JP7631103B2 - Electricity supply and demand adjustment device, electricity supply and demand adjustment method, and program - Google Patents
Electricity supply and demand adjustment device, electricity supply and demand adjustment method, and program Download PDFInfo
- Publication number
- JP7631103B2 JP7631103B2 JP2021090333A JP2021090333A JP7631103B2 JP 7631103 B2 JP7631103 B2 JP 7631103B2 JP 2021090333 A JP2021090333 A JP 2021090333A JP 2021090333 A JP2021090333 A JP 2021090333A JP 7631103 B2 JP7631103 B2 JP 7631103B2
- Authority
- JP
- Japan
- Prior art keywords
- demand
- power generation
- power
- plan
- electricity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
本発明は、電力需給調整装置、電力需給調整方法、および、プログラムに関する。 The present invention relates to a power supply and demand adjustment device, a power supply and demand adjustment method, and a program.
近年、電力取引に関し、インバランス(計画と実績の差異)の精算を実施する事業者の集団として、バランシンググループ(Balancing Group:以下「BG」とも称する。)が活用されている。BGには、発電事業者による発電BGと需要家(例えば、小売電気事業者など)による需要BGがある。 In recent years, balancing groups (hereinafter referred to as "BG") have been used as a group of businesses that settle imbalances (differences between plans and actual results) in electricity trading. BGs include generation BGs made up of power generation businesses and demand BGs made up of consumers (e.g., retail electricity businesses).
発電BGは、全体で電力の同時同量に取り組むため、インバランスが生じるリスクを抑えることができる。また、発電BGは、発電電力を、相対契約相手の需要BGと、JEPX(Japan Electric Power Exchange:日本卸電力取引所)と、に売ることができる。 Since the power generation BG works to simultaneously balance the amount of electricity as a whole, it is possible to reduce the risk of imbalances occurring. In addition, the power generation BG can sell the electricity it generates to its contract counterpart, the demand BG, and to JEPX (Japan Electric Power Exchange).
例えば、JEPXでの電力取引価格が上昇すると、発電BGとしては、相対契約相手の需要BGに売る電力を減らして、JEPXで売る電力を増やしたい場合がある。しかしながら、これまでの電力取引の相対契約では、単位期間中に取引する電力の量は固定になっていることが一般的なので、そのような販売先ごとの電力取引量の変更はできない。また、需要BGとしても、発電BGから買う電力が減ると電力が不足するので、何かのメリット等がないとそのような対応をする動機付けがないことになる。 For example, when the price of electricity trading on JEPX rises, a power generation BG may want to sell less electricity to its bilateral contract counterpart, the demand BG, and increase the electricity it sells on JEPX. However, in previous bilateral contracts for electricity trading, the amount of electricity traded during a unit period was generally fixed, so it was not possible to change the amount of electricity traded for each purchase destination. Also, for the demand BG, if the amount of electricity it buys from the power generation BG decreases, it will suffer an electricity shortage, so it will have no motivation to take such measures unless there is some benefit to it.
そこで、本発明の実施形態の課題は、発電BGと需要BGの電力取引に関して売買電力量を柔軟に変更可能とする相対契約に合わせて電力需給を適切に調整可能な電力需給調整装置、電力需給調整方法、および、プログラムを提供することである。 The objective of the embodiment of the present invention is to provide an electric power supply and demand adjustment device, an electric power supply and demand adjustment method, and a program that can appropriately adjust electric power supply and demand in accordance with a bilateral contract that allows the amount of electric power purchased and sold to be flexibly changed in electric power trading between a generation BG and a demand BG.
実施形態の電力需給調整装置は、発電BG(Balancing Group)の発電計画と販売計画を策定する発電BG計画部と、前記発電BGと電力取引の相対契約をしている需要BGの需要計画と調達計画を策定する需要BG計画部と、電力取引市場での電力取引の単価である電力市場取引単価を予測して電力市場取引単価予測値を出力する電力市場取引単価予測部と、を備える。前記発電BG計画部は、前記電力市場取引単価予測値に応じて前記販売計画における前記電力取引市場への電力販売量と前記需要BGへの電力販売量を調整し、前記需要BG計画部は、前記販売計画における前記需要BGへの電力販売量の調整に応じて前記需要計画と前記調達計画を調整する。 The power supply and demand adjustment device of the embodiment includes a power generation BG (Balancing Group) planning unit that formulates a power generation plan and a sales plan for a power generation BG, a demand BG planning unit that formulates a demand plan and a procurement plan for a demand BG that has a bilateral power trading contract with the power generation BG, and a power market trading unit price prediction unit that predicts the power market trading unit price, which is the unit price of power trading in the power trading market, and outputs a power market trading unit price prediction value. The power generation BG planning unit adjusts the amount of power sold to the power trading market and the amount of power sold to the demand BG in the sales plan according to the power market trading unit price prediction value, and the demand BG planning unit adjusts the demand plan and the procurement plan according to the adjustment of the amount of power sold to the demand BG in the sales plan.
以下、図面を参照して本実施形態の電力需給調整装置、電力需給調整方法、および、プログラムについて説明する。なお、以下の説明において、「系統」は電力系統を意味する。また、「需要家」は電力需要家を意味する。また、「負荷」は電力負荷を意味する。 The power supply and demand adjustment device, power supply and demand adjustment method, and program of this embodiment will be described below with reference to the drawings. In the following description, "system" means a power system. Also, "consumer" means a power consumer. Also, "load" means a power load.
また、DR(Demand Response)とは、電力の需給バランスをとるために、需要家による電力消費量を調整することをいう。そして、需要家の電力消費量の低減によって電力需要を引き下げるDRを「下げDR」と称する。また、需要家の電力消費量の増加によって電力需要を引き上げるDRを「上げDR」と称する。また、DRに応じた需要家に与えられる報奨(例えば金銭)を、インセンティブと称する。 DR (Demand Response) refers to adjusting the amount of electricity consumed by consumers in order to balance the supply and demand of electricity. DR that lowers electricity demand by reducing electricity consumption by consumers is called "lowering DR." DR that raises electricity demand by increasing electricity consumption by consumers is called "upper DR." Rewards (e.g., money) given to consumers in response to DR are called incentives.
また、DRに応じなかった需要家や小売事業者に課せられる弁済金を「ペナルティ」と称する。なお、インセンティブ、ペナルティの有無や、それらが有る場合の金額の算出法などはそのときの制度によって異なる可能性がある。 The compensation imposed on consumers and retailers who do not comply with DR is called a "penalty." Note that the presence or absence of incentives and penalties, and the calculation method for the amounts if there are any, may differ depending on the system at the time.
まず、図1を参照して、実施形態の電力システムSの全体の概要について説明する。図1は、実施形態の電力システムSの全体の概要を模式的に示すブロック図である。電力システムSは、系統運用者システム1と、市場取引システム2(電力取引市場)と、発電BG3と、需要BG4と、を備える。 First, an overview of the power system S of the embodiment will be described with reference to FIG. 1. FIG. 1 is a block diagram showing a schematic overview of the power system S of the embodiment. The power system S includes a grid operator system 1, a market trading system 2 (power trading market), a power generation BG3, and a demand BG4.
系統運用者システム1は、電力系統を運用して商用電力を供給する系統運用者によって使用されるシステムである。 Grid operator system 1 is a system used by a grid operator who operates a power grid to supply commercial power.
市場取引システム2は、例えば、JEPXによって使用される電力市場取引システムである。以下では、市場取引システム2を「JEPX」と称する場合がある。 The market trading system 2 is, for example, an electricity market trading system used by JEPX. Hereinafter, the market trading system 2 may be referred to as "JEPX."
発電BG3は、発電事業者31(31a、31b)によるBGである。なお、発電事業者A31a、B31bを区別しないときは、単に発電事業者31と記載する。他の構成についても同様である。 The power generation BG3 is a BG by the power generation company 31 (31a, 31b). When there is no need to distinguish between the power generation companies A31a and B31b, they are simply referred to as the power generation company 31. The same applies to other configurations.
発電事業者31は、再エネ発電リソース311(以下、単に「再エネ」とも称する。)と、可調整電源リソース312(以下、「調整電源」または「電源」とも称する。)と、を備える。再エネ発電リソース311は、再生可能エネルギー(太陽光、風力、バイオマス、水力、地熱等)を用いた発電リソースである。なお、再エネ発電リソース311によって生成された電力は、FIT(Feed-in Tariff)制度やFIP(Feed-in-Premium)制度などによって、電力市場価格よりも高値の買取価格で買取りされる場合が多い。したがって、今後、再エネ発電リソース311の活用が進むと考えられる。
The power generation business operator 31 includes a renewable energy power generation resource 311 (hereinafter also simply referred to as "renewable energy") and an adjustable power source resource 312 (hereinafter also referred to as "adjustable power source" or "power source"). The renewable energy
可調整電源リソース312は、例えば、非再生可能エネルギー(火力、原子力等)を用いた発電リソースである。
The
需要BG4は、需要家41(例えば小売電気事業者など)によるBGである。需要家41は、負荷411と、蓄電池412と、再エネ発電リソース413と、を備える。 Demand BG4 is a BG provided by a consumer 41 (e.g., a retail electricity supplier). The consumer 41 includes a load 411, a storage battery 412, and a renewable energy power generation resource 413.
負荷411は、電力を消費する装置や機器である。 Load 411 is a device or equipment that consumes power.
蓄電池412は、充放電を繰り返して使用できる電池で、二次電池やバッテリともいう。 The storage battery 412 is a battery that can be repeatedly charged and discharged, and is also called a secondary battery or battery.
再エネ発電リソース413は、再生可能エネルギーを用いた発電リソースである。 Renewable energy power generation resource 413 is a power generation resource that uses renewable energy.
そして、発電BG3と需要BG4の間で、電力取引の相対契約が結ばれる。発電BG3は、発電電力を、相対契約相手の需要BG4と、市場取引システム2と、に売ることができる。 A bilateral contract for electricity trading is then concluded between power generation BG3 and demand BG4. Power generation BG3 can sell the generated electricity to demand BG4, which is the counterpart of the bilateral contract, and to the market trading system 2.
そして、例えば、市場取引システム2での電力取引価格が上昇すると、発電BG3としては、相対契約相手の需要BG4に売る電力を減らして、市場取引システム2で売る電力を増やしたい場合がある。 For example, when the electricity trading price in the market trading system 2 rises, the power generation BG3 may want to reduce the amount of electricity it sells to its bilateral contract partner, the demand BG4, and increase the amount of electricity it sells in the market trading system 2.
しかしながら、これまでの電力取引の相対契約では、単位期間中に取引する電力量は固定になっていることが一般的なので、そのような販売先ごとの電力量の変更はできない。また、需要BG4としても、発電BG3から買う電力が減ると電力が不足するので、何かのメリット等がないとそのような対応をする動機付けがないことになる。 However, in the bilateral contracts for electricity trading up to now, the amount of electricity traded during a unit period is generally fixed, and it is not possible to change the amount of electricity for each purchase destination. Also, for demand BG4, if the amount of electricity purchased from generator BG3 decreases, there will be a shortage of electricity, so unless there is some benefit, there will be no motivation to take such measures.
そこで、まず、発電BG3と需要BG4の電力取引に関して、売買電力量を柔軟に変更可能とする相対契約を考える。そして、そのような相対契約に合わせて、例えば、発電BG3が需要BG4に売る電力を減らして市場取引システム2で売る電力を増やし、それによって獲得した利益を発電BG3と需要BG4でシェアすることにすれば、発電BG3だけでなく需要BG4にとってもメリットとなる。このように、売買電力量を柔軟に変更可能とする相対契約に合わせて電力需給を適切に調整可能な技術について、以下に説明する。 First, consider a bilateral contract for power trading between power generation BG3 and demand BG4 that allows the amount of power bought and sold to be flexibly changed. Then, in accordance with such a bilateral contract, for example, power generation BG3 can reduce the amount of power it sells to demand BG4 and increase the amount of power it sells to market trading system 2, and share the profits gained from this between power generation BG3 and demand BG4, which will benefit not only power generation BG3 but also demand BG4. Below, we will explain a technology that can appropriately adjust power supply and demand in accordance with a bilateral contract that allows the amount of power bought and sold to be flexibly changed in this way.
図2を参照して、実施形態における発電と需要の各計画の第1の変更例について説明する。図2は、実施形態における発電と需要の各計画の第1の変更例を模式的に示す図である。 A first modification example of each of the power generation and demand plans in the embodiment will be described with reference to FIG. 2. FIG. 2 is a diagram that illustrates a first modification example of each of the power generation and demand plans in the embodiment.
図2(a)は、電力需給の調整前の状態を示す。図2(a1)に示すように、発電BG3に関して、発電計画と販売計画が策定される。この例では、発電計画における発電電力には、再エネBG(再エネBGによる発電電力)と火力BG(火力BGによる発電電力)がある。 Figure 2 (a) shows the state before the adjustment of power supply and demand. As shown in Figure 2 (a1), a power generation plan and a sales plan are formulated for power generation BG3. In this example, the power generation plan includes renewable energy BG (power generated by renewable energy BG) and thermal power BG (power generated by thermal power BG).
また、販売計画における販売先には、相対小売BG(需要BG4)とJEPX(市場取引システム2)がある。 In addition, the sales destinations in the sales plan include bilateral retail BG (demand BG4) and JEPX (market trading system 2).
また、図2(a2)に示すように、需要BG4に関して、需要計画と調達計画が策定される。この例では、需要計画における需要BG(需要BGによる需要電力)に対応して、調達計画における調達先として発電BG3(相対調達)が決定される。 Furthermore, as shown in FIG. 2(a2), a demand plan and a procurement plan are formulated for demand BG4. In this example, power generation BG3 (relative procurement) is determined as the procurement source in the procurement plan in response to demand BG (demanded power by demand BG) in the demand plan.
ここで、時間前市場において、JEPX(市場取引システム2)での電力取引価格の上昇が見込まれるとする。その場合、図2(b1)に示すように、発電BG3は、販売計画において、相対小売BGを減らして、JEPXを増やしたい。また、売買電力量を柔軟に変更可能とする相対契約なので、図2(b2)に示すように、需要BG4の需要計画において下げDRによって需要を減らし、それに合わせて、調達計画における相対調達も減らすことができる。 Now, let us assume that in the hour-ahead market, an increase in the electricity trading price is expected in JEPX (market trading system 2). In that case, as shown in Figure 2 (b1), power generation BG3 wants to reduce the relative retail BG in its sales plan and increase JEPX. Also, since it is a relative contract that allows the amount of electricity purchased and sold to be changed flexibly, as shown in Figure 2 (b2), it is possible to reduce demand by using a downward DR in the demand plan of demand BG4, and accordingly reduce relative procurement in the procurement plan.
また、下げDRが失敗した場合を考える。なお、下げDRの失敗としては、例えば、以下の(1)~(3)の3つが挙げられる。
(1)発電BG3が需要BG4に下げDRを依頼したが、需要BG4が拒否した。
(2)需要BG4が下げDRを受諾したが、その配下の需要家41が拒否した。
(3)需要BG4も需要家41も下げDRを受諾したが、需要家41が実際に消費電力を抑えられなかった。
Let us now consider a case where a downward DR fails. The following three cases (1) to (3) can be cited as examples of a downward DR failure.
(1) Power generation BG3 requested a lowering DR from demand BG4, but demand BG4 refused.
(2) Demand BG4 accepted the down DR, but its subordinate customer 41 rejected it.
(3) Although both demand BG4 and consumer 41 accepted the lower DR, consumer 41 was unable to actually reduce its power consumption.
そして、下げDRの失敗のリスクを評価(予測)する場合、(1)、(2)、(3)で計算方法が異なりえる。また、発電BG3と需要BG4が異なるプレイヤーの場合、(1)~(3)のいずれも起こりえる。また、発電BG3と需要BG4が同じプレイヤーの場合、(1)は起こらず、(2)と(3)は起こりえる。 When evaluating (predicting) the risk of failure of a downward DR, the calculation methods can differ between (1), (2), and (3). Also, if the power generation BG3 and the demand BG4 are different players, any of (1) to (3) can occur. Also, if the power generation BG3 and the demand BG4 are the same player, (1) does not occur, but (2) and (3) can occur.
そして、図2(c1)に示すように、発電BG3において、発電実績は図2(b1)の発電計画を実現したものとなり、販売実績も図2(b1)の販売計画を実現したものとなったとする。 As shown in FIG. 2(c1), in power generation BG3, the power generation results are the same as the power generation plan in FIG. 2(b1), and the sales results are the same as the sales plan in FIG. 2(b1).
一方、図2(c2)に示すように、ゲートクローズ(Gate Close:以下「GC」とも称する。)後に、需要BG4において、需要実績と調達実績のいずれもそれぞれ図2(b2)の需要計画と調達計画を実現しておらず、需要インバランスとして清算する必要がある。 On the other hand, as shown in Figure 2 (c2), after gate close (hereinafter also referred to as "GC"), in demand BG4, neither the demand actual nor the procurement actual has realized the demand plan and procurement plan in Figure 2 (b2), respectively, and it needs to be settled as a demand imbalance.
そして、例えば、需要インバランスが低額であって、需要インバランスによる損失を考慮しても、発電BG3における電力の販売先ごとの販売量の変更により獲得した利益によって、総合的に利益が出ていればよいと考えられる。したがって、事前にそのような予測ができるのであれば、発電BG3における電力の販売先ごとの販売量を変更すべきであるという判断を下せる。 For example, if the demand imbalance is low and the losses due to the demand imbalance are taken into account, it is sufficient if there is an overall profit due to the profit gained by changing the sales volume of electricity to each buyer in power generation BG3. Therefore, if such a prediction can be made in advance, a decision can be made to change the sales volume of electricity to each buyer in power generation BG3.
なお、需要BG4は、不足した電力をJEPXから買うという選択肢もとりえる。 Demand BG4 can also choose to purchase the electricity shortage from JEPX.
次に、図3は、実施形態における発電と需要の各計画の第2の変更例を模式的に示す図である。図2では下げDRの失敗時について説明したが、図3では再エネによる発電量が予定よりも少なかった場合について説明する。図3(a)(b)は、図2(a)(b)と同様である。 Next, FIG. 3 is a diagram showing a second modified example of the power generation and demand plans in the embodiment. While FIG. 2 describes the case where the downward DR fails, FIG. 3 describes the case where the amount of power generation from renewable energy is less than planned. FIGS. 3(a) and (b) are similar to FIGS. 2(a) and (b).
また、図3(c2)に示すように、需要BG4における需要計画と調達計画のいずれもそれぞれ図3(b2)と同様である。 Also, as shown in Figure 3(c2), the demand plan and procurement plan for demand BG4 are the same as those in Figure 3(b2).
そして、図3(c1)に示すように、GC後に、発電BG3において、発電実績が図3(b1)の発電計画を実現していない。つまり、火力BGは計画と実績が同じであるが、再エネBGの実績が計画より少ない。この場合、発電電力の不足分について、以下の(11)、(12)の対応が考えられる。 As shown in Figure 3 (c1), after GC, the actual power generation in power generation BG3 does not achieve the power generation plan in Figure 3 (b1). In other words, the thermal power BG's actual power generation is the same as the plan, but the renewable energy BG's actual power generation is less than the plan. In this case, the following measures (11) and (12) can be considered to address the shortfall in power generation.
(11)発電BG3内の他の電源で持ち替え(代替発電)
(12)発電インバランスとして清算
(11) Switch to another power source within power generation BG3 (alternative power generation)
(12) Settlement as power generation imbalance
そして、例えば、(11)または(12)の実行による費用増加を考慮しても、発電BG3における電力の販売先ごとの販売量の変更により獲得した利益によって、総合的に利益が出ていればよいと考えられる。したがって、事前にそのような予測ができるのであれば、発電BG3における電力の販売先ごとの販売量を変更すべきであるという判断を下せる。 And, for example, even if the increased costs of implementing (11) or (12) are taken into account, it is sufficient if the profits gained by changing the sales volume of electricity to each buyer in Power Generation BG3 result in an overall profit. Therefore, if such a prediction can be made in advance, it is possible to make the decision to change the sales volume of electricity to each buyer in Power Generation BG3.
なお、ここまで、JEPXでの電力取引価格の上昇が見込まれて下げDRを行う場合について説明したが、逆に、JEPXでの電力取引価格の下降が見込まれて上げDRを行う場合についても同様である。 So far, we have explained the case where a downward DR is made when an increase in the electricity trading price on JEPX is expected, but the same applies to the opposite case where an upward DR is made when a decrease in the electricity trading price on JEPX is expected.
時間前市場で電力取引市場価格が上がる場合と下がる場合について、発電BG3における、取引戦略と、GC後のリスクと、対処法と、についてまとめると、以下の通りである。 The trading strategy, post-GC risks, and countermeasures for Power Generation BG3 in the cases where the electricity trading market price rises or falls in the hourly market are summarized as follows:
(時間前市場で電力取引市場価格が上がる場合)
(取引戦略1)下げDRでJEPX売電量増加
(GC後のリスク1)下げDR失敗
(対処法1)下げDR失敗リスクを評価し、下げDR量を調整
(対処法2)需要インバランス受け入れ(対処法1不実施)
(When the electricity trading market price rises in the pre-hours market)
(Trading strategy 1) Increase in JEPX electricity sales volume with lower DR (Risk 1 after GC) Failure of lower DR (Countermeasure 1) Evaluate the risk of failure of lower DR and adjust the amount of lower DR (Countermeasure 2) Accept demand imbalance (Countermeasure 1 not implemented)
(GC後のリスク2)再エネ出力の減少、増加
(対処法1)下げDR(計画)を増加、減少
(対処法2)調整電源で持替(計画)
(対処法3)調整電源で持替(制御)
(対処法4)発電インバランス受け入れ(対処法1~3不実施)
(Risk 2 after GC) Decrease or increase in renewable energy output (Countermeasure 1) Increase or decrease in lower DR (plan) (Countermeasure 2) Substitute with regulated power source (plan)
(Solution 3) Replace with regulated power source (control)
(Countermeasure 4) Accepting power generation imbalance (countermeasures 1 to 3 not implemented)
(取引戦略2)調整電源出力増でJEPX売電量増加
(GC後のリスク)再エネ出力の減少、増加
(対処法1)調整電源で持替(計画)
(対処法2)調整電源で持替(制御)
(対処法3)発電インバランス受け入れ(対処法1、2不実施)
(Trading strategy 2) Increase in JEPX electricity sales due to increased output from regulated power sources (Risks after GC) Decrease and increase in renewable energy output (Countermeasure 1) Switch to regulated power sources (plan)
(Solution 2) Replace with regulated power source (control)
(Countermeasure 3) Accepting power generation imbalance (countermeasures 1 and 2 not implemented)
(時間前市場で電力取引市場価格が下がる場合)
(取引戦略1)上げDRでJEPX売電量減少
(GC後のリスク1)上げDR失敗
(対処法1)上げDR失敗リスクを評価し、上げDR量を調整
(対処法2)需要インバランス受け入れ(対処法1不実施)
(When the electricity trading market price falls in the pre-hours market)
(Trading strategy 1) JEPX electricity sales volume decreases due to up-DR (Risk 1 after GC) Up-DR failure (Countermeasure 1) Evaluate the risk of up-DR failure and adjust the up-DR volume (Countermeasure 2) Accept demand imbalance (Countermeasure 1 not implemented)
(GC後のリスク2)再エネ出力の減少、増加
(対処法1)上げDR(計画)を減少、増加
(対処法2)調整電源で持替(計画)
(対処法3)調整電源で持替(制御)
(対処法4)発電インバランス受け入れ(対処法1~3不実施)
(Risk 2 after GC) Decrease or increase in renewable energy output (Countermeasure 1) Decrease or increase in increased DR (plan) (Countermeasure 2) Substitute with regulated power source (plan)
(Solution 3) Replace with regulated power source (control)
(Countermeasure 4) Accepting power generation imbalance (countermeasures 1 to 3 not implemented)
(取引戦略2)調整電源出力減でJEPX売電量減少
(GC後のリスク)再エネ出力の減少、増加
(対処法1)調整電源で持替(計画)
(対処法2)調整電源で持替(制御)
(対処法3)発電インバランス受け入れ(対処法1、2不実施)
(Trading strategy 2) Decrease in JEPX electricity sales due to decrease in regulated power source output (Risk after GC) Decrease and increase in renewable energy output (Countermeasure 1) Switch to regulated power source (plan)
(Solution 2) Replace with regulated power source (control)
(Countermeasure 3) Accepting power generation imbalance (countermeasures 1 and 2 not implemented)
次に、図4を参照して、実施形態の情報処理装置5(電力需給調整装置)について説明する。図4は、実施形態の情報処理装置5の機能構成を示すブロック図である。情報処理装置5は、例えば、PC(Personal Computer)である。
Next, the information processing device 5 (electricity supply and demand adjustment device) of the embodiment will be described with reference to FIG. 4. FIG. 4 is a block diagram showing the functional configuration of the
情報処理装置5は、記憶部51と、入力部52と、表示部53と、通信部54と、処理部55と、を備える。
The
記憶部51は、例えば、RAM(Random Access Memory)、ROM(Read Only Memory)、SSD(Solid State Drive)、HDD(Hard Disk Drive)等によって実現され、各種情報を記憶する。記憶部51は、例えば、各種設定値、各種パラメータ、所定の目的関数、各種演算結果等を記憶する。記憶部51は、DB(Data Base)511を備える。
The
DB511には、例えば、発電BG単価(電源出力調整単価)、電源出力変化可能幅、需要調整可能幅、需要BG調整単価(対需要家・対需要BG)(「需要調整単価」とも称する。)、電力市場取引単価(または予測値)、発電/需要インバランス単価(または予測値)等の情報が格納される(詳細は後述)。 In DB511, information such as the power generation BG unit price (power output adjustment unit price), the power output changeable range, the demand adjustment range, the demand BG adjustment unit price (for consumers/for demand BG) (also referred to as the "demand adjustment unit price"), the electricity market trading unit price (or forecast value), and the power generation/demand imbalance unit price (or forecast value) are stored (details will be described later).
入力部52は、オペレータが各種操作入力を行う手段で、例えば、マウス、キーボード、タッチパネル等である。
The
表示部53は、情報を表示する手段で、例えば、LCD(Liquid Crystal Display)、タッチパネル等である。
The
通信部54は、外部装置と通信を行うための通信インターフェースである。
The
処理部55は、例えば、CPU(Central Processing Unit)によって実現され、各種演算処理を実行する。処理部55は、例えば、機能部として、取得部551と、再エネ発電量予測部552と、電力市場取引単価予測部553と、インバランス単価予測部554と、発電BG計画部555と、需要BG計画部556と、インセンティブ算出部557と、利益配分算出部558と、表示制御部559と、を備える。
The
取得部551は、系統運用者システム1、市場取引システム2、発電BG3、需要BG4、DB511などから各種情報を取得する。
The
再エネ発電量予測部552は、過去のデータ、気象データなどに基づいて、再エネ発電リソース311や再エネ発電リソース413による発電量を予測する。
The renewable energy power
電力市場取引単価予測部553は、市場取引システム2での電力取引の単価である電力市場取引単価を予測して電力市場取引単価予測値を出力する。
The electricity market trading unit
インバランス単価予測部554は、発電インバランス単価と需要インバランス単価を予測する。 The imbalance cost prediction unit 554 predicts the power generation imbalance cost and the demand imbalance cost.
発電BG計画部555は、発電BG3の発電計画と販売計画を策定する。発電BG計画部555は、電力市場取引単価予測値に応じて販売計画における市場取引システム2への電力販売量と需要BG4への電力販売量を調整する。
The power generation
発電BG計画部555は、発電BG3の電源(可調整電源リソース312)の出力のコスト単価である発電BG単価のメリットオーダーに基づいて、出力を調整する電源の優先順位を決定する。
The power generation
発電BG計画部555は、出力を調整する電源の優先順位、および、需要を調整する需要リソースの優先順位(需要BG計画部556によって決定)に基づいて、販売計画における市場取引システム2への電力販売量を決定する。
The power generation
発電BG計画部555は、市場取引システム2のGC後における発電BG3の電源の出力の変動による発電インバランスのリスクを予測し、発電インバランスのリスクに基づいて損益の期待値を発電インバランス損益期待値として算出し、発電BG単価に発電インバランス損益期待値を反映する。
The power generation
需要BG計画部556は、発電BG3と電力取引の相対契約をしている需要BG4の需要計画と調達計画を策定する。需要BG計画部556は、販売計画における需要BG3への電力販売量の調整に応じて需要計画と調達計画を調整する。
The demand
需要BG計画部556は、需要BG3の需要リソース(負荷411、蓄電池412など)の需要計画と調達計画の調整に係るコスト単価である需要BG調整単価のメリットオーダーに基づいて、需要を調整する需要リソースの優先順位を決定する。
The demand
需要BG計画部556は、GC後において需要計画の需要リソースの調整が計画通り履行されないことによる需要インバランスのリスクを予測し、需要インバランスのリスクに基づいて損益の期待値を需要インバランス損益期待値として算出し、需要BG調整単価に需要インバランス損益期待値を反映する。
The demand
インセンティブ算出部557は、需要BG計画部556による需要計画と調達計画の調整に対するインセンティブ額を算出する。
The
利益配分算出部558は、販売計画の調整により得られる利益の発電BG3と需要BG4への配分を算出する。
The profit
表示制御部559は、各種情報を表示部53に表示する。表示制御部559は、例えば、発電BG単価と、需要BG調整単価と、発電BG単価のメリットオーダーと、需要BG調整単価のメリットオーダーと、電源の発電インバランス損益期待値と、需要リソースの需要インバランス損益期待値と、需要リソースの調整が計画通り履行されない場合のペナルティと、販売計画の調整により獲得が見込まれる利益と、を表示部53に表示させる。
The
ここで、図5は、実施形態における第1の目的関数例の説明図である。第1の目的関数例を用いた処理は、例えば、発電BG計画部555が需要BG計画部556などと連携することによって行われる。ここでは、連携BG(発電BG3と需要BG4)における利益の最大化を図る。したがって、発電BG3と需要BG4の間の取引である相対売電収益と需要調整コスト(BG間)は考慮しない。また、発電インバランスと需要インバランスは送配電事業者9に対して支払う。そして、以下の目的関数F1の最大化を考える。
Here, FIG. 5 is an explanatory diagram of an example of a first objective function in an embodiment. Processing using the first objective function example is performed, for example, by the power generation
目的関数F1
=「市場取引システム2(JEPX)からの売電収益(=市場取引量×市場取引単価)」
-「発電コスト(=発電BG単価×発電量)」
-「需要調整コスト(対需要家)(=需要家調整単価×需要調整量)」
-「発電インバランス(予測値)」
-「需要インバランス(予測値)」
Objective function F1
= "Electricity sales revenue from market trading system 2 (JEPX) (= market trading volume x market trading price)"
- "Power generation cost (= power generation BG unit price x power generation amount)"
- "Demand adjustment cost (for consumers) (= consumer adjustment unit price × demand adjustment amount)"
- "Power generation imbalance (forecast value)"
- "Demand imbalance (forecast)"
この目的関数F1の値を最大化させる計算を行い、各パラメータ(電力の市場取引量、発電量、需要調整量など)を決定する。 A calculation is performed to maximize the value of this objective function F1, and each parameter (market trading volume of electricity, amount of power generation, amount of demand adjustment, etc.) is determined.
なお、発電インバランス(予測値)(発電インバランス損益期待値)は発電BG単価に、需要インバランス(予測値)(需要インバランス損益期待値)は需要BG調整単価に織り込む(反映する)ことで、インバランスを考慮したメリットオーダーで扱う。 The power generation imbalance (forecast value) (power generation imbalance profit/loss expectation value) is incorporated (reflected) in the power generation BG unit price, and the demand imbalance (forecast value) (demand imbalance profit/loss expectation value) is incorporated (reflected) in the demand BG adjustment unit price, so that the imbalances are handled in a merit order that takes them into account.
次に、図6は、実施形態における第2の目的関数例の説明図である。第2の目的関数例を用いた処理は、例えば、発電BG計画部555によって行われる。ここでは、発電BG3における利益の最大化を図る。そして、以下の目的関数F2の最大化を考える。
Next, FIG. 6 is an explanatory diagram of an example of a second objective function in an embodiment. Processing using the second objective function example is performed, for example, by the power generation
目的関数F2
=「市場取引システム2(JEPX)からの売電収益(=市場取引量×市場取引単価)」
+「相対売電収益」
-「需要調整コスト(BG間)(=需要BG調整単価×需要調整量)」
-「発電コスト(=発電BG単価×発電量)」
-「発電インバランス(予測値)」
Objective function F2
= "Electricity sales revenue from market trading system 2 (JEPX) (= market trading volume x market trading price)"
+ "Relative electricity sales revenue"
- "Demand adjustment cost (between BGs) (= demand BG adjustment unit price x demand adjustment amount)"
- "Power generation cost (= power generation BG unit price x power generation amount)"
- "Power generation imbalance (forecast value)"
この目的関数F2の値を最大化させる計算を行い、各パラメータ(電力の市場取引量、発電量、需要調整量など)を決定する。 Calculations are performed to maximize the value of this objective function F2, and each parameter (market trading volume of electricity, power generation volume, demand adjustment volume, etc.) is determined.
なお、発電インバランス(予測値)(発電インバランス損益期待値)は発電BG単価に織り込む(反映する)ことで、インバランスを考慮したメリットオーダーで扱う。 The power generation imbalance (forecast value) (expected power generation imbalance profit/loss value) is incorporated (reflected) in the power generation BG unit price, and is handled in a merit order that takes the imbalance into account.
次に、図7は、実施形態における需要インバランスリスクの評価と需要BG調達単価への反映の説明図である。 Next, Figure 7 is an explanatory diagram of the assessment of demand imbalance risk in an embodiment and its reflection in the demand BG procurement unit price.
まず、図7(a)は、DR量αと、αに対するインバランスの期待値βの特性情報を示す。この特性情報は、例えば、需要リソースの特性等に基づいて作成される。 First, FIG. 7(a) shows characteristic information of the DR amount α and the expected value β of the imbalance for α. This characteristic information is created based on, for example, the characteristics of the demand resource.
また、図7(b)は、DR量αと、需要調整単価の特性情報を示す。インバランスを考慮しない場合の特性が線L2である。そして、インバランスを考慮した場合の特性が線L1である。具体的には、まず、インバランス単価予測値γを取得し、インバランス損益期待値であるβ×γのαに対する特性を、需要調整単価の特性に重畳することで、線L1が得られる。 Figure 7 (b) shows characteristic information of the DR amount α and the demand adjustment unit price. The characteristic when imbalance is not taken into account is line L2. And the characteristic when imbalance is taken into account is line L1. Specifically, first, the imbalance unit price prediction value γ is obtained, and the characteristic of β×γ, which is the expected imbalance profit and loss value, for α is superimposed on the characteristic of the demand adjustment unit price to obtain line L1.
そして、図7(c)は、計画段階の最適値を示す。この場合、図7(c2)にDR量αが示されている。また、図7(d)は、DR失敗時の期待値を示す。この場合、図7(c2)にインバランス期待値βが示されている。 Figure 7(c) shows the optimal value in the planning stage. In this case, the DR amount α is shown in Figure 7(c2). Figure 7(d) shows the expected value when DR fails. In this case, the imbalance expected value β is shown in Figure 7(c2).
このようにして、需要インバランスリスクの評価を需要BG調達単価に反映することができる。 In this way, the assessment of demand imbalance risk can be reflected in the demand BG procurement unit price.
次に、図8は、実施形態における発電インバランスリスクの評価と電源出力調整単価への反映の説明図である。 Next, FIG. 8 is an explanatory diagram showing the evaluation of power generation imbalance risk and its reflection in the power output adjustment unit price in an embodiment.
まず、図8(a)は、再エネ出力の予測誤差リスク(下落リスク)と、不足インバランスリスク(上げ余力不足)の特性情報を示す。なお、グラフの左側のように、上げ余力内に出力誤差が収まる場合は、インバランスはゼロとなる。また、図8(b)は、調整電源出力と上げ余力の特性情報を示す。 First, Figure 8 (a) shows characteristic information on the forecast error risk (risk of decline) and shortfall imbalance risk (shortage of margin of increase) of renewable energy output. Note that, as shown on the left side of the graph, if the output error falls within the margin of increase, the imbalance will be zero. Also, Figure 8 (b) shows characteristic information on regulated power source output and margin of increase.
そして、図8(c)は、計画段階の最適値を示す。図8(c1)では、図7(c1)の場合と比べて、JEPXでの電力取引単価が高いため、発電計画で火力BGを符号Sの分だけ増やし、それに伴って、販売計画でJEPXが符号Tの分だけ増えている。 Figure 8 (c) shows the optimal values at the planning stage. In Figure 8 (c1), the electricity trading price at JEPX is higher than in the case of Figure 7 (c1), so the thermal power BG is increased by the amount indicated by the symbol S in the power generation plan, and accordingly, JEPX is increased by the amount indicated by the symbol T in the sales plan.
また、図8(d)は、再エネ出力が予測値よりも低下する場合を示す。この場合、図8(d1)示すように、図8(c1)ですでに火力BGが出力可能範囲の上限に達しているため、GC後の再エネ出力低下に火力BGの増加によって対応できす、符号Uに示すインバランスが発生する。 Figure 8(d) shows a case where the renewable energy output falls below the predicted value. In this case, as shown in Figure 8(d1) and because thermal power BG has already reached the upper limit of the possible output range in Figure 8(c1), the decrease in renewable energy output after GC cannot be accommodated by increasing thermal power BG, resulting in an imbalance indicated by the symbol U.
このように、調整電源出力で決まる上げ余力と、再エネ出力予測誤差リスクから、不足インバランスリスクを算出し、インバランス単価を乗じて発電BG単価に加算して反映する。 In this way, the shortfall imbalance risk is calculated from the margin of error determined by the output of regulated power sources and the risk of errors in the renewable energy output forecast, and is then multiplied by the imbalance cost and added to the power generation BG cost to reflect this.
次に、図9を参照して、実施形態の情報処理装置5による処理について説明する。図9は、実施形態の情報処理装置5による処理を示すフローチャートである。なお、以下において、本実施形態に特有の処理以外の処理(例えば、需給調整前の発電計画、販売計画、需要計画、調達計画の策定等)については、説明がなくても従来と同様の処理が行われるものとする。
Next, the processing by the
まず、ステップS1において、再エネ発電量予測部552は、過去のデータ、気象データなどに基づいて、再エネ発電リソース311や再エネ発電リソース413による発電量を予測する。
First, in step S1, the renewable energy power
次に、ステップS2において、電力市場取引単価予測部553は、電力市場取引単価を予測して電力市場取引単価予測値を出力する。
Next, in step S2, the electricity market trading unit
次に、ステップS3において、取得部551は、DB511から電源出力調整単価情報を取得する。
Next, in step S3, the
次に、ステップS4において、取得部551は、DB511から電源出力変化可能幅情報を取得する。
Next, in step S4, the
次に、ステップS5において、取得部551は、DB511から需要調整単価情報を取得する。
Next, in step S5, the
次に、ステップS6において、取得部551は、DB511から需要調整可能幅情報を取得する。
Next, in step S6, the
次に、ステップS7において、取得部551は、DB511から需要調整インセンティブ単価情報を取得する。
Next, in step S7, the
次に、ステップS8において、インバランス単価予測部554は、発電インバランス単価と需要インバランス単価を予測する。 Next, in step S8, the imbalance cost prediction unit 554 predicts the power generation imbalance cost and the demand imbalance cost.
次に、ステップS9において、発電BG計画部555は、発電BG3の電源(可調整電源リソース312)の出力のコスト単価である発電BG単価のメリットオーダーに基づいて、出力を調整する電源の優先順位と調整量を決定する。
Next, in step S9, the power generation
次に、ステップS10において、需要BG計画部556は、需要BG3の需要リソース(負荷411、蓄電池412など)の需要計画と調達計画の調整に係るコスト単価である需要BG調整単価のメリットオーダーに基づいて、需要を調整する需要リソースの優先順位と調整量を決定する。
Next, in step S10, the demand
次に、ステップS11において、発電BG計画部555は、発電インバランスのリスクに基づいて発電インバランス損益期待値を算出し、電力出力調整単価情報(発電BG単価)に発電インバランス損益期待値を反映する。
Next, in step S11, the power generation
次に、ステップS12において、需要BG計画部556は、需要インバランスのリスクに基づいて需要インバランス損益期待値を算出し、需要調整単価情報に需要インバランス損益期待値を反映する。
Next, in step S12, the demand
次に、ステップS13において、発電BG計画部555は、目的関数(F1、F2)の値を最大化させる計算を行い、各パラメータ(電力の市場取引量、発電量、需要調整量など)を決定する。
Next, in step S13, the power generation
次に、ステップS14において、表示制御部559は、例えば、発電BG3の電源の発電BG単価と、需要BG4の需要リソースの需要BG調整単価と、発電BG単価のメリットオーダーと、需要BG調整単価のメリットオーダーと、電源の発電インバランス損益期待値と需要リソースの需要インバランス損益期待値と、需要リソースの調整が計画通り履行されない場合のペナルティと、販売計画の調整により獲得が見込まれる利益と、を表示部53に表示させる。
Next, in step S14, the
このように、本実施形態の情報処理装置5によれば、発電BG3と需要BG4の電力取引に関して売買電力量を柔軟に変更可能とする相対契約を前提として、その相対契約に合わせて電力需給を適切に調整することができる。したがって、そのような相対契約の促進に寄与する。
In this way, according to the
また、販売計画の調整により得られる利益の発電BG3と需要BG4への配分を算出し、利益を発電BG3と需要BG4でシェアすることで、発電BG3だけでなく需要BG4の側にも需給調整によるメリットが生じる。 In addition, by calculating the allocation of the profits gained by adjusting the sales plan to power generation BG3 and demand BG4 and sharing the profits between power generation BG3 and demand BG4, the benefits of supply and demand adjustment will accrue not only to power generation BG3 but also to demand BG4.
また、需要計画と調達計画の調整に対するインセンティブ額を算出し、インセンティブ付与を実施することで、DRに応じた需要家も恩恵を受けることができる。また、販売計画の調整により得られる利益を原資としてインセンティブを支払うことができる。 In addition, by calculating the amount of incentives for adjusting the demand plan and procurement plan and providing the incentives, consumers who comply with the DR can also benefit. Incentives can also be paid using the profits gained from adjusting the sales plan.
また、発電BG単価のメリットオーダーに基づいて出力を調整する電源の優先順位を決定し、さらに、需要BG調整単価のメリットオーダーに基づいて需要を調整する需要リソースの優先順位を決定し、それらに基づくことで、販売計画における電力取引市場への電力販売量をより適切に決定することができる。 In addition, the priority order of power sources that adjust output based on the merit order of power generation BG unit prices is determined, and the priority order of demand resources that adjust demand based on the merit order of demand BG adjustment unit prices is determined. Based on these, the amount of electricity sold to the electricity trading market in the sales plan can be more appropriately determined.
また、発電インバランスのリスクに基づいて算出した発電インバランス損益期待値を発電BG単価に反映し、需要インバランスのリスクに基づいて算出した需要インバランス損益期待値を需要BG調整単価に反映することで、簡潔かつ高精度な目的関数を実現することができる。また、GC後の再エネ出力やDR実現の不確実性によるインバランスリスクを適切に反映した演算結果を得ることができる。 In addition, by reflecting the power generation imbalance profit and loss expectation value calculated based on the risk of power generation imbalance in the power generation BG unit price, and reflecting the demand imbalance profit and loss expectation value calculated based on the risk of demand imbalance in the demand BG adjustment unit price, a simple and highly accurate objective function can be realized. In addition, it is possible to obtain calculation results that appropriately reflect the imbalance risk due to the uncertainty of renewable energy output after GC and the realization of DR.
また、需給調整に関する各種情報(発電BG単価およびメリットオーダー、需要BG調整単価およびメリットオーダー、発電インバランス損益期待値、需要インバランス損益期待値、需要リソースの調整が計画通り履行されない場合のペナルティ、販売計画の調整により獲得が見込まれる利益など)を表示させることで、ユーザによる検討材料とすることができる。 In addition, various information regarding supply and demand adjustment (power generation BG unit price and merit order, demand BG adjustment unit price and merit order, power generation imbalance profit and loss expected value, demand imbalance profit and loss expected value, penalties when demand resource adjustment is not carried out as planned, profit expected to be gained by adjusting the sales plan, etc.) can be displayed to provide material for the user's consideration.
本実施形態の情報処理装置5で実行されるプログラムは、インストール可能な形式又は実行可能な形式のファイルでCD-ROM、フレキシブルディスク(FD)、CD-R、DVD(Digital Versatile Disk)等のコンピュータで読み取り可能な記録媒体に記録されて提供されるようにしてもよい。
The program executed by the
また、当該プログラムを、インターネット等のネットワークに接続されたコンピュータ上に格納し、ネットワーク経由でダウンロードさせることにより提供するように構成しても良い。また、当該プログラムをインターネット等のネットワーク経由で提供又は配布するように構成しても良い。 The program may also be configured to be stored on a computer connected to a network such as the Internet and provided by being downloaded via the network. The program may also be configured to be provided or distributed via a network such as the Internet.
また、当該プログラムを、ROM等に予め組み込んで提供するように構成してもよい。 The program may also be provided in advance in a ROM or the like.
本発明のいくつかの実施形態を説明したが、これらの実施形態は、例として提示したものであり、発明の範囲を限定することは意図していない。これら新規な実施形態は、その他の様々な形態で実施されることが可能であり、発明の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。これら実施形態やその変形は、発明の範囲や要旨に含まれるとともに、特許請求の範囲に記載された発明とその均等の範囲に含まれる。 Although several embodiments of the present invention have been described, these embodiments are presented as examples and are not intended to limit the scope of the invention. These novel embodiments can be embodied in various other forms, and various omissions, substitutions, and modifications can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope and gist of the invention, and are included in the scope of the invention and its equivalents described in the claims.
例えば、上述の実施形態では、利益に関する所定条件を満たす場合の一例として、利益を最大化する場合について説明したが、これに限定されない。ほかに、利益が所定額以上となる場合等の他の条件であってもよい。 For example, in the above embodiment, the case where profits are maximized is described as an example of a case where a predetermined condition regarding profits is satisfied, but this is not limited to this. Other conditions may also be satisfied, such as when profits are equal to or greater than a predetermined amount.
また、電力システムSに、電力系統の需給バランスを調整するアグリゲータが存在していてもよい。その場合、例えば、アグリゲータは、複数の発電BG3と複数の需要BG4をまとめた大きな単位で、電力系統の需給バランスを調整する。 The power system S may also include an aggregator that adjusts the supply and demand balance of the power grid. In that case, for example, the aggregator adjusts the supply and demand balance of the power grid in a large unit that combines multiple power generation BG3 and multiple demand BG4.
また、上述の実施形態における各処理のすべてを行う必要は必ずしもない。例えば、インセンティブの算出処理をオプション扱いにして、行わないことがあってもよい。 Furthermore, it is not necessary to perform all of the processes in the above-described embodiment. For example, the incentive calculation process may be treated as optional and not be performed.
また、目的関数は、すべての金銭の出入りを反映したものであってもよいし、あるいは、基準となる場面からの金銭の出入りの変化分だけを扱ったものでもよい。 The objective function may reflect all monetary inflows and outflows, or it may only deal with the change in monetary inflows and outflows from a baseline situation.
1…系統運用者、2…市場取引システム、3…発電BG、4…需要BG、5…情報処理装置、9…送配電事業者、31…発電事業者、41…需要家、51…記憶部、52…入力部、53…表示部、54…通信部、55…処理部、311…再エネ発電リソース、312…可調整電源リソース、411…負荷、412…蓄電池、413…再エネ発電リソース、551…取得部、552…再エネ発電量予測部、553…電力市場取引単価予測部、554…インバランス単価予測部、555…発電BG計画部、556…需要BG計画部、557…インセンティブ算出部、558…利益配分算出部、559…表示制御部、S…電力システム 1...Grid operator, 2...Market trading system, 3...Power generation BG, 4...Demand BG, 5...Information processing device, 9...Power transmission and distribution company, 31...Power generation company, 41...Consumer, 51...Memory unit, 52...Input unit, 53...Display unit, 54...Communication unit, 55...Processing unit, 311...Renewable energy power generation resource, 312...Adjustable power source resource, 411...Load, 412...Storage battery, 413...Renewable energy power generation resource, 551...Acquisition unit, 552...Renewable energy power generation amount prediction unit, 553...Power market trading unit price prediction unit, 554...Imbalance unit price prediction unit, 555...Power generation BG planning unit, 556...Demand BG planning unit, 557...Incentive calculation unit, 558...Profit allocation calculation unit, 559...Display control unit, S...Power system
Claims (8)
前記発電BGと電力取引の相対契約をしている需要BGの需要計画と調達計画を策定する需要BG計画部と、
電力取引市場での電力取引の単価である電力市場取引単価を予測して電力市場取引単価予測値を出力する電力市場取引単価予測部と、を備え
前記発電BG計画部は、前記電力市場取引単価予測値に応じて前記販売計画における前記電力取引市場への電力販売量と前記需要BGへの電力販売量を調整し、
前記需要BG計画部は、前記販売計画における前記需要BGへの電力販売量の調整に応じて前記需要計画と前記調達計画を調整する、電力需給調整装置。 A Power Generation BG (Balancing Group) Planning Department that formulates power generation plans and sales plans for the Power Generation BG;
a demand BG planning unit that formulates a demand plan and a procurement plan for a demand BG that has a bilateral contract for power trading with the power generation BG;
an electricity market trading unit price prediction unit that predicts an electricity market trading unit price, which is a unit price of electricity trading in an electricity trading market, and outputs an electricity market trading unit price prediction value; and the power generation BG planning unit adjusts the amount of electricity sold to the electricity trading market and the amount of electricity sold to the demand BG in the sales plan according to the electricity market trading unit price prediction value,
The demand BG planning unit is an electric power supply and demand adjustment device that adjusts the demand plan and the procurement plan in accordance with adjustments to the amount of electric power sold to the demand BG in the sales plan.
前記発電BGの電源の出力のコスト単価である発電BG単価のメリットオーダーに基づいて、出力を調整する前記電源の優先順位を決定し、
前記需要BG計画部は、
前記需要BGの需要リソースの前記需要計画と前記調達計画の調整に係るコスト単価である需要BG調整単価のメリットオーダーに基づいて、需要を調整する前記需要リソースの優先順位を決定し、
前記発電BG計画部は、
出力を調整する前記電源の優先順位、および、需要を調整する前記需要リソースの優先順位に基づいて、前記販売計画における前記電力取引市場への電力販売量を決定する、請求項1に記載の電力需給調整装置。 The power generation BG planning unit
determining a priority order of the power sources for adjusting the output based on a merit order of a power generation BG unit price, which is a cost unit price of the output of the power source of the power generation BG;
The demand BG planning unit
determining a priority order of the demand resources for which demand is adjusted based on a merit order of a demand BG adjustment unit price, which is a cost unit price related to the adjustment of the demand plan and the procurement plan of the demand resources of the demand BG;
The power generation BG planning unit
The power supply and demand adjustment device according to claim 1 , further comprising: a power sales amount to the power trading market in the sales plan determined based on a priority of the power source that adjusts output and a priority of the demand resource that adjusts demand.
前記電力取引市場のゲートクローズ後における前記発電BGの電源の出力の変動による発電インバランスのリスクを予測し、前記発電インバランスのリスクに基づいて損益の期待値を発電インバランス損益期待値として算出し、前記発電BG単価に前記発電インバランス損益期待値を反映し、
前記需要BG計画部は、
前記ゲートクローズ後において前記需要計画の前記需要リソースの調整が計画通り履行されないことによる需要インバランスのリスクを予測し、前記需要インバランスのリスクに基づいて損益の期待値を需要インバランス損益期待値として算出し、前記需要BG調整単価に前記需要インバランス損益期待値を反映する、請求項4に記載の電力需給調整装置。 The power generation BG planning unit
predicting a risk of power generation imbalance due to fluctuations in the output of the power source of the power generation BG after the gate of the electricity trading market is closed, calculating an expected value of profit and loss based on the risk of the power generation imbalance as a power generation imbalance profit and loss expected value, and reflecting the power generation imbalance profit and loss expected value in the power generation BG unit price;
The demand BG planning unit
5. The power supply and demand adjustment device according to claim 4, which predicts a risk of demand imbalance due to adjustment of the demand resource in the demand plan not being carried out as planned after the gate is closed, calculates an expected value of profit and loss based on the risk of the demand imbalance as a demand imbalance profit and loss expected value, and reflects the demand imbalance profit and loss expected value in the demand BG adjustment unit price.
需要BG計画部が、前記発電BGと電力取引の相対契約をしている需要BGの需要計画と調達計画を策定する需要BG計画ステップと、
電力市場取引単価予測部が、電力取引市場での電力取引の単価である電力市場取引単価を予測して電力市場取引単価予測値を出力する電力市場取引単価予測ステップと、を含み、
前記発電BG計画ステップにおいて、前記発電BG計画部は、前記電力市場取引単価予測値に応じて前記販売計画における前記電力取引市場への電力販売量と前記需要BGへの電力販売量を調整し、
前記需要BG計画ステップにおいて、前記需要BG計画部は、前記販売計画における前記需要BGへの電力販売量の調整に応じて前記需要計画と前記調達計画を調整する、電力需給調整方法。
a power generation BG planning step in which a power generation BG planning unit formulates a power generation plan and a sales plan for the power generation BG;
a demand BG planning step in which a demand BG planning unit formulates a demand plan and a procurement plan for a demand BG that has a bilateral contract for power trading with the power generation BG;
an electricity market trading unit price prediction step in which an electricity market trading unit price prediction unit predicts an electricity market trading unit price, which is a unit price of electricity trading in the electricity trading market, and outputs an electricity market trading unit price prediction value;
In the power generation BG planning step, the power generation BG planning unit adjusts the amount of power sold to the power trading market and the amount of power sold to the demand BG in the sales plan according to the power market trading unit price forecast value;
An electricity supply and demand adjustment method, in which , in the demand BG planning step, the demand BG planning unit adjusts the demand plan and the procurement plan in accordance with an adjustment of the amount of electricity sold to the demand BG in the sales plan.
発電BGの発電計画と販売計画を策定する発電BG計画ステップと、
前記発電BGと電力取引の相対契約をしている需要BGの需要計画と調達計画を策定する需要BG計画ステップと、
電力取引市場での電力取引の単価である電力市場取引単価を予測して電力市場取引単価予測値を出力する電力市場取引単価予測ステップと、を実行させるための電力需給調整方法であって、
前記発電BG計画ステップは、前記電力市場取引単価予測値に応じて前記販売計画における前記電力取引市場への電力販売量と前記需要BGへの電力販売量を調整し、
前記需要BG計画ステップは、前記販売計画における前記需要BGへの電力販売量の調整に応じて前記需要計画と前記調達計画を調整する、プログラム。 On the computer,
a power generation BG planning step of formulating a power generation plan and a sales plan for the power generation BG;
a demand BG planning step of formulating a demand plan and a procurement plan for a demand BG that has a bilateral contract for power trading with the power generation BG;
An electricity market trading unit price prediction step of predicting an electricity market trading unit price, which is a unit price of electricity trading in an electricity trading market, and outputting an electricity market trading unit price prediction value,
The power generation BG planning step adjusts an amount of power sold to the power trading market and an amount of power sold to the demand BG in the sales plan according to the power market trading unit price forecast value;
The demand BG planning step is a program that adjusts the demand plan and the procurement plan in accordance with an adjustment to the amount of electricity sold to the demand BG in the sales plan.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2021090333A JP7631103B2 (en) | 2021-05-28 | 2021-05-28 | Electricity supply and demand adjustment device, electricity supply and demand adjustment method, and program |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2021090333A JP7631103B2 (en) | 2021-05-28 | 2021-05-28 | Electricity supply and demand adjustment device, electricity supply and demand adjustment method, and program |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2022182649A JP2022182649A (en) | 2022-12-08 |
| JP7631103B2 true JP7631103B2 (en) | 2025-02-18 |
Family
ID=84328623
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2021090333A Active JP7631103B2 (en) | 2021-05-28 | 2021-05-28 | Electricity supply and demand adjustment device, electricity supply and demand adjustment method, and program |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7631103B2 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7595539B2 (en) * | 2021-08-24 | 2024-12-06 | 三菱電機株式会社 | Fee calculation device, fee calculation method, and fee calculation program |
| CN118643953B (en) * | 2024-08-15 | 2025-02-18 | 国网浙江省电力有限公司宁波供电公司 | Predictive analysis method for power grid operation index |
| CN119341002A (en) * | 2024-12-23 | 2025-01-21 | 国网江苏省电力有限公司电力科学研究院 | A distribution network balancing control method and system based on balancing responsibility subject mode |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2016110255A (en) | 2014-12-03 | 2016-06-20 | 三菱電機株式会社 | Supply-demand adjustment system |
| JP2016207070A (en) | 2015-04-27 | 2016-12-08 | 株式会社日立製作所 | Power trading support device and method, or application device |
| JP2017126183A (en) | 2016-01-13 | 2017-07-20 | 富士電機株式会社 | Power trading support device, power trading support method and program |
| JP2017182698A (en) | 2016-03-31 | 2017-10-05 | 株式会社東芝 | Power supply / demand management support system, power supply / demand management support method, and power supply / demand management support program |
| JP2021047519A (en) | 2019-09-17 | 2021-03-25 | 三菱電機株式会社 | Bid plan determination device and bid plan determination method |
-
2021
- 2021-05-28 JP JP2021090333A patent/JP7631103B2/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2016110255A (en) | 2014-12-03 | 2016-06-20 | 三菱電機株式会社 | Supply-demand adjustment system |
| JP2016207070A (en) | 2015-04-27 | 2016-12-08 | 株式会社日立製作所 | Power trading support device and method, or application device |
| JP2017126183A (en) | 2016-01-13 | 2017-07-20 | 富士電機株式会社 | Power trading support device, power trading support method and program |
| JP2017182698A (en) | 2016-03-31 | 2017-10-05 | 株式会社東芝 | Power supply / demand management support system, power supply / demand management support method, and power supply / demand management support program |
| JP2021047519A (en) | 2019-09-17 | 2021-03-25 | 三菱電機株式会社 | Bid plan determination device and bid plan determination method |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2022182649A (en) | 2022-12-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Mahmoudi et al. | A bottom-up approach for demand response aggregators’ participation in electricity markets | |
| Bichler et al. | Electricity markets in a time of change: a call to arms for business research | |
| JP7631103B2 (en) | Electricity supply and demand adjustment device, electricity supply and demand adjustment method, and program | |
| Barton et al. | Aspen-EE: An agent-based model of infrastructure interdependency | |
| JP7796563B2 (en) | Power management device, power management system, power management method, and power management program | |
| JP7403264B2 (en) | Energy management system, integrated management device and energy management method | |
| JP7391444B1 (en) | Information processing device, information processing method and program | |
| JPWO2017170018A1 (en) | Power control apparatus, power control method, and program | |
| Rashidizadeh-Kermani et al. | Evaluating the impact of bilateral contracts on the offering strategy of a price maker wind power producer | |
| Fioriti et al. | A bi-level formulation to help aggregators size Energy Communities: A proposal for virtual and physical Closed Distribution Systems | |
| JP2023074143A (en) | Electricity rate unit price determination device, controller, and electricity rate unit price determination method | |
| Britton et al. | Changing actor dynamics and emerging value propositions in the UK electricity retail market | |
| van Stiphout et al. | Benefits of a multi-energy day-ahead market | |
| Jing et al. | Trading incentive mechanism and response model for high-frequency interaction between virtual power plants and main grid under spot markets | |
| JP2023074175A (en) | Electric power procurement profit and loss estimation device and electric power procurement profit and loss estimation method | |
| JP7631102B2 (en) | Associated BG determination device, associated BG determination method, and program | |
| Rubio et al. | CERTS customer adoption model | |
| KR102840407B1 (en) | System for Transacting P2P Energy to Minimize Uncertainty Cost and Energy Cost | |
| Good et al. | Business cases | |
| Chawda et al. | Impact assessment of solar integrated residential consumers on retailer decision-making | |
| JP2023129941A (en) | Power trading support device, power trading support method, and program | |
| JP7245939B2 (en) | Transaction support device, transaction support method and program | |
| Ferris et al. | Modelling demand response in organized wholesale energy markets | |
| Balducci et al. | Technoeconomic Studies for the Goldendale Energy Storage Project: Valuation Framework Test Case Study | |
| Khodabakhsh et al. | Optimizing flexibility exchanges for congestion management: a sequential intraday flexibility market approach |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20240119 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20241022 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20241105 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20241204 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20250107 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20250205 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7631103 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |