JPS5853626B2 - How to build synthetic marine structures - Google Patents
How to build synthetic marine structuresInfo
- Publication number
- JPS5853626B2 JPS5853626B2 JP54115552A JP11555279A JPS5853626B2 JP S5853626 B2 JPS5853626 B2 JP S5853626B2 JP 54115552 A JP54115552 A JP 54115552A JP 11555279 A JP11555279 A JP 11555279A JP S5853626 B2 JPS5853626 B2 JP S5853626B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- inner frame
- bottom concrete
- internal frame
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000004567 concrete Substances 0.000 claims description 90
- 229910000831 Steel Inorganic materials 0.000 claims description 29
- 239000010959 steel Substances 0.000 claims description 29
- 238000000034 method Methods 0.000 claims description 17
- 239000002131 composite material Substances 0.000 claims description 6
- 238000009415 formwork Methods 0.000 claims description 6
- 238000010276 construction Methods 0.000 description 25
- 239000000463 material Substances 0.000 description 7
- 230000000694 effects Effects 0.000 description 3
- 238000000465 moulding Methods 0.000 description 3
- 238000005266 casting Methods 0.000 description 2
- 238000005056 compaction Methods 0.000 description 2
- 238000010926 purge Methods 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Revetment (AREA)
Description
【発明の詳細な説明】
本発明は、鋼とコンクリートとが併用されている合成海
洋構造物を建造する建造方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for constructing composite marine structures using a combination of steel and concrete.
たとえば化学プラント、発電プラントなどの各種プラン
ト施設を搭載する浮遊式海洋構造物として知られるパー
ジにあっては、その側部および底部がコンクリート製の
外板により、さらにその上部は鋼製甲板で覆われており
、またその内部空間には補強用としての鋼製の内部フレ
ームが適宜配置され、いわゆる鋼とコンクリートとの合
成構造物となっている。For example, the Purge, which is known as a floating offshore structure that houses various plant facilities such as chemical plants and power generation plants, has concrete outer panels on the sides and bottom, and a steel deck on the top. In addition, a steel internal frame for reinforcement is appropriately placed in the internal space, making it a so-called composite structure of steel and concrete.
したがって、このような合成海洋構造物を建造する場合
には、鋼製の内部フレームを所望の状態で組立てて配置
させた後その周囲に順次コンクリートを打設してコンク
リート製の外板を成形するわけであるが、この場合、こ
の種の構造物自体の大きさがかなりのものであることか
ら、そのコンクリート製の外板は通常ドックあるいは船
台などにおいて場所打ち工法により施工される場合が多
く、このために、その建造時の作業が面倒で、また工事
期間が長期にわたり、これにより工事費用が嵩むもので
あり、しかもこの種の構造物の外板において必要な強度
および水密性などを得ることが難しいという不具合があ
った。Therefore, when constructing such a composite marine structure, the steel inner frame is assembled and arranged in the desired condition, and then concrete is successively poured around it to form a concrete outer panel. However, in this case, because the size of this type of structure itself is considerable, the concrete shell is usually constructed using the cast-in-place method at a dock or ship's slipway. For this reason, the construction work is troublesome and the construction period is long, which increases the construction cost.Moreover, it is difficult to obtain the necessary strength and watertightness for the outer panel of this type of structure. There was a problem that it was difficult to
すなわち、前記コンクリート製の外板を構成する底部コ
ンクリートを成形する場合には、前述した大がかりな鋼
製の内部フレームを例等かの建造用支持治具を用いてそ
の成形用型枠上に吊下げ、内部フレームの下側にコンク
リート打設空間を確保する必要があり、その作業が面倒
であるばかりでなく、その施工能率が悪く、また内部フ
レーム等の重量から支持治具がかなり犬がかりなものと
なり、さらにその着脱が繁雑で、しかもその工事費用が
嵩むという不具合があった。That is, when forming the bottom concrete that constitutes the concrete outer panel, the large-scale steel internal frame described above is suspended on the forming form using some construction support jig. It is necessary to lower the inner frame and secure a space for concrete pouring under the inner frame, which is not only troublesome, but also has poor construction efficiency, and the weight of the inner frame requires a considerable amount of work to support the jig. Furthermore, there were problems in that it was complicated to put on and take off, and the construction costs were high.
そして、このような支持治具を用いる方法では、海洋構
造物が大型化すると、その内部フレーム全体の大きさ、
重量等の問題から建造することがほとんど不可能であっ
た。In addition, with the method of using such a support jig, as the marine structure becomes larger, the overall size of the internal frame,
It was almost impossible to construct due to weight and other issues.
また、前述したコンクリート製の外板を場所打ち工法に
より施工した場合に、その打設面積等の問題から全面に
わたってコンクリートを均質なものとすることが難しく
、これは垂直に立ち上がった側部コンクリートを成形す
る場合に、その打設面積に比べて打設高さが十分に高い
ことから、特に顕著なもので、さらに底部コンクリート
を成形する場合には内部フレームおよび支持治具が邪魔
になり、その作業性の点から仕上りの面精度が悪く、均
質なコンクリートを得ることが難しいものであった。Furthermore, when constructing the aforementioned concrete exterior panels using the cast-in-place method, it is difficult to make the concrete homogeneous over the entire surface due to issues such as the pouring area. This is particularly noticeable when casting, since the pouring height is sufficiently high compared to the pouring area.Furthermore, when forming the bottom concrete, the internal frame and supporting jig get in the way. In terms of workability, the finished surface accuracy was poor and it was difficult to obtain homogeneous concrete.
そして、上述した場所打ちによる外板の成形作業は構造
物の大きさ等により長期間にわたってしまうもので、こ
れは側部コンクリートを成形する場合に特に顕著で、こ
れによりその期間中ドック、船台等を全面的に占有し、
工事費用が嵩むばかりでなく、他の工事に支障をきたす
等の不具合があった。Furthermore, the above-mentioned cast-in-place exterior panel forming work takes a long time depending on the size of the structure, and this is especially noticeable when forming the side concrete. fully occupy the
Not only did the construction cost increase, but there were also problems such as interfering with other construction work.
さらに、前述したコンクリート製の外板はその強度上の
問題からプレストレスコンクリートとすることが一般的
であり、上述した従来の建造方法であると、プレストレ
スを導入する際には構造物全体が結合されていて荷重に
対して鋼とコンクリートとの合成構造物として抵抗し、
プレストレスが少なからず内部フレームとして配設され
ている鋼製部材側へも作用することになり、これにより
内部フレームとして配設されている鋼製部材に余分な応
力として特に有害な圧縮応力が導入され、変形等を生じ
る危険性があり、またコンクリート製の外板に必要最小
限なプレストレス導入用のPC鋼材では内部フレーム側
の存在によりコンクリート製外板に対し所望のプレスト
レスを与えることができないという欠点があった。Furthermore, the concrete exterior panels mentioned above are generally made of prestressed concrete due to their strength issues, and with the conventional construction methods mentioned above, when prestressing is introduced, the entire structure is It is connected and resists loads as a composite structure of steel and concrete,
A considerable amount of prestress also acts on the steel members installed as the internal frame, and this introduces particularly harmful compressive stress as extra stress into the steel members installed as the internal frame. In addition, with PC steel materials for introducing the minimum necessary prestress to the concrete outer panel, it is difficult to apply the desired prestress to the concrete outer panel due to the presence of the inner frame. The drawback was that it couldn't be done.
そして、これを解消するには上述した鋼製部材である内
部フレームの存在を考慮してPC鋼材を多く付設する必
要があり、そのロスは大きなものであった。In order to solve this problem, it is necessary to add a large amount of prestressing steel material in consideration of the presence of the internal frame, which is a steel member mentioned above, resulting in a large loss.
また、このような合成海洋構造物としては例が少なく、
さらに本格的な大型構造物は皆無に等しいもので、在来
の工法をそのまま適用することは無理があり、この種の
合成海洋構造物に対する新たな建造方法の出現が要望さ
れている。In addition, there are few examples of such synthetic marine structures,
Furthermore, since there are almost no full-scale large-scale structures, it is impossible to apply conventional construction methods as they are, and there is a need for a new construction method for this type of synthetic marine structure.
本発明は上述した事情に鑑みなされたものであり、合成
海洋構造物における鋼製の内部フレームの下側部のみを
、底部コンクリート成形用の型枠上に一定間隔おいて支
持し、その下方にコンクリートを打設して底部コンクリ
ートを成形する一方、側部コンクリートを複数のプレキ
ャスト部材として予め分割成形し、これらを底部コンク
リートとともに一体化させ、さらにこのプレキャスト部
材に組込まれている内部フレームの外側部を前記内部フ
レームの下側部に連結し、その状態で側部および底部コ
ンクリートにプレストレスを導入し、しかる後残りの内
部フレームをその外側部および下側部に組合わせるよう
に構成することにより、側部および底部コンクリートの
成形作業が簡単で、しかも大部分の内部フレームにはプ
レストレスが導入されず、所望の強度を得ることが簡単
となり、さらに構造物全体の建造も容易で、これにより
その工事期間を短縮し、しかも工事費用を低減すること
ができる合成海洋構造物の建造方法を提供するO
以下、本1発明を図面に示した実施例を用いて詳細に説
明する。The present invention has been made in view of the above-mentioned circumstances, and includes a structure in which only the lower part of the steel internal frame of a synthetic marine structure is supported at regular intervals on the formwork for forming the bottom concrete, and the lower part thereof is While pouring concrete and forming the bottom concrete, the side concrete is pre-formed separately as multiple precast members, and these are integrated with the bottom concrete, and the outer part of the internal frame incorporated in this precast member is by connecting the inner frame to the lower part of the inner frame, introducing prestress into the side and bottom concrete, and then assembling the remaining inner frame to the outer and lower parts thereof. , the forming operations of the side and bottom concrete are simple, and most of the internal frames do not introduce prestressing, making it easy to obtain the desired strength and also the construction of the entire structure. To provide a method for constructing a synthetic marine structure that can shorten the construction period and reduce the construction cost.Hereinafter, the first invention will be explained in detail using embodiments shown in the drawings.
第1図は本発明に係る建造方法を適用する合成海洋構造
物の一実施例を示し、同図において、この合成海洋構造
物1は、たとえばパージなどのような全体略直方体状を
なす大型構造物であって、その上面部には鋼製の甲板2
が、またその側面部および底面部にはコンクリ−ト製の
外板3として4面からなる側部コンクリート4と底部コ
ンクリート5がそれぞれ設けられ、またこれらの甲板2
と外板3とによって被包される内部空間には上述した甲
板2、外板3と外力に対して合成して作用する鋼製の隔
壁、肋材等からなる補強用の内部フレーム6が適宜配置
されている。FIG. 1 shows an embodiment of a synthetic marine structure to which the construction method according to the present invention is applied. It has a steel deck 2 on its upper surface.
However, a side concrete 4 and a bottom concrete 5 each consisting of four sides are provided as a concrete outer plate 3 on the side and bottom parts, and these deck 2
In the internal space covered by the above-mentioned deck 2 and the outer panel 3, a reinforcing internal frame 6 consisting of a steel bulkhead, ribs, etc., which acts in combination with the above-mentioned deck 2, outer panel 3 and external force, is installed as appropriate. It is located.
さて、本発明によれば、上述した合成海洋構造物1を建
造する場合に、底部コンクリート5はドックなどにおい
て場所打ち工法により施工するが、鋼製甲板2と同じく
鋼製の内部フレーム6は予め別の場所で適宜ブロック化
され、さらに搬送されてドック内に準備され、また側部
コンクリート4は側部プレキャスト部材としてブロック
ヤードと呼ばれる他の場所で予め形状、大きさ等をそろ
えて多数成形され、これも同様にドック内に搬送されて
準備される。Now, according to the present invention, when constructing the above-mentioned synthetic marine structure 1, the bottom concrete 5 is constructed by a cast-in-place method at a dock or the like, but the steel internal frame 6 is pre-constructed like the steel deck 2. The side concrete 4 is suitably made into blocks at another location, further transported and prepared in the dock, and the side concrete 4 is formed in large numbers with the same shape, size, etc. in advance as side precast members at another location called a block yard. , which are also transported to the dock and prepared.
そして、上述したようにブロック化された甲板2、内部
フレーム6および側部コンクリート4を順次組合せなが
ら底部コンクリート5を成形するもので、第2図ないし
第6図を用いてその建造方法を以下に詳述する。Then, the bottom concrete 5 is formed by sequentially combining the deck 2, internal frame 6, and side concrete 4 that have been made into blocks as described above.The construction method is described below using Figures 2 to 6. Explain in detail.
第2図および第6図〔I〕は内部フレーム6の下側に底
部コンクリート成形用の打設空間7を確保する場合を示
し、ここで注目すべき点は内部フレーム6全体ではなく
その下側部8のみを成形用型枠9上に一定間隔おいて支
持させることである。Fig. 2 and Fig. 6 [I] show the case where a pouring space 7 for bottom concrete molding is secured under the internal frame 6. What should be noted here is not the entire internal frame 6, but the underside of the internal frame 6. Only the portions 8 are supported on the molding frame 9 at regular intervals.
すなわち、内部フレーム6の下側部8を構成する格子ブ
ロック8aを、型枠9上に並べられた支持台10上にそ
の中央のものから順次配置させ、それぞれの接合部を溶
接して連結しながら、第3図および第6図(IDに示す
ように、その下側の打設空間7にコンクリートを順次打
設し、これに対応する底部コンクリート5を成形する。That is, the lattice blocks 8a constituting the lower part 8 of the internal frame 6 are sequentially arranged on the support stands 10 arranged on the formwork 9 starting from the center one, and the respective joints are welded and connected. Meanwhile, as shown in FIGS. 3 and 6 (ID), concrete is successively poured into the pouring space 7 on the lower side, and the corresponding bottom concrete 5 is formed.
このとき、支持台10は支持する格子ブロック8aの重
量が十分に小さいことから簡単な構造のものでよく、さ
らにこれに高さ調整機能を持たせるようにしてもよい。At this time, the support stand 10 may have a simple structure since the weight of the lattice block 8a to be supported is sufficiently small, and may also be provided with a height adjustment function.
また、この支持台10は打設されたコンクリートが硬化
して所望の強度を得た後順次取り外される。Further, the support stand 10 is sequentially removed after the poured concrete hardens and obtains the desired strength.
なお、上述した内部フレーム6の下側部8の下方にコン
クリートを打設する作業は下側部8の形状、高さ等の理
由から障害とならずに簡単に行なえるもので、またコン
クリートに対し締め固めなども容易に行なえ、その仕上
げの面精度を大幅に向上させることができる。Note that the work of pouring concrete below the lower part 8 of the internal frame 6 described above can be easily performed without causing any obstruction due to the shape, height, etc. of the lower part 8. On the other hand, compaction can be easily performed, and the surface accuracy of the finished product can be greatly improved.
第4図a、bは側部コンクリート4を成形するためにこ
れを複数に分割成形してなる側部プレキャスト部材11
を示し、この側部プレキャスト材11の下側には底部コ
ンクリート5の一部を構成する屈折部11aが一体に形
成されて自立できる構成とされ、またその内側面には前
記内部フレーム6の外側部12が、その上端部には甲板
2の外側部2aが予め接合して設けられている。FIGS. 4a and 4b show a side precast member 11 formed by dividing and molding this into a plurality of parts in order to form the side concrete 4.
A bending part 11a, which constitutes a part of the bottom concrete 5, is integrally formed on the lower side of the side precast material 11 so that it can stand on its own. The outer portion 2a of the deck 2 is connected to the upper end portion of the portion 12 in advance.
なお、この側部プレキャスト部材11は場所打ちされる
側部コンクリートよりその均質性が良く、また強度も十
分に期待できるものである。The side precast member 11 has better homogeneity than cast-in-place side concrete, and can be expected to have sufficient strength.
また、側部プレキャスト部材11の内側に予め内部フレ
ーム6の外側部12と甲板2の外側部2aを接合させて
いるため、これに残りの内部フレーム6および甲板2を
溶接して組立てる際にその熱影響がコンクリートに及ぶ
ことはなく、その品質を向上させることができる。In addition, since the outer part 12 of the inner frame 6 and the outer part 2a of the deck 2 are joined to the inside of the side precast member 11 in advance, when the remaining inner frame 6 and deck 2 are welded and assembled, Concrete is not affected by heat and its quality can be improved.
この場合、側部プレキャスト部材11の成形および組立
て作業を前述した内部フレーム6の下側部8およびその
下側の底部コンクリート5の成形作業と同時に行なうこ
とにより工事期間の短縮化を図ることができる。In this case, the construction period can be shortened by performing the forming and assembling work of the side precast member 11 at the same time as the forming work of the lower part 8 of the internal frame 6 and the bottom concrete 5 below it. .
上述したように準備されている側部プレキャスト部材1
1は次のようにして内部フレーム6の下側部8および底
部コンクリート5と一体化される。Side precast part 1 prepared as described above
1 is integrated with the lower part 8 of the internal frame 6 and the bottom concrete 5 in the following manner.
すなわち、内部フレーム6の下側部8のうち、その側方
に配置される格子ブロック8bを支持台10上に支持さ
せ(第6図CI〕参照)、さらにその側方に前記側部プ
レキャスト部材11を所定間隙おいて順次立設させ、格
子ブロック8bと側部プレキャスト部材11側の内部フ
レームの外側部12との接合部を溶接して接合させ、そ
の下側の支持台10を取外す(第6図(IV)参照〕。That is, the lattice block 8b disposed on the side of the lower part 8 of the internal frame 6 is supported on the support stand 10 (see FIG. 6 CI), and the side precast member is further placed on the side thereof. 11 are erected one after another at predetermined intervals, the joints between the lattice blocks 8b and the outer part 12 of the internal frame on the side precast member 11 side are welded together, and the support base 10 on the lower side is removed. See Figure 6 (IV)].
そして、その状態のまま、各側部プレキャスト部材11
間の空隙部にコンクリートを打設して側部コンクリート
4を成形するとともに、前記格子ブロック8bの下側に
打設空間13にコンクリートを打設して中央側の格子ブ
ロック8aに対応する底部コンクリート5を側部プレキ
ャスト部材11の屈折部11aを順次一体化させる。Then, in that state, each side precast member 11
Concrete is cast in the gaps between the blocks to form side concrete 4, and concrete is cast in the casting spaces 13 below the lattice blocks 8b to form bottom concrete corresponding to the central lattice blocks 8a. 5 and the bent portions 11a of the side precast members 11 are successively integrated.
この状態は第5図および第6図〔■〕に示されている。This state is shown in FIGS. 5 and 6 [■].
そして、本発明では、上述した方法により構造物全体に
わたって側部および底部コンクリート45を形成し、コ
ンクリートが硬化して所望の強度がでた段階で側部およ
び底部コンクリート45にプレストレスを導入している
。Then, in the present invention, the side and bottom concrete 45 is formed over the entire structure by the method described above, and when the concrete has hardened and achieved the desired strength, prestress is introduced into the side and bottom concrete 45. There is.
このとき、側部および底部コンクリート4,5にはわず
かに内部フレーム6を構成する下側部8と外側部12の
みが接合されているだけであり、プレストレスはきわめ
て効果的にコンクリート内に導入されることになり、希
望するプレストレスによる応力度を得ることが不必要に
多くのPC鋼材を使うことなしに可能で、また内部フレ
ーム6の大部分には不必要な応力が加わることはない。At this time, only the lower part 8 and the outer part 12, which constitute the inner frame 6, are joined to the side and bottom concrete 4, 5, and the prestress is introduced into the concrete very effectively. Therefore, it is possible to obtain the desired degree of prestressing stress without using an unnecessarily large amount of prestressing steel, and unnecessary stress is not applied to the majority of the internal frame 6. .
ここで、上述した側部および底部コンクリート4.5に
対しプレストレスを導入するにあたっての具体的手段と
しては、ポストテンショニング法と呼ばれている従来上
として橋梁等において採用されているような周知のプレ
ストレス導入工法を用いるとよい。Here, as a specific means for introducing prestress to the side and bottom concrete 4.5 mentioned above, a well-known method called the post-tensioning method, which has been conventionally adopted in bridges, etc. It is recommended to use the prestress introduction method.
この工法を簡単に説明すると、シースと称する薄板鋼管
を予めコンクリート中に埋め込んでおき、コンクリート
硬化後その鋼管にPC鋼材を挿入しさらにこのPC鋼材
に張力を与えて支圧板を介して反作用としてコンクリー
トに圧縮力を加える方法である。To briefly explain this method, a thin steel pipe called a sheath is embedded in concrete in advance, and after the concrete hardens, a prestressing steel material is inserted into the steel pipe, and tension is applied to the prestressed steel material, which acts as a reaction force on the concrete through a bearing plate. This method applies compressive force to the
そして、上述したプレストレス導入後に、第6図CVI
)に示すように、残りの内部フレーム6aをその下側部
8および外側部12に順次ブロックごとに溶接して内部
フレーム6を組立て、さらに残りの甲板2を固着させる
ことにより第1図に示す合成海洋構造物1が完成するも
のである。Then, after introducing the prestress mentioned above, the CVI in Figure 6
), the remaining internal frame 6a is assembled by sequentially welding the remaining internal frame 6a to its lower part 8 and external part 12 block by block, and the remaining deck 2 is further fixed, as shown in FIG. The synthetic marine structure 1 is completed.
上述したような本発明に係る合成海洋構造物の建造方法
では、底部コンクリート5を成形する際に内部フレーム
6の下側部8のみを型枠9上に支持する構成であるため
にその施工がきわめて簡単に行なえるもので、またこれ
により側部および底部コンクリート4,5にプレストレ
スを導入する場合に内部フレーム6の大部分に不用な応
力が全く加わらず、所望の強度を側部および底部コンク
リート45に与えることができるという優れた効果があ
る。In the method for constructing a synthetic marine structure according to the present invention as described above, since only the lower part 8 of the internal frame 6 is supported on the formwork 9 when forming the bottom concrete 5, the construction is difficult. This is extremely easy to carry out, and this ensures that when introducing prestress into the side and bottom concrete 4, 5, no unnecessary stress is applied to the majority of the internal frame 6, and the desired strength is maintained in the side and bottom concrete. It has an excellent effect in that it can be applied to concrete 45.
なお、前述した実施例では、本発明に係る建造方法を、
たとえばパージなどのような直方体状をなす合成海洋構
造物に適用した場合を説明したが、これに限定されるこ
とはなく、種々の形状をもった構造物に応用できるもの
で、その形状に合わせて適宜変更することができる。In addition, in the above-mentioned embodiment, the construction method according to the present invention is
For example, we have explained the case where it is applied to a rectangular parallelepiped-shaped synthetic marine structure such as a purge, but it is not limited to this, and can be applied to structures with various shapes, and it can be applied to structures according to the shape. It can be changed as appropriate.
以上説明したように、本発明に係る合成海洋構造物の建
造方法では、底部コンクリートを成形する場合に、これ
に接合される内部フレームの下側部のみを型枠上に並べ
られた支持台により一定間隔おいて支持し、その状態で
コンクリートを順次打設するようにしたので、従来内部
フレーム全体を支持するために用いられていた大規模な
支持治具の必要がなく簡易な支持台でよく、さらにその
成形作業が簡単であるばかりでなく、コンクリートの締
め固めなども容易で、底部コンクリートの均質性をも期
待できる等の優れた効果がある。As explained above, in the method for constructing a synthetic marine structure according to the present invention, when forming the bottom concrete, only the lower part of the internal frame to be joined to this is supported by supports arranged on the formwork. Since the internal frame is supported at regular intervals and concrete is poured in sequence in that state, there is no need for large-scale support jigs that were conventionally used to support the entire internal frame, and a simple support stand can be used instead. Moreover, not only the forming operation is simple, but also the compaction of concrete is easy, and the homogeneity of the bottom concrete can be expected.
また、本発明によれば、側部コンクリートを複数の側部
プレキャスト部材により構成し、しかもこの側部プレキ
ャスト部材に内部フレームの外側部および底部コンクリ
ートの一部を一体に設けるようにしたので、側部コンク
リートおよびこれと底部コンクリートとの一体化が容易
に行なえ、これにより構造物全体の建造が簡単となり、
ドックなどにおける工事期間を短縮し、その工事費用を
大幅に削減できる等の利点がある。Further, according to the present invention, the side concrete is constituted by a plurality of side precast members, and the outer part of the internal frame and a part of the bottom concrete are integrally provided on the side precast members. It is easy to integrate the bottom concrete and the bottom concrete, which simplifies the construction of the entire structure.
It has the advantage of shortening the construction period for docks, etc., and significantly reducing construction costs.
さらに、本発明による建造方法では、側部および底部コ
ンクリートに内部フレームの外側部と下側部のみを接合
した状態でプレストレスを導入する構成としたので、従
来のようにプレストレスが内部フレーム側に導入されて
悪影響を及ぼすといった不具合がなく、極めて効果的に
コンクリートに導入されて所望の強度を得ることが容易
となる等の効果がある。Furthermore, in the construction method according to the present invention, prestress is introduced with only the outer and lower parts of the internal frame joined to the side and bottom concrete, so prestress is applied to the internal frame side as in the conventional method. There are no problems such as adverse effects caused by the introduction into the concrete, and there are effects such as the fact that it is introduced into the concrete very effectively and it becomes easy to obtain the desired strength.
なお、本発明によれば、従来のように鋼製甲板、鋼製隔
壁などを含む内部フレーム全体が組立てられて側部およ
び底部コンクリートに接合されている状態でプレストレ
スを導入する場合に比べ、この合成構造物の断面構成お
よび外力条件が同じであっても、プレストレスを内部フ
レーム全体にわたって作用させることは不要で、効率よ
くコンクリート製外板に導入し得るため、それに必要な
分だけのプレストレス導入用のPC鋼材量しか必要とせ
ず、その結果PC鋼材量を削減できるという利点がある
。According to the present invention, compared to the conventional case where prestress is introduced in a state where the entire internal frame including the steel deck, steel bulkhead, etc. is assembled and joined to the side and bottom concrete, Even if the cross-sectional configuration and external force conditions of this composite structure are the same, the prestress does not need to act over the entire internal frame, but can be efficiently introduced into the concrete skin, allowing only the necessary prestress to be applied. There is an advantage that only the amount of PC steel material for introducing stress is required, and as a result, the amount of PC steel material can be reduced.
図は本発明に係る合成海洋構造物の建造方法の一実施例
を示し、第1図はこれを実施する合成海洋構造物の概略
を示す斜視図、第2図、第3図および第5図はその建造
順序を説明するための概略斜視図、第4図a、bはこれ
に用いる側部プレキャスト部材を説明するための斜視図
、第6図はその建造方法を説明するための横断図である
。
1・・・・・・合成海洋構造物、2・・・・・・鋼製甲
板、3・・・・・・コンクリート製外板、4・・・・・
・側部コンクリート、5・・・・・・底部コンクリート
、6・・・・・・鋼製内部フレーム、7・・・・・・打
設空間、8・・・・・・下側部、9・・・・・・型枠、
10・・・・・・支持台、11・・・・・・側部プレキ
ャスト部材、12・・・・・・外側部、13・・・・・
・打設空間。The figures show an embodiment of the method for constructing a synthetic marine structure according to the present invention, and FIG. 1 is a perspective view schematically showing a synthetic marine structure for carrying out the method, and FIGS. 2, 3, and 5. 4 is a schematic perspective view for explaining the construction order, FIGS. 4a and 4b are perspective views for explaining the side precast members used for this, and FIG. be. 1...Synthetic marine structure, 2...Steel deck, 3...Concrete outer plate, 4...
・Side concrete, 5...Bottom concrete, 6...Steel internal frame, 7...Pouring space, 8...Lower side part, 9・・・・・・Formwork,
10...Support stand, 11...Side precast member, 12...Outside part, 13...
・Pouring space.
Claims (1)
の内部フレームを適宜配置させてなる合成海洋構造物を
建造する方法であって、前記内部フレームを構成する下
側部のみを、前記外板を構成する底部コンクリート成形
用の型枠上に一定間隔おいて支持する支持台上で順次組
合わせて配置させ、かつその下側の打設空間にコンクリ
ートを順次打設して底部コンクリートを成形する工程と
、前記外板を構成する側部コンクリートの一部とこれに
対応する内部フレームの外側部および底部コンクリート
の一部とを一体的に組合わせてなる側部プレキャスト部
材を、前記内部フレームの下側部の側方に所定間隙おい
て立設しかつこれら各側部プレキャスト部材間の空隙部
にコンクリートを打設して側部コンクリートを一体化さ
せるとともに、各側部プレキャスト部材における内部フ
レームの外側部と底部コンクリートの一部とをそれぞれ
前記内部フレームの下側部とその下側の底部コンクリー
トとに一体化させる工程と、前記内部フレームの外側部
および下側部のみが接合されている側部および底部コン
クリートにプレストレスを導入する工程と、前記側部お
よび底部コンクリートに接合されている内部フレームの
外側部および下側部に残りの内部フレームを順次組合わ
せて連結する工程とから構成したことを特徴とする合成
海洋構造物の建造方法。1. A method of constructing a composite marine structure having a concrete outer panel and a steel inner frame appropriately arranged inside the structure, wherein only the lower part constituting the inner frame is The bottom concrete is formed by sequentially assembling and arranging them on support stands supported at regular intervals on the formwork for forming the bottom concrete that constitutes the outer panel, and pouring concrete in the pouring space below the bottom concrete. A side precast member formed by integrally combining a part of the side concrete constituting the outer panel and a corresponding part of the outer part and bottom concrete of the inner frame is formed by forming the inner frame. It is erected on the side of the lower part of the frame with a predetermined gap, and concrete is poured into the gap between these side precast members to integrate the side concrete, and the inside of each side precast member is a step of integrating the outer part of the frame and a part of the bottom concrete into the lower part of the inner frame and the bottom concrete below the inner frame, respectively; and the step of joining only the outer part and the lower part of the inner frame. a step of introducing prestress into the side and bottom concrete, and a step of sequentially assembling and connecting the remaining inner frame to the outer and lower parts of the inner frame joined to the side and bottom concrete; A method of constructing a synthetic marine structure characterized by comprising:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP54115552A JPS5853626B2 (en) | 1979-09-08 | 1979-09-08 | How to build synthetic marine structures |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP54115552A JPS5853626B2 (en) | 1979-09-08 | 1979-09-08 | How to build synthetic marine structures |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5639985A JPS5639985A (en) | 1981-04-15 |
| JPS5853626B2 true JPS5853626B2 (en) | 1983-11-30 |
Family
ID=14665360
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP54115552A Expired JPS5853626B2 (en) | 1979-09-08 | 1979-09-08 | How to build synthetic marine structures |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5853626B2 (en) |
-
1979
- 1979-09-08 JP JP54115552A patent/JPS5853626B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5639985A (en) | 1981-04-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210658422U (en) | A kind of prefabricated substation framework foundation | |
| JPS6145042A (en) | Mold frame for casting concrete | |
| JPS5853626B2 (en) | How to build synthetic marine structures | |
| JP3973577B2 (en) | Bridge, bridge structure and bridge construction method | |
| JPH0434161A (en) | Centrifugally molded hollow pc concrete column and column construction method | |
| JPH10183533A (en) | Bridge girder, bridge girder component, and work execution method for bridge girder | |
| JPS5833155B2 (en) | How to build offshore structures | |
| CN222730924U (en) | Steel reinforcement cage with hidden column and prefabricated reinforced concrete superposed wall member thereof | |
| JPS596495A (en) | Turbine support frame | |
| JPH08184099A (en) | Reinforced concrete structures of beams and columns | |
| JPH09235912A (en) | Concrete columnar structure and its construction method | |
| JPS61290137A (en) | Construction of columnar pillar | |
| JPH0546561Y2 (en) | ||
| JPH062359A (en) | Form for semi-pc beam | |
| JPH0197744A (en) | Shear reinforcement structure of shear head part in flat plate structure building | |
| JPH0718785A (en) | Hollow concrete column and manufacturing method thereof | |
| JPS6043547A (en) | Mold frame and reinforcement iron integral assembling and constructing method | |
| JPS5851099B2 (en) | Pre-cast concrete | |
| JPH0746152B2 (en) | Structure of containment vessel wall | |
| JP2002013109A (en) | Floor slab, floor slab structural body and construction method of floor slab | |
| JPH0765339B2 (en) | Concrete pillar construction method | |
| JPS645134B2 (en) | ||
| JP2944448B2 (en) | Steel plate concrete composite structure unit | |
| JPH0791862B2 (en) | Concrete column / beam structure and its construction method | |
| JPH01226981A (en) | Heat-insulating floor formwork and construction of heat-insulating floor therewith |