JPH0686752B2 - Construction method for the roof of a large-scale building - Google Patents
Construction method for the roof of a large-scale buildingInfo
- Publication number
- JPH0686752B2 JPH0686752B2 JP12655088A JP12655088A JPH0686752B2 JP H0686752 B2 JPH0686752 B2 JP H0686752B2 JP 12655088 A JP12655088 A JP 12655088A JP 12655088 A JP12655088 A JP 12655088A JP H0686752 B2 JPH0686752 B2 JP H0686752B2
- Authority
- JP
- Japan
- Prior art keywords
- girder
- shape
- erected
- beams
- roof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は大規模建造物の屋根部の施工法に関するもの
である。TECHNICAL FIELD The present invention relates to a method for constructing a roof portion of a large-scale building.
体育館等の大規模建造物においては、梁のスパンが極め
て大きくなるため、このような梁の架設には従来様々な
施工法が採用されている。In a large-scale building such as a gymnasium, the span of the beam becomes extremely large, and thus various construction methods have been conventionally used for constructing such a beam.
例えば仮設支柱を立設し、この仮設支柱にて支えながら
梁を順に延ばして架設するなどが採用されているが、こ
のような施工法であると仮設資材が多数必要で施工費が
高価になるとともに、高所での作業が多くなり危険性が
増大することになる。For example, it is adopted to erected a temporary support pillar and extend the beam in order while supporting it with this temporary support pillar, but such a construction method requires a large number of temporary materials and the construction cost becomes expensive. At the same time, the amount of work in high places will increase and the risk will increase.
この発明は工期が短く、施工費が安価で、更に危険な作
業を少なくすることができる大規模建造物屋根部の施工
法を提供することを目的とする。It is an object of the present invention to provide a construction method for a large-scale building roof portion, which has a short construction period, a low construction cost, and can further reduce dangerous work.
この発明における、かかる大規模建造物の屋根部の施工
法は主としてクレーンを使用して梁の架設を行うもので
ある。The method of constructing the roof portion of such a large-scale building in the present invention mainly uses a crane to construct a beam.
まず四方向に各一本ずつ計四本の大黒柱を立設する。First, a total of four large black columns are erected, one in each of the four directions.
二機のクレーンによって地上で地組みした大梁を吊上
げ、各大黒柱間に架設してコの字状に組む。Two large cranes are used to hoist the large beams grounded above the ground, and they are erected between the large black columns to form a U-shape.
次いで大梁間に囲まれた内部空間内に井桁状に複数本の
井桁梁を組むものであり、架設に際しては、井桁梁の下
部に左、右端部間に跨ってタイバーを弦状に張設して変
形を防止し、井桁梁をクレーンによって吊上げて左、右
の前記大梁間に架設する。Next, multiple girder beams are assembled like a girder in the internal space surrounded by the girders.When erection, a tie bar is stretched in the shape of a chord at the bottom of the girder straddling the left and right ends. To prevent deformation, and the girder beam is hung by a crane and installed between the left and right girders.
残り一方向の大梁を大黒柱間に架設して方形状に組むこ
とを特徴としている。The other feature is that a large beam in one direction is installed between large black columns to form a square shape.
以下、図に示す一実施例に基づきこの発明を詳細に説明
する。The present invention will be described in detail below based on an embodiment shown in the drawings.
図において1は大黒柱であって、建造物の四隅角部を形
成する四方向に各一本ずつ、計四本、地上に立設する
(第1図参照)。この各大黒柱1、1間に地上にて地組
みしたトラス構造の大梁2を架設する。大梁2は大型の
クレーン3、3によって吊り上げて大梁2の左、右端部
が大黒柱1によって支持されるよう大黒柱1、1間に架
設し、まず三本の大梁2によって大黒柱1、1間に跨っ
てコの字状に組む(第2図、第3図参照)。In the figure, 1 is a large black pillar, and one is installed in each of the four directions forming the four corners of the building, a total of four standing on the ground (see FIG. 1). A large beam 2 having a truss structure grounded above the ground is erected between the large columns 1 and 1. The large beam 2 is hung by large cranes 3 and 3 and is erected between the large columns 1 and 1 so that the left and right ends of the large beam 2 are supported by the large columns 1, and first, the three large beams 2 are installed between the large columns 1 and 1. Assemble in a U-shape (see FIGS. 2 and 3).
大梁2の架設について、さらに詳述する。この大梁2は
第2図及び第3図に示めすように各々二本の分割梁2a、
2b及びつなぎ梁2cより成っており、架設に際しては、ま
ず分割梁2a、2bを地上にて地組みし、地上に固定した回
転架台8上にヒンジ結合する(第8図参照)。この分割
梁2a、2bを順次大型クレーン3、3によって建起し、回
転台8を軸心にして回転し起立する(第9図参照)。The construction of the girder 2 will be described in more detail. As shown in FIGS. 2 and 3, each of the large beams 2 has two split beams 2a,
It is composed of 2b and a connecting beam 2c. At the time of erection, the divided beams 2a and 2b are first grounded on the ground and hinged on a rotary mount 8 fixed on the ground (see FIG. 8). The divided beams 2a and 2b are sequentially erected by the large cranes 3 and 3, and are rotated around the rotary table 8 to stand up (see FIG. 9).
この分割梁2a、2bを順次回転架台8から離脱して、その
ままクレーン3、3によって吊り上げて大黒柱間に架設
する(第10図乃至第12図参照)。この場合、分割梁2a、
2bには地上からトラワイヤ10を張って、風荷重による変
形を防止するとともに建方精度微調整を行う。また分割
梁2a、2bを吊り上げた状態で、分割梁2a、2b間につなぎ
梁2cを取付け、所定の位置において大黒柱1に連結し、
クレーン3、3を解放し、さらに建入精度を確認し、ト
ラワイヤ10を撤去する。順次同様の作業を繰り返すこと
によって大梁2を大黒柱1、1間に架設する。The divided beams 2a and 2b are sequentially removed from the rotary mount 8 and lifted up by the cranes 3 and 3 to be installed between the large black columns (see FIGS. 10 to 12). In this case, split beam 2a,
A trawl wire 10 is stretched from the ground to 2b to prevent deformation due to wind load and finely adjust the erection accuracy. In addition, while the split beams 2a and 2b are suspended, a connecting beam 2c is attached between the split beams 2a and 2b and connected to the large black pillar 1 at a predetermined position,
The cranes 3 and 3 are released, the construction accuracy is confirmed, and the trawl wire 10 is removed. The girder 2 is installed between the big columns 1 and 1 by sequentially repeating the same operation.
以上のようにして架設された大梁2は、一方向を除いて
三方向を囲むコの字状に架設され(第3図参照)、これ
ら大梁2、2によって囲まれた内部空間内に、井桁状に
梁を組み合せるための井桁梁4を架設する(第4図、第
5図参照)。The girder 2 erected as described above is erected in a U-shape that surrounds three directions except one direction (see FIG. 3), and the girder is placed in the internal space surrounded by these girders 2 and 2. The cross girder beam 4 for combining the beams in a circular shape is erected (see FIGS. 4 and 5).
井桁梁4はH型鋼を二本組み合せたもので、長さ方向の
全体が山形状に形成されている。井桁梁4の架設に際し
ては、井桁梁4の下部に左、右側部間に跨ってタイバー
11を弦状に張設し、たわみ等による変形を防止する。タ
イバー11は張力をコントロールすることにより伸縮する
(第7図参照)。The double girder beam 4 is a combination of two H-shaped steels, and the entire lengthwise direction is formed in a mountain shape. At the time of erection of the girder beam 4, a tie bar should be installed at the bottom of the girder beam 4 across the left and right sides.
11 is stretched like a string to prevent deformation due to bending, etc. The tie bar 11 expands and contracts by controlling the tension (see Fig. 7).
この井桁梁4を二機のクレーン3、3によって吊り上
げ、既設の左、右大梁2、2間に架け渡して連結し、順
次上記の作業を行い、コの字状の内部空間内に井桁梁4
とつなぎ梁9とによって井桁状に組合せた梁架構を形成
する(第4図、第5図参照)。This double girder beam 4 is hoisted by two cranes 3 and 3 and is bridged and connected between the existing left and right large girders 2 and 2, and the above work is carried out in order, and the double girder beam is placed in the U-shaped internal space. Four
A beam frame combined in a cross beam shape is formed by the connecting beams 9 (see FIGS. 4 and 5).
最後に残り一方向の大梁2を大黒柱1、1間に架設して
四本の大梁によって方形状に組み、屋根部の梁架構を終
了する(第6図参照)。Finally, the remaining one-direction girder 2 is erected between the big black columns 1 and 1 and assembled into a square shape with four girders, and the beam structure of the roof is completed (see FIG. 6).
この発明は以上のように二機のクレーンによって地上に
て地組みした梁を吊上げて架設するため、仮設資材をで
きる限り少なくすることができ、工期を短く、施工費を
安価にすることができる。Since the present invention hangs and erects the beams grounded on the ground by the two cranes as described above, it is possible to reduce temporary materials as much as possible, shorten the construction period, and reduce the construction cost. .
また高所での作業を少なくすることにもなり、作業の危
険性を低くすることができる。Further, the work at a high place is reduced, and the risk of work can be reduced.
さらに井桁梁はタイバーによって変形を防止して吊上げ
るため、仮設柱が不要で施工を迅速化できる。Furthermore, since the girder beams are lifted while being prevented from being deformed by the tie bars, temporary pillars are not required and the construction can be speeded up.
第1図〜第6図はこの発明の施工順序を示す斜視図、第
7図は井桁梁の斜視図、第8図〜第12図は大梁架設の施
工順序を示す斜視図である。 1……大黒柱、2……大梁、3……クレーン、4……井
桁梁、5……井桁梁の中央部、6……井桁梁の左、右端
部、7……仮設支柱、8……回転架台、9……つなぎ
梁、10……トラワイヤ、11……タイバー。1 to 6 are perspective views showing a construction order of the present invention, FIG. 7 is a perspective view of a cross beam, and FIGS. 8 to 12 are perspective views showing a construction order of a girder erection. 1 ... Daikoku Pillar, 2 ... Large Beam, 3 ... Crane, 4 ... Double Girder Beam, 5 ... Central part of Double Girder Beam, 6 ... Left and right ends of Double Girder Beam, 7 ... Temporary Post, 8 ... Rotating mount, 9 ... Connecting beam, 10 ... Tra-wire, 11 ... Tie bar.
Claims (1)
し、二機のクレーンによって地上で地組みした大梁を吊
上げ、各大黒柱間に架設してコの字状に組み、次いで大
梁間に囲まれたコの字状の内部空間内に井桁状に複数本
の井桁梁を組むものであり、井桁梁は長さ方向全体が山
形状に形成してあり、架設に際しては、井桁梁の下部に
左、右端部間に跨ってタイバーを弦状に張設して変形を
防止し、井桁梁をクレーンによって吊り上げて左、右の
大梁間に架設し、井桁状に組んだ後、残り一方向の大梁
を大黒柱間に架設して方形状に組むことを特徴とする大
規模建造物の屋根部の施工法。Claims: 1. Four large black pillars are erected one by one in four directions, a large beam grounded on the ground is hoisted by two cranes, and it is erected between the large black pillars and assembled in a U shape, Next, multiple girder beams are assembled like a girder in the U-shaped internal space surrounded by girders.The girder girder is formed in a mountain shape in the entire length direction. A tie bar is stretched in the shape of a string across the left and right ends at the bottom of the girder beam to prevent deformation, and the girder beam is hung by a crane and erected between the left and right girders, and then assembled into a girder shape. , A method for constructing a roof of a large-scale building, characterized by erection of a large beam in the other direction between large black columns to form a square shape.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12655088A JPH0686752B2 (en) | 1988-05-24 | 1988-05-24 | Construction method for the roof of a large-scale building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12655088A JPH0686752B2 (en) | 1988-05-24 | 1988-05-24 | Construction method for the roof of a large-scale building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01295945A JPH01295945A (en) | 1989-11-29 |
| JPH0686752B2 true JPH0686752B2 (en) | 1994-11-02 |
Family
ID=14937949
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12655088A Expired - Lifetime JPH0686752B2 (en) | 1988-05-24 | 1988-05-24 | Construction method for the roof of a large-scale building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0686752B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105625578B (en) * | 2016-02-05 | 2017-09-12 | 中国航空规划设计研究总院有限公司 | It is adapted to the huge prestressing force beam string structure and construction method of the closing of super-span coal yard |
-
1988
- 1988-05-24 JP JP12655088A patent/JPH0686752B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH01295945A (en) | 1989-11-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112482577B (en) | Large-span space chord supporting wheel spoke type truss structure system and construction method | |
| JPH04111829A (en) | Construction method for large span roofs | |
| JP3072972B2 (en) | Frame system in slip form method | |
| JP2927320B2 (en) | How to assemble a large hanging boiler | |
| JP4107179B2 (en) | Construction method of steel structure | |
| JPH0686752B2 (en) | Construction method for the roof of a large-scale building | |
| JP2950726B2 (en) | Construction method of multi-layer suspension structure | |
| JPH03103560A (en) | Truss structure | |
| JPH11256690A (en) | Constructing method of roof structure | |
| JPH0686751B2 (en) | Construction method for the roof of a large-scale building | |
| JP2858891B2 (en) | Construction method of large span dome roof | |
| JPH03293447A (en) | Erection of long span construction | |
| JPH06330635A (en) | Unloading device for temporarily pitch tent | |
| JPS634141A (en) | Construction of three-dimensional truss structure | |
| JP2634271B2 (en) | Jack-up method and device | |
| JPH02213573A (en) | Super high tower | |
| JP2001073459A (en) | Construction method of roof structure | |
| JPH03217562A (en) | Garret structure | |
| JPH0423709B2 (en) | ||
| JPS61212438A (en) | Manufacturing method for foundation reinforced columns | |
| JP3324807B2 (en) | Column-beam pre-assembled reinforced body and pre-assembled reinforced construction method using it | |
| JPS62228568A (en) | Construction of roof of structure | |
| JPS6113065B2 (en) | ||
| JPS62101765A (en) | Grating like cable dome | |
| JPH08109678A (en) | Execution method of large-sized roof |