Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0437882B2 - - Google Patents
[go: Go Back, main page]

JPH0437882B2 - - Google Patents

Info

Publication number
JPH0437882B2
JPH0437882B2 JP26216284A JP26216284A JPH0437882B2 JP H0437882 B2 JPH0437882 B2 JP H0437882B2 JP 26216284 A JP26216284 A JP 26216284A JP 26216284 A JP26216284 A JP 26216284A JP H0437882 B2 JPH0437882 B2 JP H0437882B2
Authority
JP
Japan
Prior art keywords
cell
filling
sand
earth
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP26216284A
Other languages
Japanese (ja)
Other versions
JPS61142219A (en
Inventor
Fukuhiro Nishihira
Tsutomu Inaba
Yoshiteru Dobashi
Seiji Wakamatsu
Akihisa Kato
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Kokan Ltd filed Critical Nippon Kokan Ltd
Priority to JP26216284A priority Critical patent/JPS61142219A/en
Publication of JPS61142219A publication Critical patent/JPS61142219A/en
Publication of JPH0437882B2 publication Critical patent/JPH0437882B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/30Foundations made with permanent use of sheet pile bulkheads, walls of planks, or sheet piling boxes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Revetment (AREA)

Description

【発明の詳細な説明】 『産業上の利用分野』 本発明は、大水深セルの建設方法に関するもの
である。
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a method of constructing a deep water cell.

『従来の技術』 防波堤及び護岸を建設する方法としては、ケー
ソン工法・セル工法等が一般的な工法として知ら
れている。
``Prior Art'' Caisson construction method, cell construction method, etc. are known as general construction methods for constructing breakwaters and seawalls.

これらの渋来工法の内、セル工法はさらに鋼矢
板セル工法と鋼板セル工法とに分けられるが、セ
ル工法に共通する問題点としては、セル内に詰め
る中詰土砂の側圧によつて、セルの直径及び高さ
に比例してセル殻に大きな引張応力を生じるの
で、その設置深度に限界があることである。現在
のところセル工法ではその限界が約20mであり、
これ以上の水深でのセル建設は不可能であるとさ
れている。
Among these Shiburi construction methods, the cell method can be further divided into the steel sheet pile cell method and the steel plate cell method, but the common problem with the cell method is that the cells are damaged due to the lateral pressure of the filling earth and sand packed into the cells. Since a large tensile stress is generated in the cell shell in proportion to the diameter and height of the cell, there is a limit to its installation depth. Currently, the limit of cell construction method is approximately 20m.
It is believed that cell construction at deeper water depths is impossible.

『発明が解決しようとする問題点』 上記欠点を解決すべく、鋼板セル工法でセル殻
の鋼板を厚くして対処したり、セル殻を二重構造
となして対処する(特許出願公開昭和56年第
125512号)こととも可能であるが、鋼板を厚くす
るのは重量が増大し特別な大型クレーンを必要と
するほかに、鋼板自体も特注製造しなければなら
ず施工上の観点から現実的とは考えられないし、
また、セル殻を二重構造とすると、該セル殻の打
設に困難性が生じると共に、打設に要する工期も
倍増することになる。したがつて、大水深の場合
は、先ず水深に応じて所定の高さの基礎マウンド
を造成して該基礎マウンド上にケーソンまたはセ
ルを構築する所謂混成堤が最も汎用されている
が、この工法は水深に応じて基礎マウンドが莫大
なものとなる欠点を有している。
"Problems to be Solved by the Invention" In order to solve the above-mentioned drawbacks, the steel plate cell method is used to thicken the steel plate of the cell shell, or the cell shell has a double structure. year number
125512), but making the steel plate thicker would increase its weight and require a special large crane, and the steel plate itself would have to be custom-manufactured, making it impractical from a construction standpoint. I can't think of it,
Further, if the cell shell has a double structure, it becomes difficult to cast the cell shell, and the time required for casting the cell shell also doubles. Therefore, in the case of large water depths, the most commonly used method is to first create a foundation mound with a predetermined height depending on the water depth, and then construct a caisson or cell on top of the foundation mound. has the disadvantage that the foundation mound becomes enormous depending on the water depth.

また、中詰土砂の調達はセルの建設地点が沖合
に出る程困難となり、それにともなつて経費が嵩
む欠点を有している。
In addition, procurement of filler soil becomes more difficult as the cell construction site moves further offshore, which also has the drawback of increasing costs.

そこで本発明は、上記欠点に鑑みなされたもの
で、大水深地点でのセル建設を可能にする方法
と、良質な中詰土砂の入手が困難な地点でも中詰
を容易に可能にする方法を提供することを目的と
したものである。
Therefore, the present invention was made in view of the above-mentioned drawbacks, and provides a method that enables cell construction at deep water points, and a method that easily enables cell filling even in locations where it is difficult to obtain high-quality filling soil. It is intended to provide.

『問題点を解決するための手段』 上記の目的に沿い、先述特許請求の範囲を要旨
とする本発明の構成は前述問題点を解決するため
に、建設場所にセルを設置し、このセル内には水
中輸送管を使用してその最下部より硬化材と添加
剤とを混合した中詰土砂を投入し、上記中詰土砂
は、投入速度に対応して硬化開始時間を調整する
ことで、上層未硬化部の中詰土砂の側圧によつて
セル殻に生じる引張応力度がセル殻の全体にわた
り許容応力度を越えないようになしたことを特徴
とする技術的手段を講じたものである。
``Means for Solving the Problems'' In accordance with the above object, the structure of the present invention, which is summarized in the above-mentioned claims, is to solve the above-mentioned problems by installing a cell at a construction site, and inside the cell. Filling soil mixed with a hardening material and additives is introduced from the bottom of the pipe using an underwater transport pipe, and the curing start time of the above filling soil is adjusted according to the feeding speed. A technical measure is taken in which the tensile stress generated in the cell shell due to the lateral pressure of the filling earth and sand in the upper unhardened part does not exceed the allowable stress throughout the cell shell. .

『実施例』 次に、本発明の実施例を第1図および第2図に
従つて説明すれば以下の通りである。
``Example'' Next, an example of the present invention will be described below with reference to FIGS. 1 and 2.

図示実施例は、直径30mの鋼矢板セル7をすで
に造成してある基礎マウンド4の上に設置する例
で、該基礎マウンド4上の水深は40mである。な
お、この鋼矢板セル7は、鋼板を筒状に成形した
鋼板セルであつてもよいことは無論である。
The illustrated embodiment is an example in which a steel sheet pile cell 7 with a diameter of 30 m is installed on an already constructed foundation mound 4, and the water depth above the foundation mound 4 is 40 m. In addition, it goes without saying that this steel sheet pile cell 7 may be a steel plate cell formed by forming a steel plate into a cylindrical shape.

先ず、本実施例は、図示しない陸上の基地で組
立てられた鋼矢板セル7を、同じく図示しない台
船上に載せて海上を運搬し海底5に造成した基礎
マウンド4上の設置地点で図2に示す作業台船8
に引き渡すか、該作業台船8で海上に浮かべたま
ま陸上の基地から該設置地点まで曳航する。この
際、鋼矢板セル7の浮力は、鋼矢板セル7に図示
しない鋼製フロートを転用可能に取付けて得れば
よい。
First, in this embodiment, the steel sheet pile cells 7 assembled at a base on land (not shown) are placed on a barge (also not shown), transported over the sea, and installed at the installation point on the foundation mound 4 constructed on the seabed 5 as shown in FIG. Work barge 8 shown
Alternatively, the work barge 8 can tow it from the land base to the installation point while floating on the sea. At this time, the buoyancy of the steel sheet pile cell 7 may be obtained by attaching a steel float (not shown) to the steel sheet pile cell 7 in a reusable manner.

上記作業台船8については詳しくは述べない
が、門型クレーン12、住居及び指令室13、硬
化材サイロ9、混合プラント10、スラリーポン
プ及び含水比調整装置11等を備えてなる。
Although the work barge 8 will not be described in detail, it is equipped with a gate type crane 12, a residence and control room 13, a hardening material silo 9, a mixing plant 10, a slurry pump, a water content ratio adjusting device 11, and the like.

そして、該鋼矢板セル7は、所望設置地点で作
業台船8に抱えられるようにして基礎マウンド4
に設置される。
Then, the steel sheet pile cell 7 is mounted on the foundation mound 4 so as to be held by the work barge 8 at a desired installation point.
will be installed in

次いで、該鋼矢板セル7に、トレミー管と称さ
れるもので代表される水中輸送管6を建込む。こ
の水中輸送管6の本数は該鋼矢板セル7の大き
さ、混合プラント10の能力、後述中詰土砂の硬
化開始時間によつて決まる。そして、この鋼矢板
セル7内には水中輸送管6を使用してその最下部
より硬化材と添加剤とを混合した中詰土砂を投入
する。
Next, an underwater transport pipe 6 typified by what is called a tremie pipe is built into the steel sheet pile cell 7 . The number of underwater transport pipes 6 is determined by the size of the steel sheet pile cell 7, the capacity of the mixing plant 10, and the hardening start time of the filling earth and sand, which will be described later. Then, filling earth and sand mixed with a hardening material and additives are introduced into the steel sheet pile cell 7 from the lowest part thereof using an underwater transport pipe 6.

上記硬化材としてはセメント、石灰、スラグ、
特殊セメント等が考えられるが、添加材との組合
わせで早強性を有するものであれば従来公知など
の硬化材でも構わない。但し、一般的な海象条
件、急速施工を考えて硬化時間は24時間程度と考
えられるので、この条件に適合しやすいものを適
宜選定すればよい。また、上記添加剤についても
同様であり、硬化材との組合わせで早強性を有す
るものであれば何であつてもよいが、耐塩性、流
動性、早強性、を有するものであることが望まし
い。
The hardening materials mentioned above include cement, lime, slag,
A special cement or the like may be used, but any conventionally known hardening material may be used as long as it has early strength when combined with additives. However, considering general sea conditions and rapid construction, the curing time is considered to be about 24 hours, so it is best to select a material that easily meets these conditions. The same applies to the above additives, and any additive may be used as long as it has early strength when combined with the hardening material, but it must have salt resistance, fluidity, and early strength. is desirable.

さらに、上記中詰土砂は、投入速度に対応して
硬化開始時間を調整することで、上層未硬化部の
中詰土砂の側圧によつて鋼矢板セル7よりなるセ
ル殻に生じる引張応力度が該セル殻の全体にわた
り許容応力度を越えないようになしてある。
Furthermore, by adjusting the hardening start time of the filling soil in accordance with the charging speed, the tensile stress generated in the cell shell made of the steel sheet pile cells 7 due to the lateral pressure of the filling soil in the upper unhardened portion can be reduced. The entire cell shell is designed not to exceed an allowable stress level.

ここで該セル殻に働く引張応力度から許容応力
度を満足する中詰土砂の高さを計算する。
Here, the height of the filling soil that satisfies the allowable stress level is calculated from the tensile stress level acting on the cell shell.

中詰土砂の単位体積重量:γ(t/m3) 中詰土砂の高さ :H(m) 鋼矢板セルの半径 :r(m) 静止土圧係数 :Ko (静止土圧係数は中詰砂の内部摩擦角Φをも
ちいてKo=tanΦとする。) Φ=30゜、γ=1.5t/m3、r=15mとして、Ko
=約0.6であるから中詰土砂の深さH(m)において
セル殻の許容応力度を1900kgf/cm2とすれば、鋼
矢板セル7の厚み1.27cmとして高さ1m分の許容
張力は、 1.27×100×1900≒241(tf) となる。
Unit volume weight of filling earth and sand: γ (t/m 3 ) Height of filling earth and sand: H (m) Radius of steel sheet pile cell: r (m) Static earth pressure coefficient: Ko (Static earth pressure coefficient is Using the internal friction angle Φ of sand, let Ko = tanΦ.) Assuming Φ = 30°, γ = 1.5t/m 3 , r = 15m, Ko
= approximately 0.6, so if the allowable stress of the cell shell is 1900 kgf/cm 2 at the depth H (m) of the filling earth and sand, the allowable tension for a height of 1 m when the thickness of the steel sheet pile cell 7 is 1.27 cm is: 1.27×100×1900≒241(tf).

一方、セル殻に生じる引張応力は、 Ko・γ・H・rであるから、 H=241/Ko・γ・r≒17.9(m)となる。 On the other hand, the tensile stress generated in the cell shell is Since Ko・γ・H・r, H=241/Ko・γ・r≒17.9(m).

実際にはこのHの値は、セル殻の滑動(波力、
自重等による水平移動)、転倒(セル殻の波力に
よる回転)、せん断(セル殻内の中詰土砂のせん
断破壊)等の安定を計算し、さらに小さな値とな
るが、計算の都合上H=17.9mで考えると、結
局、従来の工法で上記のセル殻を使用した場合
は、このHの値である17.9m以上の水深のセル建
設は不可能ということになつてしまうが、本発明
法では、図1に示すように基礎マウンド4の上に
鋼矢板セル7が載り、該鋼矢板セル7の中詰土砂
はすでに硬化した部分である硬化部3といまだ硬
化していない部分である未硬化部2に分かれてい
る。この2つの部分のうち、側圧によりセル殻に
引張応力度を生じせしめるのは、未硬化部2であ
る。したがつて、未硬化部2の高さDが17.9mを
越えなければ、前記の計算によりセル殻は安全で
ある。そして、実際の施工時の許容応力度の割り
増し(短期的な鋼構造の場合1.5倍の割り増しで
計算する)を考えれば、該未硬化部2の高さDは
さらに高くすることが可能なものである。
In reality, the value of H is determined by the sliding of the cell shell (wave force,
The stability against horizontal movement due to its own weight, etc.), overturning (rotation due to wave force of the cell shell), and shearing (shear failure of the packed earth and sand inside the cell shell) is calculated, and the value is even smaller, but for the sake of calculation, H = 17.9m, if the above-mentioned cell shell was used with the conventional construction method, it would be impossible to construct a cell at a water depth greater than 17.9m, which is the value of H. In the method, as shown in Fig. 1, a steel sheet pile cell 7 is placed on top of a foundation mound 4, and the filling soil in the steel sheet pile cell 7 is divided into a hardened part 3, which is an already hardened part, and a part which is not yet hardened. It is divided into an uncured part 2. Of these two parts, it is the unhardened part 2 that causes tensile stress to be generated in the cell shell due to lateral pressure. Therefore, as long as the height D of the uncured portion 2 does not exceed 17.9 m, the cell shell is safe according to the above calculation. Considering the additional allowable stress during actual construction (calculated as a 1.5 times additional increase in the case of short-term steel structures), the height D of the unhardened portion 2 can be made even higher. It is.

このように本発明によると鋼矢板セル7の径、
中詰砂の単位体積重量と内部摩擦角によつて決ま
るHm以内に、未硬化部2の高さDを押さえるこ
とにより、大水深のセルの建設が可能となるもの
である。
In this way, according to the present invention, the diameter of the steel sheet pile cell 7,
By keeping the height D of the uncured portion 2 within Hm determined by the unit volume weight of the filling sand and the internal friction angle, it becomes possible to construct cells in large water depths.

上述した方法で未硬化部2の高さDを今回の場
合はH=17.9m以下に保つて中詰作業を続け、セ
ル天端まで中詰を完了させる。中詰作業は図2に
概略図示する作業台船8と台船上のプラントを用
いて行なうが、硬化材サイロ9からの硬化材と中
詰土砂を混合プラント10で混合し、スラリーポ
ンプで水中輸送管6を通して鋼矢板セル7底部に
送り込む。このとき、水中輸送管6の先端が未硬
化部2に1.5m程度入つているのは、一般の水中
コンクリート打ち施工と同様である。
Using the method described above, the filling operation is continued while keeping the height D of the uncured portion 2 below H=17.9 m in this case, and the filling is completed to the top of the cell. The filling work is carried out using a work barge 8 and a plant on the barge as schematically shown in FIG. It is fed into the bottom of the steel sheet pile cell 7 through the pipe 6. At this time, the tip of the underwater transport pipe 6 is about 1.5 m into the uncured portion 2, as in general underwater concrete pouring.

なお、該中詰土砂の配合は前述したように一種
類に特定されるものではないが今回の実施例をあ
げると、砂分が35%シルト及び粘土分が65%含水
比が260%の中詰土砂1.2m3に対し、硬化材として
水滓スラグを240Kgと消石灰を36Kg、添加剤とし
てケイ酸ソーダを12混合し撹拌したものを使用
した。この配合では、一日で固化してその時点の
1軸圧縮強度は2.6Kgf/cm2に達するものであつ
た。
As mentioned above, the composition of the filling soil is not specific to one type, but in this example, the sand content is 35%, the silt and clay content is 65%, and the water content is 260%. A mixture of 240 kg of water slag as a hardening agent, 36 kg of slaked lime, and 12 kg of sodium silicate as an additive was mixed and stirred for 1.2 m 3 of packed earth and sand. This formulation solidified in one day, and the unconfined compressive strength at that point reached 2.6 kgf/cm 2 .

さらに、該中詰土砂を陸上から運搬しない場合
は、周囲の海底からスラリーポンプで吸い上げ、
ふるい等で水分を調整して混合プラント10に送
り、以下前述と同じ方法を取るものである。
Furthermore, if the packed soil is not transported from land, it can be sucked up from the surrounding seabed using a slurry pump.
The water content is adjusted using a sieve or the like and sent to the mixing plant 10, and the same method as described above is followed.

『発明の効果』 本発明は上記のごときであるため、従来工法の
セル建設可能水深よりもずつと大きな水深のセル
の建設が可能である。これはセルの半径が大きい
程効果が大きい。また、建設終了に伴いセルの中
詰土砂は固化するのでせん断抵抗の大きな安全性
の高いセルが建設できる。このように本発明は、
大水深のセル建設及びその急速施工に多大なる貢
献をする大水深セルの建設方法を提供できるもの
である。
[Effects of the Invention] Since the present invention is as described above, it is possible to construct a cell at a water depth that is much larger than that possible with conventional construction methods. This effect becomes greater as the radius of the cell becomes larger. Furthermore, as the earth and sand filling the cell solidifies upon completion of construction, a highly safe cell with high shear resistance can be constructed. In this way, the present invention
It is possible to provide a method for constructing a deep water cell that greatly contributes to the construction of a deep water cell and its rapid construction.

また、セル周辺の海底土砂の利用により経済的
でかつ省資源の大水深セルの建設方法を提供する
ことができるものである。
Furthermore, it is possible to provide an economical and resource-saving method for constructing a deep water cell by using seabed sediment around the cell.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は中詰土砂の投入説明図断面図、第2図
本発明法を施工する作業台船の全体斜視図であ
る。 2〜未硬化部、3〜硬化部、4〜基礎マウン
ド、5〜海底、6〜水中輸送管、7〜鋼矢板セ
ル、8〜作業台船、9〜硬化材サイロ、10〜混
合プラント、11〜スラリーポンプ及び含水比調
整装置、12〜門型クレーン、13〜住居及び指
令室。
Fig. 1 is a sectional view for explaining the charging of filling earth and sand, and Fig. 2 is an overall perspective view of a work barge for carrying out the method of the present invention. 2 - uncured part, 3 - hardened part, 4 - foundation mound, 5 - seabed, 6 - underwater transport pipe, 7 - steel sheet pile cell, 8 - work barge, 9 - hardened material silo, 10 - mixing plant, 11 - Slurry pump and water content ratio adjustment device, 12 - Portal crane, 13 - Residence and control room.

Claims (1)

【特許請求の範囲】 1 建設場所にセルを設置し、このセル内には水
中輸送管を使用してその最下部より硬化材と添加
剤とを混合した中詰土砂を投入し、 上記中詰土砂は、投入速度に対応して硬化開始
時間を調整することで、上層未硬化部の中詰土砂
の側圧によつてセル殻に生じる引張応力度がセル
殻の全体にわたり許容応力度を越えないようにな
したことを特徴とする大水深セルの建設工法。 2 特許請求の範囲第1項記載の中詰土砂は、セ
ル建設場所周辺の海底から採取したもので、海上
の作業船で含水比を調整したものであることを特
徴とする特許請求の範囲第1項記載の大水深セル
の建設方法。
[Scope of Claims] 1. A cell is installed at a construction site, and filling soil mixed with hardening material and additives is introduced into the cell from the bottom of the cell using an underwater transport pipe, and the above-mentioned filling material is By adjusting the curing start time of the earth and sand in accordance with the feeding speed, the tensile stress generated in the cell shell due to the lateral pressure of the filling earth and sand in the upper unhardened area does not exceed the allowable stress level throughout the cell shell. A construction method for deep water cells characterized by the following. 2 The filling earth and sand described in claim 1 is collected from the seabed around the cell construction site, and the water content ratio is adjusted using a work boat at sea. A method for constructing a deep water cell according to item 1.
JP26216284A 1984-12-12 1984-12-12 Construction of cell at great deep of water Granted JPS61142219A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26216284A JPS61142219A (en) 1984-12-12 1984-12-12 Construction of cell at great deep of water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26216284A JPS61142219A (en) 1984-12-12 1984-12-12 Construction of cell at great deep of water

Publications (2)

Publication Number Publication Date
JPS61142219A JPS61142219A (en) 1986-06-30
JPH0437882B2 true JPH0437882B2 (en) 1992-06-22

Family

ID=17371921

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26216284A Granted JPS61142219A (en) 1984-12-12 1984-12-12 Construction of cell at great deep of water

Country Status (1)

Country Link
JP (1) JPS61142219A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63130817A (en) * 1986-11-21 1988-06-03 Ohbayashigumi Ltd Underwater large-size coffering structure
JPS6475710A (en) * 1987-09-14 1989-03-22 Nippon Steel Corp Manufacture of prestressed structure
JP5557052B2 (en) * 2011-08-31 2014-07-23 新日鐵住金株式会社 Embankment
JP5510692B1 (en) * 2013-09-04 2014-06-04 東洋建設株式会社 Steel temporary deadline installation method and low-air mobile crane carrier used therefor

Also Published As

Publication number Publication date
JPS61142219A (en) 1986-06-30

Similar Documents

Publication Publication Date Title
EP0179924A1 (en) Unit marine structure
JPS60242219A (en) Formation of offshore seabed mound
JPH0437882B2 (en)
JP2012180669A (en) Breakwater reinforcing method and reinforced breakwater
JPS61155514A (en) Mass concrete pouring method
SU1027316A1 (en) Bullwark on weak soil
JP2815492B2 (en) How to build an underwater foundation
JP2556380B2 (en) Construction method of revetment structure
JPS6340024A (en) Pile-type caisson work
JPS5931774Y2 (en) Mixed foundation rubble mound
JP2655322B2 (en) Construction method of revetment structure
JPH0323689B2 (en)
JP2676779B2 (en) Cylindrical caisson
JP2546110B2 (en) Levee structure using excavated sludge and its construction method
JPS5934331A (en) How to build a sewage treatment facility
JP2026020618A (en) Waterbed ground improvement method and waterbed ground improvement structure
JP2847148B2 (en) Submerged floating ground and construction method
JPS5911006B2 (en) Port structures such as quays on cement-based mixed treated ground and their construction method
JP2847146B2 (en) Water casting structure and construction method thereof
CN85104325A (en) Method of building piers on the seabed
JPH03197706A (en) Prevention of coastal erosion
JPS58127834A (en) Setting of caisson
Alikhani et al. Design and construction of a caisson quay wall in the south pars port project
JPS61130512A (en) Construction work of cell revetment
JPH05118015A (en) Construction of pile-type marine structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees