JPH025843B2 - - Google Patents
Info
- Publication number
- JPH025843B2 JPH025843B2 JP14564984A JP14564984A JPH025843B2 JP H025843 B2 JPH025843 B2 JP H025843B2 JP 14564984 A JP14564984 A JP 14564984A JP 14564984 A JP14564984 A JP 14564984A JP H025843 B2 JPH025843 B2 JP H025843B2
- Authority
- JP
- Japan
- Prior art keywords
- road
- excavated
- existing road
- support beam
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000009415 formwork Methods 0.000 claims description 18
- 238000010276 construction Methods 0.000 claims description 13
- 230000003014 reinforcing effect Effects 0.000 claims description 9
- 238000000034 method Methods 0.000 claims description 6
- 239000004576 sand Substances 0.000 claims description 3
- 229910000831 Steel Inorganic materials 0.000 description 18
- 239000010959 steel Substances 0.000 description 18
- 239000000463 material Substances 0.000 description 7
- 230000000694 effects Effects 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 239000012779 reinforcing material Substances 0.000 description 2
- 239000011440 grout Substances 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Road Paving Structures (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は道路拡幅工法に関するものである。[Detailed description of the invention] [Industrial application field] This invention relates to a road widening method.
本件出願人は張り出し方式による拡幅道路とし
て特開昭57−71904号公報に記載された発明を開
示した。該発明は既設道路の拡幅側端部に打設し
た支持杭上に支承して既設道路の拡幅側端部より
一部を張り出して張り出し桁を載置し、張り出し
桁の山側端部は反力用アンカーによつて固定し、
該張り出し桁上に道路進行方向の縦桁を介して床
版を載置したものである。
The applicant disclosed an invention described in Japanese Patent Application Laid-open No. 71904/1983 as a road widening road using a projecting method. In this invention, an overhanging girder is supported on support piles driven at the end of the widening side of the existing road, and a part of the overhanging girder is placed overhanging the end of the widening side of the existing road. fixed with an anchor for
A floor slab is placed on the overhanging girder via a longitudinal girder in the direction of road travel.
該張り出し拡幅道路は施工に切土、埋土の手間
が要らないという効果が得られるとともに、支持
杭及びアンカーによつて安定した構造となるとい
う極めて大きな効果が得られるものである。 The projecting widening road has the advantage that it does not require the labor of cutting and filling soil during construction, and has the extremely large effect that it has a stable structure due to the support piles and anchors.
上記のような発明において問題となるのは、資
材等の運搬にあたつて道路状況が不備である場
合、床版等の巨大なものを現場に運び込むことが
極めて困難なことであつた。
A problem with the above-mentioned invention is that if the road conditions are inadequate for transporting materials, it is extremely difficult to transport huge objects such as floor slabs to the site.
このような問題点を解消するために現場にて型
枠を組んで道路を拡幅することが考えられるが、
型枠を既設道路から谷側へ張り出して組み立てる
ために深い谷側の地山に支保工を組むのは極めて
困難な作業である。 In order to solve these problems, it is possible to construct formwork on site and widen the road.
In order to assemble the formwork by extending it out from the existing road into the valley, it is an extremely difficult task to erect shoring into the ground on the deep valley side.
また新たに拡幅道路を構築した場合張り出し桁
と縦桁、及び床版の分だけ既設道路より高くな
り、既設道路及び既設構造物との高さを調整する
ための付帯工事が必要となるという問題が生ず
る。 Another problem is that when a newly widened road is constructed, it will be higher than the existing road by the overhanging girders, longitudinal girders, and floor slabs, and additional work will be required to adjust the height with the existing road and existing structures. occurs.
この出願にかかる一方の発明は、一部を既設道
路から張り出した支持梁の山側端部は反力アンカ
ーによつて固定し、谷側は支持杭によつて支持
し、既設道路から張り出した支持梁には型枠を吊
るし、隣接する支持梁間に鉄筋等を配設してコン
クリートを打設して路盤を構築し、I形鋼やH形
鋼等の運搬し易い支持梁を使用して型枠を吊る
し、張り出し部を構築することによつて上記の問
題点を解決するものである。
One of the inventions related to this application fixes the mountain side end of the support beam that partially overhangs the existing road with a reaction anchor, supports the valley side with a support pile, and supports the support beam that overhangs the existing road. Formwork is suspended from the beams, reinforcing bars are placed between adjacent support beams, concrete is poured, and a roadbed is constructed. The above problems are solved by hanging the frame and constructing an overhang.
またこの出願にかかる他方の発明は、既設道路
の谷側一部は道路進行方向に沿つて所定深さ掘削
し、山側には道路進行方向に対して直交する方向
に溝部を適宜間隔離して掘削し、該溝部内に支持
梁を載置し、既設道路との高低差を失くせしめる
ことによつて上記の問題点を解決するものであ
る。 The other invention of this application is to excavate a part of the valley side of an existing road to a predetermined depth along the direction of road travel, and excavate a groove on the mountain side in a direction perpendicular to the direction of road travel, separating the grooves at appropriate intervals. However, the above problem is solved by placing a support beam in the groove and eliminating the difference in height from the existing road.
以下図に示す一実施例に基づきこの発明を詳細
に説明する。
The present invention will be described in detail below based on an embodiment shown in the drawings.
(1) 既設道路の掘削
新設道路と既設道路の高低差を失くせしめる
ためには既設道路表面を所定深さ掘削すればよ
い。この発明は既設道路を所定深さ掘削する場
合と、掘削しない場合双方に実施でき、更に図
に示す実施例は既設道路の一部表面を掘削した
場合であつて、全面を掘削して高低差を失くせ
しめることは勿論可能である。(1) Excavation of the existing road In order to eliminate the height difference between the new road and the existing road, the surface of the existing road should be excavated to a specified depth. This invention can be implemented both when an existing road is excavated to a predetermined depth and when it is not excavated.Furthermore, the embodiment shown in the figure is a case where a part of the surface of an existing road is excavated, and the entire surface is excavated and the height difference is Of course, it is possible to make it disappear.
図において既設道路は谷側一部を道路進行方
向に沿つて所定深さ掘削し、山側には道路進行
方向と直行する方向の溝部1を道路進行方向に
適宜間隔離して掘削する。また溝部1の山側端
部には該溝部1と連続するアンカー溝2を掘削
する。 In the figure, a part of the existing road on the valley side is excavated to a predetermined depth along the direction of road travel, and on the mountain side, grooves 1 are excavated in a direction perpendicular to the direction of road travel, separated by appropriate distances in the direction of road travel. Further, an anchor groove 2 continuous with the groove 1 is excavated at the mountain side end of the groove 1.
(2) 支持杭打設
支持杭3を既設道路の拡幅側端部に沿つて所
定間隔で打設する。実施例では溝部1の延長位
置に各々打設する。支持杭3としてはPC杭等
が使用可能でアースオーガ等の使用によつて公
知の打設方法が使用できる。(2) Support pile driving Support piles 3 will be driven at specified intervals along the widening side edge of the existing road. In the embodiment, each is cast at an extended position of the groove 1. As the support pile 3, a PC pile or the like can be used, and a known driving method can be used by using an earth auger or the like.
支持杭3上には受台であるブロツク4を載置
する。ブロツク4の側方には鉄筋が突出せしめ
られており、後に述べるようにコンクリートを
打設したときコンクリートと一体化することが
できる。 A block 4 serving as a pedestal is placed on the support pile 3. Reinforcing bars are made to protrude from the sides of the block 4, so that they can be integrated with concrete when concrete is poured, as will be described later.
(3) 既設道路の均し
既設道路表面には均しモルタル、均しコンク
リート等5が打設されている。またドライモル
タルを使用して均すことも可能である。(3) Leveling of the existing road Leveling mortar, leveling concrete, etc.5 are placed on the surface of the existing road. It is also possible to level the surface using dry mortar.
(4) 反力アンカーの設置
既設道路の山側端部に沿つて所定間隔離して
反力アンカー6を載置する。実施例ではアンカ
ー溝2底部から地山に削孔7を形成し、PC鋼
材或いはロツクボルト8等を挿入し、グラウト
材9を注入して固定し、上端は削孔7から突出
せしめる。(4) Installation of reaction anchors Reaction anchors 6 will be placed at predetermined intervals along the mountain side edge of the existing road. In the embodiment, a hole 7 is formed in the ground from the bottom of the anchor groove 2, a prestressing steel material or a lock bolt 8 is inserted, and a grout 9 is injected to fix it, and the upper end is made to protrude from the hole 7.
アンカー溝2内には横桁である溝形鋼10が
溝2に沿つて位置せしめられ、該溝形鋼10の
底面上にPC鋼材等8の上端が突出せしめられ
ている。PC鋼材等8の上端はナツト若しくは
くさび11によつて固定する。PC鋼材の場合
は緊張してプレストレス力を与えた後緊張す
る。 A channel steel 10, which is a crossbeam, is positioned in the anchor groove 2 along the groove 2, and the upper end of a prestressing steel member 8 is made to protrude above the bottom surface of the channel steel 10. The upper end of the PC steel material 8 is fixed with a nut or wedge 11. In the case of PC steel, it is tensed after applying a prestressing force.
(5) 支持梁の設置
支持梁12を道路進行方向と直交する方向に
載置して一部を既設道路より張り出す。支持梁
12は道路進行方向に適宜間隔離して複数本載
置する。実施例では支持杭3によつて支持梁1
2を支持し、一部は溝部1内に載置する。(5) Installation of support beams The support beams 12 are placed in a direction perpendicular to the direction of road travel, and a portion thereof is overhanging the existing road. A plurality of support beams 12 are placed at appropriate intervals in the direction of road travel. In the embodiment, the support beam 1 is supported by the support pile 3.
2 is supported, and a portion is placed within the groove 1.
支持梁12としてはI形鋼、H形鋼、その他
コンクリート製梁材等既製の部材が使用でき
る。実施例ではH形鋼が使用されており、側面
に異形鉄筋等より成るジベル鋼材13が突設さ
れている。 As the support beam 12, ready-made members such as I-shaped steel, H-shaped steel, and other concrete beam materials can be used. In the embodiment, H-beam steel is used, and a dowel steel material 13 made of deformed reinforcing bars or the like is protruded from the side surface.
支持梁12の山側端部は反力アンカー6によ
つて固定する。実施例では横桁である溝形鋼1
0を介して固定されている。すなわち溝形鋼1
0の端部が支持梁12であるH鋼のフランジ上
に位置しており、反力アンカー6によつて固定
された溝形鋼10を介して支持梁12の山側端
部の浮き上がりを防止されている。 The mountain side end of the support beam 12 is fixed by a reaction anchor 6. In the example, channel steel 1, which is a crossbeam
Fixed via 0. That is, channel steel 1
0 end is located on the flange of the H steel that is the support beam 12, and the mountain side end of the support beam 12 is prevented from lifting up through the channel steel 10 fixed by the reaction anchor 6. ing.
(6) 型枠の吊り下げ
支持梁12の既設道路より張り出した部分に
型枠14を吊り下げる。型枠14の底板は支持
梁12の下面に当接し、支持梁12が型枠14
内に位置するようにして型枠14を吊り下げ
る。(6) Hanging the formwork The formwork 14 is hung from the part of the support beam 12 that overhangs the existing road. The bottom plate of the formwork 14 is in contact with the lower surface of the support beam 12, and the support beam 12 is in contact with the formwork 14.
The formwork 14 is suspended so that it is positioned within the center.
(7) 鉄筋等の配設
隣接する支持梁12,12間に鉄筋15を配
設する。鉄筋15を配設するのは図に示す実施
例のように既設道路の一部表面を掘削した場合
は該掘削した部分から型枠14内までであり、
全部を掘削した場合、或いは全く掘削しない場
合は支持梁12の長手方向全長にわたつてであ
る。(7) Arrangement of reinforcing bars, etc. Reinforcing bars 15 are arranged between adjacent support beams 12, 12. When a part of the surface of an existing road is excavated as in the embodiment shown in the figure, the reinforcing bars 15 are placed from the excavated part to the inside of the formwork 14,
If the entire area is excavated or if it is not excavated at all, the entire length of the support beam 12 in the longitudinal direction is covered.
鉄筋15は主として道路進行方向に配設して
端部を支持梁12の側面に溶接によつて固定す
る。 The reinforcing bars 15 are mainly arranged in the direction of road travel, and their ends are fixed to the side surfaces of the support beams 12 by welding.
型枠14にはその他PC鋼材を配設して緊張
し、道路進行方向或いは直交方向にプレストレ
ス力を与えることがある。 Other prestressing steel materials may be placed in the formwork 14 and tensioned to provide a prestressing force in the direction of road travel or in the orthogonal direction.
(8) コンクリートの打設
コンクリート16を打設して路盤を構築す
る。(8) Placing concrete Concrete 16 will be poured to construct the roadbed.
図に示す実施例のように既設道路の一表面を
掘削した場合は該掘削した部分(溝1,2内を
含む)と型枠14内にコンクリート16を打設
し、全面掘削した場合、或いは全く掘削しなか
つた場合は既設道路全面及び型枠14内にコン
クリート16を打設する。 When one surface of the existing road is excavated as in the example shown in the figure, concrete 16 is poured into the excavated portion (including the inside of grooves 1 and 2) and the formwork 14, and the entire surface is excavated, or If no excavation is done at all, concrete 16 is poured over the entire surface of the existing road and within the formwork 14.
コンクリート16の硬化後型枠14を取り外
せば路盤が完成する。 After the concrete 16 has hardened, the formwork 14 is removed to complete the roadbed.
(9) その他実施例
施工中は既設道路の一部、或いは全部の交通
遮断が必要となる場合があるが、交通に対する
影響は極力小さくすることが望ましい。(9) Other examples During construction, it may be necessary to close some or all of the existing roads to traffic, but it is desirable to minimize the impact on traffic.
このために既設道路の一部を掘削した場合
に、該溝部1等の掘削した部分に砂17等を埋
めて締め固め、暫時通行可能にしておき支持梁
12を載置するときに砂17等を排出すればよ
い。(第4図、第5図)
〔発明の効果〕
この出願にかかる一方の発明は以上のような構
成を有するため以下のような効果を得ることがで
きる。 For this purpose, when a part of the existing road is excavated, the excavated part of the groove 1 etc. is filled with sand 17 etc. and compacted to make it passable for a while. All you have to do is discharge it. (Fig. 4, Fig. 5) [Effects of the Invention] One of the inventions according to this application has the above-mentioned configuration, so that the following effects can be obtained.
張出し方式としたため、切土あるいは埋立て
が不必要となり、土工量が大幅に削減され、工
期も短縮できる。 The overhang method eliminates the need for cutting or filling, greatly reducing the amount of earthwork and shortening the construction period.
山側の切土が不要なため、既存の法背を傷め
ることがない。従つて新たに法面の保護工事を
行なう必要がない。 There is no need to cut the mountain side, so there is no damage to the existing slope. Therefore, there is no need to carry out new slope protection work.
既存の道路の端部に支持杭を設けるので、谷
側の埋立てによるものに比べ安定した構造が得
られる。また河川等の汚染の心配もない。 Since supporting piles are installed at the end of the existing road, a more stable structure can be obtained than one created by filling in the valley side. There is also no need to worry about contaminating rivers, etc.
張出し部分のみに活荷重が作用した場合に
は、山側端部に設けたアンカーに反力をとるこ
とができ、安定した構造となつている。 When a live load acts only on the overhanging portion, the reaction force can be taken by the anchor provided at the mountain end, resulting in a stable structure.
支持梁はコンクリート中に埋め込んで補強材
としての機能を果たせしめるため強固な引出し
拡幅道路が構築できる。 The support beams are embedded in the concrete and function as reinforcing materials, making it possible to construct a strong pull-out and widening road.
支持梁は補強材として使用するとともに型枠
を吊り下げるためにも使用するため、施工が簡
易となる。 The support beams are used not only as reinforcing materials but also to hang the formwork, which simplifies construction.
型枠を既設道路端部から張り出した支持梁に
吊り下げるため、谷側地山に支保工を組み立て
る必要がなく、施工が極めて容易となる。 Since the formwork is suspended from support beams extending from the edge of the existing road, there is no need to assemble support on the valley side ground, making construction extremely easy.
床版のような巨大な資材を運搬する必要がな
く、I鋼、H鋼等の既製の搬入の容易な部材を
使用するため道路状況の劣悪な現場であつても
搬入が容易である。 There is no need to transport huge materials such as floor slabs, and because ready-made members such as I steel and H steel are used, it is easy to transport even to sites with poor road conditions.
この出願にかかる他の発明は以上の効果の
他、以下の効果を得ることが可能となる。 Other inventions according to this application can obtain the following effects in addition to the above effects.
路盤の表面位置を変えることなく施工できる
ので、従来工法に比して既設道路、既設構造物
等との高さ調整のための付帯作業が不要とな
る。 Since construction can be performed without changing the surface position of the roadbed, there is no need for incidental work for height adjustment with existing roads, existing structures, etc. compared to conventional construction methods.
路盤を全部完全に掘削することなく工事を行
うことができるので工法としての適応性が広
い。 Since construction can be carried out without completely excavating the entire roadbed, it has wide applicability as a construction method.
第1図はこの発明にかかる道路拡幅工法の一実
施例の斜視図、第2図は道路進行方向と直交する
方向の縦断面図、第3図は第2図のA−A線断面
図、第4図及び第5図は第2図のB−B線の施工
順序断面図、第6図は第2図のC−C線断面図で
ある。
1……溝部、2……アンカー溝、3……支持
杭、6……反力アンカー、10……溝形鋼、12
……支持梁、14……型枠、15……鉄筋、16
……コンクリート。
FIG. 1 is a perspective view of an embodiment of the road widening method according to the present invention, FIG. 2 is a longitudinal cross-sectional view in a direction perpendicular to the direction of road travel, and FIG. 3 is a cross-sectional view taken along line A-A in FIG. 4 and 5 are construction sequence sectional views taken along the line BB in FIG. 2, and FIG. 6 is a sectional view taken along the line CC in FIG. 2. 1... Groove, 2... Anchor groove, 3... Support pile, 6... Reaction anchor, 10... Channel steel, 12
... Support beam, 14 ... Formwork, 15 ... Reinforcement bar, 16
……concrete.
Claims (1)
た支持杭によつて、道路進行方向と直交する方向
に載置して一部を既設道路端部から張り出した支
持梁を支持し、該支持梁の山側端部は反力アンカ
ーによつて地山に固定し、該支持梁の既設道路か
ら張り出した部分には型枠を吊り下げ、隣接する
支持梁間には鉄筋等を配設してコンクリートを打
設し、路盤を構築することを特徴とする道路拡幅
工法。 2 既設道路の各側端部は道路進行方向に沿つて
所定深さ掘削し、山側端部は道路進行方向と直交
する方向の溝部を適宜間隔離して掘削し、既設道
路の拡幅側に所定間隔をおいて打設した支持杭に
よつて、前記溝部内に一部を載置し道路進行方向
と直交する方向に位置せしめて一部を既設道路か
ら張り出した支持梁を支持し、該支持梁の山側端
部は反力アンカーによつて地山に固定し、該支持
梁の既設道路から張り出した部分には型枠を吊り
下げ、隣接する支持梁間には鉄筋等を配設してコ
ンクリートを打設し、路盤を構築することを特徴
とする道路拡幅工法。 3 上記工法において掘削した溝部等に一旦砂等
を埋めて締め固め、その後砂等を排出して溝部内
に支持梁を載置することを特徴とする特許請求の
範囲第2項記載の道路拡幅工法。[Scope of Claims] 1. Support piles driven at predetermined intervals on the widening side of the existing road, placed in a direction perpendicular to the direction of road travel, and partially overhanging the edge of the existing road. A beam is supported, the mountain side end of the support beam is fixed to the ground using a reaction anchor, formwork is suspended from the part of the support beam that overhangs the existing road, and reinforcing bars are installed between adjacent support beams. A road widening construction method characterized by placing concrete and constructing a roadbed. 2 Each side edge of the existing road will be excavated to a specified depth along the direction of road travel, and at the mountain side edge, grooves in the direction perpendicular to the direction of road travel will be excavated with appropriate distances separated, and excavated at specified intervals on the widening side of the existing road. A support beam, which is partially placed in the groove and positioned in a direction perpendicular to the direction of road travel, and partially overhangs the existing road, is supported by the support piles driven at a certain angle. The mountain side end of the support beam is fixed to the ground using reaction anchors, formwork is suspended from the part of the support beam that overhangs the existing road, and concrete is placed between adjacent support beams by placing reinforcing bars, etc. A road widening method characterized by pouring concrete and constructing a roadbed. 3. Road widening according to claim 2, characterized in that the trench excavated by the above construction method is once filled with sand, etc. and compacted, and then the sand, etc. is discharged and a support beam is placed in the trench. Construction method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14564984A JPS6124702A (en) | 1984-07-13 | 1984-07-13 | Road widening construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14564984A JPS6124702A (en) | 1984-07-13 | 1984-07-13 | Road widening construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6124702A JPS6124702A (en) | 1986-02-03 |
| JPH025843B2 true JPH025843B2 (en) | 1990-02-06 |
Family
ID=15389892
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14564984A Granted JPS6124702A (en) | 1984-07-13 | 1984-07-13 | Road widening construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6124702A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0399001U (en) * | 1990-01-19 | 1991-10-16 | ||
| JPH04149303A (en) * | 1990-10-12 | 1992-05-22 | Kensetsu Kiso Eng Co Ltd | Method for widening road |
-
1984
- 1984-07-13 JP JP14564984A patent/JPS6124702A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6124702A (en) | 1986-02-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5471811A (en) | Combination traffic barrier and retaining wall and method of construction | |
| US3195312A (en) | Method for erecting precast retaining wall | |
| US6503025B1 (en) | Precast concrete beam element and methods of making and installing same | |
| US4964750A (en) | Traffic barrier and method of construction | |
| US5131786A (en) | Traffic barrier and method of construction | |
| KR101206860B1 (en) | Excavation tunnel constructing method using vertical side wall and arch ceiling | |
| US5356242A (en) | System and method for adjustably connecting wall facing panels to the soldier beams of a tie-back or anchored wall | |
| KR102272494B1 (en) | Slope reinforcement structure using support and tension and Its Construction method | |
| IE902098A1 (en) | Formwork for forming structural beams | |
| US20030131544A1 (en) | Precast concrete beam element and methods of making and installing same | |
| US9951493B2 (en) | Precast integral post and retaining wall and method for installing same | |
| US4056154A (en) | Squaring off and reaming tool for deep elongated trench excavations | |
| JP2641182B2 (en) | Slope stabilization method and slope expansion method | |
| JPH025843B2 (en) | ||
| JPH0237442B2 (en) | DOROKAKUFUKUKOHO | |
| JP3593752B2 (en) | Retaining wall structure and built flat land structure or built road structure on steep slopes | |
| US5558470A (en) | System and method for adjustably anchoring traffic barriers and wall facing panels to the soldier beams of a wall | |
| JP2787806B2 (en) | Earth retaining wall | |
| KR102118665B1 (en) | Retaining wall and method for constructing the same | |
| WO1997034053A1 (en) | Pre-cast concrete panel wall | |
| JPH03279501A (en) | Widening of road | |
| JP2536376B2 (en) | Foundation structure of shed for road protection | |
| JPS6054459B2 (en) | Slope protection method | |
| JP2022006995A (en) | Overhanging sidewalk block and construction method of sidewalk using overhanging sidewalk block | |
| JPH03199528A (en) | Steel frame foundation of construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| EXPY | Cancellation because of completion of term |