Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS606420B2 - Construction method of hollow synthetic continuous underground wall using precast boards - Google Patents
[go: Go Back, main page]

JPS606420B2 - Construction method of hollow synthetic continuous underground wall using precast boards - Google Patents

Construction method of hollow synthetic continuous underground wall using precast boards

Info

Publication number
JPS606420B2
JPS606420B2 JP11525880A JP11525880A JPS606420B2 JP S606420 B2 JPS606420 B2 JP S606420B2 JP 11525880 A JP11525880 A JP 11525880A JP 11525880 A JP11525880 A JP 11525880A JP S606420 B2 JPS606420 B2 JP S606420B2
Authority
JP
Japan
Prior art keywords
underground wall
precast
underground
wall
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11525880A
Other languages
Japanese (ja)
Other versions
JPS5740021A (en
Inventor
清 小川
貞夫 嶋村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Konoike Construction Co Ltd
Original Assignee
Konoike Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Konoike Construction Co Ltd filed Critical Konoike Construction Co Ltd
Priority to JP11525880A priority Critical patent/JPS606420B2/en
Publication of JPS5740021A publication Critical patent/JPS5740021A/en
Publication of JPS606420B2 publication Critical patent/JPS606420B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 この発明は地中壁体にプレキヤスト板を用いた連続地中
壁の施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a continuous underground wall using precast boards for the underground wall.

従釆の連続地中壁は、鋼管、H鋼或はコンクリート杭に
よる柱列で構成する場合、掘削贋に鉄筋鍵を落し込んで
コンクリートを打設する場合とが主流である。前者の場
合にあっては、地層の透水性又は杭列の曲がり等によっ
て上記杭列の内側の掘削後に漏水が甚だしく、これを防
ぐために杭列の外側に薬液を注入しなければならない等
の欠点があった。
Continuous underground walls are mainly constructed of columns made of steel pipes, H-steel, or concrete piles, or concrete is cast by dropping reinforcing bars into the excavated ground. In the former case, there are disadvantages such as severe water leakage after excavation inside the pile row due to the permeability of the stratum or bending of the pile row, and to prevent this, chemical solution must be injected outside the pile row. was there.

また、後者の場合にあっては、凝削簿中のでし、水によ
ってコンクリートの品質、強度低下を招くと共に、ジョ
イント部の水密性及び剛性に問題点があった。この発明
の目的は、ジョイント部の後処理が自由にできて、水密
性、剛性の確保が十分であると共に、合成プレキャスト
構造であるため、地中壁コンクリートの管理が十分でき
、しかも部材寸法及び材料の壁厚低減ができる等の連続
地中壁の施工方法を提供することにある。
Moreover, in the latter case, water in the coagulation sheet causes a decline in the quality and strength of the concrete, and there are problems with the watertightness and rigidity of the joints. The purpose of this invention is to be able to freely perform post-treatment of joints, ensure sufficient watertightness and rigidity, and, since it is a synthetic precast structure, to be able to adequately manage underground wall concrete, and to maintain the size and size of the members. It is an object of the present invention to provide a method of constructing a continuous underground wall that can reduce the wall thickness of the material.

以下、この発明の実施例を添付図面に基づいて説明する
Embodiments of the present invention will be described below with reference to the accompanying drawings.

図において、Aは、工場生産された縦長な地中壁体で、
この地中壁体Aは、プレキャスト板1と、このプレキャ
スト板1の片面の少なくとも両側緑部で上記プレキャス
ト板1の上下緑間から突出するウェプ2とによって構成
されている。
In the figure, A is a vertically long underground wall produced in a factory.
This underground wall body A is constituted by a precast board 1 and a web 2 that protrudes from between the upper and lower green areas of the precast board 1 at least at both green portions on one side of the precast board 1.

上記のウヱブ2は、第1図で示したように、プレキヤス
ト板1とH鋼の片側のフランジとをジベルで合成したも
のと、第2図で示したように、内部に配筋してプレキャ
スト板1のコンクリートと一体にしたものとがあり、さ
らに、両側のウェブ2間に中間ウェブ2を設ける場合も
ある。また、図示では、プレキャスト板1の突き合せ側
面に溝部3を設けて、この溝部3内にジベル材4を突出
させたが、単にプレキャスト板1のフラットな側面を突
き合せる場合もある。
The above-mentioned web 2 is made by combining the precast plate 1 and a flange on one side of H steel with a dowel, as shown in Fig. 1, and by precasting with reinforcement inside, as shown in Fig. 2. There is one that is integrated with the concrete of the plate 1, and there is also a case where an intermediate web 2 is provided between the webs 2 on both sides. In addition, in the illustration, a groove 3 is provided on the abutting side surfaces of the precast plates 1, and the dowel material 4 is made to protrude into the groove 3, but the flat side surfaces of the precast plates 1 may simply be abutted.

次に、上記地中壁体Aを用いた連続地中壁の施工方法を
説明すると、地中蟹の施工線上で「地面から地中の所定
深さ迄掘削機により掘削しながら溝Bを設ける。
Next, to explain the method of constructing a continuous underground wall using the above-mentioned underground wall body A, it is shown that on the construction line of the underground wall, a groove B is created while excavating with an excavator from the ground to a predetermined depth underground. .

しかるのち、上記の溝Bに側面が突き合さるようにして
順次地中壁体Aを挿入するが「 その際、地中壁の内側
にウェブ2を位置させておく。
Thereafter, the underground wall bodies A are sequentially inserted into the groove B so that their sides abut against each other. At this time, the web 2 is positioned inside the underground wall.

そして、プレキャスト板1の突き合せ側面を挟んで対向
する端ウェブ2,2間に突き合せジョイント部の水密性
と剛性との確保のためコンクリートCを打つ。その後に
、地中壁体Aの内側を掘削すると共に露出するゥェブ2
の先縁部に対向状にパネル5を配置して、このパネル5
間にコンクリートを打ち込んで地中構造壁体6を造成す
る。
Then, concrete C is poured between the end webs 2, 2, which face each other with the butt sides of the precast board 1 interposed therebetween, in order to ensure the watertightness and rigidity of the butt joint. After that, the inside of the underground wall body A is excavated and the web 2 is exposed.
A panel 5 is placed oppositely on the leading edge of the panel 5.
Concrete is poured in between to create an underground structure wall 6.

なお、地中構造壁体6と地中壁体Aとを合成するために
、上記ウェプ2がH鋼である場合は、ジベルを溶楯する
In addition, in order to synthesize the underground structure wall 6 and the underground wall A, if the web 2 is made of H steel, a dowel is melted.

以上のように「 この発明に係る連続地中壁の施工方法
によれば、地中壁体にプレキャスト構造を用いているの
で、コンクリートの管理が十分にできると共に、従釆の
ように「掘削溝に鉄筋縦を落し込んでコンクリートを打
ち込んだ場合のでし・水によるコンクリートの品質強度
低下を招くようなことはない。
As mentioned above, "According to the construction method of a continuous underground wall according to the present invention, since a precast structure is used for the underground wall body, it is possible to adequately manage the concrete, and it is also possible to When concrete is poured by vertically dropping reinforcing bars into the concrete, water will not cause a decline in the quality and strength of the concrete.

また、プレキャスト板の片面の少なくとも両側に二つの
端ウェブを設けてあるので、上記プレキャスト板の突き
合せ側面を挟む両ウェブ間にコンクリートを打ち込むこ
とによって比較的簡単にジョイント部の水密性と「剛性
とを十分確保することができ、かつ地中壁体の内側掘削
後でもダイヤフラム等の設置による補強等ができる。
In addition, since two end webs are provided on at least both sides of one side of the precast board, concrete can be poured between the two webs that sandwich the abutting sides of the precast board to relatively easily improve the watertightness and stiffness of the joint. Furthermore, even after excavating the inside of the underground wall, reinforcement by installing diaphragms, etc. can be performed.

さらに、ウェブ間隔を介して地中構造壁体を造成するの
で、上記プレキャスト板と地中構造壁体との間に空間が
存在する。
Furthermore, since the underground structural wall is constructed through web spacing, a space exists between the precast board and the underground structural wall.

このため、従来の溝にコンクリートを充填させるものと
異なり、コンクリートの使用量が少なくなって資材を節
約し、安価に提供することができる。
For this reason, unlike conventional methods in which concrete is filled into grooves, the amount of concrete used is reduced, saving materials and making it possible to provide the product at low cost.

また、施工期間を短縮すると共に、ゥェブを図示のよう
に鋼材を用いた合成構造とすることによって梁、柱との
接合に際し、従来のように前もって地中壁内に継手鉄筋
、ジベルを挿入したり、或は鉄筋を露出させるために地
中壁をはつるという作業を必要とせず、上記鋼材を直接
的に便することができる。
In addition to shortening the construction period, by making the web a composite structure using steel materials as shown in the diagram, when joining beams and columns, joint reinforcing bars and dowels can be inserted into the underground wall in advance, unlike conventional methods. The above-mentioned steel materials can be used directly without the need for digging underground walls to expose reinforcing bars.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明の実施の一例を示すもので、第亀図及び第
2図は地中壁体の横断平面図「第3図は掘削溝の縦断側
面図、第4図は同上に地下壁体を挿入した縦断側面図、
第5図は同平面図、第6図は地中構造壁体を造成した縦
断側面図、第7図は同平面図、第8図は同上の斜視図で
ある。 A・…・・地中壁体「B……溝「C…・・・コンクリー
ト「 1……プレキヤスト板、2……ウェブ、3…・・
・溝部t 4……ジベル材「 6・…・・地中構造壁体
。 第1図第2図 第3図 第4図 第5図 第6図 第7図 第8図
The drawings show an example of the implementation of the present invention, and FIG. 3 is a cross-sectional plan view of an underground wall, FIG. Longitudinal side view with inserted
FIG. 5 is a plan view of the same, FIG. 6 is a vertical sectional side view of the underground structure wall, FIG. 7 is a plan view of the same, and FIG. 8 is a perspective view of the same. A...Underground wall "B...Groove"C...Concrete" 1...Precast board, 2...Web, 3...
・Groove portion t 4... Dowel material 6... Underground structure wall. Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8

Claims (1)

【特許請求の範囲】[Claims] 1 縦長な板と、この板の片面の少なくとも両側縁部で
上下端を結ぶ線上から突設したウエブとでプレキヤスト
地中壁体を形成し、地中壁の施工線上で地面から地中の
所定深さに溝を掘削して、この溝に側縁が突き合さると
共に、ウエブが地中壁の内側となるようにして地中壁体
を挿入したのち、上記地中壁体の突き合せ側面を挾んで
対向するウエブ間に水密性と剛性との確保のためコンク
リートを打ち込み、その後に地中壁体の内側を掘削して
ウエブの先縁を結合するコンクリート板を打設して地中
構造壁体を形成することを特徴とするプレキヤスト板に
よる中空合成連続地中壁の施工方法。
1. A precast underground wall is formed by a vertically elongated board and a web protruding from a line connecting the top and bottom ends at least on both side edges of one side of the board, and a precast underground wall is formed from the ground on the construction line of the underground wall. After excavating a trench to a deep depth and inserting the underground wall so that the side edges abut against this trench and the web is inside the underground wall, the abutting sides of the underground wall are inserted. Concrete is poured between the opposing webs to ensure watertightness and rigidity, and then the inside of the underground wall is excavated and a concrete plate is placed to join the leading edges of the webs to create an underground structure. A method for constructing a hollow synthetic continuous underground wall using precast boards to form a wall body.
JP11525880A 1980-08-20 1980-08-20 Construction method of hollow synthetic continuous underground wall using precast boards Expired JPS606420B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11525880A JPS606420B2 (en) 1980-08-20 1980-08-20 Construction method of hollow synthetic continuous underground wall using precast boards

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11525880A JPS606420B2 (en) 1980-08-20 1980-08-20 Construction method of hollow synthetic continuous underground wall using precast boards

Publications (2)

Publication Number Publication Date
JPS5740021A JPS5740021A (en) 1982-03-05
JPS606420B2 true JPS606420B2 (en) 1985-02-18

Family

ID=14658218

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11525880A Expired JPS606420B2 (en) 1980-08-20 1980-08-20 Construction method of hollow synthetic continuous underground wall using precast boards

Country Status (1)

Country Link
JP (1) JPS606420B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0426823Y2 (en) * 1985-12-27 1992-06-26
CN111364443B (en) * 2020-04-16 2025-01-03 西安科技大学 A prefabricated grid-shaped underground continuous wall without internal support and its construction process

Also Published As

Publication number Publication date
JPS5740021A (en) 1982-03-05

Similar Documents

Publication Publication Date Title
US3650079A (en) Building block and wall construction with grout-receiving lateral cells
JPS606420B2 (en) Construction method of hollow synthetic continuous underground wall using precast boards
JPH03286029A (en) Steel underground wall and its construction
JPH041811B2 (en)
JPH0663227B2 (en) Construction method for underground wall of building
JPH08269943A (en) In-plane mating sandwich structure
KR102586998B1 (en) Underground continuous wall panel with reinforced connection part and its construction method
RU2836966C1 (en) Design of above-pile assembly, pile foundation and method of its assembly
JPS5910250Y2 (en) hollow concrete block
JPS5853321Y2 (en) Element for mountain retainer
JPS606419B2 (en) Steel panels for continuous wall construction
JPH0315624Y2 (en)
JPS609173B2 (en) Precast underground continuous wall and its construction method
JP2572680B2 (en) Underground structure by reverse strike method
JPS6335073Y2 (en)
JPH03169911A (en) Construction of underground steel wall
JPH0351416A (en) Constructing method for continuous underground wall having pole built therein
JPS5923107Y2 (en) Concrete U-shaped groove block
CN120250618A (en) Micro-disturbance implantation in prefabricated structural components of underground engineering
JPS606417B2 (en) Underground continuous wall structure
JPS606418B2 (en) Steel panels for continuous wall construction
JPS6088728A (en) Strip footing structure of plate structural part and its construction
JPS5972319A (en) Underground continuous wall work utilizing soil pillar-row wall
JPH0660492B2 (en) Vertical underground construction method for continuous underground wall
JPH04360908A (en) Construction of underground continuous wall and formwork therefor