JPS6310250B2 - - Google Patents
Info
- Publication number
- JPS6310250B2 JPS6310250B2 JP19687583A JP19687583A JPS6310250B2 JP S6310250 B2 JPS6310250 B2 JP S6310250B2 JP 19687583 A JP19687583 A JP 19687583A JP 19687583 A JP19687583 A JP 19687583A JP S6310250 B2 JPS6310250 B2 JP S6310250B2
- Authority
- JP
- Japan
- Prior art keywords
- steel sheet
- excavated
- lightweight steel
- trench
- guide panel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】
本発明は、上、下水道管、ガス管及び電線、電
話ケーブルの布設管等を埋設する為に掘削した溝
の内側壁の土砂崩れを防止する土留工法に関す
る。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an earth retaining method for preventing landslides on the inner walls of trenches excavated for burying water pipes, sewer pipes, gas pipes, electric wires, telephone cables, etc.
従来、上記掘削溝の内側壁の土砂崩れを防止す
るには、一般に掘削溝の内側壁に矢板を建て込
み、相対向する矢板に腹起しを当て切梁を張架す
る土留支保工が広く行われているが、この土留支
保工は掘削溝内に作業員が入つて行うので、作業
中掘削溝の内側壁が土砂崩れした場合には甚だ危
険である。 Conventionally, in order to prevent landslides on the inner wall of the excavated trench, earth retention shoring has been widely used, in which sheet piles are erected on the inside wall of the excavated trench, and the opposing sheet piles are erected and strut beams are stretched. However, since this earth retaining shoring is carried out by workers inside the excavated trench, it is extremely dangerous if the inner wall of the excavated trench were to cause a landslide during the work.
この為、近時矢板を使用し、作業員が掘削溝内
に入らないで施工できる土留支保装置として、実
開昭56−25744号公報に示されるものが開発され
た。 For this reason, recently, an earth retention shoring device disclosed in Japanese Utility Model Application Publication No. 56-25744 was developed that uses sheet piles and can be constructed without requiring workers to enter the excavated trench.
この土留支保装置は、第1図に示す如く掘削溝
の両側に沿つて所要間隔で起立されるガイドレー
ル1と、掘削溝の両側で隣接するガイドレール1
間に上下に摺動自在に嵌め込まれる方形枠状の案
内フレーム2と、各案内フレーム2の外面側をガ
イドとして沈降するよう相互に長手側縁部を摺動
自在に係合した複数枚の矢板3と、溝幅方向に対
向するガイドレール1間を連結するスピンドル4
と、案内フレーム2の外側上部に設けられた矢板
3の案内フレーム2からの外方への離脱を阻止す
る支持枠5とから成るものである。 As shown in Fig. 1, this earth retention shoring device consists of guide rails 1 that are erected at required intervals along both sides of an excavation trench, and guide rails 1 that are adjacent to each other on both sides of the excavation trench.
A rectangular frame-shaped guide frame 2 fitted vertically and slidably in between, and a plurality of sheet piles whose longitudinal side edges are slidably engaged with each other so as to sink using the outer surface side of each guide frame 2 as a guide. 3 and a spindle 4 that connects the guide rails 1 facing each other in the groove width direction.
and a support frame 5 which prevents the sheet pile 3 from separating outward from the guide frame 2, which is provided on the outer upper part of the guide frame 2.
斯かる土留支保装置は、予め相対向するガイド
レール1をスピンドル4にて連結しておき、これ
をクレーン等にて掘削溝内の長手方向に所定間隔
にて吊り降ろし、次に掘削溝の内側壁で隣接する
ガイドレール1間にクレーン等にて方形枠状案内
フレーム2を吊り降ろして嵌め込み、次いで方形
枠状案内フレーム2の外側上部の支持枠5を通し
て複数枚の矢板3を順次長手側縁部を係合させて
建て込むものである。 Such an earth retaining support device connects opposing guide rails 1 in advance with a spindle 4, and then suspends them using a crane or the like at predetermined intervals in the longitudinal direction of an excavated trench. The rectangular frame-shaped guide frame 2 is suspended and fitted between the guide rails 1 adjacent to each other on the wall using a crane or the like, and then a plurality of sheet piles 3 are sequentially attached to the longitudinal side edges of the rectangular frame-shaped guide frame 2 through the support frame 5 on the outside upper part. It is installed by engaging the parts.
然り乍ら、この土留支保装置では、現場でガイ
ドレール1を掘削溝の長手方向に於ける間隔を正
確に測定の上、セツトしなければならないので、
作業性が悪く、土留支保工の施工能率が期待した
程向上しないものである。またこの土留支保装置
は、各部材の構造が複雑な上、部品点数が多く、
コスト高である。 However, with this earth retention shoring device, the guide rail 1 must be set on site after accurately measuring the distance in the longitudinal direction of the excavated trench.
Workability is poor, and the construction efficiency of earth retaining shoring does not improve as much as expected. In addition, this earth retention shoring device has a complicated structure and has many parts.
The cost is high.
本発明は斯かる問題を解消すべくなされたもの
であり、掘削溝の内側壁の長手方向に、軽量鋼矢
板を差込む枠を有する帯状のガイドパネルと軽量
鋼矢板とを順次セツトしていく掘削溝の土留工法
を提供せんとするものである。 The present invention was made to solve this problem, and consists of sequentially setting a belt-shaped guide panel having a frame into which the lightweight steel sheet piles are inserted and the lightweight steel sheet piles in the longitudinal direction of the inner wall of the excavation trench. The purpose is to provide an earth retaining method for excavated trenches.
以下本発明による掘削溝の土留工法を図によつ
て説明する。 DESCRIPTION OF THE PREFERRED EMBODIMENTS The earth retaining method for an excavated trench according to the present invention will be explained below using figures.
先ず本発明の土留工法を施工する為の各部材を
第2図によつて説明すると、10は帯状のガイド
パネルで、その内面の角形パイプ(又はチヤンネ
ル材)より成る上下の横棧11間の長手方向に一
定間隔を存して複数本、本例では5本の角形パイ
プ(又はチヤンネル材)より成る縦棧12が設け
られ、各縦棧12の側面にピン穴13が設けられ
ている。このガイドパネル10の上側の横棧11
上の長手方向にはアングル材14が固設され、こ
のアングル材14上には前記縦棧12の位置で丸
穴15を有する吊上げ用プレート16が固設され
ている。またこのガイドパネル10の背面には枠
17が固設され、枠17の外板は波形鋼板18よ
り成り、枠17内の長手方向には一定間隔に複数
の、本例では5枚の補強板19が固定されて枠1
7が区画されている。20は相対向するガイドパ
ネル10を連結する水圧ジヤツキで、両端にピン
穴21を有するコネクタ22が固設されている。
23は水圧ジヤツキ20のコネクタ22のピン穴
21とガイドパネル10の縦棧12のピン穴13
とに挿通するピンである。24はガイドパネル1
0の枠17に差込む軽量鋼矢板、25は溝底に圧
入して建て込んだ軽量鋼矢板24の上端にガイド
パネル10を吊垂する為のフツクチエーンであ
る。26は建て込んだ軽量鋼矢板24の下部に当
てる腹起しとしての大鼓落し、27は大鼓落し2
6間に張架する切梁としての水圧ジヤツキで、そ
の両端に大鼓落し26に連結するコネクタ28が
固設されている。 First, each member for constructing the earth retaining method of the present invention will be explained with reference to FIG. 2. Reference numeral 10 is a band-shaped guide panel, and the inner surface thereof is made of square pipe (or channel material) between the upper and lower crossbars 11. A plurality of vertical rods 12 made of rectangular pipes (or channel materials), five in this example, are provided at regular intervals in the longitudinal direction, and a pin hole 13 is provided in the side surface of each vertical rod 12. The upper side rail 11 of this guide panel 10
An angle member 14 is fixed in the upper longitudinal direction, and a lifting plate 16 having a round hole 15 is fixed on the angle member 14 at the position of the vertical beam 12. A frame 17 is fixed to the back of the guide panel 10, and the outer plate of the frame 17 is made of a corrugated steel plate 18, and a plurality of reinforcing plates, five in this example, are arranged at regular intervals in the longitudinal direction of the frame 17. 19 is fixed and frame 1
7 are divided. A hydraulic jack 20 connects the opposing guide panels 10, and a connector 22 having pin holes 21 is fixed at both ends.
23 is the pin hole 21 of the connector 22 of the hydraulic jack 20 and the pin hole 13 of the vertical rail 12 of the guide panel 10.
This is a pin that is inserted into the 24 is guide panel 1
A lightweight steel sheet pile 25 is inserted into the frame 17 of 0, and 25 is a foot chain for suspending the guide panel 10 from the upper end of the lightweight steel sheet pile 24 which is press-fitted into the trench bottom. 26 is a large drum otoshi that is applied to the lower part of the lightweight steel sheet pile 24 that has been erected, and 27 is a large drum ochi 2.
A hydraulic jack is used as a strut extending between 6 spaces, and a connector 28 connected to a large drum drop 26 is fixedly installed at both ends of the jack.
次に上記の各部材を用いる本発明の土留工法を
第3図a乃至dによつて説明する。溝掘削に先立
つて、ガイドパネル10を相対向させ、水圧ジヤ
ツキ20の両端のコネクタ22をガイドパネル1
0の両端の縦棧12に当接し、両者のピン穴2
1,13にピン23を挿通して、相対向せるガイ
ドパネル10に水圧ジヤツキ20を結合の上、該
水圧ジヤツキ20を適宜伸縮してこれから掘削す
る溝の幅に合わせておく。 Next, the earth retaining method of the present invention using the above-mentioned members will be explained with reference to FIGS. 3a to 3d. Prior to trench excavation, the guide panels 10 are faced to each other, and the connectors 22 at both ends of the hydraulic jack 20 are connected to the guide panel 1.
0 and pin holes 2 on both ends.
A pin 23 is inserted through 1 and 13 to couple the hydraulic jack 20 to the opposing guide panel 10, and the hydraulic jack 20 is expanded and contracted appropriately to match the width of the groove to be excavated.
さて第3図aに示す如くバツクホウにて溝Aを
所定の深さまで掘削したならば、溝Aの端部内側
壁の上部に、水圧ジヤツキ20にて連結した相対
向せるガイドパネル10を、吊り上げ用プレート
16の丸穴15に吊索Wを繋留し、クレーン等に
て吊り降ろしてそのまま保持する。次にガイドパ
ネル10の背面の枠17内に第3図bに示す如く
軽量鋼矢板24を差込んで溝底にバツクホウのバ
ケツトの背面にて圧入する。次いで相対向せるガ
イドパネル10の両端の吊り上げ用プレート16
の丸穴15に第3図cに示す如くフツクチエーン
25の基端を繋留し、フツク25aを軽量鋼矢板
24の上端に係止してガイドパネル10を軽量鋼
矢板24に吊垂支持する。次に図示の如く軽量鋼
矢板24と掘削溝Aの内側壁との隙間に土砂30
を裏込めする。次いで水圧ジヤツキ20を伸長し
て相対向せる軽量鋼矢板24を突つ張る。そして
必要に応じ第3図dに示す如く相対向せる軽量鋼
矢板24の下部に腹起しとしての大鼓落し26を
当てがい、切梁としての水圧ジヤツキ27を両端
のコネクタ28を大鼓落し26に係止し、水圧ジ
ヤツキ27を伸長して突つ張り、相対向せる軽量
鋼矢板24及びガイドパネル10を安定させる。
以後溝Aの掘削進行に伴い前記工程を繰り返して
いく。 Now, as shown in Fig. 3a, once groove A has been excavated to a predetermined depth with a backhoe, the facing guide panels 10 connected with hydraulic jacks 20 are lifted onto the upper part of the inner wall of the end of groove A. The suspension rope W is moored to the round hole 15 of the plate 16, and is lowered by a crane or the like and held as it is. Next, a lightweight steel sheet pile 24 is inserted into the frame 17 on the back side of the guide panel 10 as shown in FIG. Next, the lifting plates 16 at both ends of the guide panel 10 are placed opposite each other.
As shown in FIG. 3c, the base end of the hook chain 25 is anchored to the round hole 15 of the guide panel 10, and the hook 25a is engaged with the upper end of the lightweight steel sheet pile 24, so that the guide panel 10 is suspended from the lightweight steel sheet pile 24. Next, as shown in the figure, earth and sand 30 are placed in the gap between the lightweight steel sheet pile 24 and the inner wall of the excavated trench A.
backfill. Next, the hydraulic jack 20 is extended and the lightweight steel sheet piles 24 facing each other are stretched. Then, if necessary, as shown in FIG. 3d, a large drum otoshi 26 is applied to the lower part of the lightweight steel sheet piles 24 which are facing each other, and a hydraulic jack 27 as a strut is connected to the large drum otoshi 26 by connecting connectors 28 at both ends. The lightweight steel sheet pile 24 and the guide panel 10, which are opposed to each other, are stabilized by locking and extending the hydraulic jack 27.
Thereafter, the above steps are repeated as the trench A is excavated.
かくして掘削底Aの底にガス管P等を吊り降ろ
して布設していくことができる。 In this way, the gas pipe P etc. can be suspended and laid at the bottom of the excavation bottom A.
上記のように本発明の土留工法は、掘削溝Aの
内側壁の上部に相対向せるガイドパネル10をク
レーン等にて吊垂保持しておいて、そのガイドパ
ネル10の背面の枠17内に軽量鋼矢板24を差
込んで溝底に圧入し、その後でガイドパネル10
を軽量鋼矢板24にフツクチエーン25にて吊垂
支持するのであるから、ガイドパネル10はセツ
ト間隔をとることなく順次接続配置でき、また軽
量鋼矢板24は従来のようにガイドレール、案内
フレームをセツトした後案内フレームの支持枠を
通して建て込むのと異なり、ガイドパネル10の
セツト後直ちにガイドパネル10の枠17内に差
込んで建て込むことができるので、甚だ作業性が
良く、土留工法の施工能率を向上する。しかも前
記作業は地上で行うことができるので、作業員が
掘削溝A内に入る必要が無く安全である。尚、建
て込んだ相対向せる軽量鋼矢板24の下部に必要
に応じ腹起し、切梁を施工する時には、既でに軽
量鋼矢板24が掘削溝Aの底に圧入され且つその
軽量鋼矢板24及びガイドパネル10が水圧ジヤ
ツキ20に突つ張られて強固に支持されているの
で、作業員が掘削溝A内に入つて作業しても安全
である。 As described above, in the earth retaining method of the present invention, the guide panel 10 facing the upper part of the inner wall of the excavated trench A is suspended by a crane or the like, and the guide panel 10 is suspended within the frame 17 on the back side of the guide panel 10. Insert the lightweight steel sheet pile 24 and press fit it into the groove bottom, and then insert the guide panel 10.
The guide panels 10 can be connected and arranged one after another without taking any set intervals, and the light steel sheet piles 24 can be set with guide rails and guide frames as in the past. Unlike the case where the guide panel 10 is installed through the support frame of the guide frame, it can be inserted into the frame 17 of the guide panel 10 immediately after the guide panel 10 is set. improve. Furthermore, since the work can be carried out on the ground, there is no need for the worker to enter the excavation trench A, making it safe. In addition, when constructing a cut beam by raising the lower part of the lightweight steel sheet pile 24 that has been erected and faces each other as necessary, the lightweight steel sheet pile 24 has already been press-fitted into the bottom of the excavation trench A, and the lightweight steel sheet pile 24 is 24 and the guide panel 10 are firmly supported by the hydraulic jack 20, so it is safe for the worker to enter the excavation trench A and work there.
また本発明の土留工法は、第4図に示す如く掘
削溝Aの横断する管Cが布設されていてもその部
分の軽量鋼矢板24の建て込み深さを浅くして横
断管Cを避けることにより、何ら支障無く施工で
きる。 Furthermore, in the earth retaining method of the present invention, even if a pipe C that crosses the excavated trench A is laid, the depth of the light steel sheet pile 24 in that part is made shallow to avoid the pipe C crossing the excavated trench A. Therefore, construction can be carried out without any problems.
以上詳記した通り本発明の土留工法は、作業性
が良好でしかも地上で作業を行うので施工能率が
良く安全であり、また掘削溝内に横断管があつて
も何ら支障無く施工でき、さらに使用する部材が
少なく構造が簡単であるので、各部材の組付け、
解体が容易で、施工管理がゆきとどく等の効果が
ある。 As detailed above, the earth retaining method of the present invention has good workability, and since the work is carried out on the ground, the construction is efficient and safe.Also, even if there is a cross pipe in the excavation trench, it can be constructed without any problem. The structure is simple with fewer parts used, so each part can be assembled,
It has the benefits of easy dismantling and easy construction management.
第1図は従来の掘削溝の土留支保装置を示す斜
視図、第2図は本発明の掘削溝の土留工法で用い
る各部材を示す斜視図、第3図a乃至dは本発明
の土留工法の施工工程を示す斜視図、第4図は掘
削溝に横断管が有る場合の土留工法の施工状況を
示す斜視図である。
10……帯状のガイドパネル、11……横棧、
12……縦棧、13……ピン穴、14……アング
ル材、15……丸穴、16……吊り上げ用プレー
ト、17……枠、18……波形鋼板、19……補
強板、20……水圧ジヤツキ、21……ピン穴、
22……コネクタ、24……軽量鋼矢板、25…
…フツクチエーン、26……大鼓落し、27……
水圧ジヤツキ、28……コネクタ、30……裏込
めの土砂、A……掘削溝、P……ガス管等、C…
…横断管。
Fig. 1 is a perspective view showing a conventional excavated trench earth retaining support device, Fig. 2 is a perspective view showing each member used in the excavated trench earth retaining method of the present invention, and Fig. 3 a to d are the earth retaining method of the present invention. Fig. 4 is a perspective view showing the construction process of the earth retaining method when the excavated trench has a cross pipe. 10... Band-shaped guide panel, 11... Yokoban,
12... Vertical beam, 13... Pin hole, 14... Angle material, 15... Round hole, 16... Lifting plate, 17... Frame, 18... Corrugated steel plate, 19... Reinforcement plate, 20... ...Hydraulic jack, 21...Pin hole,
22... Connector, 24... Light steel sheet pile, 25...
...Futsukuchain, 26...Otsuzumi Otoshi, 27...
Water pressure jack, 28... Connector, 30... Backfilling earth and sand, A... Excavation trench, P... Gas pipe, etc., C...
...transverse pipe.
Claims (1)
ヤツキにて連結した相対向せる帯状のガイドパネ
ルをクレーン等にて吊垂保持し、次にガイドパネ
ルの背面の枠内に軽量鋼矢板を差込んで溝底に圧
入し、次いで相対向せる帯状のガイドパネルの両
端をフツクチエーンにて軽量鋼矢板の上端に吊垂
支持し、次に軽量鋼矢板と掘削溝との間に裏込め
を施し、次いで水圧ジヤツキを伸長して相対向せ
る軽量鋼矢板を突つ張り、以後掘削溝の進行に伴
い前記工程を繰り返していく掘削溝の土留工法。1. A band-shaped guide panel that is connected to the inner wall of a trench excavated to a predetermined depth and facing each other with a hydraulic jack is suspended using a crane, etc., and then a lightweight steel sheet pile is placed inside the frame on the back of the guide panel. Then, both ends of the band-shaped guide panels facing each other are suspended from the upper end of the lightweight steel sheet pile using a foot chain, and then backfilling is performed between the lightweight steel sheet pile and the excavated groove. An earth retaining method for excavated trenches in which the hydraulic jacks are extended, the lightweight steel sheet piles facing each other are stretched, and the process is repeated as the excavated trench progresses.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19687583A JPS6088725A (en) | 1983-10-20 | 1983-10-20 | Sheathing work of excavated trench |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19687583A JPS6088725A (en) | 1983-10-20 | 1983-10-20 | Sheathing work of excavated trench |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6088725A JPS6088725A (en) | 1985-05-18 |
| JPS6310250B2 true JPS6310250B2 (en) | 1988-03-04 |
Family
ID=16365099
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19687583A Granted JPS6088725A (en) | 1983-10-20 | 1983-10-20 | Sheathing work of excavated trench |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6088725A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US9519501B1 (en) | 2012-09-30 | 2016-12-13 | F5 Networks, Inc. | Hardware assisted flow acceleration and L2 SMAC management in a heterogeneous distributed multi-tenant virtualized clustered system |
| US9554418B1 (en) | 2013-02-28 | 2017-01-24 | F5 Networks, Inc. | Device for topology hiding of a visited network |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2951200A1 (en) * | 2009-10-14 | 2011-04-15 | Acilemat | DEVICE FOR SHAPING THE WALLS OF A TRENCH |
| JP6068774B1 (en) * | 2016-03-01 | 2017-01-25 | 日本スピードショア株式会社 | Earth retaining prior construction method using adjustable erection |
| JP7712066B2 (en) * | 2020-07-02 | 2025-07-23 | 鹿島建設株式会社 | How to build an underground structure |
-
1983
- 1983-10-20 JP JP19687583A patent/JPS6088725A/en active Granted
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US9519501B1 (en) | 2012-09-30 | 2016-12-13 | F5 Networks, Inc. | Hardware assisted flow acceleration and L2 SMAC management in a heterogeneous distributed multi-tenant virtualized clustered system |
| US9554418B1 (en) | 2013-02-28 | 2017-01-24 | F5 Networks, Inc. | Device for topology hiding of a visited network |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6088725A (en) | 1985-05-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111456023A (en) | A kind of construction method of underground prestressed support structure | |
| JP2684155B2 (en) | Excavation method used for construction of underground structures | |
| US5158398A (en) | Method and apparatus for an excavation support system for trenches | |
| US3798914A (en) | Panel connectors for reinforced concrete diaphragm walls | |
| JPS6310250B2 (en) | ||
| KR20040031451A (en) | Prestressed scaffolding method | |
| JPS6310249B2 (en) | ||
| CN212336065U (en) | Guiding and sinking system suitable for underground shaft group construction | |
| JPH11190024A (en) | Earth retaining work | |
| JPH07305319A (en) | Installating method for caison for breakwater | |
| CN219410828U (en) | Spliced prefabricated underground continuous wall | |
| JP2001336151A (en) | Ground excavation method using shore strut type earth retaining timbering | |
| JP2583830B2 (en) | Construction method of concrete deep foundation pile | |
| CN116378055B (en) | Existing pipe culvert supporting and hanging type protection combined mechanism and construction method thereof | |
| JP3060195B2 (en) | Construction method of steel basement reinforced concrete continuous underground wall | |
| KR20190142677A (en) | Top down construction method using girdir support structure | |
| JPS594723A (en) | Sheathing and timbering work for excavated trench | |
| JP3314299B2 (en) | Earth retaining device | |
| JPH07985B2 (en) | Expandable and contractible liner form and its shaft excavation method | |
| JPH10152853A (en) | Construction method of underground structure and structural member used therefor | |
| JP3013353B2 (en) | Method of placing concrete on SRC underground diaphragm wall | |
| JPH05295732A (en) | Crosswise sheet pile removing method | |
| JPS63277342A (en) | Reverse execution of underground story | |
| JPH0469681B2 (en) | ||
| JPH05140940A (en) | Soil retaining method for deep drilling |