JPS5944858B2 - Demand monitoring control device - Google Patents
Demand monitoring control deviceInfo
- Publication number
- JPS5944858B2 JPS5944858B2 JP54008727A JP872779A JPS5944858B2 JP S5944858 B2 JPS5944858 B2 JP S5944858B2 JP 54008727 A JP54008727 A JP 54008727A JP 872779 A JP872779 A JP 872779A JP S5944858 B2 JPS5944858 B2 JP S5944858B2
- Authority
- JP
- Japan
- Prior art keywords
- power
- demand
- load
- circuit
- level
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Description
【発明の詳細な説明】
本発明は、デマンド時限中に需要電力が契約需要電力を
超えないように現在電力を監視し、超えそうなときには
負荷制御をおこなうデマンド監視制御装置に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a demand monitoring and control device that monitors current power so that the power demand does not exceed the contract power demand during a demand period, and performs load control when the power demand is about to exceed the contract power demand.
この種の装置において負荷の自動遮断をおこなう場合、
第1図に示すように現在電力値がデマンド時限開始時に
0に設定され終了時には契約需要電力値Qに設定されて
いる理想負荷曲線を超え、しかも予測需要電力値Rが目
標需要電力値例えば契約需要電力Qを遮断電力レベル(
その時点で調整すべき電力値)以上超えたときに負荷遮
断をおこなう方式がある。When performing automatic load shedding in this type of equipment,
As shown in Figure 1, the current power value is set to 0 at the start of the demand time period, and at the end of the demand period, it exceeds the ideal load curve set to the contract power demand value Q, and the predicted power demand value R is set to the target power demand value, for example, the contract Power level at which demand power Q is cut off (
There is a method that performs load shedding when the power exceeds (the power value that should be adjusted at that time) or more.
負荷遮断は、一度遮断したらその時限内は復帰させない
制御方式もあるが、電力を効率的に使用しようとする電
力需要家にとつては電力の余裕ができた時点で負荷を復
帰させる方が望ましい。したがつて負荷の復帰に関して
(九現在電力が理想負荷曲線を下回り、しかも予測需要
電力値が目標需要電力値を復帰レベル(その時点におけ
る調整すべき電力値)以上下回つたときに負荷を復帰さ
せている。一般には、遮断電力レベルと復帰レベルとは
等しいものである。There is a control method for load shedding that does not restore the load within the specified time limit once it has been shut off, but for power consumers who want to use electricity efficiently, it is preferable to restore the load as soon as there is surplus power. . Therefore, regarding load restoration (9) When the current power falls below the ideal load curve and the predicted power demand value falls below the target power demand value by more than the restoration level (the power value to be adjusted at that point), the load is restored. Generally, the cut-off power level and the recovery level are equal.
それは、その時点における調整すべき電力Uが次式で示
されるからである。U■(R−Q)・Thなお、Rは予
測需要電力、Qは目標需要電力、Tはデマンド時限、を
はデマンド経過時間である。This is because the electric power U to be adjusted at that time is expressed by the following equation. U■(R-Q)·Th Note that R is predicted power demand, Q is target power demand, T is demand time period, and is demand elapsed time.
調整すべき電力Uが…のときは超過、←)のときは余裕
状態である。超過のときは、1回路の遮断可能負荷電力
とこの調整電力Uとが等しくなつたときに負荷遮断信号
を発し負荷を遮断し、また逆に余裕の場合には投入すべ
き電力Uが投入可能負荷電力と等しくなつたときに負荷
投入信号を発し負荷の投入をおこなえば、予測電力は目
標需要電力に一致することとなる。ここで、複数の制御
対象負荷がある場合には、夫々の負荷における負荷電力
値を設定し、調整電力値と一致した負荷を制御すること
が望ましい。When the power U to be adjusted is..., it is in excess, and when it is ←), it is in a surplus state. In case of excess, when the load power that can be cut off for one circuit becomes equal to this adjusted power U, a load cutoff signal is issued and the load is cut off, and conversely, if there is a margin, the power U that should be input can be turned on. If the load application signal is issued and the load is applied when the power becomes equal to the load power, the predicted power will match the target power demand. Here, when there are multiple loads to be controlled, it is desirable to set a load power value for each load and control the load that matches the adjusted power value.
しかしながらこの設定のためには、夫々に例えばデイジ
タルスイツチ等を設置することとなり、非常に煩雑で信
頼性を低下させコストを上昇させることとなる。したが
つて、複数の制御対象負荷の平均電力値をもつて各負荷
電力の信、すなわち制御レベルとしている。調整電力U
={(R−Q)T半〒}は、デマンド開始時(t=O)
にはU=R−Qである。However, in order to make this setting, for example, a digital switch or the like must be installed in each of the devices, which is very complicated, reduces reliability, and increases cost. Therefore, the average power value of a plurality of loads to be controlled is used as the signal of each load power, that is, the control level. Adjusted power U
= {(R-Q)T half〒} is at the start of demand (t=O)
In this case, U=R−Q.
デマンド時限Tを30分とすると、29分経過後にはU
=30(R−Q)と開始時に比べ30倍もの大きさにな
る。これは、予想電力Rと目標需要電力Qとの差が、デ
マンド時限開始時と29分経過後等しいとしても調整電
力値Uは30倍も大きく違うものとなり、時限後半には
負荷を制御して予測電力Rと目標需要電力とを一致させ
るにはかなり大きな負荷容量の負荷を遮断しなければな
らないことを示している。大きな負荷の遮断を避けよう
とするには、第2図に示すように現在電力値を略理想負
荷曲線上に位置させる必要がある。If the demand time limit T is 30 minutes, after 29 minutes U
= 30(R-Q), which is 30 times larger than at the start. This means that even if the difference between the expected power R and the target power demand Q is the same at the start of the demand time period and after 29 minutes have elapsed, the adjusted power value U will be as much as 30 times different, and the load will not be controlled in the second half of the time period. This indicates that in order to match the predicted power R with the target power demand, it is necessary to cut off a load with a considerably large load capacity. In order to avoid cutting off a large load, it is necessary to position the current power value approximately on the ideal load curve as shown in FIG.
第2図において、経過時間が27分のとき、現在電力B
が理想負荷曲線Aの上側にあつて、このときの予測電力
R27が目標電力Qを超えしかも調整電力が制御レベル
を超えたとき負荷遮断が行われる。また、経過時間が2
8分のとき現在電力が理想負荷曲線Aの下側にあつて、
このときの予測電力R28が目標電力Qより小さく、し
かも調整電力が制御レベルを超えたとき負荷投入が行わ
れる。In Figure 2, when the elapsed time is 27 minutes, the current power B
is above the ideal load curve A, and when the predicted power R27 at this time exceeds the target power Q and the adjusted power exceeds the control level, load shedding is performed. Also, the elapsed time is 2
At 8 minutes, the current power is below the ideal load curve A,
When the predicted power R28 at this time is smaller than the target power Q and the adjusted power exceeds the control level, the load is turned on.
負荷遮断の際の制御レベルと投入の際の制御レベルが等
しいならば、現在電力が理想負荷曲線上に位置するため
、わずかな現在電力の変動により理想負荷曲線を上まわ
つたり下まわつたりすることとなり、これに伴い予測電
力も変化する。この変化のため制御レベルとして遮断対
象負荷の平均値を設定していたとしても実際に投入及び
遮断される負荷容量が制御レベルに等しいとは限らず、
これに差がある場合には負荷遮断信号と負荷投入信号と
が演算サイクル毎に交互に出力されること(これをハン
チングという)の慮があり、デマンド監視制御装置とし
ては不安定な制御をおこなうこととなり非常に不都合な
ものであつた。本発明は、上記欠点を除去したデマンド
監視制御装置を提供することを目的とする。If the control level when turning off the load is equal to the control level when turning on the load, the current power is on the ideal load curve, so a slight change in the current power will cause it to go above or below the ideal load curve. As a result, the predicted power will also change accordingly. Because of this change, even if the average value of the load to be cut off is set as the control level, the load capacity that is actually turned on and cut off is not necessarily equal to the control level.
If there is a difference between these, there is a possibility that the load cut-off signal and the load-on signal will be output alternately in each calculation cycle (this is called hunting), resulting in unstable control as a demand monitoring control device. This was extremely inconvenient. An object of the present invention is to provide a demand monitoring and control device that eliminates the above-mentioned drawbacks.
そのため遮断レベルと投入レベルに差をもたせることに
より制御信号出力のハンチングを防止させるものである
。以下第3図を参照して本発明による実施例を説明する
。Therefore, hunting of the control signal output is prevented by providing a difference between the cutoff level and the cutoff level. An embodiment according to the present invention will be described below with reference to FIG.
7
デマンド監視制御装置1は、使用電力量を計量し、その
計量値に比例したパルスを発信する発信器装置付電力量
計2からパルスを受信する。7 The demand monitoring and control device 1 receives pulses from the watt-hour meter 2 with a transmitter device that measures the amount of power used and transmits pulses proportional to the measured value.
このパルスを受信した制御装置1では、現在値カウンタ
3とサンプリングカウンタ4にパルスが供給される。カ
ウンタ3はパルスを計数し現在需要電力Pを算出し、そ
の値を現在値表示器5で表示する。一方、サンプリング
カウンタ4では供給される電力量計2からのパルスをサ
ンプリング時間Δt(例えば1分)中計数し、この計数
値をサンプリング時間△tにおける使用電力量の単位時
間(1分)当りのサンプリング値Δp/Δtとして算出
せる。6は、残時間時計回路で、デマンド時限Tの残時
間(T−t)(tは現在時間)を算出し、その値を残り
時間表示器8で表示する。In the control device 1 that receives this pulse, the pulse is supplied to the current value counter 3 and the sampling counter 4. The counter 3 counts the pulses, calculates the current demand power P, and displays the value on the current value display 5. On the other hand, the sampling counter 4 counts the pulses supplied from the electricity meter 2 during the sampling time Δt (for example, 1 minute), and calculates this counted value as the amount of electricity used per unit time (1 minute) at the sampling time Δt. It can be calculated as the sampling value Δp/Δt. 6 is a remaining time clock circuit that calculates the remaining time (T-t) of the demand time limit T (t is the current time) and displays the value on the remaining time display 8.
9は、乗算器で、サンプリングカウンタ4と残時間時計
回路6との出力△p/△tと(T−t)との積仝ヱ・(
T−t)を算出する。9 is a multiplier that calculates the product of the output △p/△t of the sampling counter 4 and the remaining time clock circuit 6 and (T-t).
T-t) is calculated.
予測電力発生器10△tは、現在値カウンタ3の出力P
と乗算回路9の出力失早・(T−1)が供給されデマン
ド時限T終了時点における使用電力の予測電力R{R=
P+尖X・(T−t)}を算出し、その予測電力値Rを
予測値表示器11に表示する。The predicted power generator 10Δt is the output P of the current value counter 3.
and the output failure of the multiplier circuit 9 (T-1) are supplied, and the predicted power consumption R{R=
P+peak X·(Tt)}, and its predicted power value R is displayed on the predicted value display 11.
12は目標需要電力設定器で、デマンド時限Tの終了時
における使用電力量の例えば契約需要電力である目標需
要電力Qが設定されている。Reference numeral 12 denotes a target power demand setting device, in which a target power demand Q, which is the amount of power to be used at the end of the demand time period T, for example, the contract power demand, is set.
13は、差・比較回路であり、予測電力発生器10の出
力Rと目標需要電力設定器12に設定されている目標需
要電力Qとの差(R−Q)及びその大小R>Q,R≦Q
を算出しそれぞれその旨の信号を発生する。13 is a difference/comparison circuit, which calculates the difference (R-Q) between the output R of the predicted power generator 10 and the target power demand Q set in the target power demand setting device 12, and its magnitude R>Q, R ≦Q
and generates a signal to that effect.
14は調整電力発生器で、差 比較回路13の出力(R
−QXど残時間時計回路6の出力(T−t)が供給さ札
調整すべき電力U{U=T
(R−Q)T−,}が算出さへ その値が調整電力表示
器15に表示される。14 is a regulated power generator, which outputs the difference comparator 13 (R
-QX is supplied with the output (T-t) of the remaining time clock circuit 6, and the power to be adjusted U{U=T (R-Q)T-,} is calculated.The value is displayed on the adjusted power display 15. Is displayed.
16は理想負荷曲線発生器で、デマンド時限経過ととも
にデマンド時限T開始時にOで、終了時に目標需要電力
Qとなる理想負荷曲線Aを発生するものである。Reference numeral 16 denotes an ideal load curve generator, which generates an ideal load curve A that is O at the start of the demand time period T and becomes the target power demand Q at the end of the demand time period as the demand time period passes.
17は第1の比較回路で、現在値カウンタ3の出力Pと
理想負荷曲線発生器16の出力Aが供給され6PとAの
差(P−A)、PとAの大小比P≧A,P<Aが算出さ
へ その旨の信号を発生する。Reference numeral 17 denotes a first comparison circuit, which is supplied with the output P of the current value counter 3 and the output A of the ideal load curve generator 16, and 6 calculates the difference between P and A (P-A), the magnitude ratio of P and A, P≧A, If P<A is calculated, a signal to that effect is generated.
18は、制御レベル設定器であり、複数群例えばn群の
制御対象負荷1群あたりで、サンプリング時間△tあた
りの平均負荷電力Kが設定されている。Reference numeral 18 denotes a control level setter, in which the average load power K per sampling time Δt is set for one group of loads to be controlled, for example, n groups.
19は、遡新レベル発生回路で、残時間時計回路6の出
力(T−t)と制御レベル設定器18の出力Kが供給さ
れ遮断レベルX{X=K・1−1}Tを算出する。Reference numeral 19 denotes a retrospective level generation circuit, which is supplied with the output (T-t) of the remaining time clock circuit 6 and the output K of the control level setter 18, and calculates the cutoff level X {X=K・1-1}T. .
20は、第2の比較回路で第1の差比較回路13の差出
力(R−Q)と遮断レベル発生回路19の出力Xが供給
され、(R−Q)とXの大小比較がなさ粍 (R−Q)
≧Xのときその旨の信号を発生する。20 is a second comparison circuit which is supplied with the difference output (R-Q) of the first difference comparison circuit 13 and the output X of the cutoff level generation circuit 19, and there is no comparison between (R-Q) and X. (R-Q)
When ≧X, a signal to that effect is generated.
21は投入レベル発生回路で、残時間時計回路6からの
出力(T−t)制御レベル設定器18の出力Kが供給さ
へ投入レベT−(t−m・△t)ルY{Y=K・?}を
算出す
T
る。Reference numeral 21 denotes a closing level generation circuit, which is supplied with the output (Tt) from the remaining time clock circuit 6 and the output K of the control level setter 18 to generate the closing level T-(t-m·△t) Y{Y= K.? } is calculated.
(ただし、m=1,2,3,・・・・・・)すなわち、
時点tにおける投入レベルYは遮断レベルXよりサンプ
リング時間△t(7)m倍の時間より以前のものとなる
。すなわち、Yの幅はXの幅より大きいものである。2
2は、第3の比較回路で、差・比較回路13の出力(R
−Q)と投入レベル発生回路21の出力Yが供給され、
Yと(R−Q)の大小比較がなさへ Y≧(R−Q)の
ときその旨の信号を発生する。(However, m=1, 2, 3,...) That is,
The input level Y at the time point t is earlier than the cutoff level X by the sampling time Δt(7)m times. That is, the width of Y is larger than the width of X. 2
2 is a third comparison circuit, which outputs the difference/comparison circuit 13 (R
-Q) and the output Y of the input level generation circuit 21 are supplied,
There is no comparison between Y and (R-Q). When Y≧(R-Q), a signal to that effect is generated.
23は、遮断指令回路であり差・比較回路13、第1の
比較器17と、第2の比較回路20の出力端が夫々接続
されている。Reference numeral 23 designates a cutoff command circuit to which the output terminals of the difference/comparison circuit 13, the first comparator 17, and the second comparison circuit 20 are connected.
遮断指令回路23は、3つの入力が夫々R>Q,P>A
,X≦(R−Q)なる旨の信号が同時に供給された時の
み遮断指令信号を負荷制御回路24に供給する。負荷制
御回路24では遮断指令信号を受信するとn群の制御対
象負荷のうち1群の負荷の遮断をおこなう旨の信号を発
生する。25は、投入指令回路で、差、比較回路13、
第1の比較回路17と第3の比較回路22の夫々の出力
側が接続されている。The cutoff command circuit 23 has three inputs of R>Q and P>A, respectively.
, X≦(R-Q) are simultaneously supplied, a cutoff command signal is supplied to the load control circuit 24. When the load control circuit 24 receives the cutoff command signal, it generates a signal to cut off one group of loads among the n groups of loads to be controlled. 25 is an input command circuit, which includes a difference and comparison circuit 13;
The respective output sides of the first comparison circuit 17 and the third comparison circuit 22 are connected.
投入指令回路25は、3つの入力が夫々R≦Q,P≦A
,Y≧(R−Q)なる旨の信号が同時に供給された時の
み投入指令信号を負荷制御回路24に供給する。負荷制
御回路24では投入指令信号を受値するとn群の制御対
象負荷の遮断されている負荷のうち1群の負荷の投入を
おこなう旨の信号を発生する。さて、このように構成さ
れた一実施例の作用を説明する。The input command circuit 25 has three inputs of R≦Q, P≦A, respectively.
, Y≧(R-Q) are simultaneously supplied, a closing command signal is supplied to the load control circuit 24. When the load control circuit 24 receives the turn-on command signal, it generates a signal to turn on one group of loads among the n groups of controlled loads that have been cut off. Now, the operation of one embodiment configured as described above will be explained.
発信器装置付電力量計2からの使用電力量に比例したパ
ルスは、現在値カウンタ3にカウントさへ現在需要電力
Pとして現在値表示器5で表示される。Pulses proportional to the amount of power used from the power meter 2 with transmitter device are counted by the current value counter 3 and displayed as the current demand power P on the current value display 5.
このカウンタ3からの出力である現在需要電力Pは、予
測電力発生器10へ供給される。The current demand power P, which is the output from this counter 3, is supplied to the predicted power generator 10.
この予測電力発生器10では、この現在需要電力Pと乗
△p算器9からの出力ー・(T−t)とからデマンド△
t時限T終了時点における使用電力の予測電力△PR{
R=P+一・(T−t)}を算出する。In this predicted power generator 10, demand △
Predicted power usage at the end of time period T △PR{
R=P+1・(Tt)} is calculated.
この△t予測電力Rは予測値表示器11で表示されると
ともに差・比較回路13へ供給される。This Δt predicted power R is displayed on the predicted value display 11 and is also supplied to the difference/comparison circuit 13.
この差・比較回路13では、目標需要電力設定器12か
らの日標需要電力Qとの比較が行なわれ(R−Q),R
>Q,R≦Qを算出し出力する。In this difference/comparison circuit 13, a comparison is made with the daily target power demand Q from the target power demand setting device 12 (R-Q), R
>Q, R≦Q is calculated and output.
この差信号(R−Q)は、調整電力発生器14へ供給さ
へ ここで残り時間時計回路6からの残り時間(T−t
)とから調整電力U{U=(R−TQ)?}が算出され
る。This difference signal (R-Q) is supplied to the regulated power generator 14 where the remaining time from the remaining time clock circuit 6 (T-t
) and the adjusted power U{U=(R-TQ)? } is calculated.
この調整電力Uは、T−T゜調整電力表示器15で表示
される。This adjusted power U is displayed on the T-T° adjusted power display 15.
また、この差信号(R−Q)は、第2、第3の比較回路
20,22に供給さ瓢遮断レベル発生回路19からの遮
断レベルX及び投入レベル発生器21からの投入レベル
Yと比較される。Further, this difference signal (R-Q) is supplied to the second and third comparison circuits 20 and 22 and is compared with the cutoff level X from the cutoff level generation circuit 19 and the closing level Y from the closing level generator 21. be done.
そして、差信号(R−Q)が、遮断レベルXと同じかあ
るいは大きい場合、前記第2の比較回路20から遮断指
令回路23へその旨の信号を供給する。一方、差信号(
R−Q)が投入レベルYと伺じかあるいは小さい場合、
前記第3の比較回路22から投入指令回路25へその旨
の信号を供給する。この際、投人レベルYの幅は遡析レ
ベルXの幅より大きいため、投入すべき信号は、遮断す
べき信号が出力される(R−Q)の値の絶対値より大き
くなつたとき始めて出力されることとなる。If the difference signal (R-Q) is equal to or larger than the cutoff level X, the second comparison circuit 20 supplies a signal to that effect to the cutoff command circuit 23. On the other hand, the difference signal (
If R-Q) is close to or smaller than the input level Y,
A signal to that effect is supplied from the third comparison circuit 22 to the input command circuit 25. At this time, since the width of the thrower level Y is larger than the width of the retrospective analysis level It will be output.
また、この第2、第3の比較回路20,22が供給され
る遮断指令回路23及び投入指令回路25には、前記差
・比較回路13からの比較信号(R>Q)及び(R≦Q
)並びに第1の比較回路17からの比較信号(P>A)
及び(P≦A)が供給される。そして、この遮断指令回
路23に信号(R−Q)≧X,R>Q,P>Aが供給さ
れるとこの回路23から負荷遮断指令が負荷制御回路2
4へ供給される。In addition, a comparison signal (R>Q) and (R≦Q) from the difference/comparison circuit 13 are supplied to a cutoff command circuit 23 and a closing command circuit 25 to which the second and third comparison circuits 20 and 22 are supplied.
) and the comparison signal from the first comparison circuit 17 (P>A)
and (P≦A) are provided. When the signal (R-Q)≧X, R>Q, P>A is supplied to this cutoff command circuit 23, a load cutoff command is sent from this circuit 23 to the load control circuit 2.
4.
一方、この投入指令回路25に信号(R一Q)≦Y,R
≦Q,P≦Aが供給されると、この回路25から負荷投
入指令が負荷制御回路24へ供給される。以上のように
して負荷の遮断投入が行なわれる。On the other hand, the input command circuit 25 receives a signal (R-Q)≦Y,R
When ≦Q and P≦A are supplied, a load application command is supplied from this circuit 25 to the load control circuit 24. Load switching is performed in the manner described above.
いま、遮断レベルXと投入レベルYとが等しいとすると
R>Q,(R−Q≧X,P>Aの条件が整つた場合遮断
指令回路23から遮断指令信号が負荷制御回路24へ供
給され負荷制御が行なわれる。この負荷制御の効果によ
つてR<Q,(R一Q)〈X,P<Aとなると今度は投
入指令回路25の入力条件が整うために負荷が投入され
結果として遮断、投入が続いて繰り返えされハンチング
が生じてしまう。ところが以上説明したようtζ制御レ
ベルKを設定し、このKと残り時間に応じ遮断レベルX
1投人レベルYを発生させ、このレベルYの幅は、レベ
ルXの幅より大きいものとし、またレベルYを発生させ
るmの値を変えることにより、Xの幅とYの幅を負荷に
応じ決定することができるため、演算サイクル毎に負荷
遮断信号と負荷投入信号が短時間のうちに交互に発生さ
れることがなくなる。したがつて、安定したデマンド監
視制御が可能となる。Now, assuming that the cutoff level Load control is performed. Due to the effect of this load control, when R<Q, (R - Q) < Shutdown and shutoff are repeated and hunting occurs.However, as explained above, the tζ control level K is set, and the shutoff level X is set according to this K and the remaining time.
1 pitcher level Y is generated, and the width of this level Y is greater than the width of level X, and by changing the value of m that generates level Y, the width of This eliminates the possibility that the load cutoff signal and the load on signal are generated alternately within a short period of time in each calculation cycle. Therefore, stable demand monitoring control becomes possible.
第1図、第2図は従来の動作を説明するための特性曲線
図、第3図は、本発明による実施例のプロツク図である
。
1・・・・・・デマンド監視制御装置、3・・・・・・
現在値カウンタ、4・・・・・・サンプリングカウンタ
、6・・・・・・残時間時計回路、9・・・・・・乗算
器、10・・・・・・予測電力発生器、12・・・・・
・目標需要電力設定器、13・・・・・・差・比較回路
、16・・・・・・理想負荷曲線発生器、17・・・・
・・第1の比較回路、18・・・・・・制御レベル設定
器、19・・・・・・遮断レベル発生回路、20・・・
・・・第2の比較回路、21・・・・・・投入レベル発
生回路、22・・・・・・第3の比較回路、23・・・
・・・遮断指令回路、24・・・・・・負荷制御回路、
25・・・・・・投入指令回路。1 and 2 are characteristic curve diagrams for explaining conventional operation, and FIG. 3 is a block diagram of an embodiment according to the present invention. 1... Demand monitoring control device, 3...
Current value counter, 4... Sampling counter, 6... Remaining time clock circuit, 9... Multiplier, 10... Predicted power generator, 12...・・・・・・
・Target power demand setting device, 13...Difference/comparison circuit, 16...Ideal load curve generator, 17...
...First comparison circuit, 18... Control level setter, 19... Cutoff level generation circuit, 20...
... Second comparison circuit, 21 ... Closing level generation circuit, 22 ... Third comparison circuit, 23 ...
... Cutoff command circuit, 24 ... Load control circuit,
25... Closing command circuit.
Claims (1)
電力に応じたデマンド監視をおこなうデマンド監視制御
装置において、現在需要電力が理想負荷曲線を超過し、
さらに予測需要電力が目標需要電力値をその時点の遮断
電力幅以上超えるとき制御対象負荷を遮断し、負荷の投
入にあたつては現在需要電力が理想負荷曲線を下まわり
さらに予測需要電力が目標需要電力値をその時点におけ
る遮断電力幅より大きい幅を有する投入電力幅以上に下
まわつたときに負荷の投入をおこなうようにしたことを
特徴とするデマンド監視制御装置。1. In a demand monitoring control device that monitors demand according to target power demand based on the number of pulses from a power meter with a transmitter, if the current power demand exceeds the ideal load curve,
Furthermore, when the predicted power demand exceeds the target power demand value by more than the current cutoff power width, the controlled load is shut off, and when the load is turned on, the current demand power is below the ideal load curve and the predicted power demand is the target. 1. A demand monitoring and control device characterized in that a load is turned on when a demand power value falls below an input power width having a width larger than a cutoff power width at that time.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP54008727A JPS5944858B2 (en) | 1979-01-30 | 1979-01-30 | Demand monitoring control device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP54008727A JPS5944858B2 (en) | 1979-01-30 | 1979-01-30 | Demand monitoring control device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS55103042A JPS55103042A (en) | 1980-08-06 |
| JPS5944858B2 true JPS5944858B2 (en) | 1984-11-01 |
Family
ID=11700974
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP54008727A Expired JPS5944858B2 (en) | 1979-01-30 | 1979-01-30 | Demand monitoring control device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5944858B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6570499B2 (en) * | 2016-09-29 | 2019-09-04 | 三菱電機ビルテクノサービス株式会社 | Power management system |
-
1979
- 1979-01-30 JP JP54008727A patent/JPS5944858B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS55103042A (en) | 1980-08-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4253151A (en) | Apparatus for monitoring and controlling consumer power consumption | |
| US3789201A (en) | Simulated load forecast and control apparatus | |
| US4125895A (en) | Maximum-power motor | |
| EP0505333A2 (en) | Estimating the charge of batteries | |
| EP4166950B1 (en) | Electrical parameter monitoring | |
| WO1980002893A1 (en) | Bidirectional integrator | |
| WO2015056634A1 (en) | Electricity storage system | |
| US4774457A (en) | Electric power measuring devices | |
| JPS5944858B2 (en) | Demand monitoring control device | |
| JP3430890B2 (en) | Power management device | |
| JP4778211B2 (en) | Annual power consumption management system | |
| EP0167299A2 (en) | Monitoring power usage | |
| Saleh et al. | Estimating frequency changes due to smart grid functions | |
| MY116557A (en) | Electronic prepayment type electric watt-hour meter | |
| SU1377937A1 (en) | Device for monitoring the state of charge of storage battery | |
| GB2061641A (en) | Method and apparatus for controlling maximum electricity demand | |
| JP2004104949A (en) | Power generation control device | |
| SU1665430A2 (en) | Device for checking state of change of storage battery | |
| JP2007271281A (en) | Electric power monitoring system | |
| JPS63273752A (en) | Integrating watt meter for airconditioner | |
| JPS62118715A (en) | Demand controller | |
| SU692000A1 (en) | Apparatus for supplying a load | |
| SU978272A1 (en) | Device for power supply of load | |
| JPH0154934B2 (en) | ||
| JPWO2002037126A1 (en) | Electronic watt-hour meter |