JPH0711199B2 - Nuclear power plant building construction method - Google Patents
Nuclear power plant building construction methodInfo
- Publication number
- JPH0711199B2 JPH0711199B2 JP60180421A JP18042185A JPH0711199B2 JP H0711199 B2 JPH0711199 B2 JP H0711199B2 JP 60180421 A JP60180421 A JP 60180421A JP 18042185 A JP18042185 A JP 18042185A JP H0711199 B2 JPH0711199 B2 JP H0711199B2
- Authority
- JP
- Japan
- Prior art keywords
- steel
- steel frame
- construction
- work
- power plant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 〔発明の技術分野〕 本発明は原子力プラントの建屋建設工法に係り、特に、
原子炉建屋やタービン建屋等の建屋の建設工期の短縮と
建設コストの低減を図る原子力プラントの建屋建設工法
に関する。Description: TECHNICAL FIELD OF THE INVENTION The present invention relates to a building construction method for a nuclear plant, and in particular,
The present invention relates to a nuclear power plant building construction method for shortening the construction period of buildings such as a reactor building and a turbine building and reducing the construction cost.
一般に、原子力プラントでは原子炉建屋やタービン建屋
等、各種建屋を建設しており、一般的なタービン建屋の
構成の一例を第8図に示す。Generally, in a nuclear power plant, various buildings such as a reactor building and a turbine building are constructed, and an example of the configuration of a general turbine building is shown in FIG.
タービン建屋はその基礎および下部をなす基礎構造物A
の上面に運転床1を形成し、この運転床1上に鉄骨構造
物Bを立設している。鉄骨構造物Bは基礎構造物Aの運
転床1上に多数の鉄骨柱2を立設し、これら鉄骨柱2の
前後方向にはトラス3がその上端部間に複数架設され、
これらトラス3相互間と鉄骨柱2相互間は小梁鉄骨4に
より横方向に連結される。また、鉄骨柱2の上部内側に
は一対のレールガーダ5が前後方向で対向するように固
着され、これらレールガータ5上にはレールがそれぞれ
敷設され、この一対のレール上には天井走行クレーン6
が搭載され、鉄骨構造物B内を縦横に走行できるように
なっている。Turbine building is the basic structure and its underlying structure A
The operation floor 1 is formed on the upper surface of the steel floor structure 1, and the steel frame structure B is erected on the operation floor 1. In the steel structure B, a large number of steel columns 2 are erected on the operation floor 1 of the substructure A, and a plurality of trusses 3 are installed between the upper ends of the steel columns 2 in the front-rear direction.
The trusses 3 and the steel columns 2 are laterally connected by the beam girders 4. A pair of rail girders 5 are fixed to the inside of the upper part of the steel frame column 2 so as to face each other in the front-rear direction.
Is mounted so that the steel frame structure B can be run vertically and horizontally.
鉄骨構造物Bの側壁はプレハブ化された壁板7の多数枚
を鉄骨柱2の外側に添設してなり、トラス3上には屋根
を支えるためのデッキプレート8を敷き詰め、配筋を組
んでコンクリート9を打設して屋根を形成している。The side wall of the steel structure B is made up of a large number of prefabricated wall plates 7 attached to the outside of the steel column 2, and a deck plate 8 for supporting the roof is laid on the truss 3 to form a bar arrangement. The concrete 9 is poured to form the roof.
このように構成されたタービン建屋の従来の建設工法
は、まず、基礎構造物Aを構築して運転床1を完成させ
る。次いで、この運転床1上に天井走行クレーン6を付
設した鉄骨構造物Bを立設する。しかる後に、この鉄骨
構造物Bの側壁および屋根Cを設ける工事を行なってい
た。In the conventional construction method of the turbine building thus configured, first, the foundation structure A is constructed and the operation floor 1 is completed. Next, the steel frame structure B provided with the overhead traveling crane 6 is erected on the operation floor 1. After that, the side wall of the steel structure B and the roof C were installed.
しかしながら、このような従来の建屋建設工法では、基
礎構造物Aの建設工事→鉄骨構造物Bの組立工事→鉄骨
構造物Bの側壁および屋根Cを設ける工事とこの順に順
次工事を進めて行き、各工事は一列に連続し、いわば直
列に接続されている。However, in such a conventional building construction method, the construction work of the basic structure A → the assembly work of the steel frame structure B → the side wall of the steel structure B and the roof C are sequentially carried out in this order, Each work is continuous in a line and is connected in series.
このために、従来工法では基礎構造物Aの運転床1が完
成してから、鉄骨構造物Bとその側壁および屋根Cとが
完成する迄の期間が長期化し、これが建屋建設工事全体
のクリティカルパスとなって、原子力プラント建設工期
の長期化を招く原因の一つとなっていた。Therefore, in the conventional method, the period from completion of the operation floor 1 of the substructure A to completion of the steel structure B, its side walls and the roof C is prolonged, which is a critical path for the entire building construction work. That was one of the causes of prolonging the construction period of the nuclear power plant.
また、運転床1より下方の基礎構造物A内に配置される
各種機械設備、配管等の据付工事の際には、風雨等に対
する保護養生作業が事前に必要となるが、この作業のた
めに、他の作業に手待ちが生じ、工事がさらに長期化し
ていた。Also, during installation work of various mechanical equipment and pipes arranged in the substructure A below the operation floor 1, protection and protection work against wind and rain is required in advance, but for this work , The work had to wait for other work, and the construction was prolonged.
本発明は上記事情に鑑みなされたもので、建設工期の大
幅な短縮と、建設コストの低減と、作業の安全性の向上
とを図ることができる原子力プラントの建屋建設工法を
提供することを目的とする。The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a building construction method for a nuclear power plant capable of significantly shortening the construction period, reducing construction cost, and improving work safety. And
本発明は従来工法の問題点が基礎構造物の建設工事完了
後に鉄骨構造物の組立工事を行なっていたことに起因す
る点に着目してなされたものであり、これら両工事を並
行して行ない、基礎構造物の運転床の完成後に、この運
転床上に鉄骨構造物を移動して固定し、これにより、建
設工期の大幅な短縮と建設コストの低減と作業の安全性
の向上とを可能としたことを特徴とする。The present invention was made by paying attention to the point that the problem of the conventional construction method was caused by the assembling work of the steel frame structure after the completion of the construction work of the foundation structure, and both these works are performed in parallel. After the operation floor of the foundation structure is completed, the steel frame structure is moved and fixed on the operation floor, which enables the construction period to be significantly shortened, the construction cost to be reduced, and the work safety to be improved. It is characterized by having done.
以下、本発明の一実施例について第1図〜第7図を参照
して説明する。なお、第1図〜第7図中、第8図と共通
する部分には同一符号を付している。An embodiment of the present invention will be described below with reference to FIGS. In FIGS. 1 to 7, the same parts as those in FIG. 8 are designated by the same reference numerals.
本実施例は第8図で示すように構成されたタービン建屋
の建設工法の一例であり、基礎構造物Aの運転床1が完
成する所定の期間前に、この基礎構造物Aの地下部分を
埋戻し、基礎構造物Aの隣接地に鉄骨構造物Bを組立て
る組立現場Dをまず造成し、鉄骨構造物Bの組立工事を
基礎構造物Aの建設工事と並行して進めて行く。The present embodiment is an example of a construction method of a turbine building configured as shown in FIG. 8, and before the predetermined period when the operation floor 1 of the substructure A is completed, the underground portion of the substructure A is First, an assembly site D for backfilling and assembling the steel structure B on the ground adjacent to the substructure A is created, and the assembling work for the steel structure B proceeds in parallel with the construction work for the substructure A.
次に、この組立現場Dには第1図に示すように少なくと
も前後一対の架台10a,10bを並設する。Next, at this assembly site D, at least a pair of front and rear mounts 10a and 10b are installed in parallel as shown in FIG.
一対の架台10a,10bは基礎構造物Aの運転床1と同一高
さに設置され、各架台10a,10b上には第2図に示すよう
に複数本、例えば内側と外側とで各2本づつの合計4本
の工形鋼の軌道レール11a,11bが前後方向に所定の間隔
をおいて全長に亘って並設されている。さらに、各軌道
レール11a,11b上には断面矩形の直棒上の滑動レール12
がそれぞれ固着され、各滑動レール12の外側壁には矩形
片のストッパ13を軸方向に所要のピッチで全長に亘って
配置している。The pair of pedestals 10a and 10b are installed at the same height as the operation floor 1 of the substructure A, and a plurality of pedestals 10a and 10b are provided on each of the pedestals 10a and 10b as shown in FIG. A total of four track rails 11a, 11b of shaped steel are arranged side by side in the front-rear direction at predetermined intervals along the entire length. Furthermore, on each track rail 11a, 11b, a sliding rail 12 on a straight rod with a rectangular cross section is used.
Are fixed to each other, and rectangular stoppers 13 are arranged on the outer wall of each sliding rail 12 in the axial direction at a required pitch over the entire length.
また、各軌道レール11a,11bの上面には鉄骨柱14の下端
部を仮固定するためのボルト穴15を軸方向に所要のピッ
チで穿設している。In addition, bolt holes 15 for temporarily fixing the lower end of the steel column 14 are bored in the upper surface of each track rail 11a, 11b at a required pitch in the axial direction.
しかる後に、クレーン16により鉄骨柱14を懸吊し、第3
図に示すように、各滑動レール12上に複数の鉄骨柱14を
起立させて搭載し、鉄骨柱14の下端部を介してボルト穴
15内にボルトを通してナットを締め付けることにより、
鉄骨柱14の下端部を各滑動レール12上に仮に固定してお
く。この作業の繰り返しにより、各滑動レール12上に立
設した複数の鉄骨柱14の上端部間には、地上にて予め組
立てられたトラス3を前後方向に架設して門形に組立て
る。この門形の鉄骨組立体を第3図に示すように架台10
a,10bの長手方向に複数並設し、これらを安全綱17に結
着して、その転倒の防止を図っている。但し、このと
き、架台10a,10bの長手方向ほぼ中間部にて立脚する鉄
骨柱14にはトラス3が架設されておらず、空間部18(第
5図参照)が形成されている。After that, the steel pillar 14 is suspended by the crane 16 and the third
As shown in the figure, a plurality of steel frame columns 14 are erected and mounted on each sliding rail 12, and bolt holes are inserted through the lower ends of the steel frame columns 14.
By passing the bolt inside 15 and tightening the nut,
The lower end of the steel column 14 is temporarily fixed on each sliding rail 12. By repeating this operation, the truss 3 preassembled on the ground is installed in the front-rear direction between the upper ends of the plurality of steel frame columns 14 erected on the sliding rails 12 to assemble in a gate shape. This gate-shaped steel frame assembly is installed as shown in FIG.
A plurality of a and 10b are provided side by side in the longitudinal direction, and these are connected to a safety rope 17 to prevent the falls. However, at this time, the truss 3 is not erected on the steel frame column 14 standing at approximately the middle portion in the longitudinal direction of the gantry 10a, 10b, and the space portion 18 (see FIG. 5) is formed.
次に、鉄骨柱14とトラス3とで形成される門形の鉄骨組
立体相互を小梁鉄骨4により横方向に順次連結して、か
ご状の鉄骨構造物Bを組立て、その内部上部にて第4図
に示すように一対のレールガーダ5が前後方向で対向す
るように配置する。この後、第5図に示すように天井走
行クレーン6を空間部18より鉄骨構造物B内に搬入し
て、一対のレールガーダ5上に搭載する。この天井走行
クレーン6の組立作業は鉄骨柱14の立上げ作業と並行し
て地上で行なっており、その一対のクレーンガーダ6aを
一対のレールガーダ5上に横方向移動可能に搭載すると
共に、これらクレーンガーダ6a上にはトロリー6bを前後
方向移動可能に搭載している。Next, the gate-shaped steel frame assemblies formed of the steel frame columns 14 and the trusses 3 are sequentially connected in the lateral direction by the beam girder steel frames 4 to assemble a cage-shaped steel frame structure B, and at the inner upper portion thereof. As shown in FIG. 4, a pair of rail girders 5 are arranged so as to face each other in the front-rear direction. Thereafter, as shown in FIG. 5, the overhead traveling crane 6 is carried into the steel frame structure B from the space 18 and mounted on the pair of rail girders 5. The assembling work of the overhead traveling crane 6 is performed on the ground in parallel with the rising work of the steel columns 14, and the pair of crane girders 6a are mounted on the pair of rail girders 5 so as to be movable in the lateral direction. A trolley 6b is mounted on the girder 6a so as to be movable in the front-rear direction.
しかる後に、上記天井走行クレーン6等を搬入した空間
部18にトラス3を架設し、鉄骨構造物Bの組立を完了さ
せる。Thereafter, the truss 3 is installed in the space 18 into which the overhead traveling crane 6 and the like have been carried in, and the assembly of the steel frame structure B is completed.
鉄骨構造物Bが完成し、しかも、この鉄骨構造物Bの組
立工事と並行して行なっていた基礎構造物Aの運転床1
が完成したときは、この運転床1上の所定位置に鉄骨構
造物Bを移動し、固定する。The steel structure B is completed, and the operation floor 1 of the basic structure A, which was performed in parallel with the assembling work of the steel structure B
When is completed, the steel frame structure B is moved to a predetermined position on the operation floor 1 and fixed.
次に、この移動方法等について述べる。Next, the moving method and the like will be described.
まず、完成した基礎構造物Aの運転床1上に、滑動レー
ル12を固着させた軌道レール11a,11bをそれぞれ延長し
て敷設し、その後、各鉄骨柱14を各軌道レール11a,11b
上に固定していたボルト・ナットおよび安全綱17を全て
取外す。First, on the operation floor 1 of the completed substructure A, the track rails 11a and 11b to which the sliding rails 12 are fixed are respectively extended and laid, and then each steel frame column 14 is installed to each track rail 11a and 11b.
Remove all bolts and nuts and safety rope 17 that were fixed above.
次に、第6図に示すように各滑動レール12上の鉄骨柱14
の下端部と、ストッパ13との間にジャッキ19を介在さ
せ、ジャッキ19を操作して鉄骨柱14を各滑動レール12上
を滑動させて、第7図の矢印で示すように基礎構造物A
に向けて順次移動させて行き、鉄骨構造物Bを運転床1
上の所定位置に位置決めする。Next, as shown in FIG. 6, the steel columns 14 on each sliding rail 12 are shown.
A jack 19 is interposed between the lower end of the and the stopper 13 and the jack 19 is operated to slide the steel column 14 on each sliding rail 12 to move the foundation structure A as shown by the arrow in FIG.
Steel structure B to the operation floor 1
Position it at the upper predetermined position.
次いで、各鉄骨柱14の下端部を各軌道レール11a,11bと
共に、図示しない基礎ボルト等を用いて運転床1上に固
着させる。これにより、鉄骨構造物Bが基礎構造物A上
の所定位置に立設される。Next, the lower ends of the steel columns 14 are fixed to the operation floor 1 together with the track rails 11a and 11b by using a foundation bolt or the like (not shown). As a result, the steel structure B is erected at a predetermined position on the foundation structure A.
しかる後に、鉄骨構造物Bに側壁・屋根Cを設けて、タ
ービン建屋が完成する。したがって、本実施例によれば
鉄骨構造物Bの組立工事を基礎構造物Aの建設工事と並
行して行なうので、建設工期の大幅な短縮と建設コスト
の低減を図ることができる。Then, the side wall and the roof C are provided on the steel structure B to complete the turbine building. Therefore, according to this embodiment, the assembling work of the steel structure B is performed in parallel with the construction work of the foundation structure A, so that the construction period can be greatly shortened and the construction cost can be reduced.
また、鉄骨構造物Bの屋根工事を従来例よりも早期に完
了させることができるので、運転床1より下方の基礎構
造物A内にて機械設備、配管工事を行なう際には、これ
らを上記屋根により風雨等から保護することができるの
で、従来例で必要としていた養生保護のための作業を省
略することができ、建設工数の低減と作業の安全性の向
上を図ることができる。Further, since the roof construction of the steel frame structure B can be completed earlier than in the conventional example, when mechanical equipment and piping work is performed in the substructure A below the operation floor 1, these are Since the roof can protect from wind and rain, it is possible to omit the work for protection and protection required in the conventional example, and it is possible to reduce the number of construction steps and improve the work safety.
以上説明したように本発明は、鉄骨構造物の組立工事を
基礎構造物の建設工事と並行して行なうので、建設工期
の大幅な短縮と建設コストの低減を図ることができる。As described above, according to the present invention, the assembling work of the steel frame structure is performed in parallel with the construction work of the foundation structure, so that the construction period can be greatly shortened and the construction cost can be reduced.
また、本発明によれば鉄骨構造物の屋根工事を従来例よ
りも早期に完了させることができるので、運転床より下
方の基礎構造物内にて機械設備、配管工事を行なう際に
は、これらを上記屋根により風雨等から保護することが
できるので、従来例で必要としていた養生保護のための
作業を省略することができ、建設工数の低減と作業の安
全性の向上を図ることができる。Further, according to the present invention, since the roof construction of the steel frame structure can be completed earlier than the conventional example, when performing the mechanical equipment and the piping construction in the foundation structure below the operation floor, Since the roof can be protected from wind and rain by the above roof, the work for protection and protection required in the conventional example can be omitted, and the number of construction steps can be reduced and the work safety can be improved.
第1図〜第7図は本発明の一実施例の建設工程をそれぞ
れ示しており、第1図は軌道レールを敷設する工程を示
す斜視図、第2図は第1図のE部拡大斜視図、第3図は
鉄骨柱とトラスとの組立を行なう工程を示す斜視図、第
4図は鉄骨構造物内にレールガーダを配置する工程を示
す正面図、第5図は天井走行クレーンを鉄骨構造物内に
取付ける工程を示す正面図、第6図は完成した鉄骨構造
物を基礎構造物の運転床上に移動する際の移動方法を説
明するための要部拡大正面図、第7図は鉄骨構造物の移
動状態を示す正面図、第8図はタービン建屋の一般的構
成を示す斜視図である。 A……基礎構造物、B……鉄骨構造物、1……運転床、
2,14……鉄骨柱、3……トラス、4……小梁鉄骨、5…
…レールガーダ、6……天井走行クレーン、10a,10b…
…架台、11a,11b……軌道レール。1 to 7 show a construction process of an embodiment of the present invention, respectively. FIG. 1 is a perspective view showing a process of laying a track rail, and FIG. 2 is an enlarged perspective view of an E portion of FIG. 3 and 4 are perspective views showing a process of assembling a steel column and a truss, FIG. 4 is a front view showing a process of arranging a rail girder in a steel frame structure, and FIG. 5 is a steel frame structure of an overhead traveling crane. FIG. 6 is a front view showing a step of mounting the structure in an object, FIG. 6 is an enlarged front view of an essential part for explaining a moving method when the completed steel frame structure is moved onto the operation floor of the foundation structure, and FIG. 7 is a steel frame structure. FIG. 8 is a front view showing a moving state of an object, and FIG. 8 is a perspective view showing a general structure of a turbine building. A ... Foundation structure, B ... Steel structure, 1 ... Driving floor,
2,14 ... Steel columns, 3 ... Truss, 4 ... Girder steel frame, 5 ...
… Rail girder, 6… Overhead traveling crane, 10a, 10b…
… Mounts, 11a, 11b …… Track rails.
Claims (2)
建設工事と、この基礎構造物の運転床上に立設される鉄
骨構造物の組立工事とを行なう原子力プラントの建屋建
設工法において、前記基礎構造物の建設地から隣接地ま
で敷設された軌道レール上にて前記基礎構造物の建設工
事と並行して前記鉄骨構造物を組立てる工程と、この鉄
骨構造物を組み立てた後前記軌道レールに沿って前記基
礎構造物上まで移動せしめる工程と、この移動した鉄骨
構造物を前記基礎構造物上に設置する工程とを有するこ
とを特徴とする原子力プラントの建屋建設工法。1. A building construction method for a nuclear power plant, which comprises a construction of a foundation of a building and a foundation structure constituting a lower part thereof, and an assembly of a steel frame structure erected on an operating floor of the foundation structure. A step of assembling the steel frame structure in parallel with the construction work of the foundation structure on the track rail laid from the construction site of the foundation structure to the adjacent land, and after assembling the steel frame structure to the track rail. A method for constructing a building of a nuclear power plant, comprising: a step of moving the steel structure to the foundation structure along with a step of installing the moved steel frame structure on the foundation structure.
立てと取付作業を含む特許請求の範囲第1項に記載の原
子力プラントの建屋建設工法。2. The method for constructing a building for a nuclear power plant according to claim 1, wherein the assembling work of the steel frame structure includes assembling and mounting work of an overhead crane.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP60180421A JPH0711199B2 (en) | 1985-08-19 | 1985-08-19 | Nuclear power plant building construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP60180421A JPH0711199B2 (en) | 1985-08-19 | 1985-08-19 | Nuclear power plant building construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6241871A JPS6241871A (en) | 1987-02-23 |
| JPH0711199B2 true JPH0711199B2 (en) | 1995-02-08 |
Family
ID=16082966
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP60180421A Expired - Lifetime JPH0711199B2 (en) | 1985-08-19 | 1985-08-19 | Nuclear power plant building construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0711199B2 (en) |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS525770B2 (en) * | 1973-10-05 | 1977-02-16 | ||
| JPS5242630A (en) * | 1975-09-30 | 1977-04-02 | Nippon Kokan Kk | Metod of constructing outer building such as factory |
| JPS5968455A (en) * | 1982-10-13 | 1984-04-18 | 株式会社大林組 | Traverse pulling of steel skeletal enclosure |
| JPS59179936A (en) * | 1983-03-31 | 1984-10-12 | Toshiba Corp | Construction work of building |
| JPS59220561A (en) * | 1983-05-31 | 1984-12-12 | 株式会社竹中工務店 | Horizontal moving enclosure construction method |
-
1985
- 1985-08-19 JP JP60180421A patent/JPH0711199B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6241871A (en) | 1987-02-23 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106760529B (en) | Roof steel truss sliding assembly construction platform and installation method | |
| CN112095780B (en) | A superstructure system for rail operating lines and its implementation method | |
| CN210049103U (en) | High-grade high-speed highway bracket spanned by large-span cast-in-place box girder | |
| CN110388096A (en) | A structure and construction method for flexible construction of coke oven greenhouses | |
| CN212335747U (en) | Beam slab in-situ prefabrication and installation system | |
| JPH07107360B2 (en) | Station construction method using multi-connection shield method | |
| JPH0633627B2 (en) | New construction method on existing facility | |
| CN118498732A (en) | Sliding pushing construction method for large-span steel structure roof | |
| JPH0711199B2 (en) | Nuclear power plant building construction method | |
| CN210798013U (en) | Cross beam floor system formed by crossed arrangement of steel secondary beams and trusses | |
| CN222275273U (en) | Soft foundation geology large-span roof beam pouring bearing structure | |
| CN222314659U (en) | An in-situ suspension protection device for a large-span power pipeline gallery | |
| CN222685270U (en) | High-altitude operation construction platform | |
| JPH0336362B2 (en) | ||
| CN222614717U (en) | A movable protective device for the construction of large-span structures in existing subway depots | |
| JP7152383B2 (en) | Structural column base structure and column base fixing method | |
| JP2513376B2 (en) | How to build a building | |
| CN211735083U (en) | Integral protective shed frame for use in revolving construction of box girder of viaduct over railway | |
| CN108166783A (en) | The assembled steel reinforced machining shed and its assembly method that can be had enough to meet the need | |
| JP2832278B2 (en) | Building method | |
| CN115288403A (en) | Assembly type operation platform system | |
| CN211472863U (en) | Detachable double-layer isolation shed for processing steel bars in construction site | |
| JP3303218B2 (en) | Reconstruction method | |
| JP2717154B2 (en) | Building method | |
| CN117904968A (en) | Upper span assembled arch ring protection and support integrated bracket and construction method |