JP7519520B2 - How to relocate the deck manufacturing facility - Google Patents
How to relocate the deck manufacturing facility Download PDFInfo
- Publication number
- JP7519520B2 JP7519520B2 JP2023130603A JP2023130603A JP7519520B2 JP 7519520 B2 JP7519520 B2 JP 7519520B2 JP 2023130603 A JP2023130603 A JP 2023130603A JP 2023130603 A JP2023130603 A JP 2023130603A JP 7519520 B2 JP7519520 B2 JP 7519520B2
- Authority
- JP
- Japan
- Prior art keywords
- deck
- facility
- slab
- bridge
- fabrication facility
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
本発明は、プレキャストコンクリート製の床版を製作する床版製作施設を移設元から移設先に移設する方法に関する。 The present invention relates to a method for relocating a deck manufacturing facility that produces precast concrete decks from a source to a destination.
道路橋などの橋は、例えば、複数の橋脚と、各々が複数の橋脚の上に跨がって橋軸方向に延びる複数の橋桁(H形鋼)と、複数の橋桁の上に跨がって配設される床版と、を含んで構成される。床版は、例えば鉄筋コンクリート製である。かかる床版については、長年の使用によるコンクリートの劣化や内部の鉄筋の腐食などの理由で、架け替え(既設床版の撤去と新設床版の設置)が求められる場合がある。この点、特許文献1では、新設床版として、工場で製作されたプレキャストPC床版を用いている。 Bridges such as road bridges are composed of, for example, multiple piers, multiple bridge girders (H-shaped steel) that each straddle the multiple piers and extend in the bridge axis direction, and a deck that is arranged straddling the multiple girders. The deck is made of, for example, reinforced concrete. Such decks may need to be replaced (removal of the existing deck and installation of a new deck) due to reasons such as deterioration of the concrete after many years of use and corrosion of the internal reinforcing bars. In this regard, Patent Document 1 uses a precast PC deck manufactured in a factory as the new deck.
しかしながら、前述の「工場」に対応する床版製作施設(プレキャストコンクリート製の床版を製作する施設)は一般に定置式のものであり、当該施設の全体的な移設(移転)については想定されてこなかった。 However, the deck manufacturing facilities (facilities that manufacture precast concrete decks), which correspond to the aforementioned "factories," are generally stationary, and no consideration has been given to the overall relocation (relocation) of the facilities.
本発明は、このような実状に鑑み、床版製作施設の移設方法を提供することを目的とする。 In view of this situation, the present invention aims to provide a method for relocating deck construction facilities.
そのため本発明に係る床版製作施設の移設方法の第1態様及び第2態様は、プレキャストコンクリート製の床版を製作する床版製作施設を移設元から移設先に移設する方法である。本発明に係る床版製作施設の移設方法の第1態様では、移設元での床版製作施設の設備のレイアウトと、移設先での床版製作施設の設備のレイアウトとが異なる。本発明に係る床版製作施設の移設方法の第2態様では、移設元での床版製作施設の設備のレイアウトと、移設先での床版製作施設の設備のレイアウトとが同じである。本発明に係る床版製作施設の移設方法の第1態様及び第2態様において、床版製作施設は、床版を構成する緊張材に緊張力を付与するための緊張架台を備え、緊張架台は、緊張材に緊張力を付与するための反力台として機能する一対の矩形状のフレーム構造を有し、一対の矩形状のフレーム構造の各々は、2つの支柱と1つの上梁と1つの下梁とを含んで構成される。 Therefore, the first and second aspects of the method for relocating a deck slab fabrication facility according to the present invention are methods for relocating a deck slab fabrication facility that fabricates a precast concrete deck from a source to a destination. In the first aspect of the method for relocating a deck slab fabrication facility according to the present invention, the layout of the equipment of the deck slab fabrication facility at the source is different from the layout of the equipment of the deck slab fabrication facility at the destination. In the second aspect of the method for relocating a deck slab fabrication facility according to the present invention, the layout of the equipment of the deck slab fabrication facility at the source is the same as the layout of the equipment of the deck slab fabrication facility at the destination. In the first and second aspects of the method for relocating a deck slab fabrication facility according to the present invention, the deck slab fabrication facility includes a tensioning frame for applying tension to the tension members that constitute the deck, and the tensioning frame has a pair of rectangular frame structures that function as reaction frames for applying tension to the tension members, and each of the pair of rectangular frame structures includes two columns, one upper beam, and one lower beam.
本発明に係る床版製作施設の移設方法の第1態様によれば、床版製作施設の移設に際して設備のレイアウトが変更され得る床版製作施設の移設方法を提供することができる。本発明に係る床版製作施設の移設方法の第2態様によれば、床版製作施設の移設に際して設備のレイアウトが変更されない床版製作施設の移設方法を提供することができる。 According to a first aspect of the method for relocating a deck fabrication facility of the present invention, it is possible to provide a method for relocating a deck fabrication facility in which the layout of the equipment can be changed when the deck fabrication facility is relocated. According to a second aspect of the method for relocating a deck fabrication facility of the present invention, it is possible to provide a method for relocating a deck fabrication facility in which the layout of the equipment is not changed when the deck fabrication facility is relocated.
以下、本発明の実施の形態について、図面を参照して説明する。尚、全図中、同一又は相当部分には同一符号を付すこととする。 The following describes an embodiment of the present invention with reference to the drawings. Note that the same or corresponding parts in all the drawings are given the same reference numerals.
図1は、本発明の一実施形態における床版製作施設100の第1例に対応する床版製作施設10の平面図である。図2は、床版製作施設10を構成する床版製作セクション11aの平面図である。図3は図2のA-A矢視図である。尚、説明の便宜上、図1~図3に示すように東西南北を規定して以下説明するが、床版製作施設10の各構成要素と東西南北との関係が図示のものに限らないことは言うまでもない。 Figure 1 is a plan view of a deck production facility 10 corresponding to a first example of a deck production facility 100 in one embodiment of the present invention. Figure 2 is a plan view of the deck production section 11a constituting the deck production facility 10. Figure 3 is a view taken along the line A-A in Figure 2. For ease of explanation, the following description defines east, west, north and south as shown in Figures 1 to 3, but it goes without saying that the relationship between each component of the deck production facility 10 and east, west, north and south is not limited to that shown in the figures.
床版製作施設10は、プレキャストコンクリート製の床版1を製作する施設である。床版製作施設10は、単数又は複数の床版製作セクション11により構成される。図1に示す例では、床版製作施設10は、3つの床版製作セクション11a~11cにより構成されている。3つの床版製作セクション11a~11cは東西方向に並んで配置されている。尚、床版製作施設10を構成する床版製作セクション11の個数は3つに限らないことは言うまでもない。この点は、後述する床版製作施設10’についても同様である。 The deck construction facility 10 is a facility for manufacturing decks 1 made of precast concrete. The deck construction facility 10 is composed of one or more deck construction sections 11. In the example shown in FIG. 1, the deck construction facility 10 is composed of three deck construction sections 11a to 11c. The three deck construction sections 11a to 11c are arranged in a line in the east-west direction. It goes without saying that the number of deck construction sections 11 constituting the deck construction facility 10 is not limited to three. The same applies to the deck construction facility 10' described below.
西側に位置する床版製作セクション11aは、鉄筋組立ヤード12、床版製作ヤード13、洗い出し・検査ヤード14、ストックヤード15、発電機16、ボイラー17、操作盤18、曲げ強度試験装置19、及び、揚重装置20を有する。 The deck construction section 11a, located on the west side, has a rebar assembly yard 12, a deck construction yard 13, a washout and inspection yard 14, a stockyard 15, a generator 16, a boiler 17, an operation panel 18, a bending strength testing device 19, and a lifting device 20.
鉄筋組立ヤード12では、床版1を構成する鉄筋2の組立作業(地組作業)が行われる。この鉄筋2の組立作業において雨風などを凌ぐために、鉄筋組立ヤード12には、当該組立作業が行われる範囲を包囲可能なように伸縮式のテントハウス21が設けられている。このテントハウス21は、南北方向に延在して南北方向に伸縮自在である。このテントハウス21を伸縮させることで、テントハウス21の開閉度合いを適宜調整することができる。このテントハウス21を最も短縮させた状態ではテントハウス21は全開状態である。一方、このテントハウス21を最も伸長させた状態ではテントハウス21は全閉状態である。尚、テントハウス21は移設可能に構成されている。 In the reinforcing bar assembly yard 12, the assembly work (ground assembly work) of the reinforcing bars 2 that make up the deck 1 is carried out. In order to protect against rain and wind during the assembly work of the reinforcing bars 2, the reinforcing bar assembly yard 12 is provided with an expandable tent house 21 that can surround the area where the assembly work is carried out. This tent house 21 extends in the north-south direction and is expandable in the north-south direction. By expanding and contracting this tent house 21, the degree to which the tent house 21 is opened or closed can be appropriately adjusted. When this tent house 21 is in its most contracted state, it is in its fully open state. On the other hand, when this tent house 21 is in its most extended state, it is in its fully closed state. The tent house 21 is configured to be movable.
床版製作ヤード13では、鉄筋組立ヤード12で組み立てられた鉄筋2を含む床版1の製作作業が行われる。この床版1の製作作業において雨風などを凌ぐために、床版製作ヤード13には、当該製作作業が行われる範囲を包囲可能なように伸縮式のテントハウス22が設けられている。このテントハウス22は、南北方向に延在しており、その南北方向中央部にて南北に2分割されて、各分割部分が南北方向に伸縮自在である。このテントハウス22の各分割部分を伸縮させることで、テントハウス22の開閉度合いを適宜調整することができる。このテントハウス22の各分割部分を最も短縮させた状態ではテントハウス22は全開状態である。一方、このテントハウス22の各分割部分を最も伸長させた状態ではテントハウス22は全閉状態である。尚、テントハウス22は移設可能に構成されている。 In the deck slab production yard 13, the work of producing the deck 1 including the reinforcing bars 2 assembled in the reinforcing bar assembly yard 12 is carried out. In order to protect against rain and wind during the production work of the deck 1, the deck slab production yard 13 is provided with an expandable tent house 22 that can surround the area where the production work is carried out. The tent house 22 extends in the north-south direction and is divided into two parts, north and south, at the center in the north-south direction, and each divided part can be expanded and contracted in the north-south direction. By expanding and contracting each divided part of the tent house 22, the degree of opening and closing of the tent house 22 can be appropriately adjusted. When each divided part of the tent house 22 is in the most contracted state, the tent house 22 is in a fully open state. On the other hand, when each divided part of the tent house 22 is in the most extended state, the tent house 22 is in a fully closed state. The tent house 22 is configured to be movable.
洗い出し・検査ヤード14では、全ての床版1の洗い出し作業と、全ての床版1の寸法検査及び外観検査などが行われる。そして、これら床版1のうち曲げ強度試験の対象であるものが洗い出し・検査ヤード14に仮置きされる。一方、曲げ強度試験の対象ではないものについては、ストックヤード15に運搬されて保管される。 In the screening/inspection yard 14, screening work for all deck slabs 1 is carried out, as well as dimensional inspection and visual inspection of all deck slabs 1. Then, of these deck slabs 1, those that are subject to bending strength testing are temporarily stored in the screening/inspection yard 14. Meanwhile, those that are not subject to bending strength testing are transported to the stockyard 15 and stored.
洗い出し・検査ヤード14に仮置きされた、曲げ強度試験の対象である床版1については、曲げ強度試験装置19にて曲げ強度試験が施される。この試験が施された床版1については、ストックヤード15に運搬されて保管される。ここで、曲げ強度試験装置19は移設可能に構成されている。また、曲げ強度試験装置19が、本発明の「床版の品質を検査するための設備」に対応する。 The flexural strength test device 19 performs a flexural strength test on the deck 1 that is the subject of the flexural strength test and is temporarily placed in the screening and inspection yard 14. The deck 1 that has undergone this test is transported to the stockyard 15 for storage. Here, the flexural strength test device 19 is configured to be portable. The flexural strength test device 19 corresponds to the "equipment for inspecting the quality of decks" of the present invention.
揚重装置20は例えばラフテレーンクレーンなどの移動式クレーンである。揚重装置20は少なくとも以下(1)~(5)の役割がある。
(1)鉄筋組立ヤード12で組み立てられた鉄筋2を床版製作ヤード13に運搬する役割。
(2)床版1を床版製作ヤード13から洗い出し・検査ヤード14に運搬する役割。
(3)床版1を洗い出し・検査ヤード14から曲げ強度試験装置19に運搬する役割。
(4)床版1を曲げ強度試験装置19からストックヤード15に運搬する役割。
(5)床版1を洗い出し・検査ヤード14からストックヤード15に運搬する役割。
The lifting device 20 is, for example, a mobile crane such as a rough terrain crane. The lifting device 20 has at least the following roles (1) to (5).
(1) The role of transporting the reinforcing bars 2 assembled in the reinforcing bar assembly yard 12 to the deck slab production yard 13.
(2) The role of transporting the deck 1 from the deck manufacturing yard 13 to the washing and inspection yard 14.
(3) The role of transporting the deck 1 from the washing/inspection yard 14 to the bending strength testing device 19.
(4) The role of transporting the deck 1 from the bending strength testing device 19 to the stockyard 15.
(5) The role of transporting the deck 1 from the washing/inspection yard 14 to the stockyard 15.
床版製作ヤード13上には、全閉状態のテントハウス22によって包囲されるように、緊張架台30が設置されている。
緊張架台30の概略構成について、図4及び図5を用いて説明する。図4及び図5は緊張架台30の側面図及び上面図である。ここで、図4に示す一点鎖線は、製作される床版1の中心位置を示すものであり、これに沿ってPC鋼材などの緊張材3(後述する図8~図10参照)が配置され得る。また、図5に示す2点鎖線は、製作される床版1の位置を示す。
A tension frame 30 is installed on the deck slab production yard 13 so as to be surrounded by a tent house 22 in a fully closed state.
The schematic configuration of the tensioning frame 30 will be described with reference to Figures 4 and 5. Figures 4 and 5 are a side view and a top view of the tensioning frame 30. Here, the dashed dotted line shown in Figure 4 indicates the center position of the deck 1 to be manufactured, along which the tensioning members 3 such as PC steel members (see Figures 8 to 10 described later) can be arranged. Also, the two-dotted dashed line shown in Figure 5 indicates the position of the deck 1 to be manufactured.
緊張架台30はプレテンション架台とも称される。緊張架台30は、床版1を構成する緊張材3に緊張力を付与するためのものであり、本発明の「床版を構成する緊張材に緊張力を付与するための設備」に対応する。 The tensioning frame 30 is also called a pretensioning frame. The tensioning frame 30 is used to apply tension to the tension members 3 that make up the deck 1, and corresponds to the "equipment for applying tension to the tension members that make up the deck" of the present invention.
緊張架台30は、床版製作ヤード13上に立設される4つの支柱31と、2つの上梁32と、2つの下梁33とを備える。支柱31は、南北方向を長辺として東西方向を短辺とする矩形状の仮想領域の四隅に配置されており、各々が上下方向に延びている。支柱31の下端部は例えばアンカーボルトを介して床版製作ヤード13のコンクリート面などに固定される。上梁32は南北方向に延在して両端部が支柱31の上端部に連結されている。下梁33は南北方向に延在して両端部が支柱31の下端部に連結されている。ゆえに、緊張架台30では、2つの支柱31と1つの上梁32と1つの下梁33とで矩形状のフレーム構造をなしている。 The tensioning frame 30 includes four columns 31, two upper beams 32, and two lower beams 33 erected on the deck construction yard 13. The columns 31 are arranged at the four corners of a rectangular imaginary area with the long side in the north-south direction and the short side in the east-west direction, and each extends in the vertical direction. The lower ends of the columns 31 are fixed to the concrete surface of the deck construction yard 13, for example, via anchor bolts. The upper beam 32 extends in the north-south direction and both ends are connected to the upper ends of the columns 31. The lower beam 33 extends in the north-south direction and both ends are connected to the lower ends of the columns 31. Therefore, the tensioning frame 30 has a rectangular frame structure with two columns 31, one upper beam 32, and one lower beam 33.
上梁32と下梁33との間に跨がるように複数の縦梁34が設けられている。縦梁34は、上端部が上梁32に連結されており、下端部が下梁33に連結されている。複数の縦梁34が南北方向に互いに間隔を空けて並んでいる。
2つの上梁32間に跨がるように複数の横梁35が設けられている。横梁35は東西方向に延びている。複数の横梁35が南北方向に互いに間隔を空けて並んでいる。横梁35は上梁32に着脱可能に固定されている。
A plurality of vertical beams 34 are provided so as to straddle between the upper beam 32 and the lower beam 33. The upper end of each vertical beam 34 is connected to the upper beam 32, and the lower end is connected to the lower beam 33. The multiple vertical beams 34 are arranged at intervals from one another in the north-south direction.
A plurality of cross beams 35 are provided so as to straddle the two upper beams 32. The cross beams 35 extend in the east-west direction. The plurality of cross beams 35 are arranged in the north-south direction at intervals. The cross beams 35 are detachably fixed to the upper beams 32.
北側に位置する2つの支柱31の上下方向中央部に跨がるように定着梁36が設けられている。定着梁36は、北側に位置する2つの支柱31より北側に位置している。定着梁36は、東側の端部が北東側の支柱31の上下方向中央部に固定されており、西側の端部が北西側の支柱31の上下方向中央部に固定されている。尚、定着梁36には、緊張材3を通すための孔(図示せず)が複数形成されている。 An anchoring beam 36 is provided so as to straddle the vertical center of the two pillars 31 located on the north side. The anchoring beam 36 is located north of the two pillars 31 located on the north side. The eastern end of the anchoring beam 36 is fixed to the vertical center of the northeastern pillar 31, and the western end is fixed to the vertical center of the northwestern pillar 31. The anchoring beam 36 has multiple holes (not shown) formed therein for passing the tension members 3 through.
北側に位置する2つの支柱31には、定着梁36を支えるための支持フレーム部37aが連結されている。支持フレーム部37aは、北側に位置する2つの支柱31より北側に位置している。 A support frame portion 37a for supporting the fixing beam 36 is connected to the two pillars 31 located on the north side. The support frame portion 37a is located north of the two pillars 31 located on the north side.
南側に位置する2つの支柱31の上下方向中央部に跨がるように、複数(本実施形態では4つ)のジャッキ38を介して、定着梁39が設けられている。ジャッキ38は、南側に位置する2つの支柱31より南側に位置しており、定着梁39は、ジャッキ38より南側に位置している。定着梁39は、東側の端部が、上下2つのジャッキ38を介して南東側の支柱31の上下方向中央部に固定されており、西側の端部が、上下2つのジャッキ38を介して南西側の支柱31の上下方向中央部に固定されている。尚、定着梁39には、緊張材3を通すための孔(図示せず)が複数形成されている。ジャッキ38は例えば油圧ジャッキであり、南北方向に伸縮自在である。ジャッキ38の伸縮動作は、操作盤18で作業員によって操作され得る。 The anchoring beam 39 is provided via a plurality of jacks 38 (four in this embodiment) so as to straddle the vertical center of the two columns 31 located on the south side. The jacks 38 are located south of the two columns 31 located on the south side, and the anchoring beam 39 is located south of the jacks 38. The eastern end of the anchoring beam 39 is fixed to the vertical center of the southeastern column 31 via two upper and lower jacks 38, and the western end is fixed to the vertical center of the southwestern column 31 via two upper and lower jacks 38. The anchoring beam 39 has a plurality of holes (not shown) for passing the tension material 3 through. The jacks 38 are, for example, hydraulic jacks, and can be freely extended and retracted in the north-south direction. The extension and retraction operation of the jacks 38 can be operated by an operator using the operation panel 18.
南側に位置する2つの支柱31には、定着梁39を支えるための支持フレーム部37bが連結されている。支持フレーム部37bは、南側に位置する2つの支柱31より南側に位置している。支持フレーム部37bは、ジャッキ38の伸縮による定着梁39の南北方向の移動を案内するガイド部としても機能し得る。 A support frame portion 37b for supporting the anchor beam 39 is connected to the two pillars 31 located on the south side. The support frame portion 37b is located south of the two pillars 31 located on the south side. The support frame portion 37b can also function as a guide portion that guides the movement of the anchor beam 39 in the north-south direction caused by the extension and contraction of the jack 38.
従来、緊張材3に緊張力を付与するために用いられる反力台はコンクリートの塊であって基礎もしっかりしているので移設が困難であった。この点、緊張架台30では、2つの支柱31と1つの上梁32と1つの下梁33とで矩形状のフレーム構造をなしているので、前述の反力台に比べて支柱31自体及びその支持構造を簡素化でき、ひいては、緊張架台30の移設を容易に行うことができる。ゆえに、緊張架台30は移設可能に構成されている。 Conventionally, the reaction base used to apply tension to the tension member 3 was a concrete block with a solid foundation, making it difficult to relocate. In this regard, the tension base 30 has a rectangular frame structure with two pillars 31, one upper beam 32, and one lower beam 33, so the pillars 31 themselves and their support structure can be simplified compared to the reaction base described above, and the tension base 30 can be easily relocated. Therefore, the tension base 30 is configured to be relocatable.
図1に戻り、東側に位置する床版製作セクション11cは、西側の床版製作セクション11aのうち曲げ強度試験装置19が省略されたものと同様である。
床版製作セクション11a,11c間に位置する床版製作セクション11bは、東側の床版製作セクション11cの設備のレイアウトの東西方向を入れ替えたものと同様である。
Returning to FIG. 1, the deck slab construction section 11c located on the east side is similar to the deck slab construction section 11a on the west side with the bending strength test device 19 omitted.
The deck construction section 11b, located between the deck construction sections 11a and 11c, is similar to the deck construction section 11c on the east side, with the east-west orientation swapped.
床版製作施設10では、床版製作セクション11a~11cの各々のテントハウス21,22の延在方向(南北方向)と、床版製作セクション11a~11cの並び方向(東西方向)とが直交している。ゆえに、床版製作施設10では、床版製作セクション11a~11cが並列的に配置されている。 In the deck construction facility 10, the extension direction (north-south direction) of each tent house 21, 22 of the deck construction sections 11a-11c is perpendicular to the arrangement direction (east-west direction) of the deck construction sections 11a-11c. Therefore, in the deck construction facility 10, the deck construction sections 11a-11c are arranged in parallel.
次に、床版1を製作する方法について、前述の図1~図5に加えて、図6~図10を用いて説明する。図6は、床版1の製作方法を示すフローチャートである。図7は、図6中の床版製作工程(ステップS1)の一例を示すフローチャートである。図8(ア)~図10(カ)は、図6中の床版製作工程(ステップS1)の一例の説明図である。
この床版製作方法は、床版製作セクション11a~11cの各々で実施され得る。
Next, a method for manufacturing the deck 1 will be described with reference to Figs. 6 to 10 in addition to Figs. 1 to 5 described above. Fig. 6 is a flowchart showing a method for manufacturing the deck 1. Fig. 7 is a flowchart showing an example of the deck manufacturing process (step S1) in Fig. 6. Figs. 8(a) to 10(f) are explanatory diagrams of an example of the deck manufacturing process (step S1) in Fig. 6.
This deck construction method may be carried out in each of the deck construction sections 11a to 11c.
図6に示すように、床版1を製作する方法では、まず、ステップS1にて、床版1の製作を行う(床版製作工程)。床版製作工程は、鉄筋組立ヤード12及び床版製作ヤード13にて実施され得る。 As shown in FIG. 6, in the method for manufacturing the deck 1, first, in step S1, the deck 1 is manufactured (deck manufacturing process). The deck manufacturing process can be carried out in a rebar assembly yard 12 and a deck manufacturing yard 13.
図7に示す床版製作工程の一例では、ステップS11として、図8(ア)に示すように、床版製作ヤード13にて、鋼製の型枠4の組立を行う(型枠組立工程)。本実施形態では、型枠4は、有底で上面開口の矩形箱形であるが、この他、上面開口かつ下面開口の矩形筒形であってもよい。型枠4が矩形筒形である場合には、型枠4の下面開口がコンクリート床又は製作ベッドで塞がれ得る。型枠4は、緊張架台30内にて組み立てられる。本実施形態では、緊張架台30内に2つの型枠4を南北方向に並べて配置しているが、緊張架台30内に配置される型枠4の個数は2つに限らず、1つ又は3つ以上であってもよい。 In an example of the deck manufacturing process shown in FIG. 7, as step S11, as shown in FIG. 8(A), a steel formwork 4 is assembled in the deck manufacturing yard 13 (formwork assembly process). In this embodiment, the formwork 4 is a rectangular box with a bottom and an open top, but it may also be a rectangular cylinder with an open top and bottom. If the formwork 4 is a rectangular cylinder, the bottom opening of the formwork 4 may be blocked by a concrete floor or a manufacturing bed. The formwork 4 is assembled in the tensioning frame 30. In this embodiment, two formworks 4 are arranged side by side in the north-south direction in the tensioning frame 30, but the number of formworks 4 arranged in the tensioning frame 30 is not limited to two, and may be one or three or more.
これと並行して、ステップS21として、鉄筋組立ヤード12にて、鉄筋2の組立(地組)を行う。 In parallel with this, in step S21, rebar 2 is assembled (ground assembly) in the rebar assembly yard 12.
次に、ステップS12として、図8(イ)に示すように、鉄筋組立ヤード12で組み立てられた鉄筋2を型枠4内にセットすると共に、鉄筋2同士の間の隙間を通るように緊張材3をセットする(鉄筋・緊張材配置工程)。ここで、緊張材3は、例えばPC鋼材であり、南北方向に延在している。緊張材3の一端部は固定具5によって定着梁36に固定され、他端部は固定具6によって定着梁39に固定される。 Next, in step S12, as shown in FIG. 8 (A), the rebars 2 assembled in the rebar assembly yard 12 are set in the formwork 4, and tension members 3 are set so as to pass through the gaps between the rebars 2 (rebar and tension member placement process). Here, the tension members 3 are, for example, PC steel members, and extend in the north-south direction. One end of the tension member 3 is fixed to the anchor beam 36 by a fixing device 5, and the other end is fixed to the anchor beam 39 by a fixing device 6.
次に、ステップS13として、図9(ウ)に示すように、ジャッキ38を伸長させることで、緊張材3に緊張力を与える(緊張材緊張工程)。つまり、緊張材3を引っ張る。 Next, in step S13, as shown in FIG. 9 (c), the jack 38 is extended to apply tension to the tension member 3 (tension member tensioning process). In other words, the tension member 3 is pulled.
次に、ステップS14として、緊張材3を緊張させたままの状態で、図9(エ)に示すように、型枠4内にコンクリートCを充填する(コンクリート打設工程)。ここで、床版1は、コンクリートCと鉄筋2と緊張材3とを含んで構成される。 Next, in step S14, while the tension members 3 are kept tensioned, concrete C is poured into the formwork 4 as shown in FIG. 9 (E) (concrete pouring process). Here, the deck 1 is composed of the concrete C, the reinforcing bars 2, and the tension members 3.
次に、ステップS15として、打設されたコンクリートCの養生を行う(養生工程)。この養生工程では、例えば蒸気養生が行われる。この蒸気養生では、コンクリートCが充填された型枠4上をシートなどで覆い、このシートで覆われた内側にボイラー17からの蒸気を導入する。これにより、型枠4内のコンクリートCの温度を強制的に上昇させることで、強度の発現を促進させることができる。尚、蒸気養生で当該シート内の温度を所定時間の間、所定温度(例えば50℃程度)で保持する温度制御装置を設けてもよい。 Next, in step S15, the poured concrete C is cured (curing process). In this curing process, for example, steam curing is performed. In this steam curing, the formwork 4 filled with the concrete C is covered with a sheet or the like, and steam from the boiler 17 is introduced inside the sheet. This forcibly increases the temperature of the concrete C inside the formwork 4, thereby promoting the development of strength. Note that a temperature control device may be provided to maintain the temperature inside the sheet at a predetermined temperature (for example, about 50°C) for a predetermined period of time during steam curing.
養生工程が完了すると、次に、ステップS16として、図10(オ)に示すようにジャッキ38を短縮させることで緊張材3の緊張を緩めた後、図10(カ)に示すように、緊張材3のうち余分な部分を切除する(緊張材弛緩・切断工程)。この緊張材3の弛緩により、床版1内に圧縮力(プレストレス)が付与される。 After the curing process is completed, in step S16, the tension of the tension member 3 is released by shortening the jack 38 as shown in FIG. 10 (E), and then the excess portion of the tension member 3 is cut off as shown in FIG. 10 (F) (tension member release and cutting process). This release of the tension member 3 applies a compressive force (prestress) to the deck slab 1.
この切除後、又は、この切除に並行して、ステップS17として、型枠4を解体して撤去する(脱型工程)。このようにして、プレキャストコンクリート製の床版1が製作される。 After this cutting, or in parallel with this cutting, in step S17, the formwork 4 is dismantled and removed (removal process). In this way, the precast concrete deck 1 is produced.
尚、前述の例では、製作されるプレキャストコンクリート製の床版1がプレストレストコンクリート床版(プレキャストPC床版)であるが、この他、製作されるプレキャストコンクリート製の床版1がRC床版(プレキャストRC床版)であってもよい。製作されるプレキャストコンクリート製の床版1がRC床版(プレキャストRC床版)である場合には、前述のステップS12,S13,S16における緊張材3に関する事項が省略される。 In the above example, the precast concrete slab 1 to be manufactured is a prestressed concrete slab (precast PC slab), but the precast concrete slab 1 to be manufactured may also be an RC slab (precast RC slab). If the precast concrete slab 1 to be manufactured is an RC slab (precast RC slab), the matters related to the tension member 3 in the above steps S12, S13, and S16 are omitted.
また、前述の例では、プレキャストコンクリート製の床版1が、いわゆるプレテンション方式で製作されるプレキャストPC床版であるが、この他、いわゆるポストテンション方式で製作されるプレキャストPC床版であってもよい。 In the above example, the precast concrete deck 1 is a precast PC deck manufactured using the so-called pretensioning method, but it may also be a precast PC deck manufactured using the so-called post-tensioning method.
床版製作工程(図6のステップS1)は、壁高欄8(図1~図3参照)を床版1と一体的に製作することを含み得る。
床版製作工程(ステップS1)が完了すると、ステップS2として、製作された床版1の洗い出しが行われる(床版洗い出し工程)。床版洗い出し工程は、洗い出し・検査ヤード14にて実施され得る。床版洗い出し工程では、床版1の表面に付着した、脱型を容易にするための剥離剤などが洗い流され得る。
The deck manufacturing process (step S1 in FIG. 6) may include manufacturing a wall parapet 8 (see FIGS. 1 to 3) integrally with the deck 1.
When the deck manufacturing process (step S1) is completed, the manufactured deck 1 is washed out in step S2 (deck washing process). The deck washing process can be carried out in a washing and inspection yard 14. In the deck washing process, a release agent and the like that is attached to the surface of the deck 1 and that facilitates demolding can be washed away.
洗い出しが完了した床版1については、ステップS3に進み、寸法検査及び外観検査などの品質検査が行われる(床版検査工程)。
ステップS3にて寸法検査及び外観検査などの品質検査が行われた床版1については、当該床版1が曲げ強度試験の対象であれば、ステップS4からステップS5に進み、曲げ強度試験装置19を用いて当該床版1の曲げ強度試験を行う(曲げ強度試験工程)。この曲げ強度試験が完了した床版1については、ストックヤード15に運搬されて保管される。ここで、ステップS3からステップS5に至る工程は、床版1の品質を検査する工程(床版品質検査工程)である。
Once the washing out is complete, the deck slab 1 proceeds to step S3, where quality inspections such as dimensional inspection and appearance inspection are carried out (deck slab inspection process).
For the deck 1 that has undergone quality inspections such as dimensional inspection and visual inspection in step S3, if the deck 1 is subject to a bending strength test, the process proceeds from step S4 to step S5, where a bending strength test is conducted on the deck 1 using a bending strength test device 19 (bending strength test process). The deck 1 that has completed this bending strength test is transported to and stored in the stockyard 15. Here, the process from step S3 to step S5 is a process for inspecting the quality of the deck 1 (deck quality inspection process).
一方、ステップS3にて寸法検査及び外観検査などの品質検査が行われた床版1について、当該床版1が曲げ強度試験の対象でなければ、ストックヤード15に運搬されて保管される。
このようにして、床版製作セクション11a~11cの各々で、床版1が製作される。
On the other hand, if the deck 1 that has undergone quality inspection such as dimensional inspection and visual inspection in step S3 is not subject to a bending strength test, it is transported to the stockyard 15 and stored.
In this manner, the deck 1 is produced in each of the deck production sections 11a to 11c.
尚、床版製作施設10では、製作された複数の床版1のうちの一部に対して曲げ強度試験を施している。それゆえ、床版製作セクション11a~11cのうち床版製作セクション11aのみが曲げ強度試験装置19を有している。この曲げ強度試験装置19を床版製作セクション11b,11cが有してもいいことは言うまでもない。すなわち、曲げ強度試験装置19は、床版製作セクション11a~11cの少なくとも1つに設けられ得る。 In addition, in the deck manufacturing facility 10, bending strength tests are conducted on some of the multiple decks 1 that have been manufactured. Therefore, of the deck manufacturing sections 11a to 11c, only the deck manufacturing section 11a has a bending strength test device 19. It goes without saying that the deck manufacturing sections 11b and 11c may also have this bending strength test device 19. In other words, the bending strength test device 19 may be provided in at least one of the deck manufacturing sections 11a to 11c.
図11は、本実施形態における床版製作施設100の第2例に対応する床版製作施設10’の平面図である。図12及び図13は、床版製作施設10’を構成する床版製作セクション11a’の平面図及び側面図である。図14は図12のB-B矢視図である。尚、説明の便宜上、図11~図14に示すように東西南北を規定して以下説明するが、床版製作施設10’の各構成要素と東西南北との関係が図示のものに限らないことは言うまでもない。また、図13では、図示簡略化のため、走行用レール26の図示を省略している。
前述の床版製作施設10と床版製作施設10’とで異なる点について説明する。
FIG. 11 is a plan view of a deck fabrication facility 10' corresponding to a second example of the deck fabrication facility 100 in this embodiment. FIG. 12 and FIG. 13 are plan and side views of a deck fabrication section 11a' constituting the deck fabrication facility 10'. FIG. 14 is a view taken along the arrows B-B in FIG. 12. For convenience of explanation, the following description will be given with east-west-north-south directions defined as shown in FIG. 11 to FIG. 14, but it goes without saying that the relationship between each component of the deck fabrication facility 10' and east-west-north-south directions is not limited to that shown in the drawings. Also, in FIG. 13, the running rails 26 are omitted for the sake of simplicity.
The differences between the deck slab production facility 10 and the deck slab production facility 10' described above will be described.
床版製作施設10’では、床版製作セクション11a’~11c’の各々のテントハウス21,22の延在方向(南北方向)と、床版製作セクション11a’~11c’の並び方向(南北方向)とが一致している。ゆえに、床版製作施設10’では、床版製作セクション11a’~11c’が直列的に配置されている。また、床版製作セクション11a’~11c’の各々では、鉄筋組立ヤード12、床版製作ヤード13、洗い出し・検査ヤード14、及び、ストックヤード15が、南北方向に一直線上に並んでいる(すなわち、直列的に配置されている)。 In the deck construction facility 10', the extension direction (north-south direction) of the tent houses 21, 22 of each of the deck construction sections 11a'-11c' coincides with the arrangement direction (north-south direction) of the deck construction sections 11a'-11c'. Therefore, in the deck construction facility 10', the deck construction sections 11a'-11c' are arranged in series. Also, in each of the deck construction sections 11a'-11c', the rebar assembly yard 12, deck construction yard 13, washout/inspection yard 14, and stockyard 15 are arranged in a straight line in the north-south direction (i.e., arranged in series).
床版製作セクション11a’~11c’の各々では、揚重装置25として、橋型クレーン(門型クレーン)を用いている。揚重装置25は、南北方向に延びる一対の走行用レール26に沿って走行可能である。走行用レール26間には鉄筋組立ヤード12、床版製作ヤード13、洗い出し・検査ヤード14、及び、ストックヤード15が位置している。尚、揚重装置25には、前述の揚重装置20と同様に前述の役割(1)~(5)がある。 Each of the deck construction sections 11a'-11c' uses a bridge crane (gantry crane) as the lifting device 25. The lifting device 25 can travel along a pair of running rails 26 that extend in the north-south direction. Between the running rails 26 are located the rebar assembly yard 12, deck construction yard 13, washout and inspection yard 14, and stockyard 15. The lifting device 25 has the aforementioned roles (1)-(5) like the previously described lifting device 20.
図11に示されている例では、走行用レール26が、床版製作セクション11a’,11b’間で分断され、かつ、床版製作セクション11b’,11c’間で分断されているが、この他、走行用レール26が、床版製作セクション11a’,11b’間で連結され、かつ、床版製作セクション11b’,11c’間で連結されてもよい。この場合には、揚重装置25が、床版製作セクション11a’~11c’を往来することができる。 In the example shown in FIG. 11, the running rails 26 are separated between the deck construction sections 11a' and 11b' and between the deck construction sections 11b' and 11c', but the running rails 26 may also be connected between the deck construction sections 11a' and 11b' and between the deck construction sections 11b' and 11c'. In this case, the lifting device 25 can travel between the deck construction sections 11a' to 11c'.
床版製作施設10(床版製作セクション11a~11c)と床版製作施設10’(床版製作セクション11a’~11c’)とを比較すると、設備のレイアウト(換言すれば、鉄筋組立ヤード12、床版製作ヤード13、洗い出し・検査ヤード14、ストックヤード15、発電機16、ボイラー17、操作盤18、曲げ強度試験装置19、テントハウス21,22、緊張架台30などの相互間の位置関係(配置))が明らかに異なっている。ここで、床版製作施設10,10’(床版製作施設100)の設備としては、鉄筋組立ヤード12、床版製作ヤード13、洗い出し・検査ヤード14、ストックヤード15、発電機16、ボイラー17、操作盤18、曲げ強度試験装置19、テントハウス21,22、緊張架台30などを挙げることができる。 Comparing the deck fabrication facility 10 (slab fabrication sections 11a-11c) and the deck fabrication facility 10' (slab fabrication sections 11a'-11c'), the layout of the facilities (in other words, the relative positions (arrangements) of the rebar assembly yard 12, deck fabrication yard 13, washout/inspection yard 14, stockyard 15, generator 16, boiler 17, operation panel 18, bending strength test device 19, tent houses 21, 22, tensioning frame 30, etc.) is clearly different. Here, the facilities of the deck fabrication facilities 10, 10' (slab fabrication facility 100) include the rebar assembly yard 12, deck fabrication yard 13, washout/inspection yard 14, stockyard 15, generator 16, boiler 17, operation panel 18, bending strength test device 19, tent houses 21, 22, tensioning frame 30, etc.
次に、床版の架け替え方法の一例について、前述の図1~図14に加えて、図15を用いて説明する。
図15は、床版製作施設10,10’の仮設場所の例を示す図である。図15(ア)は高速道路40における交通規制範囲41を示す平面図である。図15(イ)は図15(ア)のC-C断面図である。
ここで、床版の架け替え方法は、本発明の「橋の構築方法」に含まれるものである。
Next, an example of a method for replacing a deck slab will be described with reference to FIG. 15 in addition to the above-mentioned FIGS.
Figure 15 is a diagram showing an example of a temporary location for the deck fabrication facilities 10, 10'. Figure 15(A) is a plan view showing a traffic control area 41 on an expressway 40. Figure 15(B) is a cross-sectional view taken along CC in Figure 15(A).
Here, the method for replacing a deck is included in the "bridge construction method" of the present invention.
図15に示すように、交通規制範囲41内に橋42の床版取替工事範囲43が位置している。橋42の床版取替工事範囲43内にて、既設床版の撤去と新設床版の設置とが行われる。この新設床版として、床版製作施設10及び/又は床版製作施設10’で製作された複数の床版1が用いられる。 As shown in FIG. 15, the deck replacement work area 43 of the bridge 42 is located within the traffic control area 41. Within the deck replacement work area 43 of the bridge 42, the existing deck will be removed and a new deck will be installed. Multiple decks 1 manufactured at the deck manufacturing facility 10 and/or deck manufacturing facility 10' will be used as this new deck.
橋42における床版の架け替え方法(橋42の構築方法)では、床版取替工事範囲43内において、既設床版が撤去された箇所に複数の床版1を新設床版として橋42の橋軸方向に順次並べることで橋42の構築を進める。ここにおいて、橋42の構築方法は、複数の床版1を橋42の橋軸方向に並べることで橋42を構築する方法である。 In the method for replacing the deck of a bridge 42 (method for constructing a bridge 42), construction of the bridge 42 is advanced by sequentially lining up multiple decks 1 in the bridge axis direction of the bridge 42 as new decks in the area of the deck replacement work 43 where the existing deck has been removed. Here, the method for constructing the bridge 42 is a method for constructing the bridge 42 by lining up multiple decks 1 in the bridge axis direction of the bridge 42.
床版製作施設10(並列型)については、例えば、図15中の橋下面用地P1、高速道路40及び/又は橋42の近傍の一般用地P2、交通規制範囲41内のサービスエリア又はパーキングエリアP3などに仮設され得る。 The deck fabrication facility 10 (parallel type) can be temporarily installed, for example, in the bridge underside site P1 in FIG. 15, in general site P2 near the expressway 40 and/or bridge 42, or in a service area or parking area P3 within the traffic control area 41.
床版製作施設10’(直列型)については、例えば、図15中の橋下面用地P1、高速道路40及び/又は橋42の近傍の一般用地P2、交通規制範囲41内の道路面P4上などに仮設され得る。 The deck fabrication facility 10' (straight type) can be temporarily installed, for example, on the bridge underside site P1 in FIG. 15, on general site P2 near the expressway 40 and/or bridge 42, or on the road surface P4 within the traffic control area 41.
ここで、橋42における床版の架け替え方法(橋42の構築方法)は、床版製作施設10,10’を橋42の下方(例えば橋下面用地P1)に仮設することを含み得る。例えば、橋42上にクレーンなどの揚重装置を配置して当該揚重装置を用いて床版1を床版製作施設10,10’から橋42における床版1の設置場所まで揚重してもよい。この場合には、従来のものに比べて大きな寸法の床版1を製作することができる。 Here, the method of replacing the deck of the bridge 42 (method of constructing the bridge 42) may include temporarily setting up the deck manufacturing facility 10, 10' below the bridge 42 (e.g., the bridge underside site P1). For example, a lifting device such as a crane may be placed on the bridge 42, and the deck 1 may be lifted from the deck manufacturing facility 10, 10' to the installation location of the deck 1 on the bridge 42 using the lifting device. In this case, a deck 1 with larger dimensions than conventional ones can be manufactured.
また、橋42における床版の架け替え方法(橋42の構築方法)は、床版製作施設10を高速道路40のサービスエリア又はパーキングエリアP3に仮設することを含み得る。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 The method for replacing the deck of the bridge 42 (the method for constructing the bridge 42) may also include temporarily setting up the deck manufacturing facility 10 in a service area or parking area P3 of the expressway 40. In this case, too, it is possible to manufacture a deck 1 with dimensions larger than those of conventional ones.
また、橋42における床版の架け替え方法(橋42の構築方法)は、床版製作施設10’を、道路に隣接するチェーン着脱場に仮設することを含み得る。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。ここで、チェーン着脱場とは、車両のタイヤに対してチェーンの着脱作業を行うための場所である。 The method for replacing the deck of the bridge 42 (the method for constructing the bridge 42) may also include temporarily setting up the deck manufacturing facility 10' at a chain attachment/detachment site adjacent to the road. In this case, a deck 1 with larger dimensions than conventional ones can be manufactured. Here, the chain attachment/detachment site is a place where chains are attached to and detached from vehicle tires.
また、橋42における床版の架け替え方法(橋42の構築方法)は、床版製作施設10’を、道路における通行止めの領域上(例えば高速道路40における交通規制範囲41内の道路面P4上)に仮設することを含み得る。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 The method for replacing the deck of the bridge 42 (the method for constructing the bridge 42) may also include temporarily setting up the deck manufacturing facility 10' on a closed area of the road (for example, on the road surface P4 within the traffic control area 41 of the expressway 40). In this case, too, it is possible to manufacture a deck 1 with dimensions larger than those of conventional ones.
また、橋42における床版の架け替え方法(橋42の構築方法)は、床版製作施設10’を、橋42における既設の床版上(例えば、新設床版として既に橋42に設置された床版1上)に仮設することを含み得る。この点、図16は、床版製作施設10’を既設の床版上(例えば、新設床版として既に橋42に設置された床版1上)に仮設した状態を示している。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。尚、図16に図示されている揚重装置25については、走行用レール26が省略されており、その代わりとして、既設の床版上を転動可能な車輪27を有している。また、図16に図示されている揚重装置25については、壁高欄8に接触可能な車輪28も有しており、この車輪28によって、揚重装置25の走行がガイドされ得る。 The method of replacing the deck of the bridge 42 (the method of constructing the bridge 42) may include temporarily setting up the deck manufacturing facility 10' on the existing deck of the bridge 42 (for example, on the deck 1 already installed on the bridge 42 as a new deck). In this regard, FIG. 16 shows the deck manufacturing facility 10' temporarily set up on the existing deck (for example, on the deck 1 already installed on the bridge 42 as a new deck). In this case, a deck 1 with a larger size than the conventional one can be manufactured. Note that the lifting device 25 shown in FIG. 16 does not have the running rail 26, and instead has wheels 27 that can roll on the existing deck. The lifting device 25 shown in FIG. 16 also has wheels 28 that can contact the wall parapet 8, and the running of the lifting device 25 can be guided by these wheels 28.
また、橋42における床版の架け替え方法(橋42の構築方法)では、床版製作施設10,10’が橋42に隣接し得る(例えば、床版製作施設10,10’が、一般用地P2に仮設され得る)。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 In addition, in the method of replacing the deck of the bridge 42 (the method of constructing the bridge 42), the deck manufacturing facility 10, 10' may be adjacent to the bridge 42 (for example, the deck manufacturing facility 10, 10' may be temporarily installed on the general site P2). In this case, a deck 1 with larger dimensions than the conventional one can be manufactured.
尚、床版製作施設10,10’から橋42における床版1の設置場所までの床版運搬経路が公道を含まないことが好ましい。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 It is preferable that the route for transporting the deck from the deck manufacturing facility 10, 10' to the installation site of the deck 1 on the bridge 42 does not include a public road. Even in this case, it is possible to manufacture a deck 1 with larger dimensions than conventional ones.
本実施形態では、床版製作施設10,10’は、床版1を構成する緊張材3に緊張力を付与するための設備(緊張架台30)を備え、この設備(緊張架台30)が移設可能に構成されている。また、床版製作施設10,10’は、床版1の品質を検査するための設備(曲げ強度試験装置19)を備え、この設備(曲げ強度試験装置19)が移設可能に構成されている。ゆえに、床版製作施設10,10’の移設(移転)をスムーズに行うことができる。 In this embodiment, the deck fabrication facility 10, 10' includes equipment (tensioning frame 30) for applying tension to the tension members 3 that make up the deck 1, and this equipment (tensioning frame 30) is configured to be relocatable. The deck fabrication facility 10, 10' also includes equipment (bending strength testing device 19) for inspecting the quality of the deck 1, and this equipment (bending strength testing device 19) is configured to be relocatable. Therefore, the deck fabrication facility 10, 10' can be smoothly relocated (moved).
本実施形態において、床版製作施設10,10’では壁高欄8を床版1と一体的に製作する。これにより、現場での壁高欄8の形成作業を削減することができる。 In this embodiment, the balustrade 8 is manufactured integrally with the slab 1 in the slab manufacturing facilities 10, 10'. This reduces the work required to form the balustrade 8 on-site.
次に、床版製作施設100を移設元から移設先に移設する方法について、前述の図1~図16に加えて、図17を用いて説明する。
図17は、本実施形態における床版製作施設100の移設方法を示すフローチャートである。
Next, a method for relocating the deck slab production facility 100 from the source to the destination will be described with reference to FIG. 17 in addition to the above-mentioned FIGS.
FIG. 17 is a flowchart showing a method for relocating the deck manufacturing facility 100 in this embodiment.
この移設方法では、まず、ステップS31にて、床版製作施設100の移設先を決定する。
次に、ステップS32にて、当該移設先での床版製作施設100の設備のレイアウトを決定する。
次に、ステップS33にて、床版製作施設100を移設元から移設先へ移設する。
In this relocation method, first, in step S31, a relocation destination for the deck slab fabrication facility 100 is determined.
Next, in step S32, the layout of the equipment of the deck manufacturing facility 100 at the relocation destination is determined.
Next, in step S33, the deck manufacturing facility 100 is moved from the original location to the destination location.
床版製作施設100を移設元から移設先へ移設する際には、設備のレイアウトが変更され得る。例えば、移設元での床版製作施設100の設備のレイアウトが前述の床版製作施設10(並列型)の設備のレイアウトであり、移設先での床版製作施設100の設備のレイアウトが前述の床版製作施設10’(直列型)の設備のレイアウトである場合には、移設元での床版製作施設100の設備のレイアウトと、移設先での床版製作施設100の設備のレイアウトとが異なる。 When the deck fabrication facility 100 is moved from the source to the destination, the layout of the equipment may be changed. For example, if the equipment layout of the deck fabrication facility 100 at the source is the equipment layout of the deck fabrication facility 10 (parallel type) described above, and the equipment layout of the deck fabrication facility 100 at the destination is the equipment layout of the deck fabrication facility 10' (series type) described above, then the equipment layout of the deck fabrication facility 100 at the source and the equipment layout of the deck fabrication facility 100 at the destination will be different.
尚、ステップS33にて床版製作施設100を移設元から移設先へ移設する際には、設備のレイアウトが変更されなくてもよい。すなわち、移設元での床版製作施設100の設備のレイアウトと、移設先での床版製作施設100の設備のレイアウトとが同じであってもよい。 When the deck fabrication facility 100 is moved from the source to the destination in step S33, the layout of the equipment does not need to be changed. In other words, the layout of the equipment of the deck fabrication facility 100 at the source may be the same as the layout of the equipment of the deck fabrication facility 100 at the destination.
前述の移設元及び移設先の少なくとも一方は、床版製作施設100で製作される床版1が設置される橋42の下方(例えば橋下面用地P1)に位置し得る。例えば、橋42上にクレーンなどの揚重装置を配置して当該揚重装置を用いて床版1を床版製作施設100から橋42における床版1の設置場所まで揚重してもよい。この場合には、従来のものに比べて大きな寸法の床版1を製作することができる。 At least one of the aforementioned source and destination locations may be located below the bridge 42 (e.g., bridge underside site P1) on which the deck 1 produced in the deck manufacturing facility 100 is to be installed. For example, a lifting device such as a crane may be placed on the bridge 42, and the deck 1 may be lifted from the deck manufacturing facility 100 to the installation location of the deck 1 on the bridge 42 using the lifting device. In this case, a deck 1 with larger dimensions than conventional ones can be manufactured.
前述の移設元及び移設先の少なくとも一方は、床版製作施設100で製作される床版1が設置される橋42に隣接し得る(例えば、床版製作施設100が、一般用地P2に仮設され得る)。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 At least one of the aforementioned source and destination locations may be adjacent to the bridge 42 on which the deck 1 produced in the deck production facility 100 will be installed (for example, the deck production facility 100 may be temporarily installed on general site P2). In this case, a deck 1 with larger dimensions than conventional ones can be produced.
前述の移設元及び移設先の少なくとも一方は、床版製作施設100で製作される床版1が設置される橋42における既設の床版上(例えば、新設床版として既に橋42に設置された床版1上)に位置し得る(図16参照)。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 At least one of the aforementioned source and destination points can be located on an existing deck of the bridge 42 on which the deck 1 produced in the deck production facility 100 will be installed (for example, on a deck 1 that has already been installed on the bridge 42 as a new deck) (see FIG. 16). In this case, too, a deck 1 with larger dimensions than conventional ones can be produced.
前述の移設元及び移設先の少なくとも一方は、高速道路40のサービスエリア又はパーキングエリアP3に位置し得る。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 At least one of the source and destination of the relocation may be located in a service area or parking area P3 of the expressway 40. In this case, too, it is possible to manufacture a deck 1 with larger dimensions than conventional ones.
前述の移設元及び移設先の少なくとも一方は、道路に隣接するチェーン着脱場に位置し得る。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 At least one of the aforementioned source and destination locations can be located at a chain attachment/detachment site adjacent to a road. In this case, too, it is possible to manufacture a deck 1 with larger dimensions than conventional ones.
前述の移設元及び移設先の少なくとも一方は、道路における通行止めの領域上(例えば高速道路40における交通規制範囲41内の道路面P4上)に位置し得る。この場合にも、従来のものに比べて大きな寸法の床版1を製作することができる。 At least one of the aforementioned source and destination locations may be located in a closed area of a road (for example, on road surface P4 within traffic control area 41 of expressway 40). In this case, too, it is possible to manufacture a deck 1 with larger dimensions than conventional ones.
図18(ア)及び(イ)は、本実施形態における床版架け替えプロジェクトの第1例及び第2例を示す。図19は、本実施形態における床版架け替えプロジェクトの第3例を示す。 Figures 18(a) and (b) show a first and second example of a deck replacement project in this embodiment. Figure 19 shows a third example of a deck replacement project in this embodiment.
図18(ア)に示す床版架け替えプロジェクトの第1例では、橋42の床版取替工事範囲43が50~100m程度であり、短い。それゆえ、当該プロジェクトのために仮設された床版製作施設100については、当該プロジェクトが完了するまで、移設を行わない。当該プロジェクトが完了すると、次の別のプロジェクトにおける床版製作施設100の仮設場所(移設先)の用地形状などに応じて、必要であれば床版製作施設100の設備のレイアウトの変更を行いつつ、床版製作施設100の移設を実施する。 In the first example of a deck replacement project shown in FIG. 18 (A), the deck replacement work area 43 of the bridge 42 is short, about 50 to 100 m. Therefore, the deck fabrication facility 100 temporarily constructed for this project will not be relocated until the project is completed. Once the project is completed, the deck fabrication facility 100 will be relocated, with the layout of the facilities of the deck fabrication facility 100 changed if necessary, depending on the shape of the land at the temporary location (relocation destination) of the deck fabrication facility 100 for the next different project.
図18(イ)に示す床版架け替えプロジェクトの第2例では、橋42の床版取替工事範囲43が300~400m以上であり、長い。それゆえ、当該プロジェクトでは、橋42における床版の架け替え施工の進捗状況に応じて(換言すれば、橋42の構築施工の進捗状況に応じて)、床版製作施設100の移設が行われる。例えば、図18(イ)に示すように、橋42の構築が進むと、床版製作施設100が、移設元である橋下面用地P1-1から、移設先である橋下面用地P1-2に移設される。この場合には、橋下面用地P1-2(移設先)の用地形状などに応じて、必要であれば床版製作施設100の設備のレイアウトの変更を行いつつ、床版製作施設100の移設を実施する。 In the second example of a deck replacement project shown in FIG. 18(A), the deck replacement work area 43 of the bridge 42 is long, at 300 to 400 m or more. Therefore, in this project, the deck fabrication facility 100 is relocated according to the progress of the deck replacement work on the bridge 42 (in other words, according to the progress of the construction of the bridge 42). For example, as shown in FIG. 18(A), as the construction of the bridge 42 progresses, the deck fabrication facility 100 is relocated from the bridge underside site P1-1, which is the source of the relocation, to the bridge underside site P1-2, which is the destination of the relocation. In this case, the layout of the equipment of the deck fabrication facility 100 is changed if necessary depending on the site shape of the bridge underside site P1-2 (destination), and the deck fabrication facility 100 is relocated.
図19に示す床版架け替えプロジェクトの第3例では、高速道路40におけるインターチェンジM1,M2間の複数(図19では4つ)の橋42-1~42-4の床版更新を一括して行う。ここで、インターチェンジM1,M2間の距離は20~30km程度と非常に長い。当該プロジェクトでは、橋42-1~42-4の床版架け替えのスケジュールに応じて、床版製作施設100を移設するようにしてもよい。又は、橋42-1~42-4の各々に対応するように床版製作施設100を各別に仮設してもよい。床版製作施設100は、このような複雑かつ大規模なプロジェクトにおいても、容易に移設できるという柔軟性を持って効率良く床版1の製作を行うことができる。 In the third example of a deck replacement project shown in FIG. 19, deck replacement is performed on multiple bridges 42-1 to 42-4 (four in FIG. 19) between interchanges M1 and M2 on a highway 40 at the same time. Here, the distance between interchanges M1 and M2 is very long, about 20 to 30 km. In this project, the deck manufacturing facility 100 may be relocated according to the schedule for replacing the decks of bridges 42-1 to 42-4. Alternatively, the deck manufacturing facility 100 may be temporarily installed separately for each of bridges 42-1 to 42-4. The deck manufacturing facility 100 can efficiently manufacture decks 1 with the flexibility of being easily relocated, even in such a complex and large-scale project.
尚、前述の床版架け替えプロジェクトの第1例~第3例において、以下のケース1~3があり得る。
〔ケース1〕
床版製作施設100を移設する際に、設備(例えば緊張架台30など)の規模が大きくなったり小さくなったりする場合がある。
〔ケース2〕
工事が連続しないこともあるので、その場合には、移設元の設備を別の場所に仮置きし、その後、当該設備を当該別の場所から移設先に運搬する。
〔ケース3〕
床版製作施設100の仮設場所ごとで、床版製作施設100の設備の一部(例えばH形鋼、テントなど)をリース会社から調達する形とし、当該一部については、移設元から移設先に運搬しない場合がある。
In the above-mentioned first to third examples of deck replacement projects, the following cases 1 to 3 are possible.
[Case 1]
When the deck manufacturing facility 100 is relocated, the size of the equipment (e.g., the tension frame 30, etc.) may increase or decrease.
[Case 2]
Since construction work may not be continuous, in such cases the equipment to be relocated is temporarily placed in another location, and then the equipment is transported from the other location to the new location.
[Case 3]
For each temporary location of the deck fabrication facility 100, some of the equipment for the deck fabrication facility 100 (e.g., H-shaped steel, tents, etc.) will be procured from a leasing company, and this part may not be transported from the source to the destination.
図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。
尚、特願2019-158646号の出願当初の請求項は以下のとおりであった。
[請求項1]
プレキャストコンクリート製の床版を製作する床版製作施設を移設元から移設先に移設する方法であって、
前記移設元での前記床版製作施設の設備のレイアウトと、前記移設先での前記床版製作施設の設備のレイアウトとが異なる、床版製作施設の移設方法。
[請求項2]
前記床版製作施設は、前記床版を構成する緊張材に緊張力を付与するための設備を備え、この設備が移設可能に構成されている、請求項1に記載の床版製作施設の移設方法。
[請求項3]
前記床版製作施設は、前記床版の品質を検査するための設備を備え、この設備が移設可能に構成されている、請求項1又は請求項2に記載の床版製作施設の移設方法。
[請求項4]
前記床版製作施設では壁高欄を前記床版と一体的に製作する、請求項1~請求項3のいずれか1つに記載の床版製作施設の移設方法。
[請求項5]
前記移設元及び前記移設先の少なくとも一方は、前記床版製作施設で製作される前記床版が設置される橋に隣接している、請求項1~請求項4のいずれか1つに記載の床版製作施設の移設方法。
[請求項6]
前記移設元及び前記移設先の少なくとも一方は、前記床版製作施設で製作される前記床版が設置される橋における既設の床版上に位置する、請求項1~請求項4のいずれか1つに記載の床版製作施設の移設方法。
[請求項7]
前記移設元及び前記移設先の少なくとも一方は、前記床版製作施設で製作される前記床版が設置される橋の下方に位置する、請求項1~請求項4のいずれか1つに記載の床版製作施設の移設方法。
[請求項8]
前記移設元及び前記移設先の少なくとも一方は、高速道路のサービスエリア又はパーキングエリアに位置する、請求項1~請求項4のいずれか1つに記載の床版製作施設の移設方法。
[請求項9]
前記移設元及び前記移設先の少なくとも一方は、道路に隣接するチェーン着脱場に位置する、請求項1~請求項4のいずれか1つに記載の床版製作施設の移設方法。
[請求項10]
前記移設元及び前記移設先の少なくとも一方は、道路における通行止めの領域上に位置する、請求項1~請求項4のいずれか1つに記載の床版製作施設の移設方法。
[請求項11]
プレキャストコンクリート製の床版を製作する床版製作施設を移設元から移設先に移設する方法であって、
前記移設元での前記床版製作施設の設備のレイアウトと、前記移設先での前記床版製作施設の設備のレイアウトとが同じである、床版製作施設の移設方法。
It goes without saying that the illustrated embodiments are merely illustrative of the present invention, and that the present invention encompasses various modifications and variations that may be made by those skilled in the art within the scope of the claims, in addition to those directly shown in the described embodiments.
In addition, the claims at the time of filing of Patent Application No. 2019-158646 were as follows.
[Claim 1]
A method for relocating a floor slab production facility for producing precast concrete floor slabs from a relocation source to a relocation destination, comprising:
A method for relocating a deck fabrication facility, in which the layout of the equipment of the deck fabrication facility at the source of relocation is different from the layout of the equipment of the deck fabrication facility at the destination of relocation.
[Claim 2]
2. The method for relocating a deck slab fabrication facility according to claim 1, wherein the deck slab fabrication facility includes equipment for applying tension to tension members constituting the deck, the equipment being configured to be relocatable.
[Claim 3]
3. The method for relocating a deck slab manufacturing facility according to claim 1, wherein the deck slab manufacturing facility includes equipment for inspecting the quality of the deck slab, and the equipment is configured to be relocatable.
[Claim 4]
The method for relocating a deck slab manufacturing facility according to any one of claims 1 to 3, wherein a wall parapet is manufactured integrally with the deck slab at the deck slab manufacturing facility.
[Claim 5]
A method for relocating a deck fabrication facility described in any one of claims 1 to 4, wherein at least one of the source and destination is adjacent to a bridge on which the deck fabricated at the deck fabrication facility will be installed.
[Claim 6]
A method for relocating a deck fabrication facility described in any one of claims 1 to 4, wherein at least one of the source and destination is located on an existing deck of a bridge on which the deck fabricated at the deck fabrication facility will be installed.
[Claim 7]
A method for relocating a deck fabrication facility described in any one of claims 1 to 4, wherein at least one of the source and destination is located below a bridge on which the deck fabricated at the deck fabrication facility will be installed.
[Claim 8]
A method for relocating a deck manufacturing facility according to any one of claims 1 to 4, wherein at least one of the source and destination is located in a service area or a parking area of a highway.
[Claim 9]
A method for relocating a deck manufacturing facility as described in any one of claims 1 to 4, wherein at least one of the source and destination is located at a chain attachment/detachment site adjacent to a road.
[Claim 10]
A method for relocating a deck manufacturing facility according to any one of claims 1 to 4, wherein at least one of the source and destination is located on a closed area of a road.
[Claim 11]
A method for relocating a floor slab production facility for producing precast concrete floor slabs from a relocation source to a relocation destination, comprising:
A method for relocating a deck fabrication facility, in which the layout of the equipment of the deck fabrication facility at the source of relocation is the same as the layout of the equipment of the deck fabrication facility at the destination of relocation.
1…床版、2…鉄筋、3…緊張材、4…型枠、5,6…固定具、8…壁高欄、10,10’…床版製作施設、11,11a~11c,11a’~11c’…床版製作セクション、12…鉄筋組立ヤード、13…床版製作ヤード、14…洗い出し・検査ヤード、15…ストックヤード、16…発電機、17…ボイラー、18…操作盤、19…曲げ強度試験装置、20…揚重装置、21,22…テントハウス、25…揚重装置、26…走行用レール、27,28…車輪、30…緊張架台、31…支柱、32…上梁、33…下梁、34…縦梁、35…横梁、36…定着梁、37a,37b…支持フレーム部、38…ジャッキ、39…定着梁、40…高速道路、41…交通規制範囲、42,42-1~42-4…橋、43…床版取替工事範囲、100…床版製作施設、C…コンクリート、M1,M2…インターチェンジ、P1,P1-1,P1-2…橋下面用地、P2…一般用地、P3…サービスエリア又はパーキングエリア、P4…道路面 1... Deck, 2... Steel bar, 3... Tendon, 4... Formwork, 5, 6... Fixing device, 8... Wall parapet, 10, 10'... Deck slab production facility, 11, 11a to 11c, 11a' to 11c'... Deck slab production section, 12... Steel bar assembly yard, 13... Deck slab production yard, 14... Washing and inspection yard, 15... Stock yard, 16... Generator, 17... Boiler, 18... Control panel, 19... Bending strength test device, 20... Lifting device, 21, 22... Tent house, 25... Lifting device, 26... Running rail, 27, 28... Wheels, 3 0... tension frame, 31... support, 32... upper beam, 33... lower beam, 34... vertical beam, 35... horizontal beam, 36... fixed beam, 37a, 37b... support frame, 38... jack, 39... fixed beam, 40... expressway, 41... traffic control area, 42, 42-1 to 42-4... bridge, 43... deck replacement work area, 100... deck manufacturing facility, C... concrete, M1, M2... interchange, P1, P1-1, P1-2... bridge underside land, P2... general land, P3... service area or parking area, P4... road surface
Claims (2)
前記移設元での前記床版製作施設の設備のレイアウトと、前記移設先での前記床版製作施設の設備のレイアウトとが異なり、
前記床版製作施設は、前記床版を構成する緊張材に緊張力を付与するための緊張架台を備え、
前記緊張架台は、前記緊張材に緊張力を付与するための反力台として機能する一対の矩形状のフレーム構造を有し、前記一対の矩形状のフレーム構造の各々は、2つの支柱と1つの上梁と1つの下梁とを含んで構成される、床版製作施設の移設方法。 A method for relocating a floor slab production facility for producing precast concrete floor slabs from a relocation source to a relocation destination, comprising:
The layout of the equipment of the deck slab production facility at the relocation source is different from the layout of the equipment of the deck slab production facility at the relocation destination,
The deck fabrication facility includes a tension frame for applying tension to the tension members constituting the deck,
A method for relocating a deck slab manufacturing facility, wherein the tensioning frame has a pair of rectangular frame structures which function as reaction frames for applying tension to the tensioning members, and each of the pair of rectangular frame structures includes two supports, one upper beam, and one lower beam.
前記移設元での前記床版製作施設の設備のレイアウトと、前記移設先での前記床版製作施設の設備のレイアウトとが同じであり、
前記床版製作施設は、前記床版を構成する緊張材に緊張力を付与するための緊張架台を備え、
前記緊張架台は、前記緊張材に緊張力を付与するための反力台として機能する一対の矩形状のフレーム構造を有し、前記一対の矩形状のフレーム構造の各々は、2つの支柱と1つの上梁と1つの下梁とを含んで構成される、床版製作施設の移設方法。 A method for relocating a floor slab production facility for producing precast concrete floor slabs from a relocation source to a relocation destination, comprising:
The layout of the equipment of the deck slab fabrication facility at the relocation source is the same as the layout of the equipment of the deck slab fabrication facility at the relocation destination,
The deck fabrication facility includes a tension frame for applying tension to the tension members constituting the deck,
A method for relocating a deck slab manufacturing facility, wherein the tensioning frame has a pair of rectangular frame structures which function as reaction frames for applying tension to the tensioning members, and each of the pair of rectangular frame structures includes two supports, one upper beam, and one lower beam.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2023130603A JP7519520B2 (en) | 2019-08-30 | 2023-08-10 | How to relocate the deck manufacturing facility |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2019158646A JP7333727B2 (en) | 2019-08-30 | 2019-08-30 | How to relocate the floor slab production facility |
| JP2023130603A JP7519520B2 (en) | 2019-08-30 | 2023-08-10 | How to relocate the deck manufacturing facility |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2019158646A Division JP7333727B2 (en) | 2019-08-30 | 2019-08-30 | How to relocate the floor slab production facility |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2023138774A JP2023138774A (en) | 2023-10-02 |
| JP7519520B2 true JP7519520B2 (en) | 2024-07-19 |
Family
ID=74848335
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2019158646A Active JP7333727B2 (en) | 2019-08-30 | 2019-08-30 | How to relocate the floor slab production facility |
| JP2023130603A Active JP7519520B2 (en) | 2019-08-30 | 2023-08-10 | How to relocate the deck manufacturing facility |
Family Applications Before (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2019158646A Active JP7333727B2 (en) | 2019-08-30 | 2019-08-30 | How to relocate the floor slab production facility |
Country Status (1)
| Country | Link |
|---|---|
| JP (2) | JP7333727B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN121712817A (en) | 2023-08-29 | 2026-03-20 | 三菱化学株式会社 | Resin Composition |
Citations (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000017880A (en) | 1998-06-30 | 2000-01-18 | Ishii Iron Works Co Ltd | Side wall of PC storage tank |
| JP2001049621A (en) | 1999-08-10 | 2001-02-20 | Kansai Electric Power Co Inc:The | Joint structure and joining method for precast floor plate |
| JP2001310318A (en) | 2000-04-27 | 2001-11-06 | Nippon Ps:Kk | Mobile pretensioner |
| JP2002227130A (en) | 2001-02-05 | 2002-08-14 | Dps Bridge Works Co Ltd | Connecting structure for concrete member |
| JP2004243709A (en) | 2003-02-17 | 2004-09-02 | Toda Kogyo Kk | Method and equipment for manufacturing prestressed concrete product |
| JP2004346630A (en) | 2003-05-22 | 2004-12-09 | Haratekku:Kk | Prestressed concrete structure manufacturing device |
| JP2007016478A (en) | 2005-07-07 | 2007-01-25 | Taisei Corp | Ribbed floor slab, ribbed floor slab manufacturing apparatus, and ribbed floor slab manufacturing method |
| JP2008115645A (en) | 2006-11-07 | 2008-05-22 | Shimizu Corp | Three-dimensional intersection structure and method for constructing the three-dimensional intersection structure |
| JP2009264040A (en) | 2008-04-28 | 2009-11-12 | Dps Bridge Works Co Ltd | Concrete floor slab replacing method |
| JP2011006843A (en) | 2009-06-23 | 2011-01-13 | Taisei Corp | Method for constructing building |
| JP2016108789A (en) | 2014-12-04 | 2016-06-20 | 明正工業株式会社 | High strength panel for building |
| JP2018171788A (en) | 2017-03-31 | 2018-11-08 | 株式会社ホクエツ | PC member manufacturing equipment |
Family Cites Families (16)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5113107Y1 (en) * | 1970-10-21 | 1976-04-08 | ||
| JPS5323497Y2 (en) * | 1975-04-14 | 1978-06-17 | ||
| JPS5349841A (en) * | 1976-10-16 | 1978-05-06 | Oriental Concrete Co | Method of rapid execution of bridge by means of preetension girder |
| JPS58180455U (en) * | 1982-05-28 | 1983-12-02 | 株式会社東京衡機製造所 | bending testing machine |
| JPH0689524B2 (en) * | 1989-12-08 | 1994-11-09 | オリエンタル建設株式会社 | Heavy-duty precast concrete product platform |
| JPH0518115A (en) * | 1991-07-12 | 1993-01-26 | Fujita Corp | PC member supply method |
| JP3212151B2 (en) * | 1992-07-17 | 2001-09-25 | 株式会社フジタ | 3D manufacturing equipment for PC |
| JPH07109711A (en) * | 1993-10-12 | 1995-04-25 | Japan Steel & Tube Constr Co Ltd | Continuous feeding method of concrete slab |
| JP2917839B2 (en) * | 1994-11-30 | 1999-07-12 | 鹿島建設株式会社 | Method and apparatus for manufacturing precast block for bridge |
| JP2003014709A (en) | 2001-06-29 | 2003-01-15 | Aoki Corp | Defect probing method for concrete due to strike based on attenuation of energy |
| JP3950757B2 (en) | 2001-09-18 | 2007-08-01 | 株式会社神戸製鋼所 | Synthetic floor slab and its construction method |
| JP2004293060A (en) | 2003-03-25 | 2004-10-21 | Mitsubishi Heavy Ind Ltd | Bridge and its construction method |
| JP4528042B2 (en) | 2004-07-09 | 2010-08-18 | 大成建設株式会社 | Construction method of box girder bridge |
| JP6322437B2 (en) | 2014-02-25 | 2018-05-09 | 鹿島建設株式会社 | Precast concrete member construction method |
| JP6557497B2 (en) | 2015-04-08 | 2019-08-07 | 大成建設株式会社 | Method for producing precast concrete member |
| JP6839530B2 (en) | 2016-12-05 | 2021-03-10 | 鹿島建設株式会社 | Manufacturing method of precast members and precast members |
-
2019
- 2019-08-30 JP JP2019158646A patent/JP7333727B2/en active Active
-
2023
- 2023-08-10 JP JP2023130603A patent/JP7519520B2/en active Active
Patent Citations (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000017880A (en) | 1998-06-30 | 2000-01-18 | Ishii Iron Works Co Ltd | Side wall of PC storage tank |
| JP2001049621A (en) | 1999-08-10 | 2001-02-20 | Kansai Electric Power Co Inc:The | Joint structure and joining method for precast floor plate |
| JP2001310318A (en) | 2000-04-27 | 2001-11-06 | Nippon Ps:Kk | Mobile pretensioner |
| JP2002227130A (en) | 2001-02-05 | 2002-08-14 | Dps Bridge Works Co Ltd | Connecting structure for concrete member |
| JP2004243709A (en) | 2003-02-17 | 2004-09-02 | Toda Kogyo Kk | Method and equipment for manufacturing prestressed concrete product |
| JP2004346630A (en) | 2003-05-22 | 2004-12-09 | Haratekku:Kk | Prestressed concrete structure manufacturing device |
| JP2007016478A (en) | 2005-07-07 | 2007-01-25 | Taisei Corp | Ribbed floor slab, ribbed floor slab manufacturing apparatus, and ribbed floor slab manufacturing method |
| JP2008115645A (en) | 2006-11-07 | 2008-05-22 | Shimizu Corp | Three-dimensional intersection structure and method for constructing the three-dimensional intersection structure |
| JP2009264040A (en) | 2008-04-28 | 2009-11-12 | Dps Bridge Works Co Ltd | Concrete floor slab replacing method |
| JP2011006843A (en) | 2009-06-23 | 2011-01-13 | Taisei Corp | Method for constructing building |
| JP2016108789A (en) | 2014-12-04 | 2016-06-20 | 明正工業株式会社 | High strength panel for building |
| JP2018171788A (en) | 2017-03-31 | 2018-11-08 | 株式会社ホクエツ | PC member manufacturing equipment |
Also Published As
| Publication number | Publication date |
|---|---|
| JP7333727B2 (en) | 2023-08-25 |
| JP2023138774A (en) | 2023-10-02 |
| JP2021038512A (en) | 2021-03-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6004353B2 (en) | Replacement method of concrete floor slab for elevated road | |
| CN114892552B (en) | Box girder type bridge reconstruction construction method | |
| KR101394193B1 (en) | Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type | |
| KR101630244B1 (en) | Apparatus For Supporting A Construction Section And Method of Constructing Construction Section | |
| JP4569878B2 (en) | Bridge girder construction method | |
| CN113638304B (en) | Concrete beam type bridge hidden cover beam structure system and construction method thereof | |
| JP2004278148A (en) | Bridge construction method | |
| KR101214602B1 (en) | Incremental launching apparatus for constructing rail-type concrete slab of composite bridge using shearing connector rail, and method for the same | |
| KR101230049B1 (en) | Incremental launching apparatus for launching concrete slab for bridge using form and rail, and constructing method for the same | |
| CN114481874A (en) | Prefabricated portal frame assembly type box culvert and construction method | |
| KR101127130B1 (en) | A precast type pre-stress box girder bridge excution method | |
| JP7519520B2 (en) | How to relocate the deck manufacturing facility | |
| KR101223753B1 (en) | Incremental launching apparatus for launching concrete slab of tunnel type for composite bridge, and constructing method for the same | |
| CN109778700B (en) | Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road | |
| JPH11200320A (en) | Execution method of horizontal beam of concrete main tower | |
| CN112095780B (en) | A superstructure system for rail operating lines and its implementation method | |
| JP2004324164A (en) | Method of constructing corrugated steel web pc bridge closure section | |
| JP7333728B2 (en) | how to build a bridge | |
| JP2005290889A (en) | Structure of depressed road and its execution method | |
| KR20120054832A (en) | Fcm construction method using i-girder | |
| JP7134133B2 (en) | Bridge railing construction method | |
| JP2000045229A (en) | Bridge construction method | |
| JP6889010B2 (en) | Bridge construction method | |
| JP2000104220A (en) | Construction method of composite truss bridge | |
| JP2536376B2 (en) | Foundation structure of shed for road protection |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20230907 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20240305 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20240308 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240412 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20240625 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20240708 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7519520 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |