JPH0565652B2 - - Google Patents
[go: Go Back, main page]

JPH0565652B2 - - Google Patents

Info

Publication number
JPH0565652B2
JPH0565652B2 JP1141628A JP14162889A JPH0565652B2 JP H0565652 B2 JPH0565652 B2 JP H0565652B2 JP 1141628 A JP1141628 A JP 1141628A JP 14162889 A JP14162889 A JP 14162889A JP H0565652 B2 JPH0565652 B2 JP H0565652B2
Authority
JP
Japan
Prior art keywords
pile
hollow
foundation pile
head
pile head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1141628A
Other languages
Japanese (ja)
Other versions
JPH038922A (en
Inventor
Takao Kashimura
Kyoichi Nagaoka
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Iwatani Corp
Sanshin Tsusho KK
Original Assignee
Iwatani Corp
Iwatani Sangyo KK
Sanshin Tsusho KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Iwatani Corp, Iwatani Sangyo KK, Sanshin Tsusho KK filed Critical Iwatani Corp
Priority to JP14162889A priority Critical patent/JPH038922A/en
Publication of JPH038922A publication Critical patent/JPH038922A/en
Publication of JPH0565652B2 publication Critical patent/JPH0565652B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 <産業上の利用分野> この発明は地盤中へ中空基礎杭を沈設する施工
方法及び中空基礎杭の沈設に際して用いる杭頭部
充填具に関するものである。
[Detailed Description of the Invention] <Industrial Application Field> The present invention relates to a construction method for sinking a hollow foundation pile into the ground and a pile head filler used when sinking the hollow foundation pile.

<従来の技術> この種の施工方法としては、従来より例えば第
5図に示すもの(以下従来例1という)、あるい
は第6図に示すもの(特開昭62−50517号公報、
以下従来例2という)が知られている。
<Prior art> As this type of construction method, conventionally, for example, the method shown in FIG. 5 (hereinafter referred to as conventional example 1) or the method shown in FIG.
(hereinafter referred to as conventional example 2) is known.

従来例1は、掘削穴1内に根固め硬化剤2とし
てセメントミルク等を注入し、次いでその掘削穴
1内に中空状の基礎杭3を沈設することにより、
その基礎杭3の中空部3b内へ根固め硬化剤2を
充填させ、根固め硬化剤2が硬化して根固めした
時点で基礎杭3を所定の高さHに揃えて切断し、
その切断した杭頭部3aに構築物の基台部分を構
成する鉄筋類を定着するという施工方法である。
なお同図中符号10は基礎杭3の沈設用保持具で
ある。
In conventional example 1, cement milk or the like is poured into an excavated hole 1 as a hardening agent 2, and then a hollow foundation pile 3 is placed in the excavated hole 1.
Fill the hollow part 3b of the foundation pile 3 with a foot hardening hardening agent 2, and when the foot hardening hardening agent 2 hardens and hardens the foot, the foundation pile 3 is cut to a predetermined height H,
This is a construction method in which reinforcing bars forming the base of the structure are fixed to the cut pile head 3a.
In addition, the reference numeral 10 in the figure is a holder for sinking the foundation pile 3.

また従来例2は従来例1と同様、中空基礎杭3
を沈設した後、根固め硬化剤2が未硬化の間に中
空基礎杭3の頭部3a内の根固め硬化剤を噴射水
で除去し、そこへ形成された杭頭内空部3Aへ構
築物の基台部分を構成する鉄筋類を定着する施工
方法である。なお同図中符号11は根固め硬化剤
の噴射除去装置である。
Also, in conventional example 2, similar to conventional example 1, hollow foundation pile 3
After the foundation pile hardening agent 2 has not yet hardened, the root hardening agent 2 inside the head 3a of the hollow foundation pile 3 is removed with water jet, and the structure is poured into the pile head inner cavity 3A formed there. This is a construction method that fixes the reinforcing bars that make up the base of the building. In addition, the reference numeral 11 in the figure is a spray removal device for the root hardening and curing agent.

<発明が解決しようとする課題> 従来例1は第5図に示すように、中空基礎杭3
の頭部3a内に根固め硬化剤2が充填されている
ため、これが硬化した後に当該基礎杭3を所定の
高さHで切断するには中空状のものを切断する場
合の数倍の時間を要する。しかもその杭頭部3a
へ構築物の基台部分を定着するには、さらに杭頭
部を加工して杭頭内空部を形成する必要がある。
このため施工期間の長期化、ひいてはコストアツ
プを招いていた。
<Problem to be solved by the invention> In conventional example 1, as shown in FIG.
Because the head 3a of the foundation pile 3 is filled with the hardening agent 2, cutting the foundation pile 3 at a predetermined height H after this has hardened takes several times the time it would take to cut a hollow one. It takes. Moreover, the pile head 3a
In order to fix the base part of the structure to the pile head, it is necessary to further process the pile head to form a hollow space inside the pile head.
This led to longer construction periods and increased costs.

一方、従来例2は上記難点を解消するものであ
るが、杭頭内空部3Aを形成するのに未硬化の根
固め硬化剤を噴射水で除去するため、中空基礎杭
3内の根固め硬化剤2が多量の水分を含み、セメ
ントミルク等の組成変化をもたらす。また噴射除
去の時期を失し、根固め硬化剤を硬化した後で
は、従来例1と同様の問題点が生じる。しかも噴
射除去装置11を必要とするため、これに伴うコ
ストアツプは避けられない。
On the other hand, Conventional Example 2 solves the above-mentioned difficulties, but since the unhardened root hardening agent is removed by jet water to form the pile head inner cavity 3A, the root hardening inside the hollow foundation pile 3 is The hardening agent 2 contains a large amount of water, causing a change in the composition of cement milk and the like. Furthermore, if the timing of spray removal is missed and the root hardening curing agent is hardened, the same problem as in Conventional Example 1 will occur. Moreover, since the injection removal device 11 is required, an increase in cost is inevitable.

かかる不都合を回避するには、下端閉塞型の中
空基礎杭を用いればよいが、例えば第4図に示す
ように、当該基礎杭3の長さが少し短い場合には
根固め硬化剤2が上から流入して杭頭内空部3A
を塞ぐおそれがある。この杭頭内空部3Aが塞が
れると、第3図について後述するように、構築物
の基台部分8を定着することができなくなる。
To avoid such inconvenience, a hollow foundation pile with a closed bottom end may be used. However, as shown in Fig. 4, if the length of the foundation pile 3 is a little short, the foot hardening agent 2 may be Flowing in from the pile head inner cavity 3A
There is a risk of blocking the If this pile cap internal space 3A is blocked, the base portion 8 of the structure cannot be fixed, as will be described later with reference to FIG.

本発明はこのような事情に鑑みてなされたもの
であり、 イ 杭頭内空部を簡単に確保形成すること、 ロ 杭頭部の切断を容易にすること、 ハ 中空基礎杭内に充填される根固め硬化剤が組
成変化を生じないこと、 ニ 工期の短縮とコストダウンを図ること、 を技術課題とする。
The present invention has been made in view of the above circumstances, and has the following features: (a) to easily secure and form the hollow space inside the pile head; (b) to facilitate cutting of the pile head; and (c) to fill the hollow foundation pile with the hollow foundation pile. The technical challenges are to ensure that the root hardening agent used in the construction site does not change its composition, and (2) to shorten the construction period and reduce costs.

<課題を解決するための手段> 上記課題を解決するために、本発明は以下のよ
うに構成される。
<Means for Solving the Problems> In order to solve the above problems, the present invention is configured as follows.

即ち、第1の発明は従来と同様の中空基礎杭の
沈設施工方法において、中空基礎杭の頭部内にあ
らかじめ杭頭部充填具を装填し、中空基礎杭の沈
設完了後、杭頭部充填具を除去することにより杭
頭内空部を形成することを特徴とする中空基礎杭
の施工方法である。
That is, the first invention is a hollow foundation pile sinking construction method similar to the conventional method, in which a pile head filler is loaded in advance into the head of the hollow foundation pile, and after the hollow foundation pile is completely sunk, the pile head is filled. This is a construction method for hollow foundation piles, which is characterized by forming a hollow space inside the pile head by removing a tool.

そして第2の発明は基礎杭内に充填する合成樹
脂材料で形成した杭頭部充填具である。
The second invention is a pile head filler made of a synthetic resin material and filled into a foundation pile.

<作用> 第1の発明では、中空基礎杭の頭部内に、あら
かじめ杭頭部充填具を装着した状態でその中空基
礎杭を沈設するので、中空基礎杭の沈設完了後、
当該杭頭部充填具を除去すれば、そこには杭頭内
空部が形成される。
<Function> In the first invention, since the hollow foundation pile is sunk with the pile head filler installed in advance in the head of the hollow foundation pile, after the sinking of the hollow foundation pile is completed,
When the pile head filler is removed, a pile head internal cavity is formed there.

そして第2の発明では、上記第1の発明に用い
る杭頭部充填具は例えばパイルコルル等の合成樹
脂材料で軽量かつ安価に形成されており、中空基
礎杭の頭部内へ着脱も容易で、仮に根固め硬化剤
が硬化した後でも当該充填具を破断して容易に除
去することができる。
In the second invention, the pile head filler used in the first invention is made of a synthetic resin material such as pile corulu, and is lightweight and inexpensive, and can be easily attached to and removed from the head of the hollow foundation pile. Even after the root hardening hardening agent has hardened, the filling tool can be broken and easily removed.

<実施例> 第1図は本発明に係る中空基礎杭の沈設状態を
示す要部縦断面図である。
<Example> FIG. 1 is a vertical cross-sectional view of a main part showing a state in which a hollow foundation pile according to the present invention is sunk.

即ち、地盤にはプレボーリングによつて掘削穴
1があけられ、掘削穴1にはセメントミルク等の
根固め硬化剤2が注入され、その掘削穴1内に両
端開口の中空基礎杭3が沈設されている。
That is, an excavated hole 1 is made in the ground by pre-boring, a hardening agent 2 such as cement milk is poured into the excavated hole 1, and a hollow foundation pile 3 with both ends open is sunk into the excavated hole 1. has been done.

上記中空基礎杭3には、その頭部3a内にあら
かじめ杭頭部充填具4が装填され、止め具7で固
定されている。
A pile head filler 4 is loaded in advance into the head 3a of the hollow foundation pile 3 and fixed with a stopper 7.

この杭頭部充填具4はパイルコルクと称する合
成樹脂材料で形成され、その軸心部に抜き孔5が
あけられており、中空基礎杭3を沈設することに
より基礎杭3の中空部3b及び抜き孔5ヘセメン
ト、モルタル等の根固め硬化剤2が充填される。
This pile head filler 4 is made of a synthetic resin material called pile cork, and has a punch hole 5 in its axial center, and by sinking the hollow foundation pile 3, the hollow part 3b of the foundation pile The punch hole 5 is filled with a hardening agent 2 such as cement or mortar.

そして中空基礎杭3の沈設完了後、杭頭部充填
具4は除去され、そこに杭頭内空部3Aが形成さ
れる。
After completing the sinking of the hollow foundation pile 3, the pile head filler 4 is removed, and a pile head inner cavity 3A is formed there.

なお、第2図は杭頭部充填具4の別実施例を示
し、同図Aは縦方向へ二つ割り状に形成したもの
の半分を、同図Bは同じく二つ割り状に形成した
もの一組を表皮連結部4aで一体に連結したもの
を例示する斜視図であり、それぞれ取り扱い上の
便宜を考慮したものである。
In addition, Figure 2 shows another embodiment of the pile head filler 4, in which Figure A shows half of the pile head filler 4 formed vertically in half, and Figure B shows a set of the same halves formed in the skin. It is a perspective view illustrating what is integrally connected by the connection part 4a, and it is a perspective view which takes into consideration the convenience in handling.

上記のようにして形成された杭頭内空部3Aに
は、抜き孔5に充填された硬化剤が残るが、不要
ならそれを除去し、第3図に示すように構築物の
基台部分8を構成する鉄筋類が挿入され、その基
台部分8が定着される。
The hardening agent filled in the punching hole 5 remains in the pile cap inner cavity 3A formed as described above, but if it is unnecessary, it can be removed and the base portion 8 of the structure shown in FIG. The reinforcing bars that make up the structure are inserted, and the base portion 8 thereof is fixed.

なお同図中符号8a,8bは基台部分の固定用
金具である。
Note that reference numerals 8a and 8b in the figure are metal fittings for fixing the base portion.

上記実施例では中空基礎杭が両端開口型のもの
について例示したが、下端閉塞型のものについて
も適用できる。また、杭頭部充填具の横断面形状
も、円形に限らず、基礎杭の中空の形状に合わせ
て形成される。
In the above embodiments, the hollow foundation pile is of the type with both ends open, but it can also be applied to a type of hollow foundation pile with the lower end closed. Further, the cross-sectional shape of the pile head filler is not limited to a circular shape, but is formed to match the hollow shape of the foundation pile.

なお、本発明では杭頭部充填具が杭頭内空部を
形成するものであれば、その材質等は問わない。
In addition, in the present invention, the material etc. of the pile head filler are not limited as long as it forms the hollow space inside the pile head.

また上記実施例では、両端開口型の中空基礎杭
について例示したので、杭頭部充填具が基礎杭内
の中空部を大気へ連通する抜き孔を有するものに
ついて例示したが、下端閉塞型の中空基礎杭では
必ずしも抜き孔は必要ではなく、適宜変更を加え
て実施することができる。
In addition, in the above embodiment, since the hollow foundation pile with both ends open was illustrated, the pile head filling tool has a hole that communicates the hollow part in the foundation pile to the atmosphere. Foundation piles do not necessarily require punched holes, and can be implemented with appropriate modifications.

<発明の効果> 以上の説明で明らかなように、第1の発明では
中空基礎杭の頭部内に杭頭部充填具を装填し、中
空基礎杭の沈設時に杭頭内空部を確保形成するよ
うにしたので、次の効果を奏する。
<Effects of the Invention> As is clear from the above explanation, in the first invention, a pile head filler is loaded into the head of a hollow foundation pile, and a hollow space inside the pile head is secured and formed when the hollow foundation pile is sunk. By doing so, the following effects are achieved.

イ 中空基礎杭の頭部内にあらかじめ杭頭部充填
具を装填して基礎杭を沈設するだけで簡単に杭
頭内空部を確保形成し、土砂及びコンクリート
の侵入を防ぐことができる。
(b) By simply loading a pile head filler into the head of a hollow foundation pile in advance and sinking the foundation pile, a hollow space inside the pile head can be easily secured and the intrusion of earth and sand and concrete can be prevented.

ロ 杭頭部を所定の高さに揃えて切断する際に、
従来例1のような中実ではないので容易に切断
することができる。
(b) When cutting the pile head to the specified height,
Since it is not solid like Conventional Example 1, it can be easily cut.

ハ 従来例このように噴射水で未硬化の根固め硬
化剤を除去する必要がなく、根固め硬化剤が組
成変化することもないので安全である。
C. Conventional Example It is safe because there is no need to remove the unhardened root hardening hardening agent with sprayed water, and the composition of the root hardening hardening agent does not change.

また、第2の発明では杭頭部充填剤が、軽量
かつ安価な合成樹脂材料で形成されており、沈
設に際し何ら弊害を生じる事なく、しかも基礎
杭頭部内への着脱も容易であるからで次の効果
を奏する。
In addition, in the second invention, the pile head filler is made of a lightweight and inexpensive synthetic resin material, and does not cause any adverse effects during installation, and can also be easily attached to and removed from the foundation pile head. produces the following effect.

ニ 従来例2のように噴射除去装置等を必要とせ
ず、全体としてコストダウンの低減と工期の短
縮を図ることができる。
(d) There is no need for a spray removal device or the like as in Conventional Example 2, and the overall cost can be reduced and the construction period can be shortened.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る中空基礎杭の沈設状態を
例示する要部縦断面図、第2図は杭頭部充填具の
別実施例を示す斜視図、第3図は杭頭内空部に構
造物の基台部分を定着する状態を例示する要部縦
断面図、第4図は下端閉塞型中空基礎杭の縦断面
図、第5図及び第6図はそれぞれ従来例を示す要
部縦断面図である。 1……掘削孔、2……根固め硬化剤、3……中
空基礎杭、3a……中空基礎杭の頭部、3A……
杭頭内空部、3b……基礎杭内の中空部、4……
杭頭部充填具。
Fig. 1 is a vertical cross-sectional view of a main part illustrating the state of sinking a hollow foundation pile according to the present invention, Fig. 2 is a perspective view showing another embodiment of a pile head filler, and Fig. 3 is a hollow part inside the pile cap. Fig. 4 is a vertical cross-sectional view of a main part illustrating a state in which the base part of a structure is fixed, Fig. 4 is a longitudinal cross-sectional view of a bottom-end closed type hollow foundation pile, and Figs. 5 and 6 are main parts showing a conventional example. FIG. 1... Excavation hole, 2... Root hardening agent, 3... Hollow foundation pile, 3a... Head of hollow foundation pile, 3A...
Hollow part inside the pile head, 3b... Hollow part inside the foundation pile, 4...
Pile head filling tool.

Claims (1)

【特許請求の範囲】 1 掘削穴1内に根固め硬化剤2を注入し、その
掘削穴1内に中空基礎杭3を沈設し、杭頭内空部
3Aに構築物の基台部分8を定着する中空基礎杭
の施工方法において、 中空基礎杭3の頭部3a内にあらかじめ杭頭部
充填具4を装填し、中空基礎杭3の沈設完了後、
杭頭部充填具4を除去することにより杭頭内空部
3Aを形成することを特徴とする中空基礎杭の施
工方法。 2 請求項1に記載した杭頭部充填具4であつ
て、合成樹脂材料で形成した杭頭部充填具。
[Claims] 1. Injecting a foot hardening agent 2 into the excavated hole 1, sinking the hollow foundation pile 3 into the excavated hole 1, and fixing the base part 8 of the structure in the hollow part 3A of the pile head. In the hollow foundation pile construction method, a pile head filler 4 is loaded in advance into the head 3a of the hollow foundation pile 3, and after the hollow foundation pile 3 is completely sunk,
A method for constructing a hollow foundation pile, characterized in that a pile head inner cavity 3A is formed by removing the pile head filler 4. 2. The pile head filling tool 4 according to claim 1, which is made of a synthetic resin material.
JP14162889A 1989-06-02 1989-06-02 Executing method for hollow foundation pile and pile head filling-in stuff Granted JPH038922A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14162889A JPH038922A (en) 1989-06-02 1989-06-02 Executing method for hollow foundation pile and pile head filling-in stuff

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14162889A JPH038922A (en) 1989-06-02 1989-06-02 Executing method for hollow foundation pile and pile head filling-in stuff

Publications (2)

Publication Number Publication Date
JPH038922A JPH038922A (en) 1991-01-16
JPH0565652B2 true JPH0565652B2 (en) 1993-09-20

Family

ID=15296461

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14162889A Granted JPH038922A (en) 1989-06-02 1989-06-02 Executing method for hollow foundation pile and pile head filling-in stuff

Country Status (1)

Country Link
JP (1) JPH038922A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001011856A (en) * 1999-04-30 2001-01-16 Mitani Sekisan Co Ltd Burying method of ready-made pile

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0365733U (en) * 1989-10-26 1991-06-26
JP2615266B2 (en) * 1991-01-17 1997-05-28 積水化成品工業 株式会社 Spacer for removing hardened cement in tubular tube and method of using the same
CN107719161B (en) * 2017-09-29 2018-11-20 江苏来德福汽车部件有限公司 A kind of new-energy automobile device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0529238Y2 (en) * 1988-06-30 1993-07-27

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001011856A (en) * 1999-04-30 2001-01-16 Mitani Sekisan Co Ltd Burying method of ready-made pile

Also Published As

Publication number Publication date
JPH038922A (en) 1991-01-16

Similar Documents

Publication Publication Date Title
JP2000352108A (en) Precast block method
JP3373171B2 (en) Pile construction method
JPH0565652B2 (en)
JP3932094B2 (en) Method for reinforcing culvert structure
JPH1018424A (en) Root wrapping reinforcing structure of column base of steel post or the like
JP6175791B2 (en) Ground reinforcement method and structure
JPH09324422A (en) Cast-in-place compound pile and building method therefor
JPH0771032A (en) Prefabricated pile and installation method thereof
JP3817386B2 (en) Underground outer wall and its construction method
JPH0329929B2 (en)
JPH0243848B2 (en)
KR100769498B1 (en) Ground reinforcement method using stiffeners with various protrusions on the outer circumference
JPH0521533Y2 (en)
KR20030052868A (en) Joint of base concrete structure and bridge pier and its jointing method
JPH111929A (en) Grout forming method for reinforcing steel rods to communicate with precast plate for retaining wall and grout material injection guide used therefor
JPS6119787B2 (en)
JP2004300754A (en) Pile head joint structure
JPH0712421Y2 (en) Pile head metal fittings
JPS62236955A (en) Construction of pillar body in concrete structure
JPH0643219Y2 (en) Core body attached to the inner circumference of the head of a concrete pile
JPH0561409B2 (en)
JP2000319875A (en) Structure of concrete-pile head section joined with footing
JPS6214186Y2 (en)
JPH03260223A (en) Positioning plate for base construction of housing
JPS63289145A (en) How to fix anchor bolts