JPH06101900B2 - Power system simulation method - Google Patents
[go: Go Back, main page]

JPH06101900B2 - Power system simulation method - Google Patents

Power system simulation method

Info

Publication number
JPH06101900B2
JPH06101900B2 JP60111839A JP11183985A JPH06101900B2 JP H06101900 B2 JPH06101900 B2 JP H06101900B2 JP 60111839 A JP60111839 A JP 60111839A JP 11183985 A JP11183985 A JP 11183985A JP H06101900 B2 JPH06101900 B2 JP H06101900B2
Authority
JP
Japan
Prior art keywords
calculation
relay
simulation
executed
power system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP60111839A
Other languages
Japanese (ja)
Other versions
JPS61270780A (en
Inventor
幸太郎 団
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP60111839A priority Critical patent/JPH06101900B2/en
Publication of JPS61270780A publication Critical patent/JPS61270780A/en
Publication of JPH06101900B2 publication Critical patent/JPH06101900B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、制御所員の系統操作技術・技能の維持,向
上を図るための訓練装置に適用する電力系統シミユレー
シヨン方式に関するものである。
Description: TECHNICAL FIELD The present invention relates to a power system simulation system applied to a training device for maintaining and improving system operation techniques and skills of control staff.

〔従来の技術〕[Conventional technology]

第4図は従来の電力系統シミユレーシヨン方式の処理概
念図であり、図において、1はCRT装置、2は事故シー
ケンスデータフアイル、3はSV状変データフアイルであ
り、かかるシミユレーシヨン方式では後述するように、
訓練準備段階では過渡安定度計算のステツプを実行
し、訓練実行段階では周波数・潮流計算のステツプを
実行する。ここで、SV状変データとは、動作リレーとし
ゃ断器の状態変化を示すデータであって、具体的には、
その変化した状態と変化のあった時刻を表すデータから
なる。
FIG. 4 is a conceptual diagram of processing of a conventional power system simulation method. In the figure, 1 is a CRT device, 2 is an accident sequence data file, 3 is an SV-like variable data file, and such a simulation system will be described later. ,
In the training preparation stage, the transient stability calculation step is executed, and in the training execution stage, the frequency / power flow calculation step is executed. Here, the SV state change data is data indicating the state change of the operation relay and the circuit breaker, and specifically,
It is made up of data representing the changed state and the time when the change occurred.

次に動作について説明する。Next, the operation will be described.

まず、訓練準備段階において、トレーナはCRT画面1に
おいて、電力系統における故障発生時刻、故障点、故障
種別さらにはこれらの系統故障により動作すると考えら
れる主保護リレーあるいは後備保護リレーなどの動作リ
レーと、その動作リレーによりトリツプ動作するしや断
器(CB)とに関する各種データを、ライトペンを用いて
設定する。設定された上記データは、事故シーケンスデ
ータフアイル2に記憶され、また上記各動作リレーとし
や断器(CB)に関するデータについては、SV状変データ
フアイル4にも保存される。
First, in the training preparation stage, the trainer shows on the CRT screen 1 a failure occurrence time in the power system, a failure point, a failure type, and an operation relay such as a main protection relay or a backup protection relay that is considered to operate due to these system failures, Various data related to the trip operation and the circuit breaker (CB) are set by the operation relay using a light pen. The set data is stored in the accident sequence data file 2, and the data relating to each of the operation relays and the circuit breaker (CB) is also stored in the SV-like variable data file 4.

続いて、脱調リレーの動作判定を行うのであるが、これ
はトレーナにより正しく設定する事が困難なため、事故
シーケンスデータフアイル2を入力データとして、過渡
安定度計算プログラムを実行し(ステツプ)、その判
定結果として、動作SOリレーとトリツプCBの状態をSV状
変データフアイルに記憶する。
Next, the operation of the step-out relay is judged, but it is difficult to set it correctly by the trainer. Therefore, the transient stability calculation program is executed using the accident sequence data file 2 as input data (step), As a result of the determination, the states of the operating SO relay and the trip CB are stored in the SV state change data file.

過渡安定度計算が打切り時間に達した時点で、トレーナ
の指示により、SV状変データフアイルの内容を時系列順
に並べ換える。以上で、訓練準備段階は終了する。
When the transient stability calculation reaches the cutoff time, the contents of the SV-like variable data file are rearranged in chronological order according to the trainer's instructions. This concludes the training preparation stage.

次に、訓練実行段階では、SV状変データフアイル3から
しや断器(CB)の状態変化を時系列順に取出しながら、
潮流計算と周波数計算プログラムを実行し(ステツプ
)、過負荷リレー,周波数低下リレーあるいは電圧・
無効電力制御装置の動作を模擬することにより、電力系
統のリアルタイムシミユレーシヨンを行う。このリアル
タイムシミユレーシヨンの詳細を、第5図のフロー図に
従つて以下に説明する。このリアルタイムシミユレーシ
ヨンの全体的動作としては、T秒毎に周波数計算と潮流
計算を結合して行い、さらに周波数計算はΔT秒のきざ
みでn(=T/ΔT)回連続して行う。
Next, at the training execution stage, while extracting the state changes of the SV-like data file 3 from the SV-like data file 3 in chronological order,
Execute power flow calculation and frequency calculation program (step), and then overload relay, frequency drop relay or voltage
By simulating the operation of the reactive power control device, real-time simulation of the power system is performed. The details of this real-time simulation will be described below with reference to the flowchart of FIG. As the overall operation of this real-time simulation, the frequency calculation and the power flow calculation are performed every T seconds, and the frequency calculation is continuously performed n (= T / ΔT) times in steps of ΔT seconds.

つまり、周波数計算をΔT秒きざみでn(=T/ΔT)回
繰返し、その時点の潮流計算を1回実行し、全ての処理
を実時間のT秒で行つて、リアルタイムシミユレーシヨ
ンを実現している。なお、通常は、潮流計算と周波数計
算を、別々の計算機で分担処理してリアルタイムシミユ
レーシヨンを実現している。
In other words, frequency calculation is repeated n (= T / ΔT) times at intervals of ΔT seconds, power flow calculation at that point is executed once, and all processing is performed in real time T seconds to realize real-time simulation. is doing. Normally, the power flow calculation and the frequency calculation are shared by different computers to realize real-time simulation.

詳細な動作は、まず当該時刻のSV状変データフアイル3
からSV状変データを取出し、開閉器状態の変化の有無を
判定し(ステツプ)、変化が有る場合には、系統分離
計算を実行して、分離系統の判定、系統のアドミタンス
行列の修正、分離系統の系統容量や合計慣性容量などの
計算を行う(ステツプ)。続いて、この系統分離計算
の終了後に、潮流計算を実行する(ステツプ)。一
方、ステツプで変化が無いと判定された場合には、負
荷しや断などによる母線の有効電力の不連続変化の有無
をチエツクし(ステツプ)、変化がない場合には潮流
計算の終了と同様に各分離系統毎の系統周波数計算を実
行し(ステツプ)、続いて系統周波数に応動するリレ
ーの動作模擬を行い(ステツプ)、これらの処理をn
回(T/ΔT)繰り返す。なお、ステツプにおいて不連
続変化が有ると判定された場合は、ステツプの処理を
実行する。
The detailed operation is as follows: First, the SV-like data file 3 at that time.
From the SV-like data, determine whether there is a change in the switch state (step), and if there is a change, execute system separation calculation, determine the separated system, correct the system admittance matrix, and separate the system. Calculate the grid capacity and total inertial capacity of the grid (step). Subsequently, after the completion of the system separation calculation, the power flow calculation is executed (step). On the other hand, if it is determined that there is no change in step, check whether there is a discontinuous change in the active power of the bus due to load or disconnection (step), and if there is no change, the same as the end of the power flow calculation. Then, the system frequency calculation for each separated system is executed (step), and the operation of the relay that responds to the system frequency is simulated (step).
Repeat (T / ΔT) times. If it is determined that there is a discontinuous change in the step, the step process is executed.

次に上記処理を繰返した場合には、その時点の潮流計算
を実行し(ステツプ)、さらに系統電圧、送電線潮流
などに応動する過負荷リレーあるいは電圧・無効電力制
御装置の動作模擬を実行し(ステツプ)、最後に、1
サイクルT秒の同期を取るためのリアルタイム同期の処
理(delay)を実行し(ステツプ)、T秒間のシミユ
レーシヨンが完了する。続いて次のサイクルのシミユレ
ーシヨンに入る。
Next, when the above process is repeated, the power flow calculation at that point is executed (step), and the operation simulation of the overload relay or the voltage / reactive power control device that responds to the system voltage, power flow of the transmission line, etc. is executed. (Step), finally 1
A real-time synchronization process (delay) for synchronization of T seconds is executed (step), and the simulation for T seconds is completed. Then enter the simulation of the next cycle.

T秒は通常3〜5秒程度であり、ΔTは0.25秒程度とな
る。
T seconds are usually about 3 to 5 seconds, and ΔT is about 0.25 seconds.

T秒は実際の給電自動化システムの情報更新周期から決
められているものであり、この性能を満足するシミユレ
ーシヨンをリアルタイムシミユレーシヨンと定義してい
る。
T seconds is determined from the information update cycle of the actual power supply automation system, and the simulation that satisfies this performance is defined as real-time simulation.

〔発明が解決しようとする問題点〕[Problems to be solved by the invention]

従来の電力系統シミユレーシヨンは以上の様であるの
で、主保護・後備保護リレーの動作模擬をトレーナの設
定という形式で行う必要があり、訓練実行中にトレーニ
が誤操作により接地をつけたり事故設備のしや断器を投
入したりした場合には、再び系統故障となることがあ
り、主保護・後備保護リレーの動作を模擬できないとい
う問題点があつた。
Since the conventional power system simulation is as described above, it is necessary to simulate the operation of the main protection / reserve protection relay in the form of trainer settings. If the breaker is turned on, the system may be broken again and the operation of the main protection / reserve protection relay cannot be simulated.

この発明は上記のような問題点を解消するためになされ
たもので、系統故障発生時の主保護・後備保護リレーの
動作模擬を自動的に処理してしや断器状態の自動判定を
行うと共に、トレーニの誤操作により再び系統故障に至
つた場合にも、実系統と同じように、電力系統の動きを
シミユレーシヨンできる電力系統シミユレーシヨン方式
を得ることを目的とする。
The present invention has been made in order to solve the above problems, and automatically processes the operation simulation of the main protection / reserve protection relay when a system failure occurs and automatically determines the disconnection state. At the same time, it is an object of the present invention to obtain a power system simulation system that can simulate the movement of the power system in the same way as the actual system even when a system failure occurs again due to an erroneous operation of the trainee.

〔問題点を解決するための手段〕[Means for solving problems]

この発明に係る電力系統のシミユレーシヨン方式は、主
保護・後備保護リレーの動作模擬を、安定度計算をベー
スにして行い、その計算結果を周波数・潮流計算に反映
して、リアルタイムシミユレーシヨンを実現したもので
ある。
The simulation system of the power system according to the present invention simulates the operation of the main protection / reserve protection relay based on the stability calculation, reflects the calculation result in the frequency / power flow calculation, and realizes the real-time simulation. It was realized.

〔作用〕[Action]

この発明における電力系統のシミユレーシヨン方式は、
安定度計算をベースにして、主保護・後備保護リレーの
動作模擬を自動的に処理し、トレーニの訓練準備段階に
おける手動設定を不要にすると共に、訓練実行中のトレ
ーナによる誤操作にもとづいて、再故障に至つた場合の
訓練を、実系統と同じように行うことができるようにす
る。
The simulation system of the power system in the present invention is
Based on the stability calculation, the operation simulation of the main protection / reserve protection relay is automatically processed, eliminating the need for manual setting in the training preparation stage of the trainee, and re-operation based on the erroneous operation by the trainer during the training. To be able to perform training in case of failure just like in the real system.

〔実施例〕〔Example〕

以下、この発明の一実施例を図について説明する。 An embodiment of the present invention will be described below with reference to the drawings.

第1図において、1はCRT装置、2は事故シーケンスデ
ータフアイル、3はSV状変データフアイルであり、この
発明のシミユレーシヨン方式でも、過渡安定度計算のス
テツプと潮流・周波数計算のステツプとを実行す
る。
In FIG. 1, 1 is a CRT device, 2 is an accident sequence data file, and 3 is an SV-like data file. Even in the simulation system of the present invention, the step of transient stability calculation and the step of power flow / frequency calculation are executed. To do.

第2図は系統の故障の有無、過渡安定度計算および潮流
・周波数計算の動作状況を示す説明図である。
FIG. 2 is an explanatory diagram showing the presence / absence of a system fault, the operating conditions of transient stability calculation and power flow / frequency calculation.

次に上記実施例の動作を第3図(a),(b)のフロー
図に従つて具体的に説明する。
Next, the operation of the above embodiment will be specifically described with reference to the flow charts of FIGS. 3 (a) and 3 (b).

まず、訓練準備段階において、トレーナはCRT装置1の
画面において電力系統における故障発生時刻、故障点、
故障種別をライトペンを用いて設定する。設定された上
記データは事故シーケンスデータフアイル2に記憶され
る。続いて、脱調リレーを含む、主保護・後備保護リレ
ーの動作判定を、事故シーケンスデータフアイル2を入
力データとして、過渡安定度計算プログラムを実行する
ことによつて行い、その判定結果としての脱調リレーを
含む主保護・後備保護の動作リレーとしや断器(CB)の
各状態をSV状変データフアイル3に記憶する(ステツプ
)。
First, in the training preparation stage, the trainer displays the time of failure occurrence, failure point in the power system on the screen of the CRT device 1,
The failure type is set using a light pen. The set data is stored in the accident sequence data file 2. Next, the operation judgment of the main protection / reserve protection relay, including the step-out relay, is performed by executing the transient stability calculation program with the accident sequence data file 2 as the input data, and the judgment result is judged. It is used as a main protection / reserve protection operation relay including a control relay and each state of the breaker (CB) is stored in the SV-like variable data file 3 (step).

この過渡安定度計算は脱調リレーの動作判定が完了する
まで行う必要があるが、潮流・周波数計算の1サイクル
であるT秒(通常3〜5秒)まで実行する。なお、脱調
リレーの動作判定は通常1〜2秒であるので、上記の打
切り時間で十分である。
This transient stability calculation needs to be performed until the operation determination of the step-out relay is completed, but is performed until T seconds (normally 3 to 5 seconds) which is one cycle of the power flow / frequency calculation. Since the operation determination of the step-out relay is usually 1-2 seconds, the above-mentioned cutoff time is sufficient.

次に、訓練実行段階では、第1図に示すように主保護・
後備保護リレーの動作模擬を含む過渡安定度計算と電力
系統のシミユレーシヨンである潮流・周波数計算を並行
して実行する(ステツプ, )。また、第2図に示すように、訓練実行段階のスター
トからT秒までは、主保護・後備保護リレーの動作判定
を、訓練準備段階の過渡安定度計算(ステツプ)で行
つているので、過渡安定度計算は実行せず、潮流計算と
周波数計算を実行する(ステツプ)。
Next, at the training execution stage, as shown in Fig. 1, main protection and
The transient stability calculation including the operation simulation of the backup protection relay and the power flow / frequency calculation, which is the simulation of the power system, are executed in parallel (step, ). Also, as shown in FIG. 2, from the start of the training execution stage until T seconds, the operation judgment of the main protection / reserve protection relay is performed by the transient stability calculation (step) at the training preparation stage. Stability calculation is not executed, but power flow calculation and frequency calculation are executed (step).

その後のシミユレーシヨンステツプでは、過渡安定度計
算と潮流・周波数計算とを並行して処理する。
In the simulation step thereafter, the transient stability calculation and the tidal current / frequency calculation are processed in parallel.

ただし、過渡安定度計算は当該サイクル内で故障発生が
ない場合には実行しない。
However, the transient stability calculation is not executed unless there is a failure in the cycle.

また、過渡安定度計算は第3図(a),(b)に示すフ
ロー図の通りに処理するが、事故シーケンスフアイル2
から故障発生時刻、故障点、故障種別のデータを取出
し、当該時刻からT秒後の間に故障の発生があるなら
ば、過渡安定度計算を実行し、主保護・後備保護リレー
の動作模擬を行い、動作リレーとしや断器(CB)のデー
タとを時刻を付加して、SV状変データフアイル3に記憶
する。つまり、従来のように主保護・後備保護リレーの
動作模擬をトレーナが行うのでなく、過渡安定度計算に
よつて動作模擬を行つて、これをSVデータフアイル3に
記憶させる。
Further, the transient stability calculation is processed as shown in the flow charts of FIGS. 3 (a) and 3 (b), but the accident sequence file 2
The failure occurrence time, failure point, and failure type data are extracted from the data. If a failure occurs within T seconds after the time, the transient stability calculation is executed to simulate the operation of the main protection / reserve protection relay. The operation relay and the data of the breaker (CB) are added to the time and stored in the SV-like variable data file 3. In other words, the trainer does not simulate the operation of the main protection / reserve protection relay as in the conventional case, but simulates the operation by the transient stability calculation and stores it in the SV data file 3.

次に、処理のフローについて説明すると、まず当該サイ
クルで故障発生があるか否かを判定し(ステツプ)、
故障発生が無ければ計算を終了する。一方、故障発生が
有る場合には、当該サイクルより1サイクル前の潮流計
算結果を取込む(ステツプ)。そして発電機の内部電
圧と位相角の初期値を計算し(ステツプ)、さらに負
荷を定インピーダンス負荷扱いとするために、負荷の母
線電圧、有効電力と無効電力から負荷アドミタンスを計
算する(ステツプ)。
Next, the flow of processing will be described. First, it is determined whether or not a failure has occurred in the relevant cycle (step),
If no failure occurs, the calculation ends. On the other hand, if there is a failure, the result of power flow calculation one cycle before the current cycle is fetched (step). Then, the initial values of the generator internal voltage and phase angle are calculated (step), and in order to treat the load as a constant impedance load, the load admittance is calculated from the load bus voltage, active power and reactive power (step). .

次に、故障種別に応じて正相又は逆相又は零相回路のア
ドミタンス行列を計算する(ステツプ)。次に系統の
接続状態に変更があるかどうかを判定し(ステツプ
)、無い場合には回路網計算の処理へ分岐する。一
方、変更がある場合には続いて故障発生なのかどうかを
判定し(ステツプ)、故障発生でなければ故障除去の
有無の判定の処理へ移行する。一方、故障がある場合に
は、故障の種別に応じて正相回路に付加する故障等価イ
ンピーダンスを逆相と零相回路のアドミタンス行列にも
とづいて計算する(ステツプ)。
Next, the admittance matrix of the positive-phase or negative-phase or zero-phase circuit is calculated according to the fault type (step). Next, it is judged whether or not there is a change in the connection state of the system (step), and if there is no change, the process branches to the circuit network calculation process. On the other hand, if there is a change, it is subsequently determined whether or not a failure has occurred (step), and if there is no failure, the process proceeds to the determination processing of whether or not there is a failure removal. On the other hand, when there is a failure, the failure equivalent impedance added to the positive phase circuit is calculated based on the admittance matrix of the negative phase and zero phase circuits according to the type of failure (step).

次に、故障除去の有無を判定し(ステツプ)、無い場
合にはアドミタンス行列の変更に移行し、有る場合には
故障インピーダンスを無限大扱いとする処理を行う(ス
テツプ)。続いて、それらに伴う正相回路のアドミタ
ンス行列の変更の処理を行い(ステツプ)、次に、回
路網の電圧、電流の計算を行う(ステツプ)。
Next, it is determined whether or not the fault has been removed (step), and if there is no fault, the process moves to changing the admittance matrix, and if there is, a process of treating the fault impedance as infinite is performed (step). Then, the admittance matrix of the positive-phase circuit is changed accordingly (step), and then the voltage and current of the circuit network are calculated (step).

次にステツプで得た電圧,電流を用いて発電機の電気
出力を求め(ステツプ)、さらに、発電機の内部位相
角を、運動方程式 を解いて求める(ステツプ)。
Next, the electric output of the generator is obtained using the voltage and current obtained in the step (step), and the internal phase angle of the generator is calculated by the equation of motion. Solve for (step).

上記によつて、回路網の電圧,電流と発電機の内部位相
角が求まるので、次に脱調リレーを含む各種の主保護・
後備保護リレーの動作模擬を行う(ステツプ)。続い
て、ステツプの動作模擬により、リレー動作の有無を
判定し(ステツプ)、無い場合には、計算終了時間の
判定の処理へ移行する。一方、リレー動作がある場合に
は、そのリレー動作によりトリツプするしや断器(CB)
を選択し、そのデータをSV状変データフアイル3に保存
する(ステツプ)、続いて、計算時間がT秒に達した
か否かを判定し(ステツプ)、達していれば計算を終
了し、達していなければ時刻Δtだけ更新し、ステツプ
以下の処理を繰り返す。
Based on the above, the voltage and current of the network and the internal phase angle of the generator can be obtained.
Simulate the operation of a backup protection relay (step). Then, the presence or absence of the relay operation is determined by simulating the operation of the step (step), and if there is no relay operation, the process proceeds to the calculation end time determination process. On the other hand, if there is a relay operation, tripping or breaking (CB) occurs due to the relay operation.
To save the data in the SV-like variable data file 3 (step), and then determine whether the calculation time has reached T seconds (step). If it has not reached, the time is updated by Δt, and the processing from step is repeated.

一方、電力系統のシミユレーシヨンは、第1図に示すよ
うに、SV状変データフアイル3からしや断器(CB)の状
態変化データを時系列順に取出しながら、潮流計算と周
波数計算プログラムを実行し、過負荷リレー、周波数低
下リレーあるいは電力・無効電力制御装置の動作を模擬
することにより、電力系統のリアルタイムシミユレーシ
ヨンを行う。このリアルタイムシミユレーシヨンの詳細
を、第5図のフロー図に従つて以下に説明する。
On the other hand, the simulation of the power system executes the power flow calculation and the frequency calculation program while taking out the state change data of the SV-like variable data file 3 from the SV-like variable data file 3 in chronological order as shown in FIG. Real-time simulation of the electric power system is performed by simulating the operation of an overload relay, a frequency reduction relay, or a power / reactive power control device. The details of this real-time simulation will be described below with reference to the flowchart of FIG.

全体的動作としては、T秒毎に周波数計算と潮流計算を
結合して行い、さらに周波数計算はΔT秒のきざみでn
(=T/ΔT)回連続して計算する。
As an overall operation, frequency calculation and power flow calculation are combined every T seconds, and frequency calculation is performed in steps of ΔT seconds.
Calculate continuously (= T / ΔT) times.

つまり、周波数計算をΔT秒きざみでn(=T/ΔT)回
繰返し、その時点の潮流計算を1回実行し、全ての処理
を実時間のT秒で行つて、リアルタイムシミユレーシヨ
ンを実現している。なお、通常は、潮流計算と周波数計
算を、別々の計算機で分担処理して、リアルタイムシミ
ユレーシヨンを実現している。
In other words, frequency calculation is repeated n (= T / ΔT) times at intervals of ΔT seconds, power flow calculation at that point is executed once, and all processing is performed in real time T seconds to realize real-time simulation. is doing. Normally, the power flow calculation and the frequency calculation are shared by different computers to realize real-time simulation.

詳細な動作は、まず当該時刻のSV状変データフアイル3
からSV状変データを取出し開閉器状態の変化の有無を判
定し(ステツプ)、変化が有る場合には、系統分離計
算を実行してトレーニの誤操作により再故障の有無を判
定し、有る場合はSV状変データフアイル3にデータを保
存し、さらに分離系統の判定、系統のアドミタンス行列
の修正、分離系統の系統容量や合計慣性容量などの計算
を行う(ステツプ)。続いてこの系統分離計算の終了
後に、潮流計算を実行する(ステツプ)。一方、ステ
ツプで変化が無いと判定された場合には、負荷しや断
などによる母線の有効電力の不連続変化の有無をチエツ
クし(ステツプ)、変化がない場合には潮流計算の終
了と同様に各分離系統毎の系統周波数計算を実行し(ス
テツプ)、続いて系統周波数に応動するリレーの動作
模擬を行い(ステツプ)、これらの処理をn回(T/Δ
T)繰り返す。なお、ステツプにおいて不連続変化が
有ると判定された場合は、ステツプの処理を実行す
る。
The detailed operation is as follows: First, the SV-like data file 3 at that time.
If there is a change in the switch status, it is judged whether there is a change in the switch state (step). If there is a change, a system separation calculation is executed to determine whether there is a re-fault due to a malfunction of the trainee. The data is saved in the SV-like variable data file 3, and the isolated system is determined, the admittance matrix of the system is modified, and the system capacity and total inertial capacity of the separated system are calculated (step). Subsequently, after the completion of this system separation calculation, the power flow calculation is executed (step). On the other hand, if it is determined that there is no change in step, check whether there is a discontinuous change in the active power of the bus due to load or disconnection (step), and if there is no change, the same as the end of the power flow calculation. Then, the system frequency calculation for each separated system is executed (step), the operation of the relay that responds to the system frequency is simulated (step), and these processes are performed n times (T / Δ
T) Repeat. If it is determined that there is a discontinuous change in the step, the step process is executed.

こうして上記処理をn回繰返した場合には、その時点の
潮流計算を実行し(ステツプ)、さらに系統電圧、送
電線潮流などに応動する過負荷リレーあるいは電圧・無
効電力制御装置の動作模擬を実行し(ステツプ)、最
後に、1サイクルT秒の同期を取るためのリアルタイム
同期の処理(delay)を実行し(ステツプ)、T秒間
のシミユレーシヨンが完了する。続いて、次のサイクル
のシミユレーシヨンに入る。なお、トレーナによる系統
操作データは、シミユレーシヨンとは分離したプログラ
ムでSV状変データフアイル3に入力される。また、T秒
は通常3〜5秒、ΔTは0.25秒程度となる。
When the above process is repeated n times in this way, the power flow calculation at that time is executed (step), and the operation simulation of the overload relay or the voltage / reactive power control device that responds to the system voltage, power flow of the transmission line, etc. is executed. (Step), and finally, real-time synchronization processing (delay) for synchronization of one cycle T seconds is executed (step), and the simulation for T seconds is completed. Then, enter the simulation of the next cycle. The system operation data from the trainer is input to the SV-like variable data file 3 as a program separate from the simulation. Further, T seconds are usually 3 to 5 seconds and ΔT is about 0.25 seconds.

本発明による電力系統シミユレーシヨン方式では、系統
規模が小さい場合には、過渡安定度計算と潮流・周波数
計算を直列に実行しても、リアルタイムシミユレーシヨ
ンを実現できるが、通常の系統規模では潮流計算と周波
数計算を別々の計算機で分担処理し、さらに過渡安定度
計算はアレイプロセツサなどの高速演算プロセツサを用
いて、リアルタイムシミユレーシヨンを実現することに
なる。
In the power system simulation method according to the present invention, when the system scale is small, the real-time simulation can be realized even if the transient stability calculation and the power flow / frequency calculation are executed in series. Calculation and frequency calculation are shared by different computers, and for transient stability calculation, real-time simulation is realized by using a high-speed arithmetic processor such as an array processor.

〔発明の効果〕〔The invention's effect〕

以上のように、この発明によれば、主保護・後備保護リ
レーの動作模擬を、過渡安定度計算をベースにすること
によつて実現したので、訓練中におけるトレーニの誤操
作があつても、実際の系統と同じように系統の動きを模
擬でき、訓練効果を上げることができる効果がある。
As described above, according to the present invention, the operation simulation of the main protection / reserve protection relay is realized based on the transient stability calculation. The effect of being able to simulate the movement of the system as well as the system of and improving the training effect.

【図面の簡単な説明】[Brief description of drawings]

第1図はこの発明の一実施例による電力系統シミユレー
シヨン方式の処理概念図、第2図はこの処理概念図にも
とづく動作説明図、第3図は同じく過渡安定度計算の詳
細な処理フロー図、第4図は従来の電力系統シミユレー
シヨン方式の処理概念図、第5図は同じく潮流・周波数
計算の処理フロー図である。 1はCRT装置、2は事故シーケンスフアイル、3はSV状
変データフアイル。 なお、図中、同一符号は同一または相当部分を示す。
FIG. 1 is a conceptual diagram of processing of a power system simulation method according to an embodiment of the present invention, FIG. 2 is an operation explanatory diagram based on this conceptual diagram, and FIG. 3 is a detailed processing flowchart of the transient stability calculation, FIG. 4 is a processing conceptual diagram of a conventional power system simulation method, and FIG. 5 is a processing flow diagram of the same power flow / frequency calculation. 1 is a CRT device, 2 is an accident sequence file, and 3 is an SV-like data file. In the drawings, the same reference numerals indicate the same or corresponding parts.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】電力系統の故障に関する各種データを入力
データとして過渡安定度計算のプログラムを実行させ、
この実行結果である主保護・後備リレーとしゃ断器の状
態変化を示すSV状変データをSV状変データフアイルに保
存し、このSV状変データフアイルが出力する上記主保護
・後備リレーとしゃ断器のSV状変データにもとづき、潮
流・周波数計算のプログラムを実行させることにより電
力系統の動作を模擬する電力系統シミュレーション方式
において、上記主保護・後備保護リレーの動作模擬を上
記過渡安定度計算をベースにして実行し、この過渡安定
度計算結果にもとづき、上記潮流・周波数計算のプログ
ラムを実行させるようにしたことを特徴とする電力系統
シミュレーション方式。
1. A program for transient stability calculation is executed with various data relating to a failure of a power system as input data,
The result of this execution is to save the SV condition data showing the status change of the main protection / repair relay and circuit breaker in the SV condition data file, and the main protection / repair relay and circuit breaker output by this SV condition data file. In the power system simulation method that simulates the operation of the power system by executing the power flow / frequency calculation program based on the SV change data, the operation simulation of the main protection / reserve protection relay is based on the transient stability calculation. The power system simulation method is characterized in that the power flow / frequency calculation program is executed based on the transient stability calculation result.
JP60111839A 1985-05-24 1985-05-24 Power system simulation method Expired - Fee Related JPH06101900B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60111839A JPH06101900B2 (en) 1985-05-24 1985-05-24 Power system simulation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60111839A JPH06101900B2 (en) 1985-05-24 1985-05-24 Power system simulation method

Publications (2)

Publication Number Publication Date
JPS61270780A JPS61270780A (en) 1986-12-01
JPH06101900B2 true JPH06101900B2 (en) 1994-12-12

Family

ID=14571459

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60111839A Expired - Fee Related JPH06101900B2 (en) 1985-05-24 1985-05-24 Power system simulation method

Country Status (1)

Country Link
JP (1) JPH06101900B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2736133B2 (en) * 1989-10-05 1998-04-02 株式会社東芝 Power system training simulator

Also Published As

Publication number Publication date
JPS61270780A (en) 1986-12-01

Similar Documents

Publication Publication Date Title
CN110233477B (en) Stability control simulation system based on three-defense line simulation
CN110399671A (en) Synchronizing calculation method, device and the terminal of the protective relaying device of power grid
CN119561028A (en) A distribution network self-healing method, device, electronic equipment and storage medium
JPH06101900B2 (en) Power system simulation method
JP4845526B2 (en) System operation training equipment
JPH06101901B2 (en) Power system simulation method
JP4040847B2 (en) Training simulator and power system simulation method
JP2680166B2 (en) Power system simulation method
JPH06101899B2 (en) Power system simulation method
JPS61295831A (en) Power system simulation system
JPH06153396A (en) Power system frequency simulation method and power system training simulator
Zhang et al. Scenario building for operator training simulators using a transient stability program
JP2645200B2 (en) Power system operation training simulator
JP2880827B2 (en) Power system training simulator
JP3237869B2 (en) Power system operation training simulator
JPH08110809A (en) Power system simulator
JPH03261328A (en) Power system simulating method
JP2736133B2 (en) Power system training simulator
JPH05146071A (en) Power system operation training simulator
Kyuwa et al. Operator Training Simulator with real-time transient stability analysis
JP2575124B2 (en) Method of simulating operation of protection device
JPH05316651A (en) Simulating system for electric power system
CN110263457A (en) Test method, device, device and readable storage medium for in-situ protection device
JP2577392B2 (en) Pre-accident grid status creation method for automatic recovery in the event of a power grid accident
CN118586177A (en) A data processing method and device considering transient response of power system cascading failures

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees