Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS6358993B2 - - Google Patents
[go: Go Back, main page]

JPS6358993B2 - - Google Patents

Info

Publication number
JPS6358993B2
JPS6358993B2 JP16927183A JP16927183A JPS6358993B2 JP S6358993 B2 JPS6358993 B2 JP S6358993B2 JP 16927183 A JP16927183 A JP 16927183A JP 16927183 A JP16927183 A JP 16927183A JP S6358993 B2 JPS6358993 B2 JP S6358993B2
Authority
JP
Japan
Prior art keywords
formwork
column
frame structure
hanger
moved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP16927183A
Other languages
Japanese (ja)
Other versions
JPS6062366A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP16927183A priority Critical patent/JPS6062366A/en
Publication of JPS6062366A publication Critical patent/JPS6062366A/en
Publication of JPS6358993B2 publication Critical patent/JPS6358993B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 本発明は、建築物の大組柱型枠工法に係り、詳
しくは大組型枠による1階分の躯体コンクリート
の1回の打設に伴つてコンクリート柱を築造する
大組柱型枠工法に関する。
[Detailed Description of the Invention] The present invention relates to a construction method for large-scale column-forming for buildings, and more specifically, a method for constructing concrete columns with one-time pouring of concrete for one floor using large-scale formwork. Concerning the large-assembly column formwork construction method.

従来、中層建築物等の躯体構造物を作るには、
一般にメタルフオーム工法が行われてきたが、こ
のメタルフオーム工法は組立、解体が手作業で行
われる為、施工能率が悪く、工期が長期化してい
た。このようなことから近時、大組型枠を用いる
種々の工法が普及しているが、これらの工法はい
ずれも壁、柱と梁、スラブのコンクリートが2回
に分けて打設されるので、壁、柱の大組型枠の据
付け、脱型、移動と、梁、スラブの大組型枠の据
付け、脱型、移動とを交互に行うことになり、施
工が繁雑となつて、施工能率が期待したほど向上
しないのが実情である。
Traditionally, to make frame structures such as medium-rise buildings,
Generally, metal form construction methods have been used, but because assembly and disassembly are done by hand, construction efficiency is poor and the construction period is long. For this reason, various construction methods using large-scale formwork have become popular in recent years, but in all of these construction methods, concrete for walls, columns and beams, and slabs is poured in two steps. , the installation, stripping, and movement of the large formwork for walls and columns and the installation, stripping, and movement of the large formwork for beams and slabs were carried out alternately, making the construction process complicated. The reality is that efficiency has not improved as much as expected.

一方、建築物の1階分の躯体コンクリートを1
回で打設すべく内部の柱とスラブ・梁の型枠を大
組みの型枠にすると、大組みの柱型枠は建築物に
奥行があつてクレーンにて吊り出したり、所定位
置に吊り降ろしたりすることができない場合、四
面の型枠パネルに解体して運搬しなければならな
い為、折角の大組柱型枠による躯体構造物の築造
の省力化、施工の能率化を発揮できないものであ
る。
On the other hand, the concrete for the first floor of the building was
When the formwork for internal columns, slabs, and beams is made into a large-scale formwork to be poured in one step, the large-scale column formwork has a depth in the building, so it must be lifted with a crane or lowered into a predetermined position. If it is not possible to do so, it will have to be dismantled into formwork panels on all four sides and transported, making it impossible to achieve the labor-saving and efficiency of building frame structures using large column formwork. .

本発明は、斯かる諸事情に鑑みなされたもの
で、建築物に奥行があつて大組柱型枠をクレーン
にて吊り出すことができない場合、解体すること
なく築造した躯体構造物の開口部まで走行移動
し、これをリフテイングフレームにて上階に吊り
上げて所定の柱鉄筋の配筋された位置に吊り降ろ
し、柱鉄筋を内包するようにセツトし、後からセ
ツトされる大組スラブ・梁型枠の左右両端に進退
可能に支持された梁側型枠に結合し且つ走行可能
に吊垂後、躯体コンクリートの1回の打設に伴つ
て大組柱型枠の内部にコンクリート柱を築造して
いく工程を、繰り返し行つて所要階数の躯体構造
物のコンクリート柱を築造することを特徴とする
大組柱型枠工法を提供せんとするものである。
The present invention was made in view of the above circumstances, and when the building is so deep that it is not possible to lift the large column formwork with a crane, the opening of the frame structure constructed without disassembly can be removed. This is then lifted to the upper floor using a lifting frame and lowered to the predetermined position where the column reinforcing bars are arranged, and is set so as to enclose the column reinforcing bars. After connecting to the beam side formwork that is movably supported at both the left and right ends of the beam formwork and hanging it so that it can move, concrete columns are placed inside the large column formwork with one cast of concrete for the frame. The purpose of the present invention is to provide a large-assembly column form construction method characterized by repeating the construction process to construct concrete columns for a frame structure of a required number of floors.

以下本発明による大組柱型枠工法の一実施例を
説明する。
An embodiment of the large-assembly column formwork construction method according to the present invention will be described below.

先ず、本発明の大組柱型枠を実施する為の大組
柱型枠を第1,2図によつて説明すると、は複
数枚の鋼板型枠をUクリツプにて結合の上、
上、中、下3段に角パイプ2丁合わせの端太材
にて補強した広幅の型枠パネルで、この型枠パネ
ルは相対向して設けられ、各型枠パネルの互
いに反対側の側端に細幅の型枠パネルが回動可
能に支持されている。即ち、各細幅の型枠パネル
の両側端に、前記広幅の型枠パネルの側端に
当接結合するアングル材が固設され、一側端の
アングル材にヒンヂプレートが上、中、下3
段に固設され、この各ヒンヂプレートのボルト
穴と広幅の型枠パネルの端太材の端部に穿設
された長孔にヒンヂボルトが挿通され締付け
られて、細幅の型枠パネルが広幅の型枠パネル
の側端に回動可能に支持されている。従つて、
柱の二側面の型枠パネルが開閉可能となつてい
る。なお、端太材の端部に長孔を穿設する代
りに、ヒンジプレートに長孔を穿設し、端太材
の端部にボルト孔を穿設してもよい。この細幅
の型枠パネルを回動して閉じたその外側で、相
対向する端太材の端部間にはタイボルトが締
付張架されて、相対向する広幅の型枠パネル間
がコンクリートの打設により拡がらないようにな
つている。広幅の型枠パネルの上段の端太材
には左右にハンガー取付金具が設けられてい
て、これに上端にローラを有する伸縮可能なハ
ンガーの下端が結合されるようになつている。
そしてこのハンガーにて大組スラブ・梁型枠
(図示省略)の左右両側端の進退可能な梁側型枠
の下端に設けたハンガーレールに、広幅の型枠パ
ネルを走行可能に吊垂するようにしてある。広
幅の型枠パネルの外面には後述するリフテイン
グフレームで吊り上げる為の吊り金具が水平に
取付けられている。尚、細幅の型枠パネルは、
建築物の角部外面に配される大組柱型枠以外、広
幅の型枠パネルよりも上端を低くしてあつて、
所定位置にセツトした際、この部分に梁底型枠の
端部のL型鋼製型枠が配されるようになつてい
る。
First, the large-assembly column formwork for implementing the large-assembly column formwork of the present invention will be explained with reference to FIGS. 1 and 2. After joining a plurality of steel plate formworks with U clips,
It is a wide formwork panel reinforced with thick pieces of two square pipes in the top, middle, and bottom three tiers.The formwork panels are installed facing each other, and the sides of each formwork panel are opposite to each other. A narrow formwork panel is rotatably supported at the end. That is, angle members that abut and connect to the side ends of the wide form panel are fixed at both ends of each narrow formwork panel, and hinge plates are attached to the angle members at one end of the upper, middle, and lower three sides.
The hinge bolts are inserted into the bolt holes of each hinge plate and the long holes drilled at the end of the end pieces of the wide formwork panel and tightened, and the narrow formwork panel becomes the wide formwork panel. It is rotatably supported at the side edge of the formwork panel. Therefore,
Formwork panels on two sides of the column can be opened and closed. In addition, instead of drilling a long hole in the end of the thick piece, a long hole may be bored in the hinge plate, and a bolt hole may be bored in the end of the thick piece. After this narrow formwork panel is rotated and closed, tie bolts are tightened and tensioned between the ends of the opposite thick timbers, and the concrete is placed between the wide formwork panels facing each other. The concrete is placed in place to prevent it from spreading. Hanger attachment fittings are provided on the left and right sides of the upper half of the wide formwork panel, to which the lower end of an extendable hanger having a roller at the upper end is connected.
Using this hanger, a wide formwork panel is hung movably from the hanger rail provided at the lower end of the beam side formwork that can move forward and backward on both the left and right ends of the large slab/beam formwork (not shown). It is set as. Hanging fittings for lifting with a lifting frame, which will be described later, are installed horizontally on the outer surface of the wide formwork panel. In addition, narrow formwork panels are
Other than large column formwork placed on the exterior corner of a building, the upper end is lower than the wide formwork panel.
When set in a predetermined position, the L-shaped steel formwork at the end of the beam bottom formwork is placed in this portion.

次に上記構成の大組柱型枠を用いる本発明の
大組柱型枠工法について説明する。
Next, the large-assembly column form construction method of the present invention using the large-assembly column formwork having the above-mentioned configuration will be explained.

第3図aに示す如く大組柱型枠を所定位置に
セツトし、同様に所定位置にセツトした大組スラ
ブ・梁型枠の左右両側端の進退可能な梁側型枠
の下端のハンガーレールに、広幅の型枠パネル
をその上段の端太材のハンガー取付金具に
取付けたハンガーの上端のローラにて走行可
能に吊垂した上、該型枠パネルの上端を梁側型
枠の下端に結合し、細幅の型枠パネルの上端
に大組柱型枠間に配した梁底型枠の端部のL
形鋼製型枠17aを結合した状態で、1階の躯体
コンクリートの1回の打設に伴つて大組柱型枠
内にコンクリート柱を築造する。
As shown in Figure 3a, the large assembled column formwork is set in a predetermined position, and the hanger rails at the lower end of the beam side formwork that can move forward and backward at both left and right ends of the large assembled slab/beam formwork that is also set in a predetermined position. First, a wide formwork panel was suspended so that it could run from the rollers at the upper end of the hanger attached to the hanger mounting bracket of the upper end thick material, and the upper end of the formwork panel was attached to the lower end of the beam side formwork. L of the end of the beam bottom formwork that is connected and placed between the large column formworks at the upper end of the narrow formwork panel.
With the shaped steel formwork 17a connected, concrete columns are constructed within the large column formwork in conjunction with one-time pouring of concrete for the first floor frame.

次いで、細幅の型枠パネルの外側で相対向す
る端太材の端部間に第2図のように張架された
タイボルトをはずし、各型枠パネルをヒンジ
ボルトを介して、端太材の長孔に沿つて外
側方に引き、且つ、梁底型枠の端部のL型鋼製
17aと広幅の型枠パネルの上部両側面を結合
しているコーナーアングルを取外す。
Next, as shown in Fig. 2, remove the tie bolts stretched between the ends of the end pieces that face each other on the outside of the narrow formwork panels, and connect each formwork panel to the end pieces through the hinge bolts. Pull it outward along the long hole and remove the corner angle that connects the L-shaped steel 17a at the end of the beam bottom formwork to both upper sides of the wide formwork panel.

次に、ハンガーを伸長して大組柱型枠装置
を脱型し、大組柱型枠をハンガーのローラ
にてハンガーレールに沿つて走行させて躯体構
造物の開口部に移動する。同様に躯体構造物のコ
ンクリート柱を築造した各大組柱型枠を前記の
手順を経て脱型し、順次躯体構造物の開口部に移
動する。
Next, the hanger is extended to remove the large-assembly column form device from the mold, and the large-assembly column form is moved along the hanger rail by the rollers of the hanger to the opening of the frame structure. Similarly, each large column formwork for constructing the concrete columns of the frame structure is demolded through the above-mentioned procedure, and sequentially moved to the opening of the frame structure.

さて、開口部に移動した大組柱型枠は、ハン
ガーの下端をハンガー取付金具より外し、第
3図Cの一点鎖線の如く型枠パネルの外面の吊
り金具にリフテイングフレームFの吊り索Wを
掛合し、リフテイングフレームFにて大組柱型枠
を吊り、該大組柱型枠の一側が躯体構造物B
の外方にはみ出るまで引き出し、その一側面の開
かれた細幅の型枠パネルを閉じ隣接する広幅の
型枠パネルとクリツプ等で連結した後、リフテ
イングフレームFにて大組柱型枠全体を躯体構
造物Bの外に引き出して実線に示す如く吊り上げ
る。そして第3図dに示す如く柱鉄筋が配筋さ
れ、キツカーが躯体構造物Bのスラブコンクリ
ートと一体に設けられた2階の所定位置に移動
し、柱鉄筋を内側に挾んで吊り降ろし、予めス
ラブコンクリートと一体に設けられたキツカー
の外面に配置した枕上に載せ、他側面の開かれ
た細幅の型枠パネルを閉じ、両外側で相対向す
る端太材の端部間にタイボルトを締付張架し
てセツトを終える。同様に各大組柱型枠を夫々
2階の所定位置に吊り上げ移動してセツトする。
Now, for the large column formwork that has been moved to the opening, remove the lower end of the hanger from the hanger mounting bracket, and attach the hanging rope W of the lifting frame F to the hanging bracket on the outside of the formwork panel as shown by the dashed line in Figure 3C. The large-assembly column formwork is suspended by the lifting frame F, and one side of the large-assembly column formwork is connected to the frame structure B.
The narrow formwork panel opened on one side is closed and connected to the adjacent wide formwork panel with clips, etc., and then the entire large column formwork is removed using the lifting frame F. Pull it out of the frame structure B and lift it up as shown by the solid line. Then, the column reinforcing bars are arranged as shown in Figure 3d, and the kicker is moved to a predetermined position on the second floor, which is built integrally with the slab concrete of the frame structure B, and the column reinforcing bars are held inside and suspended, and pre-assembled. Place the slab on a pillow placed on the outside of the concrete slab, close the narrow formwork panel that is open on the other side, and tighten tie bolts between the ends of the end pieces facing each other on both outside sides. Finish setting by tensioning the rack. Similarly, each large column formwork is lifted up and moved to a predetermined position on the second floor and set.

そして築造された1階の躯体構造物B内から梁
底型枠、大組スラブ・梁型枠(図示省略)、そ
の大組スラブ・梁型枠の前後方向端の梁型枠(図
示省略)等を脱型して2階の所定位置に移動して
セツトし、また躯体構造物B外の外面梁側型枠を
脱型して2階の所定位置に移動してセツトした
後、2階の躯体コンクリートの1回の打設によ
り、前記各大組柱型枠内にコンクリート柱を築
造し、養生する。以後前記工程を繰り返し行つて
所要階数の躯体構造物の築造に伴つてその各階で
コンクリート柱を築造する。
Then, from inside the constructed first floor frame structure B, there is a beam bottom form, a large slab/beam form (not shown), and a beam form at the longitudinal end of the large slab/beam form (not shown). etc., and moved it to a predetermined position on the second floor and set it. Also, after demolding the external beam side formwork outside frame structure B and moved it to a predetermined position on the second floor and set it, Concrete columns are constructed and cured within each of the above-mentioned large-assembly column forms by placing concrete for the frame once. Thereafter, the above steps are repeated to construct concrete pillars on each floor as the frame structure of the required number of floors is constructed.

以上の説明で判るように本発明の大組柱型枠工
法は、大組スラブ・梁型枠の両側端の梁側型枠の
下端に設けたハンガーレールに沿つて築造した躯
体構造物の開口部まで大組柱型枠を走行移動する
ので、リフテイングフレームにて容易に吊り上げ
て上階の所定位置に吊り降ろすことができ、従つ
て、従来のように大組柱型枠を四面の型枠パネル
に解体して運搬する必要が無く、躯体構造物の築
造が省力化され、施工能率が大幅に向上する。
As can be seen from the above explanation, the large-assembly column formwork construction method of the present invention uses the opening of the frame structure constructed along the hanger rails provided at the lower end of the beam-side formwork at both ends of the large-assembly slab/beam formwork. Since the large-assembly column formwork is moved to the upper floor, it can be easily lifted up using a lifting frame and lowered to a predetermined position on the upper floor. There is no need to disassemble it into frame panels and transport it, which saves labor in constructing the frame structure and greatly improves construction efficiency.

また本発明の大組柱型枠工法は、大組柱型枠の
二側面の型枠パネルを開いて走行させるので、そ
の走行方向に築造したコンクリート柱があつても
二側面の型枠パネルを開いてそのコンクリート柱
を避けて躯体構造物の開口部まで走行移動でき、
しかも大組柱型枠を上階にリフテイングフレーム
で吊り上げる際、一側面の型枠パネルを閉じて相
対向する広幅の型枠パネルを連結するので、大組
柱型枠を安定して吊り上げ移動でき、しかも大組
柱型枠を上階の所定位置に移動した際、予め配筋
された鉄筋を囲んでセツトするので、極めて作業
性が良く、コンクリート柱築造の為の段取作業を
著しく簡易化できる等の効果がある。
In addition, in the large-assembly column formwork method of the present invention, the formwork panels on the two sides of the large-assembly column formwork are opened and run, so even if there are concrete columns constructed in the direction of travel, the formwork panels on the two sides are left open. It opens and allows you to avoid the concrete pillar and move to the opening of the frame structure.
Furthermore, when lifting the large column formwork to the upper floor using the lifting frame, one side of the formwork panel is closed and the opposing wide formwork panels are connected, so the large column formwork can be lifted and moved in a stable manner. Furthermore, when the large column formwork is moved to the specified position on the upper floor, it is set around the reinforcing bars that have been arranged in advance, making it extremely easy to work and greatly simplifying the setup work for constructing concrete columns. It has the effect of being able to be converted into

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の工法に於いて用いる大組柱型
枠の斜視図、第2図はその平面図、第3図a乃至
dは本発明の大組柱型枠工法の工程を示す図であ
る。 ……広幅の型枠パネル、……鋼製型枠、
……端太材、……細幅の型枠パネル、……ア
ングル材、……ヒンヂプレート、……長孔、
……ヒンヂボルト、……タイボルト、……
ハンガー取付金具、……ローラ、……ハンガ
ー、……吊り金具、……大組柱型枠、……
梁側型枠、……ハンガーレール、……梁底型
枠、17a……L形鋼製型枠、18……枕、…
…コーナーアングル、……柱鉄筋、……キツ
カー、B……躯体構造物、F……リフテイングフ
レーム、W……吊り索。
Fig. 1 is a perspective view of the large-assembly column formwork used in the construction method of the present invention, Fig. 2 is a plan view thereof, and Figures 3 a to 3 d are diagrams showing the steps of the large-assembly column formwork method of the present invention. It is. ...wide formwork panels, ...steel formwork,
... end timber, ... narrow formwork panel, ... angle material, ... hinge plate, ... long hole,
... Hinge bolt, ... Tie bolt, ...
Hanger mounting bracket,...Roller,...Hanger,...Hanging bracket,...Large column formwork,...
Beam side formwork,...hanger rail,...beam bottom formwork, 17a...L-shaped steel formwork, 18...pillow,...
...Corner angle, ...Column reinforcing bar, ...Kitsuka, B...Main structure, F...Lifting frame, W...Hanging rope.

Claims (1)

【特許請求の範囲】 1 大組スラブ型枠の左右両端に進退可能に支持
せる梁側型枠の下端に結合され且つ下端外側に設
けたハンガーレールに、上端にローラを有する伸
縮自在なハンガーにて走行可能に吊垂され、その
走行方向の二側面の型枠パネルが開閉可能になさ
れた各大組柱型枠内に、1階分の躯体コンクリー
トの1回の打設によりコンクリート柱を築造後、
各大組柱型枠を脱型する工程と、 各大組柱型枠の走行方向の二側面の型枠パネル
を直角に開き、該各大組柱型枠をハンガーにてハ
ンガーレール上を走行させて順次躯体構造物の開
口部側に移動する工程と、 躯体構造物の開口部に移動した大組柱型枠をリ
フテイングフレームにて吊り、ハンガーを取外し
て大組柱型枠の一側が躯体構造物の外方にはみ出
るまで引き出す工程と、 一側が躯体構造物の外方にはみ出るまで引き出
した後、開かれた一側面の開かれた型枠パネルを
閉じて大組柱型枠全体を躯体構造物の外方に引き
出して2階に吊り上げ、所定位置に配筋された鉄
筋を内側に挾むように吊り降ろした後他側面の開
かれた型枠パネルを閉じてセツトする工程と、 この大組柱型枠を後からセツトされる大組スラ
ブ・梁型枠の左右両端に進退可能に支持された梁
側型枠の下端に結合し且つ下端外側にハンガーレ
ールに上端にローラを有する伸縮自在なハンガー
にて走行可能に吊垂する工程 の諸工程を繰り返し行つて所要階数の躯体構造物
のコンクリート柱を築造することを特徴とする建
築物の大組柱型枠工法。
[Scope of Claims] 1. An extendable hanger having rollers at the upper end of the hanger rail connected to the lower end of the beam-side formwork and provided outside the lower end, which is movably supported at both left and right ends of the large slab formwork. Concrete columns are constructed by pouring one-story frame concrete in one time within each large column column formwork, which is suspended so that it can be moved around, and the formwork panels on the two sides in the direction of travel can be opened and closed. rear,
The process of demolding each large-assembly column formwork, and opening the formwork panels on two sides of each large-assembly column formwork at right angles in the running direction, and running each large-assembly column formwork on a hanger rail with a hanger. The large column formwork that has been moved to the opening of the frame structure is lifted by a lifting frame, the hanger is removed, and one side of the large column column formwork is moved to the opening side of the frame structure. The process of pulling out the frame structure until it protrudes outside the frame structure, and after pulling it out until one side protrudes outside the frame structure, the open formwork panel on one side is closed and the entire large column formwork is removed. The process of pulling out the outside of the frame structure, lifting it to the second floor, lowering it so as to sandwich the reinforcing bars placed in the predetermined positions inside, and then closing and setting the open formwork panel on the other side. The assembled column formwork is connected to the lower end of the beam side formwork which is supported on both the left and right ends of the large slab/beam formwork to be set later so that it can move back and forth, and is telescopic with a hanger rail on the outside of the lower end and rollers on the upper end. A construction method for building large column columns, which is characterized by constructing concrete columns of a frame structure having a required number of floors by repeating various steps of suspending them so that they can be moved using hangers.
JP16927183A 1983-09-16 1983-09-16 Large pillar mold frame construction method of building Granted JPS6062366A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16927183A JPS6062366A (en) 1983-09-16 1983-09-16 Large pillar mold frame construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16927183A JPS6062366A (en) 1983-09-16 1983-09-16 Large pillar mold frame construction method of building

Publications (2)

Publication Number Publication Date
JPS6062366A JPS6062366A (en) 1985-04-10
JPS6358993B2 true JPS6358993B2 (en) 1988-11-17

Family

ID=15883409

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16927183A Granted JPS6062366A (en) 1983-09-16 1983-09-16 Large pillar mold frame construction method of building

Country Status (1)

Country Link
JP (1) JPS6062366A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5925470B2 (en) * 2011-03-29 2016-05-25 友二 山田 Form lifting tool

Also Published As

Publication number Publication date
JPS6062366A (en) 1985-04-10

Similar Documents

Publication Publication Date Title
US5491948A (en) Tilt-up concrete pad and method of forming and erecting the tilt-up concrete pad
CA2038524C (en) Form and method of constructing a wall from pourable concrete material
CN103882977B (en) The frame structure and its method of construction assembled based on three sides with groove bar shaped Prefabricated Concrete wallboard
WO2016062224A1 (en) Integrated column-equipped heat insulation wallboard, manufacturing and building processes and corollary equipment thereof
CN109083272A (en) A kind of assembled architecture frame structure and its construction method
US3728838A (en) Method for making cast-in-place concrete structures
US6032424A (en) Block system
US7219474B2 (en) Load bearing building panel
CN103882976B (en) The Frame _ Shear Wall Structure and its method of construction assembled based on three sides with groove bar shaped Prefabricated Concrete wallboard
JPH0693726A (en) Method for constructing staircase and stair hall and staircase member
JPS5953428B2 (en) concrete shapes
US4180233A (en) Building construction system
US4228625A (en) Construction system
CN113152728A (en) Wallboard and floor exempt from to fall to ground supporting template system
JPS6358993B2 (en)
CN216552527U (en) Heat preservation and decoration integrated module wall and house based on heat preservation and decoration integrated module wall
JPS6358992B2 (en)
JPH0256450B2 (en)
US3611533A (en) Method of making prefabricated building unit
CN201198612Y (en) Lightweight and energy-saving large modular modular exterior wall
US3451108A (en) Movable concrete form with a pair of endless flexible mats
JPS6339316Y2 (en)
AU647783B2 (en) Improved building techniques
CN213539711U (en) Reverse ridge template fixing system
NL8201173A (en) Building construction method - using movable formworks removed for pouring next unit after pouring and hardening