Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS6361480B2 - - Google Patents
[go: Go Back, main page]

JPS6361480B2 - - Google Patents

Info

Publication number
JPS6361480B2
JPS6361480B2 JP57088873A JP8887382A JPS6361480B2 JP S6361480 B2 JPS6361480 B2 JP S6361480B2 JP 57088873 A JP57088873 A JP 57088873A JP 8887382 A JP8887382 A JP 8887382A JP S6361480 B2 JPS6361480 B2 JP S6361480B2
Authority
JP
Japan
Prior art keywords
water stop
stop sheet
shield
wall surface
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP57088873A
Other languages
Japanese (ja)
Other versions
JPS58207498A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP57088873A priority Critical patent/JPS58207498A/en
Publication of JPS58207498A publication Critical patent/JPS58207498A/en
Publication of JPS6361480B2 publication Critical patent/JPS6361480B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 本発明は、シールド工法による区間と、
NATM工法による区間が連続して形成される地
中坑の構造に関するものである。
[Detailed description of the invention] The present invention provides a section using a shield method,
This relates to the structure of an underground mine where sections are formed continuously using the NATM construction method.

都市の電線・電話線等を土中に敷設するのに、
数10mの深さに横坑をシールド工法により掘削
し、これを共同坑として用いる方法がとられてい
る。この場合、横坑と縦坑との間をNATM工
法、すなわちロツクボルト工法による斜坑で結ぶ
ようにすれば、縦坑をそれほど深く堀り下げる必
要がない等、費用などの点で有利となる。
For laying urban electric wires, telephone lines, etc. underground,
The method is to excavate a horizontal shaft several tens of meters deep using the shield method and use it as a communal shaft. In this case, if the horizontal shaft and vertical shaft are connected by an inclined shaft using the NATM construction method, that is, the rock bolt construction method, it is advantageous in terms of cost, as there is no need to dig the vertical shaft so deeply.

また、曲り部分を有する地中坑を施工する場合
には、シールド工法のみで形成することが困難で
あることから、直線部分をシールド工法で形成
し、そのシールド工法で作られた区間どうしを
NATM工法により接続した構造とするのが一般
的である。
In addition, when constructing an underground shaft with curved sections, it is difficult to form it using only the shield method, so the straight sections are formed using the shield method, and the sections created using the shield method are connected to each other.
The structure is generally connected using the NATM construction method.

ところが、シールド工法による区間とNATM
工法による区間とを連続して形成すると、その工
法の違いから接続部の止水構造が異なるため、
NATM工法区間に施工されている止水シートの
裏面における湧水が、両区間の接続部から二次覆
工側へ廻り、漏水事故を招き易いという問題点が
あつた。
However, sections using the shield method and NATM
If sections are constructed using different construction methods, the water stop structure at the connection will differ due to the difference in construction methods.
There was a problem in that spring water on the back side of the water stop sheet installed in the NATM construction method section would flow from the connection between the two sections to the secondary lining side, easily causing a water leakage accident.

本発明は、以上のような点に鑑みて成されたも
のであり、シールド工法区間とNATM工法区間
との取合い部すなわち接続部において、止水シー
トの裏面における湧水が二次覆工側に廻るおそれ
のない地中坑の構造を、経費のかからない簡単な
作業で実現することを目的とするものである。
The present invention has been made in view of the above-mentioned points, and at the junction between the shield construction method section and the NATM construction method section, the spring water on the back side of the water stop sheet flows to the secondary lining side. The purpose of this project is to create an underground shaft structure that does not have the risk of rotation, using simple and inexpensive work.

すなわち本発明は、シールド工法による区間
と、NATM工法による区間とが連続して形成さ
れる地中坑の構造において、上記NATM工法に
よる区間に取り付けられる止水シートの端が、上
記シールド工法による区間におけるシールド機外
殻の内空部に延長され、この止水シートの端とシ
ールド機外殻の内壁面とが気密に接合されている
ことを特徴とするものである。
That is, the present invention provides an underground shaft structure in which a section formed by the shield method and a section formed by the NATM method are formed in succession, and the end of the waterstop sheet attached to the section formed by the NATM method is connected to the section formed by the shield method. The water stop sheet extends into the inner cavity of the outer shell of the shield machine, and the end of the water stop sheet is airtightly joined to the inner wall surface of the outer shell of the shield machine.

次に本考案にかかる地中坑の構造の第1の実施
例を図面の第1図乃至第3図について説明する。
Next, a first embodiment of the structure of an underground shaft according to the present invention will be described with reference to FIGS. 1 to 3 of the drawings.

図中1は縦坑であり、2は他の縦坑(図示せ
ず)との間を連通接続するシールド工法による横
坑であつて、この横坑2と上記縦坑1との間は
NATM工法による斜坑3により接続されてい
る。上記横坑2はシールド機外殻4及びこのシー
ルド機外殻4に続くシールドセグメント40によ
り一次覆工が成されており、また、上記斜坑3
は、吹付コンクリート層5とロツクボルト6とに
よるNATM(ニユー・オーストリアン・トンネ
リング・メリツト)工法により一次覆工が成され
ている。さらに上記吹付コンクリート層5の内壁
面には全周に塩化ビニール樹脂又はエチレン酢酸
ビニル樹脂等による止水シート7が貼着されてお
り、図中二点鎖線で示した箇所はシート間が不
連続となるため、第2図に示すようにオーバーラ
ツプシート8が用いられている。すなわち、上記
止水シート7の突き合せ部7a,7aは、コンク
リート釘9により吹付コンクリート層5の内壁面
に固定され、そのコンクリート釘9を含む止水シ
ート7の突き合せ部7a,7aがオーバーラツプ
シート8により覆われた状態で、該オーバーラツ
プシート8の両端縁が止水シート7に溶接接続さ
れている。
In the figure, 1 is a vertical shaft, and 2 is a horizontal shaft using the shield construction method that communicates and connects with another vertical shaft (not shown).
They are connected by diagonal shaft 3 using the NATM construction method. The horizontal shaft 2 is primarily lined with a shield machine outer shell 4 and a shield segment 40 following the shield machine outer shell 4, and the above-mentioned inclined shaft 3
The primary lining was performed using the NATM (New Austrian Tunneling Merit) construction method using a shotcrete layer 5 and lock bolts 6. Furthermore, a water stop sheet 7 made of vinyl chloride resin, ethylene vinyl acetate resin, etc. is adhered to the inner wall surface of the shotcrete layer 5 all around, and the sheets are discontinuous at the locations indicated by chain double-dashed lines in the figure. Therefore, an overlap sheet 8 is used as shown in FIG. That is, the abutted portions 7a, 7a of the water stop sheet 7 are fixed to the inner wall surface of the shotcrete layer 5 by concrete nails 9, and the abutted portions 7a, 7a of the water stop sheet 7 including the concrete nails 9 are overlaid. While covered by the overlap sheet 8, both ends of the overlap sheet 8 are welded to the water stop sheet 7.

一方、前記シールド工法による横坑2とナトム
工法による斜坑3との取合い部、すなわち接続部
10は、斜坑3の止水シート7の端7bが横坑2
のシールド機外殻4内に延長された構造とされて
おり、上記止水シート7の端7bとシールド機外
殻4の内壁面4aとが気密に接合されている。第
3図は第1図の二点鎖線で示した箇所、すなわ
ち上記止水シート7の端7bとシールド機外殻4
の内壁面との接合部を示しており、この実施例で
シールド機外殻4の内壁面4aに固着される接続
プレート11と、該接続プレート11と止水シー
ト7の端7bとを固定する固定ボルト12と、こ
のボルト固定部における接続プレート11と止水
シート7の端7bとの間に密着状に介在されるゴ
ム等のパツキング材13とにより、止水シート7
の端7bとシールド機外殻4の内壁面4aとの接
合が成されている。詳細には、上記接続プレート
11は断面略S字状の型材が用いられており、そ
の一部の平坦部11aがシールド機外殻4の内壁
面4aに溶接等により固着され、内壁面4aより
ブリツジ状に浮いた平坦部11bに前記ボルト1
2が通挿されている。しかして前記斜坑3から上
記内壁面4aに沿つて延長された止水シート7
は、さらに接続プレート11に沿つて上記ボルト
固定部に至り、ここで止水シート7の端7bと接
続プレート11とがパツキング材13を挾んでボ
ルト12止めされている。
On the other hand, in the connection part 10 between the horizontal shaft 2 formed by the shield construction method and the slope shaft 3 formed by the Natom construction method, the end 7b of the water stop sheet 7 of the slope shaft 3 is connected to the horizontal shaft 2.
The end 7b of the water stop sheet 7 and the inner wall surface 4a of the shield machine outer shell 4 are hermetically joined. FIG. 3 shows the locations indicated by the two-dot chain line in FIG.
In this embodiment, the connection plate 11 is fixed to the inner wall surface 4a of the shield machine outer shell 4, and the connection plate 11 and the end 7b of the water stop sheet 7 are fixed. The water stop sheet 7 is fixed by the fixing bolt 12 and the packing material 13 such as rubber, which is tightly interposed between the connection plate 11 and the end 7b of the water stop sheet 7 at the bolt fixing part.
The end 7b is joined to the inner wall surface 4a of the shield machine outer shell 4. In detail, the connecting plate 11 is a shaped member having a substantially S-shaped cross section, and a flat part 11a of the connecting plate 11 is fixed to the inner wall surface 4a of the shield machine outer shell 4 by welding or the like. The bolt 1 is attached to the flat part 11b floating like a bridge.
2 is inserted. Thus, the water stop sheet 7 extends from the inclined shaft 3 along the inner wall surface 4a.
further extends along the connecting plate 11 to the bolt fixing portion, where the end 7b of the water stop sheet 7 and the connecting plate 11 are secured with bolts 12 with packing material 13 in between.

上述したシールド機外殻4の内壁面4a全周と
止水シート7の内面全周には、連続して図中一点
鎖線で示すように二次覆工コンクリート層14が
形成されている。
A secondary lining concrete layer 14 is continuously formed on the entire circumference of the inner wall surface 4a of the shield machine outer shell 4 and the inner circumference of the water stop sheet 7, as shown by the dashed line in the figure.

以上の構成による地中坑は、一次覆工の段階
で、横坑2と斜坑3との接続部10における止水
が成されているので、止水シート7の裏面の湧水
が二次覆工側に廻るおそれがないものとなつてい
る。しかも止水シート7の端7aをシールド機外
殻4内に若干延長させて接合させるという簡単な
作業で施工できるため経費も少なくて済み、かつ
二次覆工による内壁面に影響を与えないので、内
壁面が連続した品質の良い地中坑を得ることがで
きる。
In the underground shaft with the above configuration, water is cut off at the connecting part 10 between the side shaft 2 and the inclined shaft 3 at the stage of primary lining, so spring water on the back side of the water stop sheet 7 is prevented from flowing through the secondary lining. There is no risk of it being transferred to the engineering side. Moreover, the construction can be done by simply extending the end 7a of the water-stop sheet 7 into the shield machine outer shell 4 and joining it, so the cost is low, and the inner wall surface is not affected by the secondary lining. , it is possible to obtain a high-quality underground shaft with a continuous inner wall surface.

次に本発明に係る地中坑の構造の第2,第3の
実施例を第4図、第5図について説明する。な
お、この第2,第3の実施例は、止水シート7の
端7bとシールド機外殻4の内壁面との接合部の
構造のみが上述した第1の実施例と異なり、他は
同等であるので同等の部分の説明は省略する。
Next, second and third embodiments of the structure of an underground shaft according to the present invention will be described with reference to FIGS. 4 and 5. The second and third embodiments differ from the first embodiment described above only in the structure of the joint between the end 7b of the water stop sheet 7 and the inner wall surface of the shield machine outer shell 4, and are otherwise the same. Therefore, explanation of the equivalent parts will be omitted.

第4図に示す第2の実施例は、前記止水シート
7の端7bとシールド機外殻4の内壁面4aとの
接合部に接続用フラツトシート21が取り付けら
れており、このフラツトシート21は塩化ビニー
ル等の熱可塑性樹脂シートが用いられている。上
記フラツトシート21は、その一端縁が止水シー
ト7の端7bと重合されて溶着されており、他端
縁がシールド機外殻4の内壁面4aに熱溶融型接
着剤22により気密に接着されている。
In the second embodiment shown in FIG. 4, a connection flat sheet 21 is attached to the joint between the end 7b of the water stop sheet 7 and the inner wall surface 4a of the shield machine outer shell 4, and this flat sheet 21 is A thermoplastic resin sheet such as vinyl is used. One edge of the flat sheet 21 is overlapped and welded to the edge 7b of the water stop sheet 7, and the other edge is hermetically bonded to the inner wall surface 4a of the shield machine outer shell 4 with a hot-melt adhesive 22. ing.

第5図に示す第3の実施例は、シールド機外殻
4の内壁面4bに金網31が溶接されて張設さ
れ、この金網31にコンクリートが吹き付けられ
てなる吹付コンクリート層32が形成されてお
り、該吹付コンクリート層32の内壁面32aに
前記止水シート7の端7bが固定されている。こ
の止水シート7の端7bの固定は、上記吹付コン
クリート層32の内壁面32aと止水シート7の
端7bとの間に介在されるゴム等のパツキング材
33と、このパツキング材33と対向する止水シ
ート7の端7bの背面に取り付けられる押え金具
34と、この押え金具34と上記止水シート7の
端7b及びパツキング材33を貫通して上記吹付
コンクリート層32に打ち込まれるコンクリート
釘35により成されている。
In the third embodiment shown in FIG. 5, a wire mesh 31 is welded and stretched on the inner wall surface 4b of the shield machine outer shell 4, and a shotcrete layer 32 is formed by spraying concrete onto the wire mesh 31. The end 7b of the water stop sheet 7 is fixed to the inner wall surface 32a of the shotcrete layer 32. The end 7b of the waterstop sheet 7 is fixed by a packing material 33 such as rubber interposed between the inner wall surface 32a of the shotcrete layer 32 and the end 7b of the waterstop sheet 7, A presser metal fitting 34 is attached to the back side of the end 7b of the waterstop sheet 7, and a concrete nail 35 is driven into the shotcrete layer 32 through the presser metal fitting 34, the end 7b of the waterstop sheet 7, and the packing material 33. It is made by

以上説明したように本発明によれば、NATM
工法区間に施設される止水シートの端を、シール
ド機外殻における内空部に延長させ、その止水シ
ートの端とシールド機外殻の内壁面とを気密に接
合させた構造としたので、一次覆工の段階でシー
ルド工法区間とNATM工法区間との接続部にお
ける止水が成され、止水シートの裏面の湧水が二
次覆工側に廻るおそれがない効果がある。しか
も、止水シートの端をシールド機外殻内に若干延
長させて接合させるという簡単な作業で施工でき
るため経費も少なくて済む効果があり、かつ二次
覆工による内壁面に影響を与えないので、内壁面
が滑らかに連続した品質の良い地中坑を得ること
ができる効果がある。
As explained above, according to the present invention, NATM
The end of the water stop sheet installed in the construction method section is extended into the inner cavity of the shield machine outer shell, and the end of the water stop sheet is airtightly joined to the inner wall surface of the shield machine outer shell. Water is stopped at the connection between the shield method section and the NATM method section during the primary lining stage, and there is no risk that spring water on the back side of the water stop sheet will flow to the secondary lining side. Moreover, it can be constructed by simply extending the end of the water-stop sheet into the shield machine's outer shell and joining it, which reduces costs and does not affect the inner wall surface due to the secondary lining. Therefore, it is possible to obtain a high-quality underground shaft with a smooth and continuous inner wall surface.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係る地中坑の第1の実施例を
示す断面図、第2図は第1図の二点鎖線に示し
た箇所の断面図、第3図は第1図の二点鎖線に
示した箇所の断面図、第4図は第3図の箇所にお
ける第2の実施例を示す断面図、第5図は同第3
の実施例を示す断面図である。 2……シールド工法区間としての横坑、3……
NATM工法区間としての斜坑、4……シールド
機外殻、4a……シールド機外殻の内壁面、7…
…止水シート、7b……止水シートの端。
FIG. 1 is a sectional view showing a first embodiment of an underground shaft according to the present invention, FIG. 4 is a sectional view showing the second embodiment at the location shown in FIG. 3, and FIG.
FIG. 2... Horizontal shaft as a shield method section, 3...
Diagonal shaft as NATM construction method section, 4... Shield machine outer shell, 4a... Inner wall surface of shield machine outer shell, 7...
...Water stop sheet, 7b...End of water stop sheet.

Claims (1)

【特許請求の範囲】[Claims] 1 シールド工法による区間と、NATM工法に
よる区間とが連続して形成される地中坑の構造に
おいて、上記NATM工法による区間に取り付け
られる止水シートの端が、上記シールド工法によ
る区間におけるシールド機外殻の内空部に延長さ
れ、この止水シートの端とシールド機外殻の内壁
面とが気密に接合されていることを特徴とする地
中坑の構造。
1 In the structure of an underground mine where a section using the shield method and a section using the NATM method are formed in succession, the edge of the waterstop sheet attached to the section using the NATM method is outside the shield machine in the section using the above shield method. An underground mine structure characterized in that the water stop sheet extends into the inner cavity of the shell and the end of this water stop sheet is airtightly joined to the inner wall surface of the outer shell of the shield machine.
JP57088873A 1982-05-27 1982-05-27 Structure of underground pile Granted JPS58207498A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57088873A JPS58207498A (en) 1982-05-27 1982-05-27 Structure of underground pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57088873A JPS58207498A (en) 1982-05-27 1982-05-27 Structure of underground pile

Publications (2)

Publication Number Publication Date
JPS58207498A JPS58207498A (en) 1983-12-02
JPS6361480B2 true JPS6361480B2 (en) 1988-11-29

Family

ID=13955122

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57088873A Granted JPS58207498A (en) 1982-05-27 1982-05-27 Structure of underground pile

Country Status (1)

Country Link
JP (1) JPS58207498A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0295324A (en) * 1988-09-30 1990-04-06 Toto Ltd Bathtub with human body detector

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63130598U (en) * 1987-02-19 1988-08-26

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0295324A (en) * 1988-09-30 1990-04-06 Toto Ltd Bathtub with human body detector

Also Published As

Publication number Publication date
JPS58207498A (en) 1983-12-02

Similar Documents

Publication Publication Date Title
US20040208704A1 (en) Manhole structure constructing method, manhole structure water-stop flexible joint and manhole structure
JP3597789B2 (en) Manhole structure, watertight flexible joint for manhole structure and method of construction of manhole structure
JP2003148091A (en) Reinforcement structure of existing tunnel lining and its construction method
JP3893848B2 (en) Synthetic segment
JPS6361480B2 (en)
JP3628411B2 (en) segment
JPH07252995A (en) Tunnel timbering of method of tubbing construction
JPS62182398A (en) Shielded tunnel
CN215408680U (en) A water blocking support device for open TBM tunnel construction
JP2000145394A (en) Plastic sheet-adhered segment and its joint processing method
JPH0310238Y2 (en)
JP4153636B2 (en) Vertical tunnel wellhead stop device
JP3298100B2 (en) Waterproof segment for shield tunnel and its construction method
JPH0540157Y2 (en)
JP2698924B2 (en) Construction method of anticorrosion pipeline
JP2727307B2 (en) Joints for repairing joints of underground structures and methods of construction
JPH028000Y2 (en)
JPH0423997Y2 (en)
JPS6317911Y2 (en)
JP3230174B2 (en) Tunnel waterproofing method and waterproof sheet
JPH0713438B2 (en) Seal structure of segment corner and its construction method
JPH0220317Y2 (en)
JPS6160239B2 (en)
JPS6160959B2 (en)
JPH0460200B2 (en)