JPH0730680B2 - Buried construction method - Google Patents
Buried construction methodInfo
- Publication number
- JPH0730680B2 JPH0730680B2 JP11448087A JP11448087A JPH0730680B2 JP H0730680 B2 JPH0730680 B2 JP H0730680B2 JP 11448087 A JP11448087 A JP 11448087A JP 11448087 A JP11448087 A JP 11448087A JP H0730680 B2 JPH0730680 B2 JP H0730680B2
- Authority
- JP
- Japan
- Prior art keywords
- sand
- earth
- cavity
- bubbles
- filler
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Air Transport Of Granular Materials (AREA)
Description
【発明の詳細な説明】 《産業上の利用分野》 この発明は埋土工法に関し、特に狭い場所での土砂の埋
戻し、あるいは廃坑などの空洞、空隙に充填材を充填す
る際の施工方法に関する。Description: TECHNICAL FIELD The present invention relates to a burial method, and particularly to a construction method for backfilling earth and sand in a narrow space, or for filling a cavity or void in an abandoned mine with a filler. .
《従来の技術》 地中構造物の構築後に施工される埋戻しでは、通常掘削
土砂や砂質系の土砂が使用され、これらの土砂を30cm程
度の層状に埋め込んで、各層ごとにランマー等の締固め
機械で締固めている。《Prior art》 In backfilling after construction of underground structures, excavated sand and sandy sand are usually used.Embed these sands in a layer of about 30 cm, and use a rammer etc. for each layer. It is compacted by a compaction machine.
一方、埋戻しを狭い場所で行なう場合には、大型の締固
め機械の搬入設置ができないので、単純に土砂で埋戻し
た後に注水して水締めを行なったり、或る位は小型の棒
状振動機を利用して締固めることも行なわれている。On the other hand, when backfilling is performed in a narrow space, a large compaction machine cannot be loaded and installed.Therefore, simply backfill with earth and sand and then pour water to tighten the water. Compaction is also performed using a machine.
また、廃坑などのように不要になった空洞、空隙を充填
する際の充填方法としては、エアーモルタル工法が一般
的に採用されており、この工法ではセメントミルクに発
砲剤を混入したエアーモルタルを空洞などに注入する。In addition, the air mortar method is generally used as a filling method when filling unnecessary cavities and voids such as in abandoned mines.In this method, cement mortar mixed with a foaming agent is used. Inject into a cavity.
しかしながら、このような従来の埋戻しないしは充填方
法にはいずれも以下に説明する問題があった。However, such conventional backfilling or filling methods have the following problems.
《発明が解決しようとする問題点》 すなわち、前述した土砂の水締めおよび振動機による方
法では、狭隘な場所での土砂の搬入および投入に手間が
かかるとともに、水締めでは埋戻し土砂に水が滲み込む
のに時間がかかり且つ、多量の水を必要とする。<< Problems to be Solved by the Invention >> That is, in the above-described method of water filling of sand and a method using a vibrator, it takes time to bring in and put in earth and sand in a narrow place, and when water is tightened, water is added to backfilled earth and sand. It takes time to soak and requires a large amount of water.
また、振動機による方法では、棒状のパイブレータを使
用するので施工能率が悪かった。Further, in the method using the vibrator, since the rod-shaped vibrator is used, the construction efficiency is poor.
さらに、エアーモルタル工法では、セメントミルクを用
いるため材料費が高価になること、および充填されたエ
アーモルタルが硬化する時に、反応熱が生じ、空洞、空
隙の周辺部に悪影響を及ぼす惧れもあった。Furthermore, in the air mortar method, the material cost is high because cement milk is used, and when the filled air mortar hardens, reaction heat is generated, which may adversely affect the cavities and the periphery of the voids. It was
この発明は以上の如き問題点に鑑みてなされてものであ
って、その目的とするところは、搬入および投入が容易
にできるとともに安価でしかも周辺に悪影響を及ぼすこ
とのない埋土工法を提供することにある。The present invention has been made in view of the above problems, and an object thereof is to provide an embedding method that is easy to carry in and put in, is inexpensive, and does not adversely affect the surroundings. Especially.
《問題点を解決するための手段》 上記目的を達成するために、この発明は、地下構造物の
構築後に施工される埋戻しに用いられる埋土材あるいは
廃坑などの空洞、空隙に充填される充填材として土砂に
実質的に気泡のみを混入したものを用いることを特徴と
する。<< Means for Solving Problems >> In order to achieve the above-mentioned object, the present invention is to fill a cavity or void such as a filling material or an abandoned mine used for backfilling after construction of an underground structure. It is characterized in that earth and sand mixed with substantially only air bubbles are used as the filler.
《作用》 上記構成の埋土工法によれば、埋土材あるいは充填材に
実質的に気泡のみを混入してあるので、これらの流動性
が増し、搬入は例えばポンプ圧送が可能となる。<< Operation >> According to the burial method of the above structure, since only the bubbles are substantially mixed in the burial material or the filler, the fluidity of the burial material and the filling material is increased, and the pumping can be carried out, for example.
また、混入された気泡は土粒子間の間隙を埋めるように
して介在するので締固めは不要になる。Further, since the mixed bubbles intervene so as to fill the gaps between the soil particles, compaction is unnecessary.
《実施例》 以下、この発明の好適な実施例について添付図面を参照
にして詳細に説明する。<Example> Hereinafter, a preferred example of the present invention will be described in detail with reference to the accompanying drawings.
第1図はこの発明に係る埋土工法の一実施例を示してい
る。FIG. 1 shows an embodiment of a burial method according to the present invention.
同図に示す埋土工法は不要になった鉱山廃坑の空洞10内
に充填材12を充填する場合に適用したものを例示してい
る。The burial method shown in the figure is applied to the case where the filling material 12 is filled into the cavity 10 of an abandoned mine that is no longer needed.
ここで使用される充填材12は、土砂に実質的に気泡のみ
を混入したものであって、充填材12は攪拌槽14内で、ホ
ッパー16から供給される土砂と、エアーと起泡剤溶液と
の供給を受けて気泡を作成する気泡発生器18からの気泡
とを所定の比率で混合攪拌して、ポンプ20を介して圧送
供給される。The filler 12 used here is a mixture of substantially only air bubbles in the earth and sand, and the filler 12 is the earth and sand supplied from the hopper 16, the air and the foaming agent solution in the stirring tank 14. Are mixed with each other at a predetermined ratio and mixed and stirred at a predetermined ratio, and are supplied under pressure through a pump 20.
気泡と土砂との混合比率は、土砂の空隙率に相当する量
以上の気泡を混入し、土砂の粒子間には気泡が介在する
ように攪拌し、これにより、土砂の流動性を増加させ
る。As for the mixing ratio of air bubbles and earth and sand, air bubbles of an amount equal to or greater than the porosity of earth and sand are mixed and stirred so that air bubbles are present between particles of earth and sand, thereby increasing the fluidity of earth and sand.
また、気泡の生成に用いられる起泡剤としては、タンパ
ク系の発砲剤、例えば動物性加水分解蛋白質、あるいは
界面活性剤、例えばアニオン系界面活性剤の高級アルキ
ルエーテル硫酸エステル塩、ラウリルエーテル硫酸エス
テルナトリウムなどが使用され、これらの起泡剤は水に
溶解して気泡発生器18にエアとともに供給される。Further, as the foaming agent used for generating bubbles, a protein-based foaming agent, for example, an animal hydrolyzed protein, or a surfactant, for example, a higher alkyl ether sulfate ester salt or lauryl ether sulfate ester of an anionic surfactant is used. Sodium or the like is used, and these foaming agents are dissolved in water and supplied to the bubble generator 18 together with air.
気泡発生器18で作成される気泡は、緻密な粒径のもので
あって、シュークリーム状を呈している。The bubbles created by the bubble generator 18 have a dense particle size and have a cream puff shape.
さて、以上のようにして空洞10を充填材12で充填する
と、充填材12は土砂の空隙率を超える気泡が混入され、
その流動性が高められているので、狭隘な場所でもポン
プ圧送が可能となり、土砂の搬入および投入が簡単にで
きる。Now, when the cavity 10 is filled with the filler 12 as described above, the filler 12 is mixed with bubbles exceeding the porosity of the earth and sand,
Because of its high fluidity, pumping is possible even in a narrow space, and loading and unloading of earth and sand can be done easily.
また、充填材12の土砂粒子間には、その空隙を埋めるよ
うにして気泡が介在しているので、これを地下構造物の
埋戻し用に使用した場合でも締固める必要はない。Further, since air bubbles are present between the earth and sand particles of the filler 12 so as to fill the voids, it is not necessary to compact even when this is used for backfilling the underground structure.
さらに、充填材12は土砂と、これに混入されたタンパク
系などの起泡剤を発砲させた気泡とから構成されている
ので、エアーモルタルのように硬化熱が発生せず周辺の
地盤に悪影響を及ぼすこともない。Furthermore, since the filler 12 is composed of earth and sand and bubbles generated by firing a foaming agent such as a protein-based substance mixed therein, it does not generate heat of hardening like air mortar and adversely affects the surrounding ground. It does not affect.
なお、上記実施例では、空洞10を充填材12で充填する場
合を例示したが、充填材12を地下構造物の埋土材として
使用することもできる。In addition, in the above-mentioned embodiment, the case where the cavity 10 is filled with the filling material 12 is illustrated, but the filling material 12 can also be used as a filling material for an underground structure.
《発明の効果》 以上説明したように、この発明に係る埋土工法では、地
下構造物の構築後に施工される埋戻しに用いられる埋土
材あるいは廃坑などの空洞、空隙に充填される充填され
る充填材として土砂に実質的に気泡のみを混入したもの
を用い、気泡により土砂の流動性が向上するので、狭隘
な場所での施工が簡単にできるとともに、締固めも不要
となり、材料費、施工費用も安価になる。<< Effects of the Invention >> As described above, in the burial method according to the present invention, the burial material used for backfilling after the construction of the underground structure or the cavity such as an abandoned pit, the space filled As the filler used is a mixture of sand and sand with only substantially air bubbles, and the air bubbles improve the fluidity of the sand and sand, so construction can be performed easily in tight spaces, and compaction is not required. Construction costs are also low.
また、エアーモルタルなどのように硬化熱が生じないの
で、周辺地盤に悪影響を及ぼすこともない。Further, unlike the case of air mortar, the heat of curing does not occur, so that the surrounding ground is not adversely affected.
第1図は本発明工法の一実施例の施工状態を示す説明図
である。 10……空洞、12……充填材FIG. 1 is an explanatory view showing a construction state of an embodiment of the method of the present invention. 10 ... cavity, 12 ... filling material
Claims (1)
用いられる埋土材あるいは廃坑などの空洞、空隙に充填
される充填材として土砂に実質的に気泡のみを混入した
ものを用いることを特徴とする埋土工法。1. A filling material used for backfilling after construction of an underground structure or a cavity or a cavity such as an abandoned mine, which is a mixture of earth and sand containing substantially only bubbles. The buried soil construction method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11448087A JPH0730680B2 (en) | 1987-05-13 | 1987-05-13 | Buried construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP11448087A JPH0730680B2 (en) | 1987-05-13 | 1987-05-13 | Buried construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63280200A JPS63280200A (en) | 1988-11-17 |
| JPH0730680B2 true JPH0730680B2 (en) | 1995-04-10 |
Family
ID=14638797
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP11448087A Expired - Fee Related JPH0730680B2 (en) | 1987-05-13 | 1987-05-13 | Buried construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0730680B2 (en) |
-
1987
- 1987-05-13 JP JP11448087A patent/JPH0730680B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63280200A (en) | 1988-11-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3514614B2 (en) | Grout material and grouting method | |
| JP4506024B2 (en) | Manufacturing method of backfill grout material | |
| JPH0730680B2 (en) | Buried construction method | |
| JPH0826538B2 (en) | Sediment backfilling method | |
| JP2831441B2 (en) | Stabilized soil and construction method using stabilized soil | |
| JP2840880B2 (en) | Method for producing self-hardening backfill material | |
| JP2882259B2 (en) | Hydraulic material and self-hardening stabilizer | |
| JPH0571730B2 (en) | ||
| JP4108781B2 (en) | Self-filling filling material and method of use thereof | |
| CN103306688A (en) | Construction method of synchronous grouting technology for ground access shield tunneling method | |
| JP2004263069A (en) | Plastic grout material, injection method of grout material and injection system | |
| JPS63315724A (en) | Execution work of cast-in-place concrete pile with high yield strength | |
| JPH01247695A (en) | Three-liquid back-filling construction | |
| JPH10140155A (en) | Fluid backfill material and method for producing the same | |
| JP2004044179A (en) | Fluidized soil and method for producing fluidized soil | |
| JP3269687B2 (en) | Backfill injection method | |
| JPH0462221A (en) | Back-fill injection work | |
| JP2004353310A (en) | Ground improvement method using kneaded material containing large amount of coal ash | |
| JP2001090480A (en) | Backfill injection method | |
| JPH083183B2 (en) | Retaining wall construction method using artificial lightweight soil | |
| JPS637497A (en) | Concrete press-in filling method of steel concrete syntheticsegment | |
| JPH10183602A (en) | Air bubble generating method for cement slurry for soil improvement and its equipment | |
| JP3545641B2 (en) | Backfill method | |
| JPS57108328A (en) | Formation of basement | |
| JPH04343997A (en) | Shield excavating method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| LAPS | Cancellation because of no payment of annual fees |