JPS599696B2 - Ten-leveling method for underwater rubble mounds - Google Patents
Ten-leveling method for underwater rubble moundsInfo
- Publication number
- JPS599696B2 JPS599696B2 JP98582A JP98582A JPS599696B2 JP S599696 B2 JPS599696 B2 JP S599696B2 JP 98582 A JP98582 A JP 98582A JP 98582 A JP98582 A JP 98582A JP S599696 B2 JPS599696 B2 JP S599696B2
- Authority
- JP
- Japan
- Prior art keywords
- mound
- height
- weight
- suspended
- caisson
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/10—Placing gravel or light material under water inasmuch as not provided for elsewhere
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Underground Or Underwater Handling Of Building Materials (AREA)
Description
【発明の詳細な説明】
本発明は、ケーソンあるいはブロック等を設置する水中
捨石マウンドの暖圧均し工法に関し、その目的は、重錘
体をクレーンに吊下した状態で上下動して行うマウンド
の帳圧均しを、そのマウンドの天端の凹凸を確認しかつ
またその天端高さを測量しながら簡単にしかも正確に実
施し、堅固な水中捨石マウンドとすることにある。[Detailed Description of the Invention] The present invention relates to a warm pressure leveling method for submerged rubble mounds in which caisson or blocks are installed, and its purpose is to level the mound by moving up and down with a weight suspended from a crane. To easily and accurately level out the weight of the mound while checking the unevenness of the top of the mound and measuring the height of the top, and to make a solid underwater rubble mound.
しかして、本発明は、上記の目的を達成するために、計
画高さより少しく高い天端のマウンドを捨石投入により
形成したのち、その上に設置しようとするケーソン等の
構造体に対応する所要の高さを有する鋼材組立支粋の下
端に極厚鋼板製の錘板を設けてなる重錘体を、クレーン
に吊下した状態で上下動して行う上記マウンドの暖圧作
業と、そのマウンド上に上記重錘体を吊り降して起立さ
せ、その傾き具合でマウンド天端の凹凸方向を検知する
とともに既設ケーソン等の固定点に設置した測量器によ
り上記マウンドの天端高さを測量する検測作業とを適宜
繰り返して行い、これにより天端を計画高さに仕上げる
こととしたもので、以下にはその実施例を具体的に説明
する。Therefore, in order to achieve the above object, the present invention forms a mound with a crown slightly higher than the planned height by inserting rubble, and then creates the required structure corresponding to a structure such as a caisson to be installed on top of the mound. The above-mentioned mound warm-pressure work is carried out by moving a weight body, which has a weight plate made of extra-thick steel plate at the lower end of a tall steel assembly support, up and down while suspended from a crane, and The above-mentioned weight body is suspended and stood upright, and the direction of unevenness of the top of the mound is detected by its inclination, and the height of the top of the mound is measured using a surveying instrument installed at a fixed point such as an existing caisson. The measurement work was repeated as appropriate to finish the top end at the planned height, and an example will be specifically described below.
まず、重錘体aは、据付け設置しようとするケーソン等
の構造体に対応する所要の高さ、さらにくわしくは、そ
の構造体の寸法、形状、またマウンド天端の水深等に適
合させた所要の高さの鋼材組立支枠bと、その下端に固
着した極厚鋼板製の錘板Cとからなる。First, the weight a has a required height that corresponds to the structure such as a caisson that is to be installed, and more specifically, the required height that corresponds to the size and shape of the structure, as well as the water depth at the top of the mound. It consists of a steel assembly support frame B with a height of , and a weight plate C made of extra-thick steel plate fixed to the lower end of the frame B.
上記鋼材組立支枠bは、4本の鋼材支柱1を平面正方形
の各隅角部に相当する関係位置に配置し、それら各鋼材
支柱1間に複数本の鋼材梁2、鋼材筋交い3を適宜張架
して組立てたもので、各鋼材支柱1の外側面には上記錘
板Cの下面を起点とした1cIfL単位で目盛った目盛
尺4を表示し、マウンド天端に重錘体aを起立させたと
き、その目盛尺4の少なくとも上側部分が水面より上方
に位置するようにしてある。The above-mentioned steel assembly support frame b has four steel supports 1 arranged at related positions corresponding to each corner of a square plane, and a plurality of steel beams 2 and steel braces 3 as appropriate between each of the steel supports 1. It is assembled by tensioning, and the outer surface of each steel support column 1 is marked with a scale 4 graduated in units of 1cIfL starting from the bottom surface of the weight plate C, and a weight body a is placed at the top of the mound. When erected, at least the upper portion of the scale 4 is positioned above the water surface.
また、上記錘板Cは、正方形状の極厚鋼板の下面に鋼製
の突起5を複数個所要の間隔で配置するとともに、その
各突起5の間の部分には上下面に貫通する複数個の水抜
孔6を設けてなる。In addition, the weight plate C has a plurality of steel protrusions 5 arranged at required intervals on the lower surface of a square-shaped extra-thick steel plate, and a plurality of steel protrusions 5 penetrating the upper and lower surfaces between the protrusions 5. A water drain hole 6 is provided.
しかして、所要の捨石投入を行うことにより、マウンド
eをその天端を計画高さより少しく高くして形成すると
ともに、該天端両側位置を旗竿7により計画巾より少し
余裕をもたせて表示し、所要の検測をしながら捨石の過
不足を調整して天端が計画高さより少しく高いことを確
認したうえ、クレーン船のクレーンにワイヤー8で吊下
した重錘体aを、マウンドe上に吊り降し、鋼材組立支
枠bの水上突出具合及び傾き具合で、天端の襲圧すべき
量(計画高さより高い分)及び凹凸方向を検知し、重錘
体aを軽く上下動して、その重錘体aがぐらつかない程
度に荒均しする。By inserting the required rubble, a mound e is formed with its top a little higher than the planned height, and the positions on both sides of the top are displayed with a flagpole 7 with a little more margin than the planned width. After making the necessary measurements and adjusting the excess and deficiency of rubble to confirm that the top was slightly higher than the planned height, the weight a suspended from the crane of the crane ship with a wire 8 was placed on top of the mound e. The amount of pressure to be applied at the top (higher than the planned height) and the direction of the unevenness are detected based on the degree of protrusion above the water and the degree of inclination of the steel assembly support frame b, and the weight body a is slightly moved up and down. Roughly level the surface to the extent that the weight a does not wobble.
そのあと、測量者9が、固定点たとえば既設ケーソンd
に設置してある測量器10により、天端上に吊り降し起
立させた重錘体aの鋼材支柱1に表示した目盛尺4を読
んで天端高さを測量し、饅圧すべき正確な数値をトラン
シーバー等でクレーン船のオペレーターに知らせる。After that, the surveyor 9 checks the fixed point, for example, the existing caisson d.
Measure the height of the crown by reading the scale 4 displayed on the steel support 1 of the weight a suspended above the crown using a measuring instrument 10 installed at Inform the crane ship operator of the numerical value using a transceiver, etc.
その数値により、オペレーターは、重錘体aの吊り上げ
高さすなわち自由落下距離を調節したうえで、その重錘
体aの吊り上げと自由落下すなわち上下動を所要回数行
って天端を軛圧し、その軛圧程度に応じて、さらに上記
自由落下距離の調節を、上記の測量器10と目盛尺4と
で天端高さを測量して行い、かつその結果にもとづき再
び重錘体aの上下動による盤圧を行うもので、かかる盤
圧作業と検測作業とを適宜繰り返すことにより、マウン
ドeの天端を計画高さどおりに水平に仕上げることがで
きる。Based on this value, the operator adjusts the lifting height of the weight a, that is, the free fall distance, and then lifts the weight a and performs the free fall, that is, vertical movement the required number of times to apply yoke pressure to the top. Depending on the degree of yoke pressure, the above-mentioned free fall distance is further adjusted by measuring the top height with the above-mentioned surveying instrument 10 and scale scale 4, and based on the result, the vertical movement of the weight body a is again adjusted. By repeating the plate pressure work and inspection work as appropriate, the top of the mound e can be finished horizontally to the planned height.
なお、この実施例では、重錘体aの鋼材組立支枠b及び
鋼板製錘板Cを平面正方形としたカ瓢これに限定される
ものでなくたとえば平面円形であってもよいものである
。In this embodiment, the steel assembly support frame b of the weight body a and the steel plate weight plate C have a square planar shape, but are not limited to this, but may have a circular planar shape, for example.
以上述べたところから明らかなとおり、本発明によれば
、クレーンに吊下した状態で上下動しマウンドの帳圧均
しを行う重錘体が、そのマウンド上に設置しようとする
ケーソン等の構造体に対応する所要の高さの鋼材組立支
枠を有するから、重錘体をマウンド上に吊り降し起立さ
せたときの上記鋼材組立支粋の水上突出具合及び傾き具
合で、天端の懐圧すべき量及び凹凸方向を検知確認し、
また固定点上の測量器により天端高さを測量しながら、
それが計画高さになるまで帳圧均しを簡単かつ正確に実
施できるものである。As is clear from the above description, according to the present invention, the weight body that moves up and down while suspended from a crane to level the net pressure of the mound is attached to a structure such as a caisson that is to be installed on the mound. Since it has a steel assembly support frame with a required height corresponding to the body, when the weight body is suspended and erected on the mound, the height of the top pocket is determined by the degree of protrusion above water and the degree of inclination of the steel assembly support frame. Detect and confirm the amount of pressure to be applied and the direction of unevenness,
In addition, while measuring the height of the crown with a surveying instrument on a fixed point,
It is possible to easily and accurately level the net pressure until it reaches the planned height.
また、上記重錘体は鋼材組立支粋の下端に極厚鋼板製の
錘板を設けてなるため、重心が低く安定性がよク、シた
がって、吊下してする上下動を円滑にでき、しかも帳圧
はその錘板の衝撃によって直接行われるのできわめて効
果的なものである。In addition, since the above-mentioned weight body is made of a weight plate made of extra-thick steel plate at the lower end of the steel assembly support, the center of gravity is low and stability is improved, so vertical movement when suspended is smooth. Moreover, it is extremely effective because the pressure is applied directly by the impact of the weight plate.
そのうえ、本発明によれば、計画高さにより少しく高い
天端のマウンドを捨石投入により形成する作業と、クレ
ーンに吊下した上記重錘体にょる帳圧作業と、固定点に
設置した測量器による天端高さの計測作業といういずれ
も水上操作の可能な機械的作業によって、ケーソン等の
構造体を据付け設置するのに必要な水平で堅固な仕上げ
とした天端を有する水中捨石マウンドを簡単に得ること
ができるものであり、また少なくとも上記各作業に関し
、潜水夫による手作業を要しないことによるメリットは
、水の汚濁、波浪、水深等の影響を受けないものである
ことにおいて顕著であり、このため工期の短縮、工費の
節減等に役立つものである。Moreover, according to the present invention, the work of forming a mound at the top slightly higher than the planned height by introducing rubble, the work of applying pressure using the above-mentioned weight suspended from a crane, and the surveying instrument installed at a fixed point are performed. Measuring the height of the crown using a mechanical process that can be operated on water makes it easy to construct an underwater rubble mound with a horizontal and solid top that is necessary for installing structures such as caissons. At least with regard to each of the above tasks, the advantage of not requiring manual labor by divers is remarkable in that it is not affected by water pollution, waves, water depth, etc. Therefore, it is useful for shortening the construction period and reducing construction costs.
図面は本発明の実施例を示し、第1図は施工状況の説明
図、第2,3図は重錘体の側面図及び斜視図である。
e・・・マウンド、d・・・ケーソン、b・・・鋼材組
立支枠、C・・・錘板、10・・・測量器。The drawings show an embodiment of the present invention, and FIG. 1 is an explanatory view of the construction situation, and FIGS. 2 and 3 are a side view and a perspective view of the weight body. e...mound, d...caisson, b...steel assembly support frame, C...weight plate, 10...surveying instrument.
Claims (1)
によシ形成し、その上に設置しようとするケーソン等の
構造体に対応する所要の高さを有する鋼材組立支粋の下
端に極厚鋼板製の錘板を設けてなる重錘体を、クレーン
に吊下した状態で上下動して行う上記マウンドの標圧作
業と、そのマウンド上に上記重錘体を吊り降して起立さ
せ、その傾き具合でマウンド天端の凹凸方向を検知する
とともに、既設ケーソン等の固定点に設置した測量器に
よシ上記マウンドの天端高さを測量する検測作業とを適
宜繰り返して行い、これにより天端を計画高さに仕上げ
ることを特徴とする水中捨石マウンドの慢圧均し工法。1 A mound at the top slightly higher than the planned height is formed by inserting rubble, and an extra-thick steel plate is placed at the lower end of the steel assembly support with the required height to correspond to the structure such as a caisson to be installed on top of the mound. The above-mentioned mound marking work is carried out by moving a weight body provided with a weight plate made of aluminum up and down while suspended from a crane, and the above-mentioned weight body is suspended and erected on the mound. In addition to detecting the unevenness direction of the top of the mound based on the degree of inclination, the height of the top of the mound is repeatedly measured using a surveying instrument installed at a fixed point such as an existing caisson. A high-pressure leveling construction method for underwater rubble mounds that is characterized by finishing the top to the planned height.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP98582A JPS599696B2 (en) | 1982-01-08 | 1982-01-08 | Ten-leveling method for underwater rubble mounds |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP98582A JPS599696B2 (en) | 1982-01-08 | 1982-01-08 | Ten-leveling method for underwater rubble mounds |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2332577A Division JPS53108640A (en) | 1977-03-05 | 1977-03-05 | Compaction levelling method of underwater rubbleemound foundation and weight for compaction levelling rubbleemound |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS57197325A JPS57197325A (en) | 1982-12-03 |
| JPS599696B2 true JPS599696B2 (en) | 1984-03-05 |
Family
ID=11488887
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP98582A Expired JPS599696B2 (en) | 1982-01-08 | 1982-01-08 | Ten-leveling method for underwater rubble mounds |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS599696B2 (en) |
-
1982
- 1982-01-08 JP JP98582A patent/JPS599696B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS57197325A (en) | 1982-12-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| AU2012201012B2 (en) | Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform | |
| CN105986676B (en) | Large-span concrete floor flatness control system and use method | |
| KR20220067201A (en) | Coastal Underwater Survey Unit | |
| CN108303072A (en) | A kind of measuring device and measurement method in gate recess installation process | |
| CN107255473B (en) | measuring method for establishing dynamic reference plane | |
| JPS599696B2 (en) | Ten-leveling method for underwater rubble mounds | |
| JPH07229300A (en) | Base surface leveller and method of construction levelling base surface | |
| JP2005248661A (en) | Breakwater construction method and indicator jig | |
| JPS599695B2 (en) | "Ten" leveling method and its weight for underwater rubble foundation | |
| CN207991553U (en) | A kind of measuring device in gate recess installation process | |
| CN213748228U (en) | Detection apparatus for pier top support embedded hole position | |
| CN212179887U (en) | Slope measuring device for checking sloping roof | |
| JPS60105714A (en) | Consolidating and levelling weight for underwater rubble-mound | |
| JPH073825A (en) | Fixing device and tilt measuring device | |
| CN209446028U (en) | The flat measurement of higher degree system of vibro-rammer based on mangneto displacement sensor | |
| CN213143145U (en) | Inclined rock measuring device | |
| KR20010036580A (en) | Remote control submerged finisher and method for the same | |
| JPH03264810A (en) | Position measuring method of underwater operating machine | |
| JPS60105715A (en) | Consolidating and levelling weight for underwater rubble-mound foundation | |
| JPH0623657B2 (en) | How to measure the height of structures under water | |
| CN2478921Y (en) | Underwater terrain grid measuring platform | |
| JPH0140074Y2 (en) | ||
| JP3453710B2 (en) | Free fall type underwater rubble foundation leveling method | |
| JPH05195534A (en) | Rubble leveler | |
| JPS62274210A (en) | Level crown leveling method for base concrete |