Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0341605B2 - - Google Patents
[go: Go Back, main page]

JPH0341605B2 - - Google Patents

Info

Publication number
JPH0341605B2
JPH0341605B2 JP58041468A JP4146883A JPH0341605B2 JP H0341605 B2 JPH0341605 B2 JP H0341605B2 JP 58041468 A JP58041468 A JP 58041468A JP 4146883 A JP4146883 A JP 4146883A JP H0341605 B2 JPH0341605 B2 JP H0341605B2
Authority
JP
Japan
Prior art keywords
core
embankment
self
type dam
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58041468A
Other languages
Japanese (ja)
Other versions
JPS59170312A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP58041468A priority Critical patent/JPS59170312A/en
Publication of JPS59170312A publication Critical patent/JPS59170312A/en
Publication of JPH0341605B2 publication Critical patent/JPH0341605B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Description

【発明の詳細な説明】[Detailed description of the invention]

本発明はロツクフイルダム、アースダムなどの
フイルタイプダムの遮水を目的とするコアを構築
する方法に関する。 従来、フイルタイプダムはコアの材料として粘
土などの天然土、あるいは加熱アスフアルトコン
クリートを用いて、堤体材料とともに盛立てて堤
体を築造していた。 しかしながら、コア材料としての粘土などの天
然土は良質のものが入手しにくいこと、天候に左
右されやすく含水比の調整が困難なことなどの問
題点があつた。また、加熱アスフアルトコンクリ
ートは大かがりな加熱設備が必要であること、盛
立て厚が必要以上に取れないため施工能率が悪い
ことなどの問題点があつた。 このような問題点を解決する技術として、例え
だ、特開昭54−32258号公報には、以下に説明す
るフイルタイプダムのコア構築方法が開示されて
いる。 第1図は、上記公報に示されている構築方法の
要部を示しており、同図は、いわゆる中央コア型
のフイルタイプダムの築造方法を示す概略側面図
である。 上記公報に示されている構築方法では、コアの
構築の前に、基礎岩盤1内の所定位置にセメント
等の注入によるカーテングラウチング2を実施し
た基礎処理を行なう。 つぎに、基礎岩盤1上にセメント瀝青モルタル
やセメント瀝青コンクリートからなるコア3を型
枠を用いて形成し、このコア3を挟むように両側
にロツクあるいはランダムゾーン4を設定し、各
ゾーンの材料を並行してまき出し・締固めなどに
よる盛立て工事を行なう。 以上の作業を繰り返しながら堤頂まで施工する
ことにより所望のフイルタイプダム5が築堤され
る。 しかしながら、このようなコアの構築方法で
は、コアの継き目部分の止水性に不安があるとと
もに型枠の設置、脱型を繰り返さなければならな
いので、施工が煩雑になり、工期が長期化すると
いう問題があつた。 本発明は前記問題点をかんがみなされたもの
で、その目的とするところは、フイルタイプダム
のコアを天候に左右されることなく、能率よく、
また経済的に構築できる新しい施工法を提供する
ことにある。 上記目的を達成するために、本発明は、フイル
タイプダムのコアを構築する際に、前記フイルタ
イプダムの堤体を築造した後に、この堤体の中央
部に前記コアを構築する方法であつて、前記コア
は、基礎地盤に設けられたカーテングラウチング
の上端と重合する溝孔を自硬性安定液を満たしな
がら前記堤体の上部側から掘削し、この自硬性安
定液を硬化させることにより構築される連続壁で
あり、前記自硬性安定液は、3〜40%のベントナ
イト・粘土と、8〜16%のセメントとを含んでい
ることを特徴とする。 すなわち、本発明の基本的構想は、従来のよう
に堤体材料を盛立て工事とコア材料の盛立て工事
とを並行してフイルタイプダムを築堤することで
はなく、堤体材料の盛立て工事を先行してフイル
タイプダムを築造した後に、該堤体内のコア材料
の構築工事を後行することにある。 以下、図面を参照して本発明の実施例を説明す
る。 第2図,第3図,第4図は、本発明に係る中央
コア型のフイルタイプダムの築造方法の施工順序
を示す概略側面図である。 まず、第2図においてカーテングラウチング2
により基礎処理された基礎岩盤1上にロツクある
いはランダムゾーン4を盛立て工事により行な
う。この盛立て工事を堤頂まで繰り返すことによ
りコアのないフイルタイプダムの堤体5が築堤さ
れる。 つぎに、第3図に示すように、築堤されたコア
のないフイルタイプダムの堤体5の天端6面より
掘削装置7を使用して、堤体5内に安定液たる自
硬性安定液8を満たしながら溝孔9を掘削する。 そして、溝孔9の先端がカーテングラウチング
2の上端部を掘削する深度まで形成されると、溝
孔9の掘削が完了し、その後掘削された溝孔9内
の自硬性安定液8は時間の経過とともに硬化し、
単位硬化壁に変換される。 次いで、第4図において堤体5の長手方向に後
行単位硬化壁が、先行単位硬化壁とラツプするよ
うに連接する状態で形成され、このような作業が
繰り返されると、硬化単位壁が横方向に連結され
た連続壁すなわちコア10が構築される。 本発明で使用する自硬性安定液8は、3〜40%
のベントナイト・粘土、8〜16%のセメント、必
要に応じて添加する遅延剤からなる水懸濁液であ
る。 この自硬性安定液の硬化体の諸性状は、表−1
に示すように透水係数(k)が10-6〜10-7cm/secの
オーダーで不透水性を示し、さらにたわみ性を示
す変形係数(E50)200〜500m/cm2でロツク材あ
るいはランダム材からなる堤体5と類似の値を持
ち、堤体5の変形に追従することを示している。
The present invention relates to a method for constructing a core for the purpose of water-blocking a foil-type dam such as a rock-filed dam or an earth dam. Conventionally, foil-type dams have used natural soil such as clay or heated asphalt concrete as the core material, and have built the embankment by mounding it together with the embankment material. However, there are problems with natural soil such as clay as a core material, such as difficulty in obtaining high-quality natural soil, and the fact that it is easily influenced by the weather, making it difficult to adjust the water content ratio. In addition, heated asphalt concrete has problems such as the need for large-scale heating equipment and poor construction efficiency because it is difficult to build up the concrete to a thickness greater than necessary. As a technique for solving such problems, for example, Japanese Patent Application Laid-Open No. 54-32258 discloses a method for constructing a core of a file type dam, which will be described below. FIG. 1 shows the main part of the construction method disclosed in the above-mentioned publication, and is a schematic side view showing the construction method of a so-called central core type file type dam. In the construction method disclosed in the above publication, before constructing the core, foundation treatment is performed by performing curtain grouting 2 by injecting cement or the like into a predetermined position within the foundation rock 1. Next, a core 3 made of cement-bituminous mortar or cement-bituminous concrete is formed on the foundation rock 1 using a formwork, lock or random zones 4 are set on both sides of the core 3, and the material of each zone is At the same time, embankment work will be carried out by pouring out and compacting. By repeating the above-mentioned work and constructing the dam up to the top of the dam, the desired foil type dam 5 is constructed. However, with this type of core construction method, there are concerns about the watertightness of the joints of the core, and the formwork must be installed and removed repeatedly, making construction complicated and prolonging the construction period. There was a problem. The present invention has been made in consideration of the above-mentioned problems, and its purpose is to efficiently construct the core of a foil type dam without being affected by the weather.
It also aims to provide a new construction method that can be constructed economically. In order to achieve the above object, the present invention provides a method for constructing the core in the center of the embankment body of the foil type dam after constructing the embankment body when constructing the core of the foil type dam. The core is constructed by excavating from the upper side of the embankment while filling a self-hardening stabilizing liquid with a groove that overlaps the upper end of curtain grouting provided in the foundation ground, and hardening the self-hardening stabilizing liquid. The self-hardening stabilizer is characterized in that it contains 3 to 40% bentonite clay and 8 to 16% cement. That is, the basic concept of the present invention is not to build a file type dam in parallel with the work of heaving the embankment body material and the work of heaping the core material, as in the past, but to construct the heaping work of the embankment material. After constructing the foil type dam in advance, the construction work of the core material inside the embankment is carried out later. Embodiments of the present invention will be described below with reference to the drawings. FIG. 2, FIG. 3, and FIG. 4 are schematic side views showing the construction order of the method for constructing a central core type foil type dam according to the present invention. First, in Figure 2, curtain grouting 2
A lock or random zone 4 is created by embankment work on the foundation rock 1 that has been foundation-treated. By repeating this embankment work up to the crest of the embankment, the embankment body 5 of a coreless film type dam is constructed. Next, as shown in FIG. 3, using an excavator 7 from the top 6 surface of the embankment body 5 of the embanked film-type dam without a core, a self-hardening stabilizing liquid, which is a stable liquid, is poured into the embankment body 5. A trench hole 9 is excavated while filling the hole 8. When the tip of the groove hole 9 is formed to a depth that excavates the upper end of the curtain grouting 2, the excavation of the groove hole 9 is completed, and the self-hardening stabilizing liquid 8 in the excavated groove hole 9 is hardens over time,
Converted into a unit hardened wall. Next, in FIG. 4, a trailing unit hardened wall is formed in the longitudinal direction of the embankment body 5 so as to overlap and connect with the preceding unit hardened wall, and when such operations are repeated, the hardened unit wall becomes lateral. A directionally connected continuous wall or core 10 is constructed. The self-hardening stabilizer 8 used in the present invention has a content of 3 to 40%
bentonite clay, 8-16% cement, and an optional retarder. The properties of the cured product of this self-hardening stabilizer are shown in Table 1.
As shown in Figure 2, it shows impermeability when the permeability coefficient (k) is on the order of 10 -6 to 10 -7 cm/sec, and it is also made of rock or random material with a deformation coefficient (E50) of 200 to 500 m/ cm2 , which indicates flexibility. This value is similar to that of the embankment body 5 made of wood, indicating that it follows the deformation of the embankment body 5.

【表】 また、粒径の大きい堤体材料からなる堤体5内
の溝孔を掘削するには、自硬性安定液8に逸泥防
止材として、たとえば適当長のポリエステル繊維
(とくに、KSフアイバーが好例)を添加すると逸
泥することなく溝孔壁の安定を保持することがき
る。 また、堤体5の長手方向にコア10を単列とし
て構築することの他に、コア10を複並列として
構築することも可能である。 以上、詳述したように本発明は、フイルタイプ
ダムの堤体を築造した後に、コアを自硬性安定液
が硬化することにより形成される連続壁として構
築したから、後行のコア材料の構築工事は、先行
の堤体材料の盛立て工事とは無関係に施工できる
ので施工能率上、工期短縮上きわめて有利であ
る。 また、本発明の構築方法では、基礎地盤のカー
テングラウチングとコアとが重合して連結される
ので、十分な止水性が確保される。 さらに、後行のコア材料の構築工事は天候に左
右されることなく工事することができ、また、コ
アとして特定の範囲に調整された自硬性安定液を
使用するので、遮水性に富み、フイルタイプダム
の変形に追従するたわみ性を有する理想的なコア
が構築できる。
[Table] In addition, when excavating a groove in the embankment body 5 made of a material with a large particle size, for example, a suitable length of polyester fiber (especially KS fiber) is added to the self-hardening stabilizing liquid 8 as a sludge prevention material. (a good example), it is possible to maintain the stability of the trench wall without slippage. Moreover, in addition to constructing the cores 10 in a single row in the longitudinal direction of the embankment body 5, it is also possible to construct the cores 10 in multiple parallel rows. As described in detail above, in the present invention, after constructing the embankment body of a file type dam, the core is constructed as a continuous wall formed by hardening of the self-hardening stabilizing liquid. The construction work can be carried out independently of the preceding construction of embankment material, which is extremely advantageous in terms of construction efficiency and shortening the construction period. Furthermore, in the construction method of the present invention, the curtain grouting in the foundation ground and the core are polymerized and connected, so that sufficient water-stopping properties are ensured. Furthermore, the subsequent core material construction work can be carried out without being affected by the weather, and since the core uses a self-hardening stabilizing liquid adjusted to a specific range, it has excellent water-impermeability and a film-like structure. An ideal core with flexibility that follows the deformation of the type dam can be constructed.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の中央コア型のフイルタイプダム
の築造方法を示す概略側面図である。第2図は本
発明に係る盛立て工事により築堤されたコアのな
いロツクフイルタイプダムの概略側面図、第3図
は第2図のコアのないロツクフイルタイプダムの
堤体内のコア構築工事を示す概略側面図、第4図
はコア構築工事により完成したロツクフイルタイ
プダムの概略側面図である。 4……ロツクあるいはランダムゾーン、5……
ロツクフイルタイプダム、8……自硬性安定液、
9……溝孔、10……コア。
FIG. 1 is a schematic side view showing the construction method of a conventional central core type file type dam. Fig. 2 is a schematic side view of a rock-file type dam without a core built by embankment work according to the present invention, and Fig. 3 shows the core construction work inside the embankment of the lock-file type dam without a core shown in Fig. 2. Figure 4 is a schematic side view of a lock-file type dam completed through core construction work. 4...Lock or random zone, 5...
Lock file type dam, 8...Self-hardening stabilizer,
9...Slot hole, 10...Core.

Claims (1)

【特許請求の範囲】[Claims] 1 フイルタイプダムのコアを構築する際に、前
記フイルタイプダムの堤体を築造した後に、この
堤体の中央部に前記コアを構築する方法であつ
て、前記コアは、基礎地盤に設けられたカーテン
グラウチングの上端と重合する溝孔を自硬性安定
液を満たしながら前記堤体の上部側から掘削し、
この自硬性安定液を硬化させることにより構築さ
れる連続壁であり、前記自硬性安定液は、3〜40
%のベントナイト・粘土と、8〜16%のセメント
とを含んでいることを特徴とするフイルタイプダ
ムのコア構築方法。
1. When constructing the core of a foil type dam, the core is constructed in the center of the embankment body of the foil type dam after the embankment body is constructed, the core being installed on the foundation ground. excavating a groove from the upper side of the embankment body while filling it with a self-hardening stabilizing liquid, which overlaps with the upper end of the curtain grouting;
It is a continuous wall constructed by curing this self-hardening stabilizing liquid, and the self-hardening stabilizing liquid has a
A method for constructing a core of a fill-type dam, characterized in that the core contains 8% to 16% of bentonite clay and 8 to 16% of cement.
JP58041468A 1983-03-15 1983-03-15 Core construction of fill-type dam Granted JPS59170312A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58041468A JPS59170312A (en) 1983-03-15 1983-03-15 Core construction of fill-type dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58041468A JPS59170312A (en) 1983-03-15 1983-03-15 Core construction of fill-type dam

Publications (2)

Publication Number Publication Date
JPS59170312A JPS59170312A (en) 1984-09-26
JPH0341605B2 true JPH0341605B2 (en) 1991-06-24

Family

ID=12609201

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58041468A Granted JPS59170312A (en) 1983-03-15 1983-03-15 Core construction of fill-type dam

Country Status (1)

Country Link
JP (1) JPS59170312A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5454668A (en) * 1994-05-25 1995-10-03 Baroid Technology, Inc. Flood barrier and a method for forming a flood barrier
KR20030037829A (en) * 2001-11-06 2003-05-16 김태희 Core Retrofitting Structure for Aged Rockfill Dam or Reservior using Penetrable Waterproofing Agent
JP2006022631A (en) * 2004-07-07 2006-01-26 Eizo Aoki Method for constructing impervious layer of embankment dam
CN105756019B (en) * 2016-03-29 2018-01-16 清华大学 A kind of ruggedized construction and its construction method for damming body
CN109356102B (en) * 2018-11-23 2024-01-30 中国电建集团成都勘测设计研究院有限公司 Asphalt concrete core wall and dam foundation impervious wall connecting structure

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5363708A (en) * 1976-11-18 1978-06-07 Obayashi Gumi Kk Method of building water stop wall
JPS5432258A (en) * 1977-08-18 1979-03-09 Fujitsu Ltd Exclusive logical sum circuit

Also Published As

Publication number Publication date
JPS59170312A (en) 1984-09-26

Similar Documents

Publication Publication Date Title
CN107313431A (en) Close on not contour foundation ditch method for synchronously constructing
US4453366A (en) Process of forming a continuous wall in the ground
CN112081155A (en) A method for strengthening and lifting of strip or box-shaped foundation buildings
JP3676441B2 (en) Pit and construction method of basement using it
JPH0341605B2 (en)
US4981399A (en) Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPS63315724A (en) Execution work of cast-in-place concrete pile with high yield strength
JP2004124452A (en) Foundation pile structure and construction method of foundation pile on supporting ground
JPH09125347A (en) How to build a dam
JP3099040B2 (en) Embankment culvert
JP2764482B2 (en) Construction method of large depth human hole
JPH0612012B2 (en) Tsukishima construction method
JPH09268542A (en) Dam levee structure and cement levee body construction method using cement mixture
JP2567979B2 (en) How to build an underground wall
JP3071308B2 (en) Permeable continuous underground wall
JPH0442493B2 (en)
JPH0538125Y2 (en)
CN119243768A (en) A method for constructing a grouting steel pipe foundation retaining wall in a strongly weathered rock layer
JPS626049B2 (en)
JPS5854124A (en) Constructing method for preliminary underground wall preceding excavation of ditch for continuous underground wall
JPS6085121A (en) Building method of cut-off wall
JPS609172B2 (en) How to build underground structures
JPS61211423A (en) Refilling method of excavated trench
JPS58110732A (en) Installation of pipe culvert