JPS6339730B2 - - Google Patents
[go: Go Back, main page]

JPS6339730B2 - - Google Patents

Info

Publication number
JPS6339730B2
JPS6339730B2 JP57228597A JP22859782A JPS6339730B2 JP S6339730 B2 JPS6339730 B2 JP S6339730B2 JP 57228597 A JP57228597 A JP 57228597A JP 22859782 A JP22859782 A JP 22859782A JP S6339730 B2 JPS6339730 B2 JP S6339730B2
Authority
JP
Japan
Prior art keywords
pile
water
layer
alkaline substance
urethane prepolymer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP57228597A
Other languages
Japanese (ja)
Other versions
JPS59122621A (en
Inventor
Kazuyoshi Tamura
Hiroji Yao
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP22859782A priority Critical patent/JPS59122621A/en
Publication of JPS59122621A publication Critical patent/JPS59122621A/en
Publication of JPS6339730B2 publication Critical patent/JPS6339730B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【発明の詳細な説明】 本発明は、地中に埋設される杭を引き抜くため
の処理方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a treatment method for pulling out piles buried underground.

地中に埋設された杭、例えば土留め壁の構築に
供された杭は、地下構築物の構築の完了後、引き
抜かれ、撤去される。
Piles buried underground, for example, piles used for constructing earth retaining walls, are pulled out and removed after construction of the underground structure is completed.

ところで、杭を引き抜くには、杭の自重および
杭と周囲地盤との間の摩擦力を上回る引き抜き力
を杭に及ぼすことができる大規模な引き抜き設備
を必要とし、引き抜き設備の規模は杭の長さの増
大に伴なつて大きくしなければならないという問
題があつた。
By the way, in order to pull out a pile, large-scale extraction equipment that can exert a pulling force on the pile that exceeds the pile's own weight and the frictional force between the pile and the surrounding ground is required, and the scale of the extraction equipment is based on the length of the pile. There was a problem in that it had to be made larger as the size increased.

この問題を解消する一方法として、杭の埋設に
際し、杭の表面に、アルカリ性の雰囲気中におい
て経時的にグリース状に液状化する性質を有する
含水ゲルを形成することが考えられる。杭の引き
抜きに際し、埋設された杭と地盤との間にグリー
ス状に変化した物質が介在すれば、杭の引き抜き
時における摩擦抵抗を低減し得ると考えられる。
One possible way to solve this problem is to form a hydrous gel on the surface of the pile, which has the property of liquefying into a grease-like form over time in an alkaline atmosphere, when the pile is buried. It is thought that when a pile is pulled out, if a grease-like substance is present between the buried pile and the ground, the frictional resistance when pulling out the pile can be reduced.

ところが、この方法では、含水ゲルが形成され
た杭の埋設の対象地盤はアルカリ性の土質を有す
る場合に限られる。杭の埋設は、予め地盤に穿た
れた溝孔中に杭を挿入して行なう場合と、杭を地
盤に打込むことにより行なう場合とがあるが、杭
を溝孔に挿入する前者の場合、地盤の土質が非ア
ルカリ性のものであるときは、前記溝孔を充填す
るための充填材料にアルカリ性を有する物質を混
入すればよいが、杭を打ち込む後者の場合にはこ
のような対処の仕方ができない。また、前記含水
ゲルはこれと反応するアルカリ性物質のアルカリ
性が強いほどこれがグリース状への変化が促進さ
れるが、杭の埋設の対象地盤がアルカリ性の土質
を有する場合であつても、そのアルカリ性の強さ
が前記含水ゲルを変化させるのに十分でないこと
がある。
However, with this method, the ground in which the piles with the hydrous gel formed are to be buried is limited to cases where the ground has alkaline soil. There are two ways to bury piles: by inserting the pile into a trench drilled in the ground in advance, and by driving the pile into the ground. If the soil quality of the ground is non-alkaline, it is sufficient to mix an alkaline substance into the filling material used to fill the trench, but in the latter case, where piles are driven, this method of handling is not recommended. Can not. In addition, the more alkaline the alkaline substance that reacts with the hydrous gel, the more likely it is to turn into a grease-like substance. The strength may not be sufficient to transform the hydrogel.

したがつて、本発明は、杭の表面に、アルカリ
性の物質と反応することにより経時的にグリース
状に変化する性質を有する含水ゲルを形成するこ
とにより、また杭が埋設される地盤がアルカリ性
の土質を有するか否かを問わず杭の引き抜き抵抗
を大幅に小さくすることを可能の杭の引き抜きの
ための処理方法を提供することにある。
Therefore, the present invention has been developed by forming a water-containing gel on the surface of the pile, which has the property of changing into a grease-like state over time by reacting with an alkaline substance, and by forming a water-containing gel on the surface of the pile. To provide a processing method for pulling out piles that can significantly reduce the pulling resistance of piles regardless of whether they have soil quality.

本発明に係る処理方法は、杭の表面の少なくと
も一部にアルカリ性を有する物質の層および水溶
性ウレタンプレポリマーと水とを反応させて得た
含水ゲルの層から成る被膜を形成した後に前記杭
を溝孔中に挿入し、その後前記溝孔を充填するこ
とを特徴とする。
In the treatment method according to the present invention, after forming a coating consisting of a layer of an alkaline substance and a layer of hydrogel obtained by reacting a water-soluble urethane prepolymer with water on at least a part of the surface of the pile, is inserted into the slot, and then the slot is filled.

また、本発明は、前記被膜が形成された杭を前
記溝孔ではなく、例えば打ち込みにより直接に地
盤に埋設することを特徴とする。
Further, the present invention is characterized in that the pile on which the coating is formed is buried directly in the ground, for example, by driving, instead of in the groove.

本発明によれば、前記含水ゲルの層は、前記ア
ルカリ性を有する物質の外側に形成する場合と内
側に形成する場合とがあり、いずれの場合におい
ても、杭を取り巻く周囲地盤がアルカリ性の土質
を有するか否かあるいはその強弱の程度に拘ら
ず、前記含水ゲルは前記アルカリ性を有する物質
と反応し、時間の経過とともにグリース状に変化
し、杭と地盤とが前記グリース状を呈する物質に
より確実に分離される。前記グリース状を呈する
物質は、杭の引き抜きの際、杭および地盤間で潤
滑作用を担うことから、杭の引き抜きに要する力
を大幅に低減することができ、これにより杭の引
き抜きに要する設備の小規模化を図ることができ
る。
According to the present invention, the hydrogel layer may be formed on the outside or inside of the alkaline substance, and in either case, the surrounding ground surrounding the pile has alkaline soil. Regardless of the presence or absence of the substance or its strength, the water-containing gel reacts with the alkaline substance and turns into a grease-like substance over time. separated. The grease-like substance acts as a lubricant between the pile and the ground when the pile is pulled out, which can significantly reduce the force required to pull out the pile. It is possible to downsize.

本発明は、杭の表面の少なくとも一部にアルカ
リ性を有する物質の層および水溶性ウレタンプレ
ポリマーの層から成る被膜を形成した後、前記杭
を、地下水または安定液を有する溝孔中に挿入
し、その後前記溝孔を充填することを特徴とす
る。
In the present invention, after forming a coating consisting of a layer of an alkaline substance and a layer of a water-soluble urethane prepolymer on at least a portion of the surface of the pile, the pile is inserted into a trench containing groundwater or a stabilizing liquid. , and then filling the slot.

また、本発明は、前記アルカリ性を有する物質
の層および水溶性ウレタンプレポリマーの層から
成る被膜が形成された杭を溝孔にではなく、例え
ば打ち込みにより前記被膜の形成箇所が地下水位
下に位置するように、直接に地盤に埋設すること
を特徴とする。
In addition, the present invention provides a method in which the pile on which the coating consisting of the layer of the alkaline substance and the water-soluble urethane prepolymer layer is formed is not placed in a trench, but is driven, for example, so that the location where the coating is formed is located below the groundwater level. It is characterized by being buried directly in the ground.

本発明によれば、前記水溶性ウレタンプレポリ
マーの層が前記安定液または地下水に接すること
によりその水分と反応して含水ゲルに変化する。
該含水ゲルは前記アルカリ性を有する物質の層と
反応する。したがつて、杭を取り巻く周囲地盤が
アルカリ性の土質を有するか否かあるいはその強
弱の程度に拘らず、前記含水ゲルは層をなす前記
アルカリ性を有する物質と反応して時間の経過と
ともに、杭およびその周囲地盤間の摩擦力を軽減
するグリース状の物質に変化する。
According to the present invention, when the layer of the water-soluble urethane prepolymer comes into contact with the stabilizing liquid or ground water, it reacts with the water and changes into a hydrogel.
The hydrogel reacts with the layer of the alkaline substance. Therefore, regardless of whether or not the surrounding ground surrounding the pile has alkaline soil or its strength, the water-containing gel reacts with the alkaline material forming the layer, and over time, the pile and It turns into a grease-like substance that reduces the friction between the surrounding ground.

(実施例) 本発明が特徴とするところは、図示の実施例に
ついての以下の説明により、さらに明らかとなろ
う。
(Embodiments) The features of the present invention will become clearer from the following description of the illustrated embodiments.

一例として土留め壁の構築の際に施す処理方法
について説明する。
As an example, a treatment method applied when constructing an earth retaining wall will be explained.

まず、地盤中に掘削した溝孔中に杭を挿入する
に先立ち、杭の表面の少なくとも一部にアルカリ
性を有する物質(以下、単に「アルカリ物質」と
いう。)の層および水溶性ウレタンプレポリマー
と水とを反応させて得た含水ゲルの層から成る被
膜を形成する。この含水ゲルはアルカリに弱い性
質を有する。
First, before inserting the pile into a trench excavated in the ground, at least a portion of the surface of the pile is coated with a layer of an alkaline substance (hereinafter simply referred to as "alkaline substance") and a water-soluble urethane prepolymer. A film consisting of a layer of hydrogel obtained by reacting with water is formed. This hydrogel has a property of being weak against alkali.

前記被膜は、前記アルカリ物質で前記杭の所定
箇所における表面を被覆した後、該アルカリ物質
の層を前記含水ゲルの層で被覆し、あるいは、前
記含水ゲルの層を前記杭の表面に形成した後、該
含水ゲルの層を前記アルカリ物質の層で被覆する
ことにより形成することができる。
The coating is made by coating the surface of the pile at a predetermined location with the alkaline substance, and then coating the alkaline substance layer with the hydrogel layer, or forming the hydrogel layer on the surface of the pile. Thereafter, the hydrogel layer can be formed by covering it with a layer of the alkaline substance.

前記アルカリ物質は例えば水ガラスとセメント
ペーストとの混練物で構成することができ、前記
アルカリ物質の層は、前記混練物を前記杭の所定
の箇所の表面に層を成すように塗布し、あるい
は、前記含水ゲルの層にこれを覆うように前記混
練物を塗布することにより形成することができ
る。また、前記アルカリ物質の層は、粉状のアル
カリ性の物質を吹き付けることにより形成するこ
ともできる。
The alkaline substance may be composed of, for example, a mixture of water glass and cement paste, and the layer of the alkaline substance may be formed by applying the mixture to the surface of a predetermined portion of the pile in a layered manner, or , it can be formed by applying the kneaded material to cover the layer of the hydrogel. Further, the alkaline material layer can also be formed by spraying a powdery alkaline material.

前記含水ゲルは、前記水溶性ウレタンプレポリ
マーおよび水を別個にかつ同時に前記アルカリ物
質の層、あるいは、前記杭の所定の箇所における
表面に吹き付けることにより形成することができ
る。この吹き付けは、後述する装置を用いて行な
うことができる。
The hydrogel can be formed by spraying the water-soluble urethane prepolymer and water separately and simultaneously onto the layer of alkaline material or the surface of the pile at a predetermined location. This spraying can be performed using a device described below.

前記水溶性ウレタンプレポリマーは、親水性ポ
リオキシアルキレンポリオールと有機ポリイソシ
アネートとをウレタン結合させて末端にイソシア
ネート基を残存させることにより得られる。前記
ポリオキシアルキレンポリオールとして、エチレ
ングリコール、プロピレングリコール、グリセリ
ン等の縮合物や共縮合物がある。
The water-soluble urethane prepolymer is obtained by urethane bonding a hydrophilic polyoxyalkylene polyol and an organic polyisocyanate to leave an isocyanate group at the end. The polyoxyalkylene polyols include condensates and co-condensates of ethylene glycol, propylene glycol, glycerin, and the like.

前記含水ゲルの被膜が形成される杭は、鋼製、
コンクリート製あるいは木製であつてもよく、ま
た、管状、ボツクス状、I形状、H形状、シート
パイルのような板状等、その形状を問わない。
The pile on which the hydrogel coating is formed is made of steel,
It may be made of concrete or wood, and may have any shape such as a tube, a box, an I-shape, an H-shape, or a plate like a sheet pile.

ところで、地盤に溝孔を形成して土留め壁10
を構築する代表例としては、第1図ないし第5図
に示すいわゆる泥水固化工法、第6図ないし第8
図に示すいわゆるソイルセメント柱列杭工法、第
9図ないし第12図に示すいわゆるジヨイスト工
法がある。
By the way, the earth retaining wall 10 is constructed by forming a groove in the ground.
Typical examples of construction are the so-called mud solidification method shown in Figures 1 to 5, and the
There are the so-called soil-cement column pile method shown in the figure, and the so-called joist method shown in Figs. 9 to 12.

前記泥水固化工法においては、ベントナイト泥
水のような安定液を満たしながら溝孔12を掘削
し(第3図)、次いで溝孔12中に杭14を挿入
し(第4図)、その後、水ガラス、セメント等か
ら成る固化剤を溝孔12中に投入して安定液を固
化させ、これにより土留め壁10が構築される。
In the muddy water solidification method, a trench 12 is excavated while being filled with a stable liquid such as bentonite mud (Fig. 3), and then a pile 14 is inserted into the trench 12 (Fig. 4). A solidifying agent such as cement is poured into the groove 12 to solidify the stabilizing liquid, thereby constructing the earth retaining wall 10.

前記ソイルセメント柱列杭工法においては、ア
ースオーガのような掘削機により所定の深度まで
溝孔12を穿つた後、溝孔12中にセメントペー
ストやモルタルのような固化材を注入し、これと
溝孔12中に残存する土砂とを撹拌、混合する
(第7図)。次に、溝孔12中に杭14を挿入する
(第8図)。その後、杭14の周辺が固化されて土
留め壁10が形成される。
In the soil-cement column pile construction method, a trench hole 12 is bored to a predetermined depth using an excavator such as an earth auger, and then a solidifying material such as cement paste or mortar is injected into the trench hole 12. The earth and sand remaining in the trench 12 are stirred and mixed (Fig. 7). Next, the stake 14 is inserted into the slot 12 (FIG. 8). Thereafter, the area around the pile 14 is solidified to form the earth retaining wall 10.

また、前記ジヨイスト工法では、プレボーリン
グにより溝孔12を形成した(第10図)後、該
溝孔中に杭14を挿入し(第11図)、溝孔12
を土砂で埋め戻すことにより、土留め壁10が構
築される。
In addition, in the joist construction method, after forming the groove hole 12 by pre-boring (Fig. 10), the pile 14 is inserted into the groove hole (Fig. 11).
The earth retaining wall 10 is constructed by backfilling with earth and sand.

杭14の表面または該表面に塗布された前記ア
ルカリ物質の層の表面に前記含水ゲルの層を形成
するには、杭の仮集積場においてあるいは杭を溝
孔の上方に配置する際すなわち杭の建て起しの際
に行なうことができる。含水ゲルの被膜の形成作
業の能率を上げかつ形成後の前記被膜の損傷機会
を少なくするために、杭14を溝孔に挿入する直
前すなわち杭の建て込み時の吹き付けによること
が望ましい。
In order to form the hydrous gel layer on the surface of the pile 14 or on the surface of the layer of alkaline material applied to the surface, it is possible to form the layer of hydrogel on the surface of the pile 14 or on the surface of the layer of alkaline material applied to the surface. This can be done at the time of construction. In order to increase the efficiency of forming the hydrous gel coating and reduce the chance of damage to the coating after formation, it is desirable to spray the water immediately before inserting the pile 14 into the trench, that is, when the pile is erected.

この場合、第13図ないし第15図に示すよう
に、溝孔12の上方の地表面に設置された吹き付
け装置16を利用することにより、前記含水ゲル
をH型鋼のような杭14の表面を被覆する前記ア
ルカリ物質の層または杭14の表面に形成するこ
とができる。
In this case, as shown in FIGS. 13 to 15, by using a spraying device 16 installed on the ground surface above the trench 12, the water-containing gel is applied to the surface of a pile 14 such as an H-shaped steel. It can be formed on the layer of the alkaline material to be coated or on the surface of the pile 14.

この装置16には、溝孔12の開放端を取り囲
んで地表に載置された枠体18と、該枠体上に固
定された円筒状のカバー20と、該カバーの側面
を外方から内方へ貫通して伸びる、互いに90゜の
間隔角度をもつて配置された複数の管22とが設
けられている。
This device 16 includes a frame 18 that surrounds the open end of the slot 12 and is placed on the ground surface, a cylindrical cover 20 that is fixed on the frame, and a side surface of the cover that is inserted from the outside. A plurality of tubes 22 are provided extending through the tubes 22 and spaced apart from each other by 90 degrees.

管22は二重管から成り、外管22aおよび該
外管内で開口する内管22bの先端に、それぞ
れ、前記水溶性ウレタンプレポリマーおよび水を
噴出するためのノズルが形成されており、前記水
溶性ウレタンプレポリマーと水とは各ノズルから
同時に噴出され、外管22aのノズルの直前で混
合する。
The tube 22 is made of a double tube, and a nozzle for spouting out the water-soluble urethane prepolymer and water is formed at the tips of an outer tube 22a and an inner tube 22b that opens inside the outer tube, respectively. The polyurethane prepolymer and water are simultaneously ejected from each nozzle and mixed just before the nozzle of the outer tube 22a.

H型鋼から成る杭14がカバー20および枠体
18内を経て溝孔12内を下降する間、外管22
aのノズルから噴射される前記水溶性ウレタンプ
レポリマーおよび水の混合物が前記アルカリ物質
の層または杭14の表面に吹き付けられ、時間の
経過に従つてゲル化する。
While the pile 14 made of H-shaped steel moves down inside the slot 12 through the cover 20 and the frame 18, the outer pipe 22
The mixture of water-soluble urethane prepolymer and water injected from the nozzle a is sprayed onto the layer of alkaline material or the surface of the pile 14, and gels over time.

管22を二重管とする図示の例では、前記水溶
性ウレタンプレポリマーは、その貯蔵容器、前記
ノズルへの送給設備(図示せず)等において、こ
れと混合される水とは分離されているために、吹
き付けの間、これらの設備内で固化することはな
い。但し、前記水溶性ウレタンプレポリマーおよ
び水は外管22aの先端の前記ノズルを通過す
る。このため、前記混合物の一部が前記ノズルに
付着し、固化する。しかし、その量は、前記ノズ
ルの通過時における前記混合物の流出速度および
流出圧力は比較的高いために比較的少ない。した
がつて、前記混合物の前記アルカリ物質の層また
は杭の表面への塗布は前記装置16をもつて十分
に行なうことができるが、前記ノズルにおける前
記混合物の付着、固化を完全になくすために、前
記水溶性ウレタンプレポリマーの噴出用管および
前記水の噴出用管を二つの独立した管(図示せ
ず)とすることができる。この場合、それぞれの
管に設けられたノズルから、前記水溶性ウレタン
プレポリマーおよび前記水のそれぞれを同時に噴
出しながら両物質を混合させて前記アルカリ物質
の層または杭14の表面に吹き付ける。
In the illustrated example in which the pipe 22 is a double pipe, the water-soluble urethane prepolymer is separated from the water with which it is mixed, such as in its storage container, feeding equipment to the nozzle (not shown), etc. Because of this, it does not solidify in these equipment during spraying. However, the water-soluble urethane prepolymer and water pass through the nozzle at the tip of the outer tube 22a. Therefore, a portion of the mixture adheres to the nozzle and solidifies. However, the amount is relatively small because the exit velocity and exit pressure of the mixture during passage through the nozzle are relatively high. Therefore, although the application of the mixture to the layer of alkaline material or the surface of the pile can be sufficiently performed using the device 16, in order to completely eliminate adhesion and solidification of the mixture at the nozzle, The pipe for ejecting the water-soluble urethane prepolymer and the pipe for ejecting the water can be two independent pipes (not shown). In this case, the water-soluble urethane prepolymer and the water are simultaneously jetted from nozzles provided in each tube, and the two substances are mixed and sprayed onto the layer of the alkaline material or the surface of the pile 14.

杭14の溝孔12中への挿入は、前記含水ゲル
の層を前記アルカリ物質の層が被覆する場合は該
アルカリ物質の層の形成後、また、前記含水ゲル
の層が前記アルカリ物質の層を被覆する場合は前
記混合物がその塗布箇所でゲル化して含水ゲルと
なつたのちに行なう。杭14への前記混合物の塗
布箇所がゲル化するまでの間、杭14を一定の高
さ位置で停止させておくが、この停止時間は、ゲ
ルタイムを短縮することによつて短くすることが
できる。
The piles 14 are inserted into the slots 12 after the formation of the alkaline substance layer when the hydrogel layer is covered with the alkaline substance layer, and after the formation of the alkaline substance layer when the hydrogel layer is coated with the alkaline substance layer. In the case of coating, this is done after the mixture has gelatinized into a water-containing gel at the application site. Until the area where the mixture is applied to the pile 14 gels, the pile 14 is stopped at a certain height, but this stopping time can be shortened by shortening the gel time. .

前記ゲルタイムは、前記水の温度を上げること
(30℃〜50℃)、前記水の量を越えない範囲で前記
水溶性ウレタンプレポリマーの混合割合を増加さ
せること、あるいはトリエチレンジアミンのよう
な高級アミン、ジブチルスズジラウレートのよう
な有機スズ化合物等の触媒を添加することによ
り、短縮することができる。
The gel time can be achieved by increasing the temperature of the water (30°C to 50°C), increasing the mixing ratio of the water-soluble urethane prepolymer within a range that does not exceed the amount of water, or adding a higher amine such as triethylene diamine. , can be shortened by adding a catalyst such as an organotin compound such as dibutyltin dilaurate.

前記アルカリ物質の層および含水ゲルから成る
前記被膜の形成箇所は、杭14の全表面(第16
図)、杭14の下方部分の表面(第17図)、杭1
4の長手方向の複数のレベルにおける部分の表面
(第18図)、杭14の下方部分の表面と該下方部
分から上方の複数のレベルにおける部分の表面
(第19図)等があり、対象地盤、適用される工
法等を考慮して定められる。
The coating formed of the alkaline substance layer and hydrogel is formed on the entire surface of the pile 14 (16th
Figure), surface of the lower part of pile 14 (Figure 17), pile 1
The surface of the portion at multiple levels in the longitudinal direction of the pile 14 (Figure 18), the surface of the lower portion of the pile 14, and the surface of the portion at multiple levels above the lower portion (Figure 19), etc. , determined in consideration of the applicable construction method, etc.

前記のようにして被膜が形成された後、杭14
を溝孔12中に挿入し、次いで溝孔12を充填す
る。杭14の溝孔12中への挿入は、ソイルセメ
ント柱列杭工法におけるように、溝孔12を充填
したのちであつてもよい。
After the coating is formed as described above, the pile 14
into the slot 12 and then fill the slot 12. The piles 14 may be inserted into the slots 12 after the slots 12 have been filled, as in the soil-cement column pile method.

この際、前記泥水固化工法およびソイルセメン
ト柱列杭工法によるときは、アルカリ性を有する
固化材により固化された杭周辺の固化層で溝孔1
2が充填され、杭14が埋設される。
At this time, when using the muddy water solidification method and the soil cement column pile method, the groove hole 1 is
2 is filled and the pile 14 is buried.

前記ジヨイスト工法による場合、掘り出された
土砂をそのまま埋め戻すことにより溝孔が充填さ
れ、杭14が埋設される。
In the case of the joist construction method, the trench is filled by backfilling the excavated earth and sand as it is, and the pile 14 is buried.

前記アルカリ物質の層が前記水ガラスとセメン
トペーストとの混練物から成る場合には、前記ア
ルカリ物質の層上に前記含水ゲルを形成したとき
から、また、前記アルカリ物質の層が前記粉状物
から成るときは、杭の埋設により前記アルカリ物
質が杭の周囲地盤中の水分を吸収したときから、
前記アルカリ物質と前記含水ゲルとが反応して含
水ゲルの層が徐々に軟化し、グリース状に変化す
る。前記含水ゲルの層の部分的なグリース状化に
要する日数はほぼ数日であるが、一般に杭の引き
抜きが行なわれるのは杭の埋設後早くとも数ケ月
であることから、杭の引き抜き時においては前記
含水ゲルの層のほとんど全部がグリース状に変化
する。これにより、杭の引き抜き時には杭と周辺
の固化層あるいは埋め戻し土砂とがほぼ完全に分
離され、杭の引き抜きの際にはグリース状に変化
した前記被膜が潤滑作用をなし、引き抜き抵抗を
小さくする。
When the layer of alkaline material is made of a kneaded mixture of water glass and cement paste, from the time when the hydrogel is formed on the layer of alkaline material, the layer of alkaline material is When the alkaline substance absorbs moisture in the ground surrounding the pile due to the burial of the pile,
The alkaline substance and the hydrogel react, and the hydrogel layer gradually softens and becomes grease-like. It takes approximately several days for the hydrous gel layer to become partially greasy, but since piles are generally pulled out at the earliest several months after they are buried, Almost all of the hydrogel layer turns into a grease-like layer. As a result, when the pile is pulled out, the pile and the surrounding solidified layer or backfill earth and sand are almost completely separated, and when the pile is pulled out, the coating that changes into a grease-like form acts as a lubricant, reducing the pulling resistance. .

前記含水ゲルの層と反応するアルカリ成分が、
該含水ゲルとともに被膜を構成する前記アルカリ
物質の層であることから、前記ジヨイスト工法に
おける埋め戻し土砂がアルカリ性を有しない土質
のものであつて杭の周囲の地盤の作用による前記
含水ゲルの層のグリース状への変化を期待できな
い場合であつても、前記含水ゲルの層を確実にグ
リース状に変化させることができる。また、周囲
地盤が、前記泥水固化工法または前記ソイルセメ
ント柱列杭工法におけるように、充填材料がアル
カリ性を有する場合であつて前記含水ゲルの層が
前記アルカリ物質の層を被覆しているときは、前
記含水ゲルは前記アルカリ物質および前記充填材
料中のアルカリ成分の双方と反応する。
The alkaline component that reacts with the hydrogel layer is
Since it is a layer of the alkaline substance that forms a coating together with the hydrous gel, the backfill soil in the Jyoist construction method is of non-alkaline soil and the layer of hydrous gel is formed by the action of the ground around the pile. Even if the layer of hydrogel cannot be expected to change into a grease-like state, the hydrogel layer can be reliably changed into a grease-like state. Further, when the surrounding ground has an alkaline filling material as in the mud solidification method or the soil cement column pile method, and the layer of hydrous gel covers the layer of alkaline material, , the hydrogel reacts with both the alkaline substance and the alkaline component in the filler material.

前記した例では、杭14の表面に前記アルカリ
物質の層とともに被膜を構成する含水ゲルの層を
形成した後、杭14を溝孔12に挿入した。しか
し、掘削された溝孔12中に地下水や安定液ある
いはモルタルやセメントペーストのような水分を
有する固化材が存在するときは、前記含水ゲルの
層に代えてこれを前記水溶性ウレタンプレポリマ
ーの層とし、これを溝孔中に挿入することによ
り、溝孔中で該溝孔中の水分と水溶性ウレタンプ
レポリマーとを反応させて含水ゲルの層を形成す
ることができる。
In the example described above, the pile 14 was inserted into the slot 12 after forming a layer of hydrous gel constituting a coating together with the layer of the alkaline substance on the surface of the pile 14 . However, if underground water, a stabilizing liquid, or a solidifying material containing moisture such as mortar or cement paste is present in the excavated trench 12, this is used instead of the water-containing gel layer. By inserting this layer into a slot, water in the slot can react with the water-soluble urethane prepolymer to form a layer of hydrogel.

この場合、水溶性ウレタンプレポリマーの塗布
に先立ち、これにフライアツシユ、粘土、ベント
ナイトのような微粒物質を混入しておくことが望
ましい。これにより、塗布材料の増量を図ること
ができるとともに水溶性ウレタンプレポリマーの
みを塗布したときのたれ落ちを防止することがで
きる。また、水溶性ウレタンプレポリマーと前記
微粒物質との混合物の塗布は、ローラ塗りあるい
ははけ塗りによることができるが、前記微粒物質
の存在によりこのときの塗り性能を高める。さら
に、水溶性ウレタンプレポリマーは前記微粒物質
を取り囲んだ状態で杭の表面に塗布されるため、
塗布面が凹凸状を呈し、水溶性ウレタンプレポリ
マーを単独で塗布した場合に比べ、前記塗布面の
表面積を実質的に大きくすることができ、これに
より、水溶性ウレタンプレポリマーのゲル化を早
めることができる。
In this case, it is desirable to mix a fine particulate material such as fly ash, clay, or bentonite into the water-soluble urethane prepolymer prior to coating it. This makes it possible to increase the amount of coating material and to prevent dripping when only the water-soluble urethane prepolymer is coated. Further, the mixture of the water-soluble urethane prepolymer and the fine particulate material can be applied by roller coating or brush painting, and the presence of the fine particulate material improves the coating performance at this time. Furthermore, since the water-soluble urethane prepolymer is applied to the surface of the pile while surrounding the fine particles,
The coated surface exhibits an uneven shape, and the surface area of the coated surface can be substantially increased compared to when the water-soluble urethane prepolymer is applied alone, thereby accelerating gelation of the water-soluble urethane prepolymer. be able to.

予め地盤に溝孔を設け、該溝孔中に杭を挿入す
ることにより杭を地中に埋設する方法を採らず
に、杭を打ち込むことによりこれを地中に埋設す
ることができる。この場合、地盤がアルカリ性の
土質を有するか否かに拘らず、前記溝孔に杭を挿
入する場合と同様にして、杭の表面に前記含水ゲ
ルまたは前記水溶性ウレタンプレポリマーの層
と、前記アルカリ物質の層とを有する前記被膜を
形成した後、杭を打ち込んで地中に埋設する。
It is possible to bury the pile in the ground by driving the pile instead of using a method of burying the pile in the ground by providing a groove in the ground in advance and inserting the pile into the groove. In this case, regardless of whether the ground has alkaline soil quality or not, the layer of the hydrogel or the water-soluble urethane prepolymer is applied to the surface of the pile in the same manner as when inserting the pile into the groove. After forming the coating having the layer of alkaline material, it is buried underground by driving a pile.

前記含水ゲルに代えて水溶性ウレタンプレポリ
マーまたはこれと前記微粒物質との混合物を塗布
した杭を地中に打ち込むときは、塗布箇所が地下
水位下に位置するようにする。これにより、水溶
性ウレタンプレポリマーが地下水と反応して杭の
表面に前記と同様の含水ゲルの層が形成される。
When driving into the ground a pile coated with a water-soluble urethane prepolymer or a mixture of the same and the fine particulate material instead of the hydrogel, the application site should be located below the groundwater level. As a result, the water-soluble urethane prepolymer reacts with groundwater to form a hydrogel layer similar to that described above on the surface of the pile.

杭の表面の前記含水ゲルの層は、前記したと同
様に、前記アルカリ物質と反応して、または、該
アルカリ物質および杭を採り囲む地盤中のアルカ
リ性の成分と反応して軟化し、最終的にグリース
状になる。
As described above, the hydrous gel layer on the surface of the pile is softened by reacting with the alkaline substance or with the alkaline substance and the alkaline components in the ground surrounding the pile. Becomes greasy.

なお、予め溝孔を穿つて杭を地中に埋設する場
合および打込みにより杭を地中に埋設する場合の
いずれにあつても、杭の表面のうち根切り面を構
成する箇所への前記含水ゲルの形成を省略するこ
とができる。
In addition, whether the pile is buried in the ground by drilling a trench in advance or by driving the pile into the ground, the above-mentioned water content on the surface of the pile that constitutes the root cut surface Gel formation can be omitted.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は泥水固化工法に従つて構
築された土留め壁の概略横断面図、第3図、第4
図および第5図は泥水固化工法の工程を示す概略
図、第6図はソイルセメント柱列杭工法に従つて
構築された土留め壁の概略横断面図、第7図およ
び第8図はソイルセメント柱列杭工法の工程を示
す概略図、第9図はジヨイスト工法に従つて横築
された土留め壁の概略横断面図、第10図、第1
1図および第12図はジヨイスト工法の工程を示
す概略図、第13図は水溶性ウレタンプレポリマ
ーおよび水の吹き付け装置の正面図、第14図は
吹き付け装置の平面図、第15図は二重管の部分
拡大断面図、第16図、第17図、第18図およ
び第19図は被膜の形成箇所を示す杭の縦断面図
である。 12……溝孔、14……杭、15……水溶性ウ
レタンプレポリマーおよび水の混合物、16……
吹き付け装置。
Figures 1 and 2 are schematic cross-sectional views of an earth retaining wall constructed according to the mud solidification method, and Figures 3 and 4 are
Figure 5 and Figure 5 are schematic diagrams showing the steps of the mud water solidification method, Figure 6 is a schematic cross-sectional view of an earth retaining wall constructed according to the soil cement column pile method, and Figures 7 and 8 are soil Figure 9 is a schematic diagram showing the steps of the cement column pile construction method;
Figures 1 and 12 are schematic diagrams showing the process of the Jyoist method, Figure 13 is a front view of the water-soluble urethane prepolymer and water spraying equipment, Figure 14 is a plan view of the spraying equipment, and Figure 15 is a double The partially enlarged sectional view of the pipe, and FIGS. 16, 17, 18, and 19 are vertical sectional views of the pile showing the locations where the coating is formed. 12...Slot, 14...Pile, 15...Mixture of water-soluble urethane prepolymer and water, 16...
Spraying equipment.

Claims (1)

【特許請求の範囲】 1 杭の表面の少なくとも一部にアルカリ性を有
する物質の層および水溶性ウレタンプレポリマー
と水とを反応させて得た含水ゲルの層から成る被
膜を形成すること、前記杭を溝孔中に挿入するこ
と、その後前記溝孔を充填することを含む、杭の
引き抜きのための処理方法。 2 前記アルカリ性を有する物質は、水ガラスと
セメントペーストとの混合物から成る、特許請求
の範囲第1項の処理方法。 3 前記アルカリ性を有する物質を前記杭の表面
に塗布した後、前記アルカリを有する物質を前記
含水ゲルで被覆する、特許請求の範囲第1項の処
理方法。 4 前記含水ゲルを前記杭の表面に塗布した後、
前記含水ゲルを前記アルカリ性を有する物質で被
覆する、特許請求の範囲第1項の処理方法。 5 前記含水ゲルの層は、前記杭の表面に前記水
溶性ウレタンプレポリマーと前記水とを別個にか
つ同時に吹き付けてこれらを混合することにより
反応させる、特許請求の範囲第1項の処理方法。 6 杭の表面の少なくとも一部にアルカリ性を有
する物質の層および水溶性ウレタンプレポリマー
の層から成る被膜を形成すること、前記杭を、地
下水または安定液を有する溝孔中に挿入するこ
と、その後前記溝孔を充填することを含む、杭の
引き抜きのための処理方法。 7 杭の表面の少なくとも一部にアルカリ性を有
する物質を塗布すること、前記アルカリ性を有す
る物質を水溶性ウレタンプレポリマーと水とを反
応させて得た含水ゲルで被覆すること、その後前
記杭を地盤中に埋設することを含む、杭の引き抜
きのための処理方法。 8 前記含水ゲルの層は、前記杭の表面に前記水
溶性ウレタンプレポリマーと前記水とを別個にか
つ同時に吹き付けてこれらを混合することにより
反応させる、特許請求の範囲第7項の処理方法。 9 杭の表面の少なくとも一部にアルカリ性を有
する物質を塗布すること、前記アルカリ性を有す
る物質を水溶性ウレタンプレポリマーで被覆する
こと、その後前記杭の前記水溶性ウレタンプレポ
リマーで被覆された箇所が地下水位下に位置する
ように前記杭を地盤中に埋設することを含む、杭
の引き抜きのための処理方法。
[Scope of Claims] 1. Forming on at least a portion of the surface of the pile a coating consisting of a layer of an alkaline substance and a layer of hydrogel obtained by reacting a water-soluble urethane prepolymer with water; A method for the extraction of piles, the method comprising: inserting a pile into a slot, and subsequently filling said slot. 2. The treatment method according to claim 1, wherein the alkaline substance is a mixture of water glass and cement paste. 3. The treatment method according to claim 1, wherein after applying the alkaline substance to the surface of the pile, the alkali substance is coated with the hydrous gel. 4 After applying the hydrogel to the surface of the pile,
The treatment method according to claim 1, wherein the hydrogel is coated with the alkaline substance. 5. The treatment method according to claim 1, wherein the water-containing gel layer is formed by spraying the water-soluble urethane prepolymer and the water separately and simultaneously onto the surface of the pile and mixing them to react. 6. Forming a coating consisting of a layer of an alkaline substance and a layer of a water-soluble urethane prepolymer on at least part of the surface of the pile, inserting the pile into a trench containing groundwater or a stabilizing liquid, and then A processing method for the extraction of piles, comprising filling said slots. 7 Applying an alkaline substance to at least a portion of the surface of the pile, coating the alkaline substance with a hydrous gel obtained by reacting a water-soluble urethane prepolymer with water, and then placing the pile in the ground. Processing methods for the extraction of piles, including burying them inside. 8. The treatment method according to claim 7, wherein the water-containing gel layer is reacted by spraying the water-soluble urethane prepolymer and the water separately and simultaneously onto the surface of the pile and mixing them. 9 Applying an alkaline substance to at least a portion of the surface of the pile, coating the alkaline substance with a water-soluble urethane prepolymer, and then applying the alkaline substance to at least a portion of the pile surface, and then coating the pile with the water-soluble urethane prepolymer. A treatment method for extracting a pile, comprising burying said pile in the ground so as to be located below the groundwater level.
JP22859782A 1982-12-29 1982-12-29 Treatment for drawing pile Granted JPS59122621A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22859782A JPS59122621A (en) 1982-12-29 1982-12-29 Treatment for drawing pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22859782A JPS59122621A (en) 1982-12-29 1982-12-29 Treatment for drawing pile

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP14284686A Division JPS61290118A (en) 1986-06-20 1986-06-20 Treatment for drawing out pile

Publications (2)

Publication Number Publication Date
JPS59122621A JPS59122621A (en) 1984-07-16
JPS6339730B2 true JPS6339730B2 (en) 1988-08-08

Family

ID=16878845

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22859782A Granted JPS59122621A (en) 1982-12-29 1982-12-29 Treatment for drawing pile

Country Status (1)

Country Link
JP (1) JPS59122621A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0663477A1 (en) * 1994-01-14 1995-07-19 Nippon Shokubai Co., Ltd. Lubricating material for extraction of temporarily buried reinforcement
JP7291069B2 (en) * 2019-12-10 2023-06-14 鹿島建設株式会社 Dismantling method and pressure device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5978809A (en) * 1982-10-29 1984-05-07 西松建設株式会社 Method of drawing steel material from cement group hardened material

Also Published As

Publication number Publication date
JPS59122621A (en) 1984-07-16

Similar Documents

Publication Publication Date Title
JPS6339730B2 (en)
DE10013446A1 (en) Method and device for producing an in-situ concrete pile
DE1914554C3 (en) Method for sealing ground formations and civil engineering structures
JPH0242968B2 (en)
US3180098A (en) Soil solidification process
JP4885087B2 (en) Water stop layer formation method
JP3363099B2 (en) Supporting ground improvement method for existing structures
JPH0410529B2 (en)
JPH03271419A (en) Chemical injection device
JP3706998B2 (en) Ethanol bentonite grout method
JP2936439B2 (en) Temporary impermeable wall construction method
JPH0345193B2 (en)
JPS55165317A (en) Burying method for steel-pipe sheet pile
JP2934435B1 (en) Method for reducing lateral displacement in ground in powder injection agitation method and permeable pipe used in the method
JPH04128415A (en) Method and device for improving ground
JPH01131786A (en) Water-stopping method using water-stopping chemicals in deep boreholes
JP2005232322A (en) Production method of soil with stable soil treatment
JP2024049179A (en) Bag for box jacking method and box jacking method
JP2548057B2 (en) Caisson sinking method
JPH0377349B2 (en)
JPS594718A (en) Jet injection device
JPH0442499B2 (en)
JPS6128046B2 (en)
JP2711029B2 (en) Soil improvement method of pile formation hollow moat
JPS638245B2 (en)