JPH039483B2 - - Google Patents
Info
- Publication number
- JPH039483B2 JPH039483B2 JP58129313A JP12931383A JPH039483B2 JP H039483 B2 JPH039483 B2 JP H039483B2 JP 58129313 A JP58129313 A JP 58129313A JP 12931383 A JP12931383 A JP 12931383A JP H039483 B2 JPH039483 B2 JP H039483B2
- Authority
- JP
- Japan
- Prior art keywords
- water
- curve
- water storage
- amount
- distribution
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05D—SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
- G05D9/00—Level control, e.g. controlling quantity of material stored in vessel
- G05D9/12—Level control, e.g. controlling quantity of material stored in vessel characterised by the use of electric means
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Automation & Control Theory (AREA)
- Control Of Non-Electrical Variables (AREA)
- Barrages (AREA)
- Feedback Control In General (AREA)
- Flow Control (AREA)
Description
【発明の詳細な説明】
〔発明の利用分野〕
本発明は、上水道施設内の配水池群の貯水量の
制御装置に関する。
〔発明の背景〕
上水道施設において、配水池は、需要の変動を
吸収し、取水や浄水場の運転を平滑化するバツフ
アの役割を果たす。運転員の経験に頼る従来の貯
水量の制御方法では、複数個の配水池の総合的な
運用が困難なため、バツフアとしての機能が十分
に活かしきれなかつた。
〔発明の目的〕
本発明の目的は配水池のこの機能を十分に生か
すことにより、貯水量、浄水場の処理水量、およ
び配水池流入量の変更頻度をできる限り少なくし
て、制御を容易にし、かつ、機器の疲弊を防ぐよ
うな、配水貯群の貯水量制御装置を提供すること
にある。
〔発明の実施例〕
第1図の水系を例にとつて本発明を説明する。
取水場1で取水した原水を、浄水場2で浄化処理
し、配水池3〜6に配分する。取水や浄水場の運
転の平滑化のためには、配水池群の総合的な運用
が必要になる。そこで、配水池3〜6をひとまと
めにとらえ、1つの大きな仮想的な貯水池7を考
える。この仮想的な貯水池のバツフア機能を利用
すると、取水と浄水場運転の平滑化が図れる。
1) 取水計画、浄水場運転計画
第1図に示す系では、取水量と浄水場処理水量
は等しいので、以後、浄水場処理水量についての
み論じる。
各配水池の需要量は、何らかの方法で時系列の
予測値が得られるものとする。仮想的な貯水池7
の需要予測値は、これらの和として得られる。浄
水場処理水量は、各時間で、自身の上下限と、仮
想的な貯水池7の貯水量の上下限制約および需要
を満足するように決定しなければならない。また
仮想的配水池7の貯水量の上限値および下限値は
各池の上限値の総和および下限値の総和により与
えられる。具体的な決定法としては、第2図に示
すように、仮想的配水池7の需要量の累積曲線1
に仮想的貯水池7の貯水量の上限値および下限値
を上乗せして作つた、浄水場処理水量下限曲線2
と、浄水場処理水量上限曲線3とではさまれた帯
状領域を作成し、この領域内を通つて、傾きの変
化回数がほぼ最小の折線4を見出す。この折れ線
は求めるべき浄水場2の処理水量の累積曲線であ
る。折線の傾きが時間あたりの浄水場処理水量と
なる。累積曲線を利用したこの種の折れ線の決定
方法としては、例えば、特願昭50−95867と50−
153315号がある。このようにして各時間の、浄水
場処理水量と、仮想的な貯水池7の貯水量の計画
値を求め、浄水場への取水量又は浄水場での処理
量を制御する。こうすることにより、浄水場の処
理水量の変化を最小にでき、浄水場運転労力の軽
減およびポンプ関連機器の切換回数の低減による
ポンプ疲弊防止を図れる。なお、第2図におい
て、折れ線4と曲線1との差が配水池7の貯水量
の計画値Z(t)である。
2) 計画値のオンライン修正
計画に基づいて運転に入つた場合、需要予測の
狂いが原因で、計画値と実積値の間に偏差が生ず
る。この偏差を計算して、計画値を以下のような
アルゴリズムで修正する。
配水池3〜6の貯水量計測値の総和から、貯水
池7の貯水量の実測値を求める。この実測値の、
貯水量計画値Z(t)からの偏差が、与えられた
許容幅内にあれば、計画の修正は行わない。許容
幅を逸脱したときに、1)のアルゴリズムで、予
測および計画をたて直す。
3) 残余貯水量に基づく配水池流入量制御
1)又は2)で求めた、貯水池7の貯水量計画
値Z(t)と、需要予測値に基づいて、配水池3
〜6の流入量を制御する。配水池のバツフアリン
グ機能を活用し制御操作頻度を減少させるために
は、その貯水量が上下限制約内にある限り、前の
時間の流入量を持続し、上下限制約外に出そうに
なつたときのみ変更するようにすれば良い。しか
し単純にこの方法を用いると、2)により、配水
池3〜6の貯水量の和(仮想的な貯水池7の貯水
量)が制限されているため、配水池間に貯水量の
アンバランスが発生した場合、上下限制約を破る
配水池が出る可能性がある。例えば、次のような
場合である。
例〕貯水池7の貯水量:100
配水池3の貯水量上限:50、下限:20
配水池4の ″ :40、 ″ 20
配水池5の ″ :60、 ″ 30
配水池6の ″ :30、 ″ 10
ここで、配水池5,6の貯水量を、ともに上限
値に等しくした場合、配水池3,4の貯水量の和
を、100−(60+30)=10にしなければならない。
しかし、配水池3,4の貯水量の下限は、それぞ
れ20あるため、配水池3,4は、下限制約を破る
ことになる。
この問題を解決するため、残余貯水量という概
念を導入する。残余貯水量とは、仮想の貯水池7
の貯水量(既決定)から、既に貯水量が決定され
た配水池の貯水量の和を引いた値である。この残
余貯水量を用いて、配水池毎に、貯水量の施設上
の上下限とは別に、新たに上下限を設定し、各配
水池がこれを満足すれば、全ての配水池が、施設
上の上下限を満足することができるようにする。
以下で計算に用いる記号の説明をする。
Z(t):仮想の貯水池7の貯水量の計画値、
Ri(t):残余貯水量i、Vi:配水池i(i=
1〜4)の貯水量の施設上の上下限値、i、
RVi:配水池iの貯水量の、残余貯水量から決
まる上下限値、HVi,LVi:配水池iの貯水量
の、制御上の上下限値(i,i,Vi,R
Viから合成される)(t−1時までの貯水量と流
量は既に決定され、t時の貯水量と流量について
も、配水池6については、既に決定されているも
のとする。(V6t)。配水池5の各種上下限の計算
を以下のように行う。
残余貯水量R5(t)は、
R5(t)=Z(t)−V6(t)
これを用いて、配水池5の貯水量の新たな上下限
値を求める。(図4)。
5=R5(t)−(V3+V4)
RV5=R5(t)−(3+4)
さらに、制御上の上下限値を次式で求める。
HV5=Min(5、5)
LV5=Max(V5,RV5)
このようにして求めたHV5,LV5を配水池5
の制御上の上下限値とする(第3図a,b参照)。
次に配水池5について、t時の流入量として、
(t−1時の流入量を持続した場合の予測貯水量
を求める(需要量の予測値を用いて容易に求め
る)。これがHV5,LV5の制約を満足していれ
ば、t時の流入量を、(t−1時の流入量と等し
い値に決定する。HV5,LV5による制約を満
たしていない場合は、満たすように流入量を変更
する。以上のアルゴリズムで、配水池6から3ま
で順次流入量を決定していく。
最後に、残余貯水量から求まる上下限値を修正
して新たな許容上下限値を求める手段の補足説明
を行う。
<前提>
時刻tの貯水量計画値(全配水池の貯水量の総
和)Z(t)は、1)項及び2)項に既に決定さ
れているものとする。配水池番号をi=1,2,
…,nとし、番号の大きい方から貯水量を決定し
ていくものとし、i=k+1,…,nが既に決定
されているものとする。
<配水池kの許容上下限決手手順>
ステツプ1:配水池kの残余貯水量RKを計算
する。
Rk(t)=Z(t)−o
〓i=k+1
Vi(t) (1)
右辺第2項は既決定貯水量である
ステツプ2:配水池kの残余貯水量から定まる
上下限値を計算する。
k=Rk(t)−k―1
〓i=1
Vi (2)
RVk=Rk(t)−k―1
〓i=1V i
(3)
ステツプ3:(2),(3)式の上下限値を修正して制御
上の新たな許容上下限値を次式で求める。
HVk=Mio{Vk,RVk} (4)
LVk=Max{Vk,RVk} (5)
もし、新たな上下限を満足すれば、すなわち、
次式
LVkVHVk
を満足すれば、式(4),(5)から
VkLVkVHVk k
であるから、施設上の上下限Vk,kを満足する
ことは自明である。
なお、本発明の例において、配水池6は、貯水
量を決定する最初の配水池であり、その決定手順
は以下のようになる。
R6(t)=Z(t)
(既決定の配水池はない) (1)′
6=R6(t)−(V 3+V 4+V 5) (2)′
RV6=R6(t)−(3+4+5) (3)′
HV6=Mio{6,6} (4)′
LV6=Max{V 6,RV 6} (5)′
4) 制御装置
第4図に、本発明による制御装置の一例を示
す。装置名称は、以下の通りである。
1:需要量予測装置
2:浄水場処理水量計算装置
3:計画値記憶装置
4:計画修正判定装置
5〜8:配水池流入量計算装置
図において、実線は情報の流れを、破線は制御
信号の流れを表わすものとする。
装置1は、実績需要量に基づいて複数個の配水
池の総需要量の時系列予測を行う。
装置2は、需要量予測値、予測時点における総
貯水量、貯水量上下限値等の施設条件を入力信号
として、(1)のアルゴリズムにより、取水量、総貯
水量の計画値を計算する。装置3は、装置2で計
算された計画値を記憶する。装置4は、各サンプ
リング時間に以下の計算を行う。総貯水量の計画
値と実績量を入力信号として、(2)のアルゴリズム
により計画値の修正を行うか否かの判定をする。
修正が必要な場合は、装置1に信号を送り、リス
ケジユールに入る。修正が不要な場合は、取水場
浄水場を計画値に従つて制御すると同時に、装置
5〜8を起動する。装置5〜8は、総貯水量計画
値、実績貯水量既計算の他配水池の貯水量を入力
信号として、(3)のアルゴリズムにより流入量の計
算をし、これに基づいて制御する。
〔発明の効果〕
以上述べたように、本発明によれば、取水量、
浄水場の処理水量および配水池流入量の変更頻度
を少なくして制御を容易にできるとともに、機器
の疲弊を防ぐことができる。 DETAILED DESCRIPTION OF THE INVENTION [Field of Application of the Invention] The present invention relates to a control device for the amount of water stored in a group of water distribution reservoirs in a water supply facility. [Background of the Invention] In water supply facilities, water distribution reservoirs play the role of buffers that absorb fluctuations in demand and smooth the operation of water intake and water treatment plants. With conventional water storage control methods that rely on the experience of operators, it is difficult to comprehensively operate multiple water distribution reservoirs, making it impossible to fully utilize their functions as buffers. [Object of the Invention] The purpose of the present invention is to make full use of this function of the water distribution reservoir, thereby minimizing the frequency of changes in the amount of water stored, the amount of water treated at the water treatment plant, and the amount of water flowing into the water distribution reservoir, thereby making control easier. It is an object of the present invention to provide a water storage amount control device for a water distribution storage group, which also prevents equipment fatigue. [Embodiments of the Invention] The present invention will be explained by taking the aqueous system shown in FIG. 1 as an example.
Raw water taken at a water intake plant 1 is purified at a water purification plant 2 and distributed to water distribution reservoirs 3 to 6. In order to smooth the operation of water intake and water treatment plants, comprehensive operation of the distribution reservoir group is required. Therefore, consider the distribution reservoirs 3 to 6 as one large virtual reservoir 7. By using the buffer function of this virtual reservoir, it is possible to smooth water intake and water treatment plant operation. 1) Water intake plan, water treatment plant operation plan In the system shown in Figure 1, the amount of water intake and the amount of water treated at the water treatment plant are equal, so hereafter we will only discuss the amount of water treated at the water treatment plant. It is assumed that the demand for each water reservoir can be predicted in a time-series manner by some method. Virtual reservoir 7
The demand forecast value is obtained as the sum of these values. The amount of water treated by the water purification plant must be determined at each time so as to satisfy its own upper and lower limits, upper and lower limit constraints on the water storage amount of the virtual reservoir 7, and demand. Further, the upper limit and lower limit of the water storage amount of the virtual water distribution reservoir 7 are given by the sum of the upper limit and the sum of the lower limit of each pond. As a specific determination method, as shown in Figure 2, the cumulative demand curve 1 of the virtual water reservoir 7 is used.
Water treatment plant treated water amount lower limit curve 2 created by adding the upper and lower limit values of the water storage amount of the virtual reservoir 7 to
A band-shaped region is created between the curve 3 and the water treatment plant upper limit curve 3, and a broken line 4 with substantially the minimum number of changes in slope is found through this region. This polygonal line is a cumulative curve of the amount of water treated at the water purification plant 2 that should be determined. The slope of the broken line is the amount of water processed by the water treatment plant per hour. Examples of methods for determining this type of broken line using cumulative curves include Japanese Patent Applications 1986-95867 and 1983-
There is number 153315. In this way, planned values for the amount of water treated at the water purification plant and the amount of water stored in the virtual reservoir 7 are determined for each time, and the amount of water taken into the water purification plant or the amount of treatment at the water purification plant is controlled. By doing so, changes in the amount of water treated at the water purification plant can be minimized, reducing the operational effort of the water purification plant and reducing the number of times pump-related equipment is switched, thereby preventing pump fatigue. In addition, in FIG. 2, the difference between the polygonal line 4 and the curve 1 is the planned value Z(t) of the amount of water stored in the water distribution reservoir 7. 2) Online correction of planned values When operations are started based on the plan, deviations occur between the planned values and actual values due to discrepancies in the demand forecast. Calculate this deviation and modify the planned value using the following algorithm. An actual measured value of the amount of water stored in the reservoir 7 is obtained from the sum of the measured values of the amount of water stored in the water distribution reservoirs 3 to 6. Of this actual value,
If the deviation from the planned water storage amount Z(t) is within the given tolerance range, the plan is not revised. When the tolerance range is exceeded, the prediction and plan are revised using the algorithm 1). 3) Control of inflow into the distribution reservoir based on the remaining water storage amount Based on the planned water storage amount Z(t) of the reservoir 7 obtained in 1) or 2) and the predicted demand value, the distribution reservoir 3 is
Control the inflow amount of ~6. In order to reduce the frequency of control operations by utilizing the buffering function of the water distribution reservoir, as long as the water storage volume is within the upper and lower limit constraints, the inflow amount from the previous time is maintained, and when the water is about to go outside the upper and lower limit constraints, it is necessary to It is best to change it only when. However, if this method is simply used, due to 2), the sum of the water storage volumes of reservoirs 3 to 6 (the virtual storage volume of reservoir 7) is limited, resulting in an imbalance in water storage volume between the reservoirs. In this case, there is a possibility that some distribution reservoirs will violate the upper and lower limit constraints. For example, in the following case. Example] Reservoir 7 storage capacity: 100 Reservoir 3 storage capacity upper limit: 50, lower limit: 20 Reservoir 4 ″ : 40, ″ 20 Reservoir 5 ″ : 60, ″ 30 Reservoir 6 ″ : 30, ″ 10 Here, when the water storage amounts of the water distribution reservoirs 5 and 6 are both equal to the upper limit value, the sum of the water storage amounts of the water distribution reservoirs 3 and 4 must be 100−(60+30)=10.
However, since the lower limit of the water storage capacity of the water reservoirs 3 and 4 is 20 each, the water reservoirs 3 and 4 violate the lower limit constraint. To solve this problem, we introduce the concept of residual water storage. The remaining water storage capacity is the amount of water stored in a virtual reservoir7.
It is the value obtained by subtracting the sum of the water storage volumes of the distribution reservoirs whose water storage volumes have already been determined from the water storage volume (already determined). Using this remaining water storage amount, a new upper and lower limit is set for each distribution reservoir, in addition to the facility's upper and lower limits of water storage amount, and if each distribution reservoir satisfies this, all distribution reservoirs are The upper and lower limits above can be satisfied. The symbols used in calculations are explained below. Z(t): planned value of water storage amount of virtual reservoir 7,
Ri(t): Residual water storage amount i, Vi : Distribution reservoir i (i=
1 to 4) Facility upper and lower limits of water storage capacity, i,
RVi: Upper and lower limits of water storage in reservoir i determined from the remaining water storage, HVi, LVi: Control upper and lower limits of water storage in reservoir i (i, i, V i, R
(Synthesized from Vi) (It is assumed that the water storage amount and flow rate up to time t-1 have already been determined, and the water storage amount and flow rate at time t have already been determined for water distribution reservoir 6. (V6t) The various upper and lower limits of the water distribution reservoir 5 are calculated as follows. The remaining water storage amount R5 (t) is: R5 (t) = Z (t) - V6 (t) Using this, the water storage volume of the water distribution reservoir 5 is Find the new upper and lower limits for the amount (Figure 4). 5=R5(t)-( V3 + V4 ) RV5 =R5(t)-(3+4) Furthermore, the upper and lower limits for control can be calculated using the following formula. HV5=Min(5, 5) LV5=Max( V 5, RV 5) HV5 and LV5 obtained in this way are calculated as follows.
(See Figure 3 a and b). Next, regarding the water distribution reservoir 5, as the inflow amount at time t,
(Find the predicted water storage volume when the inflow rate at time t-1 is maintained (easily determined using the predicted value of demand). If this satisfies the constraints of HV5 and LV5, then the inflow volume at time t is determined to be equal to the inflow amount at time t-1. If the constraints by HV5 and LV5 are not satisfied, change the inflow amount so as to satisfy them. Using the above algorithm, The inflow amount is determined.Finally, we will provide a supplementary explanation of the method for determining new allowable upper and lower limits by correcting the upper and lower limits determined from the remaining water storage amount. <Assumptions> It is assumed that the total amount of water stored in the distribution reservoir (Z(t)) has already been determined in paragraphs 1) and 2). Reservoir number i = 1, 2,
..., n, and the water storage amount is determined from the larger number, and it is assumed that i=k+1, ..., n have already been determined. <Procedure for determining the allowable upper and lower limits of water distribution reservoir k> Step 1: Calculate the remaining water storage amount R K of water distribution reservoir k. R k (t)=Z(t)− o 〓 i=k+1 V i (t) (1) The second term on the right side is the determined water storage amount. Step 2: The amount determined from the remaining water storage amount of distribution reservoir k Calculate the lower limit. k = R k (t) − k ― 1 〓 i=1 V i (2) RV k = R k (t) − k ― 1 〓 i=1V i (3) Step 3: (2), (3) The upper and lower limits in the equation are corrected to find new allowable upper and lower limits for control using the following equation. HV k = M io {V k , RV k } (4) LV k = Max {V k , RV k } (5) If the new upper and lower limits are satisfied, that is,
If the following formula LV k VHV k is satisfied, then V k LV k VHV k k from formulas (4) and (5), so it is obvious that the upper and lower limits V k and k on the facility are satisfied. In the example of the present invention, the water distribution reservoir 6 is the first water distribution reservoir whose water storage amount is determined, and the determination procedure is as follows. R 6 (t) = Z (t) (There is no determined distribution reservoir) (1)' 6 = R 6 (t) - ( V 3 + V 4 + V 5 ) (2)' RV 6 = R 6 (t) - ( 3 + 4 + 5 ) (3)' HV 6 = M io { 6 , 6 } (4)' LV 6 = Max { V 6 , RV 6 } (5)' 4) Control device No. FIG. 4 shows an example of a control device according to the present invention. The device names are as follows. 1: Demand forecast device 2: Water treatment plant treated water amount calculation device 3: Planned value storage device 4: Plan modification determination device 5-8: Water reservoir inflow calculation device In the figure, the solid line represents the flow of information, and the broken line represents the control signal. shall represent the flow of The device 1 performs time-series prediction of the total demand of a plurality of water reservoirs based on the actual demand. The device 2 calculates the planned values of the water intake amount and the total water storage amount using the algorithm (1) using the facility conditions such as the predicted demand value, the total water storage amount at the time of the prediction, and the upper and lower limits of the water storage amount as input signals. Device 3 stores the planned values calculated by device 2. The device 4 performs the following calculations at each sampling time. Using the planned value and actual amount of total water storage as input signals, it is determined whether or not to modify the planned value using the algorithm (2).
If correction is necessary, a signal is sent to device 1 to enter rescheduling. If no correction is necessary, the water intake and water purification plants are controlled according to the planned values, and at the same time, the devices 5 to 8 are activated. The devices 5 to 8 calculate the inflow amount using the algorithm (3) using the planned total water storage amount, the calculated actual water storage amount, and the water storage amount of the distribution reservoir as input signals, and control based on this. [Effect of the invention] As described above, according to the present invention, the amount of water intake,
It is possible to reduce the frequency of changes in the amount of water treated at the water treatment plant and the amount of water flowing into the water distribution reservoir, making control easier and preventing equipment fatigue.
第1図は本発明をする水系の一例の構成図、第
2図および第3図は本発明を説明するための説明
図、第4図は本発明による貯水量制御装置の一実
施例の構成図を示す。
2:浄水場処理水量計算装置、5〜8…配水池
流入量計算装置。
FIG. 1 is a configuration diagram of an example of a water system according to the present invention, FIGS. 2 and 3 are explanatory diagrams for explaining the present invention, and FIG. 4 is a configuration diagram of an embodiment of a water storage amount control device according to the present invention. Show the diagram. 2: Water treatment plant treated water amount calculation device, 5 to 8... Water reservoir inflow amount calculation device.
Claims (1)
浄水場からなる配水池群の貯水量制御装置におい
て、上記配水池の各々における予測需要量の総和
の経時的変化である予測総需要量累積曲線を決定
する手段と、上記複数の配水池の貯水量の許容下
限値の総和を上記予測総需要累積曲線に加算して
浄水場の累積処理水量下限曲線を決定する手段
と、上記複数の配水池の貯水量の許容上限値の総
和を、上記予測総需要量累積曲線に加算して浄水
場の累積処理水量上限曲線を決定する手段と該浄
水場の処理水量を、該処理水量の累積曲線が、上
記浄水場累積処理水量下限曲覧と浄水場累積処理
水量上限曲線の間に位置する折れ線であつて、折
れ曲がり回数がほぼ最小の折れ線となるごとく決
定する手段と、上記予測需要曲線からすでに貯水
量の決定された配水池の貯水量の和を差し引いた
残余貯水量にもとづき上記許容下限値と許容上限
値とを修正し、修正された値に応じて上記折れ線
を変更し、変更された折れ線となるごとく決定さ
れた処理水量を該浄水場から該複数の配水部に送
水する手段とからなることを特徴とする配水池群
の貯水量制御装置。1. In a water storage amount control device for a distribution reservoir group consisting of a plurality of distribution reservoirs and a water purification plant for supplying water to the distribution reservoirs, the predicted total demand amount is the change over time of the sum of the predicted demand amounts in each of the above-mentioned distribution reservoirs. means for determining a cumulative curve; and means for determining a cumulative water treatment plant lower limit curve by adding the sum of allowable lower limit values of water storage amounts of the plurality of water distribution reservoirs to the predicted total demand cumulative curve; Means for determining the cumulative treated water volume upper limit curve of the water treatment plant by adding the sum of the allowable upper limit values of the water storage volume of the water distribution reservoirs to the above-mentioned predicted total demand cumulative volume curve; Means for determining the curve so that the curve is a polygonal line located between the water treatment plant cumulative water treatment lower limit curve and the water treatment plant cumulative treatment water upper limit curve, and the number of bends is approximately the minimum, and based on the predicted demand curve. The above permissible lower limit value and allowable upper limit value are corrected based on the remaining water storage amount after subtracting the sum of the water storage amounts of the distribution reservoirs for which the water storage amount has already been determined, and the above polygonal line is changed according to the corrected values. 1. A water storage amount control device for a water distribution reservoir group, comprising means for sending a determined amount of treated water along a polygonal line from the water purification plant to the plurality of water distribution sections.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12931383A JPS5932014A (en) | 1983-07-18 | 1983-07-18 | Water storage volume control device for distribution reservoir group |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12931383A JPS5932014A (en) | 1983-07-18 | 1983-07-18 | Water storage volume control device for distribution reservoir group |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5932014A JPS5932014A (en) | 1984-02-21 |
| JPH039483B2 true JPH039483B2 (en) | 1991-02-08 |
Family
ID=15006478
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12931383A Granted JPS5932014A (en) | 1983-07-18 | 1983-07-18 | Water storage volume control device for distribution reservoir group |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5932014A (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62160511A (en) * | 1986-01-09 | 1987-07-16 | Fuji Electric Co Ltd | Water level controller for distributing reservoir |
| JPS63101905A (en) * | 1986-10-20 | 1988-05-06 | Toshiba Corp | Operation monitor and control equipment for filter plant |
| JPH01204113A (en) * | 1988-02-09 | 1989-08-16 | Yokogawa Electric Corp | Method for controlling water quantity of purification plant |
| JP5476275B2 (en) * | 2010-11-05 | 2014-04-23 | 株式会社日立製作所 | Water distribution plan prediction system, prediction method thereof, and program thereof |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5220402A (en) * | 1975-08-08 | 1977-02-16 | Hitachi Ltd | Control system of pumps based on operation plan |
-
1983
- 1983-07-18 JP JP12931383A patent/JPS5932014A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5932014A (en) | 1984-02-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4180083A (en) | System for controlling flow rate in pipelines | |
| Gelormino et al. | Model-predictive control of a combined sewer system | |
| SE1450161A1 (en) | System and procedure for optimizing operation of a water network | |
| JPH039483B2 (en) | ||
| JP2001214470A (en) | Optimal water operation control device | |
| JPS5952448B2 (en) | Operation control method for water supply system | |
| JP2730188B2 (en) | Water pump predictive operation controller | |
| JP5783935B2 (en) | Pump operation plan support device and water treatment system | |
| JPS61263688A (en) | Device for controlling use of water in water purification plant | |
| JP5242084B2 (en) | Received flow rate calculation method and apparatus | |
| JPH0352001A (en) | Predictive operation controller for conveying pump | |
| JPS6132683B2 (en) | ||
| JP3397475B2 (en) | Water operation planning device | |
| JP3417766B2 (en) | Water supply planning support device and water supply control system | |
| JPH027685B2 (en) | ||
| JPS5944643B2 (en) | How to operate a water supply system in a water supply system | |
| JP3577538B2 (en) | Method and apparatus for controlling flow rate of multiple filtration ponds in a water purification plant | |
| JPS6033613A (en) | Water intake control system of water purifying plant | |
| JPS61182102A (en) | Controller for filtration plant | |
| JPS63101905A (en) | Operation monitor and control equipment for filter plant | |
| JP2014002535A (en) | Water operation support apparatus, water operation support method and program | |
| JP2025040013A (en) | Water treatment plant system, water treatment plant operation support system and water treatment plant operation support device | |
| Foo et al. | Centralised and decentralised control of the Broken river | |
| Sabet et al. | Model aggregation for California state water project | |
| JPH055128B2 (en) |