Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0123630B2 - - Google Patents
[go: Go Back, main page]

JPH0123630B2 - - Google Patents

Info

Publication number
JPH0123630B2
JPH0123630B2 JP3270384A JP3270384A JPH0123630B2 JP H0123630 B2 JPH0123630 B2 JP H0123630B2 JP 3270384 A JP3270384 A JP 3270384A JP 3270384 A JP3270384 A JP 3270384A JP H0123630 B2 JPH0123630 B2 JP H0123630B2
Authority
JP
Japan
Prior art keywords
plate
tank
inner tank
roof
outer tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3270384A
Other languages
Japanese (ja)
Other versions
JPS60181467A (en
Inventor
Shigeru Moritsugu
Shinji Suga
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Motors Ltd
Original Assignee
Kawasaki Jukogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Jukogyo KK filed Critical Kawasaki Jukogyo KK
Priority to JP3270384A priority Critical patent/JPS60181467A/en
Publication of JPS60181467A publication Critical patent/JPS60181467A/en
Publication of JPH0123630B2 publication Critical patent/JPH0123630B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Description

【発明の詳細な説明】 技術分野 この発明は、夫々底板、側板及び屋根を有する
内槽と外槽とを所定の間隔で重ね合せて構成され
た二重殻円筒形タンクの施工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION Technical Field The present invention relates to a method for constructing a double-shelled cylindrical tank constructed by stacking an inner tank and an outer tank at a predetermined interval, each having a bottom plate, a side plate, and a roof.

従来技術 二重殻円筒形タンクの一般的な構造は第1図に
示す如く、外槽底板1、外槽側板2、外槽屋根7
を有して成る外槽と、内槽底板16、内槽側板1
4、内槽屋根5を有して成る内槽とを互いに所定
の間隔を隔てゝ重ね合せて構成される。内槽底板
16は外槽底板1上に敷設された底部保冷層15
上に載置されるが、内槽側板14の下端部と接合
されるその周辺部は、満槽、空槽の組返しにより
繰返し応力が集中するので、疲労に耐えるように
他の部分より板厚を増している。この部分をアニ
ユラープレート4と云う。アニユラープレート4
には貯蔵液の液圧の他内槽側板14及び内槽屋根
5の重量が掛るのでその下の部分の環状の底部保
冷層3は他の部分より強度が大きくされている。
又、内槽側板14の上端と、内槽屋根5の周辺部
とは曲面を有するナツクルプレート6を介して接
続されている。内槽側板14と外槽側板2との間
及び内槽屋根5と外槽屋根7との間には保冷材を
入れて、保冷層を形成する。
Prior Art The general structure of a double shell cylindrical tank is as shown in Fig. 1, which includes an outer tank bottom plate 1, an outer tank side plate 2, and an outer tank roof 7.
an outer tank, an inner tank bottom plate 16, and an inner tank side plate 1.
4. An inner tank having an inner tank roof 5 is stacked on top of each other at a predetermined distance. The inner tank bottom plate 16 is a bottom cold insulation layer 15 laid on the outer tank bottom plate 1.
Although the inner tank side plate 14 is placed on top of the tank, the surrounding area that is joined to the lower end of the inner tank side plate 14 is subject to repeated stress concentration due to the repeated filling and emptying of the tank. It's getting thicker. This part is called an annular plate 4. Annular plate 4
Since the liquid pressure of the stored liquid and the weight of the inner tank side plate 14 and the inner tank roof 5 are applied to the tank, the annular bottom cold insulating layer 3 below the inner tank side plate 14 is made stronger than the other parts.
Further, the upper end of the inner tank side plate 14 and the peripheral part of the inner tank roof 5 are connected via a knuckle plate 6 having a curved surface. A cold insulation material is inserted between the inner tank side plate 14 and the outer tank side plate 2 and between the inner tank roof 5 and the outer tank roof 7 to form a cold insulation layer.

このような構成の二重殻円筒型低温タンクの従
来の一般的な建造方法を述べると、第2図に示す
如く、先づ外槽底板1と外槽側板2とを組立て、
次いで上記底板1上に環状底部保冷層3及び内槽
底板のアニユラープレート4を施工し、更に内槽
屋根5及びナツクルプレート6を底板上で組立
て、その上に所要の間隔を存して外槽屋根7を一
体的に組立て、かくして地上組立の完了した内外
槽屋根5,7を外槽側板2に沿つて所定の位置迄
上昇させ、その後、内槽側板14、底部保冷層1
5を施工し、その上に内槽底板16を組立てる。
上記の内外槽屋根5,7を上昇させる手段として
は、第2図に示す如く、ブロワー11によりタン
ク内に圧縮空気を送り込んで空気圧を屋根7の下
面に作用させて屋根7,5を浮上させるエアレイ
ジング法や機械的又は液圧によるジヤツキアツプ
工法が使用される。
To describe the conventional general construction method of a double shell cylindrical cryogenic tank having such a configuration, as shown in FIG. 2, first, the outer tank bottom plate 1 and the outer tank side plate 2 are assembled,
Next, an annular bottom cold insulating layer 3 and an annular plate 4 for the inner tank bottom plate are constructed on the bottom plate 1, and an inner tank roof 5 and a knuckle plate 6 are then assembled on the bottom plate, leaving a required gap thereon. The outer tank roof 7 is assembled integrally, and the inner and outer tank roofs 5 and 7, which have been assembled above ground, are raised to a predetermined position along the outer tank side plate 2, and then the inner tank side plate 14 and the bottom cold insulation layer 1 are assembled.
5 and assemble the inner tank bottom plate 16 thereon.
As shown in FIG. 2, the means for raising the inner and outer tank roofs 5, 7 is as follows: compressed air is sent into the tank by a blower 11, and air pressure is applied to the lower surface of the roof 7 to raise the roofs 7, 5. Air razing methods and mechanical or hydraulic jack up methods are used.

次いで、組立済みの外槽屋根7を利用して、ト
ロリホイスト13(第3図e参照)等の小型運搬
器を配設して、内槽側板14の組立を行ない、そ
の後、内外槽屋根を連結する吊下げ装置9を伸ば
して、側板14上にナツクルプレート6及び屋根
5を降下せしめ肌合せ後、溶接固定により組立て
る。
Next, using the assembled outer tank roof 7, a small carrier such as a trolley hoist 13 (see Figure 3 e) is installed, and the inner tank side plates 14 are assembled, and then the inner and outer tank roofs are assembled. The connecting hanging device 9 is extended, the knuckle plate 6 and the roof 5 are lowered onto the side plate 14, and after the skins are aligned, they are assembled by welding and fixing.

上記の従来工法は、長い工期を要する内槽側板
14の組立てを外槽屋根の下で施工することがで
き、風雨や雪等の気象条件に左右されないため、
品質、工程管理上有利である点及び外槽屋根組立
完了後は、タンク周囲に回らせた防液堤内は、一
部を除き舗装等の土木工事の施工が可能となるた
め、土木工事が比較的早期に開始できる点で利点
があつた。
With the above conventional construction method, the inner tank side plate 14, which requires a long construction period, can be assembled under the outer tank roof, and is not affected by weather conditions such as wind, rain, snow, etc.
It is advantageous in terms of quality and process control, and after completing the assembly of the outer tank roof, civil engineering work such as paving can be carried out inside the dike surrounding the tank, with some exceptions. The advantage was that it could be started as early as possible.

しかしながら、最近の社会的要求から、LNG、
LPG等低温液体を大量貯蔵する上記型式の低温
二重殻式タンクに関する安全性向上の立場から、
防液堤の強度の向上、防液堤及び堤内舗装、防液
堤内面の断熱材施工等の土木関係作業量が増大し
ており、上記の従来のタンク建造工法では、全体
の工程を土木作業期間の増加分だけ延ばす必要を
生ずることになる。
However, due to recent social demands, LNG,
From the standpoint of improving the safety of the above-mentioned type of low-temperature double-shell tanks that store large quantities of low-temperature liquids such as LPG,
The amount of civil engineering work is increasing, such as improving the strength of the dike, paving the dike and its interior, and installing insulation materials on the inside of the dike.The conventional tank construction method described above requires the entire process to be carried out by civil engineering work. This creates a need to extend the period by the amount of the increase.

目 的 本発明は、上記従来工法による平底円筒タンク
の施工方法における上述の問題点を除去した、早
期にタンク周囲の土木工事の開始が可能となり、
タンク建設工事の全体工程を短縮することが可能
となるのみならず、品質、作業性の向上にも寄与
する二重殻円筒形タンクの施工方法を提供するこ
とを目的とする。
Purpose The present invention eliminates the above-mentioned problems in the conventional method of constructing a flat-bottomed cylindrical tank, and enables early start of civil engineering work around the tank.
The purpose of the present invention is to provide a construction method for a double-shelled cylindrical tank that not only makes it possible to shorten the overall process of tank construction work, but also contributes to improving quality and workability.

構 成 上記目的に沿う本発明の施工方法は、二重殻円
筒形タンクの外槽底板の組立が完了した後、同底
板上で底部保冷層のアニユラー部、内槽アニユラ
ープレート、外槽側板最下段及び内槽屋根の組立
を開始し、溶接、検査に長期間を要する内槽屋根
の組立完成を待たずに、仮組後すぐに外槽屋根の
組立を開始するようにして、内槽屋根の屋根骨及
び屋根板の完成前に、外槽側板及び屋根の組立を
完了させ、この外槽屋根の下部に概ね所定の間隔
を存してナツクルプレートを吊下装置を介して固
定した後、外槽屋根をエアレイジング又はジヤツ
キアツプ等の持上げ手段により上昇させて外槽側
板上端部に固定し、次いで内槽側板、内槽屋根及
び内槽底板の組立を行ない、その後内槽側板頂部
にナツクルプレートを降下固定後、内槽屋根を持
上手段により上昇させて上記ナツクルプレートの
先端所定の位置に取付けるようにしたことを特徴
としている。
Structure According to the construction method of the present invention in accordance with the above object, after the assembly of the outer tank bottom plate of a double shell cylindrical tank is completed, the annular part of the bottom cold insulation layer, the inner tank annular plate, and the outer tank side plate are assembled on the same bottom plate. We started assembling the bottom tier and the inner tank roof, and started assembling the outer tank roof immediately after temporary assembly, without waiting for the completion of the inner tank roof assembly, which requires a long period of time for welding and inspection. Before the roof frames and roof plates were completed, the assembly of the outer tank side panels and roof was completed, and the knuckle plates were fixed to the lower part of the outer tank roof at approximately predetermined intervals via a hanging device. After that, the outer tank roof is raised by lifting means such as air raising or jack up and fixed to the upper end of the outer tank side plate, and then the inner tank side plate, inner tank roof and inner tank bottom plate are assembled, and then the top of the inner tank side plate is fixed to the upper end of the outer tank side plate. The present invention is characterized in that after the knuckle plate is lowered and fixed, the inner tank roof is raised by a lifting means and attached to the tip of the knuckle plate at a predetermined position.

以下、本発明を図面に示す実施例に基いて詳細
に説明する。
Hereinafter, the present invention will be explained in detail based on embodiments shown in the drawings.

第3図のa,b,c,d,e,f,gは本発明
による二重殻円筒タンクの施工方法の一実施例を
工程順に示す図である。
3a, b, c, d, e, f, and g are diagrams showing an embodiment of the method for constructing a double shell cylindrical tank according to the present invention in the order of steps.

予め敷地に打設した基礎上にa図に示す如く、
外槽底板1、外槽側板2の下部、アニユラー部底
部保冷層3及び内槽アニユラープレート4を組立
てる。
As shown in figure a, on the foundation that has been poured on the site in advance,
Assemble the outer tank bottom plate 1, the lower part of the outer tank side plate 2, the annular bottom cold insulation layer 3, and the inner tank annular plate 4.

次いで、b図に示す如く、内槽屋根5及びナツ
クルプレート6を図示せぬ組立架台上に載置した
後、内槽屋根5の仮組立を行ない、又、ナツクル
プレート6は溶接、検査を完了させる。
Next, as shown in Figure b, after placing the inner tank roof 5 and the knuckle plate 6 on an assembly frame (not shown), the inner tank roof 5 is temporarily assembled, and the knuckle plate 6 is welded and inspected. complete.

次いで、c図に示す如く、内槽屋根5上の架台
8上で外槽屋根7を組立て、一方、外槽側板2の
組立を完了後、d図に示す如く、ナツクルプレー
ト6を外槽屋根7にターンバツクル9a等の長さ
調整装置を有する吊下げ装置9で連結した状態
で、屋根気密シール10を外槽屋根7に取付け、
ブロワー11等で圧縮空気をタンク内に給送する
ことによりタンク内を昇圧させて外槽屋根7をエ
アレイジングにより外槽側板2の上端所定の位置
に固定する。なお、上記のナツクルプレート6、
内外槽屋根5,7は施工期間短縮のため、大ブロ
ツク化し、据付場所での現地溶接個所の低減を行
なうことが望ましい。又、ナツクルプレート6の
溶接、検査の完了を待たず、現地溶接による接手
の一部又は全部を仮組立が完了した状態として、
上述の屋根持上げ施工を行ない、その後溶接、検
査を行なうプロセスを採ることもできることは云
う迄もない。
Next, as shown in Figure c, the outer tank roof 7 is assembled on the frame 8 on the inner tank roof 5, and on the other hand, after completing the assembly of the outer tank side plates 2, the knuckle plate 6 is attached to the outer tank as shown in Figure d. Attach the roof airtight seal 10 to the outer tank roof 7 while connected to the roof 7 with a hanging device 9 having a length adjustment device such as a turnbuckle 9a,
By feeding compressed air into the tank using a blower 11 or the like, the pressure inside the tank is increased, and the outer tank roof 7 is fixed at a predetermined position at the upper end of the outer tank side plate 2 by air raising. In addition, the above-mentioned Knuckle Plate 6,
In order to shorten the construction period, it is desirable that the inner and outer tank roofs 5 and 7 be made into large blocks to reduce the number of on-site welding points at the installation site. In addition, without waiting for the completion of welding and inspection of the knuckle plate 6, some or all of the joints may be temporarily assembled by on-site welding,
It goes without saying that it is also possible to adopt the process of lifting the roof as described above and then performing welding and inspection.

上述の如く、外槽屋根が完了したら、外槽側板
の一部工事用開口17側の防液堤及び堤内敷地を
除き、タンク周囲の敷地を土木工事施工側に引渡
すことが可能になる。
As mentioned above, once the outer tank roof is completed, it becomes possible to hand over the site around the tank to the civil engineering construction side, except for the liquid dike and the site inside the dike on the side of the construction opening 17 of the outer tank side plate.

続いて、e図に示す如く、外槽屋根7に設けた
トロリホイスト13を利用して内槽屋根5、内槽
側板14、底部保冷層15の中央部を継続的に施
工し、内槽側板14の組立完了後、f図に示す如
く、外槽屋根7に連結したナツクルプレート6を
降下させ、内槽側板14と肌合せした後、溶接検
査を実施し、その後吊下げ装置9を撤去する。
又、内槽底板16の組立、溶接、検査を完了す
る。
Subsequently, as shown in Fig. e, the inner tank roof 5, the inner tank side plates 14, and the center part of the bottom cold insulation layer 15 are continuously constructed using the trolley hoist 13 provided on the outer tank roof 7, and the inner tank side plates After completing the assembly of 14, as shown in Fig. f, the knuckle plate 6 connected to the outer tank roof 7 is lowered, and after making skin contact with the inner tank side plate 14, a welding inspection is performed, and then the hanging device 9 is removed. do.
Also, the assembly, welding, and inspection of the inner tank bottom plate 16 are completed.

上記内槽側板14とナツクルプレート6との肌
合せ時には、ナツクル部のみの据付作業であり、
従来工法の如く、内槽屋根5を一体化したもので
ないため、据付施工が非常に容易になるばかりで
なく、ナツクルプレート6を仮付溶接して微調整
可能とすれば、内槽側板14とナツクルプレート
6との据付施工がさらに容易になる。更に、内槽
側板14の最上段の溶接、検査を完了させる前に
ナツクルプレート6と肌合せを行うことも考えら
れる。なお、この実施例では上述の如くナツクル
プレート6は、吊下げ装置のターンバツクル9a
で降下させるものとしたが、外槽側板2に仮設ジ
ヤツキを設置し、これにより降下させるようにす
ることも可能である。
When aligning the inner tank side plate 14 and the knuckle plate 6, only the knuckle portion is installed.
Since the inner tank roof 5 is not integrated as in the conventional construction method, not only is the installation very easy, but if the knuckle plate 6 is tack welded and fine adjustment is possible, the inner tank side plate 14 This further facilitates the installation of the Knuckle plate 6. Furthermore, it is also conceivable to perform surface alignment with the knuckle plate 6 before completing the welding and inspection of the uppermost layer of the inner tank side plate 14. In addition, in this embodiment, as described above, the knuckle plate 6 is connected to the turnbuckle 9a of the hanging device.
However, it is also possible to install a temporary jack on the outer tank side plate 2 and use this to lower the tank.

次にg図に示す如く、内槽屋根5を、エアレイ
ジング又はジヤツキアツプ等の持上げ手段により
持上げて、内槽側板14上部のナツクルプレート
6先端所定の位置に設置することによりタンクは
完成する。
Next, as shown in Fig. g, the inner tank roof 5 is lifted by lifting means such as air raising or jacking up, and the tank is completed by installing it at a predetermined position at the tip of the knuckle plate 6 on the upper part of the inner tank side plate 14.

効 果 以上の如く、本発明によれば、平底円筒タンク
の施工々程において、内槽屋根、ナツクルプレー
ト等のハンドリング困難な部材を早期にタンク内
で組立てを開始する一方、溶接、検査の終了を待
たず外槽側板、外槽屋根の完成を優先させ、又外
槽屋根にナツクルプレートを吊下げた状態で上方
に持上げておき、内槽側板を組立てた上に降下さ
せて据付け、その後内槽屋根を完成させる様にし
たことにより、タンク周囲の敷地が、従来の施工
法に比して数箇月程度早期に土木施工可能とな
り、又内槽アニユラープレート以外の内槽材の溶
接、検査を外槽屋根の据付後に施工することが可
能となり、風雨や雪等の気象条件にも左右され
ず、工程管理上優れた効果を奏する。
Effects As described above, according to the present invention, during the construction process of a flat-bottomed cylindrical tank, it is possible to start assembling difficult-to-handle parts such as the inner tank roof and the knuckle plate in the tank at an early stage, while also reducing welding and inspection. Prioritizing the completion of the outer tank side panels and the outer tank roof without waiting for the completion of the work, the Katsukuru plate was suspended from the outer tank roof and lifted upwards, and the inner tank side panels were assembled and then lowered and installed. By completing the inner tank roof afterwards, the site around the tank can be constructed several months earlier than with conventional construction methods, and welding of inner tank materials other than the inner tank annual plate is now possible. This makes it possible to carry out inspections after the installation of the outer tank roof, which is not affected by weather conditions such as wind, rain, or snow, and is highly effective in terms of process control.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は一般的な二重殻円筒形タンクの概略構
造を示す断面図、第2図はそのタンクの従来の施
工方法を説明する図式図、第3図a,b,c,
d,e,f,gは本発明の実施例の施工方法を工
程順に説明する図式図である。 1…外槽底板、2…外槽側板、3…アニユラー
部底部保冷層、4…アニユラープレート、5…内
槽屋根、6…ナツクルプレート、7…外槽屋根、
8…架台、10…シール部材、9…吊下装置、1
1…ブロワー(屋根持上手段)、14…内槽側板、
15…底部保冷層、16…内槽底板。
Figure 1 is a sectional view showing the schematic structure of a typical double-shelled cylindrical tank, Figure 2 is a schematic diagram explaining the conventional construction method for the tank, Figures 3 a, b, c,
d, e, f, and g are schematic diagrams illustrating the construction method of the embodiment of the present invention in the order of steps. 1... Outer tank bottom plate, 2... Outer tank side plate, 3... Annular part bottom cold insulation layer, 4... Annular plate, 5... Inner tank roof, 6... Knuckle plate, 7... Outer tank roof,
8... Frame, 10... Seal member, 9... Hanging device, 1
1...Blower (roof lifting means), 14...Inner tank side plate,
15...Bottom cold insulation layer, 16...Inner tank bottom plate.

Claims (1)

【特許請求の範囲】[Claims] 1 夫々底板、側板及び屋根を有する内槽と外槽
とが所定の間隔で重ね合せられて構成され、内槽
底板は外槽底板上に設けられた底部保冷層上に載
置され、内槽側板の下端部が接続される内槽底板
周辺部は内槽板の他の部分よりも増厚されたアニ
ユラープレートで形成され、該底板アニユラープ
レートは底部保冷層のアニユラー部上に載置さ
れ、内槽側板の頂部と内槽屋根周縁部とは曲面を
なすナツクルプレートにより接続されている二重
殻円筒形タンクの施工方法において、上記外槽底
板の組立が完了した後、同底板上において、底部
保冷層アニユラー部、内槽アニユラープレート、
外槽側板最下段及び内外槽屋根の組立を開始し、
内槽屋根の完成に先立つて外槽側板及び外槽屋根
の組立を完了させ、該外槽屋根の下部に概ね所定
の間隔を存してナツクルプレートを吊下装置を介
して固定した後、上記外槽屋根を持上手段により
上昇させて外槽側板上端部に固定し、次いで、内
槽側板、内槽屋根及び内槽底板の組立を行ない、
その後、内槽側板頂部にナツクルプレートを降
下、固定後、内槽屋根を持上手段により上昇させ
て、上記ナツクルプレートの先端所定の位置に取
付けるようにしたことを特徴とする二重殻円筒形
タンクの施工方法。
1. An inner tank and an outer tank each having a bottom plate, a side plate, and a roof are stacked one on top of the other at a predetermined interval, and the inner tank bottom plate is placed on a bottom cold insulation layer provided on the outer tank bottom plate, and the inner tank The peripheral part of the inner tank bottom plate to which the lower end of the side plate is connected is formed of an annular plate that is thicker than the other parts of the inner tank plate, and the bottom annular plate is placed on the annular part of the bottom cold insulation layer. In the construction method for a double-shell cylindrical tank in which the top of the inner tank side plate and the inner tank roof periphery are connected by a curved knuckle plate, after the assembly of the outer tank bottom plate is completed, the same bottom plate is On the top, the bottom cold insulation layer annular part, the inner tank annular plate,
Started assembling the bottom of the outer tank side panels and the inner and outer tank roofs.
Prior to completion of the inner tank roof, the assembly of the outer tank side plates and the outer tank roof is completed, and after fixing the knuckle plate to the lower part of the outer tank roof at approximately a predetermined interval via a hanging device, The outer tank roof is raised by a lifting means and fixed to the upper end of the outer tank side plate, and then the inner tank side plate, the inner tank roof, and the inner tank bottom plate are assembled,
Thereafter, after lowering and fixing the knuckle plate to the top of the inner tank side plate, the inner tank roof is raised by a lifting means, and the tip of the knuckle plate is attached to a predetermined position. Construction method of cylindrical tank.
JP3270384A 1984-02-24 1984-02-24 Construction of double shell cylindrical tank Granted JPS60181467A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3270384A JPS60181467A (en) 1984-02-24 1984-02-24 Construction of double shell cylindrical tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3270384A JPS60181467A (en) 1984-02-24 1984-02-24 Construction of double shell cylindrical tank

Publications (2)

Publication Number Publication Date
JPS60181467A JPS60181467A (en) 1985-09-17
JPH0123630B2 true JPH0123630B2 (en) 1989-05-08

Family

ID=12366205

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3270384A Granted JPS60181467A (en) 1984-02-24 1984-02-24 Construction of double shell cylindrical tank

Country Status (1)

Country Link
JP (1) JPS60181467A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6128678A (en) * 1984-07-19 1986-02-08 ト−ヨ−カネツ株式会社 How to assemble a double shell cylindrical tank

Also Published As

Publication number Publication date
JPS60181467A (en) 1985-09-17

Similar Documents

Publication Publication Date Title
JPH08232212A (en) Pier constructing method and execution method
US3106772A (en) Method of erecting buildings, tanks, domes or similar structures
CN110644667B (en) A prefabricated warehouse roof structure of a circular storage warehouse and an assembling method thereof
JPH0123630B2 (en)
US3974617A (en) Double shell tank construction method
JPS6092565A (en) Composite high cover
CN115450846A (en) A trough-type bamboo-shaped prefabricated concrete wind power tower and its construction method
CN116122579A (en) Hoisting method for bidirectional bending dome bracket
JP2001207689A (en) Relay type elevated construction method for steel towers and elevated guide mechanism
JP3888564B2 (en) Construction method of underground structure
JPS6026910B2 (en) Construction method of flat bottom cylindrical tank
JPH04161565A (en) Construction of large space building
BE1032782B1 (en) CONCRETE TANK FOR FERMENTATION WITH OPTIMIZED ROOF CONSTRUCTION, METHOD FOR MANUFACTURE AND USE OF SUCH A CONCRETE TANK FOR FERMENTATION
CN223951624U (en) A type of arch-supported large-volume concrete insulated shed for winter construction
JP2663102B2 (en) Long span canopy equipment and its construction method
JPS6355590B2 (en)
TW202332825A (en) Construction method of triple shell storage tank
US10662639B2 (en) Methods for erecting a wall panel proximate an outermost edge of a land parcel
JPS6337229B2 (en)
JPH10194377A (en) Method for construction of double shell tank
JP2751540B2 (en) Underground storage tank and construction method
CN119122178A (en) A curved roof construction method and a steel structure roof using the method
JPS61179964A (en) Temporarily constructed structure
JPS6226381B2 (en)
JPS5846992B2 (en) Welding assembly method of bottom plate in tank construction