JPS599694B2 - "Ten" leveling method and its weight for underwater rubble foundation - Google Patents
"Ten" leveling method and its weight for underwater rubble foundationInfo
- Publication number
- JPS599694B2 JPS599694B2 JP10988080A JP10988080A JPS599694B2 JP S599694 B2 JPS599694 B2 JP S599694B2 JP 10988080 A JP10988080 A JP 10988080A JP 10988080 A JP10988080 A JP 10988080A JP S599694 B2 JPS599694 B2 JP S599694B2
- Authority
- JP
- Japan
- Prior art keywords
- weight
- turret
- height
- wire rope
- scale
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
Description
【発明の詳細な説明】
本発明は防波堤等の構築に際し、ケーソンあるいはブロ
ック等を設置する水中捨石基礎の天端を均す水中捨石基
礎の暖圧均し工法とその重錘に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a warm-pressure leveling construction method for an underwater ripple foundation for leveling the top of an underwater ripple foundation on which a caisson or block is installed when constructing a breakwater, etc., and a weight thereof.
従来、上記水中捨石基礎の天端を均す作業はその殆んど
が潜水夫の水中作業によるもので、その手順を説明する
に、捨石を略計画高さ迄投下したのち所要位置に潜水船
をアンカーロープ等で固定させ、綱夫はたとえば既設ケ
ーソン上にいる測量者の指示に従って錘を水中に降ろし
て杭を打つ位置を潜水夫に知らせ、これにより潜水夫は
指定された位置に所要長さの杭を順次打ち込み、捨石基
礎の均し巾の位置に杭を列設する。Conventionally, most of the work to level the top of the underwater rubble foundation mentioned above was carried out underwater by divers.To explain the procedure, the rubble is dropped to approximately the planned height, and then a submersible is placed at the required position. The rope is fixed with an anchor rope, etc., and the rope man lowers a weight into the water and informs the diver of the position to drive the stake, according to the instructions of the surveyor on the existing caisson. Drive the piles one after another, and place the piles in rows at the leveled width of the rubble foundation.
次に綱夫は、箱尺を水中に降ろし、その下端を潜水夫が
上記杭の天端上に固定して支えている間に、前記測量者
が該杭の天端高さを測定し、以下同様にして各杭の天端
高さを測定するとともに、その測定結果に基づいて潜水
夫が捨石基礎の天端の計画高さより高い杭はその分を切
除し、また低い杭はその分を継ぎ足して各杭の天端を上
記計画高さに揃える。Next, Tsunao lowered the box measure into the water, and while the diver fixed and supported the bottom end on the top of the pile, the surveyor measured the height of the top of the pile. In the same way, the height of the top of each pile was measured, and based on the measurement results, the diver removed the piles that were higher than the planned height of the top of the rubble foundation, and added the height of the piles that were lower. Align the top of each pile with the above planned height.
次に潜水夫が貫を上記各杭の列設方向に向け架設して縦
定規とし、また上記貫間に別の貫を架設して水平定規と
し、これによシ遣形の設置を終える。Next, the diver erects a through hole in the direction in which the piles are arranged to serve as a vertical ruler, and erects another through hole between the above-mentioned through holes to serve as a horizontal ruler, thereby completing the installation of the shikake-gata.
次に、上記遣形を基準にして潜水夫によって捨石の過不
足を調節し天端を計画高さに均していくものである。Next, based on the above-mentioned shape, the diver adjusts the excess and deficiency of rubble to level out the top to the planned height.
上述の如く従来の水中捨石基礎の均し作業はその殆んど
が潜水夫による水中作業で、しかも手作業によるので、
極めて作業性が悪く、特に波浪条件の悪い時あるいは濁
りによって視界の悪い時等は極度に作業性が低下し、か
つ危険でもあるばかりか、手作業により均すだけで締め
固めをしないので天端が不安定でもあり、ひいては工期
の長期化および工費の増大の一因ともなっている。As mentioned above, most of the conventional leveling work for underwater rubble foundations is done underwater by divers, and moreover, by hand.
It is extremely difficult to work, especially in bad wave conditions or when visibility is poor due to turbidity. Not only is it extremely difficult to work, but it is also dangerous. It is also unstable, which is one of the causes of prolonging construction periods and increasing construction costs.
また、水深が大きくなるに深って潜水夫の作業性は極度
に悪化し、かつ危険も増大し例えば水深20〜30mで
の潜水夫による大端均し作業は実際上不可能に近いもの
である。In addition, as the water gets deeper, the workability of the diver becomes extremely worse and the danger also increases. For example, it is practically impossible for a diver to level the large pieces at a depth of 20 to 30 meters. be.
本発明は、上記従来の欠点に鑑み、大水深における捨石
基礎の天端をも、全ての操作を水上で行いながら能率的
かつ安全にしかも強固に轢圧均しできるようにするもの
である。In view of the above-mentioned conventional drawbacks, the present invention makes it possible to efficiently, safely, and firmly level the top of a rubble foundation in deep water while performing all operations above water.
以下には図示の実施例についてまず本発明帳圧均し用重
錘を説明し、その後にこの重錘を使用した本発明工法に
ついて説明する。In the following, the weight leveling weight of the present invention will be explained with reference to the illustrated embodiment, and then the construction method of the present invention using this weight will be explained.
第6,8図は水深30mの水中捨石基礎1の天端を穣圧
均しする重錘2を示す。Figures 6 and 8 show a weight 2 for leveling the top of an underwater rubble foundation 1 at a depth of 30 m.
この重錘2は錘体3に角形の櫓4を設立したもので、そ
の櫓4は上枠体5及び中枠体6と上記錘体3に起立させ
た下枠体7との3つに分離可能にしてあり、クレーン船
、既設ケーソン、ケーソンヤード等で連結して所期の使
用状態に組立て、不使用時には分離しておくことができ
る。This weight 2 has a rectangular tower 4 installed on a weight body 3, and the tower 4 has three parts: an upper frame body 5, a middle frame body 6, and a lower frame body 7 erected on the weight body 3. They are designed to be separable, and can be assembled into the desired state of use by connecting them on a crane ship, existing caisson, caisson yard, etc., and can be separated when not in use.
上記錘体3は、極厚鋼板により正方形(7〜10m”)
に形成した錘板8の上面四隅部分に型鋼材製の支柱9を
設立しその各上端に鋼材製の方形枠板10を装架固着し
て形成した収納空処に錘箱11を収納してなり高さは4
mにしてある。The weight body 3 is made of extra-thick steel plate and has a square shape (7 to 10 m”).
A weight box 11 is stored in a storage cavity formed by installing pillars 9 made of shaped steel at the four corners of the upper surface of the weight plate 8 formed in the shape of the frame, and mounting and fixing a rectangular frame plate 10 made of steel to each upper end of the pillars 9. The height is 4
It is set to m.
上記錘箱11はその中に屑鉄、砂鉄等を充填してなり、
上記収納空処にその上面開口から入れて4個積み重ね、
蓋板12により上記上面開口を閉じてある。The weight box 11 is filled with scrap iron, iron sand, etc.
Put 4 pieces into the storage cavity from the top opening and stack them.
The upper opening is closed by a cover plate 12.
しかして、錘体3の水中での重量は錘箱11の重量若し
くは収納数を加減することにより例えば20〜60tの
範囲内で調節できるようになっている。Thus, the weight of the weight body 3 in water can be adjusted within a range of, for example, 20 to 60 tons by adjusting the weight or the number of weight boxes 11 stored.
13は上記方形枠板10の上面四隅部分に設けた吊環で
、これにワイヤーロープ14の先端を係止してクレーン
15で錘体3を吊架するためのものである。Reference numeral 13 denotes suspension rings provided at the four corners of the upper surface of the rectangular frame plate 10, to which the tips of the wire ropes 14 are locked and the weight body 3 is suspended by the crane 15.
前記下枠体7は、錘体3の方形枠板10の上面四隅部分
に下端を固着して設立した4本の支柱16に梁17及び
筋交18を適宜の間隔で配置して高さ7mの角柱櫓形に
組み、支柱16の上端に鋼板で額縁状に形成した連結方
形枠板19を固着している(第2図)。The lower frame body 7 has a height of 7 m by arranging beams 17 and braces 18 at appropriate intervals on four pillars 16 whose lower ends are fixed to the four corners of the upper surface of the rectangular frame plate 10 of the weight body 3. A connecting rectangular frame plate 19 made of a steel plate and shaped like a frame is fixed to the upper end of the support column 16 (Fig. 2).
上記連結方形枠板19ぱ周囲にボルト20の挿通孔21
を所要の間隔をあげて列設し、四隅の各内側部分に固着
した三角形の補強片22に前記ワイヤーロープ14の挿
通孔23を形成し、かつこの挿通孔23にゴム製の緩衝
環24を嵌着している(第3図)。An insertion hole 21 for a bolt 20 is provided around the connection rectangular frame plate 19.
The wire ropes 14 are arranged in a row at a required interval, and a through hole 23 for the wire rope 14 is formed in the triangular reinforcing piece 22 fixed to the inside of each of the four corners, and a rubber buffer ring 24 is inserted into the through hole 23. It is fitted (Figure 3).
前記中枠体6は、4本の支柱25に梁26及び筋交27
を適宜の間隔で配置して高さ9mの角柱櫓形に組み、支
柱25の上端と下端に前記下枠体7の連結方形枠板19
と同じ構成の連結方形枠板19.19を固着している。The middle frame body 6 includes four pillars 25, beams 26 and braces 27.
are arranged at appropriate intervals and assembled into a prismatic turret shape with a height of 9 m, and connecting rectangular frame plates 19 of the lower frame body 7 are attached to the upper and lower ends of the pillars 25.
A connecting rectangular frame plate 19.19 having the same configuration as that is fixed.
前記上枠体5は、4本の支柱28に梁29及び筋交30
を適宜の間隔で配置して高さ12mの角柱櫓形に組み、
支柱28の下端に前記中枠体6の連結方形枠板19と同
じ構成の連結方形枠板19を固着するとともに、支柱2
8の上側約4mの高さ部分の周囲4面に鋼製の側板31
を張設し、かつ支柱28の上端に鋼製で方形の水平定規
板32を支柱28の軸線に直交させて張設している。The upper frame body 5 includes four pillars 28, beams 29 and braces 30.
arranged at appropriate intervals and assembled into a prismatic turret shape with a height of 12 m.
A connecting rectangular frame plate 19 having the same structure as the connecting rectangular frame plate 19 of the middle frame body 6 is fixed to the lower end of the support column 28, and
Steel side plates 31 are installed on four sides around the approximately 4m high part above 8.
A rectangular horizontal ruler plate 32 made of steel is stretched on the upper end of the support 28 so as to be perpendicular to the axis of the support 28.
33は上記側板31の隅角部分の外側面に取り付けた目
盛尺で、それは、上,中,下枠体5,6,7を第6図に
示すように直列に連結したとき、錘板8の下面を基点と
した高さ28mないし32mの範囲の高さを1cTL単
位の目盛で表示している。Reference numeral 33 denotes a scale scale attached to the outer surface of the corner portion of the side plate 31, which corresponds to the weight plate 8 when the upper, middle, and lower frames 5, 6, and 7 are connected in series as shown in FIG. The height range from 28 m to 32 m from the bottom surface of is indicated on a scale of 1 cTL.
34は前記ワイヤーロープ14を挿通する挿通管で、そ
れは、上記側板31の隅角部分の内側に各支柱28に沿
って1本づつ合計4本垂直に装架してあり、上下端部を
ラッパ状に拡開しかつゴム製の緩衝環35(下端のもの
は図示してない)を嵌着し、上端を前記水平定規板32
の四隅部分の上面に開口させている。Reference numeral 34 denotes an insertion tube through which the wire rope 14 is inserted, and a total of four insertion tubes are installed vertically inside the corner portion of the side plate 31 along each support 28, and the upper and lower ends are connected to wrappers. A rubber buffer ring 35 (the lower end is not shown) is fitted, and the upper end is attached to the horizontal ruler plate 32.
Openings are made at the top of the four corners.
36.36は水平定規板32の上面に固着した1対の吊
環である。36. 36 is a pair of hanging rings fixed to the upper surface of the horizontal ruler plate 32.
しかして、上記上枠体5、中枠体6及び下枠体1を連結
して本発明重錘2を組立てるには、ケーソンヤード37
に各別に起立してある上枠体5、中枠体6及び下枠体7
のうち上枠体5の吊環36にクレーン15のワイヤーロ
ープ37を係止して(第4図)この上枠体5を中枠体6
の上に吊り上げ、下端の連結方形枠板19を中枠体6の
上端の連結方形枠板19に重合して起立させ(第5図)
、その重合した両連結方形枠板19.19の対応する各
挿通孔21 ,21にボルト20を挿通してナット38
を緊締しこれら上,中枠体5,6を連結固定する。Therefore, in order to assemble the weight 2 of the present invention by connecting the upper frame 5, the middle frame 6, and the lower frame 1, it is necessary to
An upper frame body 5, a middle frame body 6, and a lower frame body 7 each standing upright.
The wire rope 37 of the crane 15 is locked to the hanging ring 36 of the upper frame 5 (FIG. 4), and the upper frame 5 is attached to the middle frame 6.
The connecting square frame plate 19 at the lower end is overlapped with the connecting rectangular frame plate 19 at the upper end of the middle frame body 6 and erected (Fig. 5).
, the bolts 20 are inserted into the corresponding insertion holes 21, 21 of the overlapping connecting rectangular frame plates 19 and 19, and the nuts 38 are inserted.
are tightened to connect and fix the middle frames 5 and 6.
次に上記の如く連結した上,中枠体5,6をクレーン1
5で下枠体7の上に吊り上げて中枠体6の下端の連結方
形枠板19を下枠体7の上端の連結方形枠板19に重合
して起立させ(第6図)、その重合した両連結方形枠板
19,19の各挿通孔21,21にボルト20を挿通し
てナット38を緊締し(第8図)これら中枠体6と下枠
体7を連結固定することによって角形の櫓4と錘体3か
らなる重錘2(高さ32m)が組立てられる。Next, after connecting as above, the middle frames 5 and 6 are attached to the crane 1.
5 above the lower frame body 7, and the connecting rectangular frame plate 19 at the lower end of the middle frame body 6 is overlapped with the connecting rectangular frame plate 19 at the upper end of the lower frame body 7 to stand up (Fig. 6). The bolts 20 are inserted into the respective insertion holes 21, 21 of the connected rectangular frame plates 19, 19, and the nuts 38 are tightened (Fig. 8). By connecting and fixing the middle frame body 6 and the lower frame body 7, a square shape is formed. A weight 2 (height 32 m) consisting of a tower 4 and a weight body 3 is assembled.
上記において、連結方形枠板19,19をボルト20と
ナット38で緊締する作業は、中枠体6の上端の高さ9
m,4mの高さの錘体3上にある下枠体7の上端が位置
する高さllmの夫々比較的低い位置で行うことができ
るので作業性が良く、かつ安全性も高いものである。In the above, the work of tightening the connecting rectangular frame plates 19, 19 with the bolts 20 and nuts 38 is performed at the height 9 of the upper end of the middle frame body 6.
Since the work can be carried out at relatively low positions, ie, the height llm where the upper end of the lower frame body 7 on the weight body 3 is located at a height of 4 meters, the workability is good and safety is also high. .
また、上記の組立によって、重錘2は錘板8と水平定規
板32とが互いに平行に上下に対向し、各挿通管34と
挿量孔23とが同じく上下に対向した状態になっている
。Further, due to the above assembly, the weight plate 8 and the horizontal ruler plate 32 of the weight 2 are vertically opposed to each other in parallel, and each insertion tube 34 and the insertion hole 23 are also vertically opposed to each other. .
そして、上記重錘2を前記ワイヤーロ一プ14で吊下す
るには、クレーン15から上記ワイヤーロープ37を外
したのち、そのフック38に基端を固定した4本のワイ
ヤーロープ14の先端を上枠体5の各挿通管34から各
枠体5,6,7の上下に対向している各挿通孔23に挿
通し、先端に固着した掛吊具39を錘体2の吊環13に
係止固定するもので、このワイヤーロープ14を引張す
ることにより重錘2を吊り上げて、第8図に示すように
水中捨石基礎1の天端に起立させる。In order to suspend the weight 2 by the wire rope 14, the wire rope 37 is removed from the crane 15, and then the tips of the four wire ropes 14 whose base ends are fixed to the hooks 38 are lifted up. Each insertion tube 34 of the frame body 5 is inserted into each of the vertically opposing insertion holes 23 of each frame body 5, 6, and 7, and the hanging tool 39 fixed at the tip is locked to the hanging ring 13 of the weight body 2. By pulling this wire rope 14, the weight 2 is lifted and raised to stand on the top of the underwater rubble foundation 1, as shown in FIG.
この場合、上,中,下枠体5〜7を連結固定するときに
おいて第6図に示すように補助ロープ40を予め挿通管
34、挿通孔23に挿通しておいて、このロープ40の
一端を地上でワイヤーロープ14の先端に接続しておき
、他端を引っ張ることによりワイヤーロープ14の挿通
作業を地上で安全かつ能率的に行うことができる。In this case, when connecting and fixing the upper, middle, and lower frames 5 to 7, an auxiliary rope 40 is inserted into the insertion tube 34 and the insertion hole 23 in advance as shown in FIG. is connected to the tip of the wire rope 14 on the ground, and by pulling the other end, the wire rope 14 can be inserted safely and efficiently on the ground.
また、ワイヤーロープ14は錘体3を直接吊下し、櫓4
に対してはその挿通管34及び挿通孔23に挿通案内す
るのみにしているので、重錘2を吊下したときに錘体3
の重量負荷が櫓4に掛からないものである。In addition, the wire rope 14 directly suspends the weight body 3, and the turret 4
Since the weight body 3 is only inserted and guided through the insertion tube 34 and the insertion hole 23, when the weight 2 is suspended, the weight body 3
The weight load is not applied to the turret 4.
しかして櫓4は、水平定規板32及び目盛尺33を所定
の状態に支承することのできる強度を有する構造であれ
ばよク、シたがって可及的に軽量に構成できるものであ
る。Therefore, the turret 4 can be constructed to be as light as possible as long as it has a structure strong enough to support the horizontal ruler plate 32 and the scale scale 33 in a predetermined state.
なお、上記重錘2を上,中,下枠体5〜7に分離するに
は上記組み立ての場合の手順と逆の要領で行えばよく、
またクレーン15のフック38からワイヤーロープ14
を外すには、吊環13から外した掛吊具39に補助ロー
プ40を接続しこれを繰り出しつつフック38を地上に
降ろすことによって、30m以上の高所にある櫓4の上
端に作業員が登る必要がなく地上で着脱作業を行うこと
ができる。In addition, in order to separate the weight 2 into the upper, middle, and lower frames 5 to 7, it is sufficient to perform the above assembly procedure in the reverse order.
Also, the wire rope 14 is connected to the hook 38 of the crane 15.
To remove the turret, the worker climbs onto the upper end of the turret 4, which is at a height of 30 m or more, by connecting the auxiliary rope 40 to the hanging tool 39 that has been removed from the hanging ring 13, and lowering the hook 38 to the ground while letting it out. Installation and removal work can be done on the ground without the need for it.
次に、上記構成の重錘2を直接使用して行う本発明工法
を説明する。Next, the construction method of the present invention, which is carried out by directly using the weight 2 having the above structure, will be explained.
まず、水中捨石基礎1の天端を予め計画高さより少しく
高く形成しておき、クレーン船(図示してない)のクレ
ーン15で重錘2を天端面に吊り降ろすと、目盛尺33
の略中央から上側部分が水上に突出し、かつ天端面の凹
凸状態に応じて重錘2が傾くので、水平定規板32を基
準にしてその傾き具合で天端の凹凸を検知し、それに応
じて重錘2を1〜2m吊り上げておいて落下させ、錘板
8を天端に衝突させて標圧し、以後上記検知及び懐圧を
適宜繰り返して行い天端を荒均しする。First, the top of the underwater rubble foundation 1 is formed in advance to be slightly higher than the planned height, and when a weight 2 is lowered onto the top surface using the crane 15 of a crane ship (not shown), the scale 33
The upper part protrudes above the water from approximately the center, and the weight 2 tilts according to the unevenness of the top surface, so the unevenness of the top is detected based on the degree of inclination with respect to the horizontal ruler plate 32, and the unevenness of the top is detected accordingly. The weight 2 is lifted by 1 to 2 m and dropped, the weight plate 8 collides with the top to measure the pressure, and thereafter the above-mentioned detection and pressure are repeated as appropriate to roughly level the top.
この墜圧の際4本のワイヤーロープ14は櫓4の上端四
隅の挿通管34に挿通していて均等に緊張しているので
、櫓4を不用意に傾倒することなく直立した状態に維持
できる。During this downward pressure, the four wire ropes 14 are inserted into the insertion tubes 34 at the four corners of the upper end of the turret 4 and are equally tensioned, so the turret 4 can be maintained in an upright state without being inadvertently tilted. .
そして、上記荒均しを終えたら、重錘2を天端面に吊シ
降ろし、固定点、例えば既設ケーソン41に設置した測
量器42で測量者が目盛尺33の目盛を測量して天端高
さを測定し、これをトランシーバー等でクノーン船のオ
ペレーターニ知ラせ、それによシ重錘2の吊り降ろし高
さを調節しつつその天端が計画高さになるまでさらに慢
圧を行うものである。After completing the rough leveling, the surveyor lowers the weight 2 onto the top surface and measures the scale of the scale 33 with a surveying instrument 42 installed at a fixed point, for example, the existing caisson 41, and measures the top height. Measure the height and notify the operator of the Qnorn ship of this using a transceiver, etc., and then adjust the lifting height of the weight 2 and further apply high pressure until the top reaches the planned height. It is.
なお、上記櫓及び錘板は前記形状に限らず、例えば円形
に形成してもよいとともに、目盛尺は櫓と別体でなく櫓
の所要部分に直接表示してもよい。Note that the above-mentioned turret and weight plate are not limited to the above-mentioned shape, and may be formed, for example, in a circular shape, and the scale scale may be displayed directly on a required part of the turret instead of being separate from the turret.
また、櫓4は、その冒さ32mで3個に分離可能にし、
錘体3の重量を20〜60t、錘板を7〜10m2にし
た場合を示したが、櫓4の高さと分離個数、錘体の重量
及び錘板の大きさ等はこれに限るものでなく、水中捨石
基礎の水深、天端面の幅、クレーン船の能力等を勘案し
て適宜設定すればよいものである。In addition, the turret 4 can be separated into three pieces with a height of 32 m,
Although the case where the weight of the weight body 3 is 20 to 60 tons and the weight plate is 7 to 10 m2 is shown, the height and number of separated towers 4, the weight of the weight body, the size of the weight plate, etc. are not limited to these. , the depth of the underwater rubble foundation, the width of the top surface, the capacity of the crane ship, etc., and should be set appropriately.
以上述べたところから明らかなように本発明工法によれ
ば、全ての操作を水上でしかも機械的に饅圧均しを行う
ことができるので、従来の潜水夫により水中でしかも手
作業で均す場合に比較して、極めて作業性が良く能率的
に、かつ安全に当該基礎均しを施工できる。As is clear from the above, according to the method of the present invention, all operations can be performed on the water and mechanically, so that conventional divers can level the rice under water and manually. Compared to the conventional method, the foundation leveling can be carried out with extremely good workability, efficiency, and safety.
また、高さの測定と帳圧を同時にかつ水上で機械的に行
うことができるので、均し面積が広いときあるいは波浪
が高く、水の汚濁が激しいときにも均し作業を正確に行
い得て効果的である。In addition, since height measurement and surface pressure can be performed simultaneously and mechanically on the water, leveling work can be performed accurately even when the area to be leveled is large, the waves are high, and the water is heavily polluted. It is effective.
また本発明重錘によれば、クレーンのワイヤーロープで
錘体を直接吊下することによシ櫓に錘体の重量負荷が全
く掛からないので、櫓は目盛尺を測定可能な状態に支承
できる強度を有する構造であれば良いため可及的に軽量
で、かつ高くできるから前記実施例の如く30m程度の
大水深における水中捨石基礎の天端の懐圧均しも容易、
確実に実施できる。Furthermore, according to the weight of the present invention, by directly suspending the weight body from the wire rope of the crane, the weight of the weight body is not applied to the tower at all, so the tower can support the scale scale in a measurable state. As long as it has a strong structure, it can be made as light as possible and as high as possible, so it is easy to flatten the top of the underwater rubble foundation at a deep water depth of about 30 m as in the above example.
It can be carried out reliably.
また、櫓を軽量化した分だけ錘体の相対的重量が増大し
て重心が低くなるので、重錘をケーソンヤード、既設ケ
ーソン等に起立させておくときに安定性が良く不用意に
伏倒することなく安全性が高いものである。In addition, since the relative weight of the weight body increases by the weight of the turret, and the center of gravity is lowered, it is stable when the weight is erected in a caisson yard, an existing caisson, etc., and can be easily tipped over. It is highly safe without causing any damage.
さらに、ワイヤーロープで錘体を吊下しているが、その
ワイヤーロープを櫓の上端に挿通して該上端を支承する
ようにしたので、櫓を不用意に傾倒させることなく垂直
状態に吊下することができる。Furthermore, the weight body is suspended by a wire rope, and the wire rope is inserted through the upper end of the turret to support the upper end, so the turret can be hung vertically without accidentally tilting it. can do.
図面第1〜7図は本発明重錘の実施例を示し、第1図は
上枠体の斜視図、第2図は中枠体の斜視図、第3図は錘
体とそれに起立させた下枠体の斜視図、第4図は上記上
枠体をクレーンに吊架した状態を示す正面図、第5図は
上記クンーンに吊架した十枠体を中枠体に連結した状態
を示す正面図、第6図は上,中,下枠体を連結して重錘
を組立てた状態を示す正面図、第7図は中枠体と下枠体
との連結部分及び錘体の上側部分の要部拡大断面図、第
8図は本発明工法の説明図である。
14・・・ワイヤーロープ、3・・・錘体、4・・・櫓
、1・・・水中捨石基礎、33・・・目盛尺。Figures 1 to 7 show examples of the weight of the present invention, with Figure 1 being a perspective view of the upper frame body, Figure 2 being a perspective view of the middle frame body, and Figure 3 being the weight body and its structure erected. A perspective view of the lower frame body, Fig. 4 is a front view showing the upper frame suspended on a crane, and Fig. 5 shows a state in which the ten frame suspended on the kunun is connected to the middle frame. Front view, Figure 6 is a front view showing the state in which the weight is assembled by connecting the upper, middle and lower frames, and Figure 7 is the connecting part between the middle frame and lower frame and the upper part of the weight. FIG. 8 is an enlarged sectional view of the main part of the construction method of the present invention. 14...wire rope, 3...pyramid, 4...turret, 1...underwater rubble foundation, 33...scale scale.
Claims (1)
点にしてこの櫓の高さ方向に走行する目盛尺を設けると
ともに、クレーンによシ吊下するワイヤーロープを上記
櫓の上端部に挿通し、かつこのワイヤーロープの先端を
上記錘体に固定した重錘を、天端面を計画高さよりも少
しく高く形成した水中捨石基礎の該天端面に吊下して標
圧し、かつ上記櫓の目盛尺と既設ケーソン等の固定点に
設置した測量器とにより天端面の高さを測定しつつ当該
天端を計画高さに帳圧均しすることを特徴とする水中捨
石基礎の帳圧均し工法。 2 錘体に設立した櫓の上側部分にこの錘体の底面を基
点にしてこの櫓の高さ方向に走行する目盛尺を設けると
ともに、クレーンにより吊下するワイヤーロープを上記
櫓の上端部に挿通し、かつこのワイヤーロープの先端を
上記錘体に固定してなることを特徴とする慢圧均し用の
重錘。[Scope of Claims] 1. A scale scale is provided on the upper part of the turret established on the weight body and runs in the height direction of the turret with the bottom surface of the weight body as a reference point, and a wire rope is suspended from a crane. is inserted into the upper end of the turret, and a weight with the tip of this wire rope fixed to the weight body is suspended from the top surface of an underwater rubble foundation whose top surface is formed slightly higher than the planned height. It is characterized by leveling the height of the crest to the planned height while measuring the height of the crest using the graduated scale of the turret and a surveying instrument installed at a fixed point such as an existing caisson. Leveling method for underwater rubble foundation. 2 A scale scale that runs in the height direction of the turret with the bottom of the weight as its starting point is provided on the upper part of the turret established on the weight body, and a wire rope suspended by a crane is inserted through the upper end of the turret. A weight for leveling high pressure, characterized in that the tip of the wire rope is fixed to the weight body.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10988080A JPS599694B2 (en) | 1980-08-12 | 1980-08-12 | "Ten" leveling method and its weight for underwater rubble foundation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10988080A JPS599694B2 (en) | 1980-08-12 | 1980-08-12 | "Ten" leveling method and its weight for underwater rubble foundation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5736219A JPS5736219A (en) | 1982-02-27 |
| JPS599694B2 true JPS599694B2 (en) | 1984-03-05 |
Family
ID=14521503
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10988080A Expired JPS599694B2 (en) | 1980-08-12 | 1980-08-12 | "Ten" leveling method and its weight for underwater rubble foundation |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS599694B2 (en) |
-
1980
- 1980-08-12 JP JP10988080A patent/JPS599694B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5736219A (en) | 1982-02-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2012201012B2 (en) | Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform | |
| CN107882055A (en) | A kind of construction method of blower fan cushion cap | |
| JP4079986B1 (en) | Underwater rubble leveling device and underwater rubble leveling method | |
| CN113795642B (en) | Tool arrangement for pivoting a tower or a tower section from a non-erected position to an erected position | |
| CN109898871A (en) | Inclined in two-way steel column mounting and positioning device and localization method | |
| JPS599694B2 (en) | "Ten" leveling method and its weight for underwater rubble foundation | |
| JPS599695B2 (en) | "Ten" leveling method and its weight for underwater rubble foundation | |
| JP2000096569A (en) | Method for levelling underwater rubble mound foundation slope and weight thereof | |
| JPH0645977B2 (en) | Lift up or down construction method | |
| EP3385451A2 (en) | Support structure for an offshore wind turbine | |
| CN109356196A (en) | A kind of half covers digging Metro station excavation bracing members and support equipment, method and structure | |
| CN117404009A (en) | Mountain high-steep side slope photovoltaic bracket microporous bored concrete pile foundation drilling method and application | |
| JPS60215924A (en) | Settlement of steel skeleton for underwater foundation structure | |
| JPH0455094Y2 (en) | ||
| CN219862827U (en) | Adjustable pile foundation pouring device | |
| CN223422266U (en) | A lifting vessel for steel sheet piles | |
| JPH0326734B2 (en) | ||
| CN210134460U (en) | Pile foundation detection equipment for construction acceptance | |
| JPH10121503A (en) | Foundation construction of building on soft ground | |
| JPS5935655Y2 (en) | foundation lifting device | |
| CN223805598U (en) | A steel caisson leveling mechanism | |
| CN110872843B (en) | Construction method for controlling verticality of foundation pit section steel lattice column | |
| CN212926067U (en) | Adjustable positioning device of steel pipe pile in water area suitable for vibratory hammer construction | |
| JPS5840121Y2 (en) | Support stand for pile erection | |
| CN109469118A (en) | A kind of anchored pile-testing method load test Quick Connect Kit and anchoring pile fabrication of reinforcing cage method |