JPH061946B2 - Work power failure operation device - Google Patents
Work power failure operation deviceInfo
- Publication number
- JPH061946B2 JPH061946B2 JP61098721A JP9872186A JPH061946B2 JP H061946 B2 JPH061946 B2 JP H061946B2 JP 61098721 A JP61098721 A JP 61098721A JP 9872186 A JP9872186 A JP 9872186A JP H061946 B2 JPH061946 B2 JP H061946B2
- Authority
- JP
- Japan
- Prior art keywords
- operation procedure
- work
- power
- procedure
- power failure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/20—Systems supporting electrical power generation, transmission or distribution using protection elements, arrangements or systems
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Description
【発明の詳細な説明】 [発明の技術分野] 本発明は配電系統の配電線の作業停電および復電に伴う
電力融通に必要な開閉器の切替操作を行なう作業停電操
作装置の改良に関するものである。Description: TECHNICAL FIELD OF THE INVENTION The present invention relates to an improvement of a work power failure operating device for performing switching operation of switches required for power interchange due to work power failure of a distribution line of a power distribution system and power restoration. is there.
[発明の技術的背景] 近年、配電系統における配電線の作業停電および復電に
伴う電力融通に必要な開閉器の切替操作を行なうものと
して、作業停電操作装置が採用されつつある。そして、
この種の従来の作業停電操作装置は電子計算機等のデジ
タル演算処理装置から構成されており、作業区間の停電
および復電は次のようにして実施されている。[Technical background of the invention] In recent years, a work power failure operating device has been adopted as a device for performing switch operation of a switch required for power interchange accompanying power failure and power recovery of a distribution line in a power distribution system. And
This type of conventional work power outage operation device is composed of a digital arithmetic processing device such as an electronic computer, and power outage and power recovery in a work section are carried out as follows.
(作業停電) 操作卓から、作業区間と作業停止をオペレータが指定す
ることにより、作業停電操作装置では作業区間以外の停
電区間を無くすべく電力融通計算を行ない、その計算結
果に基づいて配電系統の開閉器へ開または閉の制御信号
を送出し、その後に作業区間を停電操作するようにして
いる。(Work power outage) When the operator specifies a work section and a work stop from the operator console, the work power outage operation device performs power interchange calculation to eliminate the power outage section other than the work section, and based on the calculation result, the power distribution system A control signal for opening or closing is sent to the switch, and then the work section is operated for power failure.
(復電) 操作卓から、復電区間と作業終了をオペレータが指定す
ることにより、作業停電操作装置では原籍系統に戻すべ
く配電系統の開閉器へ開または閉の制御信号を送出する
ようにしている。(Power recovery) When the operator specifies the power recovery section and the end of work from the operator console, the work power outage control device sends an open or close control signal to the switch of the power distribution system to restore the original system. There is.
[背景技術の問題点] しかしながら、上述した従来の作業停電操作装置では以
下のような問題点がある。すなわち、作業停電時に配電
系統の切替操作を実施していることから、切替操作に多
くの時間を要するばかりでなく、また電力融通の不能箇
所が出た場合には予定外の停電箇所もしくは作業を中止
しなければならない。さらに、復電時においても原籍系
統へ戻すことから、作業区間が同時に複数ある場合には
復電時間が遅くなってしまう。[Problems of Background Art] However, the above-described conventional work power failure operating device has the following problems. That is, since the switching operation of the power distribution system is performed at the time of work blackout, not only does it take a lot of time for the switching operation, but also when there is a point where power cannot be accommodated, an unplanned power failure point or work is required. I have to stop. Furthermore, since the system is returned to the original system even at the time of power recovery, the power recovery time will be delayed if there are multiple work sections at the same time.
[発明の目的] 本発明は上述のような問題点を解決するためになされた
もので、その目的は停電操作に要する時間、ならびに復
電に要する時間の短縮化を図ることができ、また電力融
通の不能箇所が出たような場合でも予定外の停電箇所も
しくは作業を中止する必要がない信頼性の高い作業停電
操作装置を提供することにある。[Object of the Invention] The present invention has been made to solve the above problems, and an object of the present invention is to reduce the time required for a power outage operation and the time required for power recovery, and to reduce power consumption. An object of the present invention is to provide a highly reliable work power outage operation device which does not need to stop an unscheduled power outage or work even if an inflexible place appears.
[発明の概要] 上記の目的を達成するために本発明では、配電系統の配
電線の作業停電および復電に伴う電力融通に必要な開閉
器の切替操作を行なうものにおいて、上記開閉器の状態
信号およびフィーダ電流信号をオンライン情報として伝
送/制御する遠方監視制御装置と、作業区間の設定なら
びに切戻し系統の設定が可能な操作装置と、この操作装
置により作業停止前に作業区間が設定されると、上記オ
ンライン情報および予め記憶されている情報を基に電力
融通のための計算を行なう融通演算手段、この融通演算
手段による融通計算の結果に基づいて事前切替操作手順
の作成を行なう事前切替操作手順作成手段、この事前切
替操作手順作成手段による作成手順に基づいて作業区間
を停電するための停電操作手順の作成を行なう停電操作
手順作成手段、この停電操作手順作成手段による作成手
段の基づいて作業区間を復電するための復電操作手順の
作成を行なう復電操作手順作成手段、この復電操作手順
作成手段による作成手段に基づき上記操作装置からの切
戻し系統の設定内容に応じて作業前系統または原籍系統
へ切戻しするための切戻し操作手順の作成を行なう切戻
し操作手順作成手段、上記操作装置からの操作指令の内
容に応じて上記事前切替操作手順、停電操作手順、復電
操作手順、切戻し操作手順のうちの該当手順を実行させ
るべく制御信号を上記遠方監視制御装置へ送出する操作
手順実行手段よりなる作業停電操作器とを備えて構成さ
れ、作業開始前には事前切替操作を実行し、作業直前に
は停電操作を実行し、作業終了後には復電操作を実行
し、さらに作業前系統または原籍系統への切戻し操作を
実行するようにしたことを特徴とする。[Summary of the Invention] In order to achieve the above object, according to the present invention, a switch operation required for power interchange due to work power failure and power recovery of a distribution line of a distribution system is performed, and the state of the switch is Signal and feeder current signal are transmitted / controlled as online information, remote monitoring and control device, operation device that can set work interval and cutback system, and this operation device sets work interval before work is stopped. And an accommodation calculation means for performing calculation for power accommodation based on the online information and the previously stored information, and a pre-switching operation for creating a pre-switching operation procedure based on the result of the accommodation calculation by the accommodation calculation means. Procedure creation means, a power failure operator who creates a power failure operation procedure for power failure in the work section based on the procedure created by the advance switching operation procedure creation means A power recovery operation procedure creating means for creating a power recovery operation procedure for power recovery of a work section based on the power failure operation procedure creating means. Based on the setting content of the switching back system from the operating device, a switching back operation procedure creating means for creating a switching back operation procedure for switching back to the pre-working system or the original registration system, the operation command from the operating device Work consisting of operation procedure execution means for sending a control signal to the remote monitoring control device so as to execute a corresponding one of the pre-switching operation procedure, power outage operation procedure, power recovery operation procedure, and switchback operation procedure according to the content. It is configured with a power outage controller, performs pre-switching operation before starting work, executes power outage operation just before work, and restores power after work. Other is characterized in that so as to perform the switching back operation to domicile lineage.
本発明は、作業停止を、事前切替操作・停電操作・復電
操作・切戻し操作の4つの操作に振分けて、作業停止前
にこれら4つの操作手順をそれぞれ作成し、操作装置か
らの操作指令に応じて上述の事前切替操作手順、停電操
作手順、復電操作手順、切戻し操作手順の操作を、個々
に時間的に独立して実施できるようにしたものである。The present invention divides a work stop into four operations of a pre-switching operation, a power outage operation, a power recovery operation, and a switchback operation, respectively creates these four operation procedures before the work stop, and outputs an operation command from the operation device. Accordingly, the above-mentioned pre-switching operation procedure, power outage operation procedure, power recovery operation procedure, and switchback operation procedure can be individually and temporally executed.
[発明の実施例] 以下、上述に基づく本発明の一実施例について図面を参
照して説明する。Embodiments of the Invention Hereinafter, one embodiment of the present invention based on the above will be described with reference to the drawings.
第1図は、本発明による作業停電操作装置を配電系統に
適用した場合の構成例を示すものである。第1図におい
て、SSは配電変電所であり、通常変圧器TRを備え、
母線BUSからフィーダ(配電線)しゃ断器CBを介し
て配電線Fを導出している。この配電線Fを複数の区分
開閉器SWによりそれぞれ配電区間k1,k2,k3,
…に区分されると共に、他の配電線にも連けいされるよ
うに構成されている。CTはフィーダ電流(配電線導出
部の電流)を検出するため変流器、CMはフィーダ電流
測定器である。これら電流測定器の出力信号及びフィー
ダしゃ断器CBや区分開閉器SW等の開閉器のオン・オ
フ状態信号は信号伝送装置を構成する遠方監視制御装置
(以下、テレコンと称する)子局TC1,TC2,TC
3,…、およびテレコン親局TC0を介して制御所内の
監視盤KBおよび作業停電操作器CONTに入力され
る。監視盤KBは配電系統の現在時点の開閉器状態、フ
ィーダ電流等を表示し、作業停電操作器(電子計算機等
のディジタル演算処理装置で構成されている)CONT
はそのメモリ部に前記信号伝送装置から得られるオンラ
イン情報を記憶するほか各配電区間例えばk1,k2,
k3,…毎に予定された区間負荷電流値を記憶してい
る。尚、区間負荷電流は信号伝送装置を介してオンライ
ン情報として取り込むことも可能である。FIG. 1 shows a configuration example when the work power failure operating device according to the present invention is applied to a power distribution system. In FIG. 1, SS is a distribution substation, which is usually equipped with a transformer TR,
The distribution line F is derived from the bus BUS via a feeder (distribution line) breaker CB. This distribution line F is divided into distribution sections k 1 , k 2 , k 3 ,
It is divided into ... and connected to other distribution lines. CT is a current transformer for detecting the feeder current (current of the distribution line lead-out portion), and CM is a feeder current measuring instrument. The output signals of these current measuring devices and the ON / OFF state signals of the switches such as the feeder breaker CB and the classification switch SW are remote monitoring and control devices (hereinafter referred to as teleconverters) constituting the signal transmission device, slave station TC 1 , TC 2 , TC
3, ..., and is input to the monitoring panel KB and working blackout manipulator CONT control house via a telecontrol master station TC 0. The monitoring board KB displays the current switch condition of the power distribution system, the feeder current, etc., and the work power failure operation unit (comprised of a digital arithmetic processing unit such as a computer) CONT
Stores the online information obtained from the signal transmission device in its memory unit, and also distributes each power distribution section, for example, k 1 , k 2 ,
The section load current value scheduled for each k 3 , ... Is stored. The section load current can also be taken in as online information via the signal transmission device.
一方、操作卓Deskは作業区間の設定ならびに切戻し系統
の設定を行なうことが可能なものであり、また作業停電
操作器CONTは操作卓Deskにより作業停止前に作業区
間が設定されると、事前切替操作・停電操作・復電操作
・切戻し操作の4つの操作手順をそれぞれ作成し、かつ
操作卓Deskからの操作指令に応じてこれら事前切替操作
手順、停電操作手順、復電操作手順、切戻し操作手順の
操作を、個々に時間的に独立して実施するものである。On the other hand, the console Desk is capable of setting the working section and the switching back system, and the work power outage controller CONT indicates that the working section is set before the work is stopped by the Desk. Four operation procedures of switching operation, power failure operation, power recovery operation, and failback operation are created respectively, and these pre-switching operation procedures, power failure operation procedures, power recovery operation procedures, and switch operations are performed according to the operation commands from the operator desk. The operation of the return operation procedure is performed independently in terms of time.
第2図は、第1図における作業停電操作器CONTの構
成例を機能ブロック図にて示すものである。すなわち、
作業停電操作器CONTは第2図に示すように、上述の
操作卓Deskにより作業停止前に作業区間が設定される
と、上記オンライン情報および予め記憶されている情報
を基に電力融通のための計算を行なう融通演算手段1
と、この融通演算手段1による融通計算の結果に基づい
て事前切替操作手順の作成を行なう事前切替操作手順作
成手段2と、この事前切替操作手順作成手段2による作
成手段に基づいて作業区間を停電するための停電操作手
順の作成を行なう停電操作手順作成手段3、この停電操
作手順作成手段3による作成手段に基づいて作業区間を
復電するための復電操作手順の作成を行なう復電操作手
順作成手段4と、この復電操作手順作成手段4による作
成手段に基づき上記操作卓Deskからの切戻し系統の設定
内容に応じて作業前系統または原籍系統へ切戻しするた
めの切戻し操作手順の作成を行なう切戻し操作手順作成
手段5と、上記操作卓Deskからの操作指令の内容に応じ
て上記事前切替操作手順、停電操作手順、復電操作手
順、切戻し操作手順のうちの該当手順を実行させるべく
制御信号を上記テレコン親局TC0へ送出する操作手順
事項手段6とから構成している。FIG. 2 is a functional block diagram showing a configuration example of the work power outage operation unit CONT in FIG. That is,
As shown in FIG. 2, when the work section is set by the above-mentioned console Desk before the work is stopped, the work power cut operation unit CONT is provided for power interchange based on the online information and the information stored in advance. Flexible calculation means 1 for calculation
And a pre-switching operation procedure creating means 2 for creating a pre-switching operation procedure based on the result of the accommodation calculation by the accommodation calculating means 1, and a power interruption of the work section based on the creating means by the pre-switching operation procedure creating means 2. Power failure operation procedure creating means 3 for creating a power failure operation procedure for performing power recovery operation procedures, and a power recovery operation procedure for creating a power recovery operation procedure for recovering power in a work section based on the creating means by the power failure operation procedure creating means 3 Based on the creating means 4 and the creating means by the power recovery operating procedure creating means 4, a failback operation procedure for performing a failback to the pre-work system or the original control system according to the setting content of the switchback system from the console Desk. The fail-back operation procedure creating means 5 for creating the operation, the pre-switch operation procedure, the power failure operation procedure, the power recovery operation procedure, and the fail-back operation procedure according to the content of the operation command from the operator desk. A control signal in order to perform the Chino appropriate steps constituting the operation procedure matters means 6 for sending to said telecontrol master station TC 0.
次に、以上のように構成した作業停電操作装置の作用に
ついて詳細に説明する。Next, the operation of the work power failure operating device configured as described above will be described in detail.
作業停電操作器CONTは、操作卓Deskを介して与えら
れるオペレータからの指示(作業区間と作業終了後の復
旧系統および操作指令)に基づいて、下記のような処理
を行なう。The work power outage operation unit CONT performs the following processing based on an instruction (a work section, a recovery system after the work is completed, and an operation command) from the operator, which is given via the console Desk.
すなわち、まず作業区間と作業終了後の復旧系統(作業
前系統または原籍系統)の指示時には、第3図(a)に示
すフロー図に従って (a)融通演算手段1により、予め記憶されている情報と
オンライン情報とから、融通送電のための計算(以下、
融通計算と称する。) (b)事前切替操作手順作成手段2により、融通計算の結
果を基に事前切替操作手順の作成。That is, first, at the time of instructing the work section and the restoration system (pre-work system or original system) after the work is completed, (a) information stored in advance by the accommodation calculation means 1 according to the flowchart shown in FIG. 3 (a). And online information, calculations for flexible transmission (below,
This is called flexible calculation. (B) The advance switching operation procedure creating means 2 creates the advance switching operation procedure based on the result of the accommodation calculation.
(c)停電操作手順作成手段3により、作業区間を停電す
るための停電操作手順の作成。(c) The power failure operation procedure creating means 3 creates a power failure operation procedure for power failure in the work section.
(d)復電操作手順作成手段4により、作業区間を復電す
るための復電操作手順の作成。(d) The power recovery operation procedure creation means 4 creates a power recovery operation procedure for power recovery of the work section.
(e)切戻し操作手順作成手段5により、作業前系統また
は原籍系統へ切戻しするための切戻し操作手順作成。(e) The switchback operation procedure creating means 5 creates a switchback operation procedure for switching back to the pre-work system or the original system.
という一連の処理を行なう。以下、このような処理を総
括して操作手順の作成と称する。Perform a series of processing. Hereinafter, such processing will be collectively referred to as creation of an operation procedure.
次に、操作指令(事前切替操作、停電操作、送電操作、
切戻し操作のいずれか)の指示時には、第3図(b)に示
すフロー図に従って、 (f)事前切替操作指令時は、上記(b)で作成した切替操作
手順に従い、信号伝送装置を介して開閉器へ制御信号を
送出する。Next, operation commands (preliminary switching operation, power outage operation, power transmission operation,
3) (b) the flow chart shown in Fig. 3 (b), and (f) the pre-switching operation command, in accordance with the switching operation procedure created in (b) above, via the signal transmission device. Control signal to the switch.
(g)停電操作指令時は、上記(c)で作成した停電操作手順
に従い、信号伝送装置を介して開閉器へ制御信号を送出
する。(g) When a power failure operation command is issued, a control signal is sent to the switch via the signal transmission device according to the power failure operation procedure created in (c) above.
(h)送電操作指令時は、上記(d)で作成した送電操作手順
に従い、信号伝送装置を介して開閉器へ制御信号を送出
する。(h) When a power transmission operation command is issued, a control signal is sent to the switch via the signal transmission device in accordance with the power transmission operation procedure created in (d) above.
(i)切戻し操作指令時は、上記(e)で作成した切戻し操作
手順に従い、信号伝送装置を介して開閉器へ制御信号を
送出する。(i) When a switchback operation command is issued, a control signal is sent to the switch via the signal transmission device according to the switchback operation procedure created in (e) above.
という処理を操作手順実行手段6により行なう。この場
合(f)〜(i)は、運用上下記のタイミングで指示される。The processing is executed by the operation procedure executing means 6. In this case, (f) to (i) are instructed at the following timing in operation.
・事前切替操作指令…作業停止前いつでも可能 ・停電操作指令………作業開始時刻ジャスト ・復電操作指令………作業終了時刻ジャスト ・切戻し操作指令……作業終了後いつでも可能 以下、これらの(f)〜(i)を総括して操作の手順の実行と
称する。・ Advance switching operation command… Available at any time before work is stopped ・ Power failure operation command ………… Just at work start time ・ Power recovery operation command ………… Just at work end time ・ Switchback operation command …… Available at any time after work ends (f) to (i) are collectively referred to as the execution of an operation procedure.
次に、かかる操作手順の作成ならびに操作手順の実行の
詳細について具体的に述べる。Next, details of the creation of the operation procedure and the execution of the operation procedure will be specifically described.
(融通計算) 与えられた制約条件である1つ以上の停電区間と配電系
統の状態(区分開閉器と区間のつながりを示す情報すな
わち配電区間の両端に接続されている区分開閉器のどち
らが始端でどちらが終端であるかという情報や、開閉器
の開閉状態信号、更には変圧器は配電線の電流、各配電
区間の負荷電流)をもとにして健全な配電線から当該融
通送電の対象となっている停電区間群に対し、融通送電
するために目的関数に合致した最適な開閉器操作手順
(最適解)を求める計算をいう。尚、前記目的関数とは
例えば供給支障を最小化することや、融通送電機の各配
電線の予備力が平均化すること等をいう。(Interchange calculation) One or more power outage sections, which are the given constraint conditions, and the state of the distribution system (information indicating the connection between the section switches and sections, that is, which of the section switches connected to both ends of the distribution section is the start point) Based on the information about which is the end, the switching status signal of the switch, and the transformer's distribution line current, load current of each distribution section) This is a calculation to find the optimum switch operating procedure (optimal solution) that matches the objective function for the power transmission in the power failure section group. The objective function means, for example, minimizing supply disruption, averaging reserve capacity of each distribution line of the interchange power transmitter, and the like.
これを、配電系統図を参照しながら説明する。第4図は
健全時の状態を示し、K1,K2,K3が後に停電区間
群となる注目すべき配電区間群である。SS1,S
S2,SS3…SSXは配電変電所であり、フィーダし
ゃ断器CB1.CB2,CB3…CBXを介して配電線
F1,F2,F3…FXを導出している。注目すべき配
電区間群K1,K2,K3は全て配電線FXから送電さ
れており、これら配電区間群に隣接する配電線F1,F
2,F3の予備力はそれぞれF1:50[A],F2:
60[A],F3:10[A]であると仮定する。尚、
図中開閉器のシンボルを黒丸で示したものはオン状態、
白丸で示したものはオフ状態を示す。This will be described with reference to the distribution system diagram. FIG. 4 shows a state at the time of soundness, and K 1 , K 2 , and K 3 are noteworthy distribution section groups that will later become power failure section groups. SS 1 , S
S 2 , SS 3 ... SS X are distribution substations, feeder breakers CB 1 . Distribution lines F 1 , F 2 , F 3 ... F X are derived via CB 2 , CB 3 ... CB X. All of the noteworthy distribution section groups K 1 , K 2 , and K 3 are transmitted from the distribution line F X, and the distribution lines F 1 and F adjacent to these distribution section groups.
2 and F 3 have reserve forces of F 1 : 50 [A] and F 2 :
It is assumed that it is 60 [A] and F 3 : 10 [A]. still,
In the figure, the symbol of the switch is shown with a black circle is in the ON state,
The white circles indicate the off state.
この第4図の状態において、いま配電線FXの配電区間
KXを作業のために停電するとしてSWX,CBXをオ
フした場合、第5図に示すように配電区間K1〜K3ま
で停電となってしまう。この作業停電以外の停電区間群
(以下、停電区間と称する)K1〜K3の区間負荷の大
きさ(K1:30[A],K2:20[A],K3:1
0[A])、これら配電区間群に隣接する配電線の予備
力(F1:50[A],F2:60[A],F3:10
[A])、開閉機SW1〜SW2,SE4〜SW6の状
態信号を基に融通計算を行なう。In the state of this FIG. 4, SW X, if you turn off the CB X, distribution leg K 1 ~K 3 as shown in Figure 5 the distribution leg K X now distribution line F X as power failure for work There will be a power outage. This task blackout other blackout section group (hereinafter, blackout interval referred to) K 1 ~K 3 sections load magnitude (K 1: 30 [A] , K 2: 20 [A], K 3: 1
0 [A]), reserves of distribution lines adjacent to these distribution section groups (F 1 : 50 [A], F 2 : 60 [A], F 3 : 10)
[A]), and the interchange calculation is performed based on the status signals of the switches SW 1 to SW 2 and SE 4 to SW 6 .
以下、この融通計算について表を用いて説明する。先
ず、停電区間K1〜K3への融通計算を開始するにあた
り、停電区間群K1〜K3に直接接続され得る開閉機S
W1〜SW6を仮想的に全てオフ状態にしておく。Hereinafter, this interchange calculation will be described using a table. First, when starting the flexibility calculation to blackout interval K 1 ~K 3, the driving device S which may be connected directly to the power failure section group K 1 ~K 3
All of W 1 to SW 6 are virtually turned off.
次に停電区間群K1〜K3を区間負荷の小さい順になら
べる。(表1) そして、配電線F1〜F3が実際の配電区間相互の接続
状態を無視して区間負荷の大きさのみを判断要素として
停電区間群K1〜K3に送電したと仮定した場合、それ
ぞれの配電線F1〜F3が幾つの区間数まで送電できる
かについて判断する。この判断結果を表2に示す。Next, the blackout section groups K 1 to K 3 are arranged in order from the smallest section load. (Table 1) When it is assumed that the distribution lines F 1 to F 3 ignore the actual connection state between the distribution sections and transmit power to the power failure section groups K 1 to K 3 using only the size of the section load as a determination factor, It is determined how many sections the distribution lines F 1 to F 3 can transmit. The results of this judgment are shown in Table 2.
そして、与えられた停電区間数をα(この場合α=3)
とし、式α≧a1+a2+a3=Σaiを用いて、各配電
線の送電区間数aiの組み合わせを求め、これを表3とす
る。 Then, the given number of blackout sections is α (α = 3 in this case)
Then, using the formula α ≧ a 1 + a 2 + a 3 = Σai, the combination of the number of transmission sections ai of each distribution line is obtained, and this is shown in Table 3.
但し、0≦a1≦a1max 0≦a2≦a2max 0≦a3≦a3max 表3からa1,a2,a3それぞれの組み合わせのケー
スについて、系統のつながり上の制約条件および融通す
べき区間の負荷合計が、融通側配電線F1〜F3の予備
力を越えない範囲で融通区間を決定する。この決定され
た融通区間の組み合わせをパターン化して示す(表
4)。However, 0 ≦ a 1 ≦ a 1 max 0 ≦ a 2 ≦ a 2 max 0 ≦ a 3 ≦ a 3 max From Table 3, in the case of each combination of a 1 , a 2 , and a 3 , the constraint condition on the system connection and the total load of the sections to be accommodated do not exceed the reserve capacity of the interchange side distribution lines F 1 to F 3. The flexible section is determined by the range. This determined combination of the interchange sections is shown as a pattern (Table 4).
尚、表4のうち、パターン,,およびの如く、
1つの区間K1〜K3が同時に2つの配電線から融通送
電される場合は実用解ではないので、*印を付けて以後
の計算にはこれを除外する。 In addition, in Table 4, as
Since it is not a practical solution when one section K 1 to K 3 is simultaneously transmitted through two distribution lines, it is marked as * and excluded from the subsequent calculations.
次に、各パターンが目的関数(例えば供給支障の最小
化、融通後の各電線線の予備力の均平度Kpの最小化)
に合致するか否かの評価を行う。評価のための指標は表
5に示す通りである。尚、前記均平度KPは次の式から
求める。Next, each pattern is an objective function (for example, minimization of supply hindrance, minimization of flatness K p of reserve capacity of each wire after interchange).
It is evaluated whether or not The indexes for evaluation are shown in Table 5. The uniformity K P is calculated by the following formula.
ここで、FiYBは配電線iの融通送電後の予備力であ
る。 Here, Fi YB is the reserve capacity after the flexible transmission of the distribution line i.
この表5からわかるように、2つの目的関数のうち供給
支障最小を第1優先の目的関数とし、均平度KPを第2
位の目的関数としたとき、パターン12が最適解となる。 As can be seen from Table 5, of the two objective functions, the smallest supply hindrance is the first-priority objective function, and the flatness K P is the second objective function.
Pattern 12 is the optimal solution when the objective function of order is used.
以上の結果として、融通送電後の予備力はそれぞれ
F1:20[A],F2:30[A],F3:10
[A]となる。As a result of the above, the reserve capacity after the interchange power transmission is F 1 : 20 [A], F 2 : 30 [A], F 3 : 10, respectively.
It becomes [A].
尚、第4図の例は極めて単純な配電系統でありながら、
上述の如く評価すべきパターン数が17もある。実系統
で最適解を求めようとした場合、複雑な配電系統のため
数十万〜数百万のパターンを評価する必要があり、この
評価をオペレータが行うことは不可能であり、また上記
数十万〜数百万パターンを全てメモリに記載させること
は、メモリ容量が増大するので実用的でなく、現実には
パターンを生成する都度前回求めた解と比較し小さい方
の均平度のパターンを残すようにしている。Although the example of FIG. 4 is an extremely simple distribution system,
As described above, there are 17 patterns to be evaluated. When trying to find the optimum solution in an actual system, it is necessary to evaluate hundreds of thousands to millions of patterns due to the complicated distribution system, and it is impossible for the operator to perform this evaluation. It is not practical to have all 100,000 to several million patterns written in the memory because it increases the memory capacity. In reality, each time a pattern is generated, the pattern with the smaller averageness is compared to the previously obtained solution. I am trying to leave.
(事前切替操作手順の作成) 上述の融通計算結果に基づいて、事前切替操作手順とし
て表6を求める。(Creation of Advance Switching Operation Procedure) Table 6 is obtained as the advance switching operation procedure based on the above-mentioned interchange calculation result.
(停電操作手順の作成) 作業区間を停電させるべく両端の開閉器の操作手順とし
て表7を求める。 (Creation of power outage operation procedure) Table 7 is required as an operation procedure of the switches at both ends in order to cause a power failure in the work section.
(復電操作手順の作成) 作業区間を復電させるべく停電操作と逆の操作手順とし
て表8を求める。 (Creation of power recovery operation procedure) Table 8 is obtained as an operation procedure reverse to the power failure operation in order to restore power to the work section.
(切戻し操作手順の作成) 切戻し操作には、原籍系統(設備の設置段階で決められ
ている系統)への切戻しと、作業前系統への切戻しとの
2つがあり、操作卓Deskからの指示に応じてどちらか1
つの切戻し操作手順を求める。 (Creating a revertive operation procedure) There are two revertive operations: a revert to the original system (a system determined at the installation stage of the equipment) and a pre-operation system. Either depending on the instructions from
Call for one switchback procedure.
(1)原籍系統への切戻し操作 予め記憶している設備の接がり情報を基に、復電後の系
統より原籍系統への切戻し手順を求める。(1) Switch-back operation to the original system The switch-back procedure from the system after power recovery to the original system is calculated based on the stored contact information of the equipment.
(2)作業前系統への切戻し操作 作業前系統に戻すべく切替操作手順と逆の操作手順とし
て表9を求める。(2) Switch-back operation to the pre-work system To obtain the pre-work system, Table 9 is obtained as the reverse operation procedure to the switching operation procedure.
(事前切替操作手順実行) 表6で求めた事前切替操作手順に従い、伝送装置を介し
て順次開始器に制御信号(開又は閉)を送出する。この
事前切替操作手順実行後の配電系統図を第6図に示す。 (Execution of pre-switching operation procedure) In accordance with the pre-switching operation procedure obtained in Table 6, a control signal (open or closed) is sequentially sent to the starter via the transmission device. FIG. 6 shows a distribution system diagram after the execution of this pre-switching operation procedure.
(停電操作手順実行) 表7で求めた停電操作手順に従い、伝送装置を介して順
次開閉器に制御信号(開又は閉)を送出する。この停電
操作手順実行後の配電系統図を第7図に示す。(Execution of power failure operation procedure) In accordance with the power failure operation procedure obtained in Table 7, control signals (open or closed) are sequentially sent to the switches via the transmission device. FIG. 7 shows a power distribution system diagram after executing the power failure operation procedure.
(送電操作手順実行) 表8で求めた復電操作手順に従い、伝送装置を介して順
次開閉器に制御信号(開又は閉)を送出する。この送電
操作手順実行後の配電系統図を第6図に示す。(Execution of power transmission operation procedure) According to the power recovery operation procedure obtained in Table 8, a control signal (open or closed) is sequentially transmitted to the switches via the transmission device. A distribution system diagram after execution of this power transmission operation procedure is shown in FIG.
(切戻し操作手順実行) 作業前系統に戻す場合を例にとると、表9で求めた切戻
し操作手順に従い伝送装置を介して開閉器に制御信号
(開又は閉)を送出する。この操作終了により、第4図
に示すような作業前系統となる。(Execution of switchback operation procedure) Taking the case of returning to the pre-work system as an example, a control signal (open or closed) is sent to the switch via the transmission device according to the switchback operation procedure obtained in Table 9. Upon completion of this operation, the pre-work system as shown in FIG. 4 is obtained.
以上の操作により、当該作業区間の停電、復電を行なう
ことが可能である。By the above operation, it is possible to perform power failure and power recovery in the work section.
尚、本発明は上述した実施例に限定されるものではな
く、その要旨を変更しない範囲で種々に変形して実施す
ることができるものである。It should be noted that the present invention is not limited to the above-described embodiments, but can be modified in various ways without departing from the scope of the invention.
[発明の効果] 以上説明したように本発明によれば、停電操作に要する
時間、並びに復電に要する時間の短縮化を図ることがで
き、また電力融通の不能箇所が出たような場合でも予定
外の停電箇所もしくは作業を中止する必要がない極めて
信頼性の高い作業停電操作装置が提供できる。EFFECTS OF THE INVENTION As described above, according to the present invention, the time required for a power outage operation and the time required for power recovery can be shortened, and even when a portion where power cannot be accommodated appears. It is possible to provide an extremely reliable work power outage operation device that does not need to stop an unplanned power outage or work.
第1図は本発明の一実施例を示す構成図、第2図は同実
施例における作業停電操作器CONTの詳細を示す機能
ブロック図、第3図(a),(b)第4図乃至第7図は同実施
例における作用をそれぞれ説明するための図である。 1…融通演算手段、2…事前切替操作手順作成手段、3
…停電操作手順作成手段、4…復電操作手順作成手段、
5…切戻し操作手順作成手段、6…操作手順実行手段、
CONT…作業停電操作器、Desk…操作卓、TC0…テ
レコン親局、TC1〜TC3…テレコン子局。FIG. 1 is a configuration diagram showing an embodiment of the present invention, FIG. 2 is a functional block diagram showing details of a work power failure operation unit CONT in the embodiment, FIGS. 3 (a) and 3 (b), FIG. 4 to FIG. FIG. 7 is a diagram for explaining the operation in the same embodiment. 1 ... accommodation calculation means, 2 ... advance switching operation procedure creation means, 3
… Power failure operation procedure creation means, 4… Power recovery operation procedure creation means,
5 ... switchback operation procedure creating means, 6 ... operation procedure executing means,
CONT ... work a power outage operating unit, Desk ... console, TC 0 ... teleconverter master station, TC 1 ~TC 3 ... Telecom slave station.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 森山 和美 東京都府中市東芝町1番地 株式会社東芝 府中工場内 (72)発明者 鈴木 博 東京都府中市東芝町1番地 株式会社東芝 府中工場内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Kazumi Moriyama No. 1 in Toshiba Fuchu factory, Fuchu-shi, Tokyo (72) Inventor Hiroshi Suzuki No. 1 Toshiba-machi in Fuchu, Tokyo Tokyo Fuchu factory, Ltd.
Claims (1)
伴う電力融通に必要な開閉器の切替操作を行なうものに
おいて、前記開閉器の状態信号およびフィーダ電流信号
をオンライン情報として伝送/制御する遠方監視制御装
置と、作業区間の設定ならびに切戻し系統の設定が可能
な操作装置と、この操作装置により作業停止前に作業区
間が設定されると、前記オンライン情報および予め記憶
されている情報を基に電力融通のための計算を行なう融
通演算手段、この融通演算手段による融通計算の結果に
基づいて事前切替操作手順の作成を行なう事前切替操作
手順作成手段、この事前切替操作手順作成手段による作
成手順に基づいて作業区間を停電するための停電操作手
順の作成を行なう停電操作手順作成手段、この停電操作
手順作成手段による作成手段に基づいて作業区間を復電
するための復電操作手順の作成を行なう復電操作手順作
成手段、この復電操作手順作成手段による作成手順に基
づき前記操作装置からの切戻し系統の設定内容に応じて
作業前系統または原籍系統へ切戻しするための切戻し操
作手順の作成を行なう切戻し操作手順作成手段、前記操
作装置からの操作指令の内容に応じて前記事前切替操作
手順、停電操作手順、復電操作手順、切戻し操作手順の
うちの該当手順を実行させるべく制御信号を前記遠方監
視制御装置へ送出する操作手順実行手段よりなる作業停
電操作器とを備えて構成され、作業開始前には事前切替
操作を実行し、作業直前には停電操作を実行し、作業終
了後には復電操作を実行し、さらに作業前系統または原
籍系統への切戻し操作を実行するようにしたことを特徴
とする作業停電操作装置。Claim: What is claimed is: 1. A switch for switching a switch, which is necessary for power interchange due to a work power failure and a power recovery of a distribution line of a distribution system, wherein the switch status signal and feeder current signal are transmitted / controlled as online information. A remote monitoring control device, an operating device capable of setting a working section and a switching-back system, and when the working section is set by the operating device before the work is stopped, the online information and previously stored information An accommodation calculation means for performing calculation for power accommodation based on the above, an advance switching operation procedure creation means for creating an advance switching operation procedure based on the result of the accommodation calculation by this accommodation operation means, and this advance switching operation procedure creation means A power failure operation procedure creating means for creating a power failure operation procedure for power failure in the work section based on the creation procedure, and this power failure operation procedure creating means. A power recovery operation procedure creating means for creating a power recovery operation procedure for power recovery of the work section based on the creating means, and setting of a failback system from the operating device based on the creation procedure by the power recovery operation procedure creating means A switchback operation procedure creating means for creating a switchback operation procedure for switching back to the pre-work system or the original system according to the content, the advance switching operation procedure according to the content of the operation command from the operation device, A power outage operation procedure, a power recovery operation procedure, and a work power outage operation apparatus comprising operation procedure execution means for sending a control signal to the remote monitoring control device so as to execute the corresponding procedure of the switchback operation procedure, Before the work starts, the pre-switching operation is executed, the power outage operation is executed immediately before the work, the power recovery operation is executed after the work, and the switchback operation to the pre-work system or the original system is executed. Work power failure operation apparatus according to claim that it has to.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP61098721A JPH061946B2 (en) | 1986-04-28 | 1986-04-28 | Work power failure operation device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP61098721A JPH061946B2 (en) | 1986-04-28 | 1986-04-28 | Work power failure operation device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS62254620A JPS62254620A (en) | 1987-11-06 |
| JPH061946B2 true JPH061946B2 (en) | 1994-01-05 |
Family
ID=14227383
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP61098721A Expired - Lifetime JPH061946B2 (en) | 1986-04-28 | 1986-04-28 | Work power failure operation device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH061946B2 (en) |
-
1986
- 1986-04-28 JP JP61098721A patent/JPH061946B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS62254620A (en) | 1987-11-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5475558A (en) | Electrical power distribution device with isolation monitoring | |
| JPS6328238A (en) | Load group controller of motor or the like | |
| JPH061946B2 (en) | Work power failure operation device | |
| JP2645003B2 (en) | Distribution system operating device | |
| JPH0739074A (en) | Substation equipment | |
| JPH05328455A (en) | Distributed control system | |
| JPH061945B2 (en) | Distribution system operating device | |
| JP2561018B2 (en) | Transmission line interface switching device | |
| CN109240194A (en) | Electric machine control system and control method for engineering of water treatment | |
| CN111090235A (en) | Control system switching device and method | |
| JP3045748B2 (en) | Power supply switching method | |
| JPH0568085A (en) | Station data setting system for automatic exchange | |
| JPH0746762A (en) | Distribution system operating device | |
| JPH0246217Y2 (en) | ||
| JPS6043550B2 (en) | Communication line control device | |
| JPH0767237B2 (en) | Power system operating device | |
| CN115219826A (en) | Prepared self-throwing test method, device and standby self-throwing tester | |
| JPS6125224A (en) | Power supply controller | |
| JPS58188990A (en) | Control system of key telephone system | |
| JP2749443B2 (en) | How to create a planned distribution system | |
| CN115267381A (en) | A universal analog circuit breaker | |
| JPS6343558Y2 (en) | ||
| JPH02189095A (en) | Changeover system for 3-stage switch | |
| JPS63117624A (en) | Electric source system controller | |
| JPS63114533A (en) | Power factor control system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| EXPY | Cancellation because of completion of term |