JPH0544519B2 - - Google Patents
Info
- Publication number
- JPH0544519B2 JPH0544519B2 JP62103175A JP10317587A JPH0544519B2 JP H0544519 B2 JPH0544519 B2 JP H0544519B2 JP 62103175 A JP62103175 A JP 62103175A JP 10317587 A JP10317587 A JP 10317587A JP H0544519 B2 JPH0544519 B2 JP H0544519B2
- Authority
- JP
- Japan
- Prior art keywords
- box
- work boat
- existing
- lifting device
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は沈埋函の沈設工法及びその工法を実施
する作業船に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for sinking a submerged box and a work boat for carrying out the method.
[従来技術とその問題点]
函体を沈設して水面下にトンネルを構築するに
は、作業船を函体の沈設場所に移動させて、作業
船をアンカーにより固定し、作業船のクレーンを
用いて函体を所要箇所に沈設する沈埋函の沈設工
法が多く採用されていた。[Prior art and its problems] In order to construct a tunnel under water by sinking a box, a work boat is moved to the place where the box is to be sunk, the work boat is fixed with an anchor, and the crane of the work boat is moved. The submerged box construction method, in which the box is sunk in the required location, was often adopted.
しかしながら、従来のかかる工法による場合
は、作業船を固定するためのアンカースペースが
必要であり、また既設函体とのセンター合せに多
くの人手と時間を要する欠点があつた。 However, this conventional construction method requires an anchor space to secure the work boat, and has the disadvantage that it requires a lot of manpower and time to center the work boat.
すなわち、河川又は海洋における作業船の作業
は波浪による揺動や潮流による横移動および潮の
干満による上下方向の移動が生じ、そのために函
体の沈制位置の決定が困難であつた。したがつて
沈埋函を既設のものに隣接して沈設する作業が面
倒であつた。 That is, when working on a workboat in a river or ocean, the vessel is shaken by waves, moved horizontally by currents, and moved vertically by the ebb and flow of the tide, making it difficult to determine the sinking position of the box. Therefore, the work of immersing the immersed box adjacent to the existing one was troublesome.
[発明の目的]
したがつて本発明の目的は、沈埋函を比較的に
正確に位置決めして沈設できしかも多くの人手と
時間を必要としない沈埋函の沈設工法とその工法
を実施する作業船を提供するにある。[Object of the Invention] Therefore, an object of the present invention is to provide a method for sinking a submerged box that allows relatively accurate positioning and submersion of the submerged box, and that does not require much manpower and time, and a work boat that implements the method. is to provide.
[問題を解決するための手段]
本発明によれば、フロータバツグを備えた作業
船を函体の沈設箇所に移動させて位置決めし、作
業船のレグを昇降装置により降下させて作業船を
固定し、新設函体を吊り下げ、フロータバツグの
空気を抜き、昇降装置で作業船を下降させて新設
函体を既設函体の隣接位置に沈設させ、既設函体
とのセンター合せの微調整を行い、水平方向の調
整を行い、既設函体のセンターと新設函体のセン
ターが一致した後新設函体を送出した既設函体に
セツトする。[Means for Solving the Problem] According to the present invention, a work boat equipped with a floater bag is moved and positioned to the submerged location of the box, and the legs of the work boat are lowered by a lifting device to fix the work boat. , suspend the new box, remove the air from the floater bag, lower the work boat using the lifting device, lower the new box adjacent to the existing box, and fine-tune the center alignment with the existing box. After adjusting the horizontal direction and aligning the center of the existing box with the center of the new box, set the new box on the sent existing box.
また本発明によれば、多数個のフロータバツグ
を備えていて定宜の間隔をへだてて設けられた左
右一対の作業船浮函フレームを有しており、該作
業船浮函フレームは定宜の間隔をへだてて設けら
れた前後一対の作業船連結フレームにより連結さ
れており、作業船浮函フレームと作業船連結フレ
ームとの交差部にはレグ及び該レグを昇降させる
昇降装置が設けられており、そして各作業船連結
フレームには該作業船連結フレームに沿つて横行
し函体を吊り込む函体吊り込み治具を備えてトラ
ベラが設けられており、該函体吊込み治具は下方
に向うにしたがつて収斂するように傾斜し下端に
て函体の吊り金物に連結される一対の吊りロツド
と該吊りロツドの長さを変えるセンタホールジヤ
ツキよりなつている。 Further, according to the present invention, there is provided a pair of work boat floating box frames on the left and right which are provided with a large number of floater bags and are spaced apart from each other at a predetermined interval, and the work boat floating box frames are provided with a plurality of floater bags at a predetermined interval. They are connected by a pair of front and rear work boat connection frames that are separated from each other, and at the intersection of the work boat floating box frame and the work boat connection frame, a leg and a lifting device for raising and lowering the leg are provided. Each work boat connecting frame is provided with a traveler equipped with a box lifting jig that runs sideways along the work boat connecting frame and suspends the box, and the box lifting jig is directed downward. It consists of a pair of hanging rods that are inclined so as to converge and are connected to the hanging hardware of the box at the lower end, and a center hole jack that changes the length of the hanging rods.
[発明の作用効果]
本発明によれば、作業船はレグ及び昇降装置を
備えていて、レグを昇降装置により下降させて作
業船を固定するものであるので、アンカースペー
スを必要としない。また新設函体を作業船に設け
た函体送出し機構を兼ねた函体吊り込み治具によ
り吊下げ、既設函体とのセンター合せの微調整
を、上下方向の調整については昇降装置あるいは
函体吊り込み治具の吊りロツド長を調整すること
により、また水平方向の調整については函体吊り
込み治具が設けられたトラベラの横行により行う
ものであるので、新設函体の既設函体へのセンタ
ー合せ、すなわち新設函体の位置決めを容易にか
つ迅速に行うことができ、また新設函体の送出し
は函体吊り込み治具の2本の吊りロツドの長さを
変えることに行うものであるので、容易かつ確実
に行うことができる。[Operations and Effects of the Invention] According to the present invention, the work boat is equipped with legs and a lifting device, and the legs are lowered by the lifting device to fix the work boat, so no anchor space is required. In addition, the newly constructed box is suspended using a box lifting jig that also serves as a box delivery mechanism installed on the work boat, fine adjustment of center alignment with the existing box is made, and vertical adjustments are made using a lifting device or a box lifting jig. By adjusting the length of the hanging rod of the body lifting jig, and horizontal adjustment is done by moving the traveler equipped with the box lifting jig, the new box can be attached to the existing one. center alignment, that is, positioning of the newly installed box, can be done easily and quickly, and the sending of the newly installed box is done by changing the length of the two hanging rods of the box lifting jig. Therefore, it can be done easily and reliably.
[実施例]
以下、図面を参照して本発明の実施例につき説
明する。[Examples] Examples of the present invention will be described below with reference to the drawings.
まず、本発明に係る沈埋函の沈設工法を実施す
る作業船Aについて説明すると、間隔をへだてて
設けられた左右一対の作業船浮函フレーム1,1
を備えており、各作業船浮函フレーム1内には多
数個のフロータバツグ2が設けられている。この
フロータバツグ2は作業船に設けたエアーコンプ
レツサー(図示せず)からエアーが供給され、エ
アーが排出される。 First, a description will be given of the work boat A that implements the submerged box submersion method according to the present invention.A pair of left and right work boat floating box frames 1, 1 are provided with a space apart
A large number of floater bags 2 are provided in each work boat floating box frame 1. Air is supplied to the floater bag 2 from an air compressor (not shown) provided on the work boat, and air is discharged from the floater bag 2.
作業船浮函フレーム1,1は前後一対の作業船
連結フレーム3,3により連結されており、作業
船浮函フレーム1と作業船連結フレーム3との交
差部である4隅にレグ4及び昇降装置5が設けら
れている。この昇降装置5によりレグ4が昇降さ
れ、またレグ4を降下して作業船Aを固定した状
態でフロータバツグ2のエアーを抜き、作業船浮
函フレーム1や作業船連結フレーム3等の作業船
本体がレグ4と昇降装置5により昇降される。 The work boat floating box frames 1, 1 are connected by a pair of front and rear work boat connecting frames 3, 3, and there are legs 4 and lifts at the four corners where the work boat floating box frame 1 and the work boat connecting frame 3 intersect. A device 5 is provided. The leg 4 is raised and lowered by this lifting device 5, and the leg 4 is lowered to fix the work boat A, and the air in the floater bag 2 is removed. is raised and lowered by the legs 4 and the lifting device 5.
作業船連結フレーム3上に第5図に示すフレー
ム3の長手方向に伸びるレール6が設けられてお
り、このレール6上を転動する車輪7を備えたト
ラベラ8が設けられており、このトラベラ8は横
行して函体の水平方向の微調整を行う。トラベラ
8はセンターホールジヤツキ9とそのジヤツキ9
により長さが変えられる一対の吊りロツド10,
10よりなる函体送出し機構を兼ねた函体吊り込
み治具を備えており、吊りロツド10,10は下
方に向うにしたがつて収斂するように傾斜してい
て、その下端にて新設函体Bの吊り金物11に連
結され、函体Bを吊下げる。センターホールジヤ
ツキ9により吊りロツド10の長さを変えること
により函体Bを送り出す。また函体Bの上下方向
の微調整を上記の昇降装置4と共に吊りロツド1
0の長さを調整することにより行う。 A rail 6 extending in the longitudinal direction of the frame 3 shown in FIG. 8 moves horizontally to finely adjust the box in the horizontal direction. Traveler 8 has center hole jack 9 and its jack 9
A pair of hanging rods 10 whose length can be changed by
It is equipped with a box lifting jig that also serves as a box delivery mechanism, and the hanging rods 10, 10 are inclined so as to converge downward, and the newly installed box is opened at the lower end. It is connected to the hanging hardware 11 of the body B, and suspends the box B. The box B is sent out by changing the length of the hanging rod 10 using the center hole jack 9. In addition, fine adjustments in the vertical direction of the box B can be made using the lifting rod 1 together with the lifting device 4 mentioned above.
This is done by adjusting the length of 0.
作業船Aには上部デツキ12が設けられてお
り、また図示は省略したがエアーコンプレツサ
ー、発電機、制御装置その他必要な各種の機器が
設けられている。 The work boat A is provided with an upper deck 12, and is also provided with an air compressor, a generator, a control device, and various other necessary equipment, although not shown.
次に上記作業船Aを用いて函体を沈設する手順
について説明する。 Next, the procedure for sinking the box using the work boat A will be explained.
フロータバツグ2の浮力を利用して作業船Aを
新設函体を沈設する箇所に移動して位置決めし、
昇降装置5を用いてレグ4を降下し作業船Aを固
定する。なお、位置決めは詳細を後述するトラベ
ラ8の調整代範囲内の精度で設置する(第1図
,)。 Using the buoyancy of floater bag 2, move and position work boat A to the location where the new box will be sunk.
The work boat A is fixed by lowering the leg 4 using the lifting device 5. Note that the positioning is performed with accuracy within the adjustment range of the traveler 8, which will be described in detail later (FIG. 1).
新設函体Bを作業船A内に引込み、函体吊り込
み治具により函体を吊下げる。すなわち第5図に
示すように新設函体Bに溶接等により取付けられ
た吊り金物11に吊りロツド10,10の下端を
ボルト等により連結し函体Bを吊り下げる(第2
図,)。 The newly installed box B is pulled into the work boat A, and the box is suspended using a box lifting jig. That is, as shown in Fig. 5, the lower ends of the hanging rods 10, 10 are connected with bolts or the like to the hanging hardware 11 attached to the newly installed box B by welding or the like, and the box B is suspended (second
figure,).
フロータバツグ2内の空気を抜き、昇降装置5
を作動してレグ4を用いて作業船Aを下降させ
て、作業船Aに吊下げた函体Bを沈設する。そし
て上下方向(レベル)の微調整を昇降装置5また
は吊りロツド10の長さをセンターホールジヤツ
キ9により調整することにより行い、既設函体
B′のレベルに新設函体Bのレベルを合せる。ま
たトラベラ8を横行させて既設函体B′と新設函
体Bとの水平方向の微調整を行う(第3図,
)。 Remove the air from the floater bag 2, and lift the lifting device 5.
is activated to lower work boat A using leg 4, and sink box B suspended from work boat A. Fine adjustment in the vertical direction (level) is then performed by adjusting the length of the lifting device 5 or the hanging rod 10 using the center hole jack 9.
Match the level of the newly installed box B to the level of B'. In addition, the traveler 8 is moved horizontally to make fine adjustments in the horizontal direction between the existing box B' and the new box B (Fig. 3,
).
第5図においてセンターホールジヤツキ10に
より吊りロツド10,10の長さを変えることに
より新設函体Bを送出し、既設函体B′にセツト
する(第4図,)。 In FIG. 5, by changing the length of the hanging rods 10, 10 using the center hole jack 10, a new box B is sent out and set on the existing box B' (FIG. 4).
以下同様の操作を行い沈埋函の沈設を行つて水
面下にトンネルを構築する。 Thereafter, the same operation is performed to sink the submerged box and construct a tunnel under the water surface.
[まとめ]
以上の如く本発明によれば、既設函体に対して
新設函体を正しく位置決めしてセツトでき、その
作業も簡単であり、作業能率が向上できる。[Summary] As described above, according to the present invention, a new box can be correctly positioned and set with respect to an existing box, the work is simple, and work efficiency can be improved.
第1図,ないし第4図,は函体の沈設
手順を示す斜視図及び平面図で、第1図,は
作業船の移動、位置決め及びレグを降下させて作
業船を固定する状態を、第2図,は函体の引
込み及び函体吊り込み治具による函体の吊下げ状
態を、第3図,はフロータバツグの空気を抜
き函体の沈設及びセンター合せの状態を、第4図
,は函体を送出し既設函体へのセツトする状
態をそれぞれ示す。第5図は函体送出し機構を兼
ねた函体吊り治具を備えたトラベラの断面図であ
る。
A……作業船、B……新設函体、B′……既設
函体、1……浮函フレーム、2……フロータバツ
グ、3……作業時連結フレーム、4……レグ、5
……昇降装置、6……レール、8……トラベラ、
9……センターホールジヤツキ、10……吊りロ
ツド、11……吊り金物。
Figures 1 to 4 are a perspective view and a plan view showing the procedure for sinking the box, and Figure 1 shows the movement, positioning, and lowering of the legs to fix the workboat. Figure 2 shows the state of the box being pulled in and suspended by the box lifting jig, Figure 3 shows the state of removing the air from the floater bag and sinking the box and aligning the centers. The state in which the box is sent out and set into the existing box is shown. FIG. 5 is a sectional view of a traveler equipped with a box hanging jig that also serves as a box delivery mechanism. A...Work boat, B...New box, B'...Existing box, 1...Floating box frame, 2...Floater bag, 3...Connection frame during work, 4...Leg, 5
... Lifting device, 6 ... Rail, 8 ... Traveler,
9...Center hole jack, 10...Hanging rod, 11...Hanging hardware.
Claims (1)
箇所に移動させて位置決めし、作業船のレグを昇
降装置により降下させて作業船を固定し、新設函
体を吊り下げ、フロータバツグの空気を抜き、昇
降装置で作業船を下降させて新設函体を既設函体
の隣接位置に沈設させ、既設函体とのセンター合
せの微調整を行い、水平方向の調整を行い、既設
函体のセンターと新設函体のセンターが一致した
後新設函体を送出して既設函体にセツトすること
を特徴とする沈埋函の沈設工法。 2 多数個のフロータバツグを備えていて定宜の
間隔をへだてて設けられた左右一対の作業船浮函
フレームを有しており、該作業船浮函フレームは
定宜の間隔をへだてて設けられた前後一対の作業
船連結フレームにより連結されており、作業船浮
函フレームと作業船連結フレームとの交差部には
レグ及び該レグを昇降させる昇降装置が設けられ
ており、そして各作業船連結フレームには該作業
船連結フレームに沿つて横行し函体を吊り込む函
体吊り込み治具を備えたトラベラが設けられてお
り、該函体吊込み治具は下方に向うにしたがつて
収斂するように傾斜し下端にて函体の吊り金物に
連結される一対の吊りロツドと該吊りロツドの長
さを変えるセンタホールジヤツキよりなることを
特徴とする作業船。[Scope of Claims] 1. A work boat equipped with a floater bag is moved to and positioned at the location where the box is to be sunk, the legs of the work boat are lowered by a lifting device to fix the work boat, and the newly installed box is suspended. Let the air out of the floater bag, lower the work boat using the lifting device and sink the new box adjacent to the existing box, make fine adjustments to align the center with the existing box, make horizontal adjustments, and lower the work boat to the existing box. A method for submerging a submerged box, which is characterized in that after the center of the box and the center of the newly installed box match, the newly installed box is sent out and set on the existing box. 2. It has a pair of work boat floating box frames on the left and right that are equipped with a large number of floater bags and are spaced apart from each other by a certain distance; They are connected by a pair of front and rear work boat connection frames, and a leg and a lifting device for raising and lowering the leg are provided at the intersection of the work boat floating box frame and the work boat connection frame, and each work boat connection frame is equipped with a traveler equipped with a box lifting jig that travels along the work boat connection frame and suspends the box, and the box hoisting jig converges as it moves downward. 1. A work boat characterized by comprising a pair of hanging rods that are inclined as shown in FIG.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP62103175A JPS63268899A (en) | 1987-04-28 | 1987-04-28 | Method of sinking construction of sinking caisson and working ship for executing said method of construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP62103175A JPS63268899A (en) | 1987-04-28 | 1987-04-28 | Method of sinking construction of sinking caisson and working ship for executing said method of construction |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63268899A JPS63268899A (en) | 1988-11-07 |
| JPH0544519B2 true JPH0544519B2 (en) | 1993-07-06 |
Family
ID=14347173
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP62103175A Granted JPS63268899A (en) | 1987-04-28 | 1987-04-28 | Method of sinking construction of sinking caisson and working ship for executing said method of construction |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS63268899A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107651120B (en) * | 2017-08-16 | 2023-08-08 | 中交第一航务工程局有限公司 | Ship pipe connecting device and connecting method |
| JP7202346B2 (en) * | 2020-11-30 | 2023-01-11 | 五洋建設株式会社 | Caisson installation aid and installation method |
-
1987
- 1987-04-28 JP JP62103175A patent/JPS63268899A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63268899A (en) | 1988-11-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA1102570A (en) | Sea-floor template | |
| JPH0544519B2 (en) | ||
| JPH0216210A (en) | Methods and apparatus for the fabrication of floating constructions such as piers, jetties and the like | |
| JP2759428B2 (en) | Underwater steel pipe pile driving method and equipment | |
| US3381482A (en) | Marine drilling structure | |
| JPS5839279Y2 (en) | Offshore block joint structure | |
| JPS62139782A (en) | Attaching method for thruster to marine structure | |
| JPH01169021A (en) | Caisson installation method and equipment | |
| US2653452A (en) | Deepwater submersible barge | |
| JPH03121989A (en) | Construction method for graving docks equipped with floating barges and their docking vessels | |
| CN215590948U (en) | Ship positioning pile with automatic lifting function | |
| JPS58207410A (en) | Assembler for prefabricated steel sheet pile cell | |
| KR860001543Y1 (en) | Offshore drilling | |
| JPS6278309A (en) | Spat base ship set at inclined angle | |
| JPH0214485B2 (en) | ||
| JPS62112809A (en) | Setting of one-point mooring device | |
| SU1299895A1 (en) | Arrangement for lifting sunken object | |
| JP2565539Y2 (en) | Caisson launch equipment | |
| JPH0227095A (en) | Sinking and burying method | |
| JP2823968B2 (en) | Premix casting boat | |
| JPS6354600B2 (en) | ||
| JPH0637772B2 (en) | Construction method and equipment for crushed stone foundation | |
| JP2000319912A (en) | How to set up the box | |
| CN118187060A (en) | Marine pile foundation positioning device and method | |
| JPS58510A (en) | Offshore working platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |