JPS5949962B2 - Shoring method and equipment for construction of floating concrete structures - Google Patents
Shoring method and equipment for construction of floating concrete structuresInfo
- Publication number
- JPS5949962B2 JPS5949962B2 JP16352681A JP16352681A JPS5949962B2 JP S5949962 B2 JPS5949962 B2 JP S5949962B2 JP 16352681 A JP16352681 A JP 16352681A JP 16352681 A JP16352681 A JP 16352681A JP S5949962 B2 JPS5949962 B2 JP S5949962B2
- Authority
- JP
- Japan
- Prior art keywords
- frame
- shoring
- float
- floating
- water surface
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/06—Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
- Bridges Or Land Bridges (AREA)
Description
【発明の詳細な説明】
本発明は港湾施設としての桟橋又はドルフィン等の水上
コンクリート構造物施工のための支保工方法及びその装
置に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a shoring method and apparatus for constructing a floating concrete structure such as a pier or dolphin as a port facility.
桟橋等の上部コンクリート施工のための支保工として最
近浮上式の支保工が提案されている。Floating type shoring has recently been proposed as a shoring for concrete construction of the upper part of piers, etc.
この浮上式支保工は第1図に示すように長尺な鋼管によ
る縦行1とこれを連結する横梁2とを梯子状に組んで支
保工用枠体3を形成し、その縦行1の鋼管中空部を密閉
して支保工全体を海上に浮せるようにしている。As shown in Fig. 1, this floating type shoring is constructed by assembling vertical rows 1 made of long steel pipes and horizontal beams 2 that connect them in a ladder shape to form a shoring frame 3. The hollow part of the steel pipe is sealed so that the entire shoring structure can float on the sea.
このような支保工を用いて桟橋の上部コンクリートを施
工するには第2図e→に示すように枠体3を桟橋の杭4
の間に固定し、その上にさらに追加の支保工5及び型枠
6を組んだ後上部コンクリート7を打設するのであるが
、浮上式支保工設置にあたっては枠体3を海上に浮べ第
2図(イ)に示す如く杭4間に曳き入れた後、同図(ロ
)の如く枠体3をチエンブロック等の吊り上げ装置8に
より吊り上げた後、チエンブロック等の吊り上げ装置8
から鋼棒等の吊材9に盛りかえて支保工を設置している
。To construct the upper part of the pier using such shoring, the frame 3 is attached to the piles 4 of the pier as shown in Figure 2e.
After constructing additional shoring 5 and formwork 6, the upper concrete 7 is poured.When installing floating type shoring, the frame 3 is floated on the sea and the second After pulling it between the piles 4 as shown in Figure (A), the frame 3 is lifted by a lifting device 8 such as a chain block as shown in Figure (B).
Shoring is installed by replacing it with hanging materials 9 such as steel rods.
このような従来の浮上式支保工はそれ自体に浮力を有す
るのでその設置位置を満潮時水位よりも低(すると、フ
ロートを構成している部分が水面下になり、その浮力に
よって型枠を押し上げることとなるため、支保工の設置
位置を満潮時水位より高い位置に設置しなければならな
い。This kind of conventional floating shoring has its own buoyancy, so it is installed at a location lower than the water level at high tide (then the part that makes up the float will be below the water surface, and its buoyancy will push up the formwork). Therefore, the shoring must be installed at a position higher than the water level at high tide.
従って上述したような従来の支保工の設置作業には支保
工全体を吊り上げるチエンブロック等の吊り上げ装置を
必ず必要とし、しかもチエンブロックから鋼棒等への盛
りかえ作業を行わなければならないものであり、また潮
位による水面高さの変動に影響されない位置に設置する
必要上支保工の設置位置が高くならざるを得す、従って
桟橋下面と支保工との空間部が狭くなり、枠体−Fにお
ける作業空間が充分に取れないために作業能率が悪くな
らざるを得す、さらに支保工撤去のためほに設置時と同
様多数のテエンブロック等のけん引接が必要であること
や浮皮保工の吊材からテエンブロックに盛りかえる作業
が必要となる等の欠点があった。Therefore, the conventional shoring installation work described above always requires a lifting device such as a chain block to lift the entire shoring structure, and it is also necessary to transfer the chain block to steel bars, etc. In addition, it is necessary to install the shoring in a position that is not affected by fluctuations in the water surface height due to the tide level, so the installation position of the shoring has to be higher.As a result, the space between the underside of the pier and the shoring becomes narrow, and the Work efficiency inevitably suffers because there is not enough work space.Furthermore, to remove the shoring, it is necessary to tow a large number of tie blocks, etc., just like when installing the shoring, and it is necessary to suspend the floating shoring. There were drawbacks such as the need for work to transfer the wood to a tea block.
本発明は上述の如き従来の問題にかんがみ、従来のよう
に支保工全体を潮位((影響されない高さにまで吊り上
げるためのテエンブロック等の吊り上げ装置を必要とせ
ず、しかも支保工組立後には水位の変動による浮力が支
保工に影響を与えないように設置ができ、更に従来に比
べ型枠組み立て等の作業空間を広(取り得る水上コンク
リート構造物施工のための支保工方法及びその装置の提
供を目的としたものであり、その要旨とするところは、
自らの浮力では浮上し得ない支保工用枠体の底面に該枠
体を浮上させるフロートを収り外し自在に取り付は水面
上に突出させて立設した水上コンクリート構造物支持用
の杭間に前記枠体を水面上に浮べて曳き入れ、該枠体を
水面上に浮上させた状態で該枠体の外周縁の枠材に対し
て長手方向に移動自在に取り付けした吊持金具をもって
前記杭に固定し、その後、前記フロートを枠体から取り
パテとともに該枠体上に立設した脚立に支持させてコン
クリート型枠を組み立て、その型枠内にコンクリートを
打設し、そのコンクリートの硬化後、前記フロートを再
度前記枠体に取り付げし、前記杭への固定を解除して浮
上させ、杭間より引き出すようにした支保工方法及びそ
の装置に存する。In view of the above-mentioned conventional problems, the present invention eliminates the need for a lifting device such as a tie block to lift the entire shoring structure to a height unaffected by the tide level (( Providing a shoring method and equipment for constructing floating concrete structures that can be installed so that the buoyancy caused by fluctuations in water does not affect the shoring, and also allows for a wider work space for formwork erection, etc. than before. Its purpose is to:
The float that floats the frame on the bottom of the shoring frame, which cannot float by its own buoyancy, can be freely installed and removed between the piles for supporting floating concrete structures that protrude above the water surface. Tow the frame body floating above the water surface, and with the frame body floating above the water surface, use a hanging bracket attached to the frame material on the outer periphery of the frame body so as to be movable in the longitudinal direction. The float is fixed to a pile, and then the float is removed from the frame and supported along with putty on a stepladder set up on the frame to assemble a concrete form, concrete is poured into the form, and the concrete is cured. Thereafter, the float is reattached to the frame body, released from being fixed to the piles, floated, and pulled out from between the piles.
次に本発明の実施例を図面について説明する。Next, embodiments of the present invention will be described with reference to the drawings.
まず、本発明方法に使用する支保工装置の実施例を第3
図〜第8図について説明する。First, a third example of the shoring device used in the method of the present invention will be described.
8 to 8 will be explained.
図中20は支保工用枠体である。In the figure, 20 is a support frame.
この枠体20は中空角筒鋼材からなろ長枠材20a及び
短枠材20bをもって平面が略長方形状に枠組され、そ
れ自体の浮力では浮上し得ない重さに成長されている。The frame 20 is made of hollow rectangular cylindrical steel material and has a substantially rectangular planar shape with a long frame 20a and a short frame 20b, and is so heavy that it cannot float by its own buoyancy.
この枠体20は数箇所に複数の短枠材20bにまたがら
せて発泡スチロールをもって長方体形状に形成したフロ
ー21が取り付けされている。Flows 21 formed into a rectangular parallelepiped using polystyrene foam are attached to the frame 20 at several locations, extending over a plurality of short frame members 20b.
このフロート21はその上面に固定用枠材22.22を
有し、その棒材22.22を二本の短枠材20b、20
F)にまたがらせ番線23をもってゆわえて短枠材20
bに両端を固定している。This float 21 has a fixing frame member 22.22 on its upper surface, and the rod member 22.22 is attached to two short frame members 20b, 20.
F) Straddle the short frame material 20 by holding the number wire 23
Both ends are fixed to b.
そしてこのフロート21により枠体20が浮上する浮力
が与えられるように(7ている。The float 21 provides buoyancy to the frame 20 (7).
尚、このフロート21は上述の如き発泡スチロールの他
金属もしくはゴム製の中空タンク状のものを使用しても
よい。Incidentally, the float 21 may be a hollow tank-shaped object made of metal or rubber other than the above-mentioned styrene foam.
枠体20には長枠材20a短枠材20bの上面に一定間
隔を隔てて多数の脚立嵌着用突起24が突設され、その
突起24に下端開口部を嵌合させて多数の脚立25が立
設されている。A large number of stepladder fitting protrusions 24 are protruded from the top surface of the long frame member 20a and short frame member 20b at regular intervals on the frame body 20, and a large number of stepladders 25 are fitted by fitting the lower end openings into the protrusions 24. It is erected.
この脚立25は各支杆25aの上端に軸方向7.二螺合
したねじ軸25bからなるジヤツキを有し、そのねじ軸
25bの上端間に横架材25cが固定されている。This stepladder 25 is attached to the upper end of each support rod 25a in the axial direction 7. It has a jack consisting of two threaded shafts 25b, and a horizontal member 25c is fixed between the upper ends of the threaded shafts 25b.
一方枠体200外周縁を構成している長枠材20aには
その複数箇所に吊り金具20が取り付けされている。On the other hand, hanging fittings 20 are attached to a plurality of locations on the long frame member 20a forming the outer peripheral edge of the frame body 200.
この吊り金具26は第7図、第8図に示すように長枠材
20aに対し巻き掛けてその長手方向に移動自在に取り
付けした鋼製の略U状をした帯材27とその帯材21両
端間に固着1−1た一対の鋼棒支持材28とからなり、
支持材28は断面]状の鋼材を互いに背合せに配置され
、その間に鋼棒挿入間隙29が形成されている。As shown in FIGS. 7 and 8, this hanging fitting 26 includes a substantially U-shaped steel strip 27 and a strip 21 thereof, which are wrapped around a long frame material 20a and attached so as to be movable in the longitudinal direction thereof. It consists of a pair of steel rod supports 28 fixed between both ends,
The supporting members 28 are made of steel members having a cross section of 100 mm, which are arranged back to back to each other, and a steel rod insertion gap 29 is formed therebetween.
また長枠材20aの上面には隣接する他の枠体20ど連
結するための連結材止め金具30が一定間隔毎に立設さ
れている。Further, on the upper surface of the long frame member 20a, connecting member fasteners 30 for connecting other adjacent frames 20 are erected at regular intervals.
次に上述の装置を使用1−た本発明工法の実施例を第9
図以下の図面について説明する。Next, Example 9 of the method of the present invention using the above-mentioned device will be described.
The following drawings will be explained.
図中31は上端をハイウォーターレベルL1及ローウォ
ーターレベルL2 より高(して水面上に突出させて
海底より立設した鋼管杭である。In the figure, 31 is a steel pipe pile erected from the seabed with its upper end raised above the water surface (higher than the high water level L1 and low water level L2).
この杭31間に前述した枠体20にフロート21を取り
付けし、かつ上面に脚立25を立設した状態で曳航する
。The float 21 is attached to the frame 20 mentioned above between the piles 31, and the boat is towed with the stepladder 25 erected on the upper surface.
そして水面が通常の最低潮位より即ち、ローウォーター
レベルト2高い位置にあるとき、好ましくは満潮時に枠
体20と杭31の上端間に吊り下げ用鋼棒32を連結す
る。When the water surface is higher than the normal lowest tide level, that is, at a position higher than the low water level 2, preferably at high tide, a hanging steel rod 32 is connected between the upper end of the frame 20 and the stake 31.
この連結は第10図に示すように杭31の上端1(鋼製
プレート33を水平方向に突設しておき、このプレート
33の孔33aに鋼棒32の上端を挿入し、プレート3
3上で鋼棒3〕にナツト34を螺嵌し、その鋼桐2の下
端を前述した吊り金具26の鋼棒挿入間隙9に挿入し、
支持材28下において座金35及びナツト36を螺嵌す
ることにより行う。For this connection, as shown in FIG.
3, screw the nut 34 onto the steel rod 3], insert the lower end of the steel paulownia 2 into the steel rod insertion gap 9 of the above-mentioned hanging fitting 26,
This is done by screwing a washer 35 and a nut 36 under the support member 28.
これに使用する鋼棒32としては一例として全長に亘っ
て螺旋状配置に突起を設けた異形鋼棒を所望長さに切断
して用いる外、両端部にねじを刻設したねじ付付鋼棒を
用いる。Examples of the steel rod 32 used for this include a deformed steel rod with protrusions arranged in a spiral arrangement along its entire length, cut to the desired length, and a threaded steel rod with threads carved on both ends. Use.
このようにして複数の枠体20を同じ高さにして並列に
取り付けし、各枠体20間を互いに水平方向に連結する
。In this way, a plurality of frames 20 are installed in parallel at the same height, and the frames 20 are connected to each other in the horizontal direction.
この連結は第10図に示すように長枠材20a上面の金
具30に連結ボルト37を挿通し、ナツト38を締めつ
げて枠体20相互間を連結するとともに吊り金具20と
杭31間に楔39を打ち込み、杭31に対し水平方向に
も固定する。For this connection, as shown in FIG. 10, a connecting bolt 37 is inserted into the metal fitting 30 on the top surface of the long frame member 20a, and a nut 38 is tightened to connect the frames 20 to each other, and a wedge is formed between the hanging metal fitting 20 and the stake 31. 39 and fix it to the pile 31 in the horizontal direction as well.
このようにして枠体20を水面上に浮かせた状態で杭3
1に固定した後、潮位が低下すると枠体20は鋼棒32
によって吊り下げられた状態となりその底面と水面との
間に間隙が生じる。In this way, with the frame body 20 floating on the water surface, the pile 3
1, and when the tide level decreases, the frame 20 moves to the steel rod 32.
This results in a suspended state, and a gap is created between the bottom and the water surface.
そこで番線23を切断して枠体20に対するフロート2
1の固定を解き、水面上に落下させて回集する。Therefore, the number wire 23 is cut and the float 2 is attached to the frame body 20.
Unfix 1, let it fall onto the water surface, and collect it.
このフロート21の取り外し、により枠体20は水面上
に自ら浮上する浮力が取り除かれ、次に潮位が上昇した
場合でも浮上することのない状態となって杭31に支持
される。By removing the float 21, the buoyant force that causes the frame body 20 to float on the water surface is removed, and the frame body 20 is supported by the piles 31 without floating even when the tide level rises next time.
このようにして吊り下げ支持された枠体20上の脚立2
5のねじ軸25bにより横架材25cの高さを調節し、
その上面に適宜角材40を介して型枠41を組み立てて
支持させる。Stepladder 2 on frame 20 suspended and supported in this way
Adjust the height of the horizontal member 25c with the screw shaft 25b of No. 5,
A formwork 41 is assembled and supported on the upper surface of the formwork 41 via square timbers 40 as appropriate.
このようにして形成された支保工上の型枠41内にコン
クリート42を打設し、杭31に支持させて水上コンク
リート構造物を構築する。Concrete 42 is poured into the formwork 41 on the shoring thus formed and supported by the piles 31 to construct a floating concrete structure.
そして型枠41内へ打設したコンクリ−)42の硬化後
、脚立25を取り外して型枠41を外すとともに各枠体
20間を水平方向に連結しているボルト37を外す。After the concrete 42 poured into the formwork 41 has hardened, the stepladder 25 is removed and the formwork 41 is removed, and the bolts 37 horizontally connecting each frame body 20 are removed.
然る後、低潮位時を見図って再びフロート21を枠体2
0下に曳き入れ、番線23を使用して再度取り付けした
後、コンク!、1−)42下面位置で鋼棒32を切断し
、枠体20を次の施工箇所に曳航し、前述と同様に支保
工組み立てを行う。After that, the float 21 was moved to the frame 2 again in anticipation of the low tide level.
After pulling it under 0 and reinstalling it using wire number 23, Conch! , 1-) The steel rod 32 is cut at the lower surface position of 42, the frame body 20 is towed to the next construction location, and the shoring is assembled in the same manner as described above.
尚上述の実施例では潮位の変動を利用してフロート21
の脱着及び枠体20の杭への着脱を行っているが、潮や
潮の干満の少ない海岸においては潮位にかかわりなくこ
れらの作業を順次行う。In the above embodiment, the float 21 is
and attaching and detaching the frame body 20 to and from the piles, but on a coast where the tides and tides are low, these operations are performed sequentially regardless of the tide level.
本発明の工法及びその装置は上述のように構成され、フ
ロート?支保工用枠体に対して取り外し可能に取り付け
し、水上に浮上させた状態でその枠体を杭へ固定し、そ
の後フロートの取り外しを行うよう如したことにより、
従来のように枠体を潮立に影響されない高さまで吊り上
げるジヤツキ等の装置を使用する必要がなくなり、装置
自体が簡略化されてコスト減が図られ、また枠体取り付
は作業もジヤツキ等で吊り少しるものに比べ著し; く
簡略化し得ると同時に作業の危険性も少(なったもので
ある。The construction method and device of the present invention are constructed as described above, and include a float? By removably attaching it to the shoring frame, fixing the frame to the pile while floating above water, and then removing the float,
It is no longer necessary to use equipment such as jacks to lift the frame to a height where it is not affected by tides, as in the past, and the equipment itself is simplified and costs are reduced, and the frame installation work can be done with jacks, etc. It is much simpler and less dangerous to work with than when it is suspended.
更にまた枠体と;テ引き上げて吊り持ちするものでない
ため枠体とコンクリート構造物との間隔を大きく取るこ
とができ型組や支保工材の組み立で、取り外しの作業性
も向上されたものである。Furthermore, since the frame is not lifted up and held, it is possible to increase the distance between the frame and the concrete structure, and the ease of work when assembling forms and supporting materials and removing them has also been improved. be.
また本発明装置において、吊り金具を枠体に対し長手方
向に移動し、得るようにしたことによって例えば杭の打
込位置が設計ど多少ずれた場合でも吊下げ連結位置の整
合が容易となり適切な吊り下げ状態が容易に得られるこ
ととなったものである。In addition, in the device of the present invention, by moving the hanging metal fittings in the longitudinal direction with respect to the frame body, even if the driving position of the pile is slightly different from the design, for example, it is easy to align the hanging connection position. This makes it easy to obtain a suspended state.
第1図は従来の支保工に使用する浮上曳航式支保工の主
構を示す平面図、第2図は同支保工の組立工程を示す正
面図、第3図は本発明のフロート式支保工装置の平面図
、第4図は第3図中の1−1線断面図、第5図は脚立を
取り付けた状態の部分拡大側面図、第6図は脚立の嵌合
状態の部分拡大断面図、第7図は吊り金具部分の縦断面
図、第8図は第7図中の1−1線断面図、第9図は本発
明工法の施工状態を示す正面図、第10図は鋼棒による
連結状態の断面図である。
20・・・支保工用枠体、20a・・・長枠材、20b
・・・短枠材、21・・・フロート、25・・・脚立、
26・・・吊り金具、31−・・鋼管杭、32・・・吊
り下げ用鋼棒。Fig. 1 is a plan view showing the main structure of a floating towed shoring used for conventional shoring, Fig. 2 is a front view showing the assembly process of the shoring, and Fig. 3 is a floating towed shoring of the present invention. A plan view of the device, FIG. 4 is a sectional view taken along the line 1-1 in FIG. 3, FIG. 5 is a partially enlarged side view with the stepladder attached, and FIG. 6 is a partially enlarged sectional view of the stepladder in the fitted state. , Fig. 7 is a vertical cross-sectional view of the hanging metal part, Fig. 8 is a cross-sectional view taken along the line 1-1 in Fig. 7, Fig. 9 is a front view showing the construction state of the method of the present invention, and Fig. 10 is a steel rod. FIG. 20... Frame for shoring, 20a... Long frame material, 20b
...Short frame material, 21...Float, 25...Stepladder,
26... Hanging fittings, 31-... Steel pipe piles, 32... Steel rods for hanging.
Claims (1)
該枠体を浮上させるフロートを取り外し自在に取り付け
、水面−Eに突出させて立設した水上コンクリート構造
物支持用の杭間に前記枠体を水面−Lに浮べて曳き入れ
、該枠体を水面上に浮上させた状態で該枠体の外周縁の
枠材に対して長手方向に移動自在に取り付けした吊持金
具をもって前記杭に固定し、その後、前記フロートを枠
体から取り外すとともに該枠体上に立設(、た脚立に支
持させてコンクリート型枠を組み立て、その型枠内にコ
ンクリートを打設し、そのコンクリートの硬flu、前
記フロートを再度前記枠体に取り付けし、前記杭への固
定を解除して浮上させ、杭間より引き出すことを特徴と
してなる水上コンクリート構造物施工のための支保工方
法。 2 鋼材をもって枠組した支保工用枠体の複数箇所に該
枠体を水面上に浮上させるためのフロートを取り外し自
在に備えるとともに該枠体の上面に脚立を立設し、かつ
前記枠体の外周枠に対し長手方向に摺動自在に取り付け
した吊持金具を備え、該吊持金具に吊持用の鋼棒を取り
付は自在にしてなる水上コンクリート構造物施工のため
の支保工装置。[Claims] 1. A floating concrete structure in which a float for levitating the frame is removably attached to the bottom surface of a shoring frame that cannot float by its own buoyancy, and is erected so as to protrude from the water surface -E. The frame body is floated on the water surface -L and towed between the supporting stakes, and while the frame body is floating on the water surface, it is attached so as to be freely movable in the longitudinal direction with respect to the frame material on the outer periphery of the frame body. Then, remove the float from the frame and place it upright on the frame (support it on a stepladder, assemble a concrete formwork, and pour concrete into the formwork. Support for constructing a floating concrete structure, characterized in that the concrete has a hard flu, the float is reattached to the frame, the fixation to the pile is released, it floats, and it is pulled out from between the piles. Construction method. 2. Floats for floating the frame above the water surface are removably provided at multiple locations on a shoring frame made of steel materials, and a stepladder is erected on the top surface of the frame, and the frame is Support for constructing a floating concrete structure, comprising a suspension fitting attached to the outer peripheral frame of the body so as to be slidable in the longitudinal direction, and a steel rod for suspension can be freely attached to the suspension fitting. Device.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16352681A JPS5949962B2 (en) | 1981-10-15 | 1981-10-15 | Shoring method and equipment for construction of floating concrete structures |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16352681A JPS5949962B2 (en) | 1981-10-15 | 1981-10-15 | Shoring method and equipment for construction of floating concrete structures |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5865810A JPS5865810A (en) | 1983-04-19 |
| JPS5949962B2 true JPS5949962B2 (en) | 1984-12-05 |
Family
ID=15775540
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16352681A Expired JPS5949962B2 (en) | 1981-10-15 | 1981-10-15 | Shoring method and equipment for construction of floating concrete structures |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5949962B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4630500B2 (en) * | 2001-08-28 | 2011-02-09 | 日鐵住金建材株式会社 | Floating girder for underwater / water structure support |
| CN1296565C (en) * | 2004-03-16 | 2007-01-24 | 陈法根 | Frame mount type combined dam |
-
1981
- 1981-10-15 JP JP16352681A patent/JPS5949962B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5865810A (en) | 1983-04-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3466878A (en) | Rig for work at sea,in lakes,lagoons | |
| JP2557740B2 (en) | Tendon tension introduction method for vertical mooring offshore floating platform | |
| KR910001393B1 (en) | How to install the casing and its casing on the water floor | |
| JPS5949962B2 (en) | Shoring method and equipment for construction of floating concrete structures | |
| CN223168957U (en) | Cultivation system for seafloor | |
| JP5637480B2 (en) | Dismantling method of support for slab construction in pile pier construction | |
| US6748717B2 (en) | Method and system for emplacing prefabricated buildings | |
| CN116201151B (en) | Comprehensive cofferdam system and installation and removal method | |
| CN216475698U (en) | Assembled steel tube bundle shear wall | |
| JP2001140221A (en) | Repair method of overhang floor slab and support structure of formwork | |
| CN213539298U (en) | Adjustable diagonal support for square-connected reticulated shell canopy structure | |
| CN223017533U (en) | Mooring steel structure of steel pipe rack | |
| JP2012225002A (en) | Scaffold construction method and scaffold structure for water-area structure | |
| KR100823005B1 (en) | Pier construction method | |
| CN113152496A (en) | Water sealing sleeve box for underwater welding of bracket on steel casing | |
| CN223203006U (en) | A vertical ladder for dock wall | |
| CN217149906U (en) | A suspend construction structures in midair for crossing construction between sluice pier | |
| JPS5826446B2 (en) | Shoring method for floating structures | |
| CN119174404B (en) | Construction methods and aquaculture systems for seabed aquaculture | |
| CN221989312U (en) | Temporary scaffold device for large-size reinforcement cage | |
| CN119287851B (en) | Suspension type conduit frame high pile wharf structure suitable for super-large water depth and construction method | |
| CN220704773U (en) | Embedded part for steel structure of large-span factory building | |
| CN213538865U (en) | Trash rack for pump station | |
| SU1257348A2 (en) | Support for underground pipeline in soft soil | |
| CN218301545U (en) | Base station base and communication base station comprising same |