JPH068532B2 - Pile driving method - Google Patents
Pile driving methodInfo
- Publication number
- JPH068532B2 JPH068532B2 JP63040179A JP4017988A JPH068532B2 JP H068532 B2 JPH068532 B2 JP H068532B2 JP 63040179 A JP63040179 A JP 63040179A JP 4017988 A JP4017988 A JP 4017988A JP H068532 B2 JPH068532 B2 JP H068532B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- dummy
- main
- piles
- placing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000000034 method Methods 0.000 title claims description 11
- 229910000831 Steel Inorganic materials 0.000 description 6
- 239000010959 steel Substances 0.000 description 6
- 238000005452 bending Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】 《産業上の利用分野》 本発明は杭打設方法に係り、特に硬質地盤に対する長尺
杭の打設方法の改善に関するものである。Description: TECHNICAL FIELD The present invention relates to a pile driving method, and more particularly to improvement of a method for driving a long pile on a hard ground.
《従来の技術》 H型鋼,I型鋼,鋼矢板あるいは鋼管杭等の杭類を地盤
に打設する場合は一般的にバイブロハンマなどの振動杭
打機が用いられる。この振動杭打機はクレーンから吊下
げられ、杭の末端に接着して振動を与え、この振動で杭
の先端を地盤に貫入させるようになっている。<< Prior Art >> When driving piles such as H-type steel, I-type steel, steel sheet pile or steel pipe piles into the ground, a vibrating hammer driving machine such as a vibro hammer is generally used. This vibrating pile driver is hung from a crane and adheres to the end of the pile to give vibration, which causes the tip of the pile to penetrate into the ground.
《発明が解決しようとする課題》 しかし、従来の杭打設方法は振動杭打機によって一気に
杭を打込んでいたので、長い杭を打込む場合には杭が傾
斜しやすく、また岩盤のように地盤が硬い場合には打込
み抵抗によって杭が座屈曲げを生じやすく、このような
曲げにより杭の傾斜が一層大きくなるという問題を生じ
ていた。<Problems to be solved by the invention> However, in the conventional pile driving method, the piles are driven at once by the vibrating pile driving machine. In addition, when the ground is hard, the pile tends to bend due to driving resistance, and such bending causes a problem that the inclination of the pile becomes larger.
本発明は上述の課題を有効に解決すべく創案するに至っ
たものであって、その目的は硬質地盤に対しても比較的
長尺の杭を垂直に打設することのできる杭打設方法を提
供することにある。The present invention has been devised to effectively solve the above-mentioned problems, and the purpose thereof is a pile driving method capable of vertically driving a relatively long pile vertically even on hard ground. To provide.
《課題を解決するための手段》 前記課題を解決するため本発明は、継手を構成する溝と
係合部とを有する第1、第2、第3……第nの本杭と、
前記溝と係合部とを有し前記本杭と断面形状が等しく前
記本杭よりも長さが短い3本の第1、第2、第3のダミ
ー杭とを用意する準備の工程と、第1、第2、第3のダ
ミー杭を連続して一列で打設する第1の工程と、内側の
第2のダミー杭を引き抜いた後の縦孔に第1の本杭を挿
入してその両側を前記第1、第3のダミー杭で案内しつ
つ打設する第2の工程と、第2のダミー杭を第3のダミ
ー杭の外側に隣接して打設する第3の工程と、第3のダ
ミー杭を引抜いた後の縦孔に第2の本杭を挿入してその
両側を第1の本杭および第2のダミー杭で案内しつつ打
設する第4の工程と、第2、第3のダミー杭に関する第
2〜第4の工程を繰返して第3……第nの本杭をダミー
杭で案内しつつ順次打設する第5の工程とを含み、前記
案内は前記継手により行なわれるようにしたものであ
る。<< Means for Solving the Problems >> In order to solve the above problems, the present invention provides first, second, third ... Nth main piles each having a groove and an engaging portion that form a joint,
A step of preparing to prepare three first, second, and third dummy piles having the groove and the engaging portion and having the same cross-sectional shape as the main pile and a shorter length than the main pile; Insert the first main pile into the vertical hole after pulling out the second dummy pile on the inner side, and the first step of placing the first, second, and third dummy piles continuously in one row. A second step in which both sides thereof are driven while being guided by the first and third dummy piles; and a third step in which the second dummy pile is driven adjacent to the outside of the third dummy pile. A fourth step of inserting the second main pile into the vertical hole after pulling out the third dummy pile and placing the second main pile while guiding both sides thereof with the first main pile and the second dummy pile, The second to fourth steps for the second and third dummy piles are repeated, and the fifth step of sequentially placing the third ...... nth main pile while guiding the dummy piles with the dummy piles is provided. For the joint Ri is obtained so as to be performed.
《作 用》 前記の如く構成した杭打設方法では、打設する本杭の両
側がダミー杭または他の本杭によって案内されるので本
杭が傾斜しにくく、またダミー杭を引抜いた後の縦孔に
本杭を挿入して打設するので、本杭が比較的長尺でも打
込み抵抗が少なく、従って硬質地盤に対しても長尺な本
杭を垂直に打設することができる。<Operation> In the pile driving method configured as described above, since both sides of the main pile to be driven are guided by the dummy piles or other main piles, the main pile is unlikely to incline, and after the dummy pile is pulled out, Since the main pile is inserted into the vertical hole and driven, even when the main pile is relatively long, the driving resistance is small, and therefore, the long main pile can be vertically driven even on the hard ground.
《実 施 例》 以下に本発明の一実施例を図面に基づいて説明する。第
1図(A)に示すように本発明の杭打設方法では長さが
等しい3本のダミー杭1〜3を用いている。これらダミ
ー杭1〜3の長さは本杭の長さよりも短くされており、
例えば第1図(C)に示す如くダミー杭1〜3の長さは
本杭4,5の長さの約半分とされている。ダミー杭1〜
3と本杭4には同一断面のH型鋼が使用されており、そ
の一側面には第2図に示す如く一対のアングル材5がダ
ミー杭1〜3(本杭4についても同様)の長手方向に沿
って対向配置されて溝部7が形成され、また反対側側面
には前記溝部7に係合するT字状断面の係合部8が配設
されている。そして溝部7と係合部8によって継手9が
構成されている。<< Example >> An example of the present invention will be described below with reference to the drawings. As shown in FIG. 1 (A), the pile driving method of the present invention uses three dummy piles 1 to 3 having the same length. The length of these dummy piles 1 to 3 is shorter than the length of the main pile,
For example, as shown in FIG. 1 (C), the length of the dummy piles 1 to 3 is about half the length of the main piles 4 and 5. Dummy pile 1 ~
3 and the main pile 4 are made of H-section steel having the same cross section, and a pair of angle members 5 are provided on one side surface of the dummy piles 1 to 3 (the same applies to the main pile 4) as shown in FIG. Grooves 7 are formed so as to face each other along the direction, and an engaging portion 8 having a T-shaped cross section that engages with the groove 7 is provided on the opposite side surface. The groove 7 and the engaging portion 8 form a joint 9.
次に本杭4,5の打設方法を順を追って説明する。まず
第1図(A)に示す如く3本のダミー杭1〜3を地盤1
0に対し一列に連続的に打設する。この打設には第3図
に示すバイブロハンマ11などの振動杭打機を用いる。
すなわち、ダミー杭1〜3の末端をバイブロハンマ11
で支持し、バイブロハンマ11を振動させながらクレー
ン12を操作してバイブロハンマ11を徐々に下げてい
くと、バイブロハンマ11の振動によりダミー杭1〜3
の先端が地盤10に貫入されていく。なお、ダミー杭1
〜3を打設するときは隣接するダミー杭と継手9で係合
しておく。Next, a method of placing the main piles 4 and 5 will be described step by step. First, as shown in FIG. 1 (A), three dummy piles 1 to 3 are installed on the ground 1
0 is continuously cast in a line. A vibrating pile driving machine such as a vibro hammer 11 shown in FIG. 3 is used for this driving.
That is, the ends of the dummy piles 1 to 3 are connected to the vibro hammer 11
When the vibro hammer 11 is gradually lowered by operating the crane 12 while vibrating the vibro hammer 11, the vibrating hammers 11 vibrate to cause the dummy piles 1 to 3 to fall.
The tip of is penetrated into the ground 10. Dummy pile 1
When placing 3 to 3, the adjacent dummy piles are engaged with each other at the joint 9.
3本のダミー杭1〜3を打設完了した後は中間のダミー
杭2をバイブロハンマ11で振動を加えながら引抜く。
そして第1図(B),(C)に示す如く引抜いた後にで
きた縦孔13に本杭4を挿入し、バイブロハンマ12で
打設する。このとき本杭4の両側の溝部7と係合部8は
隣接するダミー杭1,3の係合部8と溝部7に係合させ
る。本杭4を打設するときは、その両側をダミー杭1,
3が案内するので、本杭4を硬質地盤に深く打設すると
きでも本杭4の傾斜を防止することができる。また本杭
4はダミー杭2を引抜いた後の縦孔13に挿入した後打
設するので、縦孔13の長さ分だけ打込み抵抗が減少
し、従って前記ダミー杭1,3による案内作用と相俟っ
て長尺の本杭4を硬質地盤に打込むときでも座屈曲げが
生ずるのを効果的に防止できる。After the completion of placing the three dummy piles 1 to 3, the intermediate dummy pile 2 is pulled out while vibrating with the vibro hammer 11.
Then, as shown in FIGS. 1 (B) and (C), the main pile 4 is inserted into the vertical hole 13 formed after being pulled out, and is driven by the vibro hammer 12. At this time, the groove portions 7 and the engaging portions 8 on both sides of the main pile 4 are engaged with the engaging portions 8 and the groove portions 7 of the adjacent dummy piles 1 and 3. When placing the main pile 4, place both sides of the dummy pile 1,
Since 3 guides, the inclination of the main pile 4 can be prevented even when the main pile 4 is driven deep into the hard ground. Further, since the main pile 4 is inserted and inserted into the vertical hole 13 after the dummy pile 2 is pulled out, the driving resistance is reduced by the length of the vertical hole 13, and therefore the dummy piles 1 and 3 have a guiding function. Together with this, it is possible to effectively prevent the seat bending even when the long main pile 4 is driven into the hard ground.
本杭4を打設した後はその前に引抜いたダミー杭2を第
1図(D)に示す如くダミー杭3の外側に隣接して打設
し、その後第1図(E)に示す如くダミー杭3を引抜い
てその後にできた縦孔14に別の本杭5を挿入してバイ
ブロハンマ11で打込む。このときの作業は本杭4の打
込みとほとんど同じであり、異なる点は本杭5の片側側
面がダミー杭でなく本杭4によって案内される点であ
る。本杭5を打設した後は第1図(G)に示す如くダミ
ー杭3をダミー杭2の外側に隣接して打設した後、ダミ
ー杭2を引抜いて以下同様の操作を繰返しながら次々と
本杭を打設していく。After the main piles 4 have been placed, the dummy piles 2 that have been pulled out before that are placed next to the outside of the dummy piles 3 as shown in FIG. 1 (D), and then as shown in FIG. 1 (E). The dummy pile 3 is pulled out, another main pile 5 is inserted into the vertical hole 14 formed thereafter, and driven by the vibro hammer 11. The work at this time is almost the same as the driving of the main pile 4, except that one side surface of the main pile 5 is guided by the main pile 4 instead of the dummy pile. After placing the main piles 5, as shown in FIG. 1 (G), after placing the dummy piles 3 adjacent to the outside of the dummy piles 2, the dummy piles 2 are pulled out, and the same operation is repeated. And pile the main pile.
以上本発明の一実施例につき説明したが本発明は上記実
施例以外にも種々の変形が可能であって、例えばダミー
杭1〜3や本杭4,5はH型鋼の他I型鋼や鋼矢板、あ
るいは鋼管杭等各種断面の杭を用いてよいし、また継手
9の構造も他の構造を採用してもよい。Although one embodiment of the present invention has been described above, the present invention can be variously modified in addition to the above embodiments. A pile having various cross-sections such as a sheet pile or a steel pipe pile may be used, and the joint 9 may have another structure.
《発明の効果》 本発明は上述の如く、本杭の両側をダミー杭または他の
本杭で案内しつつ打設するようにしているので本杭を傾
斜させることなく垂直に打設することができ、またダミ
ー杭を引抜いた後の縦孔に本杭を挿入して打設するよう
にしているので本杭に作用する打込み抵抗を軽減でき、
前記ダミー杭ないし本杭の案内作用と相俟って長尺な本
杭を硬質地盤に打設するときでもその座屈曲げが生じる
のを防止することができる。<< Effects of the Invention >> As described above, according to the present invention, since both sides of the main pile are driven while being guided by the dummy piles or other main piles, it is possible to drive the main pile vertically without inclining it. Also, since the main pile is inserted and placed in the vertical hole after the dummy pile is pulled out, the driving resistance acting on the main pile can be reduced,
In combination with the guiding function of the dummy pile or the main pile, it is possible to prevent the bending of the seat even when the long main pile is driven into the hard ground.
第1図は本発明方法の工程図、第2図は第1図(A)の
II−II線矢視断面図、第3図はクレーンの側面図であ
る。 1〜3……ダミー杭 4,5……本 杭 11……バイブロハンマ 13,14……縦 坑FIG. 1 is a process diagram of the method of the present invention, and FIG. 2 is a diagram of FIG.
II-II line sectional view, and FIG. 3 is a side view of a crane. 1-3 ... Dummy piles 4, 5 ... Main piles 11 ... Vibro hammers 13, 14 ... Vertical shafts
Claims (1)
1、第2、第3……第nの本杭と、前記溝と係合部とを
有し前記本杭と断面形状が等しく前記本杭よりも長さが
短い3本の第1、第2、第3のダミー杭とを用意する準
備の工程と、第1、第2、第3のダミー杭を連続して一
列で打設する第1の工程と、内側の第2のダミー杭を引
き抜いた後の縦孔に第1の本杭を挿入してその両側を前
記第1、第3のダミー杭で案内しつつ打設する第2の工
程と、第2のダミー杭を第3のダミー杭の外側に隣接し
て打設する第3の工程と、第3のダミー杭を引抜いた後
の縦孔に第2の本杭を挿入してその両側を第1の本杭お
よび第2のダミー杭で案内しつつ打設する第4の工程
と、第2、第3のダミー杭に関する第2〜第4の工程を
繰返して第3……第nの本杭をダミー杭で案内しつつ順
次打設する第5の工程とを含み、前記案内は前記継手に
より行なわれることを特徴とする杭打設方法。1. A first pile, a second pile, a third pile, and an n-th main pile having a groove and an engaging portion that form a joint, and a cross-sectional shape of the main pile having the groove and the engaging portion. For preparing three first, second, and third dummy piles having the same length and a shorter length than the main pile, and a row of the first, second, and third dummy piles in a row. While inserting the first main pile into the vertical hole after pulling out the inner second dummy pile and guiding both sides of the first dummy pile by the first and third dummy piles. The second step of placing, the third step of placing the second dummy pile adjacent to the outside of the third dummy pile, and the second step in the vertical hole after pulling out the third dummy pile. Fourth step of inserting the main pile of No. 3 and placing both sides of the main pile while guiding it with the first main pile and the second dummy pile, and second to fourth steps relating to the second and third dummy piles. Repeat 3rd ... nth And a fifth step of sequentially pouring while guiding the pile in dummy pile, pile 設方 method the guide is characterized by being carried out by the joint.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63040179A JPH068532B2 (en) | 1988-02-23 | 1988-02-23 | Pile driving method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63040179A JPH068532B2 (en) | 1988-02-23 | 1988-02-23 | Pile driving method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01214615A JPH01214615A (en) | 1989-08-29 |
| JPH068532B2 true JPH068532B2 (en) | 1994-02-02 |
Family
ID=12573553
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63040179A Expired - Lifetime JPH068532B2 (en) | 1988-02-23 | 1988-02-23 | Pile driving method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH068532B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2012207371A (en) * | 2011-03-29 | 2012-10-25 | Penta Ocean Construction Co Ltd | Method for installing steel sheet pile |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS61137917A (en) * | 1984-12-10 | 1986-06-25 | Nippon Press Concrete Kk | Placement of concrete sheet pile |
-
1988
- 1988-02-23 JP JP63040179A patent/JPH068532B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH01214615A (en) | 1989-08-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR20210015490A (en) | Two Rows type Self reliance retaining wall construction method Using the Prestressed pile | |
| JPH068532B2 (en) | Pile driving method | |
| JP2007247308A (en) | Pulling-out bearing strength reinforcing for pile group comprised of inclined piles and structure constructed according to the same | |
| CN110805046A (en) | Foundation pit support steel sheet pile driving and arranging support structure and foundation pit support steel sheet pile driving and arranging method | |
| JP3353200B2 (en) | Earth retaining method | |
| JP3356905B2 (en) | Steel pipe pile with spiral wings | |
| JP4453948B2 (en) | Pile foundation | |
| JPH02161014A (en) | Method of correcting inclining and falling pile and placing same | |
| JPH05339936A (en) | Column strip type underground continuous wall process | |
| JP3331110B2 (en) | Construction method and retaining wall structure of retaining wall using deep mixed consolidated pile | |
| JPS6153915A (en) | Lowering method of earthwork materials | |
| JPH0320356Y2 (en) | ||
| JPH0645936B2 (en) | Underwater sheet pile driving method | |
| JPH07900B2 (en) | Pile driving method | |
| JPH07103559B2 (en) | Construction method for steel pipe piles | |
| JPH0629512B2 (en) | How to place steel sheet pile | |
| JP2553002B2 (en) | Pile press-in / pull-out machine | |
| JP6345286B1 (en) | Shaped steel piles that support buildings and methods for driving shaped steel piles | |
| JP2017197951A (en) | Countermeasure wall against drawn-in subsidence and construction method thereof | |
| JPH0434202Y2 (en) | ||
| JPS61137917A (en) | Placement of concrete sheet pile | |
| JPS6038759Y2 (en) | pipe panel | |
| JPH05311658A (en) | Driving method for steel sheet pile | |
| JPH08170617A (en) | Driving anchor for concrete | |
| JPH073047B2 (en) | Method for driving sheet pile and sheet pile with wedge |