JPH0718656B2 - Molten metal container pouring construction method - Google Patents
Molten metal container pouring construction methodInfo
- Publication number
- JPH0718656B2 JPH0718656B2 JP61096271A JP9627186A JPH0718656B2 JP H0718656 B2 JPH0718656 B2 JP H0718656B2 JP 61096271 A JP61096271 A JP 61096271A JP 9627186 A JP9627186 A JP 9627186A JP H0718656 B2 JPH0718656 B2 JP H0718656B2
- Authority
- JP
- Japan
- Prior art keywords
- molten metal
- metal container
- pouring
- casting
- bucket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Blast Furnaces (AREA)
- Furnace Housings, Linings, Walls, And Ceilings (AREA)
Description
【発明の詳細な説明】 産業上の利用分野 本発明は、高炉の鋳床樋等の溶融金属容器流し込み施工
方法に関する。TECHNICAL FIELD The present invention relates to a method for pouring a molten metal container such as a casting floor gutter of a blast furnace.
従来の技術 近年、高炉の鋳床樋等の補修は、従来の耐火レンガ等の
内張り施工にかわって、不定形耐火物の流し込み施工に
なってきている。そのため、鋳床樋の側部にミキサー、
混練装置等を設置し、所要の不定形耐火材料を混練調製
し、鋳床樋に流し込み作業が多くなってきている。2. Description of the Related Art In recent years, the repair of cast floor gutters and the like of blast furnaces has been replaced with conventional lining construction of refractory bricks and the like, and casting of irregular-shaped refractory materials has been performed. Therefore, a mixer on the side of the cast floor gutter,
There is an increasing number of operations in which a kneading device or the like is installed to knead and prepare the required irregular-shaped refractory material and pour it into a casting floor gutter.
発明が解決しようとする問題 しかし、小型や中型の高炉等にあっては、炉前の鋳床部
が狭く、ミキサーや混練装置の搬入や搬出が容易でな
く、またこれらの装置の容量や台数にも限度があって、
流し込み材料を短時間に多量連続状に鋳床樋に流し込む
ことができず、ほぼ0.25〜0.5m3毎混練調製して逐次流
し込まねばならず、長時間かかっているものであった。
そのため、高炉等の溶融金属を取扱う鋳床樋等では、高
熱による流し込み材料の硬化が早くて材料の流動性がよ
くなく、打ち継ぎ層や亀裂、空洞等が発生して気孔の多
い施工体となり、洩銑事故や樋寿命の低下の原因となっ
ているものであった。さらには、混練作業による粉塵や
流し込み材料による水蒸気、粉煙等が発生して、作業環
境がよくなく、長時間にわたる高熱作業の負荷は作業者
にとって厳しいものであった。Problems to be Solved by the Invention However, in a small-sized or medium-sized blast furnace, etc., the casting floor in front of the furnace is narrow, and it is not easy to carry in and carry out mixers and kneading devices, and the capacity and number of these devices are large. There is also a limit,
It was not possible to pour the pouring material into the casting floor gutter in a short amount in a short time, and it was necessary to knead and prepare every 0.25 to 0.5 m 3 and pour it sequentially, which took a long time.
Therefore, in cast floor gutters that handle molten metal in blast furnaces, etc., the casting material is hardened by high heat quickly and the fluidity of the material is poor, resulting in a construction body with many porosity due to splicing layers, cracks, cavities, etc. This was the cause of the leaked iron accident and the shortened gutter life. Furthermore, dust and dust caused by the kneading work, steam and dust produced by the poured material are generated, the working environment is not good, and the load of high-temperature work for a long time is severe for the worker.
問題点を解決するための手段 本発明は上記のような点に鑑みたもので、高炉の鋳床樋
等の溶融金属容器の補修現場とは別の場所で不定形耐火
性の流し込み材料を混練調製し、この混練調製した流し
込み材料を数トン位の大容量のバケットに装填して上記
溶融金属容器の補修現場へ搬送し、補修準備した溶融金
属容器に上記大容量のバケットに装填した流し込み材料
を熱硬化が生じないようにほぼ連続状態で流し込んで装
填して、流し込み材料をほぼ連続状態で短時間に多量流
し込め、流し込み材料の熱硬化を遅らせることができて
打ち継ぎ層や空洞等の発生を防止でき、施工体の洩銑事
故の防止がはがれるとともに樋寿命を延長でき、さらに
長時間にわたる高熱作業の負荷を軽減できて作業環境の
改善等がはかれる溶融金属容器流し込み施工方法を提供
するにある。Means for Solving the Problems The present invention has been made in view of the above points, and kneads a cast material having an indeterminate fire resistance at a place different from a repair site of a molten metal container such as a casting floor gutter of a blast furnace. Prepared and kneaded The prepared pouring material is loaded into a large capacity bucket of several tons and transported to the repair site of the molten metal container, and the pouring material loaded into the large capacity bucket in the molten metal container prepared for repair Is poured in a substantially continuous state so that heat curing does not occur, and a large amount of the poured material can be poured in a short time in a substantially continuous state, so that the heat setting of the poured material can be delayed, such as a splicing layer or a cavity. It is possible to prevent the occurrence of leaks, to prevent leaking accidents of the construction body, to extend the life of the gutter, and to reduce the load of high heat work for a long time and improve the work environment, etc. There is a way to provide.
実施例 以下、本発明を実施例にもとずいて説明する。Examples Hereinafter, the present invention will be described based on Examples.
第1図、第2図は本発明の一実施例で、高炉鋳床樋に実
施したものである。鋳床1は、第1図のように高炉2の
下方部に設けられて、第2図のようにレンガのような耐
火物で囲んだ永久張りである外張耐火壁3の内側にアル
ミナー炭化珪素−炭素系の不定形耐火性材料等を混練調
製した流し込み材料4を装填して内張耐火壁5を内設し
た溶融金属容器である鋳床樋6を形成し、高炉2から出
銑される溶銑を貯積し、適宜にトピードカー7に流出自
在としている。この溶融金属容器である鋳床樋6の上部
には、第1図のようにジブクレーン8、天井走行クレー
ン9を配設していて、外部からトラックのような搬送装
置10で搬送される2〜5トン位の流し込み材料4を装填
した大容量のバケット11を吊設搬送自在として、第2図
のように鋳床樋6に流し込み材料4を順次ほぼ連続的に
流し込むようにしている。上記流し込み材料4は、第1
図のように鋳床1とは別場所の鋳床1からやや離れた混
練工場12で混練調製している。その混練工場12には、図
のように1〜2m3といった従来の数倍の大容量のミキサ
ー13を複数台設置し、上記した不定形耐火性の粉末材料
を大容量のミキサー13で短時間で混練調製し、天井クレ
ーン等の搬送機14を介して上記バケット11に順次装填し
て搬送装置10を介して補修工程に合わせて鋳床1部へ搬
送し、鋳床樋6に流し込んで補修できるようにしていも
のである。また、上記した大容量のバケット11は、第2
図のように外周部に脚部15を設けて鋳床1の中枠固定部
16に架設した中枠浮上り防止用押え架台17等に設置自在
としているとともに、上部に吊り下げ部18を設けて吊設
自在とし、さらに内部には搬送中に流し込み材料4が偏
析したり、沈降したりして分離するのを防止するためめ
の網板のような偏析分離防止板19を中央部や側部の適宜
の位置に内装しているものである。20は、バケット排出
弁で、21は排出口、22は樋中枠である。1 and 2 show an embodiment of the present invention, which is carried out on a blast furnace cast floor gutter. The casting bed 1 is provided in the lower part of the blast furnace 2 as shown in FIG. 1 and is provided with alumina-carbide inside an externally-coated fire-resistant wall 3 which is a permanent covering surrounded by refractory material such as bricks as shown in FIG. A casting bed gutter 6 which is a molten metal container having a lined refractory wall 5 therein is formed by charging a casting material 4 prepared by kneading a silicon-carbon type amorphous refractory material or the like, and tapped from the blast furnace 2. The molten pig iron is stored and can be freely discharged into the tope car 7. As shown in FIG. 1, a jib crane 8 and an overhead traveling crane 9 are arranged on the upper part of the casting floor gutter 6 which is the molten metal container, and the jib crane 8 and the overhead traveling crane 9 are transferred from the outside by a transfer device 10 such as a truck. A large-capacity bucket 11 loaded with about 5 tons of the pouring material 4 can be hung and conveyed, and the pouring material 4 is sequentially and almost continuously poured into the casting floor gutter 6 as shown in FIG. The casting material 4 is the first
As shown in the figure, kneading and preparation is performed in a kneading factory 12 which is located a little away from the casting bed 1 and is located away from the casting bed 1. In the kneading factory 12, as shown in the figure, a plurality of large-capacity mixers 13 with a capacity several times larger than the conventional one, such as 1 to 2 m 3, are installed. Kneaded and prepared by the above, and sequentially loaded into the bucket 11 through the transfer device 14 such as an overhead crane, transferred to the casting floor part 1 through the transfer device 10 according to the repair process, and poured into the casting floor gutter 6 for repair. It is something that can be done. In addition, the large capacity bucket 11 described above has a second
As shown in the figure, the legs 15 are provided on the outer periphery to fix the middle frame of the casting floor 1
It can be installed freely on the holding frame 17 for preventing the floating of the middle frame installed on 16 and can be hung by providing the hanging part 18 on the upper part. Furthermore, the pouring material 4 is segregated during the transportation, A segregation / separation prevention plate 19 such as a net plate for preventing sedimentation or separation is installed at an appropriate position in the central portion or side portions. 20 is a bucket discharge valve, 21 is a discharge port, and 22 is a gutter frame.
作 用 しかして、高炉2の鋳床樋6の内張耐火壁5を補修する
にあっては、工程表にしたがって損耗した内張耐火壁5
を解体して解体屑を排出し、第2図のように鋳床樋6の
上部の中枠固定部16に架設した中枠浮上り防止用押え架
台17に樋中枠22を配設して流し込みの準備をする。一
方、上記準備作業と併行して、第1図のように施工現場
と別の混練工場12で所定の耐火性材料を大型のミキサー
13でそれぞれ混練して所定量の流し込み材料4を調製
し、所要の複数の大容量のバケット11にそれぞれ装填し
て、トラックの搬送装置10で作業計画に合わせて鋳床1
部へ搬入するものである。Operation When repairing the lining fireproof wall 5 of the cast floor gutter 6 of the blast furnace 2, however, the lining fireproof wall 5 that is worn according to the process table is repaired.
2 to dismantle the demolition waste, and install the gutter middle frame 22 on the middle frame floating prevention presser stand 17 installed on the middle frame fixing part 16 on the upper part of the casting floor gutter 6 as shown in FIG. Prepare for pouring. On the other hand, in parallel with the above-mentioned preparatory work, as shown in Fig. 1, a predetermined mixer is used to mix a predetermined refractory material into a large-scale mixer at a kneading factory 12 separate from the construction site.
A predetermined amount of the pouring material 4 is prepared by kneading at 13 and loaded into a plurality of required large-capacity buckets 11, respectively, and the casting bed 1 is prepared by the transport device 10 of the truck according to the work plan.
It is to be carried into the department.
このようにして、従来のように高熱の鋳床部で内張耐火
壁の解体や中枠設置等の作業を行う一方、流し込み材料
を別場所で併行して混練調製するため、従来のような鋳
床部で粉塵が発生するのを防止でき、施工現場の作業環
境をよくできるとともに、混練工場では特にスペースに
制限が少なくて所要のスペースを確保できるため、大型
のミキサーを複数台設置できて、短時間に所要の多量の
流し込み材料の混練調製が行えるものである。そして、
大容量のバケットに装填して、鋳床樋の準備作業の工程
に合わせて流し込み準備体勢を整えられて、施工工事の
短縮化がはかれるものである。In this way, while performing the work such as dismantling the lining refractory wall and installing the middle frame in the high-heat casting floor part as in the conventional case, the pouring material is mixed and prepared in parallel at another place, It is possible to prevent dust from being generated in the casting floor, improve the working environment at the construction site, and ensure that the kneading plant has a limited space and the required space, so it is possible to install multiple large mixers. It is possible to knead and prepare a required large amount of casting material in a short time. And
It can be loaded into a large capacity bucket, and the pouring preparation posture can be adjusted according to the process of the preparation work of the cast floor gutter to shorten the construction work.
なお、バケットには偏析分離防止板を配設しているた
め、流し込み材料を装填して搬送しても、材料が偏析し
たり、沈降したりして分離するのが防止でき、施工現場
での混練調製と同様の品質を保持できるものである。Since the bucket is equipped with a segregation separation prevention plate, even if the pouring material is loaded and conveyed, it is possible to prevent the material from separating due to segregation or sedimentation. It is possible to maintain the same quality as the kneading preparation.
そして、第2図のように流し込みの準備が終わった鋳床
樋6の流し込み部に天井クレーン9やジブクレーン8を
介して搬入待機したバケット11を搬送して設置し、バケ
ット搬出弁20を開いて排出口21を開口すれば、流し込み
材料4は図のように樋中枠22でかこまれた外張耐火壁3
の内側に流入し、内張耐火壁5を形成していくものであ
る。1のバケット11の流し込み材料4の流入が終了すれ
ば、同様にして搬入待機したバケット11を順次搬送して
所要量装填し、所定の温度下で乾燥養生して補修するも
のである。Then, as shown in FIG. 2, the bucket 11 waiting for loading via the overhead crane 9 or the jib crane 8 is transported to and installed in the pouring portion of the casting floor gutter 6 which has been prepared for pouring, and the bucket unloading valve 20 is opened. When the discharge port 21 is opened, the pouring material 4 is covered with the gutter frame 22 as shown in the figure.
It flows into the inside of the and forms the lining fireproof wall 5. When the inflow of the pouring material 4 into the first bucket 11 is completed, similarly, the buckets 11 waiting to be carried in are sequentially transported and loaded with a required amount, and dried and cured at a predetermined temperature for repair.
このように、2〜5トンといった大容量のバケットを使
用した流し込み材料を流入するため、数回のバケットに
よる流し込みで、短時間に多量の材料を流入して装填で
きるとともにほぼ連続状態で流入できて、流し込み材料
が熱硬化するのを遅らせ、流し込み材料を流動性よく均
一状に内部に装填できるものである。したがって、流入
した流し込み材料との間に打ち継ぎ層が生じたり、亀裂
や空洞等が発生するのを防止でき、気孔の少ない充填密
度の高い施工体を形成できるものである。In this way, since the pouring material using a large capacity bucket of 2 to 5 tons is flowed in, a large number of materials can be flowed in and loaded in a short time by pouring several times in a bucket, and the material can be flowed in almost continuously. Thus, it is possible to delay the thermosetting of the pouring material and to load the pouring material into the inside uniformly with good fluidity. Therefore, it is possible to prevent a splice layer from being formed between the inflowing material and cracks, cavities and the like, and to form a construction body with few pores and a high packing density.
上記した施工方法の一例について、従来の施工のものと
比較してみると、次表の通りである。An example of the above construction method is shown in the following table when compared with the conventional construction method.
第1表は、本発明による施工と従来の施工についての施
工状況に関するものであり、第2表は、同上の110℃、2
4時間乾燥後の施工体の比重と気孔率に関するものであ
る。Table 1 relates to the construction status of the construction according to the present invention and the conventional construction, and Table 2 shows the same at 110 ° C., 2
It is related to the specific gravity and porosity of the construction body after drying for 4 hours.
本発明にあっては、第1表に示すように流し込み材料の
流し込み時間が実に従来の3分の1に短縮でき、中枠セ
ットから流し込み完了までも従来のほぼ2分の1に短縮
でき、鋳床樋の耐久性も25%も大 幅に延長できたものである。According to the present invention, as shown in Table 1, the pouring time of the pouring material can be shortened to one-third of that of the conventional one, and even the completion of pouring from the middle frame set can be shortened to about one-half of the conventional one. The casting floor gutter is as durable as 25%. It was possible to extend the width.
また、第2表のように施工体の気孔率も、5〜6%低減
でき、充填密度の向上がはかれたものである。Moreover, as shown in Table 2, the porosity of the construction body can be reduced by 5 to 6%, and the packing density is improved.
上記実施例では、施工現場から離れて混練工場を設けた
が、隔壁等の粉塵防止壁を設け隣接して適宜のスペース
の場所に設置するようにしてもよく、また搬送装置とし
てはトラックに限らずに台車等で連結するようにするこ
ともでき、さらには本発明の流し込み対象としては、高
炉鋳床樋に限ることなく、連続鋳造設備のタンディシュ
や取鍋等についても同様に適用できるものである。In the above embodiment, the kneading factory is provided apart from the construction site, but it may be installed in a place of an appropriate space by providing a dust prevention wall such as a partition wall, and the transport device is not limited to a truck. It is also possible to connect without a trolley, etc., further, as the casting object of the present invention is not limited to the blast furnace cast floor trough, it can be similarly applied to tundish or ladle of continuous casting equipment. is there.
発明の効果 以上のように本発明にあっては、高炉の鋳床樋等の溶融
金属容器に流し込み材料を熱硬化が生じないようにほぼ
連続状態で短時間に多量流し込めて、流し込み時間の短
縮化がはかれるとともに、熱硬化を遅らせることができ
て材料の流動性を改善でき、打ち継ぎ層や亀裂、空洞等
が発生するのを防止でき、施工体の比重を高められて洩
銑事故の防止や樋寿命の延長化がはかれるものである。
また、施工工現場以外で流し込み材料を混練調製できる
ため、ミキサーの容量や台数を高められ、流し込み施工
現場での粉塵の発生の防止がはかれて施工現場の作業環
境の改善がはかれるとともに、施工現場の準備作業に併
行して材料の混練調製を迅速に行え、また高熱発生の場
所での作業時間の短縮化がはかれて作業者の高熱作業の
負荷の軽減ができるととも高炉等の設備の生産性の向上
がはかれるなど優れた効果を奏するものである。Effects of the Invention As described above, in the present invention, a large amount of material is poured into a molten metal container such as a casting floor gutter of a blast furnace in a short time in a substantially continuous state so that heat curing does not occur, and the casting time In addition to being shortened, heat hardening can be delayed to improve the fluidity of the material, it is possible to prevent the formation of splice layers, cracks, cavities, etc., and it is possible to increase the specific gravity of the construction work and to prevent leak accidents. It is intended to prevent and extend the gutter life.
In addition, since the pouring material can be kneaded and prepared at a place other than the construction site, the capacity and number of mixers can be increased, the generation of dust at the pouring construction site can be prevented, and the working environment at the construction site can be improved. Kneading and preparation of materials can be performed quickly in parallel with on-site preparation work, and the work time in places where high heat is generated can be shortened, and the load of workers on high heat work can be reduced and equipment such as blast furnaces can be reduced. It has excellent effects such as improvement in productivity.
第1図は本発明の一実施例の概略説明用図、第2図は同
上の流し込み状態の側断面図である。 1……鋳床、2……高炉、4……流し込み材料、10……
搬送装置、11……バケット、19……偏析分離防止板。FIG. 1 is a schematic explanatory view of an embodiment of the present invention, and FIG. 2 is a side sectional view of the same as above in a pouring state. 1 …… Cast floor, 2 …… Blast furnace, 4 …… Casting material, 10 ……
Conveyor, 11 …… Bucket, 19 …… Segregation separation prevention plate.
Claims (2)
とは別の場所で不定形耐火性の流し込み材料を混練調製
し、この混練調製した流し込み材料を数トン位の大容量
のバケットに装填して上記溶融金属容器の補修現場へ搬
送し、補修準備した溶融金属容器に上記大容量のバケッ
トに装填した流し込み材料を熱硬化が生じないようにほ
ぼ連続状態で流し込んで装填することを特徴とする溶融
金属容器流し込み施工方法。1. A non-standard refractory casting material is kneaded and prepared in a place different from a site for repairing a molten metal container such as a cast floor gutter of a blast furnace, and the kneaded and prepared casting material is stored in a large capacity of several tons. To be loaded into a bucket and transported to the repair site of the molten metal container, and to be poured into the molten metal container prepared for repair in a substantially continuous state so that the casting material loaded in the above-mentioned large capacity bucket will not be thermoset. A method for pouring a molten metal container characterized by the above.
中に偏析したり、沈降したりして分離するのを防止する
ために網板等の材料分離防止板を備えたものである特許
請求の範囲第1項記載の溶融金属容器流し込み施工方
法。2. A large-capacity bucket is provided with a material separation prevention plate such as a mesh plate for preventing segregation or sedimentation of the pouring material during transportation thereof. The method for pouring a molten metal container according to item 1 above.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP61096271A JPH0718656B2 (en) | 1986-04-25 | 1986-04-25 | Molten metal container pouring construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP61096271A JPH0718656B2 (en) | 1986-04-25 | 1986-04-25 | Molten metal container pouring construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS62252885A JPS62252885A (en) | 1987-11-04 |
| JPH0718656B2 true JPH0718656B2 (en) | 1995-03-06 |
Family
ID=14160483
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP61096271A Expired - Lifetime JPH0718656B2 (en) | 1986-04-25 | 1986-04-25 | Molten metal container pouring construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0718656B2 (en) |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5573460A (en) * | 1978-11-27 | 1980-06-03 | Nippon Kokan Kk <Nkk> | Applying method of ladle lining |
| JPS6013103B2 (en) * | 1980-09-30 | 1985-04-05 | 松下電工株式会社 | Connection structure of external wall material for horizontal cladding |
| JPS60161095U (en) * | 1984-04-04 | 1985-10-25 | 播磨耐火煉瓦株式会社 | Storage tank that prevents particle size segregation |
| JPS60171892U (en) * | 1984-04-24 | 1985-11-14 | 播磨耐火煉瓦株式会社 | Hopper that prevents particle size segregation |
-
1986
- 1986-04-25 JP JP61096271A patent/JPH0718656B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS62252885A (en) | 1987-11-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4351058A (en) | Induction crucible furnace and method for its preparation | |
| JPH0592254A (en) | Method for manufacturing and repairing molten metal container | |
| CN104673966A (en) | Method for rapidly maintaining converter lining | |
| CN103008632B (en) | Split combined type tundish cover and manufacturing method thereof | |
| CN105177202A (en) | Iron-making blast furnace overhaul method | |
| JPH0718656B2 (en) | Molten metal container pouring construction method | |
| US5511762A (en) | Consumable form with degradable lining | |
| US3439909A (en) | Apparatus for preheating scrap metal | |
| US3259672A (en) | Method of forming and maintaining refractory bottoms of open hearth furnaces for the manufacture of steel | |
| CN215250992U (en) | A device for adding back furnace iron for a closed electric furnace | |
| JPH0631435A (en) | Ladle | |
| JP3670061B2 (en) | Ginger and its forming method | |
| CN112393605A (en) | Thermal state quick repairing method for cement burning system decomposing furnace | |
| MXPA02000015A (en) | Casting method and apparatus. | |
| CN222931824U (en) | Novel hot metal bottle masonry structure | |
| CN223005298U (en) | A construction system of unshaped refractory materials for rotary kiln | |
| CN222569277U (en) | Blast furnace hot-metal bottle | |
| CN224012633U (en) | Tank lining knotting system | |
| Koryt’ko et al. | Monolithic lining for steel-pouring ladles | |
| JPS60121208A (en) | Relining method of blast furnace | |
| JPH09174230A (en) | Lining construction method for ladle floor | |
| CN110449568A (en) | A kind of compound packet bottom construction technology of ladle | |
| CN210305735U (en) | Continuous casting tundish overflow tank for easy slag removal | |
| JP2005015847A (en) | Blast furnace lower work place | |
| JPH02166207A (en) | Vessel for molten metal of iron tapping trough and the like |