JPH0364009B2 JP60063700A JP6370085A JPH0364009B2 JP H0364009 B2 JPH0364009 B2 JP H0364009B2 JP 60063700 A JP60063700 A JP 60063700A JP 6370085 A JP6370085 A JP 6370085A JP H0364009 B2 JPH0364009 B2 JP H0364009B2
Authority
JP
Japan
Prior art keywords
pile
footing
present
pile head
steel material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60063700A
Other languages
Japanese (ja)
Other versions
JPS61225426A (en
Inventor
Yukio Ookawa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Kk
Original Assignee
Fujita Kk
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Kk filed Critical Fujita Kk
Priority to JP6370085A priority Critical patent/JPS61225426A/en
Publication of JPS61225426A publication Critical patent/JPS61225426A/en
Publication of JPH0364009B2 publication Critical patent/JPH0364009B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は杭基礎に係るものである。[Detailed description of the invention] (Industrial application field) The present invention relates to a pile foundation.

(従来の技術)及び(発明が解決しようとする問
題点) 従来、杭頭接合部はピンジヨイント機構の仕様
が確立されていないのにもかかわらず、杭頭接合
部をピンジヨイントとして設計する場合が多かつ
た。
(Prior Art) and (Problems to be Solved by the Invention) Conventionally, pile cap joints are often designed as pin joints, even though specifications for the pin joint mechanism have not been established. It was.

これは実情にそぐわないのみならず、最近の設
計指針によれば杭頭接合部は全て固定として設計
せざるを得ず、このように杭頭接合部の仮定がピ
ンジヨイントから固定に移行すると、経済設計上
不利になる場合が多い。
This not only does not suit the actual situation, but according to recent design guidelines, all pile cap joints must be designed as fixed, and if the assumption of pile cap joints shifts from pin joint to fixed, economic design It is often at a disadvantage.

従つて杭頭接合部をピンジヨイント機構とする
具体的な構造の出現が要望されている。
Therefore, there is a demand for a concrete structure in which the pile head joint is a pin joint mechanism.

(問題点を解決するための手段) 本考案はこのような問題点を解決するために提
案されたもので、杭頭部に植立した碇着長の短か
い鋼材をフーチングに碇着するとともに、同フー
チングと前記杭頭部との間に両者を構造的に絶縁
する仕切材を介装してなることを特徴とする杭基
礎に係るものである。
(Means for solving the problem) The present invention was proposed to solve the above problem. This invention relates to a pile foundation characterized in that a partition material is interposed between the footing and the pile head to structurally insulate them.

(作用)及び(発明の効果) 本発明においては前記したように、杭頭部に碇
着長の短かい鋼材を植設し、同鋼材をフーチング
に碇着して曲げモーメントは伝達できないが、水
平剪断力は伝達できるようにし、且つ前記杭頭部
とフーチング下面との間に仕切材を介装し、同仕
切材によつて杭とフーチングとを杭頭面で構造的
に絶縁し、更に杭のフーチングへの埋込み量が0
か極めて小さいものとして、杭の側面からの杭の
曲げモーメント、及び剪断力が殆んど伝達できな
いようにし、かくして本発明によれば簡単な構成
で杭頭接合部をピンジヨイントとすることができ
る。
(Function) and (Effects of the Invention) As described above, in the present invention, a steel material with a short anchoring length is planted at the pile head and the steel material is anchored to the footing, so that bending moment cannot be transmitted. The horizontal shearing force can be transmitted, and a partition material is interposed between the pile head and the bottom surface of the footing, and the partition material structurally insulates the pile and the footing on the pile cap surface, and The amount of pile embedded in the footing is 0.
By making it extremely small, almost no bending moment and shearing force of the pile can be transmitted from the side of the pile, and thus, according to the present invention, the pile cap joint can be made into a pin joint with a simple structure.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

第1図において1は杭で、その杭頭部に碇着長
の短かい水平剪断力伝達用鋼材2が植立され、同
鋼材2がフーチング3に碇着されるとともに、杭
頭部に弗素樹脂板、鉄板等の仕切板14が載架さ
れ、同仕切板4によつてフーチング3と杭1とが
構造的に絶縁されている。
In Fig. 1, reference numeral 1 indicates a pile, and a steel material 2 for transmitting horizontal shearing force with a short anchoring length is planted on the pile head, and the steel material 2 is anchored to a footing 3. A partition plate 14 made of a resin plate, an iron plate, or the like is mounted, and the footing 3 and the pile 1 are structurally insulated by the partition plate 4.

図中5は捨コンクリート、6は敷砂利である。 In the figure, 5 is concrete and 6 is gravel.

図示の実施例によれば前記したように、杭1の
杭頭部に載架された仕切板4によつて杭1とフー
チング3とが構造的に絶縁され、杭1のフーチン
グ3への根入れは0、若しくは極めて小さいもの
として、杭1の側面から、杭1の曲げモーメント
及び剪断力が殆んど伝達できないようになつてい
る。更に杭頭部に植立された碇着長の短かい前記
鋼材2が、フーチング3に碇着されていることに
よつて、曲げモーメントは伝達されないが水平剪
断力が伝達される。
According to the illustrated embodiment, as described above, the pile 1 and the footing 3 are structurally insulated by the partition plate 4 mounted on the pile head of the pile 1, and the root of the pile 1 to the footing 3 is The insertion is set to 0 or extremely small so that almost no bending moment and shearing force of the pile 1 can be transmitted from the side surface of the pile 1. Further, since the steel material 2 having a short anchorage length planted on the pile head is anchored to the footing 3, a horizontal shearing force is transmitted although no bending moment is transmitted.

かくして図示の実施例によれば、簡単な構成で
杭頭接合部がピンジヨイントに構成されるもので
ある。
Thus, according to the illustrated embodiment, the pile cap joint is formed into a pin joint with a simple construction.

第2図は本発明の他の実施例を示し、複数の水
平剪断力伝達用鋼材1が使用されている。
FIG. 2 shows another embodiment of the invention, in which a plurality of horizontal shear force transmitting steel members 1 are used.

図中前記実施例と均等部分には同一符号が附さ
れている。
In the figure, parts equivalent to those of the above embodiment are given the same reference numerals.

第3図及び第4図は本発明の更に他の各実施例
を示し、前記仕切板4の代りに、一定層の砂また
は砂利等の粒度材4′を杭頭部に載架し、同粒度
材4′によつて杭1とフーチング3とを構造的に
絶縁したものである。
3 and 4 show still other embodiments of the present invention, in which, instead of the partition plate 4, a certain layer of granular material 4' such as sand or gravel is mounted on the pile head. The pile 1 and the footing 3 are structurally insulated by the granular material 4'.

図中前記各実施例と均等部分には同一符号が附
されている。
In the drawings, parts equivalent to those of the above embodiments are given the same reference numerals.

以上本発明を実施例について説明したが、本発
明は勿論このような実施例にだけ局限されるもの
ではなく、本発明の精神を逸脱しない範囲内で
種々の設計の改変を施しうるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第4図は本発明に係る杭基礎の各実
施例を示す縦断面図である。 1…杭、2…鋼材、3…フーチング、4…仕切
板、4′…粒度材。
1 to 4 are longitudinal cross-sectional views showing each embodiment of the pile foundation according to the present invention. 1...Pile, 2...Steel material, 3...Footing, 4...Partition plate, 4'...Grain size material.

Claims (1)

【特許請求の範囲】[Claims] 1 杭頭部に植立した碇着長の短かい鋼材をフー
チングに碇着するとともに、同フーチングと前記
杭頭部との間に両者を構造的に絶縁する仕切材を
介装してなることを特徴とする杭基礎。
1 A steel material with a short anchorage length planted at the pile head is anchored to a footing, and a partition material is interposed between the footing and the pile head to structurally insulate the two. A pile foundation featuring:
JP6370085A 1985-03-29 1985-03-29 Pile foundation Granted JPS61225426A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6370085A JPS61225426A (en) 1985-03-29 1985-03-29 Pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6370085A JPS61225426A (en) 1985-03-29 1985-03-29 Pile foundation

Publications (2)

Publication Number Publication Date
JPS61225426A JPS61225426A (en) 1986-10-07
JPH0364009B2 true JPH0364009B2 (en) 1991-10-03

Family

ID=13236912

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6370085A Granted JPS61225426A (en) 1985-03-29 1985-03-29 Pile foundation

Country Status (1)

Country Link
JP (1) JPS61225426A (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58153823A (en) * 1982-03-08 1983-09-13 Takenaka Komuten Co Ltd Connecting work of pile and footing

Also Published As

Publication number Publication date
JPS61225426A (en) 1986-10-07

Similar Documents

Publication Publication Date Title
US4583336A (en) Joint of preformed concrete elements
US3382815A (en) Method of constructing railway track
JPH0364009B2 (en)
JPH09256390A (en) Vibration-isolation pile foundation
JPS61225425A (en) Pile foundation
JPS6181979A (en) Precast prestressed concrete tank and execution method thereof
JPS61261556A (en) Reinforcement of connection part of pillar and beam/slab in inverse impact construction method
US2296756A (en) Load transfer device
JPH033638Y2 (en)
US3982365A (en) Distribution blocks for the formation of joints resisting to differential settling and joints obtained by using said blocks
JPH0128162B2 (en)
JPH0674591B2 (en) Anchor support beam construction method
JPH0439922Y2 (en)
JPH10204968A (en) Joining structure for common ditch and its joint frame
JPH063029B2 (en) Seismic retrofitting method for pile foundation structure
SU949076A1 (en) Pile footing anf method for erecting it
JPS59187922A (en) Pile foundation
JPH0518414Y2 (en)
JP3388024B2 (en) Floor plate
JPS6383317A (en) Cut-off mechanism at setting section of ground anchor head section
JPS5851109B2 (en) Cloud-resistant construction structure of stone slab walls of buildings such as concrete buildings
JPS5965149A (en) Rebar joint structure
JPS61186644A (en) Fixing of reinforced pillar leg
JPS647162B2 (en)
JPS61146938A (en) Connection of precast reinforced concrete pillar and beam

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term