JPH0686751B2 - Construction method for the roof of a large-scale building - Google Patents
Construction method for the roof of a large-scale buildingInfo
- Publication number
- JPH0686751B2 JPH0686751B2 JP12654988A JP12654988A JPH0686751B2 JP H0686751 B2 JPH0686751 B2 JP H0686751B2 JP 12654988 A JP12654988 A JP 12654988A JP 12654988 A JP12654988 A JP 12654988A JP H0686751 B2 JPH0686751 B2 JP H0686751B2
- Authority
- JP
- Japan
- Prior art keywords
- girder
- erected
- shape
- beams
- cranes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は大規模建造物の屋根部の施工法に関するもの
である。TECHNICAL FIELD The present invention relates to a method for constructing a roof portion of a large-scale building.
体育館等の大規模建造物においては、梁のスパンが極め
て大きくなるため、このような梁の架設には従来様々な
施工法が採用されている。In a large-scale building such as a gymnasium, the span of the beam becomes extremely large, and thus various construction methods have been conventionally used for constructing such a beam.
例えば仮設支柱を立設し、この仮設支柱にて支えながら
梁を順に延ばして架設するなどが採用されているが、こ
のような施工法であると仮設資材が多数必要で施工費が
高価になるとともに、高所での作業が多くなり危険性が
増大することになる。For example, it is adopted to erected a temporary support pillar and extend the beam in order while supporting it with this temporary support pillar, but such a construction method requires a large number of temporary materials and the construction cost becomes expensive. At the same time, the amount of work in high places will increase and the risk will increase.
この発明は工期が短く、施工費が安価で、更に危険な作
業を少なくすることができる大規模建造物屋根部の施工
法を提供することを目的とする。It is an object of the present invention to provide a construction method for a large-scale building roof portion, which has a short construction period, a low construction cost, and can further reduce dangerous work.
〔問題点を解決するための手段〕 この発明における、かかる大規模建造物の屋根部の施工
法は、主としてクレーンを使用して梁の架設を行うもの
である。[Means for Solving Problems] The method of constructing the roof portion of such a large-scale building in the present invention mainly uses a crane to construct a beam.
まず四方向に各一本ずつ計四本の大黒柱を立設する。First, a total of four large black columns are erected, one in each of the four directions.
二機のクレーンによって地上で地組みした大梁を吊上
げ、各大黒柱間に架設してコ字状に組む。Two large cranes are used to hoist the large beams grounded above the ground, and they are erected between the large black columns to form a U-shape.
次いで大梁間に囲まれた内部空間内に井桁状に複数本の
井桁梁を組むものであり、各井桁梁を架設するに際して
は、井桁梁を長さ方向に三分割し、まず井桁梁の左、右
端部を大梁に連結して仮設支柱によって支持し、さらに
井桁梁の中央部を前記井桁梁の左、右端部間に配して連
結し、順次井桁梁を交叉させて井桁状に組む。Next, multiple girder beams are assembled like a girder in the internal space surrounded by the girders.When installing each girder beam, the girder beam is divided into three parts in the longitudinal direction, and first the left part of the girder beam is The right end is connected to a large beam and supported by a temporary strut, and the central part of the double girder beam is arranged between the left and right ends of the double girder to be connected, and the double girder beams are sequentially crossed to form a double girder.
残り一方向の大梁を大黒柱間に架設して方形状に組むこ
とを特徴としている。The other feature is that a large beam in one direction is installed between large black columns to form a square shape.
以下、図に示す一実施例に基づきこの発明を詳細に説明
する。The present invention will be described in detail below based on an embodiment shown in the drawings.
図において1は大黒柱であって、建造物の四隅角部を形
成する四方向に各一本ずつ、計四本、地上に立設する
(第1図参照)。この各大黒柱1、1間に地上にて地組
みしたトラス構造の大梁2を架設する。大梁2は大型の
クレーン3、3によって吊上げて大梁2の左、右端部が
大黒柱1によって支持されるように大黒柱1、1間に架
設し、まず三本の大梁2によって大黒柱1、1間に跨っ
てコの字状に組む(第2図、第3図参照)。In the figure, 1 is a large black pillar, and one is installed in each of the four directions forming the four corners of the building, a total of four standing on the ground (see FIG. 1). A large beam 2 having a truss structure grounded above the ground is erected between the large columns 1 and 1. The large beam 2 is hung by large cranes 3 and 3 and is erected between the large columns 1 and 1 so that the left and right ends of the large beam 2 are supported by the large columns 1, and first, three large beams 2 are provided between the large columns 1 and 1. Cross over and assemble in a U shape (see FIGS. 2 and 3).
大梁2の架設について、さらに詳述する。この大梁2は
第2図及び第3図に示すように各々2本の分割梁2a、2b
及びつなぎ梁2cより成っており、架設に際しては、まず
分割梁2a、2bを地上にて地組みし、地上に固定した回転
架台8上にヒンジ結合する(第7図参照)。この分割梁
2a、2bを順次大型クレーン3、3によって建起し、回転
台8を軸心にして回転し起立する(第8図参照)。The construction of the girder 2 will be described in more detail. As shown in FIGS. 2 and 3, the large beam 2 includes two split beams 2a and 2b, respectively.
And the connecting beam 2c. At the time of erection, the divided beams 2a and 2b are first grounded on the ground and hinged on the rotary mount 8 fixed to the ground (see FIG. 7). This split beam
2a and 2b are sequentially erected by large-sized cranes 3 and 3, and are rotated around the rotary table 8 as an axis to stand up (see FIG. 8).
この分割梁2a、2bを順次回転架台8から離脱して、その
ままクレーン3、3によって吊上げて大黒柱間に架設す
る(第9図乃至第11図参照)。この場合、分割梁2a、2b
には地上からトラワイヤ10を張って、風荷重による変形
を防止するとともに建方精度微調整を行う。また分割梁
2a、2bを吊上げた状態で、分割梁2a、2b間につなぎ梁2c
を取付け、所定の位置において大黒柱1に連結し、クレ
ーン3、3を解放し、さらに建入精度を確認し、トラワ
イヤ10を撤去する。順次、同様の作業を繰り返すことに
よって大梁2を大黒柱1、1間に架設する。The divided beams 2a and 2b are sequentially removed from the rotary mount 8 and lifted up by the cranes 3 and 3 to be installed between the large black columns (see FIGS. 9 to 11). In this case, split beams 2a, 2b
A trough wire 10 is stretched from the ground to prevent deformation due to wind load and finely adjust the erection accuracy. Also split beams
With 2a and 2b lifted, connecting beam 2c between split beams 2a and 2b
Is attached, the crane 3 and 3 are released at the predetermined position, the crane 3 and 3 are released, the installation accuracy is confirmed, and the trawl wire 10 is removed. By sequentially repeating the same operation, the girder 2 is installed between the big columns 1 and 1.
以上のようにして架設された大梁2は、一方向を除いて
三方向を囲むコの字状に架設され(第3図参照)、これ
ら大梁2、2によって囲まれた内部空間内に、井桁状に
梁を組み合せるための井桁梁4を架設する(第4図、第
5図参照)。The girder 2 erected as described above is erected in a U-shape that surrounds three directions except one direction (see FIG. 3), and the girder is placed in the internal space surrounded by these girders 2 and 2. The cross girder beam 4 for combining the beams in a circular shape is erected (see FIGS. 4 and 5).
井桁梁4はH型鋼を二本組み合せたもので、長さ方向の
全体が山形状に形成されている。井桁梁4の架設に際し
ては、井桁梁4は長さ方向の中央部5と左右端部6に分
割された状態で、大梁2、2間に架設する。The double girder beam 4 is a combination of two H-shaped steels, and the entire lengthwise direction is formed in a mountain shape. At the time of erection of the cross girder beam 4, the cross girder beam 4 is erected between the girders 2, 2 in a state of being divided into a central portion 5 and left and right end portions 6 in the length direction.
架設しようとする井桁梁4の直下には大梁2より左右に
間隔を離して仮設支柱7、7を立設する。まず井桁梁4
の左、右端部6、6をそれぞれ大型のクレーン3によっ
て吊り上げ、その一端部をすでに井桁梁4と直角方向に
架設されている大梁2に側面方向から連結し、他端部を
仮設支柱7上に載置する(第4図参照)。Immediately below the girder beam 4 to be erected, temporary columns 7, 7 are erected at right and left intervals from the large beam 2. First, girder beam 4
The left and right end portions 6 and 6 of the above are respectively lifted by a large-sized crane 3, one end of which is connected to a large beam 2 which is already erected in a direction perpendicular to the cross girder 4 from the side direction, and the other end is on a temporary support column 7. (See Fig. 4).
次いで井桁梁4の中央部5を大型クレーン3、3によっ
て吊り上げ、すでに架設した左、右端部6、6間に位置
させて、仮設支柱7、7上に載置し、井桁梁4の中央部
5の両端部をそれぞれ左、右端部6、6と連結し、仮設
支柱7、7上のジャッキを下げて中央部5の荷重を左、
右端部によって支持する。さらに大梁4(井桁梁と平行
に架設された)と井桁梁4間、及び井桁梁4と井桁梁4
間に各々つなぎ梁9を掛け渡して連結し、順次上記作業
を行いコの字状の内部空間を井桁梁4とつなぎ梁9とに
よって井桁状に組み合せた梁架構を形成する(第5図、
第6図参照)。Next, the central portion 5 of the cross girder beam 4 is hoisted by the large cranes 3 and 3 and is placed between the left and right end portions 6 and 6 which have already been erected, and is placed on the temporary support columns 7 and 7, and the central portion of the cross girder beam 4 is placed. Both ends of 5 are connected to the left and right ends 6 and 6, respectively, and the jacks on the temporary columns 7 and 7 are lowered to load the central part 5 to the left,
Support by the right edge. Furthermore, between the large girder 4 (which was installed parallel to the girder beam) and the girder beam 4, and between the girder beam 4 and the girder beam 4.
Connecting beams are connected to each other and connected to each other, and the above work is sequentially performed to form a beam frame structure in which the U-shaped internal space is combined in a girder shape by the girder beams 4 and the connecting beams 9 (FIG. 5,
(See FIG. 6).
最後に残り一方向の大梁2を大黒柱1、1間に架設して
四本の大梁2によって方形状に組み、屋根部の梁架構を
終了する(第6図参照)。Finally, the remaining one-direction girder 2 is erected between the big black columns 1 and 1 and assembled into a square shape with four girders 2 to complete the beam structure of the roof portion (see FIG. 6).
この発明は以上のように二機のクレーンによって地上に
て地組みした梁を吊上げて架設するため、仮設資材をで
きる限り少なくすることができ、工期を短く、施工費を
安価にすることができる。Since the present invention hangs and erects the beams grounded on the ground by the two cranes as described above, it is possible to reduce temporary materials as much as possible, shorten the construction period, and reduce the construction cost. .
また高所での作業を少なくすることにもなり、作業の危
険性を低くすることができる。Further, the work at a high place is reduced, and the risk of work can be reduced.
第1図〜第6図はこの発明の施工順序を示す斜視図、第
7図〜第11図は大梁架設の施工順序を示す側面図であ
る。 1……大黒柱、2……大梁、3……クレーン、4……井
桁梁、5……井桁梁の中央部、6……井桁梁の左、右端
部、7……仮設支柱、8……回転架台、9……つなぎ
梁、10……トラワイヤ。1 to 6 are perspective views showing the construction order of the present invention, and FIGS. 7 to 11 are side views showing the construction order of the girder installation. 1 ... Daikoku Pillar, 2 ... Large Beam, 3 ... Crane, 4 ... Double Girder Beam, 5 ... Central part of Double Girder Beam, 6 ... Left and right ends of Double Girder Beam, 7 ... Temporary Post, 8 ... Rotating frame, 9 ... Connecting beam, 10 ... Tra-wire.
フロントページの続き (72)発明者 相沢 恂 神奈川県横浜市中区太田町4―51 鹿島建 設株式会社横浜支店内 (72)発明者 堀内 一文 神奈川県横浜市中区太田町4―51 鹿島建 設株式会社横浜支店内 (72)発明者 井上 正博 神奈川県横浜市中区太田町4―51 鹿島建 設株式会社横浜支店内 (72)発明者 三ノ輪 幸平 神奈川県横浜市中区太田町4―51 鹿島建 設株式会社横浜支店内Continuation of the front page (72) Kazumi Aizawa 4-51 Ota-machi, Naka-ku, Yokohama-shi, Kanagawa Kashima Construction Co., Ltd., Yokohama Branch (72) Kazumi Horiuchi 4-51, Ota-cho, Naka-ku, Yokohama, Kanagawa Ken Incorporated Yokohama Branch (72) Inventor Masahiro Inoue 4-51 Ota-machi, Naka-ku, Yokohama, Kanagawa Construction Kashima Construction Yokohama Branch (72) Inventor Kohei Minowa 4-51 Ota-machi, Naka-ku, Yokohama-shi, Kanagawa Kashima Construction Co., Ltd.Yokohama Branch
Claims (1)
設し、二機のクレーンによって地上で地組みした大梁を
吊上げ、各大黒柱間に架設してコの字状に組み、次いで
大梁間に囲まれたコの字状の内部空間内に井桁状に複数
本の井桁梁を組むものであり、井桁梁を架設するに際し
ては、井桁梁を長さ方向に三分割し、まず井桁梁の左、
右端部を大梁に連結して仮設支柱によって支持し、さら
に井桁梁の中央部を二機のクレーンによって吊上げて前
記井桁梁の左、右端部間に配して連結し、順次井桁梁を
交叉させて、井桁状に組んだ後、残り一方向の大梁を大
黒柱間に架設して方形状に組むことを特徴とする大規模
建造物の屋根部の施工法。1. A total of four large black pillars are erected in each of four directions, and a large beam grounded on the ground is lifted by two cranes and erected between the large black pillars to form a U-shape. , Next, a plurality of girder beams are assembled in a girder shape in a U-shaped internal space surrounded by girders.When erecting a girder beam, the girder beam is divided into three parts in the longitudinal direction, First of all, on the left side of the beam
The right end is connected to a large beam and supported by a temporary strut, and the center part of the girder beam is hoisted by two cranes to connect and connect between the left and right ends of the girder beam, and cross the girder beams sequentially. The construction method of the roof of a large-scale building is characterized by arranging it in the shape of a cross girder, and then erection a large beam in the other direction between the large black columns to form a square shape.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12654988A JPH0686751B2 (en) | 1988-05-24 | 1988-05-24 | Construction method for the roof of a large-scale building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12654988A JPH0686751B2 (en) | 1988-05-24 | 1988-05-24 | Construction method for the roof of a large-scale building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01295944A JPH01295944A (en) | 1989-11-29 |
| JPH0686751B2 true JPH0686751B2 (en) | 1994-11-02 |
Family
ID=14937927
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12654988A Expired - Lifetime JPH0686751B2 (en) | 1988-05-24 | 1988-05-24 | Construction method for the roof of a large-scale building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0686751B2 (en) |
-
1988
- 1988-05-24 JP JP12654988A patent/JPH0686751B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH01295944A (en) | 1989-11-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112482577B (en) | Large-span space chord supporting wheel spoke type truss structure system and construction method | |
| JPH04111829A (en) | Construction method for large span roofs | |
| JP2981061B2 (en) | How to build a cable dome roof | |
| JPH06200625A (en) | Frame method of arch truss construction | |
| JPH0686751B2 (en) | Construction method for the roof of a large-scale building | |
| JP2979039B2 (en) | Large space building construction equipment | |
| JP2579715B2 (en) | External tower crane | |
| JP3281962B2 (en) | Construction method of large space truss | |
| JP2950726B2 (en) | Construction method of multi-layer suspension structure | |
| JPH0686752B2 (en) | Construction method for the roof of a large-scale building | |
| JP2858891B2 (en) | Construction method of large span dome roof | |
| JPH11256690A (en) | Constructing method of roof structure | |
| JP3303218B2 (en) | Reconstruction method | |
| GB2268764A (en) | Roof structure with movable support columns | |
| CN222576243U (en) | A building construction frame that is easy to assemble | |
| JPH09256535A (en) | Constructing method of dome type roof | |
| JP2592980B2 (en) | Construction method of steel frame material for high-rise structure | |
| JP2547920B2 (en) | Push-up method and equipment for large span structures | |
| JP2634271B2 (en) | Jack-up method and device | |
| JP2994205B2 (en) | Structural assembly method | |
| JP2888913B2 (en) | External wall panel mounting method | |
| CN120465736A (en) | Truss support device and truss construction method | |
| JPH06185120A (en) | Construction method for upper structure of roof, etc. | |
| JPH05311868A (en) | Pillar reinforcement structure in temporarily installed beam assembly device for building construction | |
| JPH09310498A (en) | Stadium roof constructing technique |