JPS5919226B2 - How to build a tank - Google Patents
How to build a tankInfo
- Publication number
- JPS5919226B2 JPS5919226B2 JP8849079A JP8849079A JPS5919226B2 JP S5919226 B2 JPS5919226 B2 JP S5919226B2 JP 8849079 A JP8849079 A JP 8849079A JP 8849079 A JP8849079 A JP 8849079A JP S5919226 B2 JPS5919226 B2 JP S5919226B2
- Authority
- JP
- Japan
- Prior art keywords
- side plate
- welding
- tank
- circumferential direction
- side plates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000003466 welding Methods 0.000 claims description 39
- 238000000034 method Methods 0.000 claims description 6
- 238000004519 manufacturing process Methods 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 5
- 238000007689 inspection Methods 0.000 description 5
- 230000001066 destructive effect Effects 0.000 description 3
- 230000001681 protective effect Effects 0.000 description 3
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 210000000078 claw Anatomy 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000003028 elevating effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】
本発明はジヤツキアップ工法を採用したタンクの建設方
法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing a tank using the jack-up construction method.
ジヤツキアップ工法は、
0タンクが半径方向に比較して極端に高い場合でも、高
所作業がないため、作業を安全に且つ容易に行なえる。With the jack-up method, even if the zero tank is extremely high compared to the radial direction, the work can be done safely and easily because there is no need to work at heights.
0クレーンなど揚重設備が小さいもので済むことから、
タンク建設現場・の敷地、通路が限られている場合でも
作業を行なえる。Since only small lifting equipment such as 0 crane is required,
Work can be carried out even when tank construction sites/sites and passageways are limited.
0全作業の約70%がタンク内作業となるため、天候の
影響を受けにくく、悪天候でも作業し得る。Approximately 70% of all work is done inside the tank, so it is less affected by the weather and can be done even in bad weather.
0側板などへの治具の取付けが少なく、外観がきれいで
ある。There are fewer jigs to attach to the 0 side plate, etc., and the appearance is beautiful.
0タンクのレベル、真円度を保ち易い。0 Easy to maintain tank level and roundness.
などの利点がある。There are advantages such as
このようなジヤツキアップ工法で従来では、第1図に示
すように、底板1上に一段目の側板2を取付け、この側
板2の上方にジヤツキアップ空間3を形成して新しい側
板を挿入可能とし、挿入した新しい側板間の縦溶接と、
この新しい側板と前工程でジヤツキアップしてなる側板
4との横溶接とを行なっている。Conventionally, in this jack-up method, as shown in Fig. 1, the first side plate 2 is attached on the bottom plate 1, and a jack-up space 3 is formed above this side plate 2 to allow insertion of a new side plate. new vertical welding between the side plates,
Lateral welding is performed between this new side plate and the side plate 4 which was jacked up in the previous process.
ところで側板の巾は例えば250cmもあり、したがっ
て横溶接は約5mの位置で行なわれている。By the way, the width of the side plate is, for example, 250 cm, so the lateral welding is performed at a position of about 5 m.
このことから、既設タンクまたはその他の設備に隣接し
た場所でタンクの建設を行なう場合には、溶接による引
火防止用の防護壁5が周囲に必要であり、またこの防護
壁5は高い(5m以上)ものとなる。For this reason, when constructing a tank adjacent to an existing tank or other equipment, a protective wall 5 to prevent ignition by welding is required around the area, and this protective wall 5 must be high (5 m or more). ) to become something.
さらに新しい側板の挿入や溶接は周方向で行なわれるこ
とから、例えばタンクの周りでレッカーを走行させなけ
ればならず作業範囲が広くなる。Furthermore, since the insertion and welding of a new side plate is performed in the circumferential direction, for example, a tow truck must be driven around the tank, increasing the work area.
本発明は上記問題点を解決し得るタンクの建設方法を提
供するもので、以下その一実施例を第2図〜第11図に
基づいて説明する。The present invention provides a tank construction method that can solve the above-mentioned problems, and one embodiment thereof will be described below with reference to FIGS. 2 to 11.
囚、先ず第2図に示すように、打設された基礎10の確
認が行なわれる。First, as shown in FIG. 2, the poured foundation 10 is checked.
次いで底板11の位置決め、敷き並べ、スケッチ部また
はアニユラ−外端の溶接、非破壊検査が行なわれる。Next, the bottom plate 11 is positioned, laid out, the sketched portion or the outer end of the annular part is welded, and a non-destructive inspection is performed.
その後に、仮想線で示すように側板支持治具12の取付
けが行なわれる。Thereafter, the side plate support jig 12 is attached as shown by the imaginary line.
この側板支持治具12は周方向において適当間隔置きに
複数個取付けられる。A plurality of side plate support jigs 12 are attached at appropriate intervals in the circumferential direction.
ノ)、前記側板支持治具12は第10図、第11図に示
すように、底板11に取付は可能な基板13と、この基
板13から立設した一対の支柱14A、14Bと、これ
ら支柱14A、14B間に固定受は面15aを形成する
架台15と、この架台15に取付けられ且つ滑動受は面
16aを形成するローラ16と、両受は面15a。(c) As shown in FIGS. 10 and 11, the side plate support jig 12 includes a base plate 13 that can be attached to the bottom plate 11, a pair of support columns 14A and 14B erected from the base plate 13, and these support columns. Between 14A and 14B, there is a pedestal 15 which forms a surface 15a as a fixed holder, a roller 16 attached to this pedestal 15 and which forms a surface 16a as a sliding holder, and a surface 15a as both holders.
16aに側板を案内すべく支柱14A、14Bと架台1
5との間に設けられたガイド体17A。Supports 14A, 14B and frame 1 are installed to guide the side plate to 16a.
A guide body 17A provided between the guide body 5 and the guide body 17A.
17Bとからなり、前記両受は面15a、16aは支柱
14A、14B間に並設されると共に、その並設方向と
は直交方向が滑動方向になり、また固定受は面15aを
内側にして底板11に取付けられる。17B, the surfaces 15a and 16a of both supports are arranged side by side between the pillars 14A and 14B, and the sliding direction is orthogonal to the direction in which they are arranged side by side, and the fixed support has surfaces 15a and 16a on the inside. It is attached to the bottom plate 11.
(C)、第3図仮想線で示すように、側板支持治具12
の外側において周方向全長に亘って外側足場20を組立
て、さらにこの外側足場20の上端外側に外面自動溶接
機走行レール21を組立てる。(C), as shown by the imaginary line in FIG. 3, the side plate support jig 12
An outer scaffold 20 is assembled over the entire length in the circumferential direction on the outer side of the outer scaffold 20, and an outer automatic welding machine running rail 21 is further assembled on the outer side of the upper end of the outer scaffold 20.
そして第3図実線に示すように、クレーン18により最
上段の側板19−+oを側板支持治具12上に搭載する
。Then, as shown by the solid line in FIG. 3, the crane 18 mounts the uppermost side plate 19-+o onto the side plate support jig 12.
次いで側板19−toの縦継手の溶接が行なわれる。Next, the vertical joints of the side plates 19-to are welded.
この溶接作業は、同一場所で側板19−1oを搭載しつ
つ同一場所で行なわれ、溶接により連なった側板19−
1゜は第10図実線に示すように滑動受は面16aに受
止められた状態で周方向に送られる。This welding work is performed at the same place while mounting the side plate 19-1o, and the side plate 19-1o is connected by welding.
1°, the sliding receiver is sent in the circumferential direction while being received by the surface 16a, as shown by the solid line in FIG.
所定枚数の側板19−18を溶接したとき、滑動受は面
16aに支持されている側板19−1o群は所期のタン
ク径よりもやや犬に拡径しており、且つ周方向の一箇所
が未溶接である。When a predetermined number of side plates 19-18 are welded, the sliding receiver is such that the group of side plates 19-1o supported by the surface 16a has a slightly enlarged diameter than the intended tank diameter, and one location in the circumferential direction. is not welded.
この状態で未溶接端部が相接するように引き締めること
により、側板19−1o群はタンク径と同じになるよう
に縮径し、第10図仮想線で示すように固定受は面15
aで受止められるべく移動する。In this state, by tightening the unwelded ends so that they are in contact with each other, the diameter of the side plate 19-1o group is reduced to be the same as the tank diameter, and the fixed receiver is attached to the surface 15 as shown by the imaginary line in FIG.
Move to be caught by a.
これがセット位置となり、このとき未溶接部の縦溶接が
行なわれる。This becomes the set position, and at this time vertical welding of the unwelded parts is performed.
■)、第4図に示すように、屋根22の組立て溶接と、
この屋根22と最上段側板19.oとの溶接イが行なわ
れる。■) As shown in FIG. 4, assembling and welding the roof 22,
This roof 22 and the uppermost side plate 19. Welding with o is performed.
この溶接イは走行レール21上で外面自動溶接機を走行
させるなどして行なわれる。This welding is performed by running an automatic external welding machine on the traveling rail 21.
その後、側板支持治具12群の内側に、周方向複数個の
油圧ジヤツキ装置23が組立てられる。Thereafter, a plurality of hydraulic jacking devices 23 are assembled in the circumferential direction inside the group of side plate support jigs 12.
この油圧ジヤツキ装置23は、底板11に取付けられる
ベース24と、このベース24からの支柱25と、ラッ
クや爪などを介してこの支柱25に案内される昇降体2
6とこの昇降体26に取付けた持上げ係止片27と、前
記支柱25の上部に取付けた受止め係止片28とからな
り、昇降体26の昇降動と、側板19−18の内面に取
付けた一対のピース29゜30に対する両係止片27,
2Bの係脱動とにより、該側板19−1o群をジヤツキ
アップ可能としている。This hydraulic jack device 23 includes a base 24 attached to the bottom plate 11, a support 25 from the base 24, and an elevating body 2 guided to the support 25 via a rack, a claw, etc.
6, a lifting locking piece 27 attached to the lifting body 26, and a receiving locking piece 28 attached to the upper part of the support column 25, which prevents the lifting and lowering movement of the lifting body 26 and is attached to the inner surface of the side plate 19-18. Both locking pieces 27 for the pair of pieces 29°30,
By engaging and disengaging 2B, the side plates 19-1o group can be jacked up.
(E)、第5図実線に示すように、油圧ジヤツキ装置2
3の作動により、側板19.。(E) As shown in the solid line in Fig. 5, the hydraulic jack device 2
3, the side plate 19. .
および屋根22をジヤツキアップさせる。And the roof 22 is jacked up.
そして第5図仮想線に示すように、油圧ジヤツキ装置2
3群の内側に周方向全長に亘って内側上段足場31と内
側下段足場32とを組立て、さらに内側上段足場31の
上端内側に内面自動溶接機走行レール33を組立てる。As shown in the imaginary line in FIG. 5, the hydraulic jack device 2
Inside the third group, an inner upper scaffold 31 and an inner lower scaffold 32 are assembled over the entire length in the circumferential direction, and an inner automatic welding machine running rail 33 is further assembled inside the upper end of the inner upper scaffold 31.
34は支え治具を示す。(F″)、第6図仮想線に示す
ように、クレーン18により次段の側板19−0を側板
支持治具12上に搭載する。34 indicates a support jig. (F''), as shown by the imaginary line in FIG. 6, the next stage side plate 19-0 is mounted on the side plate support jig 12 by the crane 18.
そして前(C)項で述べたのと同様にして縦継手の溶接
が行なわれ、セットにより上段の側板19−1oとの間
に少しの間隙35が生じる。Then, the vertical joint is welded in the same manner as described in the previous section (C), and a small gap 35 is created between the vertical joint and the upper side plate 19-1o.
(0、第7図に示すように、油圧ジヤツキ装置23によ
り、前述した間隙35がなくなるように佃[板19−1
oを若干さげ、その下端を側板19−9の上端に接当さ
せた状態で両者を仮付は溶接する。(0. As shown in FIG.
o is slightly lowered, and the lower end is brought into contact with the upper end of the side plate 19-9, and the two are temporarily welded together.
その後、走行レール21上で外面自動溶接機を走行させ
ながら、両側板19−10.19−9間における横継手
の外面の自動溶接口を行なう。Thereafter, while running the automatic external welding machine on the traveling rail 21, automatic welding of the external surfaces of the horizontal joints between the side plates 19-10 and 19-9 is performed.
そして側板19−10の溶接部の非破壊検査を行なう。Then, a non-destructive inspection of the welded portion of the side plates 19-10 is performed.
■、第8図実線に示すように、屋根22ならびに両側板
19−1o、19−9を油圧ジヤツキ装置23によりジ
ヤツキアップさせる。(2) As shown by solid lines in FIG. 8, the roof 22 and both side plates 19-1o and 19-9 are jacked up by the hydraulic jacking device 23.
そして仮想線に示すように次段の側板19−8の搭載と
縦継手の溶接を行なったのち、前(G)項で述べたよう
に若干さげて仮付は溶接を行ない、そして最上段と次段
との側板19−1o、19 、間における横継手の内
面の自動溶接ハを行なうと同時に、次段と次々段との側
板19 、.19−8間における横継手の外面の自動溶
接(第7図口参照)を行なう。Then, as shown in the imaginary line, after mounting the next stage side plate 19-8 and welding the vertical joint, lower it slightly and weld the temporary attachment as described in the previous section (G), and then attach it to the top stage. At the same time, automatic welding of the inner surface of the horizontal joint between the side plates 19-1o, 19, 19-1o, 19-1, and the next stage is performed, and at the same time, the side plates 19-1o, 19-19, 19-1o, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, 19-19, . Automatically weld the outer surface of the horizontal joint between 19 and 8 (see Figure 7).
(υ、上述したのと同様にして下から2段目までの側板
の搭載、溶接を行なうのであり、第9図はその途中を示
している。(υ) The side plates from the bottom to the second stage are mounted and welded in the same manner as described above, and Fig. 9 shows the process in progress.
(J)、上述したように下から2段目までの溶接を終え
たのち、全体をジヤツキアップさせる。(J) After completing the welding from the bottom to the second stage as described above, jack up the whole thing.
そしてタンク内部に組立てた油圧ジヤツキ装置23の油
圧ポンプ部分を外部へ移設する。Then, the hydraulic pump portion of the hydraulic jacking device 23 assembled inside the tank is moved to the outside.
次いで最下段の側板19−1を挿入し、縦継手の溶接を
行なう。Next, the lowermost side plate 19-1 is inserted, and the vertical joint is welded.
そして側板19−2を若干に降して間隙35をなくした
のち、下から2段目と3段目との側板19−2,19−
3の内面の自動溶接を行なう。After lowering the side plate 19-2 slightly to eliminate the gap 35, the side plates 19-2 and 19-2 of the second and third tier from the bottom are removed.
Perform automatic welding of the inner surface of step 3.
さらに下から2段目と最下段との側板19−2,19−
1間の仮付は溶接を行なったのち、両側板19−2,1
9−1間の外面の自動溶接と、内面の手溶接とを行なう
。Furthermore, the side plates 19-2, 19- of the second row from the bottom and the bottom row
After welding for temporary attachment between 1 and 1, both side plates 19-2, 1
Perform automatic welding of the outer surface between 9-1 and manual welding of the inner surface.
次いで底板11上の側板支持治具12を撤去したのち底
板11上にタンク全体を降し、そしてタンク内外の足場
20,31,32、ならびに油圧ジヤツキ装置23の撤
去を行なう。Next, after removing the side plate support jig 12 on the bottom plate 11, the entire tank is lowered onto the bottom plate 11, and the scaffolds 20, 31, 32 inside and outside the tank and the hydraulic jacking device 23 are removed.
卸、上述した(5)項から(J)項までの間において、
底板11の矩形部における溶接と検査とが行なわれる。Wholesalers, between paragraphs (5) to (J) above,
Welding and inspection are performed on the rectangular portion of the bottom plate 11.
(L)、その後、最下段の側板19−1と底板11のす
み肉溶接、および底板11のスケッチ部と矩形部の溶接
が行なわれると共に、非破壊検査が行なわれる。(L) After that, fillet welding of the lowermost side plate 19-1 and the bottom plate 11, and welding of the sketch part and the rectangular part of the bottom plate 11 are performed, and a non-destructive inspection is performed.
そして水張り試験などの総合検査を行なう。Then, a comprehensive inspection such as a water filling test is performed.
以上述べたように本発明によると、各段の環状側板を製
作する際に、分割側板の供給を特定場所から行なえると
共に、分割側板間の縦溶接も特定場所で行なえ、したが
って狭い作業範囲であったとしても何んら支障なく行な
うことができると共に、自動溶接も可能にできる。As described above, according to the present invention, when manufacturing the annular side plates of each stage, the divided side plates can be supplied from a specific location, and the vertical welding between the divided side plates can also be performed at a specific location. Even if welding occurs, it can be carried out without any problems, and automatic welding can also be performed.
また製作した側板間の横溶接は、下段の側板を固定受は
面上に位置させブレなどが生じないようにセットした状
態で確実に且つ容易に行なうことができ、しかもブレが
生じないことから、内外の走行レール上で夫々溶接機を
走行させることにより、内外面の溶接を自動的に確実に
行なうことができる。In addition, the horizontal welding between the fabricated side plates can be carried out reliably and easily with the lower side plate positioned on the surface and set to prevent wobbling. By running the welding machine on the inner and outer running rails, it is possible to automatically and reliably weld the inner and outer surfaces.
また溶接レベルは最も低くし得て防護壁は不要に或いは
最小高さのものだけでよいことになる。Also, the welding level can be made the lowest, so that no protective wall is required or only one of the minimum height is required.
第1図は従来例の概略説明図、第2図〜第11図は本発
明の一実施例を示し、第2図〜第8図は建設状態を示す
要部の縦断正面図、第9図は建設途中での一部切欠斜視
図、第10図は側板支持治具の正面図、第11図は同平
面図である。
11・・・・・・底板、12・・・・・・側板支持治具
、16−a・・・・・・滑動受は面、18・・・・・・
クレーン、19−16〜19−1・・・・・・側板、2
1・・・・・・外面自動溶接機走行レール、22・・・
・・・屋根、23・・・・・・油圧ジヤツキ装置、33
・・・・・・内面自動溶接機走行レール。Fig. 1 is a schematic explanatory diagram of a conventional example, Figs. 2 to 11 show an embodiment of the present invention, Figs. 2 to 8 are longitudinal sectional front views of main parts showing the construction state, and Fig. 9 10 is a partially cutaway perspective view of the construction in progress, FIG. 10 is a front view of the side plate support jig, and FIG. 11 is a plan view thereof. 11...Bottom plate, 12...Side plate support jig, 16-a...Sliding receiver is surface, 18...
Crane, 19-16 to 19-1...Side plate, 2
1... External automatic welding machine running rail, 22...
... Roof, 23 ... Hydraulic jacking device, 33
...Inner automatic welding machine running rail.
Claims (1)
板上の周方向複数箇所に前記固定費は面を内側にして配
置し、成る特定場所において、側板支持治具上に最上段
用の側板を順次搭載し、縦溶接を行ないつつ滑動受は面
上で周方向に移動させ、そして周方向の一箇所が未溶接
の状態で引き締め縮径させて固定費は面上で受止めさせ
たのち、未溶接部分の縦溶接を行なって環状の最上段側
板を製作し、この最上段側板上に屋根を取付けたのちこ
れらを油圧ジヤツキ装置により持上げ、そして次段側板
を最終的に固定費は面上で製作したのち最上段側板を下
降させて両側板の上下端間を接当させ、次いで外側に配
設した環状の走行レール上で溶接機を走行させなから両
段側板間の外面を横溶接し、そして次段側板の持ち上げ
ならびに側板製作を繰返して順次段階的にタンク建設を
行なうと共に、内側に配設した環状の走行レール上で溶
接機を走行させながら各段側板間の内面を横溶接するこ
とを特徴とするタンクの建設方法。1 The fixed cost is a surface and the sliding receiver is a side plate support jig that has a surface and is placed at multiple locations in the circumferential direction on the bottom plate with the surface facing inside, and at a specific location, the topmost side plate support jig is placed on the side plate support jig. The side plates were installed one after another, and the sliding bridge was moved in the circumferential direction on the surface while vertical welding was performed, and the fixed cost was absorbed on the surface by tightening and reducing the diameter with one spot in the circumferential direction unwelded. After that, the unwelded parts are vertically welded to create an annular uppermost side plate, and the roof is attached to this uppermost side plate, which is then lifted by a hydraulic jacking device, and the next side plate is finally fixed. After the cost is fabricated on the surface, the uppermost side plate is lowered and the upper and lower ends of both side plates are brought into contact, and then the welding machine is run on the annular running rail installed on the outside, and the uppermost side plate is lowered to touch the upper and lower ends of both side plates. The tank was constructed step by step by horizontally welding the outer surface, then lifting the next stage side plate, and repeating the fabrication of the side plate. At the same time, the welding machine was run on the annular running rail installed inside, and the space between each stage side plate was welded. A method of constructing a tank, characterized by horizontal welding of the inner surface.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8849079A JPS5919226B2 (en) | 1979-07-11 | 1979-07-11 | How to build a tank |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8849079A JPS5919226B2 (en) | 1979-07-11 | 1979-07-11 | How to build a tank |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5612473A JPS5612473A (en) | 1981-02-06 |
| JPS5919226B2 true JPS5919226B2 (en) | 1984-05-04 |
Family
ID=13944239
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8849079A Expired JPS5919226B2 (en) | 1979-07-11 | 1979-07-11 | How to build a tank |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5919226B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6371169B2 (en) * | 2014-09-04 | 2018-08-08 | 鹿島建設株式会社 | Construction method of storage tank |
-
1979
- 1979-07-11 JP JP8849079A patent/JPS5919226B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5612473A (en) | 1981-02-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5490364A (en) | Telescopic flare pipe tower | |
| US4177915A (en) | Method for manufacturing large tanks | |
| CN111119497B (en) | Ultra-large box-type steel column installation system and construction method | |
| JP2003326390A (en) | Tower inner wall operating device and operating method using the same | |
| JP6277158B2 (en) | Traveling heavy lifting device | |
| CN108729357B (en) | High-position beam falling method based on jacking construction | |
| US3699688A (en) | Apparatus and method for removing and/or adding column sections to a column of a marine structure | |
| JPS5919226B2 (en) | How to build a tank | |
| CN215941801U (en) | Submerged arc welding dolly operation platform and submerged arc welding equipment with adjustable hydraulic pressure | |
| JP7825406B2 (en) | Reinforced concrete cage assembly method and assembly device | |
| CN113857790B (en) | Method for processing stiffening plate in large-diameter tubular column reinforcing area | |
| JP3046552B2 (en) | Blast furnace furnace construction method | |
| CN217193202U (en) | A gantry type welding platform device that can walk and lift | |
| JP2009127338A (en) | Wall panel assembly apparatus and wall panel assembly method | |
| CN215967309U (en) | Curved outer plate assembling device | |
| CN223098386U (en) | Welding operation platform for lifting pipe structure | |
| JPS631408B2 (en) | ||
| CN223406343U (en) | Steel construction interfacing apparatus for construction | |
| CN220482079U (en) | A simple platform for RH furnace vacuum tank maintenance operations | |
| JPH0645971B2 (en) | Post device for side plate repair of storage tank | |
| JP7802273B1 (en) | Temporary elevator | |
| JPS5921404B2 (en) | How to build super large structures | |
| JP6153481B2 (en) | Existing tank bottom plate replacement jig, existing tank bottom plate replacement method using the jig, and strong wind countermeasure fixing jig | |
| CN113003468A (en) | Large-scale gas chamber installation method | |
| JPS624393Y2 (en) |