JP7611677B2 - Temporary structure, assembly structure for temporary structure, and building construction method - Google Patents
Temporary structure, assembly structure for temporary structure, and building construction method Download PDFInfo
- Publication number
- JP7611677B2 JP7611677B2 JP2020195100A JP2020195100A JP7611677B2 JP 7611677 B2 JP7611677 B2 JP 7611677B2 JP 2020195100 A JP2020195100 A JP 2020195100A JP 2020195100 A JP2020195100 A JP 2020195100A JP 7611677 B2 JP7611677 B2 JP 7611677B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- protruding
- construction
- protruding member
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims description 25
- 238000009435 building construction Methods 0.000 title claims description 20
- 238000010276 construction Methods 0.000 claims description 62
- 239000002184 metal Substances 0.000 claims description 18
- 230000003014 reinforcing effect Effects 0.000 description 13
- 238000010586 diagram Methods 0.000 description 6
- 238000009434 installation Methods 0.000 description 3
- 238000012423 maintenance Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005452 bending Methods 0.000 description 2
- 238000004891 communication Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
Landscapes
- Load-Bearing And Curtain Walls (AREA)
- Steps, Ramps, And Handrails (AREA)
Description
本発明は、仮設構造体、仮設構造体の組み付け構造及び建物施工方法に係り、特に、建物の施工中に用いられ、建物本体に取り付けられる転落防止用の仮設構造体、仮設構造体の組み付け構造及び建物施工方法に関する。 The present invention relates to a temporary structure, an assembly structure for the temporary structure, and a building construction method, and in particular to a temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building, an assembly structure for the temporary structure, and a building construction method.
従来、建物の施工時や施工後のメンテナンス時において、室外側から施工作業を行うために足場や手摺り等の構造体が仮設されている。
また、隣接する隣接構造物と接近して建てられる建物の施工時やメンテナンス時においては、狭小地用の専用足場(専用手摺り)が仮設されている。
2. Description of the Related Art Conventionally, during construction of a building or maintenance after construction, temporary structures such as scaffolding and handrails are set up so that construction work can be carried out from the outside of the building.
In addition, during construction or maintenance of a building that is constructed close to adjacent structures, special scaffolding (special handrails) for narrow spaces are temporarily set up.
上記専用足場を用いれば、狭小スペースにおいて室外側から施工作業を行うことが可能であるものの、作業対象の建物と隣接構造物との間の隙間部分において専用足場を地面から立ち上げる必要があったため、建物の大きさが制約される虞があった。そのため、専用足場を地面から立ち上げる必要のない工法が検討されていた。
上記専用足場に代わる転落防止用の仮設構造体として、例えば特許文献1、2のように、建物本体の施工部材(H形鋼からなる梁)に仮設することが可能な仮設手摺りが提案されている。
Although the above-mentioned dedicated scaffolding makes it possible to carry out construction work from the outside in a small space, it is necessary to erect the dedicated scaffolding from the ground in the gap between the building to be worked on and the adjacent structure, which may limit the size of the building. Therefore, a construction method that does not require erecting the dedicated scaffolding from the ground has been considered.
As a temporary structure for preventing falls as an alternative to the above-mentioned dedicated scaffolding, temporary handrails that can be temporarily installed on construction members (beams made of H-shaped steel) of the main body of a building have been proposed, for example, as disclosed in Patent Documents 1 and 2.
そうしたなかで、既存の仮設手摺りよりも安定性に優れ、容易に取り付け及び取り外しすることが可能な仮設構造体が求められており、当該仮設構造体を用いて施工性の向上を図ることが求められていた。
特に、建物本体に対し建築用パネル(例えば外壁パネル)を取り付ける前、及び取り付ける際の転落防止対策として上記仮設構造体を有効に活用した施工技術が求められていた。
In this situation, there was a demand for a temporary structure that was more stable than existing temporary handrails and could be easily attached and removed, and there was a need to use such a temporary structure to improve workability.
In particular, there has been a demand for construction techniques that effectively utilize the above-mentioned temporary structures as a fall prevention measure before and during the attachment of architectural panels (e.g., exterior wall panels) to the main body of a building.
詳しく述べると、特許文献1に記載の仮設手摺りでは、上下方向に長尺な支柱部材と、支柱部材の下端部に設けられ、建物本体の梁の上面に当接するベース部材と、ベース部材から下方に向かって突出し、梁の上部及び下部に設けられた貫通穴に挿通される一対の突出部材と、を備えている。
上記構成により、建物本体の梁を利用して簡易的に仮設手摺りを仮設することができる。
一方で、梁の上部及び下部の両方に対して仮設手摺り(一対の突出部材)を挿通させて仮設する必要があるため、建物本体の内側にいる作業者にとって仮設作業を効率良くできない虞があった。例えば、作業者が手探りで一対の突出部材を同時に挿通させる必要があった。
In more detail, the temporary handrail described in Patent Document 1 comprises a long support member that is elongated in the vertical direction, a base member that is attached to the lower end of the support member and abuts the upper surface of the beam of the building body, and a pair of protruding members that protrude downward from the base member and are inserted into through holes provided at the upper and lower parts of the beam.
With the above-mentioned configuration, temporary handrails can be easily installed by utilizing the beams of the building body.
On the other hand, because it is necessary to insert the temporary handrail (a pair of protruding members) through both the upper and lower parts of the beam, there is a risk that workers inside the building body cannot efficiently install the temporary handrail. For example, the worker needs to insert the pair of protruding members simultaneously by feel.
また、特許文献2に記載の仮設手摺りでは、支柱部材と、支柱部材の下端部に設けられ、梁の上面に当接するベース部材と、ベース部材から下方に突出し、梁の上部及び下部に設けられた貫通穴に挿通される1本の突出部材と、を備えている。また、梁の上部にベース部材を固定するためのクランプ部材を備えている。
上記構成の場合には、特許文献1のように作業者が手探りで一対の突出部材を挿通させることはないものの、別途クランプ部材を取り付け及び取り外しする作業が発生してしまう。また、梁の上部及び下部の両方に一対の突出部材を挿通させてはおらず、仮設手摺りの安定感に劣る虞があった。
The temporary handrail described in Patent Document 2 includes a support member, a base member attached to the lower end of the support member and in contact with the upper surface of the beam, and one protruding member protruding downward from the base member and inserted into through holes provided in the upper and lower parts of the beam. Also, a clamp member for fixing the base member to the upper part of the beam is included.
In the case of the above configuration, although the worker does not have to insert the pair of protruding members by feel as in Patent Document 1, the worker still has to attach and remove the clamp member separately. Also, since the pair of protruding members is not inserted through both the upper and lower parts of the beam, there is a risk that the temporary handrail will be less stable.
本発明は、上記の課題に鑑みてなされたものであり、本発明の目的は、施工性向上を図った仮設構造体、仮設構造体の組み付け構造及び建物施工方法を提供することにある。
また、本発明の目的は、狭小スペースにおいて安定性に優れ、容易に取り付け及び取り外しすることが可能な仮設構造体、仮設構造体の組み付け構造及び建物施工方法を提供することにある。
The present invention has been made in consideration of the above problems, and an object of the present invention is to provide a temporary structure, an assembly structure for a temporary structure, and a building construction method that improve workability.
Another object of the present invention is to provide a temporary structure, an assembly structure for a temporary structure, and a building construction method that are highly stable in small spaces and can be easily attached and removed.
前記課題は、本発明の仮設構造体によれば、建物の施工中に用いられ、建物本体に取り付けられる転落防止用の仮設構造体であって、上下方向に長尺に延びている支柱部材と、前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、前記第1突出部材、前記第2突出部材それぞれの突出先端部は、テーパー形状を有し、それぞれ先端に向かうほど細くなるように形成されており、前記第1突出部材においてテーパー形状の開始位置となる部位が、前記第2突出部材の先端よりも前記ベース部材から遠ざかる位置に配置されていること、により解決される。
上記構成により、施工性向上を図った仮設構造体を実現することができる。
詳しく述べると、仮設構造体が、支柱部材と、ベース部材と、ベース部材から下方に突出し、梁の上面に設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、第1突出部材が第2突出部材よりも長尺に突出しているため、梁の貫通穴に対して仮設構造体(第1、第2突出部材)を挿通する作業が容易になる。すなわち、現場の作業者は、梁の貫通穴に対してより長尺な第1突出部材を先に挿通させた後に、第2突出部材を挿通させることができるため、従来のように2本の突出部材を同時に挿通させる場合と比較して仮設構造体の取り付け作業が容易になる。
特に、狭小スペースにおいては、作業者が手探りで仮設手摺りを仮設することになるため、格段に仮設構造体の取り付け作業が効率化する。
また上記のように、第1、第2突出部材それぞれの突出先端部がテーパー形状を有しているため、梁の貫通穴に対して第1、第2突出部材をより容易に挿通できる。
また上記のように、第1突出部材においてテーパー形状の開始位置となる部位が、第2突出部材の先端よりもベース部材から遠ざかる位置に配置されている。そのため、作業者は、梁の貫通穴に第1突出部材を挿通させた後、当該第1突出部材のうちテーパー部分ではない太い部分(最大幅の部分)をガイド部として利用しながら第2突出部材を挿通できる。すなわち、第1突出部材の太い部分を貫通穴の縁部分に当接させて安定した状態で、第2突出部材を別の貫通穴に挿通できる。
The above problem is solved by the temporary structure of the present invention, which is a temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building, comprising: a support member extending a long length in the vertical direction; a base member that is provided at the lower end of the support member and abuts the upper surface of the construction member of the building main body; and a first protruding member and a second protruding member that are provided at intervals in the length or width direction of the base member, each protruding downward from the base member and each being inserted into a through hole provided at intervals in the upper surface of the construction member, wherein the first protruding member protrudes longer than the second protruding member, and the protruding tip portions of the first protruding member and the second protruding member have a tapered shape and are formed so as to become thinner toward the tip, and a portion of the first protruding member that is the starting position of the tapered shape is located at a position farther from the base member than the tip of the second protruding member .
With the above configuration, a temporary structure with improved workability can be realized.
In more detail, the temporary structure includes a support member, a base member, and a first protruding member and a second protruding member that protrude downward from the base member and are inserted into through holes provided on the upper surface of the beam, and since the first protruding member protrudes longer than the second protruding member, the work of inserting the temporary structure (first and second protruding members) into the through holes of the beam is facilitated. In other words, the worker on-site can insert the longer first protruding member into the through hole of the beam first, and then insert the second protruding member, which makes the work of attaching the temporary structure easier than when two protruding members are inserted at the same time as in the conventional method.
In particular, in small spaces, where workers must set up temporary handrails by feel, this dramatically improves the efficiency of installation work for temporary structures.
Furthermore, as described above, since the protruding tip portions of the first and second protruding members each have a tapered shape, the first and second protruding members can be more easily inserted into the through holes of the beam.
As described above, the portion of the first protruding member that is the starting position of the tapered shape is disposed at a position farther from the base member than the tip of the second protruding member. Therefore, after inserting the first protruding member into the through hole of the beam, the worker can insert the second protruding member while using the thick portion (the portion with the widest width) of the first protruding member that is not the tapered portion as a guide. In other words, the second protruding member can be inserted into another through hole in a stable state with the thick portion of the first protruding member abutting against the edge portion of the through hole.
また前記課題は、本発明の仮設構造体によれば、建物の施工中に用いられ、建物本体に取り付けられる転落防止用の仮設構造体であって、上下方向に長尺に延びている支柱部材と、前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、前記ベース部材は、前記建物本体の梁の上面に当接し、前記第1突出部材及び前記第2突出部材は、前記梁の上部に間隔を空けて形成された前記貫通穴にそれぞれ挿通され、かつ、前記梁の下部に間隔を空けて形成され、前記貫通穴に対応する位置に配置された第2貫通穴にそれぞれ挿通されること、により解決される。Furthermore, the above problem is solved by the temporary structure of the present invention, which is a temporary structure for preventing falls that is used during construction of a building and is attached to the building main body, comprising a support member extending a long length in the vertical direction, a base member that is provided at the lower end of the support member and abuts against the upper surface of the construction member of the building main body, and a first protruding member and a second protruding member that are provided at intervals in the length or width direction of the base member, protrude downward from the base member, and are each inserted into through holes provided at intervals on the upper surface of the construction member, wherein the first protruding member protrudes longer than the second protruding member, the base member abuts against the upper surface of the beams of the building main body, and the first protruding member and the second protruding member are each inserted into the through holes formed at an interval on the upper part of the beam, and are also each inserted into second through holes formed at an interval on the lower part of the beam and positioned at positions corresponding to the through holes.
上記のように、第1、第2突出部材は、梁の上部に形成された貫通穴にそれぞれ挿通され、かつ、梁の下部に形成され、貫通穴に対応する位置に配置された第2貫通穴にそれぞれ挿通されるため、従来(特許文献1、2の発明)と比較して、安定性に優れながら容易に取り付け及び取り外しすることが可能な仮設構造体となる。As described above, the first and second protruding members are each inserted into a through hole formed in the upper part of the beam, and are also each inserted into a second through hole formed in the lower part of the beam and positioned at a position corresponding to the through holes, resulting in a temporary structure that is more stable and easier to attach and remove than the conventional structure (the inventions of Patent Documents 1 and 2).
また前記課題は、本発明の仮設構造体によれば、建物の施工中に用いられ、建物本体に取り付けられる転落防止用の仮設構造体であって、上下方向に長尺に延びている支柱部材と、前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、前記第1突出部材、前記第2突出部材は、前記ベース部材と一体である(前記第2突出部材が前記ベース部材から取り外し可能であるものを除く。)こと、により解決される。Furthermore, the above problem is solved by the temporary structure of the present invention, which is a temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building, comprising a support member extending a long length in the vertical direction, a base member that is attached to the lower end of the support member and abuts the upper surface of the construction member of the main body of the building, and a first protruding member and a second protruding member that are spaced apart in the length or width direction of the base member, each protruding downward from the base member and each being inserted into a through hole that is spaced apart on the upper surface of the construction member, wherein the first protruding member protrudes longer than the second protruding member, and the first protruding member and the second protruding member are integral with the base member (except for a case in which the second protruding member is detachable from the base member).
また前記課題は、上記仮設構造体の組み付け構造であって、前記仮設構造体は、上下方向に長尺に延びている支柱部材と、前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、前記仮設構造体は、梁の上部に取り付けられる支柱体と、前記梁の上部において建築用パネルを取り付ける際に用いられるパネル取り付け金具を介して取り付けられる第2支柱体と、前記支柱体及び前記第2支柱体それぞれの上方部を連結する連結体と、を備えており、前記支柱体は、前記支柱部材と、前記ベース部材としての梁ベース部材と、前記第1突出部材及び前記第2突出部材と、を有しており、前記第2支柱体は、前記支柱部材と、前記支柱部材の下端部に設けられ、前記パネル取り付け金具の上面に取り付けられる金具ベース部材と、を有していること、によっても解決される。
上記構成により、仮設構造体の一方側の支柱体は、梁の上面に取り付けられ、他方側の第2支柱体は、建築用パネルを取り付けるためのパネル取り付け金具を介して取り付けられることになる。
そのため、建築用パネルを取り付けるための比較的剛性の高いパネル取り付け金具を利用することで、仮設構造体をより安定させて仮設することができる。
また、梁に予め設けられた既存部品(パネル取り付け金具)を利用しているため、他の構成部品を別途取り付ける必要がなく、施工性を向上させることができる。
また、建物本体に建築用パネルを取り付ける際の位置決め部材として仮設構造体(第2支柱体)を利用することもできる。
The problem is also solved by an assembly structure for the temporary structure, the temporary structure comprising a support member extending long in the vertical direction, a base member provided at the lower end of the support member and abutting against an upper surface of a construction member of the building body, and a first protruding member and a second protruding member provided at an interval in the length direction or width direction of the base member, protruding downward from the base member, and inserted into through holes provided at an interval in the upper surface of the construction member, the first protruding member protruding longer than the second protruding member, and the temporary structure is a beam. The problem is also solved by the fact that the beam comprises a first support body attached to the top of the beam, a second support body attached via a panel mounting bracket used to attach an architectural panel to the top of the beam, and a connector connecting the upper parts of the support body and the second support body, wherein the support body has the support member, a beam base member as the base member, the first protruding member and the second protruding member, and the second support body has the support member and a bracket base member provided at the lower end of the support member and attached to the upper surface of the panel mounting bracket.
With the above-described configuration, the support column on one side of the temporary structure is attached to the upper surface of the beam, and the second support column on the other side is attached via a panel mounting bracket for mounting a building panel.
Therefore, by using panel mounting fixtures with relatively high rigidity for attaching architectural panels, the temporary structure can be made more stable.
In addition, since it utilizes existing parts (panel mounting brackets) that are already installed on the beams, there is no need to attach other components separately, improving workability.
The temporary structure (second support body) can also be used as a positioning member when attaching a construction panel to the main body of a building.
このとき、前記支柱体及び前記第2支柱体は、前記建物本体の間口方向において所定の間隔を空けて配置され、前記支柱体は、前記間口方向に沿って長尺に延びている前記梁のうち、前記建物本体の柱に近接した梁端部に取り付けられ、前記第1突出部材は、前記第2突出部材よりも前記柱に近い位置において前記貫通穴に挿通されると良い。
一般に、建物本体の間口方向に沿って延びている梁には、当該間口方向に間隔を空けてパネル取り付け金具が複数設けられているところ、当該梁のうち、建物本体の柱に近接した梁端部においては、パネル取り付け金具が設けられていない。理由として、建物本体に建築用パネル(外壁パネル)を取り付けるときには、建物本体の柱を含めて外側から覆う必要があって、梁端部ではなく当該柱の外側面にパネル取り付け金具を設けたほうが建築用パネルを安定して取り付けられるためである。
そこで、上記の構成であれば、間口方向に沿って延びている梁の延出方向において間隔を空けることなく転落防止用の仮設構造体を連続して仮設することができ、作業者の安全性をより高めることができる。例えば、仮設構造体を設置するにあたって、パネル取り付け金具を利用可能な箇所については第2支柱体を取り付けることで安定性を確保し、パネル取り付け金具が設けられていない梁端部の箇所については支柱体を取り付けることができる。
また、梁端部において支柱体を取り付けるにあたっては、より長尺な第1突出部材が、第2突出部材よりも柱に近い位置において貫通穴に先に挿通されることで、より効率良く仮設構造体(支柱体)を取り付けることができる。
In this case, the support body and the second support body are arranged at a predetermined interval in the frontage direction of the building main body, the support body is attached to the beam end portion of the beam extending longitudinally along the frontage direction that is closest to the column of the building main body, and the first protruding member is inserted into the through hole at a position closer to the column than the second protruding member.
Generally, a beam extending along the frontage direction of the building body is provided with a plurality of panel mounting brackets spaced apart in the frontage direction, but no panel mounting brackets are provided at the beam end portions of the beams that are close to the pillars of the building body. The reason for this is that when attaching architectural panels (exterior wall panels) to the building body, it is necessary to cover the building body including the pillars from the outside, and the architectural panels can be attached more stably if panel mounting brackets are provided on the outer surface of the pillars rather than on the beam ends.
Therefore, with the above-mentioned configuration, temporary structures for preventing falls can be temporarily installed in succession without leaving any gaps in the extension direction of the beam extending along the frontage direction, thereby further improving the safety of workers. For example, when installing temporary structures, stability can be ensured by attaching second support bodies to locations where panel mounting metal fittings can be used, and support bodies can be attached to locations of beam ends where panel mounting metal fittings are not provided.
In addition, when attaching the pillar body to the end of the beam, the longer first protruding member is inserted into the through hole first at a position closer to the column than the second protruding member, allowing the temporary structure (pillar body) to be attached more efficiently.
このとき、前記第2支柱体の前記金具ベース部材は、前記パネル取り付け金具において前記建築用パネルが取り付けられるパネル取り付け部よりも前記建物本体の内側に設けられた取り付け部に対して取り付けられ、前記仮設構造体は、前記建物本体に取り付けられたときに、前記建築用パネルの取り付け位置よりも前記建物本体の内側に位置すると良い。
上記構成により、建物本体に取り付けられた仮設構造体と、建築用パネル(例えば外壁パネル)との干渉を避けることができる。そのため、建築用パネルを取り付ける前、及び取り付ける際の転落防止対策として仮設構造体を有効利用することができ、より施工性の向上を図ることができる。
また上記構成により、仮設構造体が建物本体から外側に張り出すことがなく、仮設構造体を容易に取り付け及び取り外しすることができる。
In this case, the metal fitting base member of the second support body is attached to a mounting portion of the panel mounting fitting that is provided on the inside of the building main body further inward than the panel mounting portion to which the architectural panel is attached, and the temporary structure, when attached to the building main body, is preferably positioned on the inside of the building main body further inward than the mounting position of the architectural panel.
With the above-mentioned configuration, it is possible to avoid interference between the temporary structure attached to the building body and the architectural panel (e.g., the exterior wall panel). Therefore, the temporary structure can be effectively used as a fall prevention measure before and during the installation of the architectural panel, and workability can be improved.
Furthermore, with the above-mentioned configuration, the temporary structure does not protrude outward from the main body of the building, and the temporary structure can be easily attached and removed.
また前記課題は、上記仮設構造体を利用した建物施工方法であって、前記仮設構造体は、上下方向に長尺に延びている支柱部材と、前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、前記建物施工方法は、前記施工部材に対し前記仮設構造体を取り付ける工程と、前記施工部材において前記仮設構造体よりも前記建物本体の外側に位置する部分に対し前記建築用パネルを取り付ける工程と、前記施工部材から前記仮設構造体を取り外す工程と、を含み、前記仮設構造体を取り付ける工程では、前記施工部材に設けられたそれぞれの前記貫通穴に対し、前記第1突出部材を挿通した後に前記第2突出部材を挿通することとする建物施工方法によっても解決される。 The above problem can also be solved by a building construction method that utilizes the above-mentioned temporary structure, wherein the temporary structure comprises a support member extending in a vertical direction, a base member that is provided at the lower end of the support member and abuts against the upper surface of the construction member of the building main body, and a first protruding member and a second protruding member that are provided at intervals in the length or width direction of the base member, each protruding downward from the base member, and each being inserted into a through hole provided at an interval on the upper surface of the construction member, wherein the first protruding member protrudes longer than the second protruding member, and the building construction method includes a step of attaching the temporary structure to the construction member, a step of attaching the architectural panel to a portion of the construction member that is located outside the building main body relative to the temporary structure, and a step of removing the temporary structure from the construction member, and wherein in the step of attaching the temporary structure, the first protruding member is inserted into each of the through holes provided in the construction member, and then the second protruding member is inserted into each of the through holes provided in the construction member.
本発明の仮設構造体、仮設構造体の組み付け構造及び建物施工方法によれば、建物の施工時や施工後のメンテナンス時において施工性の向上を図ることができる。
また、狭小スペースにおいて安定性に優れ、容易に取り付け及び取り外しすることが可能な仮設構造体を実現することができる。
According to the temporary structure, the assembly structure for the temporary structure, and the building construction method of the present invention, it is possible to improve workability during construction of a building and during maintenance after construction.
It is also possible to realize a temporary structure that is highly stable in a small space and can be easily attached and removed.
以下、本発明に係る実施形態について図1-図12を参照して説明する。
本実施形態は、建物の施工中に用いられ、建物本体に取り付けられる転落防止用の仮設構造体であって、上下方向に長尺に延びている支柱部材と、支柱部材の下端部に設けられ、建物本体の施工部材(梁)の上面に当接するベース部材と、ベース部材の長さ方向において間隔を空けて設けられ、ベース部材から下方に向かってそれぞれ突出し、施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、第1突出部材が、第2突出部材よりも長尺となるように突出していることを主な特徴とする発明に関するものである。
なお、本実施形態では「仮設手摺り」が仮設構造体に相当する。
Hereinafter, an embodiment of the present invention will be described with reference to FIGS.
This embodiment relates to an invention characterized in that it is a temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building, comprising a support member extending a long length in the vertical direction, a base member that is attached to the lower end of the support member and abuts the upper surface of a construction member (beam) of the main body of the building, and a first protruding member and a second protruding member that are spaced apart in the longitudinal direction of the base member, each protruding downward from the base member and each being inserted into through holes that are spaced apart on the upper surface of the construction member, and the first protruding member protrudes longer than the second protruding member.
In this embodiment, the "temporary handrail" corresponds to the temporary structure.
本実施形態の仮設手摺りの組み付け構造では、図1に示すように、建物の施工中において、建物本体Bの梁B1又は梁B1に設けられたパネル取り付け金具1に対して仮設手摺り20が組み付けられる。
詳しく述べると、仮設手摺り20は、建物本体Bの間口方向に沿って長尺に延びている梁B1のうち、建物本体Bの柱B4に近接した位置(梁端部)に取り付けられている。
そして、仮設手摺り20が組み付けられた状態で、建物本体B(パネル取り付け金具1、10)に対して建築用パネル30を取り付けることができる。
以下、上記組み付け構造について詳しく説明する。
In the temporary handrail assembly structure of this embodiment, as shown in FIG. 1, during construction of a building, a temporary handrail 20 is assembled to a beam B1 of a building body B or a panel mounting bracket 1 provided on the beam B1.
More specifically, the temporary handrail 20 is attached to a beam B1 extending longitudinally along the frontage direction of the building main body B at a position (beam end) close to a pillar B4 of the building main body B.
Then, with the temporary handrail 20 assembled, the architectural panel 30 can be attached to the building main body B (panel mounting fittings 1, 10).
The above assembly structure will now be described in detail.
パネル取り付け金具1、第2パネル取り付け金具10は、図1に示すように、建物本体Bの梁B1にそれぞれ固定され、建物本体Bに建築用パネル30を取り付ける際に用いられる接合金具である。
パネル取り付け金具1は、仮設手摺り20を仮設するための接合金具としても機能し、特に狭小スペースにおいて仮設手摺り20を仮設するために利用される。
詳しく述べると、パネル取り付け金具1は、建物本体Bの上階においてH形鋼の梁B1の上面に固定されており、建物本体Bの間口方向に間隔を空けて複数配置されている。
第2パネル取り付け金具10は、パネル取り付け金具1と上下方向で重なる位置に配置され、梁B1の底面に固定されており、当該間口方向に間隔を空けて複数配置されている。
The panel mounting bracket 1 and the second panel mounting bracket 10 are, as shown in FIG. 1, respectively fixed to beams B1 of a building body B, and are connecting brackets used when mounting a construction panel 30 to the building body B.
The panel mounting bracket 1 also functions as a connecting bracket for temporarily setting up a temporary handrail 20, and is used to temporarily set up the temporary handrail 20 in particular in small spaces.
More specifically, the panel mounting brackets 1 are fixed to the upper surface of the H-shaped steel beams B1 on the upper floors of the building body B, and are arranged at intervals in the frontage direction of the building body B.
The second panel mounting bracket 10 is arranged at a position overlapping with the panel mounting bracket 1 in the vertical direction, fixed to the bottom surface of the beam B1, and arranged at intervals in the width direction.
パネル取り付け金具1は、図2A、Bに示すように、断面略L字形状の部材であって、梁B1の上フランジ部B2に当接し、梁B1よりも建物本体Bの外側に突出している底壁部1aと、底壁部1aの外側端部から連続して上方に延びている外側壁部1bと、底壁部1aの幅方向の両端部から連続してそれぞれ上方に延びており、底壁部1a及び外側壁部1bを連結している一対の補強壁部1cと、から主に構成されている。
パネル取り付け金具1の底壁部1aには、梁B1に固定するための取り付け穴2が形成されている。また、取り付け穴2を利用することで、仮設手摺り20を着脱可能に取り付けることができる。
また、外側壁部1bには、建築用パネル30を着脱可能に取り付けるためのパネル取り付け穴3が形成されている。
As shown in Figures 2A and 2B, the panel mounting bracket 1 is a member having a generally L-shaped cross section, and is mainly composed of a bottom wall portion 1a that abuts against the upper flange portion B2 of the beam B1 and protrudes further outward from the building body B than the beam B1, an outer wall portion 1b that extends upward continuously from the outer end portion of the bottom wall portion 1a, and a pair of reinforcing wall portions 1c that extend upward continuously from both widthwise ends of the bottom wall portion 1a and connect the bottom wall portion 1a and the outer wall portion 1b.
A mounting hole 2 for fixing to a beam B1 is formed in the bottom wall portion 1a of the panel mounting bracket 1. By using the mounting hole 2, a temporary handrail 20 can be detachably attached.
Further, the outer wall portion 1b is formed with a panel mounting hole 3 for detachably mounting a building panel 30 thereto.
取り付け穴2は、底壁部1aに対し上下方向に貫通した貫通穴であって、パネル取り付け金具1の幅方向に間隔を空けて複数形成されている。
取り付け穴2と、梁B1の上面に形成された貫通穴B2aとが上下方向に連通した状態で固定ボルト4がナット締めされることで、パネル取り付け金具1が梁B1に固定されている。
また、取り付け穴2と、図6に示す仮設手摺り20(金具ベース部材25)に形成された取り付け穴26とが上下方向に連通した状態で固定ボルト4がナット締めされることで、仮設手摺り20がパネル取り付け金具1に取り付けられている。
詳しく述べると、図6に示すように、パネル取り付け金具1の取り付け穴2と、固定ナット5と、仮設手摺り20の取り付け穴26と、固定ナット6とが上下方向に連通した状態で固定ボルト4によって締結されている。
The mounting holes 2 are through holes that penetrate the bottom wall portion 1a in the up-down direction, and are formed in a plurality at intervals in the width direction of the panel mounting bracket 1.
The panel mounting bracket 1 is fixed to the beam B1 by tightening the nut of the fixing bolt 4 with the mounting hole 2 and the through hole B2a formed in the upper surface of the beam B1 communicating in the vertical direction.
In addition, the temporary handrail 20 is attached to the panel mounting bracket 1 by tightening the nut on the fixing bolt 4 while the mounting hole 2 and the mounting hole 26 formed in the temporary handrail 20 (metal fitting base member 25) shown in Figure 6 are connected in the vertical direction.
In detail, as shown in Figure 6, the mounting hole 2 of the panel mounting bracket 1, the fixing nut 5, the mounting hole 26 of the temporary handrail 20, and the fixing nut 6 are fastened by the fixing bolt 4 in a state of communication in the vertical direction.
パネル取り付け穴3は、図2A、Bに示すように、外側壁部1bの上端部に形成された切り欠き穴であって、パネル取り付け金具1の幅方向に間隔を空けて一対形成されている。
パネル取り付け穴3は、図10Cに示す建築用パネル30の下端部の取り付け軸33を上方から嵌合させるための穴である。
As shown in FIGS. 2A and 2B, the panel mounting holes 3 are cut-out holes formed in the upper end portion of the outer wall portion 1b, and are formed as a pair with a space therebetween in the width direction of the panel mounting bracket 1.
The panel mounting hole 3 is a hole into which a mounting shaft 33 at the lower end of the building panel 30 shown in FIG. 10C is fitted from above.
パネル取り付け穴3は、取り付け軸33を導き入れるためのガイド穴となる第1穴部3aと、第1穴部3aから連続して形成され、パネル取り付け穴3の中で取り付け軸33を嵌合させるための嵌合穴となる第2穴部3b、とから構成されている。
第1穴部3aは、略逆台形状のガイド穴であって、外側壁部1bの上端から下方に向かうに従って幅狭となるように傾斜しながら切り欠き形成されている。
第2穴部3bは、略半円形状の嵌合穴であって、取り付け軸33を着脱可能に嵌合させる縁を有しており、第1穴部3aから連続して所定の幅を有しながら下方に向かって切り欠き形成されている。
上記構成により、パネル取り付け金具1に対し建築用パネル30を上下方向から容易に取り付け及び取り外しすることができる。
The panel mounting hole 3 is composed of a first hole portion 3a which serves as a guide hole for guiding the mounting shaft 33, and a second hole portion 3b which is formed continuously from the first hole portion 3a and serves as a fitting hole for fitting the mounting shaft 33 inside the panel mounting hole 3.
The first hole portion 3a is a guide hole having a generally inverted trapezoidal shape, and is cut out while being inclined so as to become narrower from the upper end of the outer wall portion 1b downward.
The second hole portion 3b is a substantially semicircular fitting hole having an edge for removably fitting the mounting shaft 33, and is cut out downwardly, continuing from the first hole portion 3a, with a predetermined width.
With the above-described configuration, the architectural panel 30 can be easily attached to and detached from the panel mounting bracket 1 from above and below.
第2パネル取り付け金具10は、図3に示すように、段差形状を有する部材であって、梁B1の下フランジ部B3に当接し、梁B1よりも建物本体Bの外側に突出している上壁部10aと、上壁部10aの外側端部から下方に延びている第1外側壁部10bと、第1外側壁部10bの下端部から建物本体Bの外側に突出している底壁部10cと、底壁部10cの外側端部から下方に延びている第2外側壁部10dと、上壁部10aの幅方向の両端部からそれぞれ下方に延びており、上壁部10aから第2外側壁部10dまでを連結している一対の補強壁部10eと、を備えている。
また、第2パネル取り付け金具10は、底壁部10cの上面から上方に突出している第3外側壁部10fと、第3外側壁部10fの幅方向の両端部からそれぞれ建物本体B側に向かって延びており、第3外側壁部10f、第1外側壁部10b及び底壁部10cを連結している一対の第2補強壁部10gと、を備えている。
第2パネル取り付け金具10の上壁部10aには、梁B1に固定するための取り付け穴11が形成されている。
また、第2外側壁部10dには、建築用パネル30を固定するためのパネル固定穴12が形成されており、第3外側壁部10fには、建築用パネル30を着脱可能に取り付けるためのパネル取り付け穴13が形成されている。
As shown in Figure 3, the second panel mounting bracket 10 is a stepped member and comprises an upper wall portion 10a that abuts against the lower flange portion B3 of the beam B1 and protrudes further outward from the building main body B than the beam B1, a first outer wall portion 10b extending downward from the outer end of the upper wall portion 10a, a bottom wall portion 10c that protrudes outward from the lower end of the first outer wall portion 10b to the outside of the building main body B, a second outer wall portion 10d extending downward from the outer end of the bottom wall portion 10c, and a pair of reinforcing wall portions 10e that extend downward from both widthwise ends of the upper wall portion 10a and connect the upper wall portion 10a to the second outer wall portion 10d.
The second panel mounting bracket 10 also includes a third outer wall portion 10f protruding upward from the upper surface of the bottom wall portion 10c, and a pair of second reinforcing wall portions 10g extending from both widthwise ends of the third outer wall portion 10f toward the building main body B, connecting the third outer wall portion 10f, the first outer wall portion 10b, and the bottom wall portion 10c.
An attachment hole 11 is formed in the upper wall portion 10a of the second panel mounting bracket 10 for fixing to the beam B1.
In addition, a panel fixing hole 12 for fixing the architectural panel 30 is formed in the second outer wall portion 10d, and a panel mounting hole 13 for removably mounting the architectural panel 30 is formed in the third outer wall portion 10f.
取り付け穴11は、取り付け穴2と同様の貫通穴であって、第2パネル取り付け金具10の幅方向に間隔を空けて複数形成されている。
取り付け穴11と、梁B1の底面に形成された第2貫通穴B3aとが上下方向に連通した状態で固定ボルト14がナット締めされることで、第2パネル取り付け金具10が梁B1に固定されている。
The mounting holes 11 are through holes similar to the mounting holes 2, and are formed in plurality at intervals in the width direction of the second panel mounting bracket 10.
The second panel mounting bracket 10 is fixed to the beam B1 by tightening the nut on the fixing bolt 14 while the mounting hole 11 and the second through hole B3a formed in the bottom surface of the beam B1 are connected in the vertical direction.
パネル固定穴12は、図3に示すように、第2外側壁部10dに対し建物本体Bの出幅方向に貫通した貫通穴であって、第2パネル取り付け金具10の幅方向に間隔を空けて複数形成されている。
パネル固定穴12に対し、図10Dに示す建築用パネル30の上端部の固定ナット35を連通させた状態でボルト固定することで、建物本体Bに建築用パネル30が固定されている。
As shown in Figure 3, the panel fixing holes 12 are through holes that penetrate the second outer wall portion 10d in the width direction of the building main body B, and are formed in multiple spaces in the width direction of the second panel mounting bracket 10.
The building panel 30 is fixed to the building body B by bolting the fixing nuts 35 at the upper end of the building panel 30 shown in Figure 10D in a communicating state with the panel fixing holes 12.
パネル取り付け穴13は、上述のパネル取り付け穴3と同様の切り欠き穴であって、第2パネル取り付け金具10の幅方向に間隔を空けて一対形成されている。
パネル取り付け穴13は、図10Cに示す建築用パネル30の下端の第2取り付け軸34を上方から嵌合させるための穴である。
パネル取り付け穴13は、ガイド穴となる第1穴部13aと、パネル取り付け穴13の中で第2取り付け軸34を嵌合させるための嵌合穴となる第2穴部13b、とから主に構成されている。
上記構成により、複数のパネル取り付け金具1、10に対し、建築用パネル30を上下方向で複数支持させるように取り付けることができる。
The panel mounting holes 13 are cut-out holes similar to the panel mounting holes 3 described above, and are formed as a pair spaced apart in the width direction of the second panel mounting bracket 10 .
The panel mounting hole 13 is a hole into which the second mounting shaft 34 at the lower end of the building panel 30 shown in FIG. 10C is fitted from above.
The panel mounting hole 13 is mainly composed of a first hole portion 13a which serves as a guide hole and a second hole portion 13b which serves as a fitting hole for fitting the second mounting shaft 34 into the panel mounting hole 13.
With the above-described configuration, a plurality of architectural panels 30 can be attached to a plurality of panel mounting brackets 1, 10 so as to be supported in the vertical direction.
仮設手摺り20は、図4-図8に示すように、建物の施工中に用いられる転落防止用の仮設構造体であって、建物本体Bに建築用パネル30を取り付ける前に取り付けられ、建築用パネル30を取り付けた後に取り外されるものである。
仮設手摺り20は、梁B1の上部に取り付けられる支柱体20Aと、梁B1の上部においてパネル取り付け金具1を介して取り付けられる第2支柱体20Bと、支柱体20A及び第2支柱体20Bそれぞれの上方部、中央部を連結する連結体20Cと、から主に構成されている。
連結体20Cは、板状の長尺体として形成されており、梁B1の長尺方向に沿って延びている。また、連結体20Cは、図1に示すように、梁B1の長尺方向に沿って複数並ぶように配置されている。詳しく述べると、一方の連結体20Cの端部と、他方の連結体20Cの端部とが重なるように配置され、重なり合った端部が支柱体(第2支柱体20B)によって支持されている。
As shown in Figures 4 to 8, the temporary handrail 20 is a temporary structure for preventing falls used during construction of a building, which is attached before the architectural panel 30 is attached to the building main body B and is removed after the architectural panel 30 is attached.
The temporary handrail 20 is mainly composed of a support body 20A attached to the upper part of the beam B1, a second support body 20B attached to the upper part of the beam B1 via a panel mounting bracket 1, and a connecting body 20C connecting the upper and central parts of the support body 20A and the second support body 20B.
The connector 20C is formed as a plate-like long body and extends along the longitudinal direction of the beam B1. As shown in Fig. 1, the connectors 20C are arranged in a line along the longitudinal direction of the beam B1. More specifically, an end of one connector 20C and an end of the other connector 20C are arranged to overlap each other, and the overlapping ends are supported by a support body (second support body 20B).
支柱体20Aは、図5、図6に示すように、上下方向に長尺に延びている支柱部材21と、支柱部材21の下端部に設けられ、梁B1の上面に当接する梁ベース部材22と、梁ベース部材22の長さ方向において間隔を空けて設けられ、梁ベース部材22から下方に向かってそれぞれ突出し、梁B1上に間隔を空けて設けられた貫通穴B2a(B3a)にそれぞれ挿通される第1突出部材23及び第2突出部材24と、から主に構成されている。 As shown in Figures 5 and 6, the support body 20A is mainly composed of a support member 21 that extends vertically, a beam base member 22 that is provided at the lower end of the support member 21 and abuts the upper surface of the beam B1, and a first protruding member 23 and a second protruding member 24 that are provided at intervals in the longitudinal direction of the beam base member 22, protrude downward from the beam base member 22, and are inserted into through holes B2a (B3a) provided at intervals on the beam B1.
支柱部材21は、断面矩形状の長尺な中空体である。支柱部材21の上方部、中央部には、連結体20Cの端部に設けられた係合穴20Caを着脱可能に係合させるための係合軸21aが設けられている。係合軸21aは、支柱部材21の外側面から建物本体Bの内側に向かって突出している。 The support member 21 is a long, hollow body with a rectangular cross section. An engagement shaft 21a is provided in the upper and central parts of the support member 21 for detachably engaging an engagement hole 20Ca provided at the end of the connecting body 20C. The engagement shaft 21a protrudes from the outer surface of the support member 21 toward the inside of the building body B.
梁ベース部材22は、仮設手摺り20の取り付け強度(曲げ強度)を確保するための部材であって、梁B1の上面に当接している。
詳しく述べると、梁ベース部材22は、支柱部材21の下端部から幅方向の両側に突出している一対の第1ベース部22aと、支柱部材21の下端部から建物本体Bの内側に突出している第2ベース部22bと、第2ベース部22bから幅方向の両側に突出し、第1ベース部22a及び第2ベース部22bを連結する一対の補強ベース部22cと、から主に構成されている。
The beam base member 22 is a member for ensuring the attachment strength (bending strength) of the temporary handrail 20, and abuts against the upper surface of the beam B1.
In detail, the beam base member 22 is mainly composed of a pair of first base portions 22a protruding on both sides in the width direction from the lower end of the support member 21, a second base portion 22b protruding from the lower end of the support member 21 toward the inside of the building main body B, and a pair of reinforcing base portions 22c protruding on both sides in the width direction from the second base portions 22b and connecting the first base portions 22a and the second base portions 22b.
一対の第1ベース部22a、第2ベース部22b、一対の補強ベース部22cは、それぞれ板状部材からなり、梁B1の上面に当接している。
一対の第1ベース部22aのうち、梁B1の貫通穴B2a(B3a)に対向する位置には、第1、第2突出部材23、24が溶接されている。
第2ベース部22bは、一対の第1ベース部22aの外側端部の間に配置されており、かつ、第1、第2突出部材23、24の間に配置されている。
一対の補強ベース部22cは、上下方向において支柱部材21側から梁B1側へ向かうに従って傾斜しながら広がっている。
The pair of first base portions 22a, the second base portion 22b, and the pair of reinforcing base portions 22c are each made of a plate-like member, and abut against the upper surface of the beam B1.
First and second protruding members 23, 24 are welded to the pair of first base portions 22a at positions facing the through hole B2a (B3a) of the beam B1.
The second base portion 22b is disposed between the outer ends of the pair of first base portions 22a, and is also disposed between the first and second protruding members 23, 24.
The pair of reinforcing base portions 22c are inclined and widen in the vertical direction from the support member 21 side to the beam B1 side.
第1突出部材23、第2突出部材24は、上下方向に長尺な棒状部材であって、第1突出部材23が、第2突出部材24よりも長尺となるように突出している。
第1突出部材23、第2突出部材24それぞれの先端部23a、24aは、テーパー形状を有し、それぞれ先端に向かうほど細くなるように形成されている。
また、第1突出部材23(先端部23a)においてテーパー形状の開始位置となる部位が、第2突出部材24の先端よりも梁ベース部材22から遠ざかる位置に配置されている。
The first protruding member 23 and the second protruding member 24 are rod-shaped members that are long in the vertical direction, and the first protruding member 23 protrudes longer than the second protruding member 24.
The tip portions 23a, 24a of the first protruding member 23 and the second protruding member 24 respectively have a tapered shape and are formed so as to become thinner toward the tip.
In addition, the portion of the first protruding member 23 (tip portion 23 a ) that is the starting position of the tapered shape is located at a position farther from the beam base member 22 than the tip of the second protruding member 24 .
上記構成において、第1突出部材23、第2突出部材24は、梁B1の上フランジ部B2に間隔を空けて形成された貫通穴B2aにそれぞれ挿通され、かつ、下フランジ部B3に間隔を空けて形成された第2貫通穴B3aにそれぞれ挿通されている。
そのため、安定性に優れながら、容易に取り付け及び取り外すことが可能な仮設手摺り20を実現できる。
In the above configuration, the first protruding member 23 and the second protruding member 24 are each inserted into a through hole B2a formed at a distance in the upper flange portion B2 of the beam B1, and are also each inserted into a second through hole B3a formed at a distance in the lower flange portion B3.
Therefore, it is possible to realize a temporary handrail 20 that is highly stable and can be easily attached and removed.
第2支柱体20Bは、図7、図8に示すように、上下方向に長尺に延びている支柱部材21と、支柱部材21の下端部に設けられ、パネル取り付け金具1の上面に当接して取り付けられる金具ベース部材25と、から主に構成されている。 As shown in Figures 7 and 8, the second support body 20B is mainly composed of a support member 21 that extends vertically and a bracket base member 25 that is provided at the lower end of the support member 21 and is attached by abutting against the upper surface of the panel mounting bracket 1.
金具ベース部材25は、パネル取り付け金具1に対し上下方向で取り付けられ、また、パネル取り付け金具1に対し建物本体Bの出幅方向で当接するように保持されている。
詳しく述べると、金具ベース部材25は、支柱部材21の下端部から幅方向の両側に突出している一対の第1ベース部25aと、支柱部材21の下端部から建物本体Bの外側に突出している第2ベース部25bと、第2ベース部25bから幅方向の両側に突出し、第1ベース部25a及び第2ベース部25bを連結する一対の補強ベース部25cと、から主に構成されている。
The metal fitting base member 25 is attached to the panel mounting metal fitting 1 in the vertical direction, and is held so as to abut against the panel mounting metal fitting 1 in the width direction of the building body B.
In detail, the metal fittings base member 25 is mainly composed of a pair of first base portions 25a protruding on both sides in the width direction from the lower end of the support member 21, a second base portion 25b protruding from the lower end of the support member 21 to the outside of the building main body B, and a pair of reinforcing base portions 25c protruding on both sides in the width direction from the second base portions 25b and connecting the first base portions 25a and the second base portions 25b.
一対の第1ベース部25aは、パネル取り付け金具1の底壁部1aに対し固定ナット5を介して上下方向で当接している。
一対の第1ベース部25aのうち、パネル取り付け金具1の取り付け穴2に対向する位置には、パネル取り付け金具1に取り付けるための取り付け穴26がそれぞれ形成されている。
The pair of first base portions 25 a abuts against the bottom wall portion 1 a of the panel mounting bracket 1 in the vertical direction via fixing nuts 5 .
In the pair of first base portions 25 a , mounting holes 26 for mounting to the panel mounting bracket 1 are formed at positions facing the mounting holes 2 of the panel mounting bracket 1 .
第2ベース部25bは、パネル取り付け金具1の外側壁部1bに向かって突出しており、当該外側壁部1bに建物本体Bの出幅方向で当接している。また、底壁部1aに上下方向で当接している。
詳しく述べると、第2ベース部25bは、外側壁部1bのうち、一対のパネル取り付け穴3の間の中央部分に当接している。
一対の補強ベース部25cは、略三角形状の板状部材からなり、上下方向において支柱部材21側からパネル取り付け金具1側へ向かうに従って傾斜しながら広がっている。
The second base portion 25b protrudes toward the outer wall portion 1b of the panel mounting bracket 1 and abuts against the outer wall portion 1b in the width direction of the building main body B. The second base portion 25b also abuts against the bottom wall portion 1a in the up-down direction.
More specifically, the second base portion 25b abuts against a central portion between the pair of panel mounting holes 3 of the outer wall portion 1b.
The pair of reinforcing base portions 25c are made of plate-like members having a substantially triangular shape, and are gradually wider and inclined in the vertical direction from the support member 21 side toward the panel mounting bracket 1 side.
建築用パネル30は、図1、図10C、Dに示すように、建物を構成する矩形板状の部材であって、具体的には、外壁パネルであって、矩形板状のパネルフレーム31と、パネルフレーム31の表面に固定されている仕上げ面材32と、から主に構成されている。
なお、建築用パネル30は、「外壁パネル」に特に限定されることなく、「腰壁パネル」や「屋根パネル」、「庇パネル」であっても良く、各種の建築用パネルを採用することができる。
As shown in Figures 1, 10C and 10D, the architectural panel 30 is a rectangular plate-shaped member that constitutes a building, and more specifically, is an exterior wall panel, and is mainly composed of a rectangular plate-shaped panel frame 31 and a finishing surface material 32 fixed to the surface of the panel frame 31.
In addition, the architectural panel 30 is not particularly limited to an "exterior wall panel", but may be a "wain wall panel", a "roof panel", or a "eaves panel", and various types of architectural panels can be adopted.
パネルフレーム31の裏面における下端部には、パネル取り付け金具1、10(柱B4に設けられた金具B4a、B4b)にそれぞれ着脱可能に取り付けるための取り付け軸33、第2取り付け軸34が突出するように設けられている。
また、パネルフレーム31の裏面における上端部には、第2パネル取り付け金具10(第2金具B4b)に固定するための固定ナット35が突出するように設けられている。
これら取り付け軸33、34及び固定ナット35は、それぞれ建築用パネル30の幅方向の両端部に一対となって配置されている。
A mounting shaft 33 and a second mounting shaft 34 are protrudingly provided at the lower end on the back surface of the panel frame 31 for detachably mounting the panel frame 31 to the panel mounting fittings 1, 10 (fittings B4a, B4b provided on the pillar B4), respectively.
Furthermore, a fixing nut 35 for fixing to the second panel mounting bracket 10 (second bracket B4b) is provided so as to protrude from the upper end portion on the rear surface of the panel frame 31.
These mounting shafts 33, 34 and fixing nuts 35 are arranged in pairs at both ends in the width direction of the building panel 30.
取り付け軸33は、図10C、Dに示すように、フック式の軸部材であって、パネル取り付け穴3の縁に嵌合される。
なお、第2取り付け軸34も同様にしてパネル取り付け穴13の縁に嵌合される。
As shown in FIGS. 10C and 10D, the mounting shaft 33 is a hook-type shaft member that fits into the edge of the panel mounting hole 3.
The second mounting shaft 34 is similarly fitted into the edge of the panel mounting hole 13 .
パネル取り付け金具1のパネル取り付け穴3に取り付け軸33を上方から取り付けるにあたって、図10Cに示すように、第1延出部33aがパネル取り付け穴3に挿通可能な大きさで形成されている一方で、第2延出部33bはパネル取り付け穴3には挿通できない大きさで形成されている。
すなわち、パネルフレーム31及び第2延出部33bがパネル取り付け穴3を挟み込むことで、取り付け軸33がパネル取り付け穴3の縁に嵌合される。
なお、第2取り付け軸34も同様にして、パネル取り付け穴13の縁に嵌合される。
固定ナット35は、図10Dに示すように、第2パネル取り付け金具10のパネル固定穴12に連通した状態でボルト締めされる。
When attaching the mounting shaft 33 from above into the panel mounting hole 3 of the panel mounting bracket 1, as shown in Figure 10C, the first extension portion 33a is formed to a size that allows it to be inserted into the panel mounting hole 3, while the second extension portion 33b is formed to a size that does not allow it to be inserted into the panel mounting hole 3.
That is, the panel frame 31 and the second extending portion 33 b sandwich the panel mounting hole 3 , so that the mounting shaft 33 fits into the edge of the panel mounting hole 3 .
Similarly, the second mounting shaft 34 is fitted into the edge of the panel mounting hole 13 .
As shown in FIG. 10D, the fixing nut 35 is bolted in a state in which it communicates with the panel fixing hole 12 of the second panel mounting bracket 10.
上記構成において、各パネル取り付け金具1、10に建築用パネル30を固定する際には、図10C、Dに示すように、まず、建築用パネル30の下端部の取り付け軸33、34をパネル取り付け穴3、13に嵌合させる。その後、建築用パネル30を建物本体B側に引き寄せて、建築用パネル30の上端部の固定ナット35を、別途設けられた第2パネル取り付け金具10のパネル固定穴12に連通させた状態で固定ボルト36によって固定する。
上記構成により、パネル取り付け金具1、10に対し建築用パネル30を上下方向から容易に取り付けることができる。
In the above configuration, when fixing the architectural panel 30 to each panel mounting bracket 1, 10, first, as shown in Figures 10C and 10D, the mounting shafts 33, 34 at the lower end of the architectural panel 30 are fitted into the panel mounting holes 3, 13. Then, the architectural panel 30 is pulled toward the building main body B, and the architectural panel 30 is fixed by the fixing bolt 36 with the fixing nut 35 at the upper end of the architectural panel 30 communicating with the panel fixing hole 12 of the second panel mounting bracket 10 provided separately.
With the above-described configuration, the architectural panel 30 can be easily attached to the panel mounting brackets 1, 10 from above and below.
上記構成において、図2A、Bに示すように、パネル取り付け金具1のパネル取り付け穴3が、取り付け穴2よりも建物本体Bの外側に配置されており、かつ、取り付け穴2よりも上方位置に形成されている。
そのため、パネル取り付け金具1及び仮設手摺り20が連結された部分と、パネル取り付け金具1及び建築用パネル30が連結された部分とが互いに干渉することを抑制できる。
In the above configuration, as shown in Figures 2A and 2B, the panel mounting hole 3 of the panel mounting bracket 1 is positioned outside the building body B relative to the mounting hole 2, and is formed at a higher position than the mounting hole 2.
Therefore, it is possible to prevent interference between the portion where the panel mounting bracket 1 and the temporary handrail 20 are connected and the portion where the panel mounting bracket 1 and the architectural panel 30 are connected.
<仮設構造体を利用した建物施工方法>
次に、仮設手摺り20を利用した建物施工方法について図9に基づいて説明する。
具体的には、図10A-図10Eに示すように、建物本体Bに設けられた梁B1、パネル取り付け金具1、10に対し仮設手摺り20を仮設し、建築用パネル30を取り付ける建物施工方法について説明する。
<Building construction method using temporary structures>
Next, a building construction method using the temporary handrail 20 will be described with reference to FIG.
Specifically, as shown in Figures 10A to 10E, a building construction method will be described in which a temporary handrail 20 is temporarily installed on a beam B1 and panel mounting fittings 1, 10 provided on a building body B, and a building panel 30 is attached.
上記建物施工方法では、図9に示すように、まず、建物本体Bの梁B1に、建物本体Bの間口方向に間隔を空けてパネル取り付け金具1、10を複数取り付ける工程(ステップS1)から始まる。
具体的には、図10Aに示すように、梁B1の上面にパネル取り付け金具1を固定ボルト4(固定ナット5)で固定するとともに、梁B1の底面に対して第2パネル取り付け金具10を固定ボルト14で固定する。
このとき、パネル取り付け金具1と第2パネル取り付け金具10とが上下方向で重なる位置に配置されることになる。
The building construction method starts with a process (step S1) of attaching a plurality of panel mounting brackets 1, 10 to beams B1 of a building body B at intervals in the frontage direction of the building body B, as shown in FIG.
Specifically, as shown in FIG. 10A, the panel mounting bracket 1 is fixed to the upper surface of the beam B1 with a fixing bolt 4 (fixing nut 5), and the second panel mounting bracket 10 is fixed to the bottom surface of the beam B1 with a fixing bolt 14.
At this time, the panel mounting bracket 1 and the second panel mounting bracket 10 are positioned so as to overlap each other in the vertical direction.
その後、建物本体Bの梁B1、パネル取り付け金具1それぞれに対し、仮設手摺り20を取り付ける(ステップS2)。
具体的には、図1、図10Bに示すように、梁B1に形成された所定の貫通穴B2aと、梁B1上に設けられた所定のパネル取り付け金具1とに対し、仮設手摺り20を支持させるように取り付ける。
詳しく述べると、貫通穴B2aそれぞれに対し、支柱体20Aの第1、第2突出部材23、24を挿通する。このとき、第1、第2突出部材23、24の先端部23a、24aを梁B1の下部にある第2貫通穴B3aそれぞれに対しても挿通する。
さらに詳しく述べると、より長尺な第1突出部材23を、第2突出部材24よりも柱B4に近い位置にある貫通穴B2aに先に挿通する。その後、第2突出部材24を挿通する。
そして、パネル取り付け金具1に対し、第2支柱体20Bの金具ベース部材25を取り付ける。このとき、パネル取り付け金具1に形成された一対の取り付け穴2と、金具ベース部材25に形成された一対の取り付け穴26とが連通した状態で、上記取り付け穴2、26から上方に一部突出した固定ボルト4がナット締めされることで、仮設手摺り20がパネル取り付け金具1に取り付けられる。
Thereafter, the temporary handrails 20 are attached to the beams B1 of the building body B and the panel mounting brackets 1 (step S2).
Specifically, as shown in Figures 1 and 10B, the temporary handrail 20 is attached so as to be supported by a predetermined through hole B2a formed in the beam B1 and a predetermined panel mounting bracket 1 provided on the beam B1.
More specifically, the first and second protruding members 23, 24 of the support column 20A are inserted into the through holes B2a, respectively. At this time, the tip portions 23a, 24a of the first and second protruding members 23, 24 are also inserted into the second through holes B3a in the lower part of the beam B1, respectively.
More specifically, the first protruding member 23, which is longer, is first inserted through the through hole B2a located closer to the pillar B4 than the second protruding member 24. Then, the second protruding member 24 is inserted.
Then, the metal fitting base member 25 of the second support body 20B is attached to the panel mounting metal fitting 1. At this time, with the pair of mounting holes 2 formed in the panel mounting metal fitting 1 and the pair of mounting holes 26 formed in the metal fitting base member 25 communicating with each other, the fixing bolt 4 partially protruding upward from the mounting holes 2, 26 is nut-tightened, thereby attaching the temporary handrail 20 to the panel mounting metal fitting 1.
その後、図10Cに示すように、パネル取り付け金具1、10のパネル取り付け穴3、13に対し建築用パネル30を取り付ける(ステップS3)。
建築用パネル30を取り付けるときには、図10Cに示すように、まず、建築用パネル30の下端部の取り付け軸33、34をパネル取り付け穴3、13に嵌合する。その後、建築用パネル30を建物本体B側に引き寄せて、図10Dに示すように、建築用パネル30の上端部の固定ナット35を、別途設けられた第2パネル取り付け金具10のパネル固定穴12に連通させた状態で固定ボルト36によって固定する。
なお、建築用パネル30を取り付けるにあたって、建物本体Bに対し間口方向に延びた仮設手摺り20を位置決め部材として有効利用することができる。
Thereafter, as shown in FIG. 10C, the architectural panel 30 is attached to the panel mounting holes 3, 13 of the panel mounting brackets 1, 10 (step S3).
When attaching the architectural panel 30, first, as shown in Fig. 10C, the mounting shafts 33, 34 at the lower end of the architectural panel 30 are fitted into the panel mounting holes 3, 13. Then, the architectural panel 30 is pulled toward the building body B, and as shown in Fig. 10D, the fixing nut 35 at the upper end of the architectural panel 30 is fixed by the fixing bolt 36 in a state in which it is connected to the panel fixing hole 12 of the second panel mounting bracket 10 provided separately.
When attaching the architectural panel 30, the temporary handrail 20 extending in the width direction relative to the building main body B can be effectively used as a positioning member.
その後、図10Eに示すように、パネル取り付け金具1にボルト締結された仮設手摺り20を取り外して(ステップS4)、本作業工程を終了する。 Then, as shown in FIG. 10E, the temporary handrail 20 bolted to the panel mounting bracket 1 is removed (step S4), completing this work process.
上記建物施工方法であれば、施工性向上を図った建物施工方法を実現できる。
詳しく述べると、長尺な梁B1のうち、柱B4に近接した梁端部において、容易に取り付け及び取り外すことができ、安定性に優れた仮設手摺りを組み付けることができる。
The above-described building construction method can realize a building construction method that improves workability.
More specifically, a temporary handrail that can be easily attached and detached and has excellent stability can be assembled at the end of the long beam B1 that is close to the column B4.
<第2実施形態>
次に、本発明の第2実施形態について、図11、図12に基づいて説明する。
第2施形態では「仮設手摺り」及び「仮設板」が仮設構造体に相当する。
なお、第2実施形態の仮設手摺りは、上記仮設手摺り20と同様の構成であるため説明を省略する。
Second Embodiment
Next, a second embodiment of the present invention will be described with reference to FIGS.
In the second embodiment, the "temporary handrail" and the "temporary board" correspond to the temporary structure.
In addition, since the temporary handrail of the second embodiment has a similar configuration to the above-mentioned temporary handrail 20, a description thereof will be omitted.
第2実施形態の仮設板120は、建物の施工中に用いられる転落防止用の仮設構造体であって、建物本体Bに建築用パネル30を取り付ける前に取り付けられ、建築用パネル30を取り付けた後に取り外されるものである。
仮設板120は、仮設手摺り20(支柱部材21)の下方部分に取り付けられており、仮設手摺り20よりも建物本体Bの内側に配置され、建物本体Bの床パネルB5上に支持されている。なお、梁B1上に支持されていても良い。
The temporary board 120 of the second embodiment is a temporary structure for preventing falls used during construction of a building, which is attached before attaching the architectural panel 30 to the building main body B and is removed after the architectural panel 30 is attached.
The temporary plate 120 is attached to the lower portion of the temporary handrail 20 (support member 21), is disposed inside the building main body B relative to the temporary handrail 20, and is supported on the floor panel B5 of the building main body B. It may also be supported on the beam B1.
具体的には、仮設板120は、仮設手摺り20(支柱部材21)に取り付けられ、建物本体Bの内側に延びている一対の支柱部材121と、一対の支柱部材121の延出端部を連結する連結部材122と、から主に構成されている。
なお、支柱部材121は、断面矩形状の長尺体として形成されており、連結部材122は、板状の長尺体(幅木)として形成されている。
Specifically, the temporary board 120 is mainly composed of a pair of support members 121 attached to the temporary handrail 20 (support members 21) and extending toward the inside of the building main body B, and a connecting member 122 connecting the extended ends of the pair of support members 121.
The support member 121 is formed as an elongated body having a rectangular cross section, and the connecting member 122 is formed as a plate-like elongated body (baseboard).
支柱部材121の基端部には、支柱部材21に着脱可能に取り付けるための取り付け部材123が設けられている。
また、支柱部材121の延出端部には、連結部材122の長尺方向の端部を着脱可能に把持するため把持部材124が設けられている。
An attachment member 123 is provided at the base end of the support member 121 for detachably attaching the support member 121 to the support member 21 .
Further, a gripping member 124 is provided at the extending end of the support member 121 for detachably gripping the end of the connecting member 122 in the longitudinal direction.
取り付け部材123は、図12に示すように、支柱部材21を内部に挿通させた状態で保持することが可能な部材であって、支柱部材121の基端部から支柱部材21に向かって突出している一対の側壁部123aと、一対の側壁部123aの突出端部を連結する連結壁部123bと、から主に構成されている。
連結壁部123bには、取り付け部材123の内部に挿通させた支柱部材21を側方から押圧するための押圧ボルト123cが取り付けられている。
押圧ボルト123cを支柱部材21の側面に押し当てることで、取り付け部材123が支柱部材21を保持することができる。
そのため、仮設手摺り20(支柱部材21)に対して仮設板120(支柱部材121)を任意の高さ位置で取り付けることができる。
As shown in Figure 12, the mounting member 123 is a member capable of holding the support member 21 inserted therein, and is mainly composed of a pair of side wall portions 123a protruding from the base end of the support member 121 toward the support member 21, and a connecting wall portion 123b connecting the protruding ends of the pair of side wall portions 123a.
A pressing bolt 123c for pressing the support member 21 inserted inside the mounting member 123 from the side is attached to the connecting wall portion 123b.
By pressing the pressure bolt 123 c against the side surface of the support member 21 , the mounting member 123 can hold the support member 21 .
Therefore, the temporary board 120 (support member 121) can be attached to the temporary handrail 20 (support member 21) at any height position.
把持部材124は、支柱部材121に対して伸縮可能であって、連結部材122を把持することが可能な部材である。
把持部材124は、支柱部材121の内部に挿入され、支柱部材121の延出端部から伸縮可能に延びている伸縮部124aと、伸縮部124aの延出端部から下方に突出している第1把持部124bと、支柱部材121の延出願部から下方に突出している第2把持部124cと、から主に構成されている。
支柱部材121の延出端部には、支柱部材121の内部に挿入された伸縮部124aを側方から押圧するための押圧ボルト124dが取り付けられている。
押圧ボルト124dを伸縮部124aの側面に押し当てることで、支柱部材121に対して伸縮部124aを任意の延出長さで保持することができる。
そのため、把持部材124が、連結部材122の厚さによらず、連結部材122を把持することができる。
The gripping member 124 is a member that is extendable and retractable relative to the support member 121 and is capable of gripping the connecting member 122 .
The gripping member 124 is inserted inside the support member 121 and is mainly composed of an extension portion 124a extending expandably from the extended end of the support member 121, a first gripping portion 124b protruding downward from the extended end of the extension portion 124a, and a second gripping portion 124c protruding downward from the extended portion of the support member 121.
A pressing bolt 124d is attached to the extending end of the support member 121 for pressing the expandable portion 124a inserted inside the support member 121 from the side.
By pressing the pressure bolt 124d against the side surface of the expandable portion 124a, the expandable portion 124a can be held at any extension length relative to the support member 121.
Therefore, the gripping member 124 can grip the connecting member 122 regardless of the thickness of the connecting member 122 .
上記構成により、建築用パネル30を取り付ける前、及び取り付ける際に、施工部品等の落下防止対策として仮設板120を用いることができる。
また、仮設板120が、仮設手摺り20の下方部分に取り付けられ、仮設手摺り20よりも建物本体Bの内側に配置された状態で床パネルB5に支持されている。そのため、建物本体Bの出幅方向において仮設手摺り20がより安定して支持されることになる(仮設手摺り20の曲げ強度を高められる)。
With the above-described configuration, the temporary board 120 can be used as a measure to prevent construction parts, etc. from falling before and during the installation of the architectural panel 30.
In addition, the temporary board 120 is attached to the lower portion of the temporary handrail 20 and is supported by the floor panel B5 in a state where it is positioned inside the building main body B relative to the temporary handrail 20. Therefore, the temporary handrail 20 is more stably supported in the projection direction of the building main body B (the bending strength of the temporary handrail 20 can be increased).
なお、図9に示す建物施工方法において、仮設手摺り20に対し仮設板120を取り付ける工程は、ステップS2における仮設手摺り20を取り付ける工程の後に実行されると好ましい。あるいは、仮設手摺り20に仮設板120を予め取り付けておき、ステップS2で仮設板120付きの仮設手摺り20を取り付けることとしても良い。 In the building construction method shown in FIG. 9, the step of attaching the temporary plate 120 to the temporary handrail 20 is preferably carried out after the step of attaching the temporary handrail 20 in step S2. Alternatively, the temporary plate 120 may be attached to the temporary handrail 20 in advance, and the temporary handrail 20 with the temporary plate 120 attached may be attached in step S2.
<その他の実施形態>
上記実施形態では、図1に示すように、仮設手摺り20が「仮設構造体」に相当するものとして説明されているが、特に限定されることなく変更可能である。
例えば、仮設手摺りではなく、仮設足場であっても良い。あるいは、仮設梯子、仮設壁等であっても良い。
<Other embodiments>
In the above embodiment, as shown in FIG. 1, the temporary handrail 20 is described as being equivalent to the "temporary structure", but this is not particularly limited and can be modified.
For example, a temporary scaffold may be used instead of a temporary handrail, or a temporary ladder, a temporary wall, or the like may be used.
上記実施形態では、図1に示すように、仮設手摺り20(支柱体20A)が、建物本体Bのうち梁B1に取り付けられているが、特に限定されることなく、建物本体Bの所定の施工部材に取り付けられていても良い。
また、パネル取り付け金具1、10についても同様に、建物本体Bの所定の施工部材に取り付けられていても良い。
In the above embodiment, as shown in FIG. 1 , the temporary handrail 20 (support body 20A) is attached to a beam B1 of the building main body B, but is not particularly limited thereto and may be attached to a specified construction member of the building main body B.
Similarly, the panel mounting fittings 1, 10 may also be attached to a specified construction member of the building body B.
上記実施形態では、図1、図4に示すように、仮設手摺り20が、支柱体20Aと、第2支柱体20Bとを備えているが、特に限定されることなく、代わりに一対の支柱体20Aを備えていても良い。
なお、図1に示すように、長尺な梁B1において柱B4に近接した位置には、支柱体20Aを備える「手摺り20」を設置することとし、その他の位置には、一対の第2支柱体20Bを備えた「不図示の手摺り」を設置すると好ましい。
上記構成であれば、梁B1において柱B4に近接した位置では、「仮設手摺り20」を利用することで容易に取り付け及び取り外しすることができる。また、その他の位置では、上記「不図示の手摺り」を利用することで、より安定性を確保することができる。
In the above embodiment, as shown in Figures 1 and 4, the temporary handrail 20 comprises a support body 20A and a second support body 20B, but is not particularly limited and may instead comprise a pair of support bodies 20A.
As shown in FIG. 1, a "handrail 20" equipped with a support body 20A is installed in the position close to the column B4 on the long beam B1, and it is preferable to install a "handrail (not shown)" equipped with a pair of second support bodies 20B in other positions.
With the above-mentioned configuration, the "temporary handrail 20" can be used to easily attach and detach the beam B1 at a position close to the column B4. In other positions, the "handrail (not shown)" can be used to ensure greater stability.
上記実施形態では、図4-図6に示すように、第1突出部材23及び第2突出部材24が、梁ベース部材22の長さ方向において間隔を空けて設けられているが、特に限定されることなく、梁ベース部材22の幅方向に間隔を空けて設けられていても良い。
すなわち、第1、第2突出部材23、24が、建物本体Bの出幅方向に並ぶように設けられていても良い。
In the above embodiment, as shown in Figures 4 to 6, the first protruding member 23 and the second protruding member 24 are spaced apart in the longitudinal direction of the beam base member 22, but this is not particularly limited and they may also be spaced apart in the width direction of the beam base member 22.
In other words, the first and second protruding members 23, 24 may be arranged side by side in the projection direction of the building main body B.
上記実施形態では、図1、図10Dに示すように、パネル取り付け金具1、10が、建物本体Bに建築用パネル30(外壁パネル)を取り付ける際に用いられる接合金具であったが、外壁パネルに特に限定されることなく変更可能である。
例えば、パネル取り付け金具1が、建物本体Bに「腰壁パネル」や「屋根パネル」、「庇パネル」のような各種建築用パネルを取り付ける際に用いられる接合金具であっても良い。
In the above embodiment, as shown in Figures 1 and 10D, the panel mounting fittings 1, 10 were joining fittings used when attaching an architectural panel 30 (exterior wall panel) to a building main body B, but the present invention can be modified without being particularly limited to exterior wall panels.
For example, the panel mounting bracket 1 may be a joining bracket used when mounting various architectural panels such as a "waist wall panel," a "roof panel," or a "eaves panel" to the building body B.
上記実施形態では、図7、図8に示すように、パネル取り付け金具1の取り付け穴2と、仮設手摺り20の取り付け穴26とが連通した状態で固定ボルト4がナット締めされることで、仮設手摺り20がパネル取り付け金具1に取り付けられているが、特に限定されることなく変更可能である。
すなわち、「取り付け穴」と、「固定ボルト」及び「固定ナット」との係合関係に特に限定されなくても良い。すなわち、パネル取り付け金具1に設けられた取り付け部2に対し、仮設手摺り20の被取り付け部26が着脱可能に取り付けられている構成であれば良い。
In the above embodiment, as shown in Figures 7 and 8, the temporary handrail 20 is attached to the panel mounting bracket 1 by tightening the nut on the fixing bolt 4 while the mounting hole 2 of the panel mounting bracket 1 and the mounting hole 26 of the temporary handrail 20 are in communication with each other, but this can be modified without any particular limitation.
In other words, there is no need to be any particular limitation on the engagement relationship between the "mounting hole" and the "fixing bolt" and "fixing nut." In other words, it is sufficient that the mounting portion 26 of the temporary handrail 20 is detachably attached to the mounting portion 2 provided on the panel mounting bracket 1.
上記実施形態では、主として本発明に係る仮設構造体、仮設構造体の組み付け構造及び建物施工方法に関して説明した。
ただし、上記の実施形態は、本発明の理解を容易にするための一例に過ぎず、本発明を限定するものではない。本発明は、その趣旨を逸脱することなく、変更、改良され得るとともに、本発明にはその等価物が含まれることは勿論である。
In the above embodiment, the temporary structure, the assembly structure for the temporary structure, and the building construction method according to the present invention have been mainly described.
However, the above embodiment is merely an example for facilitating understanding of the present invention, and does not limit the present invention. The present invention can be modified or improved without departing from the spirit of the present invention, and the present invention naturally includes equivalents thereof.
B 建物本体
B1 梁(施工部材)
B2 上フランジ部
B2a 貫通穴
B3 下フランジ部
B3a 第2貫通穴
B4 柱
B4a 金具
B4b 第2金具
B5 床パネル
1 パネル取り付け金具
1a 底壁部
1b 外側壁部
1c 補強壁部
2 取り付け穴(取り付け部)
3 パネル取り付け穴(パネル取り付け部)
3a 第1穴部
3b 第2穴部
4 固定ボルト(固定部材)
5、6 固定ナット(固定部材)
10 第2パネル取り付け金具
10a 上壁部
10b 第1外側壁部
10c 底壁部
10d 第2外側壁部
10e 補強壁部
10f 第3外側壁部
10g 第2補強壁部
11 取り付け穴
12 パネル固定穴
13 パネル取り付け穴
13a 第1穴部
13b 第2穴部
14 固定ボルト
20 仮設手摺り(仮設構造体)
20A 支柱体
20B 第2支柱体
20C 連結体
20Ca 係合穴
21 支柱部材
21a 係合軸
22 梁ベース部材(ベース部材)
22a 第1ベース部
22b 第2ベース部
22c 補強ベース部
23 第1突出部材
23a、24a 先端部
24 第2突出部材
25金具ベース部材
25a 第1ベース部
25b 第2ベース部
25c 補強ベース部
26 取り付け穴(被取り付け部)
30 建築用パネル
31 パネルフレーム
32 仕上げ面材
33 取り付け軸
33a 第1延出部
33b 第2延出部
34 第2取り付け軸
35 固定ナット
36 固定ボルト
120 仮設板(第2仮設構造体)
121 支柱部材
122 連結部材
123 取り付け部材
123a 側壁部
123b 連結壁部
123c 押圧ボルト
124 把持部材
124a 伸縮部
124b 第1把持部
124c 第2把持部
124d 押圧ボルト
B Building body B1 Beam (construction member)
B2 Upper flange B2a Through hole B3 Lower flange B3a Second through hole B4 Pillar B4a Metal fitting B4b Second metal fitting B5 Floor panel 1 Panel mounting metal fitting 1a Bottom wall 1b Outer wall 1c Reinforcing wall 2 Mounting hole (mounting portion)
3 Panel mounting holes (panel mounting part)
3a First hole portion 3b Second hole portion 4 Fixing bolt (fixing member)
5, 6 Fixing nut (fixing member)
10 Second panel mounting bracket 10a Upper wall portion 10b First outer wall portion 10c Bottom wall portion 10d Second outer wall portion 10e Reinforcing wall portion 10f Third outer wall portion 10g Second reinforcing wall portion 11 Mounting hole 12 Panel fixing hole 13 Panel mounting hole 13a First hole portion 13b Second hole portion 14 Fixing bolt 20 Temporary handrail (temporary structure)
20A: Support body 20B: Second support body 20C: Connector body 20Ca: Engagement hole 21: Support member 21a: Engagement shaft 22: Beam base member (base member)
22a: First base portion; 22b: Second base portion; 22c: Reinforcing base portion; 23: First protruding member; 23a, 24a: Tip portion; 24: Second protruding member; 25: Metal fitting base member; 25a: First base portion; 25b: Second base portion; 25c: Reinforcing base portion; 26: Mounting hole (mounted portion);
30 Building panel 31 Panel frame 32 Finishing surface material 33 Mounting shaft 33a First extension portion 33b Second extension portion 34 Second mounting shaft 35 Fixing nut 36 Fixing bolt 120 Temporary board (second temporary structure)
121 Support member 122 Connecting member 123 Mounting member 123a Side wall portion 123b Connecting wall portion 123c Pressing bolt 124 Grip member 124a Expandable portion 124b First gripping portion 124c Second gripping portion 124d Pressing bolt
Claims (7)
上下方向に長尺に延びている支柱部材と、
前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、
前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、
前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、
前記第1突出部材、前記第2突出部材それぞれの突出先端部は、テーパー形状を有し、それぞれ先端に向かうほど細くなるように形成されており、
前記第1突出部材においてテーパー形状の開始位置となる部位が、前記第2突出部材の先端よりも前記ベース部材から遠ざかる位置に配置されていることを特徴とする仮設構造体。 A temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building,
A support member extending in a vertical direction;
A base member provided at the lower end of the support member and abutting against an upper surface of the construction member of the building body;
a first protruding member and a second protruding member provided at an interval in the length direction or width direction of the base member, protruding downward from the base member, and inserted into through holes provided at an interval on the upper surface of the construction member;
The first protruding member protrudes to be longer than the second protruding member ,
a protruding tip portion of each of the first protruding member and the second protruding member has a tapered shape and is formed so as to become thinner toward the tip,
A temporary structure, characterized in that a portion of the first protruding member that is the starting position of the tapered shape is located farther from the base member than the tip of the second protruding member .
上下方向に長尺に延びている支柱部材と、
前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、
前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、
前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、
前記ベース部材は、前記建物本体の梁の上面に当接し、
前記第1突出部材及び前記第2突出部材は、
前記梁の上部に間隔を空けて形成された前記貫通穴にそれぞれ挿通され、かつ、
前記梁の下部に間隔を空けて形成され、前記貫通穴に対応する位置に配置された第2貫通穴にそれぞれ挿通されることを特徴とする仮設構造体。 A temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building,
A support member extending in a vertical direction;
A base member provided at the lower end of the support member and abutting against an upper surface of the construction member of the building body;
a first protruding member and a second protruding member provided at an interval in the length direction or width direction of the base member, protruding downward from the base member, and inserted into through holes provided at an interval on the upper surface of the construction member;
The first protruding member protrudes to be longer than the second protruding member ,
The base member abuts against an upper surface of a beam of the building body,
The first protruding member and the second protruding member are
The through holes are respectively inserted into the through holes formed at intervals on the upper portion of the beam, and
A temporary structure characterized in that the first and second through holes are formed at intervals in the lower part of the beam and are inserted into second through holes arranged at positions corresponding to the first and second through holes .
上下方向に長尺に延びている支柱部材と、
前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、
前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、
前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、
前記第1突出部材、前記第2突出部材は、前記ベース部材と一体である(前記第2突出部材が前記ベース部材から取り外し可能であるものを除く。)ことを特徴とする仮設構造体。 A temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building,
A support member extending in a vertical direction;
A base member provided at the lower end of the support member and abutting against an upper surface of the construction member of the building body;
a first protruding member and a second protruding member provided at an interval in the length direction or width direction of the base member, protruding downward from the base member, and inserted into through holes provided at an interval on the upper surface of the construction member;
The first protruding member protrudes to be longer than the second protruding member ,
A temporary structure, characterized in that the first protruding member and the second protruding member are integral with the base member (except for a structure in which the second protruding member is detachable from the base member).
前記仮設構造体は、
上下方向に長尺に延びている支柱部材と、
前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、
前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、
前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、
前記仮設構造体は、
梁の上部に取り付けられる支柱体と、
前記梁の上部において建築用パネルを取り付ける際に用いられるパネル取り付け金具を介して取り付けられる第2支柱体と、
前記支柱体及び前記第2支柱体それぞれの上方部を連結する連結体と、を備えており、
前記支柱体は、前記支柱部材と、前記ベース部材としての梁ベース部材と、前記第1突出部材及び前記第2突出部材と、を有しており、
前記第2支柱体は、前記支柱部材と、前記支柱部材の下端部に設けられ、前記パネル取り付け金具の上面に取り付けられる金具ベース部材と、を有していることを特徴とする仮設構造体の組み付け構造。 An assembly structure for a temporary structure for preventing falls that is used during construction of a building and is attached to the main body of the building ,
The temporary structure includes:
A support member extending in a vertical direction;
A base member provided at the lower end of the support member and abutting against an upper surface of the construction member of the building body;
a first protruding member and a second protruding member provided at an interval in the length direction or width direction of the base member, protruding downward from the base member, and inserted into through holes provided at an interval on the upper surface of the construction member;
The first protruding member protrudes to be longer than the second protruding member,
The temporary structure includes:
A support body attached to the upper part of the beam;
A second support body is attached to the upper part of the beam via a panel mounting bracket used when attaching a building panel;
a connecting body connecting the upper portion of the support body and the upper portion of the second support body,
The support body includes the support member, a beam base member serving as the base member, the first protruding member, and the second protruding member,
An assembly structure for a temporary structure, characterized in that the second support body has the support member and a fitting base member provided at the lower end of the support member and attached to the upper surface of the panel mounting fitting.
前記支柱体は、前記間口方向に沿って長尺に延びている前記梁のうち、前記建物本体の柱に近接した梁端部に取り付けられ、
前記第1突出部材は、前記第2突出部材よりも前記柱に近い位置において前記貫通穴に挿通されることを特徴とする請求項4に記載の仮設構造体の組み付け構造。 The support column and the second support column are arranged at an interval in the frontage direction of the building main body,
The support body is attached to a beam end portion of the beam extending long along the frontage direction that is adjacent to a column of the building main body,
5. The temporary structure assembly structure according to claim 4, wherein the first protruding member is inserted into the through hole at a position closer to the pillar than the second protruding member.
前記パネル取り付け金具において前記建築用パネルが取り付けられるパネル取り付け部よりも前記建物本体の内側に設けられた取り付け部に対して取り付けられ、
前記仮設構造体は、前記建物本体に取り付けられたときに、前記建築用パネルの取り付け位置よりも前記建物本体の内側に位置することを特徴とする請求項4又は5に記載の仮設構造体の組み付け構造。 The metal fitting base member of the second support body is
The panel mounting bracket is attached to a mounting portion provided on the inside of the building body relative to a panel mounting portion to which the architectural panel is attached,
6. The assembly structure for a temporary structure according to claim 4 or 5, characterized in that, when the temporary structure is attached to the building main body, it is located inside the building main body relative to the attachment position of the architectural panel.
前記仮設構造体は、
上下方向に長尺に延びている支柱部材と、
前記支柱部材の下端部に設けられ、前記建物本体の施工部材の上面に当接するベース部材と、
前記ベース部材の長さ方向又は幅方向において間隔を空けて設けられ、前記ベース部材から下方に向かってそれぞれ突出し、前記施工部材の上面に間隔を空けて設けられた貫通穴にそれぞれ挿通される第1突出部材及び第2突出部材と、を備えており、
前記第1突出部材が、前記第2突出部材よりも長尺となるように突出しており、
前記建物施工方法は、
前記施工部材に対し前記仮設構造体を取り付ける工程と、
前記施工部材において前記仮設構造体よりも前記建物本体の外側に位置する部分に対し建築用パネルを取り付ける工程と、
前記施工部材から前記仮設構造体を取り外す工程と、を含み、
前記仮設構造体を取り付ける工程では、前記施工部材に設けられたそれぞれの前記貫通穴に対し、前記第1突出部材を挿通した後に前記第2突出部材を挿通することを特徴とする建物施工方法。 A building construction method using a temporary structure for preventing falls that is used during construction of a building and is attached to the building body, comprising :
The temporary structure includes:
A support member extending in a vertical direction;
A base member provided at the lower end of the support member and abutting against an upper surface of the construction member of the building body;
a first protruding member and a second protruding member provided at an interval in the length direction or width direction of the base member, protruding downward from the base member, and inserted into through holes provided at an interval on the upper surface of the construction member;
The first protruding member protrudes to be longer than the second protruding member,
The building construction method includes:
A step of attaching the temporary structure to the construction member;
A step of attaching a construction panel to a portion of the construction member that is located outside the building body relative to the temporary structure;
and removing the temporary structure from the construction member,
A building construction method characterized in that, in the process of attaching the temporary structure, the first protruding member is inserted into each of the through holes provided in the construction member, and then the second protruding member is inserted into each of the through holes provided in the construction member.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020195100A JP7611677B2 (en) | 2020-11-25 | 2020-11-25 | Temporary structure, assembly structure for temporary structure, and building construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020195100A JP7611677B2 (en) | 2020-11-25 | 2020-11-25 | Temporary structure, assembly structure for temporary structure, and building construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2022083661A JP2022083661A (en) | 2022-06-06 |
| JP7611677B2 true JP7611677B2 (en) | 2025-01-10 |
Family
ID=81855477
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020195100A Active JP7611677B2 (en) | 2020-11-25 | 2020-11-25 | Temporary structure, assembly structure for temporary structure, and building construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7611677B2 (en) |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008291609A (en) | 2007-05-28 | 2008-12-04 | Juso Tech Kk | Handrail bracket |
| JP2010071042A (en) | 2008-09-22 | 2010-04-02 | Sekisui House Ltd | Temporary handrail |
| JP2010185185A (en) | 2009-02-10 | 2010-08-26 | Sekisui House Ltd | Temporary handrail and its construction method |
| JP2021123867A (en) | 2020-01-31 | 2021-08-30 | 大和ハウス工業株式会社 | Building construction method and temporary structure used for building construction method |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0810628Y2 (en) * | 1990-05-16 | 1996-03-29 | 積水ハウス株式会社 | Opening enclosure assembly for construction sites |
-
2020
- 2020-11-25 JP JP2020195100A patent/JP7611677B2/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008291609A (en) | 2007-05-28 | 2008-12-04 | Juso Tech Kk | Handrail bracket |
| JP2010071042A (en) | 2008-09-22 | 2010-04-02 | Sekisui House Ltd | Temporary handrail |
| JP2010185185A (en) | 2009-02-10 | 2010-08-26 | Sekisui House Ltd | Temporary handrail and its construction method |
| JP2021123867A (en) | 2020-01-31 | 2021-08-30 | 大和ハウス工業株式会社 | Building construction method and temporary structure used for building construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2022083661A (en) | 2022-06-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3851105B2 (en) | Construction method of temporary structure and handrail braiding used for this | |
| JP7611677B2 (en) | Temporary structure, assembly structure for temporary structure, and building construction method | |
| JP7560251B2 (en) | Building construction method and temporary structure production method | |
| CN100577965C (en) | Detachable Platform | |
| JP2010090676A (en) | Ledger frame with floor, and frame scaffold | |
| JP5374178B2 (en) | Cloth frame with floor | |
| JP6242176B2 (en) | Elevator car floor and manufacturing method thereof | |
| JP3971420B2 (en) | Balcony railing | |
| JP7510179B2 (en) | Scaffolding panel connecting member and scaffolding | |
| JP2024140718A (en) | Temporary structure and building construction method | |
| JP7050376B1 (en) | Strut reinforcement and temporary scaffolding using this | |
| JP4312323B2 (en) | Construction method of temporary structure | |
| JP5180499B2 (en) | Cloth frame with floor and frame scaffold | |
| JP5270950B2 (en) | Stairs, tread mounting brackets for stairs | |
| JP5574185B2 (en) | Panel installation structure | |
| JP3542061B2 (en) | Scaffold support | |
| JP3916548B2 (en) | Scaffolding compression member and scaffold connection structure | |
| JP5118789B2 (en) | Temporary material connector | |
| JP7689892B2 (en) | Structure and method for mounting nose-end PC to steel structure | |
| JP2025072191A (en) | Temporary structure and building construction method | |
| KR102870480B1 (en) | Detachable safety handrail poles for A deck plate reinforcement bar | |
| JPH1181653A (en) | Scaffold support | |
| KR101413269B1 (en) | Light shape steel and assembly system using the same | |
| JP7552712B2 (en) | scaffold | |
| JP2021055454A (en) | Building construction method, and temporary structure used in building construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20231101 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20240628 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20240709 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240902 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20241210 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20241224 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7611677 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |