JPS6043520B2 - Upward lock bolt construction method - Google Patents
Upward lock bolt construction methodInfo
- Publication number
- JPS6043520B2 JPS6043520B2 JP54009538A JP953879A JPS6043520B2 JP S6043520 B2 JPS6043520 B2 JP S6043520B2 JP 54009538 A JP54009538 A JP 54009538A JP 953879 A JP953879 A JP 953879A JP S6043520 B2 JPS6043520 B2 JP S6043520B2
- Authority
- JP
- Japan
- Prior art keywords
- drill hole
- packer
- lock bolt
- bolt
- grout
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Rock Bolts (AREA)
Description
【発明の詳細な説明】
本発明は、継目のない長尺ロックボルトを使用して坑
内の上向き掘進時における天盤安保を行う・方法に係る
。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for securing the roof during upward excavation in a mine using seamless long rock bolts.
従来上向き掘進において天盤安保用ロックボルトを用
いる時には、水平坑道或は採掘切羽から直角方向にボル
トを運び上げねばならない都合上、使用し得るボルトの
長さがこれらの坑道又は切羽の径、高さによつて大きく
制約され、10〜15Tn、程度の長尺ロックボルトを
使用しようとする際には、短かいロックボルトを順次つ
なぎ合せて挿入しなければならなかつた。Conventionally, when using rock bolts for roof security in upward excavation, the bolts must be carried up in a perpendicular direction from a horizontal tunnel or mining face, so the length of the bolt that can be used depends on the diameter and height of these tunnels or mining faces. When using long lock bolts of about 10 to 15 Tn, it was necessary to connect short lock bolts one after another and insert them.
ロックボルトは掘削面の多数個所に挿入されるものであ
るから、このような接続作業を要することは工程管理を
複雑且つ困難にし、事故防止の観点からも好ましいもの
てはなかつた。本発明においては、上述のような欠陥を
除くために、所要の長さに切り取つた可撓性のロックボ
ルトをドリルホール中に挿入し、その周囲にグラウト剤
を注入し固定するようにしたものである。Since rock bolts are inserted at multiple locations on the excavated surface, the necessity of such connection work complicates and makes process control complicated and difficult, which is not desirable from the standpoint of accident prevention. In the present invention, in order to eliminate the above-mentioned defects, a flexible rock bolt cut to the required length is inserted into the drill hole, and grout is injected around it to fix it. It is.
以下本発明の工法につき、図面を参照して説明す一る。
第1図は、本発明による工法の一例を示すもので、ロッ
クボルト1は例えばワイヤのような可撓性材料を所定の
長さに切取つたもので、アンカー部材すなわち掛止体2
に対して溶着又は圧着等の−手段により固定されている
。The construction method of the present invention will be explained below with reference to the drawings.
FIG. 1 shows an example of the construction method according to the present invention, in which a rock bolt 1 is made by cutting a flexible material such as wire to a predetermined length, and an anchor member, that is, a hanging body 2.
It is fixed by means such as welding or crimping.
掛止体2は、第1図においては円錐台金具3とくさび4
とを組合せ、ドリルホール底部に達した時ボルトを引張
ることにより該くさびを働らかせる、いわゆるウェッジ
型のものとして示されているが、その他の公知の掛止体
、例えばエキスパンシヨン型、或は先端接着型等のいず
れでも使用することができる。次にバイブガイド5を先
端に有しているグラウト剤注入バイブ6を、ドリルホー
ル中に導入する。バイブガイド5は、後述するようにパ
ツカーとしても機能するもので、ドリルホールの内径に
対応する外径を有し、導入及び引出しに支障がないよう
に、例えば第1図に図示されるような曲線部をもつてド
リルホール内壁に接するようにされる。グラウト剤注入
バイブ6はバイブガイド5を貫通してその上側まで突出
している。さらにバイブガイド5は、その中をロックボ
ルトが通過し得るように作られる。このロックボルトの
挿通については、第1図に見られるように、グラウト剤
注入バイブ6中にロックボルトを引込み、後述するグラ
ウト剤注入作業の進行と共に引抜くようにすることがで
きる。しかし例えば第2図に見られるように、バイブガ
イド5中に、ロックボルト挿通孔をグラウト剤注入バイ
ブとは別個に形成し、注入バイブの導入、引き抜きの際
ロックボルトが該挿通孔を通過するようにすることも可
能である。The hanging body 2 includes a truncated conical fitting 3 and a wedge 4 in FIG.
It is shown as a so-called wedge type in which the wedge is activated by pulling the bolt when the bottom of the drill hole is reached, but other known latching bodies such as expansion type or can be used in any type, such as a tip-adhesive type. Next, a grouting agent injection vibe 6 having a vibe guide 5 at its tip is introduced into the drill hole. The vibe guide 5 also functions as a packer, as will be described later, and has an outer diameter corresponding to the inner diameter of the drill hole, and has a shape such as the one shown in FIG. It has a curved part and is brought into contact with the inner wall of the drill hole. The grouting agent injection vibe 6 penetrates through the vibe guide 5 and protrudes above it. Furthermore, the vibe guide 5 is made such that a lock bolt can pass through it. Regarding the insertion of the lock bolt, as shown in FIG. 1, the lock bolt can be pulled into the grouting agent injection vibe 6 and pulled out as the grouting agent injection operation, which will be described later, progresses. However, as shown in FIG. 2, for example, a lock bolt insertion hole is formed in the vibe guide 5 separately from the grouting agent injection vibe, and the lock bolt passes through the insertion hole when the injection vibe is introduced or withdrawn. It is also possible to do so.
グラウト剤注入バイブ6の先端がドリルホール底に致達
したら、図示しないグラウトポンプ或は圧縮空気により
、グラウト剤を該注入バイブ6を通してドリルホール内
に供給する。When the tip of the grouting agent injection vibe 6 reaches the bottom of the drill hole, the grouting agent is supplied into the drill hole through the injection vibe 6 using a grout pump or compressed air (not shown).
この時バイブガイド5はパツカーとして作用し、押出さ
れたグラウト剤が該バイブガイド5の位置より下に逸漏
しないように阻止する。グラウト剤の注入が進行するに
つれて、注入バイブ6はパツカー5によつて案内されな
がら、且つその上方の区間のドリルホールをグラウト剤
で充填しながら次第に引抜かれてドリルホール入口に達
する。この場合、引抜きは、ドリルホール内に空洞部を
生じないように、徐々に均一な速度で行われる。これに
より、ロックボルト1はグラウト剤によつて取囲まれた
状態においてドリルホール内に固定される。グラウト剤
注入が終つてバイブガイドがドリルホール入口に到達し
たら、注入孔を例えば第3図に見られるようなゴム製等
のプラグ7で閉塞し、モルタルを硬化させる。ロックボ
ルト用材料としては前述したようにワイヤを用いること
ができるが、、水平坑道或は採掘切羽からの搬入に支障
を生じない程度に可撓性を有し、しかも引張強度の大き
い材料、例えばFRP(繊維強化プラスチック)等も勿
論使用できる。At this time, the vibe guide 5 acts as a packer and prevents the extruded grout from leaking below the position of the vibe guide 5. As the injection of the grouting agent progresses, the injection vibrator 6 is guided by the packer 5 and is gradually pulled out while filling the drill hole in the upper section with the grouting agent and reaches the entrance of the drill hole. In this case, the drawing is carried out gradually and at a uniform speed so as not to create cavities in the drill hole. Thereby, the rock bolt 1 is fixed in the drill hole in a state surrounded by the grouting agent. When the grouting agent injection is completed and the vibe guide reaches the entrance of the drill hole, the injection hole is closed with a plug 7 made of rubber or the like as shown in FIG. 3, and the mortar is hardened. As mentioned above, wire can be used as the material for the rock bolt, but it is also possible to use a material that is flexible to the extent that it does not cause problems when being carried in from a horizontal mine shaft or mining face, and has a high tensile strength, such as a material that has a high tensile strength. Of course, FRP (fiber reinforced plastic) etc. can also be used.
但しこの場合はモルタルとの接合状態を強固にするため
に、その表面に多数の小突起を設ける等の処置をする。
本発明による工法を施工するドリルホール及び使用する
工具の寸法については特に限定されることはないが、代
表的な例としてはドリルホールの深さ10〜15TrL
1内径46〜50mm程度であり、ロックボルトとして
はワイヤの場合16mn..FRPの場合19〜22悶
程度のものが用いられ、FRP中の脱気孔の内径は4〜
6Tf0nとされる。However, in this case, measures such as providing a large number of small protrusions on the surface are taken to strengthen the bond with the mortar.
There are no particular limitations on the dimensions of the drill hole used to construct the construction method of the present invention and the tools used, but as a typical example, the depth of the drill hole is 10 to 15 TrL.
1 The inner diameter is about 46 to 50 mm, and the lock bolt is 16 mm in the case of wire. .. In the case of FRP, a material of about 19 to 22 mm is used, and the inner diameter of the deaeration hole in FRP is 4 to 22 mm.
6Tf0n.
L 本発明の工法によれば、下部水平坑道及び採掘切羽
の仕様に無関係に所望の長尺のロックボルト支保を行う
ことができ、採掘工程上、及び保安上大きな効果を挙げ
ることができる。L According to the construction method of the present invention, it is possible to provide a desired long rock bolt support regardless of the specifications of the lower horizontal tunnel and the mining face, and it is possible to achieve great effects in terms of the mining process and security.
第1図は、本発明のロックボルト支保方法の一つの実施
例を示す断面図である。
第2図は第1図に示された方法について一部を変更した
ものを示す説明図である。第3図は、ドリルホール入口
に配置されるプラグの構成を示す。)l:ロツクボルト
、2:掛止体、5:パイプガイド兼パツカー、6:グラ
ウト剤注入バイブ、7:プラグ。FIG. 1 is a sectional view showing one embodiment of the rock bolt supporting method of the present invention. FIG. 2 is an explanatory diagram showing a partially modified version of the method shown in FIG. FIG. 3 shows the configuration of the plug placed at the entrance of the drill hole. )l: lock bolt, 2: hanging body, 5: pipe guide and packer, 6: grouting agent injection vibe, 7: plug.
Claims (1)
ボルトを挿入し、グラウト剤注入パイプの先端を囲むパ
ッカーによりグラウト剤の逸出を防止しながらドリルホ
ール内にグラウト剤を注入するようにする、上向き掘進
作業のために天盤をロックボルトにより支持する方法に
おいて、ロックボルトを挿入した後、ロックボルト上端
部に取付けられた掛止体を作動させてロックボルトをド
リルホール底に固定させ、パッカー内をロックボルトが
挿通するようにしながらパッカーをドリルホール底まで
上げ、グラウト剤をドリルホール内に充填しながら、且
つ前記パッカーをガイドとしながら注入パイプを引抜く
ようにする方法。 2 特許請求の範囲1による方法において、グラウト剤
注入パイプが、その中にロックボルトを収納しながらド
リルホール底に達し、グラウト剤注入時に該ロックボル
トがグラウト剤注入パイプから引抜かれるようにされる
方法。 3 特許請求の範囲1による方法において、パツカー中
に、ロックボルト挿通孔が、グラウト剤注入パイプとは
別個に設けられている方法。 4 特許請求の範囲1から3までのいずれかによる方法
において、ロックボルトがワイヤとされる方法。 5 特許請求の範囲1から3までのいずれかによる方法
において、ロックボルトが、FRPとされる方法。[Claims] 1. A flexible grout rock bolt is inserted into the drilled drill hole, and the grout is poured into the drill hole while preventing the grout from escaping with a packer surrounding the tip of the grout injection pipe. In this method, the ceiling plate is supported by rock bolts for upward excavation work, in which the rock bolt is inserted, and then the lock bolt is drilled by operating the latch attached to the upper end of the rock bolt. The packer is fixed to the bottom of the hole, the lock bolt is inserted through the packer, the packer is raised to the bottom of the drill hole, and the injection pipe is pulled out while filling the drill hole with grout and using the packer as a guide. how to. 2. In the method according to claim 1, the grouting agent injection pipe reaches the bottom of the drill hole while housing the rock bolt therein, and the rock bolt is pulled out from the grouting agent injection pipe when grouting agent is injected. Method. 3. The method according to claim 1, wherein the lock bolt insertion hole is provided in the packer separately from the grouting agent injection pipe. 4. A method according to any one of claims 1 to 3, in which the lock bolt is a wire. 5. A method according to any one of claims 1 to 3, in which the rock bolt is made of FRP.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP54009538A JPS6043520B2 (en) | 1979-01-30 | 1979-01-30 | Upward lock bolt construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP54009538A JPS6043520B2 (en) | 1979-01-30 | 1979-01-30 | Upward lock bolt construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS55101699A JPS55101699A (en) | 1980-08-02 |
| JPS6043520B2 true JPS6043520B2 (en) | 1985-09-28 |
Family
ID=11723038
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP54009538A Expired JPS6043520B2 (en) | 1979-01-30 | 1979-01-30 | Upward lock bolt construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6043520B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS60242300A (en) * | 1984-05-14 | 1985-12-02 | 鉱研工業株式会社 | Lock bolt construction method |
| JP2007021401A (en) * | 2005-07-19 | 2007-02-01 | Asahi Kasei Chemicals Corp | Filling nozzle and construction method |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS50113006A (en) * | 1974-02-14 | 1975-09-04 | ||
| JPS52124710A (en) * | 1976-04-12 | 1977-10-20 | Katsuhiro Katase | Anchoring method |
-
1979
- 1979-01-30 JP JP54009538A patent/JPS6043520B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS55101699A (en) | 1980-08-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4036137A (en) | Method and means of extracting a soil anchor consisting of a prestressed steel tendon | |
| KR20190023619A (en) | Tunnel Reinforcement structure and Tunnel Reinforcement methods using the same | |
| JP2008522058A (en) | Pre-support tunnel construction method and equipment adapted to it | |
| US6520718B1 (en) | Sardine-bone construction method for large-section tunnel | |
| JPS6043520B2 (en) | Upward lock bolt construction method | |
| JPS6149473B2 (en) | ||
| JP4318026B2 (en) | Support structure and support method of underground cavity | |
| JPS622120B2 (en) | ||
| US4103618A (en) | Means for extracting a soil anchor consisting of a prestressed steel tendon | |
| JP4244215B2 (en) | Pipe type lock bolt and pipe type lock bolt construction method | |
| WO1992020902A1 (en) | A rock or concrete injection method and a device for performing the method | |
| CN112832776B (en) | Pre-grouting solidification treatment method for shield interval to penetrate through prestressed anchor cable area | |
| CN212614801U (en) | A fast sealing device for annular space | |
| JPH02176093A (en) | Vertical shaft for shield construction | |
| CN117145486B (en) | Drilling directional grouting method | |
| JPS6114321A (en) | Anchoring method of pile in rock with rock anchor | |
| KR0123886B1 (en) | Basic construction pile construction method and device | |
| JPS62101711A (en) | Earth anchor and its construction | |
| JP2675858B2 (en) | Vertical shaft excavation method | |
| SU1113626A1 (en) | Device for filling cracks and cavities in injection hole walls | |
| JPS58189410A (en) | Forcibly controlled injection work | |
| JPS6248040B2 (en) | ||
| JPS59145822A (en) | Construction work of underground continuous wall | |
| JPH0243410A (en) | Method for building vertical hole on underground structure | |
| JPH06158980A (en) | Method and device for starting shield machine and arriving method and device for the same |