻毎に、前記蓄電池の前記充電モード、前記待機モード、及び前記オートモードをいずれかに設定する。 Further, a storage battery according to another aspect of the present invention is a storage battery controlled by a power management device that manages power in a facility that includes a natural energy power generation device, a power load, and a storage battery, wherein the power management The device has a scheduled time to start using the storage battery outside the facility, a scheduled time to end the use outside the facility, a scheduled time to end the use, and an amount of power required for the use. The amount of power stored in the storage battery for each time based on the schedule for use outside the facility including the prediction of the amount of power used outside the facility as a prediction, the prediction of the power consumption of the power load, and the prediction of the power generated by the natural energy power generation device. and an externally supplied power during a period when the power rate is relatively low so that the maximum value of the obtained stored power amount for each time becomes a predetermined maximum stored power amount. a maximum storage amount adjustment unit that plans charging of the storage battery; and a charge/discharge control unit that controls charging/discharging of the storage battery based on the obtained plan, wherein the storage battery supplies the externally supplied power. a charging mode in which charging is forcibly performed with a constant power, including; a standby mode in which neither charging nor discharging is performed; and an auto mode in which charging is performed when the power generated by the natural energy generator is greater than the power consumed by the power load. and the power management device sets the charging mode, the standby mode, or the auto mode of the storage battery for each time.

また、本発明の他の一態様による蓄電池は、自然エネルギー発電装置と、電力負荷とを具備する施設に含まれ、充放電を計画する充放電計画装置により充放電が計画される蓄電池であって、前記充放電計画装置は、前記蓄電池の前記施設外での使用を開始する予定時刻である施設外使用開始予定時刻、当該使用を終了する予定時刻である施設外使用終了予定時刻、および当該使用に要する電力量の予測である施設外使用電力量予測を含む施設外使用予定と、前記電力負荷の消費電力の予測と、前記自然エネルギー発電装置の発電電力の予測とに基づいて、時刻毎の前記蓄電池の蓄電量を算出する蓄電量予測算出部と、得られた時刻毎の蓄電量における最大値が所定の蓄電量最大値となるように、電力料金が比較的安価な時間帯における外部供給電力を用いての前記蓄電池の充電を計画する最大蓄電量調整部と、前記施設外使用終了予定時刻における前記蓄電池の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値以上となるように前記蓄電池の充放電を計画する施設外使用時蓄電量調整部と、を具備し、前記蓄電池は、前記外部供給電力を含めて強制的に一定の電力で充電する充電モードと、充電および放電ともに行わない待機モードと、前記自然エネルギー発電装置の発電電力が前記電力負荷の消費電力より大きい場合に充電を行うオートモードとを有し、前記電力管理装置は、時刻毎に、前記蓄電池の前記充電モード、前記待機モード、及び前記オートモードをいずれかに設定する。 Further, a storage battery according to another aspect of the present invention is a storage battery that is included in a facility that includes a natural energy power generation device and an electric power load, and whose charging and discharging is planned by a charging and discharging planning device that plans charging and discharging. , the charging/discharging planning device includes a scheduled time to start using the storage battery outside the facility, a scheduled time to start using the storage battery outside the facility, a scheduled time to finish using the storage battery outside the facility, and a scheduled time to finish using the storage battery outside the facility. Based on the schedule for use outside the facility including the prediction of the amount of power used outside the facility, which is the prediction of the amount of power required for each time, the prediction of the power consumption of the power load, and the prediction of the power generated by the natural energy power generation device A power storage amount prediction calculation unit that calculates the power storage amount of the storage battery, and an external supply during a time period when the power rate is relatively low so that the maximum value of the power storage amount obtained for each time becomes a predetermined power storage amount maximum value. a maximum storage amount adjustment unit that plans charging of the storage battery using electric power; a charging mode in which the storage battery is forcibly charged with a constant power including the externally supplied power; and an auto mode in which charging is performed when the power generated by the natural energy power generating device is greater than the power consumed by the power load. , the charging mode, the standby mode, and the auto mode.

また、本発明の他の一態様による車両は、上述の蓄電池を搭載した車両である。 A vehicle according to another aspect of the present invention is a vehicle equipped with the storage battery described above.

本発明によれば、1つの蓄電池にて電力供給対象の施設における電力負荷に電力を供給しつつ、蓄電池の施設外使用において電気不足を回避することができる。 ADVANTAGE OF THE INVENTION According to this invention, while supplying electric power to the electric power load in the facility of the electric power supply object with one storage battery, electricity shortage can be avoided when the storage battery is used outside the facility.

本発明の第1の実施形態における電力管理装置を備える施設の構成を示す概略構成図である。1 is a schematic configuration diagram showing the configuration of a facility provided with a power management device according to the first embodiment of the present invention; FIG. 同実施形態における電力管理装置の機能構成を示す概略ブロック図である。It is a schematic block diagram which shows the functional structure of the power management apparatus in the same embodiment. 同実施形態において消費電力予測取得部が取得する電力負荷の消費電力の予測の例を示すグラフである。It is a graph which shows the example of the prediction of the power consumption of a power load which the power consumption prediction acquisition part acquires in the same embodiment. 同実施形態において発電電力予測取得部が取得する自然エネルギー発電装置の発電電力の予測の例を示すグラフである。4 is a graph showing an example of prediction of generated power of a natural energy power generation device acquired by a generated power prediction acquisition unit in the same embodiment. 同実施形態において蓄電量予測算出部が算出する需給予測の例を示すグラフである。It is a graph which shows the example of the demand-and-supply prediction which the electrical storage amount prediction calculation part calculates in the same embodiment. 同実施形態において蓄電量予測算出部が算出する蓄電池の蓄電量の例を示すグラフである。It is a graph which shows the example of the electrical storage amount of a storage battery which the electrical storage amount prediction calculation part calculates in the same embodiment. 同実施形態において、最大蓄電量調整部が、最大ピーク蓄電量が最大蓄電量SOCmaxになるように、安価期間での充電を計画した例を示すグラフである。In the same embodiment, it is a graph which shows the example which planned charging in a cheap period so that the maximum peak electrical storage amount might become maximum electrical storage amount SOCmax. 同実施形態にて、充電計画部が安価期間における充電にて蓄電量を確保する例を示すグラフである。It is a graph which shows the example which a charge planning part secures the electrical storage amount by charge in a cheap period in the same embodiment. 同実施形態にて、充電計画部が、蓄電池の施設外使用の直前の時間帯において蓄電池の充電を行うよう計画した例を示すグラフである。7 is a graph showing an example in which the charging planning unit plans to charge the storage battery in the time period immediately before the storage battery is used outside the facility in the same embodiment. 同実施形態において、放電抑制計画部が、蓄電池の放電を抑制することで、施設外使用時に必要な蓄電量を確保する例を示すグラフである。In the same embodiment, it is a graph which shows the example which secures the required electrical storage amount at the time of outside use by suppressing discharge of a storage battery by the discharge suppression planning part. 同実施形態において、放電抑制計画部が、外部供給電力を用いての蓄電池の充電を計画した例を示すグラフである。In the same embodiment, it is a graph which shows the example which the discharge suppression planning part planned charging of the storage battery using the externally supplied electric power. 同実施形態において、電力管理装置が蓄電池の充放電計画を生成する処理手順を示すフローチャートである。In the same embodiment, it is a flow chart which shows a processing procedure by which a power management device generates a charging/discharging plan of a storage battery. 同実施形態において、施設外使用時蓄電量調整部が、蓄電池の施設外使用に必要な蓄電量を確保する処理の手順を示すフローチャートである。4 is a flow chart showing a procedure of a process in which an out-of-facility use power storage amount adjusting unit secures a power storage amount necessary for out-of-facility use of a storage battery in the same embodiment. 同実施形態において、施設外使用時蓄電量調整部が行うかさ上げ処理の手順を示すフローチャートである。In the same embodiment, it is a flow chart which shows the procedure of the padding processing which the charge amount adjustment part at the time of facility use performs. 同実施形態において、充電計画部がピーク前処理を行う手順を示すフローチャートである。In the same embodiment, it is a flowchart which shows the procedure which a charge planning part performs a peak pre-processing. 同実施形態において、充電計画部が安価期間でのピーク前処理を行う手順を示すフローチャートである。In the same embodiment, it is a flowchart which shows the procedure in which a charge planning part performs the peak pre-processing in a cheap period. 同実施形態において、充電計画部が高価期間でのピーク前処理を行う手順を示すフローチャートである。In the same embodiment, it is a flow chart which shows the procedure in which the charge planning unit performs the peak pre-processing in the expensive period. 同実施形態において、放電抑制計画部がピーク後処理を行う手順を示すフローチャートである。In the same embodiment, it is a flowchart which shows the procedure which a discharge suppression planning part performs a peak post-processing. 同実施形態における、最大ピーク時直後まで放電禁止を考慮するスケジュールの例を示すグラフである。FIG. 10 is a graph showing an example of a schedule considering discharge prohibition until immediately after the maximum peak time in the same embodiment; FIG. 同実施形態における、処理開始時刻から車両使用開始のSOCとなるまで変更無しとし、その後は放電禁止を考慮したスケジュールの例を示すグラフである。10 is a graph showing an example of a schedule in which no change is made from the processing start time until the vehicle use start SOC is reached, and discharge is prohibited after that, according to the same embodiment.

<第1の実施形態>
以下、図面を参照して、本発明の実施の形態について説明する。
図1は、本発明の第1の実施形態における電力管理装置を備える施設の構成を示す概略構成図である。同図において、施設1は、電力管理装置100と、蓄電池201を搭載した車両200と、自然エネルギー発電装置300と、電力負荷400とを具備する。
<First Embodiment>
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 is a schematic configuration diagram showing the configuration of a facility equipped with a power management device according to the first embodiment of the present invention. In the figure, facility 1 includes power management device 100 , vehicle 200 equipped with storage battery 201 , natural energy power generation device 300 , and power load 400 .

電力管理装置100は、施設内において発電され、または消費される電力の管理を行う。また、電力管理装置100は、ネットワーク500に接続されており、当該ネットワーク500を介して天気予報などの情報を受信する。電力管理装置100は、充放電計画装置の一例に該当し、電力管理に際して蓄電池201の充放電を計画する。
なお、電力管理装置100は、自然エネルギー発電装置300による電力自給率の向上を目的として電力管理を行う。太陽光発電等が普及して逆潮流が増加すると、商用電力系統側への売電を行えなくなることや、売電価格が買電価格よりも安くなることが考えられる。かかる場合、自然エネルギー発電装置300による電力自給率を向上させて買電量を低減させることが望まれる。
The power management device 100 manages power generated or consumed within the facility. The power management apparatus 100 is also connected to a network 500 and receives information such as weather forecasts via the network 500 . The power management device 100 corresponds to an example of a charge/discharge planning device, and plans charge/discharge of the storage battery 201 in power management.
The power management device 100 performs power management for the purpose of improving the power self-sufficiency rate of the natural energy power generation device 300 . If the reverse power flow increases due to the spread of photovoltaic power generation, etc., it is conceivable that it will become impossible to sell power to the commercial power system side, and that the power selling price will become lower than the power buying price. In such a case, it is desirable to improve the power self-sufficiency rate of the natural energy power generator 300 and reduce the amount of purchased power.

車両200は、搭載する蓄電池201から供給される電力により走行する。また、車両200が施設内に停車しているときは、電力管理装置100によって蓄電池201の充放電が制御される。
ただし、蓄電池201から供給される電力による車両200の走行は、蓄電池201の施設外使用の一例であり、これに限らない。ここでいう、蓄電池201の施設外使用とは、自然エネルギー発電装置300や電力負荷400と切り離した状態での蓄電池201の使用である。例えば、蓄電池201を使用する系統を切り替える場合のように、蓄電池201の施設外使用は、蓄電池201の移動を伴わない使用であってもよい。
自然エネルギー発電装置300は、太陽光または風力などの自然エネルギーによる発電を行う。
電力負荷400は、施設に設けられた電気機器の総称であり、蓄電池201が供給する電力、自然エネルギー発電装置300が供給する電力、または系統電力などの外部供給電力によって稼働する。
The vehicle 200 runs on electric power supplied from a storage battery 201 mounted thereon. Further, when the vehicle 200 is stopped within the facility, the power management device 100 controls charging and discharging of the storage battery 201 .
However, running of the vehicle 200 on the power supplied from the storage battery 201 is an example of the use of the storage battery 201 outside the facility, and is not limited to this. Here, the use of the storage battery 201 outside the facility is the use of the storage battery 201 in a state in which the natural energy power generation device 300 and the power load 400 are disconnected. For example, the use of the storage battery 201 outside the facility may be a use that does not involve moving the storage battery 201, as in the case of switching the system that uses the storage battery 201.
The natural energy power generator 300 generates power using natural energy such as sunlight or wind power.
The electric power load 400 is a general term for electrical equipment provided in a facility, and is operated by power supplied by the storage battery 201, power supplied by the natural energy power generation device 300, or externally supplied power such as grid power.

ここで、施設1が外部から供給を受ける電力(外部供給電力)の使用料金は、電力供給を受ける時刻によって異なる。例えば、午後11時から午前7時の時間帯は、午前7時から午後11時までの時間帯と比較して外部供給電力の使用料金が安くなる。
そこで、電力管理装置100は、午後11時から午前7時の時間帯(安価期間)の間に、外部供給電力を用いる蓄電池201の充電(後述する充電モードでの充電)を行い、午前7時から午後11時の時間帯(高価期間)の間、蓄電池201が供給する電力によって電力負荷400を稼働させる。したがって、電力管理装置100は、高価期間の間、蓄電池201が供給する電力によって電力負荷400を稼働させることができるよう、蓄電池201の容量の制御を行う。
Here, the usage fee for the power (externally supplied power) supplied to the facility 1 from the outside varies depending on the time at which the power is supplied. For example, in the time period from 11:00 pm to 7:00 am, the charge for use of externally supplied power is lower than in the time period from 7:00 am to 11:00 pm.
Therefore, the power management apparatus 100 charges the storage battery 201 using the externally supplied power (charging in a charging mode described later) during the time period (low cost period) from 11:00 pm to 7:00 am. to 11:00 pm (expensive period), the power load 400 is operated by the power supplied by the storage battery 201 . Therefore, the power management apparatus 100 controls the capacity of the storage battery 201 so that the power load 400 can be operated by the power supplied by the storage battery 201 during the expensive period.

図2は、電力管理装置100の機能構成を示す概略ブロック図である。同図において、電力管理装置100は、施設外使用予定取得部110と、消費電力予測取得部120と、発電電力予測取得部130と、蓄電量予測算出部140と、最大蓄電量調整部150と、施設外使用時蓄電量調整部160と、充放電制御部170とを具備する。施設外使用時蓄電量調整部160は、調整要否判定部161と、前後判定部162と、充電計画部163と、放電抑制計画部164とを具備する。 FIG. 2 is a schematic block diagram showing the functional configuration of the power management device 100. As shown in FIG. In the figure, the power management apparatus 100 includes an out-of-facility usage schedule acquisition unit 110, a power consumption prediction acquisition unit 120, a power generation prediction acquisition unit 130, a power storage amount prediction calculation unit 140, and a maximum power storage amount adjustment unit 150. , an out-of-facility use power storage amount adjustment unit 160 and a charge/discharge control unit 170 . The outside-of-facility use power storage amount adjustment unit 160 includes an adjustment necessity determination unit 161 , a before/after determination unit 162 , a charge planning unit 163 , and a discharge suppression planning unit 164 .

以下では、電力管理装置100が、安価期間の開始時刻である午後11時から翌午後11時までの1日分の充放電計画を生成する場合を例に説明する。このように安価期間の開始時刻をから次の安価期間の開始時刻までの計画を立てることで、安価期間になるべく充電しておき、高価期間における充電を低減させる計画を比較的生成し易くなる。 A case where the power management apparatus 100 generates a charge/discharge plan for one day from 11:00 pm, which is the start time of the low cost period, to 11:00 pm the following day will be described below as an example. By making a plan from the start time of the low-price period to the start time of the next low-price period in this way, it becomes relatively easy to generate a plan for charging as much as possible during the low-price period and reducing charging during the high-price period.

また、以下では、電力管理装置100が、1分毎の充放電計画を生成する場合を例に説明するが、これに限らない。例えば、電力管理装置100が、5分毎など、より長い時間間隔で充放電計画を生成するようにしてもよいし、30秒毎など、より短い時間間隔で充放電計画を生成するようにしてもよい。 Moreover, although the case where the power management apparatus 100 produces|generates the charging/discharging plan for every 1 minute is demonstrated below as an example, it does not restrict to this. For example, the power management apparatus 100 may generate the charging/discharging plan at longer time intervals such as every 5 minutes, or may generate the charging/discharging plan at shorter time intervals such as every 30 seconds. good too.

施設外使用予定取得部110は、蓄電池201の施設1外での使用を開始する予定時刻である施設外使用開始予定時刻と、当該使用を終了する予定時刻である施設外使用終了予定時刻と、当該使用に要する電力量の予測である施設外使用電力量予測とを含む施設外使用予定を取得する。
例えば、施設外使用予定取得部110は、電力管理装置100のユーザ(以下、単に「ユーザ」と称する)から、車両200の使用予定の入力を受け付ける。
The out-of-facility use schedule acquisition unit 110 acquires a scheduled out-of-facility use start time that is a scheduled time to start using the storage battery 201 outside the facility 1, a scheduled out-of-facility use end time that is a scheduled time to end the use, and An out-of-facility usage schedule is obtained that includes an out-of-facility power usage prediction that is a prediction of the amount of power required for the use.
For example, the out-of-facility usage schedule acquisition unit 110 receives an input of the usage schedule of the vehicle 200 from the user of the power management device 100 (hereinafter simply referred to as “user”).

この場合、車両200の使用予定の入力は、使用予定がある日の前日までにユーザによって使用予定毎に行われるのが原則であるが、施設外使用予定取得部110は、使用目的に応じて使用予定を推測することで、一部の情報の入力を省略する。
具体的には、車両200の使用目的が通勤などの定期利用である場合、施設外使用予定取得部110は、初回にユーザから使用開始予定時刻、運転距離、及び使用時間、並びに繰り返しパターンの入力を受け付けて、内部のデータベースにこの情報を記録する。例えば、施設外使用予定取得部110は、使用開始予定時刻=午前7時、運転距離=30キロメートル(km)、使用時間=10時間、繰り返しパターン=毎週月~金といった入力を受ける。
そして、施設外使用予定取得部110は、当該使用予定と同じ使用予定を、繰り返しパターン毎に設定する。従って、ユーザは、2回目以降の入力を省略することができる。
In this case, in principle, the use schedule of the vehicle 200 is input by the user for each use schedule by the day before the scheduled use date. By estimating the usage schedule, input of some information is omitted.
Specifically, when the purpose of using the vehicle 200 is regular use such as commuting, the out-of-facility use schedule acquisition unit 110 initially inputs the scheduled start time of use, driving distance, usage time, and repetition pattern from the user. and record this information in an internal database. For example, the out-of-facility usage schedule acquisition unit 110 receives inputs such as scheduled usage start time = 7:00 am, driving distance = 30 kilometers (km), usage time = 10 hours, repetition pattern = every week from Monday to Friday.
Then, the out-of-facility usage schedule acquisition unit 110 sets the same usage schedule as the usage schedule for each repetition pattern. Therefore, the user can omit input from the second time onward.

また、車両200の使用目的が買い物などの高頻度不定期利用である場合、施設外使用予定取得部110は、初回にユーザから運転距離及び使用時間の入力を受け付けて、内部のデータベースにこの情報を記録する。例えば、施設外使用予定取得部110は、使用開始予定時刻=午前10時、運転距離=10キロメートル、使用時間=2時間といった入力を受ける。
2回目以降の入力では、施設外使用予定取得部110は、使用予定時刻のみをユーザから受け付け、残りのパラメータは、当該使用予定と同じものを用いる。これは、車両200を買物などに利用する場合、行き先及び買物に要する時間がほぼ変わらないと推測されるためである。
なお、車両200の使用目的が単発利用である場合、使用予定を予測することは困難であるため、施設外使用予定取得部110は、当該使用予定の入力を毎回受け付ける。例えば、施設外使用予定取得部110は、使用開始予定時刻=午前8時、運転距離=200キロメートル、使用時間=48時間といった入力を受ける。
Further, when the purpose of using the vehicle 200 is frequent irregular use such as shopping, the out-of-facility use schedule acquisition unit 110 first receives input of driving distance and usage time from the user, and stores this information in the internal database. record. For example, the out-of-facility usage schedule acquisition unit 110 receives inputs such as scheduled usage start time = 10:00 am, driving distance = 10 kilometers, usage time = 2 hours.
For the second and subsequent inputs, the out-of-facility usage schedule acquisition unit 110 receives only the scheduled usage time from the user, and uses the same parameters as the usage schedule for the remaining parameters. This is because it is assumed that when the vehicle 200 is used for shopping, the destination and the time required for shopping are almost the same.
If the purpose of use of the vehicle 200 is one-time use, it is difficult to predict the use schedule, so the out-of-facility use schedule acquisition unit 110 receives the input of the use schedule each time. For example, the out-of-facility usage schedule acquisition unit 110 receives inputs such as scheduled usage start time = 8:00 am, driving distance = 200 kilometers, usage time = 48 hours.

消費電力予測取得部120は、電力負荷400の消費電力の予測を取得する。例えば、消費電力予測取得部120は、ネットワーク500を介して取得した天気予報や、過去の電力負荷400の稼働履歴などに基づいて、電力管理装置100が充放電計画を生成する対象期間について、計画生成対象の時刻毎(以下、単に「時刻毎」と称する)の電力負荷400の消費電力を予測する。例えば、消費電力予測取得部120は、23時から翌23時までの期間について、電力負荷400の1分毎の消費電力を予測する。あるいは、消費電力予測取得部120が電力負荷400の制御部など電力管理装置100の外部から予測を取得するようにしてもよい。 The power consumption prediction acquisition unit 120 acquires prediction of power consumption of the power load 400 . For example, the power consumption prediction acquisition unit 120 determines the target period for which the power management apparatus 100 generates the charge/discharge plan based on the weather forecast acquired via the network 500, the past operation history of the power load 400, and the like. The power consumption of the power load 400 is predicted for each generation target time (hereinafter simply referred to as “each time”). For example, the power consumption prediction acquisition unit 120 predicts the power consumption of the power load 400 for each minute from 23:00 to 23:00. Alternatively, the power consumption prediction acquisition unit 120 may acquire the prediction from outside the power management apparatus 100 such as the control unit of the power load 400 .

図3は、消費電力予測取得部120が取得する電力負荷400の消費電力の予測の例を示すグラフである。同図の横軸は時刻を示し、縦軸は、電力負荷400の消費電力を示す。なお、時刻の「-2」は、前日の午後10時を示す。
図3において、消費電力予測取得部120は、安価期間の開始時刻である23時から翌23時までの、電力負荷400の消費電力を予測している。
FIG. 3 is a graph showing an example of prediction of power consumption of the power load 400 acquired by the power consumption prediction acquisition unit 120. As shown in FIG. The horizontal axis of the figure indicates the time, and the vertical axis indicates the power consumption of the power load 400 . The time "-2" indicates 10:00 pm of the previous day.
In FIG. 3, the power consumption prediction acquisition unit 120 predicts the power consumption of the power load 400 from 23:00, which is the start time of the low price period, to 23:00 the next day.

発電電力予測取得部130は、自然エネルギー発電装置300の発電電力の予測を取得する。例えば、発電電力予測取得部130は、ネットワーク500を介して取得した天気予報などに基づいて、電力管理装置100が充放電計画を生成する対象期間について、自然エネルギー発電装置300の時刻毎の発電電力を予測する。あるいは、発電電力予測取得部130が自然エネルギー発電装置300の制御部など電力管理装置100の外部から予測を取得するようにしてもよい。 The generated power prediction acquisition unit 130 acquires a prediction of the generated power of the natural energy power generation device 300 . For example, based on the weather forecast acquired via the network 500, the power generation prediction acquisition unit 130 generates power generated by the natural energy power generation device 300 at each time for the target period for which the power management device 100 generates the charge/discharge plan. to predict. Alternatively, the generated power prediction acquisition unit 130 may acquire the prediction from outside the power management device 100 such as the control unit of the natural energy power generation device 300 .

図4は、発電電力予測取得部130が取得する自然エネルギー発電装置300の発電電力の予測の例を示すグラフである。同図の横軸は時刻を示し、縦軸は、電力負荷400の消費電力を示す。
図4において、発電電力予測取得部130は、安価期間の開始時刻である23時から翌23時までの、電力負荷400の消費電力を予測している。発電電力予測取得部130の発電量は、太陽光の照射する昼間の時刻に大きくなっている。
FIG. 4 is a graph showing an example of prediction of the power generated by the natural energy power generation device 300 acquired by the power generation prediction acquisition unit 130 . The horizontal axis of the figure indicates the time, and the vertical axis indicates the power consumption of the power load 400 .
In FIG. 4, the generated power prediction acquisition unit 130 predicts the power consumption of the power load 400 from 23:00, which is the start time of the low price period, to 23:00 the next day. The amount of power generated by the power generation prediction acquisition unit 130 is large during the daytime when the sun is shining.

蓄電量予測算出部140は、施設外使用予定と、消費電力予測と、発電電力予測とに基づいて、時刻毎の蓄電池201の蓄電量を算出する。具体的には、蓄電量予測算出部140は、まず、自然エネルギー発電装置300の発電電力予測値から、電力負荷400の消費電力予測値と、車両200の消費電力予測値とを減算して、時刻毎の需給予測を算出する。そして、蓄電量予測算出部140は、得られた需給予測を積算して、外部供給電力を用いての充電を行わない場合の、時刻毎の蓄電池201の蓄電量を算出する。 The power storage amount prediction calculation unit 140 calculates the power storage amount of the storage battery 201 for each time based on the out-of-facility use schedule, the power consumption prediction, and the power generation prediction. Specifically, the stored electricity amount prediction calculation unit 140 first subtracts the predicted power consumption value of the power load 400 and the predicted power consumption value of the vehicle 200 from the predicted power generation value of the natural energy power generation device 300, Calculate the supply and demand forecast for each hour. Then, the stored electricity amount prediction calculation unit 140 integrates the obtained demand-supply prediction, and calculates the amount of electricity stored in the storage battery 201 at each time when charging is not performed using the externally supplied power.

図5は、蓄電量予測算出部140が算出する需給予測の例を示すグラフである。同図の横軸は時刻を示し、縦軸は電力需給を示す。同図の上側が、自然エネルギー発電装置300および電力負荷400から見ての供給側を示し、下側が、自然エネルギー発電装置300および電力負荷400から見ての需要側を示す。
同図にM11~M13で示す時間は、車両200の使用が予定されている時間であり、使用目的から想定される消費電力が設定されている。他の時間では、自然エネルギー発電装置300の発電電力から電力負荷400の消費電力を減算した値が設定されている。
FIG. 5 is a graph showing an example of demand and supply prediction calculated by the stored electricity amount prediction calculation unit 140. As shown in FIG. In the figure, the horizontal axis indicates time, and the vertical axis indicates power supply and demand. The upper side of the figure shows the supply side as seen from the natural energy power generator 300 and the power load 400 , and the lower side shows the demand side as seen from the natural energy power generator 300 and the power load 400 .
The time indicated by M11 to M13 in the figure is the time during which the vehicle 200 is scheduled to be used, and the power consumption assumed from the purpose of use is set. At other times, a value obtained by subtracting the power consumption of the power load 400 from the power generated by the natural energy power generator 300 is set.

需給予測が得られると、蓄電量予測算出部140は、得られた需給予測を積算して、外部供給電力を用いての充電を行わない場合の、時刻毎の蓄電池201の蓄電量を算出する。具体的には、蓄電量予測算出部140は、計画生成対象時間の開始時刻(以下、単に「開始時刻」と称する)における蓄電量を取得し、当該蓄電量に需給予測で得られた電力値を時刻毎に順次積算していくことで、時刻毎の蓄電量を算出する。
図6は、蓄電量予測算出部140が算出する蓄電池201の蓄電量の例を示すグラフである。
同図の横軸は時刻を示し、縦軸は蓄電池201の蓄電量(SOC)を示している。なお、同図のSOCmaxは、蓄電池201の運用において許容される最大蓄電量を示し、SOCminは、蓄電池201の運用において許容される最小蓄電量を示す。図6の例では、8時頃~11時頃の時間帯において、蓄電池201の蓄電量が蓄電量最小値SOCmin以下となっている。この段階では蓄電池201の蓄電量の調整は、まだ行われていないためである。
When the supply and demand prediction is obtained, the stored electricity amount prediction calculation unit 140 integrates the obtained demand and supply prediction, and calculates the amount of electricity stored in the storage battery 201 at each time when charging is not performed using the externally supplied power. . Specifically, the stored electricity amount prediction calculation unit 140 acquires the stored electricity amount at the start time of the plan generation target time (hereinafter simply referred to as “start time”), is sequentially integrated for each time to calculate the amount of stored electricity for each time.
FIG. 6 is a graph showing an example of the power storage amount of the storage battery 201 calculated by the power storage amount prediction calculation unit 140 .
In the figure, the horizontal axis indicates time, and the vertical axis indicates the amount of charge (SOC) of storage battery 201 . In addition, SOCmax in the same figure indicates the maximum amount of stored electricity that is allowed in the operation of the storage battery 201, and SOCmin indicates the minimum amount of stored electricity that is allowed in the operation of the storage battery 201. FIG. In the example of FIG. 6, in the time period from about 8:00 to about 11:00, the power storage amount of the storage battery 201 is equal to or less than the power storage amount minimum value SOCmin. This is because the adjustment of the amount of electricity stored in the storage battery 201 has not yet been performed at this stage.

最大蓄電量調整部150は、得られた時刻毎の蓄電量における最大値(以下、「最大ピーク蓄電量」と称する)が所定の蓄電量最大値SOCmaxとなるように、電力料金が比較的安価な時間帯における外部供給電力を用いての、蓄電池201の充電を計画する。具体的には、最大蓄電量調整部150は、まず、蓄電池201の蓄電量が最大となっている時刻(以下、「最大ピーク時刻」と称する)を検出する。図6の例では、16時の手前の時刻において蓄電量が最大となっている。 The maximum stored electricity amount adjustment unit 150 adjusts the power rate so that the maximum value of the obtained stored electricity amount at each time (hereinafter referred to as “maximum peak stored electricity amount”) becomes a predetermined maximum stored electricity amount SOCmax. The charging of the storage battery 201 is planned using the externally supplied electric power in a certain time period. Specifically, the maximum power storage amount adjustment unit 150 first detects the time when the power storage amount of the storage battery 201 is at its maximum (hereinafter referred to as “maximum peak time”). In the example of FIG. 6, the amount of stored electricity is maximum at a time just before 16:00.

次に最大蓄電量調整部150は、蓄電池201の最大ピーク値が最大蓄電量SOCmaxになるように、安価期間での充電を計画する。すなわち、最大蓄電量調整部150は、自然エネルギー発電装置300の発電電力を蓄電可能な範囲でできるだけ安価期間に充電しておくよう計画する。これにより、高価期間における充電量を低減させ得る。なお、蓄電池201の最大ピーク値が最大蓄電量SOCmaxになるように調整することを「ピーク合わせ」と称する。 Next, the maximum storage amount adjustment unit 150 plans charging in the low cost period so that the maximum peak value of the storage battery 201 becomes the maximum storage amount SOCmax. That is, the maximum power storage amount adjustment unit 150 plans to charge the power generated by the natural energy power generation device 300 in the cheapest period possible within the power storage range. This can reduce the charge amount in the expensive period. Adjusting the maximum peak value of the storage battery 201 to the maximum storage amount SOCmax is referred to as “peak matching”.

図7は、最大蓄電量調整部150が、最大ピーク蓄電量が最大蓄電量SOCmaxになるように、安価期間での充電を計画した例を示すグラフである。同図の横軸は時刻を示し、縦軸は蓄電池201のSOC(以下単に「SOC」とも表記する)を示す。最大蓄電量調整部150は、安価期間の終了時刻である7時の手前の時間T11において、安価期間での充電を計画しており、SOCが上昇している。このSOCの上昇に伴い、点P11に示される最大ピーク蓄電量が最大蓄電量SOCmaxとなっている。 FIG. 7 is a graph showing an example in which the maximum stored electricity amount adjustment unit 150 plans charging in the inexpensive period so that the maximum peak stored electricity amount becomes the maximum stored electricity amount SOCmax. The horizontal axis of the figure indicates the time, and the vertical axis indicates the SOC of the storage battery 201 (hereinafter also simply referred to as "SOC"). At time T11 before 7:00, which is the end time of the low price period, the maximum storage amount adjustment unit 150 plans charging during the low price period, and the SOC is rising. As the SOC rises, the maximum peak storage amount shown at point P11 becomes the maximum storage amount SOCmax.

例えば、最大蓄電量調整部150は、安価期間の終了時刻である7時まで外部供給電力を用いて蓄電池201の充電を行うことに決定し、充電時間を、最大ピーク蓄電量が最大蓄電量SOCmaxになるように設定する。これにより、最大蓄電量調整部150は、図7の例のように、安価期間の終盤において外部供給電力を用いて蓄電池201の充電を行うよう計画する。充電時期を遅くすることで、最大蓄電量調整部150は、電力負荷400の消費電力が予測よりも少なかった場合に充電量を低減させることができる。したがって、電力管理装置100は、不必要な充電を回避することができる。 For example, the maximum power storage amount adjustment unit 150 determines to charge the storage battery 201 using the externally supplied power until 7:00, which is the end time of the low price period, and sets the charging time to the maximum peak power storage amount SOCmax. set to be As a result, the maximum storage amount adjusting unit 150 plans to charge the storage battery 201 using the externally supplied power at the end of the low price period, as in the example of FIG. 7 . By delaying the charging timing, maximum stored power amount adjustment unit 150 can reduce the amount of charge when the power consumption of power load 400 is less than expected. Therefore, the power management device 100 can avoid unnecessary charging.

施設外使用時蓄電量調整部160は、施設外使用終了予定時刻における蓄電池201の蓄電量(SOC)である施設外使用終了時蓄電量が所定の蓄電量最小値SOCmin以上となるように蓄電池の充放電を計画する。
ここで、施設外使用終了予定時刻において蓄電池201のSOCが蓄電量最小値SOCminより小さい場合、施設外使用において電気が不足することが予測される。施設1内部での電気の使用と異なり施設外使用では、商用電力などの外部供給電力を取得できないことが考えられる。このため、施設外使用における電気不足は多大な不都合を引き起こすおそれがある。例えば、車両200の走行中に電気が不足すると、車両200が走行できなくなり、施設1へ帰着できなくなってしまう。
そこで、施設外使用時蓄電量調整部160は、施設外使用において必要な電気を確保できるよう、施設外使用前に外部供給電力を用いて蓄電池201への充電を行うよう計画する。
The outside-use storage amount adjustment unit 160 adjusts the storage battery so that the outside-use storage amount, which is the storage amount (SOC) of the storage battery 201 at the out-of-facility use end scheduled time, is equal to or greater than a predetermined storage amount minimum value SOCmin. Plan charging and discharging.
Here, if the SOC of the storage battery 201 is smaller than the storage amount minimum value SOCmin at the scheduled end time of use outside the facility, it is predicted that electricity will be insufficient for use outside the facility. Unlike the use of electricity inside the facility 1, in the use outside the facility, it is conceivable that externally supplied power such as commercial power cannot be obtained. For this reason, a shortage of electricity in off-site use can cause a great deal of inconvenience. For example, if the vehicle 200 runs short of electricity, the vehicle 200 cannot run, and it becomes impossible to return to the facility 1 .
Therefore, the power storage amount adjusting unit 160 for use outside the facility plans to charge the storage battery 201 using the externally supplied power before use outside the facility so as to secure necessary electricity for use outside the facility.

ここで、蓄電池201は、充電モードと待機モードとオートモードとの3つのモードを有しており、施設外使用時蓄電量調整部160は、時刻毎に、蓄電池201のモードをいずれかに設定する。
充電モードとは、外部供給電力を含めて強制的に一定の電力で充電するモードである。例えば、自然エネルギー発電装置300の余剰発電が3キロワット(kW)あり、蓄電池201を5キロワットで充電する場合、自然エネルギー発電装置300の3キロワットと、外部供給電力の2キロワットとを合わせた5キロワットで蓄電池201の充電を行う。
Here, the storage battery 201 has three modes: a charging mode, a standby mode, and an auto mode. do.
The charge mode is a mode in which the battery is forcibly charged with a constant power including the externally supplied power. For example, when the surplus power generation of the natural energy power generation device 300 is 3 kilowatts (kW) and the storage battery 201 is charged with 5 kilowatts, the 3 kilowatts of the natural energy power generation device 300 and the 2 kilowatts of externally supplied power are combined to give 5 kilowatts. , the storage battery 201 is charged.

待機モードは、充電、放電とも行わないモードである。
オートモードでは、余剰電力がある場合(すなわち、自然エネルギー発電装置300の発電電力が、電力負荷400の消費電力より大きい場合)、余剰電力で充電を行う。例えば、余剰電力が3キロワットあれば、3キロワットで充電し1キロワットであれば1キロワットで充電する。
一方、電力が不足している場合(すなわち、自然エネルギー発電装置300の発電電力が、電力負荷400の消費電力以下である場合)、蓄電池201は放電を行う。
Standby mode is a mode in which neither charging nor discharging is performed.
In the auto mode, if there is surplus power (that is, if the power generated by the natural energy power generation device 300 is greater than the power consumed by the power load 400), charging is performed with the surplus power. For example, if the surplus power is 3 kilowatts, it is charged at 3 kilowatts, and if it is 1 kilowatts, it is charged at 1 kilowatts.
On the other hand, when the power is insufficient (that is, when the power generated by the natural energy power generator 300 is less than or equal to the power consumed by the power load 400), the storage battery 201 discharges.

車両200の使用との関係では、車両200が使用中(すなわち、蓄電池201が施設外使用中)または使用予定時刻の場合、施設外使用時蓄電量調整部160は、蓄電池201のモードを待機モードとする。一方、車両200が未使用の場合(従って、蓄電池201と電力負荷400や自然エネルギー発電装置300とを接続可能な場合)、充電が必要であれば充電モードとし、蓄電量確保のため放電を禁止するときは、待機モードとし、それ以外のときはオートモードとする。 In relation to the use of the vehicle 200, when the vehicle 200 is in use (that is, the storage battery 201 is in use outside the facility) or at the scheduled time of use, the storage battery amount adjusting unit 160 changes the mode of the storage battery 201 to the standby mode. and On the other hand, when the vehicle 200 is unused (thus, when the storage battery 201 can be connected to the power load 400 or the natural energy power generation device 300), if charging is necessary, the charging mode is set, and discharging is prohibited in order to secure the amount of stored electricity. Standby mode is selected when it is necessary, and auto mode is selected otherwise.

また、電力管理装置100が充放電計画を生成している時点で施設外使用が行われている場合、それ以降は全て待機モードとしておき、施設外使用終了後に計画しなおすようにする。すなわち、施設外使用がいつ終了するか分からず、計画を生成しても無駄になる可能性があるため、まずは待機モードとすることが考えられる。
また、施設外使用終了時においても、一度待機モードとし、蓄電量を検出し計画を生成し直した後に充電モードまたはオードモードとすることが考えられる。
Further, when the power management apparatus 100 is generating the charging/discharging plan and the use outside the facility is being performed, the standby mode is set thereafter, and the plan is rescheduled after the end of the use outside the facility. That is, since it is not known when the out-of-facility use will end, and even if a plan is generated, it may be useless, it is conceivable to first set the standby mode.
Also, when the use outside the facility is finished, it is conceivable that the standby mode is set once, and then the charge mode or the mode is set after the power storage amount is detected and the plan is generated again.

施設外使用時蓄電量調整部160において、調整要否判定部161は、施設外使用終了時蓄電量と、蓄電量最小値SOCminとを比較して蓄電量の調整要否を判定する。具体的には、施設外使用終了時蓄電量が蓄電量最小値SOCminより小さければ、調整要否判定部161は、調整必要と判定する。一方、施設外使用終了時蓄電量が蓄電量最小値SOCmin以上であれば、調整要否判定部161は、調整不要と判定する。 In the off-facility use power storage amount adjustment unit 160, an adjustment necessity determination unit 161 determines whether or not adjustment of the power storage amount is necessary by comparing the power storage amount at the end of off-facility use with the power storage amount minimum value SOCmin. Specifically, if the stored electricity amount at the end of use outside the facility is smaller than the stored electricity amount minimum value SOCmin, the adjustment necessity determination unit 161 determines that adjustment is necessary. On the other hand, if the stored electricity amount at the end of use outside the facility is equal to or greater than the minimum stored electricity amount SOCmin, the adjustment necessity determination unit 161 determines that adjustment is unnecessary.

前後判定部162は、調整要否判定部161が調整必要と判定すると、施設外使用終了予定時刻が、最大ピーク時刻より早いか否かを判定する。
充電計画部163は、施設外使用終了予定時刻が最大ピーク時刻より早いと前後判定部162が判定すると、外部供給電力を用いての蓄電池201の充電を計画する。施設外使用終了予定時刻が最大ピーク時刻より早い場合、安価期間における充電量を増やすことで、施設外使用時の蓄電池201の蓄電量を増やすことができる。安価期間に充電を行うことで、電気料金を安く抑えることができる。
そこで、充電計画部163は、蓄電池201を充電することで、施設外使用時に必要な蓄電量を確保する。
When the adjustment necessity determination unit 161 determines that adjustment is necessary, the before/after determination unit 162 determines whether or not the scheduled end time of use outside the facility is earlier than the maximum peak time.
When the before/after determining unit 162 determines that the scheduled end time of use outside the facility is earlier than the maximum peak time, the charging planning unit 163 plans charging of the storage battery 201 using the externally supplied power. When the scheduled end time of use outside the facility is earlier than the maximum peak time, the amount of power stored in the storage battery 201 during use outside the facility can be increased by increasing the amount of charge during the low cost period. Electricity charges can be kept low by charging during the low-cost period.
Therefore, the charging planning unit 163 charges the storage battery 201 to secure the required amount of stored electricity for use outside the facility.

図8は、充電計画部163が安価期間における充電にて蓄電量を確保する例を示すグラフである。同図(A)は、充電計画部163が安価期間における充電を計画する前の電力需給および蓄電池201のSOCを示している。具体的には、線L211が電力需給を示し、線L212は蓄電池201のSOCを示している。
同図(A)において、点P21の示す施設外使用終了時蓄電量は、蓄電量最小値SOCminより小さくなっている。そこで、充電計画部163は、安価期間における充電を計画する。
FIG. 8 is a graph showing an example in which the charging planning unit 163 secures the amount of stored electricity by charging during the low cost period. 4A shows the power supply and demand and the SOC of storage battery 201 before charging planning unit 163 plans charging in the low cost period. Specifically, line L211 indicates power supply and demand, and line L212 indicates the SOC of storage battery 201 .
In FIG. 4A, the power storage amount at the end of use outside the facility indicated by point P21 is smaller than the power storage amount minimum value SOCmin. Therefore, the charging planning unit 163 plans charging during the low cost period.

図8(B)は、充電計画部163が安価期間における充電を計画した後の電力需給および蓄電池201のSOCを示している。具体的には、線L221が電力需給を示し、線L222は蓄電池201のSOCを示している。充電計画部163は、時間T21において外部供給電力を用いての蓄電池201の充電を計画している。これにより、点P22の示す施設外使用終了時蓄電量が、蓄電量最小値SOCmin以上となっている。従って、蓄電池201の施設外使用に必要な蓄電量を確保することができる。 FIG. 8B shows the power supply and demand and the SOC of the storage battery 201 after the charging planning unit 163 has planned charging in the inexpensive period. Specifically, line L221 indicates power supply and demand, and line L222 indicates the SOC of storage battery 201 . Charging planning unit 163 plans charging of storage battery 201 using externally supplied power at time T21. As a result, the power storage amount at the end of use outside the facility indicated by the point P22 is equal to or greater than the power storage amount minimum value SOCmin. Therefore, it is possible to secure the amount of electricity stored in the storage battery 201 required for use outside the facility.

また、充電計画部163は、施設外使用開始予定時刻を充電終了時刻として時刻を遡る時間帯において、外部供給電力を用いての蓄電池201の充電を継続するよう計画し、当該時間帯の時間幅を、施設外使用終了時蓄電量が蓄電量最小値以上となる時間幅とする。すなわち、充電計画部163は、蓄電池201の施設外使用の直前の時間帯において蓄電池201の充電を行うよう計画する。 In addition, the charging planning unit 163 plans to continue charging the storage battery 201 using the externally supplied power in a time period retroactive to the scheduled start time of use outside the facility as the charging end time, and the time width of the time period is the time period during which the stored power amount at the end of use outside the facility is equal to or greater than the minimum stored power amount. That is, the charging planning unit 163 plans to charge the storage battery 201 in the time period immediately before the storage battery 201 is used outside the facility.

図9は、充電計画部163が、蓄電池201の施設外使用の直前の時間帯において蓄電池201の充電を行うよう計画した例を示すグラフである。同図は、充電計画部163の計画後の電力需給および蓄電池201のSOCを示している。具体的には、線L31が電力需給を示し、線L32は蓄電池201のSOCを示している。充電計画部163は、時間T31において外部供給電力を用いての蓄電池201の充電を計画している。これにより、点P31の示す施設外使用終了時蓄電量が、蓄電量最小値SOCmin以上となっている。従って、蓄電池201の施設外使用に必要な蓄電量を確保することができる。 FIG. 9 is a graph showing an example in which the charging planning unit 163 plans to charge the storage battery 201 in the time period immediately before the storage battery 201 is used outside the facility. The figure shows the power supply and demand after planning by the charging planning unit 163 and the SOC of the storage battery 201 . Specifically, line L31 indicates power supply and demand, and line L32 indicates the SOC of storage battery 201 . Charging planning unit 163 plans charging of storage battery 201 using external power supply at time T31. As a result, the power storage amount at the end of use outside the facility indicated by the point P31 is equal to or greater than the power storage amount minimum value SOCmin. Therefore, it is possible to secure the amount of electricity stored in the storage battery 201 required for use outside the facility.

安価期間における充電のみでは施設外使用に必要な蓄電量を確保できない場合の不足分や、安価期間終了後の再計画など安価期間における充電を行えない場合、充電計画部163は、図9の例のように、蓄電池201の施設外使用の直前の時間帯において蓄電池201の充電を行うよう計画する。充電時期を遅くすることで、充電計画部163は、電力負荷400の消費電力が予測よりも少なかった場合に充電量を低減させることができる。したがって、電力管理装置100は、不必要な充電を回避することができる。 If charging during the low-cost period alone cannot secure the amount of stored electricity necessary for use outside the facility, or if charging cannot be performed during the low-cost period such as re-planning after the end of the low-cost period, the charging planning unit 163 performs the example shown in FIG. , the storage battery 201 is planned to be charged in the time period immediately before the storage battery 201 is used outside the facility. By delaying the charging timing, the charging planning unit 163 can reduce the charging amount when the power consumption of the power load 400 is less than expected. Therefore, the power management device 100 can avoid unnecessary charging.

放電抑制計画部164は、施設外使用終了予定時刻が、最大ピーク時刻以後であると前後判定部162が判定すると、蓄電池201の放電の抑制を計画する。
施設外使用終了予定時刻が最大ピーク時刻以降である場合、安価期間における充電量を増やしても、施設外使用時の蓄電池201の蓄電量を増やすことはできない。この場合、外部供給電力を一旦蓄電池201に蓄電してから電力負荷400へ供給するよりも、直接電力負荷400へ供給したほうが、簡明であり、充放電によるロスも生じない。
そこで、放電抑制計画部164は、蓄電池201の放電を抑制することで、施設外使用時に必要な蓄電量を確保する。
The discharge suppression planning unit 164 plans suppression of discharge of the storage battery 201 when the before-and-after determination unit 162 determines that the scheduled end time of use outside the facility is after the maximum peak time.
If the scheduled end time of use outside the facility is after the maximum peak time, even if the amount of charge during the low cost period is increased, the amount of power stored in the storage battery 201 during use outside the facility cannot be increased. In this case, it is simpler to supply the externally supplied power directly to the power load 400 than to temporarily store it in the storage battery 201 and then supply it to the power load 400, and there is no loss due to charge/discharge.
Therefore, the discharge suppression planning unit 164 suppresses the discharge of the storage battery 201 to ensure the required amount of stored electricity during use outside the facility.

図10は、放電抑制計画部164が、蓄電池201の放電を抑制することで、施設外使用時に必要な蓄電量を確保する例を示すグラフである。同図(A)は、放電抑制計画部164が蓄電池201の放電を抑制する前の電力需給および蓄電池201のSOCを示している。具体的には、線L411が電力需給を示し、線L412は蓄電池201のSOCを示している。
同図(A)において、点P41の示す施設外使用終了時蓄電量は、蓄電量最小値SOCminより小さくなっている。そこで、放電抑制計画部164は、蓄電池201の放電の抑制を計画する。
FIG. 10 is a graph showing an example in which the discharge suppression planning unit 164 suppresses the discharge of the storage battery 201 to secure the required amount of stored electricity during use outside the facility. 4A shows the power supply and demand and the SOC of storage battery 201 before discharge suppression planning unit 164 suppresses the discharge of storage battery 201. FIG. Specifically, line L411 indicates power supply and demand, and line L412 indicates the SOC of storage battery 201 .
In FIG. 4A, the power storage amount at the end of use outside the facility indicated by point P41 is smaller than the power storage amount minimum value SOCmin. Therefore, the discharge suppression planning unit 164 plans to suppress the discharge of the storage battery 201 .

図10(B)は、放電抑制計画部164が蓄電池201の放電を抑制した後の電力需給および蓄電池201のSOCを示している。具体的には、線L421が電力需給を示し、線L422は蓄電池201のSOCを示している。放電抑制計画部164は、時間T41およびT42において蓄電池201の放電を抑制している。これにより、点P42の示す施設外使用終了時蓄電量が、蓄電量最小値SOCmin以上となっている。従って、蓄電池201の施設外使用に必要な蓄電量を確保することができる。 FIG. 10B shows the power supply and demand and the SOC of storage battery 201 after discharge suppression planning unit 164 suppresses the discharge of storage battery 201 . Specifically, line L421 indicates power supply and demand, and line L422 indicates the SOC of storage battery 201 . Discharge suppression planning unit 164 suppresses discharge of storage battery 201 at times T41 and T42. As a result, the power storage amount at the end of use outside the facility indicated by the point P42 is equal to or greater than the power storage amount minimum value SOCmin. Therefore, it is possible to secure the amount of electricity stored in the storage battery 201 required for use outside the facility.

また、蓄電池201の放電を抑制しても施設外使用に必要な蓄電量を確保できない場合、放電抑制計画部164は、外部供給電力を用いての蓄電池201の充電を計画する。 図11は、放電抑制計画部164が、外部供給電力を用いての蓄電池201の充電を計画した例を示すグラフである。同図は、放電抑制計画部164の計画後の電力需給および蓄電池201のSOCを示している。具体的には、線L51が電力需給を示し、線L52は蓄電池201のSOCを示している。
図11の例では、施設外使用開始までの全時間において蓄電池201の放電を抑制しても、22時の時点における施設外使用終了時蓄電量を確保できない。そこで、放電抑制計画部164は、時間T51において外部供給電力を用いての蓄電池201の充電を計画している。これにより、点P51の示す施設外使用終了時蓄電量が、蓄電量最小値SOCmin以上となっている。従って、蓄電池201の施設外使用に必要な蓄電量を確保することができる。
In addition, when the amount of power storage necessary for use outside the facility cannot be secured even if the discharge of the storage battery 201 is suppressed, the discharge suppression planning unit 164 plans charging of the storage battery 201 using externally supplied power. FIG. 11 is a graph showing an example in which discharge suppression planning unit 164 plans charging of storage battery 201 using external power supply. The figure shows the power supply and demand after planning by the discharge suppression planning unit 164 and the SOC of the storage battery 201 . Specifically, line L51 indicates power supply and demand, and line L52 indicates the SOC of storage battery 201 .
In the example of FIG. 11, even if the discharge of the storage battery 201 is suppressed for the entire time until the start of use outside the facility, the amount of electricity stored at the end of use outside the facility at 22:00 cannot be secured. Therefore, discharge suppression planning unit 164 plans charging of storage battery 201 using the externally supplied power at time T51. As a result, the power storage amount at the end of use outside the facility indicated by the point P51 is equal to or greater than the power storage amount minimum value SOCmin. Therefore, it is possible to secure the amount of electricity stored in the storage battery 201 required for use outside the facility.

充放電制御部170は、施設外使用時蓄電量調整部160によって得られた計画に基づいて蓄電池201の充放電を制御する。具体的には、充放電制御部170は、計画に従って、上述した蓄電池201のモードを切り替える。 The charging/discharging control unit 170 controls charging/discharging of the storage battery 201 based on the plan obtained by the off-facility use power storage amount adjustment unit 160 . Specifically, the charge/discharge control unit 170 switches the mode of the above-described storage battery 201 according to the plan.

次に、図12~図20を参照して、電力管理装置100の動作について説明する。
図12は、電力管理装置100が蓄電池201の充放電計画を生成する処理手順を示すフローチャートである。電力管理装置100は、安価期間の開始時刻までに同図の処理を行って、安価期間の開始時刻から次の安価期間の開始時刻までの充放電計画を生成する。また、計画と実際の蓄電量がずれた場合、電力管理装置100は、同図の処理を行って蓄電池201の充放電を再計画する。
Next, operations of the power management apparatus 100 will be described with reference to FIGS. 12 to 20. FIG.
FIG. 12 is a flowchart showing a processing procedure for the power management device 100 to generate a charge/discharge plan for the storage battery 201. As shown in FIG. The power management apparatus 100 performs the processing shown in FIG. 10 before the start time of the low-price period and generates a charge/discharge plan from the start time of the low-price period to the start time of the next low-price period. Further, when the planned amount and the actual amount of stored electricity deviate from each other, the power management apparatus 100 performs the processing shown in FIG.

図12の処理において、まず、発電電力予測取得部130は、計画対象の期間の各時刻における自然エネルギー発電装置300の発電電力を予測する(ステップS111)。あるいは、発電電力予測取得部130が、発電電力の予測を他機器から取得するようにしてもよい。
また、消費電力予測取得部120は、計画対象の期間の各時刻における電力負荷400の消費電力を予測する(ステップS112)。あるいは、消費電力予測取得部120が、消費電力の予測を他機器から取得するようにしてもよい。
また、施設外使用予定取得部110は、車両200の使用予定を取得し、当該車両200の使用予定電力を算出する(ステップS113)。
In the process of FIG. 12 , first, the generated power prediction acquisition unit 130 predicts the generated power of the natural energy power generation device 300 at each time of the planning target period (step S111). Alternatively, the generated power prediction acquisition unit 130 may acquire the prediction of the generated power from another device.
In addition, the power consumption prediction acquisition unit 120 predicts the power consumption of the power load 400 at each time during the planning target period (step S112). Alternatively, the power consumption prediction acquisition unit 120 may acquire a power consumption prediction from another device.
Further, the out-of-facility usage schedule acquisition unit 110 acquires the usage schedule of the vehicle 200 and calculates the scheduled usage power of the vehicle 200 (step S113).

次に、蓄電量予測算出部140は、自然エネルギー発電装置300の発電電力の予測と、電力負荷400の消費電力の予測と、車両200の使用予定電力とに基づいて、計画対象の期間の各時刻における電力需給予測を算出する(ステップS114)。そして、蓄電量予測算出部140は、得られた電力需給予測に基づいて、計画対象の期間の各時刻について、外部供給電力を用いての充電を受けない場合の蓄電池201の蓄電量予測を算出する(ステップS115)。 Next, based on the prediction of the power generated by the natural energy power generation device 300, the prediction of the power consumption of the power load 400, and the planned power consumption of the vehicle 200, the power storage amount prediction calculation unit 140 A power supply and demand prediction at the time is calculated (step S114). Then, based on the obtained electric power supply and demand prediction, the electric power storage amount prediction calculation unit 140 calculates the electric power storage amount prediction of the storage battery 201 when charging is not performed using the externally supplied electric power for each time of the period to be planned. (step S115).

次に、最大蓄電量調整部150は、蓄電池201の蓄電量の最大値を最大蓄電量SOCmaxに合わせるピーク合わせを行う(ステップS116)。
そして、施設外使用時蓄電量調整部160は、蓄電池201の施設外使用(本実施形態では、車両200による蓄電池201の使用)に必要な蓄電量を確保するため、施設外使用終了時蓄電量を蓄電量最小値SOCmin以上とする処理を行う(ステップS117)。
その後、図12の処理を終了し、得られた計画に従って充放電制御部170が蓄電池201の充放電を制御する。
Next, the maximum stored electricity amount adjustment unit 150 performs peak matching for matching the maximum value of the stored electricity amount of the storage battery 201 to the maximum stored electricity amount SOCmax (step S116).
Then, the power storage amount adjustment unit 160 for out-of-facility use ends the power storage amount at the end of out-of-facility use in order to secure the amount of power storage necessary for the outside use of the storage battery 201 (in this embodiment, the use of the storage battery 201 by the vehicle 200). is equal to or greater than the minimum stored amount SOCmin (step S117).
After that, the process of FIG. 12 is ended, and the charge/discharge control unit 170 controls the charge/discharge of the storage battery 201 according to the obtained plan.

図13は、施設外使用時蓄電量調整部160が、蓄電池201の施設外使用に必要な蓄電量を確保する処理の手順を示すフローチャートである。施設外使用時蓄電量調整部160は、図12のステップS117において、図13の処理を行う。
図13の処理において、施設外使用時蓄電量調整部160は、まず、車両200の使用予定毎に処理を行うループL11を開始する(ステップS121)。
FIG. 13 is a flowchart showing a procedure of a process of securing the amount of stored electricity necessary for the outside use of the storage battery 201 by the off-facility use power storage amount adjustment unit 160 . The outside-use power storage amount adjustment unit 160 performs the process of FIG. 13 in step S117 of FIG.
In the process of FIG. 13, the outside-use power storage amount adjusting unit 160 first starts a loop L11 in which the process is performed for each planned use of the vehicle 200 (step S121).

そして、調整要否判定部161が、ループL11で処理対象となっている車両使用について、施設外使用終了時蓄電量(本実施形態では、車両200の使用終了時のSOC)が蓄電量最小値SOCminより小さいか否かを判定する(ステップS122)。
施設外使用終了時蓄電量が蓄電量最小値SOCminより小さいと判定した場合(ステップS122:YES)、施設外使用時蓄電量調整部160は、施設外使用終了時蓄電量を蓄電量最小値SOCmin以上にするかさ上げ処理を行う(ステップS123)。
Then, the adjustment necessity determination unit 161 determines that the stored electricity amount at the end of the use outside the facility (in this embodiment, the SOC at the end of the use of the vehicle 200) is the minimum stored electricity amount for the vehicle use that is the processing target in the loop L11. It is determined whether or not it is smaller than SOCmin (step S122).
When it is determined that the power storage amount at the end of outside use is smaller than the minimum power storage amount SOCmin (step S122: YES), the power storage amount at outside use end adjustment unit 160 adjusts the power storage amount at the end of outside use to the minimum power storage amount SOCmin. The raising process described above is performed (step S123).

そして、調整要否判定部161は、計画対象の期間内の全ての車両使用についてループL11の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS124)。未処理の車両使用があると判定した場合、ステップS121へ戻り、残りの車両使用に対してループL11の処理を行う。一方、全ての車両使用について処理を完了したと判定した場合、図13の処理を終了する。
一方、ステップS122において、施設外使用終了時蓄電量が蓄電量最小値SOCmin以上であると判定した場合(ステップS122:NO)、ステップS124へ進む。
Then, the adjustment necessity determining unit 161 determines whether or not the processing of the loop L11 has been completed for all vehicle uses within the planned period, and transitions according to the determination result (step S124). If it is determined that there is unprocessed vehicle use, the process returns to step S121, and loop L11 is processed for the remaining vehicle use. On the other hand, if it is determined that the processing has been completed for all vehicle uses, the processing of FIG. 13 ends.
On the other hand, when it is determined in step S122 that the power storage amount at the end of use outside the facility is equal to or greater than the power storage amount minimum value SOCmin (step S122: NO), the process proceeds to step S124.

図14は、施設外使用時蓄電量調整部160が行うかさ上げ処理の手順を示すフローチャートである。施設外使用時蓄電量調整部160は、図13のステップS123において、図14の処理を行う。
図14の処理において、まず、前後判定部162が、施設外使用終了予定時刻(本実施形態では車両使用終了時刻)が最大ピーク時刻より早い(小さい)か否かを判定する(ステップS131)。
FIG. 14 is a flow chart showing the procedure of the raising process performed by the off-facility use power storage amount adjustment unit 160 . In step S123 of FIG. 13, the out-of-facility use power storage amount adjustment unit 160 performs the process of FIG.
In the process of FIG. 14, first, the before/after determination unit 162 determines whether or not the scheduled end time of use outside the facility (the end time of vehicle use in this embodiment) is earlier (less than) the maximum peak time (step S131).

施設外使用終了予定時刻が最大ピーク時刻より早いと判定した場合(ステップS131:YES)、充電計画部163が、施設外使用終了予定時刻が最大ピーク時刻より早い場合のかさ上げ処理であるピーク前処理を行う(ステップS132)。
その後、図14の処理を終了する。
一方、ステップS131において、施設外使用終了予定時刻が最大ピーク時刻より早くないと判定した場合(ステップS131:NO)、放電抑制計画部164が、施設外使用終了予定時刻が最大ピーク時刻より早くない場合のかさ上げ処理であるピーク後処理を行う(ステップS133)。
その後、図14の処理を終了する。
When it is determined that the scheduled end time of use outside the facility is earlier than the maximum peak time (step S131: YES), the charging planning unit 163 performs charging processing when the scheduled end time of use outside the facility is earlier than the maximum peak time. Processing is performed (step S132).
After that, the process of FIG. 14 ends.
On the other hand, when it is determined in step S131 that the scheduled end time of use outside the facility is not earlier than the maximum peak time (step S131: NO), the discharge suppression planning unit 164 determines that the scheduled end time of use outside the facility is not earlier than the maximum peak time. A post-peak process, which is a raising process for the case, is performed (step S133).
After that, the process of FIG. 14 ends.

図15は、充電計画部163がピーク前処理を行う手順を示すフローチャートである。充電計画部163は、図14のステップS132において図15の処理を行う。
図15の処理において、充電計画部163は、まず、安価期間でのピーク前処理として、安価期間において外部供給電力を用いて蓄電池201の充電を行うかさ上げ処理を行う(ステップS141)。
FIG. 15 is a flow chart showing a procedure for the charge planning unit 163 to perform pre-peak processing. The charging planning unit 163 performs the process of FIG. 15 in step S132 of FIG.
In the process of FIG. 15 , the charging planning unit 163 first performs a raising process of charging the storage battery 201 using the externally supplied power during the low price period as pre-peak processing during the low price period (step S141).

そして、調整要否判定部161が、かさ上げ量が不足しているか否かを判定する(ステップS142)。具体的には、調整要否判定部161は、図13のステップS122と同様、施設外使用終了時蓄電量が蓄電量最小値SOCminより小さいか否かを判定する。 かさ上げ量が不足している判定した場合(ステップS142:YES)、充電計画部163は、高価期間でのピーク前処理として、高価期間において外部供給電力を用いて蓄電池201の充電を行うかさ上げ処理を行う(ステップS143)。
その後、図15の処理を終了する。
一方、ステップS142において、かさ上げ量が足りていると判定した場合(ステップS142:NO)、図15の処理を終了する。
Then, the adjustment necessity determining unit 161 determines whether or not the raising amount is insufficient (step S142). Specifically, similarly to step S122 in FIG. 13, the adjustment necessity determining unit 161 determines whether or not the power storage amount at the end of use outside the facility is smaller than the power storage amount minimum value SOCmin. When it is determined that the raising amount is insufficient (step S142: YES), the charging planning unit 163 charges the storage battery 201 using the externally supplied power in the expensive period as peak pre-processing in the expensive period. Processing is performed (step S143).
After that, the process of FIG. 15 ends.
On the other hand, if it is determined in step S142 that the raised amount is sufficient (step S142: NO), the process of FIG. 15 is terminated.

図16は、充電計画部163が安価期間でのピーク前処理を行う手順を示すフローチャートである。充電計画部163は、図15のステップS141において、図16の処理を行う。
図16の処理において、充電計画部163は、まず、目標かさ上げ量を、蓄電量最小値SOCminから施設外使用終了時蓄電量(本実施形態では車両使用終了時のSOC)を減算した値に設定する(ステップS151)。すなわち、充電計画部163は、施設外使用終了時蓄電量が蓄電量最小値SOCmin以上となるかさ上げを、かさ上げの目標とする。
次に、充電計画部163は、必要かさ上げ量を、ステップS151で設定した目標かさ上げ量に設定する(ステップS152)。ここでの必要かさ上げ量は、後述するループL16でのSOCの逆算において、充電にて得る必要のある残りのかさ上げ量である。
FIG. 16 is a flow chart showing a procedure for the charging planning unit 163 to perform peak pre-processing in a low price period. The charging planning unit 163 performs the process of FIG. 16 in step S141 of FIG.
In the process of FIG. 16, the charging planning unit 163 first sets the target raising amount to a value obtained by subtracting the storage amount at the end of use outside the facility (SOC at the end of vehicle use in this embodiment) from the minimum storage amount SOCmin. Set (step S151). In other words, the charging planning unit 163 sets a target of raising the amount of electricity stored at the end of use outside the facility to be equal to or higher than the minimum amount of electricity storage SOCmin.
Next, the charging planning unit 163 sets the required amount of raising to the target amount of raising set in step S151 (step S152). The necessary inflation amount here is the remaining inflation amount that needs to be obtained by charging in the inverse calculation of the SOC in loop L16, which will be described later.

次に、充電計画部163は、安価期間中に追加充電可能な期間があるか否かを判定する(ステップS153)。安価期間中に追加充電可能な期間が無いと判定した場合(ステップS153:NO)、図16の処理を終了する。
一方、安価期間中に追加充電可能な期間があると判定した場合(ステップS153:YES)、充電計画部163は、追加充電可能期間の終了時刻から追加充電可能期間の開始時刻まで、1分ずつ(すなわち時刻毎に)逆進して処理を行うループL16を開始する(ステップS161)。ループL16では、充電計画部163は、追加充電可能期間内において蓄電池201を充電モードに設定して蓄電量のかさ上げを行う。
Next, the charging planning unit 163 determines whether or not there is a period during which additional charging is possible during the low cost period (step S153). If it is determined that there is no additional charging period during the low cost period (step S153: NO), the process of FIG. 16 is terminated.
On the other hand, if it is determined that there is a period during which the additional charge is possible during the inexpensive period (step S153: YES), the charging planning unit 163 charges the additional charge period from the end time of the additional charge period to the start time of the additional charge period by one minute. A loop L16 in which processing is performed backward (that is, at each time) is started (step S161). In loop L16, the charge planning unit 163 sets the storage battery 201 to the charge mode within the additional chargeable period to increase the amount of stored electricity.

具体的には、充電計画部163は、まず、ループL16の処理対象の時刻(分)における蓄電池201のSOCを、次の時刻におけるSOCの値から、1分当たりの充電量を減算した値にする(ステップS162)。すなわち、充電計画部163は、蓄電池201のモードを充電モードとして、1分後のSOCからその前の時刻のSOCを逆算する。 Specifically, charging planning unit 163 first sets the SOC of storage battery 201 at the time (minute) to be processed in loop L16 to a value obtained by subtracting the charge amount per minute from the SOC value at the next time. (step S162). That is, charging planning unit 163 sets the mode of storage battery 201 to the charging mode, and calculates backward the SOC at the time before from the SOC one minute later.

次に、充電計画部163は、必要かさ上げ量を、SOCの変化分に設定する(ステップS163)。すなわち、充電計画部163は、必要なかさ上げ量から、処理対象の時刻の充電によるSOC増加分を減算する。
そして、充電計画部163は、必要かさ上げ量が0以下になったか否かを判定する(ステップS164)。0以下になったと判定した場合(ステップS164:YES)、必要なかさ上げ量を得られたので、ループL16を抜けて、後述するステップS171へ進む。
Next, the charging planning unit 163 sets the required amount of inflation to the change in SOC (step S163). That is, charging planning unit 163 subtracts the SOC increase due to charging at the time to be processed from the necessary raising amount.
Then, the charging planning unit 163 determines whether or not the required amount of inflation has become 0 or less (step S164). If it is determined that the value has become 0 or less (step S164: YES), the required amount of raising has been obtained, so the loop L16 is exited and the process proceeds to step S171, which will be described later.

一方、ステップS164において、必要かさ上げ量が0より大きいと判定した場合(ステップS164:NO)、充電計画部163は、処理対象の全ての分についてループL16の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS165)。全ての分について処理を完了したと判定した場合、ループL16の処理を終了する。一方、未処理の分があると判定した場合、ステップS161に戻り、未処理の分について引き続きループL16の処理を行う。 On the other hand, if it is determined in step S164 that the required amount of inflation is greater than 0 (step S164: NO), the charging planning unit 163 determines whether or not the processing of loop L16 has been completed for all the portions to be processed. and transitions according to the determination result (step S165). If it is determined that the processing has been completed for all minutes, the processing of loop L16 ends. On the other hand, if it is determined that there is an unprocessed portion, the process returns to step S161, and loop L16 is continued for the unprocessed portion.

ステップS165においてループL16を終了すると、充電計画部163は、追加可能充電終了時刻から処理終了時刻まで1分ずつ順に処理を行うループL17の処理を行う(ステップS171)。ループL17では、ループL16の処理において得られたかさ上げ量を、追加可能充電終了時刻以降のSOCにも反映させる。
具体的には、充電計画部163は、ループL17で処理対象となっている時刻のSOCに(目標かさ上げ量-必要かさ上げ量)を加算する(ステップS172)。この目標かさ上げ量-必要かさ上げ量は、追加充電にて得られるかさ上げ量である。
After completing the loop L16 in step S165, the charging planning unit 163 performs the processing of the loop L17 in which the processing is performed one minute at a time from the additional charge end time to the processing end time (step S171). In loop L17, the raising amount obtained in the processing of loop L16 is also reflected in the SOC after the additional charge end time.
Specifically, the charging planning unit 163 adds (target raising amount−necessary raising amount) to the SOC at the time to be processed in the loop L17 (step S172). This target inflation amount-required inflation amount is the inflation amount obtained by additional charging.

そして、充電計画部163は、処理対象の全ての分についてループL17の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS173)。全ての分について処理を完了したと判定した場合、ループL17の処理を終了する。一方、未処理の分があると判定した場合、ステップS171に戻り、未処理の分について引き続きループL17の処理を行う。
ステップS173においてループL17を終了した後、図16の処理を終了する。
Then, the charging planning unit 163 determines whether or not the processing of the loop L17 has been completed for all the portions to be processed, and transitions according to the determination result (step S173). If it is determined that the processing has been completed for all minutes, the processing of loop L17 ends. On the other hand, if it is determined that there is an unprocessed portion, the process returns to step S171, and the loop L17 is continued for the unprocessed portion.
After completing the loop L17 in step S173, the process of FIG. 16 is terminated.

図17は、充電計画部163が高価期間でのピーク前処理を行う手順を示すフローチャートである。充電計画部163は、図15のステップS143において、図17の処理を行う。
図17の処理において、充電計画部163は、まず、かさ上げ量を、蓄電量最小値SOCminから施設外使用終了時蓄電量(本実施形態では車両使用終了時のSOC)を減算した値に設定する(ステップS201)。すなわち、充電計画部163は、施設外使用終了時蓄電量が蓄電量最小値SOCmin以上となるかさ上げを行うことに決定する。
FIG. 17 is a flow chart showing a procedure for the charging planning unit 163 to perform the peak pre-processing in the high price period. The charging planning unit 163 performs the process of FIG. 17 in step S143 of FIG.
In the process of FIG. 17, the charging planning unit 163 first sets the raising amount to a value obtained by subtracting the storage amount at the end of use outside the facility (SOC at the end of vehicle use in this embodiment) from the minimum storage amount SOCmin. (step S201). That is, the charging planning unit 163 decides to raise the amount of stored electricity at the end of use outside the facility to be equal to or greater than the minimum stored amount of electricity SOCmin.

次に、充電計画部163は、車両使用開始時の蓄電池201のSOCにかさ上げ量を加算する(ステップS202)。
そして、充電計画部163は、車両使用開始時刻から計画対象となっている時間の開始時刻まで、1分ずつ(すなわち時刻毎に)逆進して処理を行うループL21を開始する(ステップS211)。ループL21では、充電計画部163は、車両使用開始時刻に設定した必要な蓄電量から逆算して、必要な蓄電量と蓄電池201の蓄電量が一致するまで蓄電池201を充電モードに設定する。
Next, charging planning unit 163 adds the raising amount to the SOC of storage battery 201 at the start of vehicle use (step S202).
Then, the charging planning unit 163 starts a loop L21 in which the process is reversed one minute at a time (that is, at each time) from the vehicle use start time to the start time of the time to be planned (step S211). . In loop L21, charging planning unit 163 calculates backward from the required amount of stored electricity set at the vehicle use start time, and sets storage battery 201 to the charging mode until the required amount of stored electricity matches the amount of stored battery 201.

具体的には、充電計画部163は、まず、車両200が使用中または蓄電池201へ充電中か否かを判定する(ステップS212)。車両200が使用中または蓄電池201へ充電中ではないと判定した場合(ステップS212:NO)、充電計画部163は、ループL21の処理対象の時刻(分)における蓄電池201のSOCを、次の時刻におけるSOCの値から、1分当たりの充電量を減算した値にする(ステップS221)。すなわち、充電計画部163は、蓄電池201のモードを充電モードとして、1分後のSOCからその前の時刻のSOCを逆算する。 Specifically, charging planning unit 163 first determines whether vehicle 200 is in use or storage battery 201 is being charged (step S212). If it is determined that the vehicle 200 is not in use or the storage battery 201 is not being charged (step S212: NO), the charging planning unit 163 changes the SOC of the storage battery 201 at the time (minute) subject to processing in the loop L21 to the next time. A value obtained by subtracting the charge amount per minute from the SOC value in (step S221). That is, charging planning unit 163 sets the mode of storage battery 201 to the charging mode, and calculates backward the SOC at the time before from the SOC one minute later.

次に、充電計画部163は、必要かさ上げ量を、SOCの変化分に設定する(ステップS222)。ここでの必要かさ上げ量は、ループL21でのSOCの逆算において、充電にて得る必要のある残りのかさ上げ量である。
そして、充電計画部163は、必要かさ上げ量が0以下になったか否かを判定する(ステップS223)。0以下になったと判定した場合(ステップS223:YES)、必要なかさ上げ量を得られたので、ループL21を抜けて、後述するステップS261へ進む。
Next, the charging planning unit 163 sets the required amount of inflation to the amount of change in the SOC (step S222). The necessary inflation amount here is the remaining inflation amount that needs to be obtained by charging in the SOC inverse calculation in loop L21.
Then, the charging planning unit 163 determines whether or not the required amount of inflation has become 0 or less (step S223). If it is determined that the value has become 0 or less (step S223: YES), the required amount of raising has been obtained, so the loop L21 is exited and the process proceeds to step S261, which will be described later.

一方、ステップS223において、必要かさ上げ量が0より大きいと判定した場合(ステップS223:NO)、充電計画部163は、処理対象の全ての分についてループL21の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS241)。全ての分について処理を完了したと判定した場合、ループL21の処理を終了する。一方、未処理の分があると判定した場合、ステップS211に戻り、未処理の分について引き続きループL21の処理を行う。
また、ステップS212において、車両200が使用中または蓄電池201へ充電中であると判定した場合(ステップS212:YES)、いずれの場合も蓄電池201へ新たに充電を行うことはできないので、ループL21で処理対象の時刻のSOCに必要かさ上げ量を加算する(ステップS231)。その後、ステップS241へ進む。
On the other hand, if it is determined in step S223 that the required amount of inflation is greater than 0 (step S223: NO), the charging planning unit 163 determines whether or not the processing of loop L21 has been completed for all the portions to be processed. and transitions according to the determination result (step S241). If it is determined that the processing has been completed for all minutes, the processing of loop L21 ends. On the other hand, if it is determined that there is an unprocessed portion, the process returns to step S211, and the loop L21 is continued for the unprocessed portion.
If it is determined in step S212 that the vehicle 200 is in use or that the storage battery 201 is being charged (step S212: YES), in either case, the storage battery 201 cannot be newly charged. The necessary amount of raising is added to the SOC at the time to be processed (step S231). After that, the process proceeds to step S241.

ステップS241においてループL21を終了すると、充電計画部163は、処理開始時刻から車両使用開始時刻まで1分ずつ順に処理を行うループL22の処理を行う(ステップS251)。ループL21の処理において、得られていないかさ上げ量が残っているため、ループL21で算出した各時刻の値から減算していく。
具体的には、充電計画部163は、ループL22で処理対象となっている時刻のSOCから、必要かさ上げ量(すなわち、得られていないかさ上げ量)を減算する(ステップS252)。
そして、充電計画部163は、処理対象の全ての分についてループL22の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS253)。全ての分について処理を完了したと判定した場合、ループL22の処理を終了する。一方、未処理の分があると判定した場合、ステップS251に戻り、未処理の分について引き続きループL22の処理を行う。
After completing the loop L21 in step S241, the charging planning unit 163 performs the processing of the loop L22 in which the processing is performed one minute at a time from the processing start time to the vehicle use start time (step S251). In the processing of the loop L21, since the amount of raising that has not been obtained remains, it is subtracted from the value at each time calculated in the loop L21.
Specifically, charging planning unit 163 subtracts the required amount of raising (that is, the amount of raising that has not been obtained) from the SOC at the time to be processed in loop L22 (step S252).
Then, the charging planning unit 163 determines whether or not the processing of the loop L22 has been completed for all the portions to be processed, and transitions according to the determination result (step S253). If it is determined that the processing has been completed for all minutes, the processing of loop L22 ends. On the other hand, if it is determined that there is an unprocessed portion, the process returns to step S251, and the loop L22 is continued for the unprocessed portion.

ステップS253においてループL22を終了すると、充電計画部163は、車両使用開始時刻から処理終了時刻まで1分ずつ順に処理を行うループL23の処理を行う(ステップS261)。ループL21の処理において、得られたかさ上げ量を、車両使用開始時刻以降のSOCにも反映させる。
具体的には、充電計画部163は、ループL23で処理対象となっている時刻のSOCに(かさ上げ量-必要かさ上げ量)を加算する(ステップS262)。
After completing the loop L22 in step S253, the charging planning unit 163 performs the processing of the loop L23 in which the processing is performed one minute at a time from the vehicle use start time to the processing end time (step S261). In the processing of loop L21, the obtained amount of raising is also reflected in the SOC after the vehicle use start time.
Specifically, the charging planning unit 163 adds (raising amount−necessary raising amount) to the SOC at the time to be processed in the loop L23 (step S262).

そして、充電計画部163は、処理対象の全ての分についてループL23の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS263)。全ての分について処理を完了したと判定した場合、ループL23の処理を終了する。一方、未処理の分があると判定した場合、ステップS261に戻り、未処理の分について引き続きループL23の処理を行う。
ステップS263においてループL23を終了した後、図17の処理を終了する。
Then, the charging planning unit 163 determines whether or not the processing of the loop L23 has been completed for all the portions to be processed, and transitions according to the determination result (step S263). If it is determined that the processing has been completed for all minutes, the processing of loop L23 ends. On the other hand, if it is determined that there is an unprocessed portion, the process returns to step S261, and the loop L23 is continued for the unprocessed portion.
After the loop L23 ends in step S263, the process of FIG. 17 ends.

図18は、放電抑制計画部164がピーク後処理を行う手順を示すフローチャートである。放電抑制計画部164は、図14のステップS133において、図18の処理を行う。
図18の処理において、放電抑制計画部164は、まず、最大ピーク時直後まで放電禁止を考慮するスケジュールを生成する(ステップS301)。ステップS301にて放電抑制計画部164が行う処理について、図19を参照して説明する。
FIG. 18 is a flowchart showing a procedure for the discharge suppression planning unit 164 to perform post-peak processing. The discharge suppression planning unit 164 performs the process of FIG. 18 in step S133 of FIG.
In the process of FIG. 18, the discharge suppression planning unit 164 first generates a schedule that considers discharge prohibition until immediately after the maximum peak time (step S301). Processing performed by the discharge suppression planning unit 164 in step S301 will be described with reference to FIG.

図19は、最大ピーク時直後まで放電禁止を考慮するスケジュールの例を示すグラフである。同図の横軸は時刻を示し、縦軸はSOCを示す。
線L61は、放電禁止考慮前のスケジュールによる蓄電池201のSOCの変化例を示す。線L61の例では、時刻T61においてSOCが最大ピーク蓄電量V61となっている。また、時刻T62からT63まで、および、時刻T64からT65までは、車両200の使用が予定されている。処理終了時刻(23時)以前で最後の車両使用終了時(時刻T65)の蓄電量が蓄電量最小値SOCminより小さくなっているため、このスケジュールのままでは、車両使用時に電力が不足することが予想される。
FIG. 19 is a graph showing an example of a schedule that considers discharge prohibition until just after the maximum peak time. In the figure, the horizontal axis indicates time, and the vertical axis indicates SOC.
A line L61 shows an example of change in the SOC of the storage battery 201 according to the schedule before prohibition of discharge is considered. In the example of the line L61, the SOC reaches the maximum peak storage amount V61 at time T61. Also, vehicle 200 is scheduled to be used from time T62 to T63 and from time T64 to T65. Before the processing end time (23:00), the last time the vehicle was used (time T65), the stored electricity amount was smaller than the minimum stored electricity amount SOCmin. is expected.

一方、線L62は、処理終了時刻以前で最後の車両使用終了時(時刻T65)の蓄電量を蓄電量最小値SOCminに合わせ、さらに、放電禁止を考慮したスケジュールによる蓄電池201のSOCの変化例を示す。線L62の例では、最大ピーク時(時刻T61)から、処理終了時刻以前で最後の車両使用終了時(時刻T65)までの時間帯について、車両使用時以外の時刻における放電が禁止されている。具体的には、時刻T61からT62まで、および、時刻T63からT64までの放電が禁止されている。
このように、放電抑制計画部164は、最大ピーク時から、処理終了時刻以前で最後の車両使用終了時(時刻T65)までの時間帯について、車両使用時以外の時刻における放電を禁止した場合のスケジュールを生成する。
On the other hand, line L62 shows an example of a change in the SOC of storage battery 201 according to a schedule that matches the storage amount at the end of vehicle use (time T65) before the processing end time to match the storage amount minimum value SOCmin, and also takes into account the prohibition of discharging. show. In the example of line L62, discharge is prohibited at times other than when the vehicle is in use in the time period from the maximum peak time (time T61) to the final vehicle use end time (time T65) before the process end time. Specifically, discharge is prohibited from time T61 to T62 and from time T63 to T64.
In this manner, the discharge suppression planning unit 164 prohibits discharge at times other than when the vehicle is in use in the time period from the maximum peak time to the last vehicle use end time (time T65) before the processing end time. Generate a schedule.

図19の例では、放電禁止を考慮した場合の、最大ピーク時以降最初の車両使用開始時(時刻T62)における蓄電量V62が、放電禁止前の最大ピーク蓄電量V61以下となっている。これは、放電禁止を行えば、新たに充電を行わずとも車両使用時の電力不足を回避し得ることを示している。
これに対して、放電禁止を考慮した場合の、最大ピーク時以降最初の車両使用開始時における蓄電量が、放電禁止前の最大ピーク蓄電量より大きい場合は、車両使用時の電力不足を回避するために、新たな充放電を計画する必要がある。
In the example of FIG. 19, when the prohibition of discharge is taken into consideration, the storage amount V62 at the first start of use of the vehicle after the maximum peak (time T62) is equal to or less than the maximum peak storage amount V61 before the prohibition of discharge. This indicates that if discharge is prohibited, power shortage during vehicle use can be avoided without recharging.
On the other hand, if the amount of electricity stored at the time the vehicle is first used after the maximum peak time is greater than the maximum peak amount of electricity stored before the prohibition of discharge, the power shortage during vehicle use is avoided. Therefore, it is necessary to plan new charging and discharging.

図18に戻って、ステップS301の後、放電抑制計画部164は、車両使用開始時のSOCがピーク時のSOC(最大ピーク蓄電量)より大きいか否かを判定する(ステップS302)。
車両使用開始時のSOCがピーク時のSOCより大きいと判定した場合(ステップS302:YES)、すなわち、新たな充電が必要な場合、放電抑制計画部164は、必要かさ上げ量を、車両使用開始時のSOCからピーク時のSOCを減算した値に設定する(ステップS311)。
そして、放電抑制計画部164は、車両使用開始時刻からピーク時刻まで1分ずつ逆進して処理を行うループL31を開始する(ステップS321)。
Returning to FIG. 18, after step S301, discharge suppression planning unit 164 determines whether or not the SOC at the start of vehicle use is greater than the peak SOC (maximum peak power storage amount) (step S302).
If it is determined that the SOC at the start of vehicle use is higher than the SOC at the peak (step S302: YES), that is, if new charging is required, the discharge suppression planning unit 164 sets the required amount of inflation to A value obtained by subtracting the SOC at the peak time from the SOC at the hour is set (step S311).
Then, the discharge suppression planning unit 164 starts a loop L31 in which the processing is reversed by one minute from the vehicle use start time to the peak time (step S321).

ステップS322、S331~S333、S341およびS342における処理は、それぞれ図17のステップS212、S221~S223、S231およびS241における処理と同様である。
ステップS342においてループL31を終了すると、放電抑制計画部164は、最大ピーク時刻から処理終了時刻まで1分ずつ順に処理を行うループL32の処理を行う(ステップS351)。
The processes in steps S322, S331 to S333, S341 and S342 are the same as the processes in steps S212, S221 to S223, S231 and S241 of FIG. 17, respectively.
After completing the loop L31 in step S342, the discharge suppression planning unit 164 performs the processing of the loop L32 in which the processing is performed one minute at a time from the maximum peak time to the processing end time (step S351).

そして、放電抑制計画部164は、ループL32で処理対象となっている時刻のSOCから、必要かさ上げ量(すなわち、得られていないかさ上げ量)を減算する(ステップS352)。
そして、放電抑制計画部164は、処理対象の全ての分についてループL32の処理を完了したか否かを判定し、判定結果に従って遷移する(ステップS353)。全ての分について処理を完了したと判定した場合、図18の処理を終了する。一方、未処理の分があると判定した場合、ステップS351に戻り、未処理の分について引き続きループL32の処理を行う。
Then, discharge suppression planning unit 164 subtracts the required amount of raising (that is, the amount of raising that has not been obtained) from the SOC at the time to be processed in loop L32 (step S352).
Then, the discharge suppression planning unit 164 determines whether or not the processing of loop L32 has been completed for all the portions to be processed, and transitions according to the determination result (step S353). If it is determined that the processing has been completed for all minutes, the processing of FIG. 18 ends. On the other hand, if it is determined that there is an unprocessed portion, the process returns to step S351, and the loop L32 is continued for the unprocessed portion.

一方、ステップS302において、車両使用開始時のSOCがピーク時のSOC(最大ピーク蓄電量)以下である判定した場合(ステップS302:NO)、すなわち、新たな充電を行わずとも放電禁止にて対応可能な場合、放電抑制計画部164は、処理開始時刻から車両使用開始のSOCとなるまで変更無しとし、その後は放電禁止を考慮したスケジュールを生成する(ステップS361)。ステップS361にて放電抑制計画部164が行う処理について、図20を参照して説明する。 On the other hand, if it is determined in step S302 that the SOC at the start of use of the vehicle is equal to or less than the peak SOC (maximum peak storage amount) (step S302: NO), discharge is prohibited even if new charging is not performed. If possible, the discharge suppression planning unit 164 does not change the SOC from the processing start time until the vehicle use start SOC, and then generates a schedule considering discharge prohibition (step S361). Processing performed by the discharge suppression planning unit 164 in step S361 will be described with reference to FIG.

図20は、処理開始時刻から車両使用開始のSOCとなるまで変更無しとし、その後は放電禁止を考慮したスケジュールの例を示すグラフである。図20では、図19の例における処理結果に基づいて放電抑制計画部164生成するスケジュールの例を示している。図20の横軸は時刻を示し、縦軸はSOCを示す。 FIG. 20 is a graph showing an example of a schedule in which there is no change from the processing start time until the vehicle use start SOC is reached, and discharge is prohibited thereafter. FIG. 20 shows an example of a schedule generated by the discharge suppression planning unit 164 based on the processing results in the example of FIG. The horizontal axis of FIG. 20 indicates time, and the vertical axis indicates SOC.

図20の例において、最大ピーク時刻T61以降最初の車両使用開始時刻T62における、放電禁止を考慮したスケジュールでの蓄電量はV62となっている。そこで、放電抑制計画部164は、蓄電量がV62となる時刻T71までは、スケジュールの変更無し(すなわち、放電禁止考慮前のスケジュール(図19の線L61参照))とする。一方、時刻T71以降については、放電抑制計画部164は、放電禁止を考慮したスケジュール(図19の線L62参照)とする。 In the example of FIG. 20, the amount of stored electricity in the schedule considering the prohibition of discharge at the first vehicle use start time T62 after the maximum peak time T61 is V62. Therefore, the discharge suppression planning unit 164 does not change the schedule (that is, the schedule before consideration of discharge prohibition (see line L61 in FIG. 19)) until time T71 when the charged amount reaches V62. On the other hand, after time T71, the discharge suppression planning unit 164 makes a schedule (see line L62 in FIG. 19) that considers discharge prohibition.

このように、放電抑制計画部164が、処理開始時刻から車両使用開始のSOCとなるまで変更無しとし、その後は放電禁止を考慮したスケジュールを生成することで、車両使用時の電力不足を回避することができ、かつ、可能な範囲で蓄電池201の放電を許可して高価期間における外部供給電力の使用を低減させることができる。 In this way, the discharge suppression planning unit 164 generates a schedule that does not change from the processing start time until the SOC at which the vehicle starts to be used, and then generates a schedule that considers discharge prohibition, thereby avoiding power shortage during vehicle use. and, to the extent possible, discharge of the storage battery 201 can be allowed to reduce the use of externally supplied power during high-value periods.

図18に戻って、ステップS361の後、図18の処理を終了する。
一方、ステップS333において、必要かさ上げ量が0以下であると判定した場合、(ステップS333:YES)、放電抑制計画部164は、ピーク時刻から必要かさ上げ量を確保できるまで放電禁止とする(ステップS381)。その後、図18の処理を終了する。
Returning to FIG. 18, after step S361, the process of FIG. 18 ends.
On the other hand, if it is determined in step S333 that the required amount of raising is 0 or less (step S333: YES), the discharge suppression planning unit 164 prohibits discharge from the peak time until the required amount of raising is secured ( step S381). After that, the process of FIG. 18 ends.

以上のように、最大蓄電量調整部150は、時刻毎の蓄電量における最大値が所定の蓄電量最大値SOCmaxとなるように、電力料金が比較的安価な時間帯における外部供給電力を用いての蓄電池201の充電を計画する。
そして、施設外使用時蓄電量調整部160は、施設外使用終了予定時刻における蓄電池201の蓄電量である施設外使用終了時蓄電量が所定の蓄電量最小値SOCmin以上となるように蓄電池201の充放電を計画する。
これにより、1つの蓄電池201から電力負荷400へ電力を供給しつつ、車両200の走行など蓄電池201の施設外使用も行う場合において電力不足を回避することができる。
As described above, the maximum stored electricity amount adjustment unit 150 uses the externally supplied electric power in the time period when the electricity rate is relatively low so that the maximum value of the stored electricity amount for each time becomes the predetermined maximum stored electricity amount SOCmax. charging of the storage battery 201 is planned.
Then, the storage battery amount adjusting unit 160 adjusts the storage battery 201 so that the storage amount at the end of the outside use, which is the storage amount of the storage battery 201 at the scheduled termination time of the use outside the facility, is equal to or greater than the predetermined minimum storage amount SOCmin. Plan charging and discharging.
As a result, power shortage can be avoided when power is supplied from one storage battery 201 to the power load 400 and the storage battery 201 is also used outside the facility, such as when the vehicle 200 travels.

また、調整要否判定部161が、施設外使用のために蓄電池201の蓄電量の調整が必要と判定すると、前後判定部162は、施設外使用終了予定時刻が、蓄電池の蓄電量が最大となる時刻より早いか否かを判定する。
そして、施設外使用終了予定時刻が、蓄電池201の蓄電量が最大となる時刻より早いと前後判定部162が判定すると、充電計画部163は、外部供給電力を用いての蓄電池201の充電を計画する。一方、施設外使用終了予定時刻が、蓄電池の蓄電量が最大となる時刻以後であると前後判定部162が判定すると、蓄電池201の放電の抑制を計画する。
これにより、電力管理装置100は、施設外使用のタイミングと蓄電量のピークのタイミングとに応じて適切なかさ上げ方法(施設外使用に必要な蓄電量を確保する方法)を選択できる。
Further, when the adjustment necessity determining unit 161 determines that the amount of power stored in the storage battery 201 needs to be adjusted for use outside the facility, the before/after determining unit 162 determines that the scheduled end time for use outside the facility is the maximum amount of power stored in the storage battery. It is determined whether or not it is earlier than the time that becomes.
Then, when the before-and-after determination unit 162 determines that the scheduled end time of use outside the facility is earlier than the time when the amount of power stored in the storage battery 201 reaches its maximum, the charging planning unit 163 plans charging of the storage battery 201 using the externally supplied power. do. On the other hand, when the before-and-after determination unit 162 determines that the scheduled end time of use outside the facility is after the time when the amount of power stored in the storage battery reaches its maximum, suppression of discharge of the storage battery 201 is planned.
As a result, the power management apparatus 100 can select an appropriate raising method (method for securing the amount of stored electricity necessary for use outside the facility) according to the timing of the usage outside the facility and the timing of the peak of the stored electricity amount.

より具体的には、施設外使用終了予定時刻が最大ピーク時刻より早い場合、安価期間における充電量を増やすことで、施設外使用時の蓄電池201の蓄電量を増やすことができる。安価期間に充電を行うことで、電気料金を比較的安く抑えることができる。すなわち、充電計画部163が安価期間に蓄電池201を充電することで、電気料金を比較的安く抑えて施設外使用時に必要な蓄電量を確保することができる。
また、施設外使用終了予定時刻が最大ピーク時刻以降である場合、安価期間における充電量を増やしても、施設外使用時の蓄電池201の蓄電量を増やすことはできない。この場合、外部供給電力を一旦蓄電池201に蓄電してから電力負荷400へ供給するよりも、直接電力負荷400へ供給したほうが、簡明であり、充放電によるロスも生じない。そこで、放電抑制計画部164は、蓄電池201の放電を抑制することで、不要な充放電によるロスを避けて、施設外使用時に必要な蓄電量を確保することができる。
More specifically, when the scheduled end time of use outside the facility is earlier than the maximum peak time, the amount of power stored in the storage battery 201 during use outside the facility can be increased by increasing the amount of charge during the low cost period. By charging during the low-cost period, the electricity bill can be kept relatively low. That is, the charge planning unit 163 charges the storage battery 201 during the low-cost period, so that the electricity charge can be kept relatively low and the amount of stored electricity necessary for use outside the facility can be secured.
Further, when the scheduled end time of use outside the facility is after the maximum peak time, even if the amount of charge during the low cost period is increased, the amount of power stored in the storage battery 201 during use outside the facility cannot be increased. In this case, it is simpler to supply the externally supplied power directly to the power load 400 than to temporarily store it in the storage battery 201 and then supply it to the power load 400, and there is no loss due to charge/discharge. Therefore, by suppressing the discharge of the storage battery 201, the discharge suppression planning unit 164 can avoid loss due to unnecessary charge/discharge and secure the required amount of stored power when the battery is used outside the facility.

また、充電計画部163は、施設外使用開始予定時刻を充電終了時刻として時刻を遡る時間帯において、外部供給電力を用いての蓄電池201の充電を継続するよう計画し、当該時間帯の時間幅を、施設外使用終了時蓄電量が蓄電量最小値SOCmin以上となる時間幅とする。
これにより、充電計画部163は、蓄電池201の施設外使用の直前の時間帯において蓄電池201の充電を行うよう計画する。充電時期を遅くすることで、充電計画部163は、電力負荷400の消費電力が予測よりも少なかった場合に充電量を低減させることができる。したがって、電力管理装置100は、不必要な充電を回避することができる。
In addition, the charging planning unit 163 plans to continue charging the storage battery 201 using the externally supplied power in a time period retroactive to the scheduled start time of use outside the facility as the charging end time, and the time width of the time period is the time width during which the stored electricity amount at the end of use outside the facility is equal to or greater than the minimum stored electricity amount SOCmin.
Accordingly, the charging planning unit 163 plans to charge the storage battery 201 in the time zone immediately before the storage battery 201 is used outside the facility. By delaying the charging timing, the charging planning unit 163 can reduce the charging amount when the power consumption of the power load 400 is less than expected. Therefore, the power management device 100 can avoid unnecessary charging.

なお、電力管理装置100は、1日分の車両使用による電力消費量の合計が、蓄電池201の蓄電量(蓄電量最大値SOCmax-蓄電量最小値SOCmin)以下である場合に特にゆうこうである。なお、車両使用の電力が蓄電量をこえる場合、蓄電池201が充電可能となると充放電制御部170が即充電を行うようにすることで、対応できる。 Power management device 100 is particularly effective when the total amount of power consumed by vehicle use for one day is less than or equal to the storage amount of storage battery 201 (maximum storage amount SOCmax−minimum storage amount SOCmin). If the power used by the vehicle exceeds the amount of stored electricity, it can be dealt with by causing the charge/discharge control unit 170 to immediately charge the storage battery 201 when it becomes possible to charge it.

なお、23時(安価期間の開始時刻)をまたいで施設外使用の予定がある場合、施設外使用時蓄電量調整部160が、23時までの利用として処理するようにしてもよい。
例えば、22時30分から23時30分までの間に3キロワットアワー(kwh)の使用予定がある場合、22時30分から23時までに3キロワットアワー使用する予定に組み替えるようにしてもよい。これにより、施設外使用時蓄電量調整部160が計画を立てるのがより容易になる。
Note that if there is a plan to use outside the facility beyond 23:00 (the start time of the low-price period), the outside-use power storage amount adjustment unit 160 may process the use as use until 23:00.
For example, if there is a plan to use 3 kilowatt hours (kwh) from 22:30 to 23:30, it may be rearranged so as to use 3 kilowatt hours from 22:30 to 23:00. This makes it easier for the off-facility use power storage amount adjustment unit 160 to make a plan.

また、23時以降に施設外使用の予定がある場合、施設外使用時蓄電量調整部160が、使用予定電力量と施設外使用開始予定時刻までに充電可能な電力量とを比較し、使用予定電力量>充電可能電力量であれば、23時までの最後の車両使用予定電力量に、使用予定電力量と充電可能電力量との差を加えることで、予め充電しておくようにしてもよい。その次の車両予定についても同様の処理を行うようにしてもよい。
なお、充電量最小値SOCminは、蓄電池201の性能から設定される値に、予測誤差のマージンを含んだやや大きめの値であってもよい。
In addition, if there is a plan to use outside the facility after 23:00, the power storage amount adjustment unit 160 for outside use compares the planned power amount to be used with the amount of power that can be charged by the scheduled start time of use outside the facility. If the planned power amount > the chargeable power amount, the difference between the planned use power amount and the chargeable power amount is added to the last planned use power amount of the vehicle until 23:00 to charge the vehicle in advance. good too. Similar processing may be performed for the next vehicle schedule.
Note that the minimum charge amount SOCmin may be a slightly larger value that includes a prediction error margin in addition to the value set based on the performance of the storage battery 201 .

<第2の実施形態>
第1の実施形態では、充電計画部163は、高価期間に外部供給電力を用いて蓄電池201の充電を行う場合、施設外使用の直前(なるべく遅い時刻)に充電を行うように計画した。
これに対して、第2の実施形態では、充電計画部163が、なるべく早い時刻に蓄電池201の充電を行う。具体的には、充電計画部163は、充放電計画対象時間帯の開始時刻を充電開始時刻とする時間帯において、外部供給電力を用いての蓄電池201の充電を継続するよう計画し、当該時間帯の時間幅を、施設外使用終了時蓄電量が蓄電量最小値以上となる時間幅とする。
このように、充電計画部163が、なるべく早い時刻に蓄電池201の充電を行うことで、蓄電池201の発電量が予想よりも少なかった場合など、蓄電池201の容量不足が見込まれる場合にも余裕をもって蓄電池201を充電することができ、施設外使用時における電気不足をより確実に回避できる。
それ以外は、第1の実施形態と同様である。
<Second embodiment>
In the first embodiment, the charging planning unit 163 plans to charge the storage battery 201 using the externally supplied power during the expensive period so that the charging is performed just before the use outside the facility (as late as possible).
On the other hand, in the second embodiment, the charging planning unit 163 charges the storage battery 201 as early as possible. Specifically, the charging planning unit 163 plans to continue charging the storage battery 201 using the externally supplied power in a time period in which the charging start time is the start time of the charging/discharging plan target time period. The time width of the band is the time width in which the stored electricity amount at the end of use outside the facility is equal to or greater than the minimum stored electricity amount.
In this way, the charging planning unit 163 charges the storage battery 201 as early as possible, so that even if the capacity of the storage battery 201 is expected to be insufficient, such as when the amount of power generation of the storage battery 201 is less than expected, the charge planning unit 163 can easily charge the storage battery 201. The storage battery 201 can be charged, and power shortages during use outside the facility can be more reliably avoided.
Otherwise, it is the same as the first embodiment.

<第3の実施形態>
第1の実施形態では、充放電制御部170は、蓄電池201の施設外使用時や施設外使用が予定されている時間において、蓄電池201と電力負荷400や自然エネルギー発電装置300や外部供給電力との間で充放電を行わない待機モードに設定した。
これに対して、第3の実施形態では、充放電制御部170は、蓄電池201の施設外使用時や施設外使用が予定されている時間において、充電モードを選択する。具体的には、充放電制御部170は施設外使用開始予定時刻から施設外使用終了予定時刻までの時間帯において蓄電池201が接続されている状態を検出すると、外部供給電力を用いての蓄電池201の充電を行う。
すなわち、充放電制御部170は、電池が自然エネルギー発電装置300や外部供給電力に接続可能となると、速やかに充電を開始する。これにより、蓄電池201への充電をより速く行うことができ、予定外の蓄電池201の使用にも対応し易くなる。
それ以外は、第1の実施形態と同様である。
なお、第2の実施形態と第3の実施形態とを組み合わせて実施するようにしてもよい。
<Third Embodiment>
In the first embodiment, when the storage battery 201 is used outside the facility or is scheduled to be used outside the facility, the charge/discharge control unit 170 controls the storage battery 201 and the power load 400, the natural energy power generator 300, or the externally supplied power. It was set to standby mode in which charging and discharging are not performed between
On the other hand, in the third embodiment, the charge/discharge control unit 170 selects the charge mode when the storage battery 201 is used outside the facility or when the use outside the facility is scheduled. Specifically, when the charge/discharge control unit 170 detects that the storage battery 201 is connected during the period from the scheduled start time of use outside the facility to the scheduled end time of use outside the facility, the charge/discharge control unit 170 detects that the storage battery 201 is connected using the externally supplied power. charge the battery.
That is, the charge/discharge control unit 170 immediately starts charging when the battery becomes connectable to the natural energy power generation device 300 or external power supply. As a result, it is possible to charge the storage battery 201 more quickly, and it becomes easier to deal with unscheduled use of the storage battery 201 .
Otherwise, it is the same as the first embodiment.
Note that the second embodiment and the third embodiment may be combined for implementation.

なお、電力管理装置100の全部または一部の機能を実現するためのプログラムをコンピュータ読み取り可能な記録媒体に記録して、この記録媒体に記録されたプログラムをコンピュータシステムに読み込ませ、実行することにより各部の処理を行ってもよい。なお、ここでいう「コンピュータシステム」とは、OSや周辺機器等のハードウェアを含むものとする。
また、「コンピュータシステム」は、WWWシステムを利用している場合であれば、ホームページ提供環境(あるいは表示環境)も含むものとする。
また、「コンピュータ読み取り可能な記録媒体」とは、フレキシブルディスク、光磁気ディスク、ROM、CD-ROM等の可搬媒体、コンピュータシステムに内蔵されるハードディスク等の記憶装置のことをいう。さらに「コンピュータ読み取り可能な記録媒体」とは、インターネット等のネットワークや電話回線等の通信回線を介してプログラムを送信する場合の通信線のように、短時間の間、動的にプログラムを保持するもの、その場合のサーバやクライアントとなるコンピュータシステム内部の揮発性メモリのように、一定時間プログラムを保持しているものも含むものとする。また上記プログラムは、前述した機能の一部を実現するためのものであっても良く、さらに前述した機能をコンピュータシステムにすでに記録されているプログラムとの組み合わせで実現できるものであってもよい。
By recording a program for realizing all or part of the functions of power management apparatus 100 in a computer-readable recording medium, and causing a computer system to read and execute the program recorded in this recording medium, Each part may be processed. It should be noted that the "computer system" referred to here includes hardware such as an OS and peripheral devices.
The "computer system" also includes the home page providing environment (or display environment) if the WWW system is used.
The term "computer-readable recording medium" refers to portable media such as flexible discs, magneto-optical discs, ROMs and CD-ROMs, and storage devices such as hard discs incorporated in computer systems. Furthermore, "computer-readable recording medium" means a medium that dynamically retains a program for a short period of time, like a communication line when transmitting a program via a network such as the Internet or a communication line such as a telephone line. It also includes those that hold programs for a certain period of time, such as volatile memories inside computer systems that serve as servers and clients in that case. Further, the program may be for realizing part of the functions described above, or may be capable of realizing the functions described above in combination with a program already recorded in the computer system.

以上、本発明の実施形態について図面を参照して詳述してきたが、具体的な構成はこの実施形態に限られるものではなく、この発明の要旨を逸脱しない範囲の設計変更等も含まれる。 Although the embodiments of the present invention have been described in detail above with reference to the drawings, the specific configuration is not limited to these embodiments, and design changes and the like are also included within the scope of the present invention.

100 電力管理装置
110 施設外使用予定取得部
120 消費電力予測取得部
130 発電電力予測取得部
140 蓄電量予測算出部
150 最大蓄電量調整部
160 施設外使用時蓄電量調整部
161 調整要否判定部
162 前後判定部
163 充電計画部
164 放電抑制計画部
170 充放電制御部
200 車両
201 蓄電池
300 自然エネルギー発電装置
400 電力負荷
100 power management device 110 outside use schedule acquisition unit 120 power consumption prediction acquisition unit 130 generated power prediction acquisition unit 140 power storage amount prediction calculation unit 150 maximum power storage amount adjustment unit 160 power storage amount adjustment unit for outside facility use 161 adjustment necessity determination unit 162 Forward/backward determining unit 163 Charging planning unit 164 Discharge suppression planning unit 170 Charging/discharging control unit 200 Vehicle 201 Storage battery 300 Natural energy power generator 400 Power load

Claims (3)

発電装置と、電力負荷と、蓄電池とを具備する施設において電力の管理を行い、前記蓄電池の充放電を制御する電力管理装置であって、
前記発電装置の発電電力と外部供給電力とにより前記蓄電池に充電を行う第一モードと、
前記発電装置の発電電力が前記電力負荷の消費電力より大きく、余剰電力が生じる場合に、前記余剰電力で前記蓄電池に充電を行い、前記発電電力が前記電力負荷の消費電力以下であり、電力が不足している場合に、前記電力負荷に対して前記蓄電池から放電を行う第二モードと、
前記蓄電池の充電及び放電を行わない第三モードとを有し、
前記第一乃至第三モードは切り替え可能であり、
前記電力管理装置は、前記外部供給電力の電気料金が高価な時間帯よりも安価な時間帯を優先して前記第一モードで充電を行うように設定することにより前記外部供給電力の電気料金が高価な時間帯での充電を低減させつつ、何れのモードにおいても前記蓄電池の蓄電量が前記蓄電池の施設外使用終了予定時刻において許容される最小蓄電量以上となるように管理し、前記第一モード及び前記第一モードとは異なる時間帯で動作する第二モードは一日における異なる時間帯に夫々設定可能であり、前記設定に関わらず前記蓄電池の施設外使用中は前記第三モードになることを特徴とする電力管理装置。
A power management device that manages power in a facility that includes a power generation device, a power load, and a storage battery, and controls charging and discharging of the storage battery,
a first mode in which the storage battery is charged by the power generated by the power generation device and the externally supplied power;
When the power generated by the power generation device is greater than the power consumed by the power load and surplus power is generated, the storage battery is charged with the surplus power, and the generated power is less than or equal to the power consumption of the power load, and the power is a second mode in which the storage battery is discharged to the power load when there is a shortage;
and a third mode in which the storage battery is not charged or discharged,
The first to third modes are switchable,
The power management device sets the charging in the first mode by prioritizing a time period in which the electricity rate of the externally supplied power is inexpensive over a time period in which the electricity rate of the externally supplied power is expensive, thereby reducing the electricity rate of the externally supplied power. While reducing charging during expensive time periods, in any mode, the amount of electricity stored in the storage battery is managed so that it is equal to or greater than the minimum amount of electricity stored at the scheduled end time of the use of the storage battery outside the facility, and the first The mode and the second mode that operates in a time zone different from the first mode can be set to different time zones in a day, and regardless of the settings, the third mode is set while the storage battery is being used outside the facility. A power management device characterized by:
前記電力管理装置は、前記蓄電池の施設外使用開始予定時刻までに、前記蓄電池の蓄電量が、前記蓄電池の施設外使用中に使用される電力量に前記最小蓄電量に加えた蓄電量以上となるように、前記蓄電池に充電するよう管理する請求項1に記載の電力管理装置。 The power management device determines that the amount of power stored in the storage battery is equal to or greater than the amount of power used during the use of the storage battery outside the facility plus the minimum amount of power stored by the scheduled start time of use of the storage battery outside the facility. 2. The power management device according to claim 1, which manages charging of the storage battery so as to 前記電力管理装置は、前記蓄電池の施設外使用開始予定時刻までに、前記蓄電池の蓄電量が、前記蓄電池の施設外使用中に使用される電力量に前記最小蓄電量を加えた蓄電量以上となるように、前記蓄電池の放電を禁止するよう管理する請求項1に記載の電力管理装置。 The power management device determines that the storage amount of the storage battery is equal to or greater than the storage amount obtained by adding the minimum storage amount to the amount of power used while the storage battery is used outside the facility by the scheduled start time of use of the storage battery outside the facility. 2. The power management apparatus according to claim 1, wherein management is performed so as to prohibit discharge of the storage battery so as to
JP2020136050A 2013-02-18 2020-08-11 power management device Active JP7254752B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2020136050A JP7254752B2 (en) 2017-10-26 2020-08-11 power management device
JP2022030166A JP7334287B2 (en) 2013-02-18 2022-02-28 power management device

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2017207524A JP2018014888A (en) 2016-11-29 2017-10-26 Storage battery and power management device
JP2020136050A JP7254752B2 (en) 2017-10-26 2020-08-11 power management device

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2017207524A Division JP2018014888A (en) 2013-02-18 2017-10-26 Storage battery and power management device

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2022030166A Division JP7334287B2 (en) 2013-02-18 2022-02-28 power management device

Publications (2)

Publication Number Publication Date
JP2020182381A JP2020182381A (en) 2020-11-05
JP7254752B2 true JP7254752B2 (en) 2023-04-10

Family

ID=73024563

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020136050A Active JP7254752B2 (en) 2013-02-18 2020-08-11 power management device

Country Status (1)

Country Link
JP (1) JP7254752B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6053554B2 (en) * 2013-02-18 2016-12-27 三菱重工業株式会社 Power management apparatus, charge / discharge planning apparatus, charge / discharge planning method, and program
JP2023146771A (en) * 2022-03-29 2023-10-12 旭化成ホームズ株式会社 Charge/discharge control system, charge/discharge control method, and computer program

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008182851A (en) 2007-01-25 2008-08-07 Chugoku Electric Power Co Inc:The Power storage apparatus and system
JP2011250673A (en) 2010-04-26 2011-12-08 Omron Corp Energy controller and control method
JP2012100449A (en) 2010-11-02 2012-05-24 Sharp Corp Charging control device, control method of the same, control program and recording medium
JP2012115115A (en) 2010-11-01 2012-06-14 Mitsubishi Electric Corp Power control device, power control system, power control program and power control method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018014888A (en) * 2016-11-29 2018-01-25 三菱重工業株式会社 Storage battery and power management device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008182851A (en) 2007-01-25 2008-08-07 Chugoku Electric Power Co Inc:The Power storage apparatus and system
JP2011250673A (en) 2010-04-26 2011-12-08 Omron Corp Energy controller and control method
JP2012115115A (en) 2010-11-01 2012-06-14 Mitsubishi Electric Corp Power control device, power control system, power control program and power control method
JP2012100449A (en) 2010-11-02 2012-05-24 Sharp Corp Charging control device, control method of the same, control program and recording medium

Also Published As

Publication number Publication date
JP2020182381A (en) 2020-11-05

Similar Documents

Publication Publication Date Title
JP7334287B2 (en) power management device
KR102621905B1 (en) System and Method for reservation charge of electric vehicle
JP6402256B2 (en) V2G system
JP6402255B2 (en) Charge / discharge devices and transport equipment
JP6393834B2 (en) Server device
CA2952372C (en) Electric vehicle charging to reduce utility cost
US20160266561A1 (en) Control device of electrical apparatus and energy management system
US11958375B2 (en) Handling surplus and/or deficit of energy in local energy systems
JP7254752B2 (en) power management device
KR101712944B1 (en) Apparatus and method for charge and discharge scheduling in energy storage device
CN109767087A (en) Photovoltaic power scheduling method and device, computer equipment and storage medium
KR102703365B1 (en) How to charge an accumulator battery via a charging terminal
CN113479096B (en) Distributed discharging method, distributed charging method, electronic device and storage medium
KR20190000038A (en) Method of optimum power demand management using electric vehicle and apparatus thereof
FR3122951A1 (en) Method and system for controlling the charging of a fleet of electric motor vehicles
JP5843970B2 (en) Method and device for optimal charging of batteries
CN117154784A (en) Energy storage optimization
US20150236531A1 (en) Recharging of a pool of batteries
JP2018014888A (en) Storage battery and power management device
CN117950338B (en) Cooking pot control method and device, electronic equipment and storage medium
US20230011773A1 (en) Optimized electric vehicle battery charging
EP4543709A1 (en) A method of counteracting degradation of a fuel cell system of a vehicle
JP2023013835A (en) Storage battery control device, storage battery control system, and storage battery control program
JP7355551B2 (en) Control device, control method, and program
Shibl et al. Energy Reports

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200811

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210628

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210720

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210921

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20211130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220228

C60 Trial request (containing other claim documents, opposition documents)

Free format text: JAPANESE INTERMEDIATE CODE: C60

Effective date: 20220228

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20220311

C21 Notice of transfer of a case for reconsideration by examiners before appeal proceedings

Free format text: JAPANESE INTERMEDIATE CODE: C21

Effective date: 20220315

A912 Re-examination (zenchi) completed and case transferred to appeal board

Free format text: JAPANESE INTERMEDIATE CODE: A912

Effective date: 20220401

C211 Notice of termination of reconsideration by examiners before appeal proceedings

Free format text: JAPANESE INTERMEDIATE CODE: C211

Effective date: 20220405

C22 Notice of designation (change) of administrative judge

Free format text: JAPANESE INTERMEDIATE CODE: C22

Effective date: 20220913

C22 Notice of designation (change) of administrative judge

Free format text: JAPANESE INTERMEDIATE CODE: C22

Effective date: 20221025

C13 Notice of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: C13

Effective date: 20230104

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230203

C23 Notice of termination of proceedings

Free format text: JAPANESE INTERMEDIATE CODE: C23

Effective date: 20230221

C03 Trial/appeal decision taken

Free format text: JAPANESE INTERMEDIATE CODE: C03

Effective date: 20230322

C30A Notification sent

Free format text: JAPANESE INTERMEDIATE CODE: C3012

Effective date: 20230322

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230329

R150 Certificate of patent or registration of utility model

Ref document number: 7254752

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150