Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH026900B2 - - Google Patents
[go: Go Back, main page]

JPH026900B2 - - Google Patents

Info

Publication number
JPH026900B2
JPH026900B2 JP22291983A JP22291983A JPH026900B2 JP H026900 B2 JPH026900 B2 JP H026900B2 JP 22291983 A JP22291983 A JP 22291983A JP 22291983 A JP22291983 A JP 22291983A JP H026900 B2 JPH026900 B2 JP H026900B2
Authority
JP
Japan
Prior art keywords
formwork
work
construction
frame
small beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP22291983A
Other languages
Japanese (ja)
Other versions
JPS60115755A (en
Inventor
Kunio Myajima
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP22291983A priority Critical patent/JPS60115755A/en
Publication of JPS60115755A publication Critical patent/JPS60115755A/en
Publication of JPH026900B2 publication Critical patent/JPH026900B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【発明の詳細な説明】 本発明は、従来の締付けセパレーター、フオー
ムタイ、パイプ等を用いて組み立てていたコンク
リート用型枠組付け工法の改良に関し、特に、労
力の能率化を企図して開発されたものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an improvement to the method of assembling concrete forms using conventional tightening separators, form ties, pipes, etc., and was developed with a particular aim of streamlining labor. It is.

従来のコンクリート型枠工法において多用され
ている締付け金具は、周知の如く、ネジによる締
付け作業が多く、しかも、型組補強の為に、数多
くの締付け用パイプを必要とするので、これ等多
数本のパイプ相互間の金具締付けが作業能率を低
下させる要因となつていた。
As is well known, the fastening metal fittings that are often used in conventional concrete formwork construction methods require a lot of tightening work with screws, and also require a large number of fastening pipes to reinforce the form. The tightening of metal fittings between pipes was a factor that reduced work efficiency.

又、この従来の工法では、型枠間に釘打ち付け
等の作業も伴うので、解体後の処理に大変手間が
かかりコスト高の原因となつていた。
In addition, this conventional construction method involves work such as nailing between the formworks, which requires a lot of time and effort to process after dismantling, leading to high costs.

一方、このような従来工法における型枠構造上
の問題点に加えて、施工手段においても、現場で
の作業が多いために、現場が枠組可能な状態にな
る迄作業に掛かれないこと、作業期間が限られて
いるので作業を短期間に行なうことが要求される
こと、作業全体が高所作業の為に上げ下げの作業
が多くて作業手順などに無駄が多いこと、更には
用いる作業器具が多いこと、機械力の導入が困難
であることなどの点から、施工コストを高める結
果となつていた。しかも、現場作業は天候不順、
工事進行状態によつて左右されて、工事の遅れな
どの計画性を乱す要因が多くあつた。
On the other hand, in addition to these problems with the formwork structure in conventional construction methods, the construction method involves a lot of work on site, which means that work cannot begin until the site is ready for framing, and the work period is short. The work must be done in a short period of time because the work is limited; the entire work is done at heights, so there is a lot of lifting and lowering work and there is a lot of waste in work procedures; and there is also a lot of work equipment used. This resulted in increased construction costs due to the difficulty of introducing mechanical power. Moreover, the work on site is subject to unfavorable weather conditions.
There were many factors that disrupted planning, such as construction delays, depending on the state of construction progress.

そこで、本発明は、上述のような従来施工にお
ける種々の欠点に鑑み、現場における悪条件を越
えて工期の短縮を企図し、加えて、従来施工され
ている締付け作業の多い型枠構造を改良して、従
来の締付け作業を行うことなくてコンクリート打
設が可能な工法を提案するものである。
Therefore, in view of the various drawbacks of conventional construction as described above, the present invention aims to shorten the construction period by overcoming the adverse conditions at the site, and in addition, improves the conventional formwork structure that requires a lot of tightening work. Therefore, we propose a method that enables concrete pouring without the need for conventional tightening work.

以下、本発明を図示の実施例を参照して詳述す
る。
Hereinafter, the present invention will be explained in detail with reference to illustrated embodiments.

第1図は本発明工法によつて組付けたコンクリ
ート打設部の一部を示す平面図で、鉄骨先組工法
によつて、柱1,1…間の大梁部2,2…に予め
鉄骨3を組み付けた状態で、この四隅の柱1,1
…に囲まれた部分を、一個の大型型枠4によつて
埋めてある。
Figure 1 is a plan view showing a part of the concrete pouring section assembled using the method of the present invention. With 3 assembled, pillars 1 and 1 at the four corners
The area surrounded by... is filled with one large formwork 4.

そして、該大型枠体4は、第2図に示す如く、
溝型鋼からなる二本の主軸5,5を長辺とし、左
右の両短辺をL字鋼からなる側軸6,6とした長
方形の枠組みと、この各四隅に取付けたブレース
14,14…と、後述する小梁部7に相当する位
置の両側に前記短辺の向きに平行したL字鋼から
なるアングル8,8…との各支持材からなる枠体
9を芯に構成してある。更に、これ等支持材から
なる枠体9に、第3図示の如く、厚板若しくは鋼
板パネルからなるスラブ型わく10を張り、前記
アングル8,8…の対向内側に当るところに側板
11を張り付けて前記小梁部7を形成する溝を構
成する。このとき、小梁部7の溝の底板(図示せ
ず)は後付け部材として図示状態では取付けられ
ていない。次いで、大梁部2の側壁となる枠体9
の四周側に鋼板12を取付けて、大型型枠4を完
成する。そして、完成した大型型枠4の主軸5に
平行な断面を第4図に示す。
The large frame body 4, as shown in FIG.
A rectangular frame with two main shafts 5, 5 made of channel-shaped steel as the long sides, and side shafts 6, 6 made of L-shaped steel as the left and right short sides, and braces 14, 14 attached to each of the four corners of this frame. and angles 8, 8 made of L-shaped steel parallel to the direction of the short side on both sides of the position corresponding to the small beam part 7, which will be described later. . Furthermore, as shown in the third diagram, a slab-type frame 10 made of a thick plate or steel plate panel is attached to the frame 9 made of these supporting materials, and a side plate 11 is attached to the opposite inner side of the angles 8, 8... A groove forming the small beam portion 7 is formed. At this time, the bottom plate (not shown) of the groove of the small beam portion 7 is not attached as a retrofitted member in the illustrated state. Next, the frame body 9 which becomes the side wall of the girder part 2
Steel plates 12 are attached to the four circumferential sides of the large formwork 4 to complete the large formwork 4. FIG. 4 shows a cross section of the completed large formwork 4 parallel to the main axis 5.

尚、この大型型枠4の構成下で、前記枠体9に
張り付けるスラブ型わく10の平面度を保つため
の補強手段としては、アングル8と側軸6との間
に間隔を置いて数本のパイプを根太(主軸5,
5)に渡し掛ける構成が有効である。
In addition, under the structure of this large formwork 4, as reinforcing means to maintain the flatness of the slab mold frame 10 attached to the frame body 9, several reinforcements are provided at intervals between the angle 8 and the side shaft 6. The main pipe is joist (main shaft 5,
5) is effective.

そして、この大型枠体4を前記大梁部2,2に
囲まれた部分に据え付けるには、先端に鈎状のフ
ツクを取付けた四本の釣りワイヤー13,13…
を第3図示のように該型枠4に装着して、これを
クレーン等によつて釣り上げて設置するが、この
釣りワイヤー13,13……の該型枠4への取付
けは、前記フツクを大型型枠4の小梁部7の開放
された底部を通して、前記主軸5,5の溝型鋼の
一方の辺に掛けることによつてなされる。
In order to install this large frame body 4 in the area surrounded by the large beam parts 2, 2, four fishing wires 13, 13... each having a hook-shaped hook attached to the tip thereof are used.
are attached to the formwork 4 as shown in the third figure, and then lifted up and installed using a crane or the like.The hooks are attached to the formwork 4 to attach the fishing wires 13, 13... to the formwork 4. This is done by passing through the open bottom of the small beam part 7 of the large formwork 4 and hanging it on one side of the channel steel of the main shafts 5, 5.

据え付けた大型型枠4はその小梁部7の溝底板
を設置した後に、小梁部7及びスラブ型わく10
上に鉄骨を組んで、コンクリート打設可能とな
る。
After the installed large formwork 4 has installed the groove bottom plate of the small beam part 7, the small beam part 7 and the slab type frame 10 are installed.
Once a steel frame has been erected on top, concrete can be poured.

このように、従来の型枠組付け手段が小型のス
ラブ型わくを組み合わせて所定の広さのコンクリ
ート打設面を構成するに付けてフオームタイ、パ
イプ及びセパレーターなどを用いて型枠の枠組を
行い、しかも、この枠組が施工現場でのネジ付け
作業によるところで、作業能率の向上を図る上で
の障害であり、しかも、このネジ締め付け作業に
よる組付けが鉄骨先組工法においては、先に組ま
れた鉄骨に邪魔されて作業自体が困難であること
から、更に作業能率が低下していたのに対して、
本発明工法の大型型枠の釣り込みによれば、施工
場所での作業が極めて少なく、しかも、先組鉄骨
の建込みと同時的に型枠の据え付けを行うことが
出来て、その作業能率は従来のそれに比して十倍
程度向上させることができる。
In this way, while the conventional formwork assembly method combines small slab frames to construct a concrete pouring surface of a predetermined area, the formwork is assembled using form ties, pipes, separators, etc. Moreover, this framework requires screw tightening work at the construction site, which is an obstacle to improving work efficiency.Furthermore, in the steel frame pre-assembly method, assembly using screw tightening work is difficult when the work is assembled first. The work itself was difficult due to the obstruction of the steel frame, which further reduced work efficiency.
According to the construction method of the present invention, the work required at the construction site is extremely small, and the formwork can be installed at the same time as the pre-assembled steel frame is erected, which is much more efficient than before. This can be improved by about 10 times compared to that of .

この型枠の据え付けの高効率化は、本質的には
大型型枠を予め組付け加工しておくことにあり、
この大型型枠の加工は、作業蓄積が出来ることを
意味し、従来の工法がこの作業蓄積が殆ど出来な
かつたことに起因する天候不順などにおける工事
の遅れ、或いは、短期内で多くの作業を強いられ
るなどの不都合さをなくして、工期の短縮を図り
得る。
The high efficiency of formwork installation essentially lies in the fact that the large formwork is assembled and processed in advance.
Processing this large formwork means that it is possible to accumulate work, and it is possible to avoid delays in construction due to inclement weather, etc. due to the fact that conventional construction methods could hardly accumulate this work, or to do a lot of work in a short period of time. It is possible to shorten the construction period by eliminating inconveniences such as being forced to do so.

又、本発明工法における作業能率の向上の今一
つの要因は、従来の型枠工法が施工現場での人手
による作業であつたのに対して、レツカー車ある
いはクレーンなどの機械力を導入しての作業が可
能になることにあり、合せて、このクレーン利用
の工法によれば、施工現場の高所作業時間を短縮
し得るので、作業危険率を少なくなすことが出来
ることが有利である。
Another reason for the improvement in work efficiency in the method of the present invention is that whereas the conventional formwork construction method required manual work at the construction site, mechanical power such as a truck or a crane was introduced. In addition, according to this method of construction using a crane, it is possible to shorten the time required for working at high places at the construction site, which is advantageous in that the risk of work can be reduced.

そして、この場合のクレーン等による型枠の釣
り上げ作業が、アンカー等の係架金具などを設け
ることなくて、小梁通し溝の開口した溝底部を通
して釣フツクを枠材の下面側に引掛けることによ
つて出来るので、型枠として不要の突起又は凹所
などが生ぜず、これによつて、予めスラブ型わく
を張付けた型枠の作業蓄積が可能である。
In this case, the work of lifting the formwork using a crane or the like can be carried out by hooking the fishing hook onto the bottom side of the frame material through the open bottom of the girder passage groove, without installing anchors or other mooring metal fittings. Since it is possible to do so without creating unnecessary protrusions or recesses in the formwork, it is possible to accumulate work on the formwork to which the slab mold frame has been attached in advance.

なお、本発明方向による図示実施例の大型型枠
の実用寸法の一例を示せば、長辺が9100mm及び短
辺が4000mmの長方形であつて、溝巾300mmの小梁
部を両側辺から2800mmのところに夫々設けた構造
である。
An example of the practical dimensions of the large formwork of the illustrated embodiment according to the present invention is that it is a rectangle with a long side of 9100 mm and a short side of 4000 mm. This is a structure that is installed at each location.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明工法による施工現場の平面図、
第2図は本発明工法における大型型枠の枠体を示
す斜視図、第3図は本発明工法における大型型枠
を釣り下げた状態を示す斜視図、第4図は同じく
完成した大型型枠を長手向きに縦断して示す側面
図である。 1……柱、2……大梁部、3……鉄骨、4……
大型型枠、5……主軸、6……側軸、7……小梁
部、8……アングル、9……枠体、10……スラ
ブ型わく、11……側板、12……剛板、13…
…釣りワイヤー、14……ブレース。
Figure 1 is a plan view of the construction site using the construction method of the present invention.
Figure 2 is a perspective view showing the frame body of the large formwork in the construction method of the present invention, Figure 3 is a perspective view showing the large formwork in a suspended state in the construction method of the invention, and Figure 4 is the same completed large formwork. FIG. 1...Column, 2...Girder section, 3...Steel frame, 4...
Large formwork, 5... main shaft, 6... side shaft, 7... small beam section, 8... angle, 9... frame body, 10... slab type frame, 11... side plate, 12... rigid plate , 13...
...Fishing wire, 14...Brace.

Claims (1)

【特許請求の範囲】[Claims] 1 鋼材を四周辺並びに小梁通し位置の両側に渡
し付けると共に四隅ブレースを取付けた枠体に、
後付け可能な状態で小梁通し溝の底板部を残し
て、スラブ型わくと側板とを張付けて大型型枠を
予め構成しておき、鉄骨先組工法によつて組付け
られた大梁四側内に、前記小梁通し溝の開口した
底板部を通して枠体に釣フツクを係架して、該大
型型枠を釣り込み配置するようになしたコンクリ
ート型枠工法。
1. Pass the steel materials around the four sides and on both sides of the small beam passing position, and attach the four corner braces to the frame body.
A large formwork is constructed in advance by attaching the slab type frame and side plates, leaving the bottom plate of the girder through-groove so that it can be retrofitted. A method of constructing a concrete formwork, in which a fishing hook is suspended from the frame body through the bottom plate portion of the small beam passage groove, and the large formwork is placed therein.
JP22291983A 1983-11-25 1983-11-25 Concrete mold frame construction method Granted JPS60115755A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22291983A JPS60115755A (en) 1983-11-25 1983-11-25 Concrete mold frame construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22291983A JPS60115755A (en) 1983-11-25 1983-11-25 Concrete mold frame construction method

Publications (2)

Publication Number Publication Date
JPS60115755A JPS60115755A (en) 1985-06-22
JPH026900B2 true JPH026900B2 (en) 1990-02-14

Family

ID=16789914

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22291983A Granted JPS60115755A (en) 1983-11-25 1983-11-25 Concrete mold frame construction method

Country Status (1)

Country Link
JP (1) JPS60115755A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6268947A (en) * 1985-09-24 1987-03-30 株式会社フジタ Small beam, floor slab construction method

Also Published As

Publication number Publication date
JPS60115755A (en) 1985-06-22

Similar Documents

Publication Publication Date Title
JPH026900B2 (en)
JPH04222742A (en) Composite beam
JPH0657710A (en) Construction of concrete main tower
JP2885023B2 (en) Construction method of reinforced concrete slab which does not need support under slab and temporary beam generating peeling
JPH025213B2 (en)
JPH0726644A (en) How to build a parapet
JP2534009B2 (en) Form support for overhang
JP2891113B2 (en) Installation method of reinforced concrete shear walls
JPH0235168A (en) Form for panel zone
JP2797023B2 (en) Construction method of beam
JPH044091Y2 (en)
JP2990216B2 (en) Construction method of reinforced concrete building
JPH0211521Y2 (en)
JPH02229337A (en) Concrete pillar construction method
JPH01223248A (en) Folded plate unit slab construction method
JPH0634491Y2 (en) Formwork and floor slab
JP2602362B2 (en) Thick wall and beam or floor slab joining method
JPS63171939A (en) Execution of reinforced concrete building
JPH0558112B2 (en)
JPH0531757B2 (en)
JPH03151430A (en) Building method for reinforced concrete beam using beam formwork of precast concrete
JPH06185108A (en) Beam construction method
JPS6149462B2 (en)
JPH0586677A (en) Slab construction method using slab discard formwork with latch
JPH02112534A (en) Fixing device for external wall member and reinforcement column for reinforced concrete