JPH0622367B2 - Cable installation method in cave - Google Patents
Cable installation method in caveInfo
- Publication number
- JPH0622367B2 JPH0622367B2 JP18212489A JP18212489A JPH0622367B2 JP H0622367 B2 JPH0622367 B2 JP H0622367B2 JP 18212489 A JP18212489 A JP 18212489A JP 18212489 A JP18212489 A JP 18212489A JP H0622367 B2 JPH0622367 B2 JP H0622367B2
- Authority
- JP
- Japan
- Prior art keywords
- cable
- trough
- roller
- work
- cave
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title claims description 14
- 238000009434 installation Methods 0.000 title claims 2
- 230000005540 biological transmission Effects 0.000 description 4
- 238000004804 winding Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 239000000498 cooling water Substances 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Electric Cable Installation (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は、洞道内にケーブルを布設する方法に関し、特
に、作業台車等のような大きな装置を使用せずに、ケー
ブルラックの上の部分に配置したトラフ内に、ケーブル
を布設することが出来るようにする方法に関する。Description: FIELD OF THE INVENTION The present invention relates to a method of laying cables in a cave, and in particular to the upper part of a cable rack without the use of large equipment such as a work trolley. A method for enabling a cable to be laid in a trough arranged in.
(従来の技術) 高圧送電線を布設する洞道内では、作業用通路を挟ん
で、その両側にケーブルラックを配置しており、それぞ
れのケーブルラックには、上下方向に複数のトラフ支持
材を設けて、各トラフ支持材に設けたトラフ内に、3本
ずつの高圧送電ケーブルを収容させるようにしている。
また、前記ケーブルは、275KVのOFケーブルの場
合、1m当たりの重量が35kg程度で、径が13〜4cm
程度ある。(Prior Art) Inside a cavern where a high-voltage transmission line is laid, cable racks are placed on both sides of a working passage, and each cable rack is provided with a plurality of trough support members in the vertical direction. Thus, three high-voltage power transmission cables are housed in the troughs provided on each trough support member.
In the case of the 275KV OF cable, the cable has a weight per meter of about 35 kg and a diameter of 13 to 4 cm.
There is a degree.
前述したような洞道において、低い位置に設けたトラフ
支持材にケーブルを布設する際には、例えば特公昭55
−38885号公報等に示されるような作業台車を用い
ることが出来る。前記台車は、洞道の中央部の床に延線
されたケーブルを、作業台車に設けたローラ手段によっ
て上方に案内し、その持上げたケーブルを端部から順に
トラフ支持材内に送り込むようにして、ケーブルの布設
の作業を連続して行うことが出来るようにされる。When installing a cable on a trough support member provided at a low position in a cave as described above, for example, Japanese Patent Publication No.
It is possible to use a work carriage as disclosed in Japanese Patent Publication No. 38885. The trolley is configured such that the cable extended to the floor in the center of the cave is guided upward by the roller means provided on the work trolley, and the lifted cable is sequentially fed into the trough support member from the end. The cable laying work can be done continuously.
ところが、前述したような作業の作業台車は、ケーブル
ラックの上部のトラフ支持材が2m以上も高い位置に設
けられている場合には、台車の作業床が高い位置に設定
されることと、その安定性が良くない等の理由により、
非常に作業性が良くないという問題がある。However, in the work cart for the above-described work, when the trough support member on the upper part of the cable rack is provided at a position higher than 2 m, the work floor of the cart is set to a high position, and For reasons such as poor stability,
There is a problem that workability is very poor.
そこで、上部のトラフに対してケーブルを布設する際に
は、実公昭60−15840号公報等に示されるよう
に、安定性を向上させた作業台車を用いるようにする場
合がある。この従来例に示される作業台車は、台車の上
部にガイドレールに案内される手段を設け、走行車輪を
洞道の床に設けた溝に沿って移動させるように構成して
いる。Therefore, when a cable is laid on the upper trough, a work carriage having improved stability may be used as shown in Japanese Utility Model Publication 60-15840. The work trolley shown in this conventional example is provided with a means to be guided by a guide rail on the upper part of the trolley, and the traveling wheels are configured to move along a groove provided on the floor of the tunnel.
また、前記台車の作業台には、ケーブルを側部に案内す
るためのガイド手段を設けていて、ケーブルをトラフに
向けて移動させる際に、その作業を容易に行い得るよう
にしている。Further, the work table of the truck is provided with a guide means for guiding the cable to the side part so that the work can be easily performed when the cable is moved toward the trough.
(発明が解決しようとする問題点) しかしながら、前述したような従来の洞道内ケーブル布
設方法においては、台車等の装置が比較的大きく構成さ
れる必要がある。また、ケーブルが大容量のものとなっ
ている現状では、該ケーブルの単位長さ当たりの重量が
比較的重いものとなり、該台車からケーブルをトラフに
向けて移動させるための作業を、小数の作業員によって
行うことが困難であるという問題がある。(Problems to be Solved by the Invention) However, in the conventional cavernous cable laying method as described above, a device such as a truck needs to be relatively large. In addition, in the present situation where the cable has a large capacity, the weight per unit length of the cable is relatively heavy, and the work for moving the cable from the trolley toward the trough is a small number of works. There is a problem that it is difficult for a member to do.
これに対して、作業台車上や、トラフの部分に多くの作
業員が乗って、ケーブルを人力で移動させて布設の作業
を行うことは、安全性等の面で大きな問題があり、必ず
しも作業能率を向上させることにもならない。On the other hand, it is a problem in terms of safety that many workers ride on work trolleys or troughs and manually move cables to perform laying work. It also does not improve efficiency.
さらに、前述したような作業台車を用いない場合には、
上部のトラフに対応した高さに足場を組み、該足場上で
ケーブルを延線してから、そのケーブルをトラフ上に移
動させるような手段を用いることが必要であり、例え
ば、1つのドラムに巻かれたケーブルが6〜700mも
ある場合に、そのケーブルを全て作業員が持上げて移動
させるようにすることは、非常に手間のかかる作業を強
いられるという問題がある。Furthermore, when the work cart as described above is not used,
It is necessary to install a scaffold at a height corresponding to the upper trough, to extend a cable on the scaffold, and then to use a means for moving the cable onto the trough, for example, one drum When the wound cable has a length of 6 to 700 m, it is very laborious for the operator to lift and move all the cables.
(発明の目的) 本発明は、上記したような従来のケーブル布設方法の欠
点を解消するもので、比較的簡単な設備を用いて、ケー
ブルを洞道内で延線し得るとともに、トラフに向てて容
易に移動させて、布設の作業をより能率的に行い得るよ
うにする洞道内ケーブル布設方法を提供することを目的
としている。(Object of the Invention) The present invention solves the above-mentioned drawbacks of the conventional cable laying method, and uses a relatively simple facility to extend the cable in the cave and to the trough. It is an object of the present invention to provide a cable laying method in a cave that can be moved easily and easily to perform the work of laying more efficiently.
(問題点を解決するための手段および作用) 本発明の洞道内ケーブル布設方法は、上下方向に多数の
棚を設けたケーブルラックを配置し、該ケーブルラック
に対応して支柱を配置して構成した洞道における作業方
法に関する。(Means and Actions for Solving Problems) The method for laying a cable in a cave according to the present invention is configured by arranging a cable rack provided with a large number of shelves in the vertical direction and arranging columns corresponding to the cable rack. Regarding working methods in a closed cave.
本発明においては、洞道内の支柱に対して、棚の高さに
合せて取付けブラケットを設け、該取付けブラケットを
介してケーブルを案内するためのローラと、該ケーブル
の延線を行うためのケーブル送り出し装置とを配置する
とともに、棚のトラフとの間に配置するスライド棒を取
付け出来るように構成している。In the present invention, a mounting bracket is provided to the pillar in the cave according to the height of the shelf, a roller for guiding the cable through the mounting bracket, and a cable for extending the cable. The feeding device is arranged, and a slide rod arranged between the trough of the shelf is attached.
そして、前記ローラ装置によってケーブルを延線した後
で、一定の区間毎にスライド棒を配置し、該スライド棒
を配置した区間のローラ装置を揺動させて、ケーブルに
対する支持を解除し、スライド棒に支持されるケーブル
を、該スライド棒の傾斜にしたがって、トラフに向けて
移動させることにより、トラフ内にケーブルを収容させ
るようにすることが出来る。Then, after the cable is extended by the roller device, slide bars are arranged at regular intervals, and the roller device in the section in which the slide bars are arranged is rocked to release the support for the cable. By moving the cable supported on the trough toward the trough according to the inclination of the slide rod, the cable can be accommodated in the trough.
したがって、本発明の洞道内ケーブル布設方法において
は、台車等を用いることなしに、連続してケーブルの布
設の動作を行うことが出来るとともに、作業用の通路を
十分に確保し、作業を安全に行うことが出来る。Therefore, in the method for laying a cable in a cave according to the present invention, it is possible to continuously perform the operation of laying the cable without using a trolley, etc., and also to secure a sufficient passage for work to ensure safe work. You can do it.
本発明に使用される装置は、各支柱に取付けられる取付
けブラケットと、該ブラケットに設けられるローラ装
置、および、ケーブルを横方向に移動させるためのスラ
イド棒のみであり、それ等の各作業部材を、構成の簡単
なものとすることが出来る。The device used in the present invention is only a mounting bracket attached to each strut, a roller device provided in the bracket, and a slide rod for laterally moving the cable. , The configuration can be simple.
また、ケーブルの布設の作業を行うに際しては、ローラ
装置によってケーブルを長さ方向に移動させることと、
スライド棒上で自重によって摺動させることにより、該
ケーブルを横方向へ移動させる動作を行うことが出来る
ので、トラフ上へのケーブルの移動の作業を容易に行い
得るものとなる。In addition, when performing the work of laying the cable, moving the cable in the length direction by the roller device,
By sliding on the slide rod by its own weight, the operation of moving the cable in the lateral direction can be performed, so that the work of moving the cable on the trough can be easily performed.
(実施例) 図示された例に従って、本発明の洞道内ケーブル布設方
法を説明する。(Example) The method of laying a cable in a cave according to the present invention will be described with reference to the illustrated example.
第1図に示されるように、洞道内でケーブル20の布設
を行う際には、洞道の所定の区間に亘って、例えば、ケ
ーブルの1巻きの長さに相当する区間(例えば275k
v用のOFケーブルの長さ650m区間)で、各支柱2
に対して所定の高さで取付けブラケット30を固定し、
各取付けブラケットに設けたブロック35に対して、ロ
ーラ装置40を取付ける作業を行う。また、前記ローラ
装置に対して、所定の間隔毎にケーブル送り出し装置2
5を配置し、ケーブル20に無理な張力を付与せずに延
線を行い得るようにする。As shown in FIG. 1, when laying the cable 20 in the cave, for example, a section corresponding to the length of one turn of the cable (for example, 275 k
In the 650m long section of the OF cable for v), each post 2
Fix the mounting bracket 30 at a predetermined height against
The roller device 40 is attached to the block 35 provided on each mounting bracket. Further, the cable feeding device 2 is provided at predetermined intervals with respect to the roller device.
5 is arranged so that the wire can be extended without applying excessive tension to the cable 20.
そして、洞道の一定の区間毎に配置されるマンホールの
部分に、ケーブルの繰出装置と巻き取り装置とをそれぞ
れ配置して、巻き取り装置によりケーブルの端部に接続
したワイヤ等を巻き取る動作を行う。An operation of winding a wire or the like connected to the end of the cable by the winding device, by arranging a cable feeding device and a winding device in the manhole portion arranged in each fixed section of the cave I do.
前記動作と同時に、洞道内の所定区間毎に配置した各ケ
ーブル送り出し装置25により送り、ケーブルを各ロー
ラ装置40に沿って移動させて、洞道内でのケーブルの
延線の作業を行う。Simultaneously with the above operation, the cables are fed by the respective cable feeding devices 25 arranged in each predetermined section in the cave, and the cables are moved along the respective roller devices 40 to perform the work of extending the cable in the cave.
全部のケーブルを洞道に対して延線した状態では、該ケ
ーブル20はローラ上に支持された状態にある。また、
各ローラ装置40は、その支持アームの端部がワイア4
5により接続されていて、ローラ41上をケーブルが移
動する際に、支持アームが振れたりすること、ローラ装
置に細かい振動が加えられることによる、騒音の発生を
防止することが出来る。In the state where all the cables are extended to the sinus, the cable 20 is supported on the rollers. Also,
Each roller device 40 has a wire 4 at the end of its support arm.
It is possible to prevent the generation of noise due to the support arm swinging when the cable moves on the roller 41 and the fine vibration applied to the roller device.
前記第1図に示される実施例において、区間Aはケーブ
ルの延線を行っている状態を示し、区間Bはローラによ
る支持状態を解除して、スライド棒50にケーブルを支
持させた状態を、区間Cはケーブルをトラフ内に収容し
た状態を示している。In the embodiment shown in FIG. 1, the section A shows a state in which the cable is extended, and the section B shows a state in which the support state by the roller is released and the slide rod 50 supports the cable. Section C shows a state in which the cable is housed in the trough.
すなわち、本発明のケーブル布設方法においては、区間
Aに示されるようにして、ケーブル20をローラ装置4
0のローラ41により案内する状態で、ケーブル送り出
し装置25によって長さ方向に移動させ、所定の布設区
間全部にケーブルを延線する。なお、前記ケーブル送り
出し装置25は、取付けブラケットによって支柱2に支
持されているが、ケーブルを延線する際に、そのケーブ
ルの長さ方向に引張り力が付与されるので、この張力に
対向させるために、両側の支柱に対してワイヤ等の連接
部材27、27を接続して、1つの支柱にのみ力が作用
することがないようにされる。That is, in the cable laying method of the present invention, the cable 20 is connected to the roller device 4 as shown in the section A.
In the state of being guided by the roller 41 of 0, it is moved in the length direction by the cable feeding device 25 and the cable is extended to the entire predetermined laying section. The cable feeding device 25 is supported by the supporting column 2 by a mounting bracket, but when the cable is extended, a pulling force is applied in the length direction of the cable, so that the cable feeding device 25 is opposed to this tension. Further, connecting members 27, 27 such as wires are connected to the columns on both sides so that the force does not act on only one column.
前述したようにして、ローラ装置に沿ってケーブル20
を延線した後て、該ケーブルをトラフ15に移載する際
には、一定の区間(例えば、35m程度の長さ)に区切
って、取付けブラケット30とトラフ支持材12との間
を接続するような状態で、各支柱2の部分に符号a1で
示されるようにして、スライド棒50を取付ける そして、前記スライド棒を設けた部分で、区間Bに示さ
れるようにして、ローラ装置を揺動させるための作業が
行われる。このローラ装置を揺動させるための構成は、
第2図にもとづいて説明を行うが、装置の取付けブロッ
ク35に対して、支持アームを支持するピンを引抜くこ
とによって行われる。As described above, the cable 20 is installed along the roller device.
When the cable is transferred to the trough 15 after being extended, the mounting bracket 30 and the trough support member 12 are connected to each other by dividing into a certain section (for example, a length of about 35 m). In such a state, the slide bar 50 is attached to each of the columns 2 as indicated by reference numeral a1. Then, at the portion where the slide bar is provided, the roller device is swung as shown in the section B. Work to do so is performed. The structure for swinging this roller device is
As will be described with reference to FIG. 2, this is performed by pulling out a pin supporting the support arm from the mounting block 35 of the device.
つまり、支持アーム42の端部をブロック35に支持し
た状態で、支持ピンを引き抜くと、ローラ装置40は支
持ピンを中心にして下方に揺動して、符号b1に示され
るようにして、ケーブル20に対する支持状態から解放
される。That is, when the support pin is pulled out while the end portion of the support arm 42 is supported by the block 35, the roller device 40 swings downward about the support pin, and as shown by reference numeral b1, the cable The support state for 20 is released.
そして、ケーブル20はスライド棒50の上にのみ支持
される状態となり、該スライド棒の傾斜にしたがって、
ケーブルの自重により摺動して、トラフ15に向けて移
動され得るようになる。The cable 20 is supported only on the slide rod 50, and the inclination of the slide rod causes
The cable is slid by its own weight so that it can be moved toward the trough 15.
前述したようにして、ローラ装置の揺動の動作を区間B
の全体に亘って行うと、ケーブルが、区間Cに示される
ようにして、トラフ15内に収容される。つまり、ケー
ブル20は区間Bにおいて、区間Cに近接する位置か
ら、順次スライド棒50の上を滑ってトラフ方向に摺動
し、トラフ15内に符号c1の部分に示されるようにし
て収容されるようになる。As described above, the swing operation of the roller device is performed in the section B.
, The cable is housed in the trough 15 as shown in section C. That is, the cable 20 slides on the slide rod 50 in the trough direction in order from the position close to the section C in the section B, and is accommodated in the trough 15 as indicated by a portion c1. Like
前述したようにして、スライド棒50に沿ってケーブル
を摺動させる際に、作業員は、トラフ内の所定の位置
に、該ケーブルを位置決めする補助作業のみを行うよう
にすることによって、トラフ15内の任意の位置にケー
ブルを固定させることが出来る。As described above, when the cable is slid along the slide rod 50, the worker performs only the auxiliary work for positioning the cable at a predetermined position in the trough, so that the trough 15 The cable can be fixed at any position inside.
そして、所定の区間Bの部分で、ケーブルをスライド棒
に沿ってトラフ15に向けて摺動させて、移載する作業
が終了すると、その区間Bからスライド棒50を取り外
して、次の区間Aに移動させ、該区間Aで、各ローラ装
置に対応させる位置に、スライド棒を装着する作業を行
う。Then, in the portion of the predetermined section B, the cable is slid along the slide rod toward the trough 15, and when the transfer work is completed, the slide rod 50 is removed from the section B and the next section A Then, in the section A, the work of mounting the slide bar at the position corresponding to each roller device is performed.
前述したようにして、所定の区間毎に区切った状態で、
ローラ装置からスライド棒を介してケーブルを移動させ
てトラフ内に収容される作業を繰返して行い、ケーブル
の所定の長さに亘って洞道内でのケーブルの布設を行う
ようにする。As described above, in the state of dividing into predetermined sections,
The cable is moved from the roller device through the slide rod to be accommodated in the trough repeatedly, and the cable is laid in the cave over a predetermined length of the cable.
また、本発明の実施例において、比較的短い区間毎に区
切った状態で、スライド棒を取付ける作業を行うことに
より、作業員の数の問題と、同時に設置するスライド棒
の数の問題、等に対応させることが出来るようにする。
なお、本発明において、作業区間の区切り長さは、ケー
ブル送り出し装置25の間隔に対応させて設置すると、
各作業を区切り良く行うことができる。Further, in the embodiment of the present invention, by performing the work of mounting the slide rod in a state of being divided into relatively short sections, the problem of the number of workers, the problem of the number of slide rods installed at the same time, etc. Be able to correspond.
In addition, in the present invention, when the separation length of the work section is set in correspondence with the interval of the cable sending device 25,
Each work can be done in good condition.
そして、前記短いケーブル送り出し装置の区間に対応さ
せて、ケーブルをトラフに向けて移動させる作業を行う
ことによって、同時に洞道内に入る作業員の数を少なく
することが出来るとともに、スライド棒等の部材を多く
使用することがないようになる。Then, by performing the work of moving the cable toward the trough in correspondence with the section of the short cable feeding device, it is possible to reduce the number of workers who simultaneously enter the cave, and at the same time, a member such as a slide rod. You won't need to use much.
さらに、比較的短い区間を限ってケーブルの移動の作業
を行うようにすることによって、単位長さ当たりの重量
が大きいOFケーブル等に対して、その取扱い作業を容
易に行い得るようにすることが出来る。Further, by carrying out the work of moving the cable only in a relatively short section, it becomes possible to easily carry out the work of handling an OF cable or the like having a large weight per unit length. I can.
なお、ケーブルをスライド棒に沿って移動させる際に、
ケーブル送り出し装置25のキャタピラー装置のケーブ
ルに対する挟持状態を解除しておくと、ケーブルはケー
ブル送り出し装置から容易に離脱されて、トラフに向け
て移動されるようになる。In addition, when moving the cable along the slide bar,
When the pinching state of the cable feeding device 25 with respect to the cable of the caterpillar device is released, the cable is easily separated from the cable feeding device and moved toward the trough.
前記ケーブルの布設は作業は、トラフ内に3本のケーブ
ルを収容させる場合には、該ケーブルを布設する区間全
体に亘って3回繰返して行い、そのケーブルの布設の都
度、短い区間毎にスライド棒の取付け、取外しの動作を
繰返して行うものとされる。When the three cables are to be accommodated in the trough, the work of laying the cables is repeated three times over the entire section where the cables are laid, and every time the cable is laid, the cable is slid in short sections. It is assumed that the rod mounting and removing operations are repeated.
また、前述したようにして、1本のケーブルに対応する
区間で、洞道内のケーブルの布施の作業が終了すると、
支柱に取付けたブラケットとローラ装置を全部取り外
す。そして、次の区間に対応させて支柱に対してブラケ
ットを介してローラ装置の取付けを行い、ケーブルを延
線して、トラフに収容する作業を行うことになる。Further, as described above, when the work of applying the cable in the cave is completed in the section corresponding to one cable,
Remove all brackets and roller devices attached to the columns. Then, the roller device is attached to the column via the bracket in correspondence with the next section, the cable is extended, and the work is accommodated in the trough.
前記動作を行うために、本発明のケーブル布設装置は、
第2図に詳細に説明されるように構成されたローラ装置
40と、スライド棒50とを用いるようにする。第2図
に示される本発明の実施例において、洞道の巾方向の中
央部に配置される支柱2には、ケーブルを布施するトラ
フ15の高さに対応させて、取付けブラケット30を取
付けるようにしている。In order to perform the above operation, the cable laying device of the present invention is
A roller device 40 configured as described in detail in FIG. 2 and a slide rod 50 are used. In the embodiment of the present invention shown in FIG. 2, the mounting bracket 30 is attached to the support column 2 arranged in the central portion in the width direction of the sinusway in correspondence with the height of the trough 15 for applying the cable. I have to.
前記取付けブラケット30は、支柱2の上下方向に、所
定の間隔で形成されるネジ孔3………に対して、上下の
ピン孔31、31aを介してネジを差込むことによって
取付けるようにしているもので、該ネジ孔3、3……に
対する取付け位置を変化させることにより、支柱2の任
意の高さの位置に取付けブラケットを装着させることが
出来る。The mounting bracket 30 is mounted in the vertical direction of the column 2 by inserting screws into the screw holes 3 formed at predetermined intervals through the upper and lower pin holes 31 and 31a. By changing the mounting position with respect to the screw holes 3, 3, ..., The mounting bracket can be mounted on the column 2 at an arbitrary height position.
本発明の支柱2に取付けられる取付けブラケット30に
対して、図示されるように、ローラ支持ブロック35と
ブラケット33とを設けている。前記ローラ支持ブロッ
ク35は、下部に開口を形成した溝を設け、該溝に対し
てローラ41を支持する支持アーム42を取付けるよう
にしており、前記溝に対して支持アーム42を取付ける
ために、2つのピン孔36、38を設けている。As shown in the figure, a roller support block 35 and a bracket 33 are provided for a mounting bracket 30 that is mounted on the column 2 of the present invention. The roller support block 35 is provided with a groove having an opening formed in the lower portion, and a support arm 42 for supporting the roller 41 is attached to the groove. To attach the support arm 42 to the groove, Two pin holes 36 and 38 are provided.
そして、前記2つのピン孔のうち、一方の固定用ピン孔
36に挿入されるピン37は、支持アーム42の端部を
貫通するように設けられ、他方のアーム支持用のピン孔
38には、支持アーム42の下面を支持するピン39が
装着される。Of the two pin holes, the pin 37 inserted into one of the fixing pin holes 36 is provided so as to penetrate the end portion of the support arm 42, and the other arm supporting pin hole 38 is provided in the pin hole 38. A pin 39 that supports the lower surface of the support arm 42 is mounted.
なお、前記第1図に示される例において、ローラ装置4
0のローラ41を支持するアーム42の先端部に、ワイ
ヤ固定部46を介して振れ止め用ワイヤ45を取付けて
いる。前記ワイヤ45は、片持ち状にアームに支持され
たローラ装置40に対して、表面にコルゲーションを有
するケーブルが移動される際に、そのケーブルの凹凸に
よって、上下左右方向に振れたりすることを防止するた
めに設けられている。In the example shown in FIG. 1, the roller device 4
A steady wire 45 is attached to the tip of an arm 42 that supports the roller 41 of No. 0 via a wire fixing portion 46. The wire 45 prevents the cable having corrugation on its surface from swaying in the vertical and horizontal directions when the cable having corrugation on its surface is moved with respect to the roller device 40 supported by the arm in a cantilever manner. It is provided to do so.
すなわち、支柱に沿って配置される各ローラ41……に
対して、1本のワイヤを用いて接続することによって、
ローラ列上をケーブルが移動して、各ローラ41に対し
て上下左右方向に衝撃を加えたとしても、隣接するロー
ラの全てに同一位相の衝撃が加えられることがないの
で、各ローラの振動は互いに打消され、ローラの振動を
少なくすることと、そのローラが振動することによる、
騒音の発生を防ぐことが出来る。That is, by connecting each roller 41 arranged along the support column with one wire,
Even if the cable moves on the roller row and a shock is applied to each roller 41 in the vertical and horizontal directions, the shock of the same phase is not applied to all the adjacent rollers. By canceling each other and reducing the vibration of the roller and the vibration of the roller,
It is possible to prevent the generation of noise.
また、ブラケット33は、取付けブラケット30から側
方に延長されて設けられ、ローラ装置40がケーブルの
搬送を行う装置にセットされた際に、該ローラに対して
邪魔にならない位置にスライド棒50を取付けることが
出来る。なお、前記スライド棒50は、ブラケット33
に設けた孔34に一端部を挿入し、他端部は端部支持ブ
ラケット53とL字状に曲げられたアーム55を介し
て、トラフ支持材12の端部に支持される。Further, the bracket 33 is provided so as to extend laterally from the mounting bracket 30, and when the roller device 40 is set to a device that conveys a cable, the slide rod 50 is placed at a position that does not interfere with the roller. Can be installed. In addition, the slide bar 50 includes the bracket 33.
One end portion is inserted into the hole 34 provided in the trough support member 12 and the other end portion is supported by the end portion of the trough support member 12 through the end portion support bracket 53 and the L-shaped bent arm 55.
前述したように、トラフ支持材12の端部にアーム55
を取付けるために、本発明の実施例においては、チャン
ネル材により構成されたトラフ支持材の端部に、略コの
字状のアーム取付け部材56を組合せ、固定用ネジ57
で締付けるような手段を用いている。As described above, the arm 55 is attached to the end of the trough support member 12.
In the embodiment of the present invention, a trough support member made of a channel material is combined with a substantially U-shaped arm attachment member 56, and a fixing screw 57 is attached.
I use a means such as tightening.
そして、前述したようにして、スライド棒50の一方の
端部をブラケット33の孔34に挿入し、他方の端部付
近をアーム55を介して、トラフ支持材12に支持させ
ることによって、支柱2とトラフ支持材との間でスライ
ド棒50を支持させて、ケーブル20が載置された場合
にその荷重を支持出来るようにされる。Then, as described above, one end of the slide rod 50 is inserted into the hole 34 of the bracket 33, and the vicinity of the other end is supported by the trough support member 12 via the arm 55, so that the pillar 2 is supported. The slide rod 50 is supported between the trough support member and the trough support member so that the load can be supported when the cable 20 is placed.
また、本発明のスライド棒50は、支柱2からトラフ1
5に向けて下降する状態に傾斜されており、その傾斜角
度はケーブルが自重で滑ることが出来る程度に設定され
る。さらに、前記スライド棒50のトラフ15側の端部
は、図示されるように、傾斜角度を大きくして、トラフ
の上部分に突出するようにして配置される。前記スライ
ド棒のトラフ上への突出長さは、ケーブルの配置位置等
に応じて調整することが出来、それは、スライド棒50
の支柱側に端部をブラケット33の孔に挿入する長さ
で、任意に調整することが出来る。In addition, the slide rod 50 of the present invention is configured such that
It is inclined so that it descends toward 5, and its inclination angle is set so that the cable can slide under its own weight. Further, as shown in the drawing, the end portion of the slide rod 50 on the trough 15 side is arranged so as to have a large inclination angle and to project to the upper portion of the trough. The protruding length of the slide rod on the trough can be adjusted according to the arrangement position of the cable and the like.
It is possible to arbitrarily adjust the length by inserting the end portion into the hole of the bracket 33 on the column side.
前述したように構成されたスライド棒とローラとの2つ
の部材は、第3図に示されるようにして、洞道1内の支
柱2に取付けられるようになる。そして、例えば、洞道
1の側部に配置されたケーブルラック10に、側柱11
を介して多数段にトラフ支持材12、12……を取付
け、それぞれのトラフ支持材に対してトラフ15……を
設けた場合に、その最上部のトラフに対してケーブルを
布設する際に、特に有効に使用することが出来る。The two members of the slide rod and the roller configured as described above can be attached to the column 2 in the sinus 1 as shown in FIG. Then, for example, the side posts 11 are provided on the cable rack 10 arranged on the side of the cave 1.
When trough support members 12, 12 ... Are attached to a plurality of stages via the and troughs 15 are provided for the respective trough support members, when laying a cable on the uppermost trough, It can be used particularly effectively.
第3図に示される実施例において、トラフ15は密閉型
防災トラフとして構成されているもので、略U字状の下
部材16に対して、接続部17、17を介して上部材1
8を取付け、上下の部材16、18によって内部を密閉
した状態で、ケーブルの収容部分を構成する。In the embodiment shown in FIG. 3, the trough 15 is configured as a closed type disaster prevention trough, and the upper member 1 is connected to the lower member 16 having a substantially U-shape via the connecting portions 17 and 17.
8 is attached, and the inside of the cable is sealed by the upper and lower members 16 and 18 to form a cable housing portion.
前述したようなトラフ15を構成する上下の部材は、F
RPまたは鉄板等で構成されるもので、ケーブルから発
生される熱が、外部に漏れ出すことを防止するととも
に、外部で発生した障害が他のケーブルに影響すること
がないようにされる。また、ケーブルを密閉トラフ内に
収容した場合に、そのケーブルから発生される熱を除去
するために、トラフ15の上部に冷却水用パイプ23が
配置される。そして、該パイプ23の内部に低温の水を
通すことにより、トラフの内部を冷却し、ケーブルの熱
が上昇することを防止出来るようにする。The upper and lower members constituting the trough 15 as described above are F
It is composed of RP or an iron plate or the like, and prevents heat generated from the cable from leaking to the outside and prevents a failure generated outside from affecting other cables. Further, a cooling water pipe 23 is arranged above the trough 15 in order to remove heat generated from the cable when the cable is housed in the closed trough. Then, by passing low-temperature water through the inside of the pipe 23, the inside of the trough is cooled and the heat of the cable can be prevented from rising.
本発明の実施例において、洞道内に多数のトラフを配置
した場合に、各トラフ15にそれぞれ3本ずつのケーブ
ルを収容させて、各々が高圧送電線の回路を形成するよ
うにしている。In the embodiment of the present invention, when a large number of troughs are arranged in a cave, each trough 15 accommodates three cables, and each trough forms a circuit of a high voltage transmission line.
また、本発明の洞道において、高い位置に配置されたロ
ーラに沿ってケーブル20を移動させるために、第4図
に示されるようなケーブル送り出し装置25を用いるこ
とが出来る。Further, in the cavern of the present invention, a cable feeding device 25 as shown in FIG. 4 can be used to move the cable 20 along the roller arranged at a high position.
前記ケーブル送り出し装置25は、通常ケーブルの移動
に用いられるキャタピラ方式の装置を用いることが出来
るもので、ローラの位置と同じ高さに、該ケーブル送り
出し装置25を取付けブラケット30aを介して支柱2
に取付け、キャタピラ手段によってケーブル20を上下
から挟んだ状態で延線して、ケーブルをその長さ方向に
移動させることが出来る。The cable feeding device 25 can use a caterpillar type device that is usually used for moving a cable, and the cable feeding device 25 is mounted at the same height as the position of the roller via the mounting bracket 30a.
It is possible to move the cable in its length direction by mounting it on the cable 20 and extending the cable with the caterpillar means sandwiching the cable 20 from above and below.
前記ケーブル送り出し装置25は、一般のケーブル布設
工事を行う場合と同様に、35m程度の間隔を持って、
洞道の内部に配置され、ケーブルの延線を行うことが出
来るようにされる。また、前記ケーブル送り出し装置2
5は、第1図に示されたように、両側の支柱に対して、
連接部材27、27を用いて接続するものであり、該ケ
ーブル送り出し装置を支柱する支柱にのみ、大きな力が
負荷されることを防止することが出来るようにされる、
ケーブルを延線する作用を安定した状態で行うことが出
来るようになる。The cable feeding device 25 has an interval of about 35 m, as in the case of general cable laying work.
It is placed inside the cavern and is designed to allow cable extension. In addition, the cable feeding device 2
5 is, as shown in FIG. 1, for the columns on both sides,
Connections are made by using the connecting members 27, 27, and it is possible to prevent a large force from being applied only to a column that supports the cable sending device.
It becomes possible to perform the action of extending the cable in a stable state.
また、本発明のケーブルの布設に際して、支柱に設ける
ブラケット30に対して、ローラ装置やスライド棒を取
付ける作業は、第4図に示されるような作業台車を用い
て行う。この作業台車5は、例えば実公昭60−158
40号公報等に示されるようなものを用いることが出来
るが、本発明の実施例においては、洞道内での台車の走
行方向の規制を行うために、床4に設けた側溝4aにガ
イド車輪9を案内させるようにする。Further, when the cable of the present invention is laid, the work for attaching the roller device and the slide rod to the bracket 30 provided on the column is performed by using a work carriage as shown in FIG. This work trolley 5 is, for example, the actual public sho 60-158
For example, a guide wheel can be used in the side groove 4a provided in the floor 4 in order to regulate the traveling direction of the truck in the cave, although the one shown in Japanese Patent Publication No. 40, etc. can be used. Let me guide you through 9.
また、前記ガイド車輪9は、台車本体の側部に突出させ
た支持アーム9aに設けられ、走行車輪8が溝4aに落
ち込んだりすることがないようにされる。前記台車5の
上には作業台6が設けられ、作業員は作業台6の上に乗
って、取付けブラケットの取付けや、ローラ、スライド
棒の取付け、および、後述するようなケーブルの移載等
の各作業を行うことが出来るようにされる。Further, the guide wheel 9 is provided on a support arm 9a protruding to the side portion of the bogie body so that the traveling wheel 8 does not fall into the groove 4a. A workbench 6 is provided on the dolly 5, and an operator rides on the workbench 6 to mount a mounting bracket, a roller and a slide rod, and transfer a cable as described later. You will be able to perform each work.
なお、本発明の作業台車5においては、その支柱側の側
部に上ガイド部材7を設けておき、該ガイド部材7が支
柱に摺動させるようにすることによって、台車5を移動
させる際に、側溝4aによるガイドと共同させて、洞道
内の作業通路に沿って台車を移動させ得るようにするこ
とが出来る。In the work carriage 5 of the present invention, the upper guide member 7 is provided on the side portion of the support pillar side, and the guide member 7 is slid on the support pillar so that the carriage 5 can be moved. It is possible to allow the carriage to move along the working path in the cave by cooperating with the guide by the gutter 4a.
前記本発明の実施例において、OFケーブルを洞道内に
布設する場合の例で説明を行ったが、本発明の装置は、
CVケーブル等の他の種類の高圧送電ケーブルにも、適
用することが可能である。In the embodiment of the present invention, the case where the OF cable is laid in the cave has been described, but the device of the present invention is
It can also be applied to other types of high-voltage power transmission cables such as CV cables.
(発明の効果) 本発明の洞道内ケーブル布設方法においては、台車等を
使用せずに、連続してケーブルの布設の動作を行うこと
が出来るとともに、作業用の通路を十分に確保し、作業
を安全に行うことが出来る。(Effects of the Invention) In the cable laying method for a cave according to the present invention, the cable laying operation can be continuously performed without using a trolley or the like, and a sufficient passage for work can be secured to perform work. Can be done safely.
また、本発明のケーブル布設装置は、上記したような構
成を有するものであるから、比較的簡単な構成の部材を
用いることによって、単位重量の大きなケーブルを、洞
道内の所定の高さに配置されたトラフに布設することが
出来る。Further, since the cable laying device of the present invention has the above-mentioned configuration, a cable having a large unit weight is arranged at a predetermined height in the cave by using a member having a relatively simple configuration. It can be laid in a trough that has been cut.
本発明に使用される装置は、各支柱に取付けられる取付
けブラケットと、該ブラケットに設けられるローラ装
置、および、ケーブルを横方向に移動させるためのスラ
イド棒のみであり、それ等の各作業部材を、構成の簡単
なものとすることが出来る。The device used in the present invention is only a mounting bracket attached to each strut, a roller device provided in the bracket, and a slide rod for laterally moving the cable. , The configuration can be simple.
そして、ケーブルの布設の作業を行うに際しては、ロー
ラ装置によってケーブルを長さ方向に移動させること
と、スライド棒上で自重によって摺動させることによ
り、該ケーブルを横方向へ移動させる動作を行うことが
出来るので、トラフ上へのケーブルの移動の作業が容易
なものとなる。When laying the cable, the cable is moved in the length direction by a roller device and the cable is moved in the lateral direction by sliding it on the slide rod by its own weight. Since it is possible, the work of moving the cable onto the trough becomes easy.
第1図は本発明のケーブルの布設方法を示す説明図、第
2図は本発明に用いられる装置の構成を示す斜視図、第
3図は洞道内に配置されるケーブル布設装置とトラフと
の関係を示す説明図であり、第4図は支柱にケーブル送
り出し装置を取付けた場合の説明図である。 図中の符号 1……洞道、2……支柱、4……床、5……作業台車、
10……ケーブルラック、11……側柱、12……トラ
フ支持部材、15……トラフ、20……ケーブル、23
……冷却水用パイプ、25……ケーブル送り出し装置、
30……取付けブラケット、31……ピン孔、33……
スライド棒支持ブラケット、34……孔、35……ロー
ラ支持ブロック、40……ローラ装置、42……支持ア
ーム、45……ワイヤ、50……スライド棒、55……
アーム、56……アーム取付け部材。FIG. 1 is an explanatory view showing a cable laying method of the present invention, FIG. 2 is a perspective view showing a configuration of an apparatus used in the present invention, and FIG. 3 is a cable laying apparatus and a trough arranged in a cave. FIG. 4 is an explanatory diagram showing the relationship, and FIG. 4 is an explanatory diagram in the case where the cable feeding device is attached to the column. Reference numeral 1 in the figure 1 ... Caveway, 2 ... Post, 4 ... Floor, 5 ... Work cart,
10 ... Cable rack, 11 ... Side pillar, 12 ... Trough support member, 15 ... Trough, 20 ... Cable, 23
...... Cooling water pipe, 25 …… Cable feeding device,
30 ... Mounting bracket, 31 ... Pin hole, 33 ...
Slide rod support bracket, 34 ... Hole, 35 ... Roller support block, 40 ... Roller device, 42 ... Support arm, 45 ... Wire, 50 ... Slide rod, 55 ...
Arm, 56 ... Arm mounting member.
Claims (1)
クを両側に配置し、中央部に支柱を設けてなる洞道にお
いて、 洞道内の支柱に対して、棚の高さに合せて取付けブラケ
ットを設け、該取付けブラケットを介してケーブルを案
内するためのローラ装置と、該ケーブルの延線を行うた
めのケーブル送り出し装置とを配置するとともに、棚の
トラフとの間に配置するスライド棒を取付け出来るよう
に構成し、 前記ローラ装置によって洞道内にケーブルを延線した後
で、一定の区間毎にローラ装置に対応させてスライド棒
を取付け、該スライド棒を配置した区間のローラ装置を
揺動させて、ケーブルに対するローラの支持を解除し、 スライド棒に支持されるケーブルを、該スライド棒の傾
斜にしたがって、トラフに向けて移動させることによ
り、ケーブルラックに設けたトラフ内に布設することを
特徴とする洞道内ケーブル布設方法。1. In a cavern with a plurality of shelves arranged vertically on both sides and a column in the center, the cavern is mounted to the column in the cavern in accordance with the height of the shelves. A slide bar is provided which is provided with a bracket and which is provided with a roller device for guiding the cable through the mounting bracket and a cable feeding device for extending the cable, and which is arranged between the shelf and the trough of the shelf. After the cable is extended in the cave by the roller device, a slide bar is attached in correspondence with the roller device at regular intervals, and the roller device in the section where the slide bar is arranged is shaken. By moving the roller to support the cable, and moving the cable supported by the slide rod toward the trough according to the inclination of the slide rod. , Sinus Hokkaido cable installation method characterized by laying in the trough provided in the cable racks.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18212489A JPH0622367B2 (en) | 1989-07-14 | 1989-07-14 | Cable installation method in cave |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18212489A JPH0622367B2 (en) | 1989-07-14 | 1989-07-14 | Cable installation method in cave |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0349512A JPH0349512A (en) | 1991-03-04 |
| JPH0622367B2 true JPH0622367B2 (en) | 1994-03-23 |
Family
ID=16112750
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP18212489A Expired - Lifetime JPH0622367B2 (en) | 1989-07-14 | 1989-07-14 | Cable installation method in cave |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0622367B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113809688B (en) * | 2021-10-27 | 2023-02-17 | 河南吉诚电力工程有限公司 | Power cable laying method and laying bracket |
| CN118554335B (en) * | 2024-03-01 | 2024-12-03 | 威海中能电气有限公司 | Cable laying bracket |
-
1989
- 1989-07-14 JP JP18212489A patent/JPH0622367B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0349512A (en) | 1991-03-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101209242B1 (en) | Underground power transmission cable and power distribution cable support device | |
| CN206922350U (en) | A kind of supporting adn fixing device for cable testing bridge | |
| CN217741139U (en) | Electric power installation tensioner bullwheel | |
| CN109551147B (en) | Hardware frame welding fixing frame | |
| JPH0622367B2 (en) | Cable installation method in cave | |
| SU1584014A1 (en) | Trolley for moving along wires of split phase of aerial power transmission line | |
| US3098638A (en) | Stringing block | |
| CN210041115U (en) | A multifunctional support for replacing large-spacing insulators | |
| JPH0622368B2 (en) | Cable laying equipment | |
| CN113178818B (en) | Cable trench multi-row wiring device | |
| JP2005333789A (en) | Hanging wire type transfer method by net formation | |
| CN113746026A (en) | High wire driving for power maintenance of security | |
| JPH0722978Y2 (en) | Cable laying equipment | |
| CN210156819U (en) | Trolley set for replacing ground wire | |
| CN114696262B (en) | Cable hoisting and laying device and method, wind turbine generator set | |
| CN211320775U (en) | Cable erecting device | |
| CN221380363U (en) | Indoor ceiling wiring frame | |
| CN219304275U (en) | Underground distribution box placement frame | |
| CN217063073U (en) | Power transmission line engineering stringing construction tackle | |
| CN110729666A (en) | An installation and pay-off device for overhead ground wire | |
| CN215332869U (en) | Tunnel chute installation and maintenance operation vehicle | |
| CN217437364U (en) | Pay-off rack | |
| CN223467172U (en) | Transfer equipment for building glass curtain wall installation | |
| JPH0645921U (en) | Ladder device of stacker crane in automatic warehouse | |
| KR101348175B1 (en) | Side rollers, wiring cable tray is configured |