JPH0715183B2 - Connection structure of precast steel concrete columns - Google Patents
Connection structure of precast steel concrete columnsInfo
- Publication number
- JPH0715183B2 JPH0715183B2 JP15773589A JP15773589A JPH0715183B2 JP H0715183 B2 JPH0715183 B2 JP H0715183B2 JP 15773589 A JP15773589 A JP 15773589A JP 15773589 A JP15773589 A JP 15773589A JP H0715183 B2 JPH0715183 B2 JP H0715183B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- psc
- column
- precast
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は、プレキャスト鉄骨コンクリート柱を使用した
多階建築物の構築に際し、そのコンクリート柱を互いに
突き合わせ位置に連結する連結構造に関する。Description: TECHNICAL FIELD The present invention relates to a connecting structure for connecting concrete columns to a butt position when constructing a multi-storey building using precast steel concrete columns.
(従来の技術) 近年、工期の短縮化、工事の簡略化及び品質の安定化を
企図して、予め工場にて管理製造されたプレキャスト鉄
骨コンクリート柱体(以下PSC柱体と略記する)を使用
した工法が開発されており、この工法は第6図に示すよ
うに運搬の都合上全長を複数に分割したPSC柱体1,1……
を互いに突き合わせ配置に連結し、また各PSC柱体1,1…
…の側面に突出させた梁連結突部2,2間にプレキャスト
大梁3,3……を掛け渡して固定している。(Prior art) In recent years, precast steel-reinforced concrete pillars (hereinafter abbreviated as PSC pillars) manufactured and managed in advance in the factory are used in order to shorten the construction period, simplify the construction, and stabilize the quality. A new construction method has been developed. As shown in Fig. 6, this construction method has PSC columns 1,1 ...
Are connected to each other in a butt arrangement, and each PSC column 1,1…
Precast large girders 3 and 3 are hung and fixed between the beam connecting projections 2 and 2 which are projected to the side of.
この従来のPSC柱体1,1の連結は、第7図〜第8図に示す
ように内部の鉄骨4を端面に突出させたPSC柱体1を使
用し、その鉄骨4,4を互いに突き合わせ、両鉄骨4,4にま
たがらせて連結プレート5をボルト6によって固定した
後、その鉄骨4,4の露出部分に後打コンクリート7を打
設することにより行っている。The connection of this conventional PSC column 1,1 uses the PSC column 1 in which the internal steel frame 4 is projected to the end face as shown in FIG. 7 to FIG. 8, and the steel frames 4, 4 are butted against each other. After fixing the connecting plate 5 by straddling both steel frames 4 and 4 with bolts 6, post-casting concrete 7 is placed on the exposed portions of the steel frames 4 and 4.
(発明が解決しようとする課題) 一般に鉄骨コンクリート柱体は、鉄骨とコンクリートと
が一定の割合で垂直荷重を分担するのが好ましく、全体
に一様な場所打コンクリート柱体や、一本のPSC柱体に
おいては鉄骨とコンクリートとが同時に垂直荷重を支え
る構造となっている。(Problems to be Solved by the Invention) Generally, in a steel-framed concrete column, it is preferable that the steel frame and the concrete share a vertical load at a constant rate, and a uniform cast-in-place concrete column or a single PSC is used throughout. In the column, steel frame and concrete simultaneously support vertical load.
これに対し、上述した従来のPSC柱体の連結構造による
場合は、PSC柱体から鉄骨のみを突出させ、これを連結
した後、後打コンクリートにて上下の柱体間の空間を埋
めるため、後打コンクリートの荷重負担割合が小さく、
連結部分における鉄骨の荷重負担が他の部分より大きく
なってしまい、このため連結後の柱体に断面欠損が存在
しているのと同じ状態になり、非常時にその部分に応力
集中が生じ易くなる。そこで従来はそれに見合った強度
の鉄骨を使用する必要が生じ、PSC柱体全体の鉄骨使用
量が大きくなり不経済であるという問題があった。On the other hand, in the case of the conventional PSC column connection structure described above, only the steel frame is projected from the PSC column, and after connecting this, the space between the upper and lower columns is filled with post-cast concrete, The load ratio of post-cast concrete is small,
The load on the steel frame at the connecting part becomes larger than that at other parts, so that it becomes the same state as when there is a cross-section defect in the column after connection, and stress concentration tends to occur in that part in an emergency. . Therefore, conventionally, it was necessary to use a steel frame having a strength commensurate with that, and there was a problem that the amount of steel frame used in the entire PSC column was large and it was uneconomical.
更に、鉄骨の連結の後、後打コンクリートが所定の強度
を発現するまで待たなければ次の作業ができず、工期が
長くなり、柱体をプレキャスト化する利点が少ないとい
う問題があった。Further, there is a problem that after the connection of the steel frames, the next work cannot be performed unless the post-cast concrete shows a predetermined strength, the construction period becomes long, and the advantage of precasting the columnar body is small.
本発明はこのような従来の問題にかんがみPSC柱体の連
結部分において、鉄骨とコンクリートとの垂直荷重分担
割合が他のプレキャスト部分と大きな変化がなく、か
つ、工期が短縮できるPSC柱体の連結構造の提供を目的
としたものである。In view of such a conventional problem, the present invention, in the connection portion of the PSC column body, the vertical load sharing ratio between the steel frame and the concrete does not significantly change from other precast portions, and the connection of the PSC column body can shorten the construction period. The purpose is to provide the structure.
(課題を達成するための手段) 上述の如き従来の問題を解決し、所期の目的を達成する
本発明の特徴は、長手方向に向けて鉄骨が埋設され、端
面を互いに突き合わせ配置に接合する一対のプレキャス
ト鉄骨コンクリート柱体の各接合端面周縁にコンクリー
ト欠除部を設けるとともに、該柱体の端面に前記鉄骨と
一体化され、周縁部背面が前記コンクリート欠除部に露
出されたベースプレートを設け、該ベースプレートを互
いに重ね合わせて前記両プレキャスト鉄骨コンクリート
柱体を接合させ、その互いに重ね合わされた両ベースプ
レートをボルト締め、もしくは溶接等の固着手段によっ
て一体化させたことにある。(Means for Achieving the Problem) The feature of the present invention that solves the above-mentioned conventional problems and achieves the intended purpose is that a steel frame is embedded in the longitudinal direction, and end faces are joined to each other in a butted arrangement. A pair of precast steel-framed concrete columns are provided with concrete cutouts at the periphery of each joint end surface, and the end faces of the columns are provided with a base plate that is integrated with the steel frame and the peripheral edge back surface is exposed to the concrete cutouts. The base plates are overlapped with each other to join the precast steel-framed concrete columns, and the overlapped base plates are integrated with each other by fastening means such as bolting or welding.
(作用) 本発明のPSC柱体の連結構造によれば、PSC柱体の接合端
面はベースプレートに対し、プレキャストコンクリート
が直接接しているため、上側のPSC柱体が金骨及びコン
クリート全体で負担している垂直荷重はそのままベース
プレートを介して下側のPSC柱体の金骨及びコンクリー
ト全体に常に総合的に伝えられることとなり、極部的に
鉄骨に過大な垂直荷重を負担させることがなく、鉄骨及
びコンクリートの荷重分担割合が他のプレキャスト部分
と大差がない状態となる。(Operation) According to the connection structure of the PSC columnar body of the present invention, since the precast concrete is in direct contact with the base plate at the joint end surface of the PSC columnar body, the upper PSC columnar body bears the entire bone and concrete. The vertical load is always transmitted as it is through the base plate to the whole of the lower PSC pillar's gold frame and the entire concrete, without excessively loading the steel frame on the extreme vertical load. Also, the load sharing ratio of concrete does not differ much from other precast parts.
(実施例) 次に本発明の実施の一例を第1図〜第5図について説明
する。(Embodiment) An embodiment of the present invention will be described with reference to FIGS.
図において、11aは互いに連結しようとする下側のPSC柱
体であり、11bは同じく上側のPSC柱体である。両PSC柱
体11a,11bは、いずれも工場生産により断面が正方形状
をしたコンクリート部12a,12b内に断面が十字状をした
鉄骨13a,13b及びその周囲の位置に配置した高張力筋か
らなる主筋14a,14bが埋め込まれて成形されている。In the figure, 11a is a lower PSC column which is to be connected to each other, and 11b is an upper PSC column. Both PSC columns 11a, 11b are made of factory-made concrete sections 12a, 12b having square cross sections, and steel frames 13a, 13b having cross-shaped cross sections and high-strength muscles arranged around them. The main bars 14a and 14b are embedded and molded.
下側のPSC柱体11aの上端には、鉄骨13aが埋設された位
置の外側にコンクリート欠除部15aが上端周縁に沿って
方形環状に成形されている。At the upper end of the lower PSC column 11a, a concrete cutout portion 15a is formed in a rectangular ring shape along the upper end periphery outside the position where the steel frame 13a is embedded.
このコンクリート欠除部15aに一端を開口させて主筋連
結用のスリーブジョイント16が各主筋14aに対応させて
埋設され、その各スリーブジョイント16の下半分内に主
筋14aの上端が挿入されている。なお、図中17はスリー
ブジョイント用のグラウト注入口である。A sleeve joint 16 for connecting main reinforcements is embedded corresponding to each main reinforcement 14a with one end opened in the concrete cutout portion 15a, and the upper end of the main reinforcement 14a is inserted into the lower half of each sleeve joint 16. Reference numeral 17 in the figure is a grout inlet for a sleeve joint.
また、PSC柱体11aの上端面には鉄骨13aの端部に一体に
溶接したベースプレート18aがコンクリート欠除部14aを
除いた残りのコンクリート部12aの端面に密接した状態
で備えられており、このベースプレート18aはその周縁
部がフランジ状にコンクリート欠除部位置まで張り出さ
れる大きさに成形されたものを使用している。そして、
その周縁部に主筋貫通孔19が開口されている。In addition, a base plate 18a integrally welded to the end of the steel frame 13a is provided on the upper end surface of the PSC column 11a in close contact with the end surface of the remaining concrete portion 12a excluding the concrete cutout portion 14a. As the base plate 18a, the one whose peripheral edge is formed in a flange shape to the size of the concrete cutout portion is used. And
A main bar through hole 19 is opened in the peripheral portion.
一方上側のPSC柱体11bの下側には、前述した下側のPSC
柱体11aの上端と同様に鉄骨13bが埋設された位置の外側
にコンクリート欠除部15bが下端周縁に沿って方形環状
に成形されている。On the other hand, on the lower side of the upper PSC column 11b, the above-mentioned lower PSC
Similar to the upper end of the pillar 11a, a concrete cutout portion 15b is formed in a rectangular ring shape along the lower end periphery on the outer side of the position where the steel frame 13b is embedded.
PSC柱体11bの下端面には、鉄骨13bの端部に一体に溶接
したベースプレート18bがコンクリート欠除部15bを除い
た残りのコンクリート部12bの端面に密接した状態で備
えられている。このベースプレート18bは周縁がフラン
ジ状にコンクリート欠除部位置まで張り出されている。A base plate 18b integrally welded to the end of the steel frame 13b is provided on the lower end surface of the PSC column 11b in close contact with the end surface of the remaining concrete portion 12b excluding the concrete cutout portion 15b. The base plate 18b has a flange-like peripheral edge protruding to a concrete cutout position.
また、PSC柱体11b内の各主筋14bはコンクリート欠除部1
5bに突出され、ベースプレート18bの周縁部を貫通して
突出されている。Also, each main bar 14b in the PSC column 11b is
5b, and penetrates the peripheral edge of the base plate 18b.
上述の如き形状にあらかじめ工場にて成形した各PSC柱
体11a,11bを建築現場に搬入し、下側のPSC柱体11aを立
設した後、第1図に示すように上側のPSC柱体11bの下側
に突出している。主筋14bの先端を下側のベースプレー
ト18aに貫通させてスリーブジョイント16内に挿入し、
上下のベースプレート18a,18bを互いに重ね合わせ、ボ
ルトナット20により仮止めする。この状態で両ベースプ
レート18a,18bの周縁間を溶接21により固着するととも
に、各スリーブジョイント16内にグラウト22を注入して
主筋14a,14bを連結する。After each PSC pillar 11a, 11b molded in the factory in the shape as described above is carried into the construction site, the lower PSC pillar 11a is erected, and then the upper PSC pillar as shown in Fig. 1. It projects below 11b. Insert the tip of the main bar 14b into the sleeve joint 16 by penetrating the lower base plate 18a,
The upper and lower base plates 18a, 18b are superposed on each other and temporarily fixed by a bolt nut 20. In this state, the peripheral edges of both base plates 18a, 18b are fixed by welding 21 and the grout 22 is injected into each sleeve joint 16 to connect the main bars 14a, 14b.
このようにして鉄骨13a,13b間及び主筋14a,14b間を互い
に連結した後、互いに連結した配置となっている両コン
クリート欠除部15a,15b内を後打コンクリート23にて埋
めて両PSC柱体11a,11bの連結を完了する。After connecting the steel frames 13a, 13b and the main bars 14a, 14b to each other in this manner, both concrete notch parts 15a, 15b arranged to be connected to each other are filled with post-casting concrete 23 to both PSC columns. The connection between the bodies 11a and 11b is completed.
(発明の効果) 上述したように本発明のPSC柱体の連結構造において
は、両PSC柱体の端面のベースプレートにそれぞれのプ
レキャストコンクリート部が密接され、かつ、そのベー
スプレートが鉄骨と一体化されているため、上側のPSC
柱体の垂直荷重が後打コンクリートの打設前においても
両PSC柱体のコンクリート部及び鉄骨に共に所定の割合
で分担されて下側PSC柱体に伝わることとなり、連結部
分において特別に鉄骨の荷重負担割合が大きくならず、
連結部分においても他の部分と同様の強度が経済的に得
られる。(Effect of the invention) As described above, in the connection structure of the PSC columnar body of the present invention, the respective precast concrete parts are in close contact with the base plates on the end faces of both PSC columnar bodies, and the base plate is integrated with the steel frame. Therefore, the upper PSC
Even before the post-casting concrete is placed, the vertical load of the pillars will be shared by the concrete parts of both PSC pillars and the steel frame at a predetermined ratio and will be transmitted to the lower PSC pillars. The load bearing ratio does not increase,
Even at the connecting portion, the same strength as other portions can be economically obtained.
また、本発明においては、ベースプレート間の一体化に
よって、垂直荷重に対する強度が得られるものであるた
め、後打コンクリートの強度発現を待つ必要がなくな
り、工期が短縮できる。In addition, in the present invention, since strength against vertical load is obtained by integrating the base plates, it is not necessary to wait for the strength of the post-cast concrete to develop, and the construction period can be shortened.
第1図は本発明の連結構造を示す断面図、第2図は下側
のPSC柱体の端部の側面図、第3図は第2図中のA−A
線断面図、第4図は上側のPSC柱体の端部の側面図、第
5図は第4図中のB−B線断面図、第6図は従来のプレ
キャスト柱体による組立例の側面図、第7図は従来のプ
レキャスト柱体の連結構造を示す断面図、第8図は第7
図中のC−C線断面図である。 11a,11b……PSC柱体、12a,12b……コンクリート部、13
a,13b……鉄骨、14a,14b……主筋、15a,15b……コンク
リート欠除部、16……スリーブジョイント、17……グラ
ウト注入口、18a,18b……ベースプレート、19……主筋
貫通孔、20……ボルトナット、21……溶接、22……グラ
ウト、23……後打コンクリート。FIG. 1 is a sectional view showing a connecting structure of the present invention, FIG. 2 is a side view of an end portion of a lower PSC column, and FIG. 3 is AA in FIG.
A line sectional view, FIG. 4 is a side view of an end portion of the upper PSC column, FIG. 5 is a sectional view taken along line BB in FIG. 4, and FIG. 6 is a side view of an example of assembly by a conventional precast column. Fig. 7 is a sectional view showing a conventional precast column connecting structure, and Fig. 8 is a sectional view.
It is the CC sectional view taken on the line in the figure. 11a, 11b …… PSC column, 12a, 12b …… Concrete part, 13
a, 13b …… Steel, 14a, 14b …… Main bar, 15a, 15b …… Concrete notch, 16 …… Sleeve joint, 17 …… Grout injection port, 18a, 18b …… Base plate, 19 …… Main bar through hole , 20 …… Bolt nut, 21 …… Welding, 22 …… Grout, 23 …… Post-cast concrete.
Claims (1)
互いに突き合わせ配置に接合する一対のプレキャスト鉄
骨コンクリート柱体の各接合端面周縁にコンクリート欠
除部を設けるとともに、該柱体の端面に前記鉄骨と一体
化され、周縁部背面が前記コンクリート欠除部に露出さ
れたベースプレートを設け、該ベースプレートを互いに
重ね合わせて前記両プレキャスト鉄骨コンクリート柱体
を接合させ、その互いに重ね合わされた両ベースプレー
トをボルト締め、もしくは溶接等の固着手段によって一
体化させてなるプレキャストコンクリート柱体の連結構
造。1. A concrete notch is provided at each joint end face peripheral edge of a pair of precast steel-concrete concrete columns in which a steel frame is embedded in the longitudinal direction and whose end faces are joined to each other in a butted arrangement, and at the end faces of the column bodies. A base plate integrated with the steel frame and having a peripheral back surface exposed to the concrete cutout portion is provided, the base plates are overlapped with each other to join the precast steel concrete columns, and the base plates overlapped with each other are provided. Connection structure of precast concrete columns that are integrated by fastening means such as bolting or welding.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15773589A JPH0715183B2 (en) | 1989-06-20 | 1989-06-20 | Connection structure of precast steel concrete columns |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP15773589A JPH0715183B2 (en) | 1989-06-20 | 1989-06-20 | Connection structure of precast steel concrete columns |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0325130A JPH0325130A (en) | 1991-02-01 |
| JPH0715183B2 true JPH0715183B2 (en) | 1995-02-22 |
Family
ID=15656213
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP15773589A Expired - Fee Related JPH0715183B2 (en) | 1989-06-20 | 1989-06-20 | Connection structure of precast steel concrete columns |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0715183B2 (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20170123371A (en) * | 2016-04-28 | 2017-11-08 | 경희대학교 산학협력단 | the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure between precast concrete column and precast concrete beam |
| KR20180122152A (en) * | 2017-05-02 | 2018-11-12 | 경희대학교 산학협력단 | the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure of the precast concrete girder using the same |
| CN111851735A (en) * | 2020-07-13 | 2020-10-30 | 广东石油化工学院 | Vertical prefabricated structural member, its prefabrication method and on-site assembly construction method |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101995496B1 (en) * | 2017-05-02 | 2019-10-01 | 경희대학교 산학협력단 | the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure of the precast concrete girder using the same |
-
1989
- 1989-06-20 JP JP15773589A patent/JPH0715183B2/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20170123371A (en) * | 2016-04-28 | 2017-11-08 | 경희대학교 산학협력단 | the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure between precast concrete column and precast concrete beam |
| KR20180122152A (en) * | 2017-05-02 | 2018-11-12 | 경희대학교 산학협력단 | the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure of the precast concrete girder using the same |
| CN111851735A (en) * | 2020-07-13 | 2020-10-30 | 广东石油化工学院 | Vertical prefabricated structural member, its prefabrication method and on-site assembly construction method |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0325130A (en) | 1991-02-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH09209451A (en) | Joint construction of up and down columns with beam and joint method | |
| JPH0715183B2 (en) | Connection structure of precast steel concrete columns | |
| JPH08144425A (en) | Prefabricated member of mixed structure and construction method of mixed structure | |
| JPH0790933A (en) | Construction method of structure | |
| JPH0657971B2 (en) | Building frame | |
| JPS62178634A (en) | Frame construction method for structures | |
| JPH02272125A (en) | How to join steel reinforced precast concrete columns and steel beams | |
| JPH0749681B2 (en) | Steel frame / reinforced concrete composite construction method | |
| JP2759361B2 (en) | Pillar support members for building reinforced concrete buildings | |
| JPH0366878A (en) | Construction method of precast columns and beams and precast shear walls | |
| JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
| JP2635872B2 (en) | How to build a composite structure | |
| JPH06220869A (en) | Drop-in type steel frame bridge pier and process of construction thereof | |
| JPH0749680B2 (en) | Construction method of precast steel reinforced concrete structure | |
| JPH0765368B2 (en) | Precast concrete half flat slab | |
| JPH0453223B2 (en) | ||
| JPH0830360B2 (en) | Connection method for columns and beams | |
| JPS5830459B2 (en) | Construction method of precast reinforced concrete structure | |
| JPH0410935B2 (en) | ||
| JPH06995B2 (en) | Method for joining columns and PC beams | |
| JPS58204246A (en) | Construction of reinforced concrete structure | |
| JPH0739695B2 (en) | Connection structure of precast steel concrete columns | |
| JPH02132236A (en) | Column and beam joint section unit | |
| JPS6141857Y2 (en) | ||
| JPS62280435A (en) | Construction method of body |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090222 Year of fee payment: 14 |
|
| LAPS | Cancellation because of no payment of annual fees |